The Company is obliged by the ESO Licence to maintain the CUSC and to enter into arrangements for connection and use of system with Users pursuant to its terms.
SECTION 1: APPLICABILITY OF SECTIONS AND RELATED AGREEMENTS STRUCTURE
The CUSC is divided into different sections, including sections dealing specifically with Connection to and Use of System, the provision of Balancing Services, Interconnectors and other sections of more general application.
Compliance with the various sections by a User is dependent on the nature of that User’s connection and/or use in any given instance. A User may be party to the CUSC in a number of different categories.
This Section also deals with the requirement for a User to enter into Bilateral Agreements, Construction Agreements and Mandatory Services Agreements.
The CUSC and the proforma Bilateral Agreements set out as Exhibits 1, 2 and 5 of Schedule 2 are drafted to reflect the standard terms in relation to The Company’s charges (an indicative price agreement). Where a User chooses to have a different charging option, where provided for in the Charging Statements current at the time of application for the relevant Bilateral Agreement, that Bilateral Agreement will provide for the specific terms relating to the charging option and for the relevant paragraphs of Section 2 to apply (or be disapplied) subject to those specific terms. This may lead to the areas covered by the relevant Bilateral Agreement being wider in certain circumstances.
Each User is required to comply with the various Sections of the CUSC as provided for in this Section 1. Each Section may contain further detail in relation to particular categories of connection and/or use.
The different categories of connection and/or use reflect the types of utilisation which can exist. For example a User could have a directly connected Power Station and also be acting as a Supplier. In that case that User will need to comply in relation to two categories of connection and/or use, and its obligations in relation to each will differ.
Section 1, Sections 5 to 8, 11 and 14 of the CUSC apply to all categories of connection and/or use, and therefore should be complied with by all Users, subject as specifically provided in those Sections. Section 4 of the CUSC applies to Users who provide Balancing Services to The Company, and contains its own provisions on applicability to such Users.
In relation to Sections 2, 3, 9, 15 and 16 the following table sets out the applicability of those Sections in addition to those Sections referred to in Paragraph 1.2.3: Users, when making a Connection Application or Use of System Application (in each case in the form of the relevant exhibit), should identify the category for which they are applying.
| Categories | Applicable Sections | |
|---|---|---|
| 1. | Power Station directly connected to the GB Transmission System (including in the case of OTSDUW Build, a Power Station connected prior to the OTSUA Transfer Time by means of OTSUA) | 2 and 3 and 15 and 16 |
| 2. | Non-Embedded Customer Site | 2 and 16 |
| 3. | Distribution System directly connected to the GB Transmission System | 2 and (where a Construction Agreement is associated with Distributed Generation) 15 and (except where a Construction Agreement is required because of a connection to that Distribution System and the Distribution Queue Management Process applies) 16 |
| 4. | Suppliers | 3 only |
| 5. | Embedded Power Station except those which are the subject of a BELLA | 3 only and, where the subject of a BEGA, 15 |
| 6. | Small Power Station Trading Parties | 3 only |
| 7. | Interconnector User | 9 Part II only |
| 8. | Interconnector Error Administrator | 9 Part II only |
| 9. | Interconnector Owner | 9 Part I only and 15 and 16 |
| 10. | Distribution Interconnector Owner | 3 Only |
| 11. | Embedded Exemptable Large Power Stations whose Boundary Point Metering System is either SMRS registered or is registered in CMRS by a User who is responsible for the Use of System Charges associated with the BM Unit registered in CMRS | None |
| 12 | Virtual Lead Party (VLP) | 3 only |
Each Bilateral Agreement, Use of System Supply Confirmation Notice or Use of System Interconnector Confirmation Notice, will set out the category of connection and/or use to which it relates.
Where a Paragraph states a category of connection and/or use, or type of User, to which that Paragraph (or part of that Paragraph) applies, the application of that Paragraph (or part of Paragraph) shall be limited to the User in relation to that category of connection and/or use, or type of User, described.
Where a Paragraph does not state a category of connection and/or use, or type of User, to which that Paragraph (or some part of that Paragraph) applies, that Paragraph (or part of the Paragraph) shall apply to all types of Users and categories of connection and/or use.
Where a Paragraph is stated “as between The Company and that User”, rights and obligations under that Paragraph shall arise only between The Company and each User individually to whom that Paragraph applies. Accordingly, no User shall enjoy any rights nor incur any obligations against any other User pursuant to the terms of any such Paragraph.
Notwithstanding any other provision of this Code, where a User owns or operates an Exemptable Embedded Large Power Station which is Embedded in part of a Distribution System or the System of any other User where and to the extent that such part of the system in which the Exemptable Embedded Large Power Station is Embedded is not directly or indirectly connected to the GB Transmission System, that User need not comply with paragraphs 1.3, 1.7, 6.3.6 and 6.3.7 in respect of that Exemptable Embedded Large Power Station.
Section 17 applies to all Gated Applications.
Bilateral Agreements
Each User in respect of each category of connection and/or use with a direct connection to the National Electricity Transmission System shall enter into and comply with a Bilateral Connection Agreement in relation to such connection and/or use as identified in Paragraph 1.3.1(e).
Each User in respect of each category of connection and/or use with an Embedded Power Station (except those which are the subject of a BELLA) and/or in relation to a Small Power Station Trading Party and/or a Distribution Interconnector shall enter into and comply with a Bilateral Embedded Generation Agreement in relation to such use as identified in Paragraph 1.3.1(e).
Each User in respect of its Embedded Exemptable Large Power Station whose Boundary Point Metering System is registered in SMRS or is registered in CMRS by another User who is responsible for the Use of System Charges associated with the BM Unit registered in CMRS shall enter into and comply with a BELLA as identified in Paragraph 1.3.1(e).
Each User with a Secondary BM Unit shall enter in to and comply with a Virtual Lead Party Agreement in respect of the VLP Assets as identified in Paragraph 1.3.1(e).
Exhibits 1, 2, 5 and 7 in Schedule 2 to the CUSC contain the forms of Bilateral Agreements contemplated to be entered into pursuant to this Paragraph 1.3, being:
Exhibit 1 – Bilateral Connection Agreement: direct connection to the National Electricity Transmission System (Power Station directly connected to the NETS Distribution System directly connected to the NETS, Non-Embedded Customer Site and/or Interconnector);
Exhibit 2 – Bilateral Embedded Generation Agreement: embedded use of system (Embedded Power Station (except those which are the subject of a BELLA) and/or in relation to a Small Power Station Trading Party and/or Distribution Interconnector);
Exhibit 5 – BELLA: provisions associated with such Embedded Exemptable Large Power Stations who have no rights and obligations under Section 3 of the CUSC.
Exhibit 7 – Virtual Lead Party Agreement: embedded use of system in relation to VLP Assets
Construction Agreements Each User who wishes to construct or modify a direct connection to the GB Transmission System or commence or modify use by his Embedded Power Station or Distribution Interconnector, or any Distributor who wishes to connect a Relevant Embedded Power Station to his system shall enter into and comply with a Construction Agreement in respect of any construction works required as a result of that connection or Modification, together with a Bilateral Agreement as identified in Paragraph 1.3.1 or, as appropriate, an agreement to vary such Bilateral Agreement. In any case under the OTSDUW Arrangements, paragraph 1.5 applies to such Construction Agreement.
Mandatory Services Agreements
The Company and each User if a Generator shall, as between The Company and that User, in respect of the Generating Units, DC Converters and Power Park Modules from which that User is required to provide the Mandatory Ancillary Services in accordance with the Grid Code, enter into and comply with a Mandatory Services Agreement where applicable in accordance with Paragraph 1.3.3(b) in a form to be agreed between The Company and that User but based substantially on the form set out in Exhibit 4 in Schedule 2 (with necessary changes to enable the operation of those provisions, and those in Section 4 and Schedule 3 where the Generating Units, DC Converters or Power Park Modules (as the case may be) are not registered as BM Unit(s)).
Each User and The Company shall, as between The Company and that User, not later than 6 months (or such lesser time as may be agreed) prior to the expected Commissioning Programme Commencement Date, have entered into a Mandatory Services Agreement providing for payment for Mandatory Ancillary Services to be supplied by the User to The Company. In the event of a Mandatory Services Agreement not having been entered into by the said date, either party shall be entitled to initiate the procedure for resolution of the issue as an Other Dispute in accordance with Paragraph 7.4 to settle the terms of the said Mandatory Services Agreement. The Company shall not Energise the User’s Equipment or in the case of an Embedded Power Station issue an Operational Notification until the said Mandatory Services Agreement shall have been entered into by both parties.
General Provisions
Bilateral Agreements and Construction Agreements which are entered into between The Company and Users shall be in or substantially in the relevant exhibited form of Bilateral Agreement and/or Construction Agreement unless the parties thereto agree otherwise.
Each and every Bilateral Agreement, Mandatory Services Agreement and Construction Agreement entered into by a User and in force from time to time shall constitute a separate agreement governed by the terms of the CUSC and will be read and construed accordingly. For the avoidance of doubt no User shall enjoy any rights nor incur any obligations against any other User pursuant to the terms of any Bilateral Agreement, Mandatory Services Agreement or Construction Agreement.
Any Offer or Modification Offer made to an Applicant or User in the category of:
a Power Station directly connected to the National Electricity Transmission System; or
an Embedded Power Station which is the subject of a Bilateral Embedded Generation Agreement or a Bilateral Embedded Licence Exemptable Large Power Station Agreement; or
where such Offer or Modification Offer is associated with Distributed Generation, a Distribution System directly connected to the National Electricity Transmission System, shall be offered on the basis of the Connect and Manage Arrangements.
Transitional Arrangements The Company shall as soon as reasonably practical after the Connect and Manage Implementation Date and in any event by the end of the Connect and Manage Transition issue:
a revised Offer on the basis of the Connect and Manage Arrangements as regards any Offer issued but not accepted pursuant to the Interim Connect and Management Arrangements
an offer to vary each Existing ICM Construction Agreement such that it is in a form and on terms consistent with a Construction Agreement entered into on the basis of the Connect and Manage Arrangements; and/or
a Modification Offer as regards any Bilateral Agreement entered into on the basis of the Interim Connect and Manage Arrangements which would require amendments in order to comply with the Connect and Management Arrangements, in each case on terms no less advantageous than those contained in offers made or agreements entered into pursuant to the Interim Connect and Manage Arrangements. The Applicant or User (as appropriate) shall be entitled to accept such a proposal or continue with its existing arrangements.
Any Offer or Modification Offer made to an Applicant in respect of a New Connection Site located in Offshore Waters shall, unless the Applicant indicates otherwise, be made on the assumption that the User (following agreement with The Company) will undertake OTSDUW Build. For the avoidance of doubt, this shall not prevent the Applicant and The Company from agreeing (prior to signing the Construction Agreement) that the scope of OTSDUW will be narrower than that set out in the Offer or that OTSDUW will not be undertaken by the User.
Provisions of the CUSC which apply in relation to OTSDUW and OTSUA, and/or a Transmission Interface Site, shall (in any particular case) apply up to the OTSUA Transfer Time, whereupon such provisions shall (without prejudice to any prior non-compliance) cease to apply, without prejudice to the continuing application of provisions of the CUSC applying in relation to the relevant Offshore Transmission System and/or Connection Site.
OTSUA Completion Notice
In the case of OTSDUW Build, The Company will issue the OTSUA Completion Notice to the Authority on the OTSUA Completion Notice Trigger Date and The Company shall also provide a copy of such OTSUA Completion Notice to the User.
In respect of any OTSUA Operational at the OTSUA Commissioning Period Effective Date, The Company will issue the OTSUA Completion Notice to the Authority as soon as practicable within 10 Business Days after the OTSUA Commissioning Period Effective Date and The Company shall also provide a copy of such OTSUA Completion Notice to the User. An OTSUA Completion Notice issued in accordance with this paragraph 1.5.3.2 for any OTSUA Operational at the OTSUA Commissioning Period Effective Date, shall be issued with effect from the same date for all OTSUA Operational at the OTSUA Commissioning Period Effective Date.
Implementation Each Existing Offshore Agreement shall be read and construed on and from the OTSUA Commissioning Period Effective Date such that:
the defined terms within it, and the effect of those defined terms, shall be deemed to have the meanings they would have had if those agreements had been entered into after the OTSUA Commissioning Period Effective Date; and
the relevant Clauses within each Existing Offshore Agreement are amended and new Clauses introduced into each Existing Offshore Agreement so that each Existing Offshore Agreement is consistent in form and content with the changes introduced in CUSC Schedule 2 Exhibit 1 (Bilateral Connection Agreement) and Schedule 2 Exhibit 3A (Offshore Construction Agreement) on the OTSUA Commissioning Period Effective Date, and The Company and the User shall as quickly and as reasonably practicable take any steps as may be necessary to enable the Existing Offshore Agreements to be construed as if those agreements had been entered into after the OTSUA Commisioning Period Effective Date.
Three categories of use of the GB Transmission System do not require a Bilateral Agreement to be entered into as all the relevant provisions are included in the CUSC itself. These relate to Suppliers, Interconnector Users and Interconnector Error Administrators who in those categories of connection and/or use have no physical presence on the system. Further provisions on this are contained in Section 3 and Section 9 Part II.
A User in respect of its Embedded Exemptable Large Power Station whose Boundary Point Metering System is registered in SMRS (or who intends to so register) or in CMRS by a User who is responsible for the Use of System Charges associated with the BM Unit registered in CMRS (or who intends to so register), shall complete and submit to The Company a BELLA Application and comply with the terms thereof.
The BELLA Application and BELLA Offer shall be processed in accordance with the Gated Application and Offer Process. The BELLA Offer shall be in the form of a BELLA.
The BELLA Offer shall remain open for acceptance (subject to CUSC Paragraph 6.10.4.4) for 3 months from its receipt by that User unless either that User or The Company makes an application to the Authority under Paragraph 1.7 of the CUSC, in which event the BELLA Offer shall remain open for acceptance until 14 days after any determination by the Authority pursuant to such application.
Upon acceptance of the BELLA Offer (as offered by The Company or determined by the Authority) by the User and execution by The Company, the User’s rights and obligations pursuant thereto shall commence in accordance with its terms. Such rights and obligations shall continue until the BELLA is terminated.
A User who is required by this Paragraph 1.7 to submit a BELLA Application shall not energise or operate its Embedded Exemptable Large Power Station until it has entered into a BELLA with The Company and until The Company has issued the User with an Operational Notification in accordance with the terms of the BELLA.
If, after a period which appears to the Authority to be reasonable for the purpose, The Company or the User have failed to enter into a BELLA in respect of the Embedded Exemptable Large Power Station either The Company or the User may apply to the Authority for the Authority to settle any terms of the BELLA Offer in dispute.
Upon such application, the Authority, pursuant to section 7 (3) (c) of the Act, may settle any terms in dispute between The Company and the User in respect of such BELLA in such manner as appears to the Authority to be reasonable having (in so far as relevant) regard in particular to the following considerations:
that the performance by The Company of its obligations under the BELLA should not cause it to be in breach of those provisions referred to at condition E12.6 of the ESO Licence;
that any methods by which the Relevant Transmission Licensee’s transmission system is connected to any other System for the transmission or distribution of electricity accord (insofar as applicable to The Company) with the Grid Code, the STC and the Distribution Code;
that the terms and conditions of the BELLA so settled by the Authority and of any other agreements entered into by The Company pursuant to Paragraph 1.7 should be in as similar a form as is practicable.
Where the Authority settles any terms in dispute, the User and The Company shall forthwith enter into the BELLA as settled.
If either the User or The Company proposes to vary the terms of the BELLA in a manner provided for under such agreement, the Authority may, at the request of The Company or the User, settle any dispute relating to such variation in such manner as appears to the Authority to be reasonable.
SECTION 2: CONNECTION
This Section deals with connection to the National Electricity Transmission System of User's Equipment at Connection Sites and certain related issues.
Part I of this Section 2 sets out general provisions relating to connection to the National Electricity Transmission System, Part II sets out provisions related to charging for connection and Part III sets out the credit requirements related to Termination Amounts. Section 3 which deals with Use of System will also be applicable in relation to a Power Station directly connected to the National Electricity Transmission System.
In the case of OTSDUW Build, if the Transmission Interface Site is Operational prior to the OTSUA Transfer Time, until the OTSUA Transfer Time the User’s Equipment will be connected to the National Electricity Transmission System through the connection of the OTSUA to the National Electricity Transmission System at the Transmission Interface Point. In such case up to the OTSUA Transfer Time certain provisions of this Section 2 will be applied as provided for in the relevant Bilateral Connection Agreement. Further provisions relating to OTSDUW Build are dealt with in section 11.2.7. PART I - GENERAL
Right to Remain Connected Subject to the other provisions of the CUSC, the relevant Bilateral Connection Agreement and the Grid Code, each User as between The Company and that User, shall have the right for the User's Equipment at each of its Connection Sites to be and/or remain connected to the National Electricity Transmission System at the Connection Site once Commissioned and then for the duration of the relevant Bilateral Connection Agreement in relation to that Connection Site.
Rights to remain Energised and Operational
Subject to the other provisions of the CUSC and in particular Paragraphs 2.2.2(b) and 2.2.3, the relevant Bilateral Connection Agreement and the Grid Code, each User as between The Company and that User, shall have the right for the User's Equipment at each of its Connection Sites to remain Energised and Operational once Commissioned for the duration of the relevant Bilateral Connection Agreement in relation to that Connection Site.
If the User becomes aware that the bank or insurance company issuing the Performance Bond or Letter of Credit ceases to be a Qualified Bank or that the company giving the Performance Bond ceases to be a Qualified Company, the User shall notify The Company in writing as soon as it becomes so aware. If The Company becomes aware that the bank or insurance company issuing the Performance Bond or Letter of Credit ceases to be a Qualified Bank or that the company giving the Performance Bond ceases to be a Qualified Company, The Company may notify the User to that effect in writing. Where the bank, insurance company or the company so ceases to be either a Qualified Bank or a Qualified Company (as the case may be) as a consequence of The Company having reasonable cause to doubt the continued rating of the said bank, insurance company or company, such notice shall be accompanied by a statement setting out The Company’s reasons for having such doubt. The User shall within 21 days of the giving of such notice by The Company or the User whichever is the earlier provide a replacement Performance Bond and/or Letter of Credit from a Qualified Bank or Qualified Company, as the case may be, and/or provide a cash deposit in the required amount in a Bank Account. From the date the replacement Performance Bond or Letter of Credit or Bank Account cash deposit is effectively and unconditionally provided and Valid, The Company will consent in writing to the security which it replaces being released.
Obligation to Remain Connected Without prejudice to its rights to make Modifications to the User's Plant (and/or User’s Equipment as the case may be) pursuant to the CUSC and subject to the provisions of Paragraph 5.2.2 and the other provisions of the CUSC, and the Grid Code, each User as between The Company and that User, shall keep the User's Equipment at each of its Connection Sites connected to the National Electricity Transmission System until Disconnection is permitted pursuant to the CUSC and the relevant Bilateral Connection Agreement or as otherwise agreed between the Parties.
Connection Entry Capacity With respect to a particular connection to the National Electricity Transmission System, each User acting in the category of a Power Station directly connected to the National Electricity Transmission System, as between The Company and that User, shall not operate its User's Equipment such that any of it exceeds the Connection Entry Capacity specified for each Generating Unit or the Connection Entry Capacity to the Connection Site such figures being set out in Appendix C to the relevant Bilateral Connection Agreement save as expressly permitted or instructed pursuant to an Emergency Instruction under the Grid Code or save as expressly permitted or instructed pursuant to the Fuel Security Code or as may be necessary or expedient in accordance with Good Industry Practice.
Subject to the other provisions of the CUSC, the relevant Bilateral Connection Agreement and the Grid Code, The Company shall, as between The Company and that User, accept into the National Electricity Transmission System at each Connection Site of a User acting in the category of Power Station directly connected to the National Electricity Transmission System, power generated by such User up to the Transmission Entry Capacity and (if any) STTEC and\or LDTEC and\or any Temporary Received TEC less any Temporary Donated TEC for the relevant Period as set out in Appendix C of the relevant Bilateral Connection Agreement except to the extent (if any) that The Company is prevented from doing so by transmission constraints which could not be avoided by the exercise of Good Industry Practice by The Company.
Subject to the other provisions of the CUSC, the relevant Bilateral Connection Agreement and the Grid Code a User acting in the capacity of a Power Station directly connected to the National Electricity Transmission System shall not export on to the National Electricity Transmission System power generated by such User in excess of the Transmission Entry Capacity and (if any) STTEC and\or LDTEC and\or any Temporary Received TEC less any Temporary Donated TEC for the relevant Period as set out in Appendix C of the relevant Bilateral Connection Agreement save as expressly permitted or instructed pursuant to an Emergency Instruction under the Grid Code or save as expressly permitted or instructed pursuant to the Fuel Security Code or as may be necessary or expedient in accordance with Good Industry Practice.
IMPORT OF POWER TO CONNECTION SITE Subject to the other provisions of the CUSC and in particular Paragraph 2.2.2(b), the relevant Bilateral Connection Agreement and the Grid Code, The Company shall as between The Company and that User, transport a supply of power to each Connection Site of a User through the National Electricity Transmission System up to the Connection Site Demand Capability except to the extent (if any) that The Company is prevented from doing so by transmission constraints or by insufficiency of generation which, in either case, could not have been avoided by the exercise of Good Industry Practice by The Company.
MAINTENANCE OF ASSETS Subject to the other provisions of the CUSC, the relevant Bilateral Connection Agreement, and the Grid Code, The Company shall as between The Company and that User use all reasonable endeavours to maintain the Transmission Connection Assets at each Connection Site in the condition necessary to render the same fit for the purpose of passing power up to the value of Connection Entry Capacity and Connection Site Demand Capability as appropriate between the User's Equipment and the National Electricity Transmission System.
OUTAGES Subject to the provisions of the Grid Code and the relevant Bilateral Connection Agreement, The Company and each User shall, as between The Company and that User, be entitled to plan and execute outages of parts of in the case of The Company the National Electricity Transmission System or Transmission Plant or Transmission Apparatus and in the case of the User its System or Plant or Apparatus at any time and from time to time.
SPECIAL AUTOMATIC FACILITIES The Company and each User shall, as between The Company and that User, operate respectively the National Electricity Transmission System and the User System in accordance with the schemes set out in Appendix F3 to the relevant Bilateral Connection Agreement.
PROTECTION AND CONTROL RELAY SETTINGS/FAULT CLEARANCE TIMES The Company and each User shall, as between The Company and that User, record the respective protection and control relay settings and fault clearance times to be operated by each of them in documents in the format set out in Appendix F4 to the relevant Bilateral Connection Agreement and shall operate them accordingly.
Each User shall, as between The Company and that User, ensure that in the case of a Connection Site Commissioned prior to the Transfer Date, on the Transfer Date, and in the case of a Connection Site Commissioned after the Transfer Date on the Completion Date(s), the User's Equipment complies with the site specific technical conditions set out in Appendix F5 to the relevant Bilateral Connection Agreement.
Each User shall, as between The Company and that User, use all reasonable endeavours to ensure during the period in which it is a party to a particular Bilateral Connection Agreement that the User's Equipment which is subject to that Bilateral Connection Agreement shall continue to comply with the site-specific technical conditions set out in Appendix F5 to that Bilateral Connection Agreement.
If a User or The Company wishes to modify, alter or otherwise change the site specific technical conditions relating to a Connection Site or the manner of their operation:
under Appendix F4 to the relevant Bilateral Connection Agreement it may do so upon obtaining the agreement of the other party such agreement not to be unreasonably withheld;
under Appendices F1, F3 or F5 to the relevant Bilateral Connection Agreement it shall be deemed to be a Modification for the purposes of the CUSC.
Where, in the case of a Connection Site Commissioned in England and Wales prior to the Transfer Date, on or immediately prior to the Transfer Date a User's Equipment subject to a particular Bilateral Connection Agreement has any of the following technical attributes or facilities:
circuit breaker fail protection
pole slipping protection
fault disconnection facilities
automatic switching equipment
control arrangements
voltage and current signals for system monitoring
control telephony
operational metering, the User shall, as between The Company and that User, use all reasonable endeavours to ensure that during the period of such Bilateral Connection Agreement the User's Equipment which is subject to that Bilateral Connection Agreement retains such technical attributes or facilities provided always that if the User wishes to modify alter or otherwise change the same or their operation it may do so by following the procedures relating to a Modification in accordance with the CUSC.
SAFETY RULES Safety Rules
In relation to a Connection Site The Company shall procure that the Relevant Transmission Licensee supplies to the User a copy of their Safety Rules current from time to time, including any site- specific Safety Rules, and also a copy of the Local Safety Instructions applicable at each Connection Site from time to time.
In relation to a Connection Site each User will supply to the Relevant Transmission Licensee a copy of their Safety Rules current from time to time, including any site-specific Safety Rules, and also a copy of the Local Safety Instructions applicable at each Connection Site from time to time.
In relation to Connection Sites and New Connection Site(s) The Company shall procure that the Relevant Transmission Licensee shall enter into an Interface Agreement with a User in either case in a form to be agreed between them but based substantially on the forms set out in Exhibit O to the CUSC as appropriate where such Interface Agreement(s) is/are required pursuant to the applicable Bilateral Connection Agreement or otherwise.
In relation to Connection Sites and New Connection Site(s) the User undertakes to enter into an Interface Agreement with the Relevant Transmission Licensee in a form to be agreed between them but based substantially on the forms set out in Exhibit O to the CUSC as appropriate where such Interface Agreement(s) is/are required pursuant to the applicable Bilateral Connection Agreement or otherwise.
Subject to the Transfer Scheme or any contrary agreement in any Bilateral Agreement or any other agreement the division of ownership of Plant and Apparatus shall be at the electrical boundary, such boundary to be determined in accordance with the following principles: In the case of air insulated switchgear:
in relation to Plant and Apparatus located between the National Electricity Transmission System and a Power Station, the electrical boundary is at the busbar clamp on the busbar side of the busbar isolators on Generators and Power Station transformer circuits;
save as specified in Paragraph 2.12.1(c) below, in relation to Plant and Apparatus located between the National Electricity Transmission System and a Distribution System, the electrical boundary is at the busbar clamp on the busbar side of the Distribution System voltage busbar selector isolator(s) of the National Electricity Transmission System circuit or if a conventional busbar does not exist, an equivalent isolator. If no isolator exists an agreed bolted connection at or adjacent to the tee point shall be deemed to be an isolator for these purposes;
in relation to Transmission Plant and Transmission Apparatus located between the National Electricity Transmission System and a Distribution System but designed for a voltage of 132KV or below in England and Wales and below 132kV in Scotland, the electrical boundary is at the busbar clamp on the busbar side of the busbar selector isolator on the Distribution System circuit or, if a conventional busbar does not exist, an equivalent isolator. If no isolator exists, an agreed bolted connection at or adjacent to the tee point shall be deemed to be an isolator for these purposes;
in relation to Plant and Apparatus located between the National Electricity Transmission System and the system of a Non-Embedded Customer, the electrical boundary is at the clamp on the circuit breaker side of the cable disconnections at the Non-Embedded Customer’s sub- station; and In the case of metal enclosed switchgear, that is not Gas Insulated Switchgear:
the electrical boundary will be the equivalent of those specified in this Paragraph 2.12.1 save that for rack out switchgear, the electrical boundary will be at the busbar shutters. In the case of Gas Insulated Switchgear:
the electrical boundary will be the equivalent of those specified in this Paragraph 2.12.1 save that the electrical boundary will be at:
the first component on the outside of the Gas Insulated Switchgear Circuit Breaker gas zone on the User’s side of that gas zone or, where a circuit disconnector is fitted, the first component on the outside of the Gas Insulated Switchgear circuit disconnector gas zone, on the User's side of that gas zone; or
the first gas zone separator on the busbar side of the busbar selection devices, and in such case the busbar selection devices’ gas zone may contain a single section of the busbar as agreed between The Company and the User and a diagram showing these electrical boundaries is attached at Schedule 1 to this Section 2.
If a User wants to use transformers of specialised design for unusual load characteristics at the electrical boundary, these shall not be owned by the User and shall form part of the National Electricity Transmission System but the User shall pay The Company for the proper and reasonable additional cost thereof as identified by The Company in the Offer covering such transformers. In this Paragraph 2.12.2 “unusual load characteristics” means loads which have characteristics which are significantly different from those of the normal range of domestic, commercial and industrial loads (including loads which vary considerably in duration or magnitude).
For the avoidance of doubt nothing in this Paragraph 2.12 shall effect any transfer of ownership in any Plant or Apparatus.
(f) (i)
(f) (ii) SCHEDULE 2 Please read through ‘TEMPLATE A’ ‘TEMPLATE B’. Customers should submit only 1 completed template below in line with the circumstances of their project. [TEMPLATE A: to be used by landowner where Connecting Customer is not the landowner of the site or is yet to obtain relevant rights to the site] NB – Please note that the LOA must be signed and dated by the Landowner/Landowner representative no more than 12 months prior to the date of application. I am the : Landowner Landowner Representative If completing as Landowner Representative, please confirm if you are happy for the ESO to contact the landowner directly for verification purposes. Yes No By submitting this letter you confirm that you have been appointed by the Landowner to represent them in regards to this application. Contact details for Landowner / Landowner’s Representative (delete as appropriate) ADDRESS LINE 1: ADDRESS LINE2: POSTCODE: [LANDOWNER CONTACT DETAILS (Phone and email] Project details [NAME OF LANDOWNER] [NAME OF CONNECTING CUSTOMER] [PROJECT NAME] (The “Project”) [SITE ADDRESS] (The “Property”)Acreage: Please confirm if land is registered with Land Registry: Yes/No Land Registry Title number (s) (if applicable): Contact details for User ADDRESS LINE 1: ADDRESS LINE2: POSTCODE: [User CONTACT DETAILS (Phone and email] Project Technology Type: FAO National Energy System Operator Limited (NESO), Contact details for User ADDRESS LINE 1: ADDRESS LINE2: POSTCODE: We/I, [NAME] of landowner] / [[Name of agent] of [company name] ([company number]), authorised by the landowner as their agent,] at [address] ]], hereby confirm we are the legal owner of the land situated at [Address of Property] as outlined in [Colour of line] on Plan 1 annexed to this letter ( “The Property”). Please take this letter as confirmation that we authorise [] (or their authorised agents or representatives whomsoever) to apply for a grid connection to the NESO on and in relation to the Property. I confirm that I am happy for the NESO to contact me for the following purposes: - To verify that this letter is genuine. - To verify the contact details and address of the landowner and/or the landowner’s agent. - To verify that the landowner owns the land shown on the attached site plan and authorises the developer to include it in the application for connection of the Project mentioned above in this letter Disclaimer: This letter is provided solely for the purpose of confirming support for this project’s application to the NESO at this time and is not commercially or legally binding upon the landowner Yours faithfully, [SIGNATURE] [NAME] [DATE] [Image of the sample plan showing the boundaries of the Site referred] [TEMPLATE B: to be used by the connecting customer where connecting customer is the landowner of the site OR has already obtained the required rights to the site] NB – Please note that the LOA must be signed and dated by the Landowner/Landowner representative no more than 12 months prior to the date of application. [CONNECTING CUSTOMER ADDRESS LINE 1] [CONNECTING CUSTOMER ADDRESS LINE2] [CONNECTING CUSTOMER ADDRESS POSTCODE] [DATE] FAO National Energy System Operator Limited (NESO), [PROJECT NAME] (The “Project”) [SITE ADDRESS] (The “Property”) [SITE ADDRESS] (The “Property”)Acreage: Please confirm if land is registered with Land Registry: Yes/No Land Registry Title number (if applicable): Project Technology type: I, [ AUTHORISED SIGNATORY/DIRECTOR OF [THE COMPANY], a company registered in [Scotland / England and Wales], with Company Number [xxxxx] ], as the applicant for the connection of the Project confirm that [THE COMPANY] [ [is the landowner of the Property] / [ has obtained the required rights for use of the Property for the purpose of constructing the Project] ] and that this Property is to be noted as part of our application to the Electricity System Operator for an electricity connection for the Project. I consent to the ESO contacting me where necessary. The documents evidencing [THE COMPANY’s] [ownership of / rights to] the Property are attached. Yours faithfully, [SIGNATURE] [NAME] [Image of the sample plan showing the boundaries of the Site referred]
If a User wishes to connect a New Connection Site it shall complete and submit to The Company a Connection Application (and if a Gated Application in accordance with the Gated Application and Offer Process) and comply with the terms thereof. An application for a New Connection Site which is not a Gated Application or which is a Gate 1 Application shall include the provision of at least one Letter of Authority in the form of one of the templates provided in Section 2, Schedule 2 in the case of a New Connection Site Onshore or a Letter of Acknowledgement in the case of a New Connection Site Offshore or a New Connection Site for Offshore Projects.
The Applicant shall ensure that a Letter of Authority in the form of one of the templates provided in Section 2 Schedule 2 (or multiple such letters taken in combination) shall be for a minimum area of land pertaining to the New Connection Site Onshore set out in the Connection Application, by reference to the minimum values specified in the Energy Density Table(s). The Applicant shall ensure that a Letter of Acknowledgement shall be for a minimum area of seabed pertaining to the New Connection Site Offshore or the New Connection Site for an Offshore Project (other than an Interconnector) set out in the Connection Application by reference to the offshore specific guidance in the LoA Guidance.
Where the Connection Application:
is not a Gated Application for the purposes of the Gated Application and Offer Process, without prejudice to condition E12 of the ESO Licence The Company shall make a Connection Offer to that User as soon as practicable after receipt of the Connection Application and (save where the Authority consents to a longer period) in any event not more than 3 months after receipt by The Company of the Connection Application; and 2.13.3.2 is a Gated Application for the purposes of the Gated Application and Offer Process, The Company shall make a Connection Offer to that User in accordance with the Gated Application and Offer Process.
The Connection Offer and any offer to vary referred to in paragraph 2.13.10 shall remain open for acceptance (subject to CUSC Paragraph 6.10.4.4) for 3 months from its receipt by that User unless either that User or The Company makes an application to the Authority under condition E13 of the ESO Licence, in which event the Connection Offer shall remain open for acceptance until the date 14 days after any determination by the Authority pursuant to such application.
If the Connection Offer is accepted by that User the connection shall proceed according to the terms of the CUSC and the relevant Bilateral Connection Agreement and Construction Agreement entered into consequent upon acceptance of the Offer.
Prior to so proceeding a person who is not already a party to the CUSC Framework Agreement must become a party to the CUSC Framework Agreement.
Certain provisions relating to New Connection Sites and Transmission Interface Sites are dealt with in Section 6. This is due to their inter-relationship with the provisions on Modifications.
In the event that the User requests a Connection Offer in respect of a Connection Site located Onshore on the basis of a Design Variation then:
The Company shall only be obliged to provide such an offer in so far as such an offer satisfies the conditions detailed in Chapter 2 of the NETS SQSS; and
The Company shall be obliged, at the request of the User as part of the Connection Offer, to provide such information that the User may reasonably require in order to assess the probability of Notification of Restrictions on Availability being issued. For the avoidance of doubt, the information that is provided by The Company under this clause shall be a best estimate only and is not legally binding.
In the case of New Connection Sites located in Offshore Waters the Connection Offer will identify the Onshore Construction Works. These will be based on assumptions about the Offshore Construction Works and these assumptions will be set out in the Construction Agreement. Where the Connection Offer is not made on the basis of the OTSDUW Arrangements, the Offshore Construction Works will not themselves be identified at that time. Where the Connection Offer is made on the basis of the OTSDUW Arrangements, the Connection Offer will identify initial Offshore Transmission System Development User Works as being the OTSDUW Build required to provide a connection between the User’s Equipment and the Onshore Transmission System at the Transmission Interface Point as set out in the assumptions.
In the case of New Connection Sites located in Offshore Waters, where a Connection Offer is not made on the basis of the OTSDUW Arrangements the Bilateral Connection Agreement and Construction Agreement for such New Connection Site will contain provisions specifically allowing them to be varied to reflect both the Offshore Construction Works and any changes necessary to the Onshore Construction Works once they have been identified and changes to the Construction Programme consequent on any delay in the appointment of the Offshore Transmission Owner from the date assumed in the relevant Construction Agreement.
In the case of New Connection Sites located in Offshore Waters, where a Construction Agreement is entered into on the basis of the OTSDUW Arrangements, the Construction Agreement for such New Connection Site will reflect the extent and scope of the Onshore Construction Works, the Offshore Construction Works and the Offshore Transmission System Development User Works as agreed between The Company and the User reflecting any changes in the assumptions referred to in paragraph 2.13.9 as agreed between The Company and the User prior to acceptance of the Connection Offer. The Construction Agreement may contain continuing assumptions and provisions allowing for its variation upon changes in such continuing assumptions.
In the case of a New Connection Site located in Offshore Waters:
The Company will include Offshore Restrictions on Availability in any Offer made for New Connection Sites located in Offshore Waters which meet the Offshore Standard Design or Design Variation but not where the design is of a standard equivalent to or higher than the deterministic criteria detailed in Paragraphs 2.5 to 2.13 of the NETS SQSS. The Bilateral Connection Agreement will specify the circumstances of Offshore Restrictions on Availability during which access to the National Electricity Transmission System will be restricted; and
In the event that the User requests a Connection Offer on the basis of a Design Variation then:
The Company shall only be obliged to provide such an offer in so far as such an offer satisfies the conditions detailed in Chapter 7 of the NETS SQSS; and
The Company shall be obliged, at the request of the User as part of the Connection Offer, to provide such information that the User may reasonably require in order to assess the probability of Notification of Restrictions on Availability being issued. For the avoidance of doubt, the information that is provided by The Company under this clause shall be a best estimate only and is not legally binding.
In the case of a New Connection Site located in Offshore Waters and which is connected or to be connected to an ET Offshore Transmission System, The Company will include ET Restrictions on Availability in any Offer made and the Bilateral Connection Agreement will provide for access to the National Electricity Transmission System to be restricted during the ET Restrictions on Availability.
In the case where a User undertakes OTSDUW Build in respect of an ET Offshore Transmission System, the principles and intent of the OTSUA Commissioning Period will be applied to OTSUA connected to an ET Offshore Transmission System in a manner consistent with OTSUA connected at a Transmission Interface Site.
Introduction Subject to the provisions of the CUSC, and the relevant Bilateral Connection Agreement, each User shall, as between The Company and that User, with effect from the relevant date set out in the relevant Bilateral Connection Agreement, be liable to pay to The Company the Connection Charges calculated and applied in accordance with the Statement of the Connection Charging Methodology and as set out in the relevant Bilateral Connection Agreement. The User shall make those payments in accordance with the provisions of the CUSC. The Company shall apply and calculate the Connection Charges in accordance with the Statement of the Connection Charging Methodology.
Security The User shall provide The Company with Security Cover in respect of Termination Amounts in respect of the Transmission Connection Assets commissioned after the Transfer Date in accordance with the provisions of Part III of this Section 2.
Connection Charges - Outturn Reconciliation
The following provisions relate to the ability for invoices to be issued for Connection Charges based on an estimate of the cost of Transmission Connection Asset Works, and for a reconciliation once those costs are known.
The Company shall be entitled to invoice each User for Connection Charges payable in accordance with the CUSC in respect of any Plant and Apparatus installed as part of the Transmission Connection Asset Works on the basis set out in the Statement of the Connection Charging Methodology, until the final cost of carrying out the said Transmission Connection Asset Works shall have been determined.
As soon as practicable after the Completion Date and in any event within one year (or such later period as The Company and the relevant User shall agree) thereof. The Company shall, as between The Company and that User, provide to the User a written statement specifying the Connection Charges calculated in accordance with the Charging Statements based on the cost of carrying out the Transmission Connection Asset Works (the “Cost Statement”). The Company shall be entitled to revise Appendix B to the relevant Bilateral Connection Agreement accordingly.
In the event that the Connection Charges specified in the Cost Statement are greater than the amount paid by the User based on The Company’s estimate under Paragraph 2.14.3(b), the User shall pay to The Company the difference between the two amounts plus interest on a daily basis from the date of payment by the User of the amounts calculated on The Company’s estimate to the date of payment by the User of the difference at the Base Rate. In the event that the Connection Charges specified in the Cost Statement are less than the amount paid by the User based on The Company’s estimate, The Company shall pay to the User the difference between the two amounts plus interest on a daily basis from the date of payment by the User of the amounts calculated on The Company’s estimate to the date of repayment by The Company at the Base Rate. Such payment of reconciliation shall be made by one party to the other within 28 (twenty eight) days of the Cost Statement.
Connection Charges - One-off Charges
The following provisions relate to the payment for certain One-off Works, which arise in relation to the construction of a Connection Site.
Each User shall forthwith on the relevant date set out in the relevant Bilateral Connection Agreement be liable to pay to The Company the One-off Charge (if any) as set out in the relevant Bilateral Connection Agreement.
The Company shall invoice the User for an amount equal to The Company’s estimate of the One-off Charge before, on or after the relevant date set out in the relevant Bilateral Connection Agreement and the User shall pay to The Company the amount stated in The Company invoice at the later of such relevant date or 28 (twenty eight) days after the date of the said invoice.
As soon as practicable thereafter The Company shall provide the User with a statement of the One-off Charge. In the event of the amount specified in the statement being more than the amount paid by the User to The Company in terms of Paragraph 2.14.4(c), the User shall pay to The Company the difference plus interest on a daily basis from the date of the invoice under Paragraph 2.14.4(c) to the date of invoice for the difference at the Base Rate from time to time within 28 days (twenty eight) days of the date of The Company’s invoice. In the event of the amount specified in the statement being less than the amount paid by the User under the terms of Paragraph 2.14.4(c), The Company shall forthwith pay to the User an amount equal to the difference plus interest calculated on a daily basis at the Base Rate from the date of payment by the User under Paragraph 2.14.4(c) to the date on which the difference is repaid by The Company.
Connection Charges – Site Specific Maintenance Charge
The Company shall be entitled to invoice each User for the indicative Site Specific Maintenance Charge in each Financial Year as set out in the Statement of the Connection Charging Methodology.
As soon as reasonably practicable and in any event by 31 July in each Financial Year The Company shall:
in accordance with the Statement of the Connection Charging Methodology calculate the actual Site Specific Maintenance Charge that would have been payable by the User during the preceding Financial Year (the “Actual Charge”) and compare this with the indicative Site specific Maintenance Charge received from the User during the preceding Financial Year (the “Notional Charge”) and
prepare and send to the User a Maintenance Reconciliation Statement specifying the Actual Charge and the Notional Charge for the preceding Financial Year.
Two months after the date of issue of the Maintenance Reconciliation Statement and in any event by 30 September The Company shall issue a credit note in relation to any sums shown by the Maintenance Reconciliation Statement to be due to the User or an invoice in respect of sums due to The Company (such invoice to be payable within 30 days of the date of the invoice) and in each case interest thereon calculated pursuant to Paragraph 2.14.5(d) below.
Interest on all amounts due under this Paragraph 2.14.5 shall be payable by the paying CUSC Party to the other on such amounts from the date of payment applicable to the month concerned until the date of invoice for such amounts and such interest shall be calculated on a daily basis at a rate equal to the Base Rate during such period.
The Connection Charges shall be paid as specified in paragraph 6.6.1(a) and shall be treated as a recurrent monthly payment.
The User shall be liable to pay The Company Termination Amounts in the event of the termination of the User's Bilateral Connection Agreement (or in the case of Paragraph 5.3.4 Disconnection of the User's Equipment) in accordance with Section 5 of the CUSC.
The Connection Charges in the Financial Year in which the relevant date for charging set out in the relevant Bilateral Connection Agreement occurs shall be apportioned as follows:- For each complete calendar month from that date to the end of the Financial Year in which the date occurs the User shall be liable to pay one twelfth of the Connection Charges and for each part of a calendar month the User shall be liable to pay to The Company one twelfth of the Connection Charges prorated by a factor determined by the number of days for which the User is liable divided by the total number of days in such calendar month.
Pursuant to the ESO Licence and/or the CUSC and/or the Charging Statements and/or the Bilateral Agreements, The Company may revise its Connection Charges or the basis of their calculation including issuing revisions to Appendices A and B of the Bilateral Connection Agreements.
Subject to Paragraph 2.15.3 below, The Company shall give the User not less than 2 months prior written notice of any revised charges, including revisions to Appendices A and B of the Bilateral Connection Agreements, which notice shall specify the date upon which such revisions become effective (which may be at any time). The User shall pay any such revised charges and Appendix A and B shall be amended automatically (and a copy sent to the User) to reflect any changes to such Appendices with effect from the date specified in such notice.
Where in accordance with the ESO Licence, the Authority requires a shorter period than 2 months for the implementation of revised charges, the notice period will be determined by the Authority. Where The Company and the User agree a shorter period than 2 months for the implementation of revised charges, the notice period will be as agreed between the parties. The notice of revisions issued by The Company will specify when the new charges are effective and the User shall pay any such revised charges and Appendix A and B shall be amended automatically with effect from the date specified in such notice;
Subject to the provisions of Paragraph 2.17 (Replacement of Transmission Connection Assets) below, if in the reasonable opinion of The Company any development, replacement, renovation, alteration, construction or other work to the National Electricity Transmission System or termination of a Bilateral Agreement or use of the National Electricity Transmission System by another User or an alteration to the requirements of the User or any other User means that to ensure that The Company is charging in accordance with the provisions of the Charging Statements pursuant to conditions E10 and E11 of the ESO Licence The Company needs to vary the Connection Charges payable by a User in relation to any of its Connection Sites then The Company shall have the right to vary such charges accordingly upon giving to the User not less than 2 months prior written notice. Following any such variation the provisions of Appendices A and B shall be amended automatically (and a copy sent to the User) to reflect such variation with effect from the date such variation comes into effect.
On or before the end of the second week of December in each Financial Year, each User shall supply The Company with such data as The Company may from time to time reasonably request pursuant to the Charging Statements to enable The Company to calculate the Connection Charges due from the User to The Company in respect of the Connection Site including the data specified in the Charging Statements.
Where the relevant date for charging set out in the relevant Bilateral Connection Agreement in relation to Connection falls during a Financial Year the User shall on the date specified in writing by The Company to the User supply to The Company such data in respect of the Financial Year in which the charging date falls and the following Financial Year which it would otherwise have supplied and The Company would otherwise have requested in accordance with Paragraph 2.16.1, in accordance with the terms of the Charging Statements.
The Company will provide information to each User on an ongoing basis with regards to its long term intentions and any programme for the replacement of any Transmission Connection Assets at a Connection Site.
Where in The Company’s reasonable opinion to enable The Company to comply with its statutory and licence duties and\or to enable any Relevant Transmission Licensee to comply with its statutory and licence duties it is necessary to replace a Transmission Connection Asset The Company shall give written notice of this (a “Replacement Notice”) such notice to be given (subject to Paragraph 2.17.7) as soon as practicable.
Following the issue of the Replacement Notice The Company shall provide an explanation of the economic and engineering reasons to asset replace and the parties shall meet as soon as practicable to consider options, programme and costs associated with the replacement.
The Company shall make an offer to the User(s) (subject to Paragraph 2.17.7) no earlier than 6 months after the date of the Replacement Notice detailing the variations it proposes to make to Appendices A and B of and any other changes required to the Bilateral Connection Agreement and if appropriate enclosing a Construction Agreement in respect of the replacement of the Transmission Connection Assets.
If after a period of 3 months from receipt of the offer or such longer period as the parties might agree the User(s) and The Company have failed to reach agreement on the offer then either party may make an application to the Authority under condition E13 of the ESO Licence to settle any dispute about the replacement of the Transmission Connection Assets.
Subject to Paragraph 2.17.7, The Company shall not replace the Transmission Connection Assets until the offer has been accepted by the User(s) or until the determination of the Authority if an application to the Authority has been made.
The Company shall take all reasonable steps to avoid exercising its rights pursuant to this Paragraph but in the event that The Company has reasonable grounds to believe, given its licence and statutory duties or the statutory and licence duties of a Relevant Transmission Licensee that a Transmission Connection Asset should be replaced prior to or during the process outlined above then The Company shall consult with the User(s) as far as reasonably practicable and shall be entitled to replace such Transmission Connection Asset and shall advise the User(s) of this and as soon as practicable make an offer for such replacement which can be accepted or referred in accordance with Paragraph 2.17.5 above.
Subject to Paragraph 2.17.9 Connection Charges shall be payable in respect of such replaced Transmission Connection Assets in accordance with the Statement of the Connection Charging Methodology and The Company shall give the User(s) not less than 2 months prior written notice of such varied charges and specify the date upon which such charges become effective. The Company shall be entitled to invoice the Connection Charges based on an estimate of the cost and the provisions of Paragraphs 2.14.3 and 2.14.4 shall apply.
Where Transmission Connection Assets have been replaced pursuant to Paragraph 2.17.7 The Company shall not be entitled to vary the Connection Charges until the offer has been accepted or the matter has been determined by the Authority and until such time the User(s) shall continue to pay Connection Charges as if the Transmission Connection Assets had not been replaced. If the matter is determined in The Company‘s favour then The Company shall be entitled to issue a revised Appendices A and B and the User(s) shall pay to The Company the difference between the two amounts plus interest at Base Rate on a daily basis from completion of the replacement to the date of payment by the User(s). if the matter is not determined in The Company’s favour Connection Charges shall be payable as directed by the Authority.
The obligation on the User to pay Termination Amounts is contained in Paragraph 2.14.7 and Section 5. Further provisions relating to Termination Amounts, including calculation of Termination Amounts, are dealt with in the Statement of the Connection Charging Methodology. The following parts of this Paragraph 2.18 deal with issues relating to re-use of Transmission Connection Assets in respect of which Termination Amounts have been paid.
The Company shall use its reasonable endeavours to re-use Transmission Connection Assets where Termination Amounts have been paid on the basis set in the Statement of the Connection Charging Methodology. Subject to Paragraph 2.18.4, in the event that a Termination Amount is paid in respect of Transmission Connection Assets and subsequently such Transmission Connection Assets in respect of which a payment has been made are re-used in the National Electricity Transmission System then The Company shall pay to the User a sum calculated in accordance with the Statement of the Connection Charging Methodology.
Re-use shall not occur where any Transmission Connection Asset remains connected for the purpose of providing a continuing connection for other Users connected to the National Electricity Transmission System at the Connection Site at the date of termination. However in the event of any User requiring a continued connection modifying its requirements or another User connecting at the Connection Site and the Transmission Connection Assets in respect of which a payment has been made are required for this modification this shall constitute re-use.
The Company shall be under no obligation to rebate any of the Termination Amounts relating to the re-use of assets as set out in the Statement of the Connection Charging Methodology except to the extent that Connection and/or Transmission Network Use of System Charges are subsequently received in respect of Transmission Connection Assets in relation to which such Termination Amounts have been paid to The Company during the Financial Year in which termination has occurred.
Upon request in writing, and at the cost of the User, The Company shall issue a certificate no more frequently than once each calendar year indicating whether or not such assets have or have not been re- used. If The Company at any time decides that it is not economic to retain any Plant and Apparatus constituting any Transmission Connection Asset in respect of which Termination Amounts have been paid it may at its reasonable discretion dispose of the said Plant and Apparatus and pay the User any sums due in accordance with the Statement of the Connection Charging Methodology.
Where a User has a connection to the National Electricity Transmission System it shall provide security for Termination Amounts for Transmission Connection Assets Commissioned after the Transfer Date in accordance with this Paragraph 2.19. For the avoidance of doubt references to Termination Amounts in this Part III only relate to Termination Amounts payable in respect of such Transmission Connection Assets.
Each User which has a connection to the National Electricity Transmission System shall provide security in respect of each of its Bilateral Connection Agreement(s):-
in the case of a User which meets The Company Credit Rating at the date of the Bilateral Connection Agreement, in accordance with Paragraph 2.20; and
in the case of a User which does not meet The Company Credit Rating at the date of the Bilateral Connection Agreement or thereafter ceases to meet it, in accordance with Paragraph 2.21.
Each User shall, as soon as possible after entering into a Bilateral Connection Agreement and in any event no later than one (1) month after such date, confirm to The Company the position on whether it meets The Company Credit Rating of which it advised The Company at the time that the offer was made by The Company. Thereafter not less than 75 days before 1 April and 1 October in each year the User shall confirm its The Company Credit Rating position to The Company (which in the case of a long term private credit rating shall be confirmed by Standard and Poor’s or Moody’s within a period of 45 days prior to the date of confirmation). The User shall inform The Company in writing forthwith if it becomes aware of losing its The Company Credit Rating or if it is or is likely to be put on credit watch or any similar credit surveillance procedure which may give The Company reasonable cause to believe that the User may not be able to sustain its The Company Credit Rating for at least 6 months.
In the event that the User has elected to provide The Company with an indicative credit rating and The Company is of the reasonable opinion that the User has ceased to comply with the requirements of Paragraph 2.20.1 then The Company may require the User forthwith:-
to apply to Standards and Poor’s and/or Moody’s for a further indicative long term private credit rating; or
to confirm to The Company that it shall provide the security referred to in Paragraph 2.20.4 hereof.
In the event of the User:-
not having an The Company Credit Rating; or
having a credit rating below The Company Credit Rating; or
not having obtained from Standard and Poor’s or Moody’s within 30 days of the written notification under Paragraph 2.20.2 above an indicative long term private credit rating, or if The Company becomes aware that
the User ceases to have an The Company Credit Rating; or
the User is put on credit watch or other similar credit surveillance procedure as specified above which may give The Company reasonable cause to believe that the User may not be able to maintain an The Company Credit Rating for at least 6 months; or
the User has not obtained from Standard and Poor’s or Moody’s within 30 days of the written notification by The Company under Paragraph 2.20.2 above a further indicative long term private credit rating, the User shall (where appropriate on receipt of written notification from The Company) comply with the terms of Paragraph 2.20.4.
The User shall within 21 days of the giving of a notice under Paragraph 2.20.3 or within 30 days of the User confirming to The Company under Paragraph 2.20.2 that it will provide the security specified in Paragraph 2.22.1 (whichever is the earlier), provide The Company with the security specified below to cover the User’s payment obligations to The Company arising in the event of termination of the relevant Bilateral Connection Agreement. The security to be provided shall be in an amount not greater than such sums payable on termination and specified in writing by The Company to the User from time to time in accordance with the timescales specified in Paragraph 2.21.2. Such security shall be of a type set out in 2.22.1.
Until the facts or circumstances giving rise to the obligations of the User to provide the security have ceased then the provisions of Paragraphs 2.21.2 to 2.22.2 shall apply.
In the event of The Company’s credit requirements being reviewed at any time The Company shall advise the User in writing of the new credit requirements and if acceptable to the User the security arrangements will be amended accordingly.
In the event that the facts or circumstances giving rise to the obligations of the User to provide the security have ceased, then The Company shall release the security.
Each User hereby agrees that it shall at the date of the relevant Bilateral Connection Agreement provide to The Company or procure the provision to The Company of, and the User shall at all times thereafter (unless and until the Bilateral Connection Agreement shall be terminated and all sums due or which will or might fall due in respect of which security is to be provided shall have been paid) maintain or procure that there is maintained in full force and effect (including by renewal or replacement), a security arrangement of a type specified in Paragraph 2.22.1 from time to time and for the time being to provide security for the User’s obligation to pay The Company Termination Amounts on termination of a Bilateral Agreement, in accordance with Paragraph 2.21.2.
Provision of Bi-annual Estimate and Secured Amount Statement
The Company shall provide to each relevant User a Bi- annual Estimate showing the amounts of all payments required or which may be required to be made by the User to The Company in respect of Termination Amounts (inclusive of any applicable Value Added Tax that would be due) at the following times and in respect of the following periods:-
forthwith on and with effect from the date required in accordance with Paragraph 2.20.4 in respect of the period from and including such date until the next following 31st March or 30th September (whichever shall first occur); and
not less than 75 (seventy five) days (or if such day is not a Business Day the next following Business Day) prior to each 31st March and 30th September thereafter in respect of the period of six calendar months commencing on the immediately following 1st April or 1st October (as the case may be), until the relevant Bilateral Connection Agreement shall be terminated and all sums due or which will or might fall due in respect of which security is to be provided shall have been paid.
Such Bi-annual Estimate shall be accompanied by the Secured Amount Statement specifying the aggregate amount to be secured at the beginning of and throughout each such period.
If The Company shall not provide any subsequent Bi-annual Estimate and Secured Amount Statement by the requisite date, then the User shall at the date it is next required to have in full force and effect security and whether by renewal or replacement or otherwise in respect of the following six calendar month period nonetheless provide security in accor- dance with the provisions of this Paragraph 2.21 in the same amount as the amount then in force in respect of the then current six calendar month period. Notwithstanding the foregoing, if The Company shall provide the User with any Bi-annual Estimate and Secured Amount Statement later than the date specified in Paragraph 2.21.2(a) then the following shall apply. The User shall within 30 (thirty) days of receipt of the said Secured Amount Statement procure that to the extent that the amount in respect of which security has been or is to be provided pursuant to this Paragraph 2.21.2(c) in respect of the relevant period (“the Secured Amount”) falls short of the amount stated in the Secured Amount Statement (the “Required Amount”) the Secured Amount shall be adjusted to the Required Amount.
Entitlement to Estimate If The Company is (for whatever reason) unable on any relevant date to calculate precisely any sum due or which has accrued due or in respect of which the User has a liability to The Company for payment under any of the provisions of this CUSC, The Company shall be entitled to invoice the User for a sum equal to The Company’s fair and reasonable estimate of the sums due or which may become due or in respect of which the User has a liability to The Company for payment. The Company shall also be entitled to send the User further invoices for such sums not covered in previous invoices. The User shall pay The Company all sums so invoiced by The Company.
Demands not Affected by Disputes It is hereby agreed between The Company and the User that if there shall be any dispute between the User and The Company as to:-
any amount certified by The Company in any Secured Amount Statement as requiring at any time and from time to time to be secured; or
the fairness and reasonableness of The Company’s estimate; or
whether there has been an Event of Default as provided in Section 5; or
the lawfulness or otherwise of any termination or purported termination of the relevant agreement, such dispute shall not affect the ability of The Company to make demands pursuant to the security arrangement to be provided pursuant to Paragraph 2.21 and to recover the amount or amounts payable thereunder, it being acknowledged by the User that but for such being the case The Company’s security would be illusory by reason of the period of validity of the relevant security being likely to expire or capable of expiring before the final resolution of such dispute. The User accordingly covenants with The Company that it will not take any action, whether by way of proceedings or otherwise, designed or calculated to prevent, restrict or interfere with the payment to The Company of any amount secured under the security arrangement nor seek nor permit nor assist others to do so.
If there shall be any dispute as mentioned in Paragraph 2.21.2(e) the same shall, whether The Company shall have terminated the relevant Bilateral Connection Agreement and recovered or sought to recover payment under the security arrangement or not, and without prejudice to The Company’s right to recover or seek to recover such payment, be dealt with in the case of Paragraphs 2.21.2(e)(i) and 2.21.2(e)(ii) under Section 7 as a Charging Dispute and, in the case of Paragraphs 2.21.2(e)(iii) and 2.21.2(e)(iv) be dealt with under Section 7 as an Other Dispute.
Security can be provided by:
A Performance Bond or Letter of Credit from a Qualified Bank for the amount stated in the Secured Amount Statement as the estimated amount to be secured, such Performance Bond or Letter of Credit to be Valid for at least the period stated in such Secured Amount Statement and to be renewed periodically where applicable in the manner stated in Paragraph 2.22.2(c); or
A cash deposit in a Bank Account at least for the amount stated in the Secured Amount Statement as the estimated amount to be secured, such cash deposit to be increased or reduced periodically where applicable in the manner stated in Paragraph 2.22.2(d); or
A Performance Bond from a Qualified Company for the amount stated in the Secured Amount Statement as the estimated amount to be secured, such Performance Bond to be Valid for at least the period stated in such Secured Amount Statement and to be renewed periodically where applicable in the manner stated in Paragraph 2.22.2(c)
General Provisions
Any Notice of Drawing to be delivered to Barclays Bank PLC or any other bank at which the Bank Account shall have been opened or a Qualified Bank or a Qualified Company may be delivered by hand, by post, or by other agreed communication method.
If the User becomes aware that the bank issuing the Performance Bond or Letter of Credit ceases to be a Qualified Bank or that the company giving the Performance Bond ceases to be a Qualified Company, the User shall notify The Company in writing as soon as it becomes so aware. If The Company becomes aware that the bank issuing the Performance Bond or Letter of Credit ceases to be a Qualified Bank or that the company giving the Performance Bond ceases to be a Qualified Company, The Company may notify the User to that effect in writing. Where the bank or the company so ceases to be either a Qualified Bank or a Qualified Company (as the case may be) as a consequence of The Company having reasonable cause to doubt the continued rating of the said bank or company, such notice shall be accompanied by a statement setting out The Company’s reasons for having such doubt. The User shall within 21 days of the giving of such notice by The Company or the User whichever is the earlier provide a replacement Performance Bond and/or Letter of Credit from a Qualified Bank or Qualified Company, as the case may be, and/or provide a cash deposit in the required amount in a Bank Account. From the date the replacement Performance Bond or Letter of Credit or Bank Account cash deposit is effectively and unconditionally provided and Valid, The Company will consent in writing to the security which it replaces being released.
The following provisions shall govern the issuance, renewal and release of the Performance Bond or Letter of Credit:-
The Performance Bond or Letter of Credit shall be Valid initially from the date required in accordance with Paragraph 2.20.4 or 2.21.1 respectively at least to and including the following 31st March or 30th September whichever is the earlier date. Such Performance Bond or Letter of Credit shall be for an amount not less than that stated in the Secured Amount Statement to be secured during the period specified in the Secured Amount Statement.
On a date which is at least 45 days (or if such day is not a Business Day then on the immediately preceding Business Day) before the next following 31st March or 30th September whichever is the earlier date such Performance Bond or Letter of Credit shall be renewed so as to be Valid for not less than 6 months commencing from the immediately following 1st April or 1st October (as the case may be). Such renewed Performance Bond or Letter of Credit shall be for an amount not less than the amount stated in the Secured Amount Statement as the amount to be secured during the period that such renewed Performance Bond or Letter of Credit shall be Valid.
Thereafter, the renewed Performance Bond or Letter of Credit shall be further renewed in like manner every 6 months.
The following provisions shall govern the maintenance of cash deposits in the Bank Account:-
The amount of the User’s cash deposit to be maintained in the Bank Account shall be maintained by the User from the date required in accordance with Paragraph 2.20.4 or 2.21.1 respectively at least to and including the following 31st March or 30th September, whichever is the earlier date. Such cash deposit shall be in an amount as stated in the Secured Amount Statement to be secured during the period stated in the Secured Amount Statement.
If the amount stated in the Secured Amount Statement as the amount to be secured from the following 1st April to 30th September or from the following 1st October to 31st March (as the case may be) is an amount greater than the amount then secured, the User’s cash deposit in the Bank Account shall be increased by the User to such greater amount on a date which is 45 days before the following 31st March or 30th September (as the case may be) which immediately precedes the commencement of the relevant above mentioned period.
If such amount stated in the Secured Amount Statement is smaller than the amount then secured, the User’s cash deposit in the Bank Account shall not be reduced to the amount so stated until the expiry of 7 days after the next following 31st March or 30th September (as the case may be) (the “Release Date”).
The sum equal to the amount of reduction in User’s the cash deposit in the Bank Account shall be paid by The Company to the User from the Bank Account on the Release Date.
Any interest accruing in respect of the User’s cash deposit into the Bank Account shall be for the account of and belong to the User absolutely, and The Company agrees to take any steps required to be taken by it for the release from the Bank Account or such associated bank account in the name of The Company in which such interest is held and payment to the User of such interest as soon as the same shall have been credited to the Bank Account and The Company shall have received notice from the User requesting such payment.
For the avoidance of doubt, the User’s cash deposit in the Bank Account shall remain the sole property and entitlement of the User until such time when (and to such extent as) the Company exercises its right of set off against the User’s cash deposit in accordance with the terms of the CUSC, and the User shall have no right to have the cash deposit returned to it for so long as it is under any prospective or contingent liability to the Company.
Notwithstanding any provision aforesaid:-
The User may provide different securities to The Company at any one time, each securing a different amount, provided that the aggregate amount secured by such securities shall be not less than the aggregate amount required to be secured pursuant to the Secured Amount Statement for any period specified therein.
The User may upon the expiry of at least 14 days prior written notice to The Company, substitute one type of security for another provided that unless The Company shall otherwise agree in writing such substituted security must be Valid from 1st April or 1st October (as the case may be) and committed at least 45 days before the immediately preceding 31st March or 30th September (as the case may be) in the following manner:-
where a Performance Bond or a Letter of Credit is to substitute for other securities, it must be issued or given at least 45 days before such immediately preceding 31st March or 30th September (as the case may be).
where a cash deposit in a Bank Account is to substitute for other securities, it must be deposited into the Bank Account at least 45 days before such immediately preceding 31st March or 30th September (as the case may be).
Upon request by the User to The Company, securities substituted in the aforesaid manner shall, providing the substitute security shall be Valid, be released on the following 1st April or 1st October (as the case may be). However, where the amount required by the Secured Amount Statement to be secured for any period is less than the amount required to be secured in the preceding period, the substituted security shall not be released until 7 days after the then following 31st March or 30th September (as the case may be). SCHEDULE 1
SECTION 3: USE OF SYSTEM
INTRODUCTION This Section 3 deals with use of the National Electricity Transmission System and certain related issues. Part I of this Section sets out general provisions (split into Parts A and B dealing with generation, supply and VLP), Part II sets out charging related provisions and Part III sets out the credit requirements related to Use of System. Depending on the category of connection and/or use of a User, the Section dealing with Connection (Section 2) may also be applicable.
Embedded Use of System Subject to the other provisions of the CUSC, the Grid Code and the relevant Bilateral Embedded Generation Agreement, and subject to there continuing to be a Distribution Agreement with the owner/operator of the Distribution System, each User, as between The Company and that User, may in relation to each of its Embedded generation sites and each of its Distribution Interconnectors transmit (or put, as the case may be) supplies of power on to and/or take supplies of power from the National Electricity Transmission System as the case may be.
Embedded Power Station and Distribution Interconnector Conditions
The rights and obligations of a User, and The Company in connection therewith, are subject to the following conditions precedent having been fulfilled before such rights and obligations arise:
the User having provided (in a form reasonably satisfactory to The Company) proof of having entered into a Distribution Agreement with the owner/operator of the Distribution System; and
in the case of an Embedded Small Power Station The Company having received satisfactory confirmation from the owner/operator of the Distribution System as to the running arrangements within the Distribution System;
in the case of an Embedded Small, Medium and Large Power Station, in relation to a Small Power Station Trading Party and in the case of a Distribution Interconnector, of the acceptance by the owner/operator of the Distribution System of any necessary Modification Offer relevant to the Embedded Power Station or Distribution Interconnector (as the case may be);
If the conditions precedent of 3.2.2(a)(i) to (iii) have not been fulfilled in the case of 3.2.2(a)(i) and 3.2.2(a)(ii) within 6 months of the date of the relevant Bilateral Embedded Generation Agreement or in the case of 3.2.2(a)(iii) within 3 months of the date of receipt by the owner/operator of the Distribution System of the Modification Offer The Company or the relevant User may rescind the relevant Bilateral Embedded Generation Agreement and any associated Construction Agreement by giving to the other notice to that effect in which event all rights and liabilities of the parties thereunder and under the CUSC in relation to relevant Embedded Power Stations or relevant Distribution Interconnectors shall cease.
Transmission Entry Capacity
Other than as provided in Paragraph 3.2.3(b), each User, as between The Company and that User, shall not operate its User's Equipment such that its export of power onto the National Electricity Transmission System exceeds the Transmission Entry Capacity and (if any) STTEC and\or LDTEC and\or any Temporary Received TEC less any Temporary Donated TEC for the relevant Period set out in Appendix C to the relevant Bilateral Embedded Generation Agreement save as expressly permitted and instructed pursuant to an Emergency Instruction under the Grid Code or save as expressly permitted and instructed pursuant to the Fuel Security Code or as may be necessary or expedient in accordance with Good Industry Practice.
Each User in respect of an Embedded Small Power Station and a Distribution Interconnector and as a Trading Party responsible for Embedded Small Power Stations, as between The Company and that User, shall not operate its User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) such that its export of power onto the National Electricity Transmission System exceeds the Transmission Entry Capacity and (if any) STTEC and\or LDTEC and\or any Temporary Received TEC less any Temporary Donated TEC for the relevant Period set out in Appendix C to the relevant Bilateral Embedded Generation Agreement save as expressly permitted and instructed pursuant to the Fuel Security Code or as may be necessary or expedient in accordance with Good Industry Practice.
Subject to the other provisions of the CUSC and the Grid Code and any relevant Bilateral Agreement, The Company shall, as between The Company and that User, accept into the National Electricity Transmission System power generated by each User up to the Transmission Entry Capacity and (if any) STTEC and\or any Temporary Received TEC less any Temporary Donated TEC for the relevant Period set out in Appendix C of the relevant Bilateral Connection Agreement except to the extent (if any) that The Company is prevented from doing so by transmission constraints which could not be avoided by the exercise of Good Industry Practice by The Company. Outages Subject to the provisions of the Grid Code, The Company and each User (with Plant and/or Apparatus) shall, as between The Company and that User, be entitled to plan and execute outages of parts of in the case of The Company, the National Electricity Transmission System or Transmission Plant or Transmission Apparatus and in the case of a User, its System or Plant or Apparatus, at any time and from time to time.
Commissioning The Company agrees to assist the User (if requested by the User), with the commissioning and on-load testing of the User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) and the User shall pay reasonable The Company Charges in connection therewith. The User must ensure the commissioning programme for the User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) at the site of connection agreed between the User and the owner/operator of the Distribution System contains adequate provisions in respect of the timing of commissioning to ensure that the User can be in receipt of an Operational Notification before or during (as appropriate) the said commissioning programme.
Operational Notification Upon compliance by the User with the provisions of Paragraph 3.2.2(a) after the commissioning programme in Paragraph 3.2.6 and subject, if The Company so requires, to Transmission Reinforcement Works being carried out and/or notification by the User that the site of connection of the User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) to the Distribution System is operational (any or all as appropriate) The Company shall forthwith notify (“Operational Notification”) the User in writing that it has the right to use the National Electricity Transmission System. It is an express condition of the CUSC that in no circumstances will the User use or operate the User’s Equipment or Equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) without receiving this Operational Notification.
The Company and each User shall, as between The Company and that User, operate respectively the National Electricity Transmission System and the User System with the special automatic facilities and schemes set out in Appendix F3 to the relevant Bilateral Embedded Generation Agreement.
Each User shall ensure the User’s Equipment complies with the site specific technical conditions set out in Appendix F4 to the relevant Bilateral Embedded Generation Agreement.
Each User shall use all reasonable endeavours to ensure during the period of the relevant Bilateral Embedded Generation Agreement that the User’s Equipment shall continue to comply with the site specific technical conditions set out in Appendix F5 to the relevant Bilateral Embedded Generation Agreement.
If a User or The Company wishes to modify, alter or otherwise change the site specific technical conditions or the manner of their operation under Appendices F1, F3, F4 or F5 to the relevant Bilateral Embedded Generation Agreement this shall be deemed to be a Modification for the purposes of the CUSC.
Where in the case of a site Commissioned in England and Wales prior to the Transfer Date, on or immediately prior to the Transfer Date a User’s Equipment subject to a Bilateral Embedded Generation Agreement has any of the following technical attributes or facilities:
control arrangements
voltage and current signals for system monitoring
control telephony
operational metering the User shall, as between The Company and that User, use all reasonable endeavours to ensure that during the period of such Bilateral Agreement the User's Equipment which is subject to that Bilateral Agreement retains such technical attributes or facilities provided always that if the User wishes to modify, alter or otherwise change the same or their operation it may do so by following the procedures relating to a Modification in accordance with the CUSC.
Subject to the other provisions of the CUSC and the Grid Code, each User, as between The Company and that User, may take supplies of power from the National Electricity Transmission System.
Subject to the provisions of the CUSC and the Grid Code, The Company shall, as between The Company and that User, transport a supply of power through the National Electricity Transmission System to the level forecast by the User from time to time pursuant to the Data Requirements set out in Part IIB of this Section 3 submitted by that User together with such margin as The Company shall in its reasonable opinion consider necessary having due regard to The Company 's duties under the ESO Licence except to the extent (if any) that The Company is prevented from doing so by transmission constraints or by insufficiency of generation which, in either case, could not have been avoided by the exercise of Good Industry Practice by The Company.
Subject to the provisions of the Grid Code, The Company shall be entitled to plan and execute outages of parts of the National Electricity Transmission System or Transmission Plant or Transmission Apparatus at any time and from time to time.
Each User shall, as between The Company and that User, give written notice to The Company of the following details of all exit points from time to time in existence between any Distribution System and the User’s customer:-
the electrical location and nomenclature of the Energy Metering Equipment installed in relation to each such customer;
the identity of the operator of the Distribution System to which such customers are connected;
the Grid Supply Point and Transmission Network Use of System Demand Zone meeting the Demand (Active Power) of each customer;
the loss factors applying to the Energy Metering Equipment installed in relation to each such customer, save where the User’s customer is connected to a Distribution System owned by a Public Distribution System Operator in which case the Public Distribution System Operator’s published statement of loss factors shall apply. Such written notice shall be given to The Company no later than 28 days prior to the commencement or cessation of use of any such exit point. If the Grid Supply Point referred to in (c) changes the User shall notify The Company forthwith after being notified of such change by the Public Distribution System Operator in question. If The Company’s basis of charging changes pursuant to the Charging Statements or, subject thereto, Parts II and III below at any time, The Company shall be entitled to ask for other information it reasonably requires for charging purposes under this Paragraph 3.5.
CUSC Parties agree that, insofar as The Company has alternative reasonable means of obtaining this information then Paragraph 3.5.1 shall not apply.
This Paragraph 3.6 relates specifically to the position of a Supplier in respect of its supply of electricity to a Non-Embedded Customer. Insofar as the provisions of this Paragraph 3.6 conflict with any other provision of this Section 3 dealing with an equivalent issue, the provisions of this Paragraph 3.6 shall prevail in relation to such a category.
In the case of such a User, subject to the provisions of the CUSC and the Grid Code, The Company shall transport a supply of power through the National Electricity Transmission System to the Connection Site of the Non-Embedded Customer to the level forecast by the User from time to time pursuant to the Data Requirements set out in Part IIB of this Section 3 submitted by that User together with such margin as The Company shall in its reasonable opinion consider necessary having due regard to The Company’s duties under the ESO Licence except to the extent (if any) that The Company is prevented from doing so by transmission constraints or by insufficiency of generation which, in either case, could not have been avoided by the exercise of Good Industry Practice by The Company.
The right in 3.6.2 above is subject to:
the User being authorised by a current Supply Licence to supply electricity to the premises to be supplied with electricity through the Connection Site; and
there being a subsisting Bilateral Connection Agreement with the Non-Embedded Customer for the Connection Site.
Where The Company agrees, the Supplier of a Non-Embedded Customer may be liable for payment of Connection Charges in relation to the Metering Equipment of a Non-Embedded Customer. The existence of such an arrangement shall be reflected in the relevant Bilateral Connection Agreement with the Non-Embedded Customer and the Use of System Supply Confirmation Notice. Where such an arrangement exists, the provisions of Section 2 Part II in relation to such charges shall be deemed incorporated within this Paragraph 3.6.4 and the Supplier shall comply with those provisions in relation to such charges as if references to the User were references to the Supplier.
The User acknowledges that breach of the provisions of the CUSC by the Non-Embedded Customer may give rise to Deenergisation of the Non-Embedded Customer’s Connection Site pursuant to Section 5.
The User acknowledges that site specific technical conditions as provided for in Paragraphs 2.7 to 2.9 of the CUSC may apply between The Company and a Non-Embedded Customer at a Connection Site.
The Company shall be entitled to Deenergise the Non- Embedded Customer’s Equipment at any Connection Site when instructed to do so by the Non-Embedded Customer in accordance with the terms of its Bilateral Connection Agreement or the CUSC.
Where the Supplier supplying the Connection Site has informed The Company that it has received an order or direction from the Secretary of State for Energy under the Energy Act 1976 or the Act, requiring it to cease supplying the Non-Embedded Customer with electricity and instructs The Company to Deenergise the Non-Embedded Customer’s User’s Equipment at the Connection Site, The Company shall as soon as reasonably practicable Deenergise the Non-Embedded Customer’s User’s Equipment at the Connection Site (unless The Company considers that it is not reasonably practicable, whether on technical grounds or otherwise, to effect such Deenergisation) and if it does Deenergise, shall promptly notify the User of the date and time at which such Deenergisation was effected. The User shall reimburse The Company any expense incurred in relation to such Deenergisation, if any, and shall indemnify The Company against any costs, liability, loss or damage suffered by The Company as a result of such Deenergisation.
SUPPLIER DEENERGISATION OF NON-EMBEDDED CUSTOMERS
The Company shall, to the extent that it may lawfully do so, at the request of the Supplier, when the Supplier is entitled to have the Deenergisation of a Non-Embedded Customer, Connection Site(s), carried out, carry out such Deenergisation on behalf of and at the cost of the Supplier within a reasonable time or, in circumstances of urgency, as soon as is reasonably practicable.
The Company shall if requested by the Supplier, inform the Supplier of its reasonable requirements for the details of the Non-Embedded Customer’s Connection Site(s) to be De- energised.
The Company shall Reenergise the User’s Equipment at the Non-Embedded Customer’s Connection Site as soon as is reasonably practicable after the circumstances leading to Deenergisation under Paragraph 3.6.9.(a) have ceased to exist. Duty to Indemnify
Where The Company carries out a Deenergisation on behalf of a Supplier under Paragraph 3.6.9.(a) The Company shall indemnify the Supplier against (a) all actions, proceedings, costs, demands, claims, expenses, liability, loss or damage made against or incurred or suffered by the Supplier as a consequence of, physical damage to the property of the Supplier, its officers, employees or agents, (including any claim by another User connecting at the same substation) and (b) in respect of the liability of the Supplier to any other person for loss in respect of physical damage to the property of any person, in each case as a consequence of The Company acting contrary to an accurate and appropriate instruction from the Supplier to Deenergise the Non-Embedded Customer’s Connection Site;
Save for any matters arising from or in connection with the negligent act or omission or default of The Company, its officers, employees or agents, the Supplier shall indemnify The Company against (a) all actions, proceedings, costs, demands, claims, expenses, liability, loss or damage arising from, or incurred by The Company as a consequence of, physical damage to the property of The Company, its officers, employees or agents, and (b) in respect of the liability of The Company to any other person for loss in respect of physical damage to the property of any person, in each case as a consequence of acting in reliance on any instructions given by the Supplier to The Company to Deenergise the Non-Embedded Customer’s Connection Site which are materially inaccurate or misleading; and
Where the Supplier requests The Company to Deenergise a single point of connection that is both a Grid Supply Point and a Grid Entry Point, the Supplier shall also indemnify The Company against all actions, proceedings, costs, demands, claims, expenses, liability, loss or damage made against or incurred or suffered by The Company and resulting directly from such Deenergisation howsoever arising (including any claim by another User connecting at the same substation) except insofar as such actions, proceedings, costs, demands, claims, expenses, liability, loss or damage arise from the negligent act or omission or default of The Company, its officers, employees or agents. Downstream Parties
A Non- Embedded Customer shall provide its Supplier on request and as soon as is reasonably practicable with the details of any Downstream Parties including (but not limited to) contact names, addresses, email addresses, and telephone numbers.
Prior to a Supplier instructing The Company to Deenergise the Non-Embedded Customer’s Connection Site(s) under Paragraph 3.6.9.(a):
(a) the Supplier shall request the Non- Embedded Customer to confirm within 48 hours of such request that the details supplied under Paragraph 3.6.9.(g), remain correct and/or provide updated details for any Downstream Parties, and where such details had been supplied by the Non-Embedded Customer to the Supplier within the preceding 10 Business Days, the Supplier may, whilst making this request, in parallel and without delay give notice to arrange the meeting described in (b), below;
where there are Downstream Parties (other than Downstream Parties that are Affiliates of the Non-Embedded Customer), the Supplier shall, giving not less than 48 hours’ notice, arrange a meeting between the Supplier, the Non-Embedded Customer, those Downstream Parties and The Company to discuss the impact of the Deenergisation and whether an agreement to avoid the Deenergisation and resulting impact on those Downstream Parties can be reached to the reasonable satisfaction of the Supplier (acting reasonably); and
the Supplier shall not issue its Deenergisation instruction to The Company within 72 hours (or such longer period, determined by the Supplier from time to time, at their sole discretion, and notified to the attendees of any meeting held under (b)) from the commencement of any meeting held under (b).
If a User wishes to use the National Electricity Transmission System in a category of use which does not include connection to the National Electricity Transmission System, it shall complete and submit to The Company a Use of System Application and comply with the terms thereof.
Where the Use of System Application:
is not a Gated Application for the purposes of the Gated Application and Offer Process, without prejudice to Condition E12 of the ESO Licence The Company shall make a Use of System Offer to that User as soon as practicable after receipt of the Use of System Application and (save where the Authority consents to a longer period) in any event not more than 28 days after receipt by The Company of the Use of System Application.
is a Gated Application for the purposes of the Gated Application and Offer Process, the Use of System Application and Use of System Offer shall be processed in accordance with the Gated Application and Offer Process.
The Use of System Offer shall in the case of an application relating to an Embedded Power Station or to a Small Power Station Trading Party or to a Distribution Interconnector be in the form of a Bilateral Embedded Generation Agreement together with any Construction Agreement relating thereto. In the case of a Virtual Lead Party, it shall be in the form of a Virtual Lead Party Agreement. In the case of a Supplier, it shall be in the form of a Use Of System Supply Offer Notice.The provisions of Standard Condition C8 shall apply to an application by a Supplier as if the Use of System Supply Offer and Confirmation Notice was an agreement for the purposes of that condition.
The Use of System Offer shall remain open for acceptance (subject to CUSC Paragraph 6.10.4.4) for 3 months from its receipt by that User unless either that User or The Company makes an application to the Authority under Condition E13 of the ESO Licence, in which event the Use of System Offer shall remain open for acceptance until the date 14 days after any determination by the Authority pursuant to such application.
Upon acceptance of the Use of System Offer (as offered by The Company or determined by the Authority) by the User and execution by The Company of the Bilateral Embedded Generation Agreement or Virtual Lead Party Agreement or the issuing by The Company of a Use of System Supply Confirmation Notice, as the case may be, the User shall have the right to use the National Electricity Transmission System. Such right shall continue until the Bilateral Embedded Generation Agreement or Virtual Lead Party Agreement is terminated or a Use of System Termination Notice is submitted pursuant to Paragraph 3.8.
Such rights shall be conditional upon the Applicant, if it is not already a party to the CUSC Framework Agreement, becoming a party to the CUSC Framework Agreement.
In the event that the User requests a Use of System Offer in the form of a Bilateral Embedded Generation Agreement on the basis of a Design Variation then:
The Company shall only be obliged to provide such an offer in so far as such an offer satisfies the conditions detailed in Chapter 3 of the NETS SQSS; and
The Company shall be obliged, at the request of the User as part of the Use of System Offer, to provide such information that the User may reasonably require in order to assess the probability of Notification of Restrictions on Availability being issued. For the avoidance of doubt, the information that is provided by The Company under this clause shall be a best estimate only and is not legally binding.
Provisions relating to Disconnection relating to Users who have Bilateral Embedded Generation Agreements are dealt with in Section 5. 3.8.1(A) Provisions relating to Users who have Virtual Lead Party Agreements are dealt with in Section 5.
In addition to the provisions in Section 5, this paragraph deals with termination of the right to use the system in respect of a Supplier who in that category of connection and/or use has no physical presence on the System and with a specific additional provision for the Supplier of a Non-Embedded Customer.
(a) A Supplier may terminate its use of the National Electricity Transmission System by giving The Company a Use of System Termination Notice not less than 28 days prior to such termination of use.
If a Use of System Termination Notice is given under this Section 3, the right to use the National Electricity Transmission System shall cease upon the termination date in the Use of System Termination Notice.
Prior to cessation of use by a User under this Paragraph, the User shall pay The Company all Use of System Charges payable by it under Section 3 in respect of the Financial Year in which the cessation takes place.
In addition, in the case of a User in its category of connection and/or use as a Supplier of a Non-Embedded Customer the use of the National Electricity Transmission System in respect of the Connection Site shall cease upon either Disconnection of the User’s Equipment of the Non-Embedded Customer or termination of the Bilateral Connection Agreement in respect of that Connection Site. PART IC – GENERAL – VIRTUAL LEAD PARTIES This Part IC deals with rights and obligations relating to Virtual Lead Parties. References to “User” in this Part IC should be construed accordingly. 3.8A RIGHTS TO USE THE NATIONAL ELECTRICITY TRANSMISSION SYSTEM 3.8A.1 Virtual Lead Party Subject to the other provisions of the CUSC, the Grid Code and the relevant Virtual Lead Party Agreement, and subject to there continuing to be a Distribution Agreement with the owner/operator of the Distribution System in respect of the VLP Assets, each User, as between The Company and that User, may in relation to each of its VLP Assets transmit (or put, as the case may be) supplies of power on to and/or take supplies of power from the National Electricity Transmission System as the case may be. 3.8A.2 Virtual Lead Party Conditions
The rights and obligations of a User, and The Company in connection therewith, are subject to the following conditions precedent having been fulfilled before such rights and obligations arise:
the User having provided (in a form reasonably satisfactory to The Company) proof of having entered into a Distribution Agreement with the owner/operator of the Distribution System in respect of the VLP Assets; and
The Company having received satisfactory confirmation from the owner/operator of the Distribution System as to the running arrangements within the Distribution System;
The User having successfully registered a Secondary BMU.
If the conditions precedent of 3.8A.2(a)(i) to (iii) have not been fulfilled within 6 months of the date of the relevant Virtual Lead Party Agreement, The Company or the relevant User may rescind the relevant Virtual Lead Party Agreement by giving to the other notice to that effect in which event all rights and liabilities of the parties thereunder and under the CUSC in relation to the VLP Assets shall cease. 3.8A.3 Outages and Constraints
Subject to the other provisions of the CUSC and the Grid Code and any relevant Virtual Lead Party Agreement, The Company shall, as between The Company and that User, accept into the National Electricity Transmission System power from each User except to the extent (if any) that The Company is prevented from doing so by transmission constraints which could not be avoided by the exercise of Good Industry Practice by The Company. 3.8A.4 TECHNICAL CONDITIONS FOR VIRTUAL LEAD PARTIES 3.8A.4.1 Each User shall use all reasonable endeavours to ensure during the period of the relevant Virtual Lead Party Agreement that the VLP Assets shall comply with the technical conditions set out in Appendix F5 to the relevant Virtual Lead Party Agreement. 3.8A.4.2 If a User or The Company wishes to modify, alter or otherwise change the technical conditions or the manner of their operation under Appendix F5 to the relevant Virtual Lead Party Agreement this shall be deemed to be a Modification for the purposes of the CUSC.
Subject to the provisions of the CUSC, and any relevant Bilateral Agreement, together with the relevant Charging Statements, each User shall with effect from the relevant date set out in the relevant Bilateral Agreement (or in the Use of System Supply Confirmation Notice) be liable to pay to The Company the Use of System Charges in accordance with the CUSC calculated in accordance with the Statement of Use of System Charges and the Statement of the Use of System Charging Methodology. The Company shall apply and calculate the Use of System Charges in accordance with the Statement of Use of System Charges and the Statement of the Use of System Charging Methodology.
Each User shall, as between The Company and that User, in accordance with this Part II and Paragraph 6.6, be liable to pay to The Company (or The Company shall be so liable to pay to the User) the Transmission Network Use of System Charges and (if appropriate) the STTEC and LDTEC Charge in respect of its use of the National Electricity Transmission System applied and calculated in accordance with the Statement of Use of System Charges and Statement of the Use of System Charging Methodology.
Except in respect of Distribution Interconnector Owners each User shall, as between The Company and that User, in accordance with this Part II and Paragraph 6.6, be liable to pay to The Company in respect of each Settlement Day the Balancing Services Use of System Charges calculated in accordance with the Statement of the Use of System Charging Methodology.
Each User shall, as between The Company and that User, provide The Company with Security Cover in respect of Transmission Network Use of System Demand Reconciliation Charges, Transmission Services Use of System Charges and Balancing Services Use of System Charges in accordance with Part III below.
The charges payable in relation to use of the National Electricity Transmission System may also include One-off Charges where those are to be payable by the relevant User as provided in the relevant Bilateral Embedded Generation Agreement. In that case, the relevant provisions of Section 2 will apply to that User in relation to the One-off Charges.
Where a User’s connection to the National Electricity Transmission System involves the connection of an Offshore Transmission System to a Distribution System, the ET Use of System Charges shall be payable by the User in an amount, manner and timing that reflects The Company’s obligation to the ET Interface Operator for the charges for connection to and use of that Distribution System. These will be specified, to the extent practicable, in the User’s Bilateral Connection Agreement. PART IIB – TRANSMISSION NETWORK USE OF SYSTEM CHARGES
On or before the end of the second week of December in each Financial Year, each User shall supply The Company with such data as described under Section 3.10 as The Company may from time to time reasonably request to enable The Company to calculate the tariffs for the Transmission Network Use of System Charges pursuant to the Charging Statements for the Financial Year to which the data relates.
On or before the 10th day of March in each Financial Year, each User shall supply The Company on The Company’s reasonable request with its Demand Forecast for the following Financial Year pursuant to the Charging Statements to enable The Company to use such Demand Forecast as the basis for calculation of the Transmission Network Use of System Charges for the Financial Year to which the Demand Forecast relates.
In the event that a User fails to provide a Demand Forecast in accordance with Paragraph 3.10.2 above the User shall be deemed to have submitted as its Demand Forecast the last Demand Forecast supplied under Paragraph 3.11.1.
Where a Use of System Supply Confirmation Notice is completed during a Financial Year, the User shall supply The Company, with its Demand Forecast for that Financial Year on or before the 10th day of the month following completion of the Use of System Supply Confirmation Notice.
On or before the end of the second week in December in each Financial Year, each User that is liable for generation Use of System Charges in accordance with 3.9 shall supply The Company with a forecast maximum TEC for the following year, to inform The Company of the forecast generation to be used for the purposes of setting TNUos Tariffs.
Where a User’s connection to the National Electricity Transmission System involves the connection of an Offshore Transmission System to a Distribution System, each such User shall supply The Company with such data as The Company may from time to time reasonably request to enable the calculation of the ET Use of System Charges.
Each User shall notify The Company of any revision to its Demand Forecast at least quarterly or at such intervals as may be agreed between The Company and the User from time to time.
Subject to Paragraph 3.12, The Company shall revise the Transmission Network Use of System Charges payable by a User to take account of any revised Demand Forecast and shall commence charging the revised Transmission Network Use of System Charges from the first day of the month following the month in which such revised Demand Forecast was received provided always that such Demand Forecast is provided before the 10th day of such month.
The Demand Forecast shall represent a User’s reasonable estimate of its Demand. 3.12.1a The Company shall use the latest available data of actual FDSC and Unmetered Supply Volume as the basis of its FDSC Forecast and Unmetered Supply Volume Forecast.
The Company shall notify the User in the event that the Transmission Network Use of System Charges due from the User to The Company or from The Company to the User (as the case may be) calculated by The Company using the Demand Forecast, FDSC Forecast and Unmetered Supply Volume Forecast differ by more than 20% from that calculated by The Company using The Company’s forecast Demand, FDSC Forecast and Unmetered Supply Volume Forecast as provided for in the Charging Statements.
In the event that The Company does not receive a satisfactory explanation for the difference between the Demand Forecast and The Company’s forecast of Demand or a satisfactory revised Demand Forecast from the User within 5 Business Days of such notice then The Company shall be entitled to invoice a User for Transmission Network Use of System Charges calculated on the basis of The Company forecast Demand.
Any dispute regarding a Demand Forecast, or FDSC Forecast or Unmetered Supply Volume Forecast or the resulting Transmission Network Use of System Charges shall be a Charging Dispute.
RECONCILIATION STATEMENTS Calculation of Initial Reconciliation
On or before 30 June in each Financial Year, The Company shall promptly calculate in accordance with the Statement of the Use of System Charging Methodology and the Statement of Use of System Charges the Demand related, FDSC related, Unmetered Supply Volume related or generation related Transmission Network Use of System Charges (as the case may be) that would have been payable by the User during each month during the preceding Financial Year (Actual Amount). The Company shall then compare the Actual Amount with the amount of Demand related, FDSC related, Unmetered Supply Volume related or generation related Transmission Network Use of System Charges (as the case may be) paid each month during the preceding Financial Year by the User (the “Notional Amount”). Generation Reconciliation
As soon as reasonably practicable and in any event by 30 April in each Financial Year The Company shall prepare a generation reconciliation statement (the “Generation Reconciliation Statement”) in respect of generation related Transmission Network Use of System Charges and send it to the User. Such statement shall specify the Actual Amount and the Notional Amount of generation related Transmission Network Use of System Charges for each month during the relevant Financial Year and, in reasonable detail, the information from which such amounts were derived and the manner in which they were calculated.
Together with the Generation Reconciliation Statement, The Company shall issue a credit note in relation to any sums shown by the Generation Reconciliation Statement to be due to the User or an invoice in respect of sums due to The Company and in each case interest thereon calculated pursuant to Paragraph 3.13.6 below. Initial Demand Reconciliation Statement
As soon as reasonably practicable and in any event by 30 June in each Financial Year The Company shall then prepare an initial Demand reconciliation statement (the “Initial Demand Reconciliation Statement”) in respect of Demand and FDSC and Unmetered Supply Volume related Transmission Network Use of System Charges and send it to the User. Such statement shall specify the Actual Amount and the Notional Amount of Demand and FDSC and Unmetered Supply Volume related Transmission Network Use of System Charges for each month during the relevant Financial Year and, in reasonable detail, the information from which such amounts were derived and the manner in which they were calculated.
Together with the Initial Demand Reconciliation Statement The Company shall issue a credit note in relation to any sum shown by the Initial Demand Reconciliation Statement to be due to the User or an invoice in respect of sums due to The Company and in each case interest thereon calculated pursuant to Paragraph 3.13.6.
General Provisions
Invoices issued under paragraphs 3.13.3 and 3.13.5 above and 3.13.8 (b) below shall be payable within 30 days of the date of the invoice.
Interest on all amounts due under this Paragraph 3.13 shall be payable by the paying CUSC Party to the other on such amounts from the date of payment applicable to the month concerned until the date of actual payment of such amounts and such interest shall be calculated on a daily basis at a rate equal to the Base Rate during such period.
Final Reconciliation Statement
The Company shall as soon as reasonably practicable following receipt by it of the Final Reconciliation Settlement Run or Final Reconciliation Volume Allocation Run as appropriate in respect of the last Settlement Day in each Financial Year issue a further Demand and FDSC and Unmetered Supply Volume reconciliation statement (the “Final Demand Reconciliation Statement”) in respect of Demand and FDSC and Unmetered Supply Volume related Transmission Network Use of System Charges payable in respect of each month of that Financial Year showing:-
any change in the Demand and FDSC and Unmetered Supply Volume related Transmission Network Use of System Charges from those specified in the Initial Demand Reconciliation Statement provided in accordance with Paragraph 3.13.4;
whether the change represents a reconciliation payment owing by The Company to a User or by a User to The Company;
the amount of interest determined in accordance with Paragraph 3.13.6 above; and
the information from which the amounts in (i) above are derived and the manner of their calculation.
Together with the Final Demand Reconciliation Statement The Company shall issue a credit note in relation to any sum shown in the Final Demand Reconciliation Statement to be due to the User or an invoice in respect of sums due to The Company and in each case interest thereon calculated pursuant to Paragraph 3.13.6.
Payment of any invoice issued pursuant to Paragraph 3.13.7(b) above or the application of any credit note issued pursuant to that paragraph against any liability of the User to The Company for Demand and FDSC and Unmetered Supply Volume related Transmission Network Use of System Charges will be in full and final settlement of all Demand and FDSC and Unmetered Supply Volume related Transmission Network Use of System Charges for the Financial Year to which the invoice or credit note relates provided that nothing in this Paragraph 3.13.8(c) shall affect the rights of the parties under the provisions of Paragraph 7.3.5.
The right to submit Generation Reconciliation Statements, Initial Demand Reconciliation Statements and Final Demand Reconciliation Statements and the consequential invoices and/or credit notes shall survive the termination of the User's rights under the CUSC and the parties agree that the provisions contained in Paragraphs 3.13 and 3.14 shall continue to bind them after such termination (the version in existence at the date of termination being the applicable version in the case of any amendments).
Pursuant to the ESO Licence and/or the CUSC and/or the Charging Statements and/or the Bilateral Agreements The Company may revise its Transmission Network Use of System Charges or the basis of their calculation. Where The Company proposes a change to the Transmission Network Use of System Charges then it shall notify the User as soon as practicable after the proposal is made to the Authority pursuant to the ESO Licence.
The User acknowledges that due to the timescales associated with the replacement of the Pooling and Settlement Agreement with the Balancing and Settlement Code, The Company was prevented from providing the User with notice pursuant to Clause 2.1 of Part 1 of Appendix E (as in force on the day prior to the NETA Go-live Date) of the basis of calculation of Transmission Network Use of System Charges from the NETA Go-live Date until the end of the Financial Year in which the NETA Go-live Date occurred. However, the User further acknowledges that The Company consulted with the User prior to the NETA Go- live Date on Transmission Network Use of System Charges to apply from the NETA Go-live Date until the end of the Financial Year in which the NETA Go-live Date occurred. The User hereby agrees to pay Transmission Network Use of System Charges in respect of the Financial Year in which the NETA Go-live Date occurred in accordance with the principles notified by The Company prior to the NETA Go-live Date.
Subject to paragraph 3.14.4 below, The Company shall give the User not less than two months prior written notice of any revised Transmission Network Use of System Charges, which notice shall specify the date upon which such revisions become effective (which may be at any time) and will make reference to the new tariffs set out in the relevant Charging Statements. The User shall pay any such revised charges from the effective date.
Where in accordance with the ESO Licence, the Authority determines a shorter period than 2 months for the implementation of revised charges, the notice period will be determined by the Authority. The notice will specify when the new charges are effective and the User shall pay any such revised charges from the effective date.
Where a User’s connection to the National Electricity Transmission System involves the connection of an Offshore Transmission System to a Distribution System, The Company shall notify the User as soon as practicable in the event that The Company receives notice from the ET Interface Operator of a change in the charges to The Company which would require a change in the ET Use of System Charges. The Company shall advise the User of the resultant revision to the ET Use of System Charges and the date upon which such revision shall become effective.
Each Financial Year The Company shall prepare and update its forecast of Transmsission Network Use of System Charges in accordance with the TNUos Tariff Forecast Timetable.
Under the terms of the CUSC each User except in the case of Distribution Interconnector Owners is liable to pay Balancing Services Use of System Charges. The basis upon which Balancing Services Use of System Charges are levied and the calculation methodology and rules which will be used to quantify those charges are set out in the Statement of the Use of System Charging Methodology.
Balancing Services Use of System Charges Notwithstanding the provisions of Paragraphs 6.6.1 and 6.6.2 the following provisions shall apply to the payment of the Balancing Services Use of System Charges.
The Company shall not later than 17.00 hours on the relevant Notification Date (and if this is not practicable as soon as possible thereafter as The Company, acting reasonably, considers is practicable) despatch an advice notice to the User in respect of the Settlement Day in relation to which the Balancing Services Use of System Charges are due on the relevant Payment Date.
The information on the advice notice in respect of each Settlement Day shall include the name of the User and the total amount payable to The Company in respect of Balancing Services Use of System Charges and in all cases together with any Value Added Tax thereon during each Settlement Day.
The Company shall, within a reasonable time thereafter provide a valid Value Added Tax invoice in respect of Balancing Services Use of System Charges identified on the advice note.
The User shall pay the Balancing Services Use of System Charges specified in the advice notice together with the Value Added Tax thereon to The Company no later than 12.30 hours on the Payment Date specified on the advice note in respect of such Settlement Date as if they were payments made in the manner specified in Paragraph 6.6.3.
Balancing Services Use of System Charges Information
The Company shall use reasonable endeavours to publish no later than the last Business Day in each month the Balancing Services Use of System (BSUoS) charges Forecast Information
The Balancing Services Use of System Charges Forecast Information will include:
estimated BSUoS volumes
estimated external BSUoS costs
estimated internal BSUoS costs
estimated average BSUoS charges in £/MWh
incentive scheme performance where applicable The Company will engage with industry participants to discuss assumptions and provide information to explain and support any changes to previously published Balancing Services Use of System Charges Forecast Information.
Each update shall be based on the latest information for items which The Company reasonably expects to make a material impact to the expected Balancing Services Use of System Charges.
As soon as reasonably practicable after receipt by The Company of the Final Reconciliation Volume Allocation Run in respect of a Settlement Day The Company shall prepare and submit to each User a statement (which may form part of an invoice or other document) calculated in accordance with the data specified in the Statement of the Use of System Charging Methodology in respect of that Settlement Day (“Balancing Services Use of System Reconciliation Statement”), showing the new value (if any) of data (as specified in the Statement of the Use of System Charging Methodology in force on that Settlement Day) attributable to the User in respect of such Settlement Day and the amount of Balancing Services Use of System Charges payable by the User on the basis of the new value (the "Reconciled Charge").
In the event that:
the Reconciled Charge exceeds the Balancing Services Use of System Charges paid by the User in respect of that Settlement Day (“Initial Charge”) The Company shall at its option either:
send to the User as soon as reasonably practicable after issue of the Balancing Services Use of System Reconciliation Statement an invoice for the amount by which the Reconciled Charge exceeds the Initial Charge and interest thereon calculated in accordance with the provisions set out in Paragraph 3.17.3; or
include such amount in another invoice in respect of Balancing Services Use of System Charges to the User.
the Reconciled Charge is less than the Initial Charge The Company shall at its option either:-
send to the User as soon as reasonably practicable after issue of the Balancing Services Use of System Reconciliation Statement a credit note for the amount by which the Initial Charge exceeds the Reconciled Charge and interest thereon calculated in accordance with the provisions set out in Paragraph 3.17.3; or
include such amount as a credit in an invoice in respect of Balancing Services Use of System Charges from The Company to the User.
Interest payable in respect of each reconciliation payment shall accrue from and including the relevant Use of System Payment Date up to but excluding the date upon which the amounts specified in the Balancing Services Use of System Reconciliation Statement are paid, and shall be at a rate equal to the Base Rate for the time being and from time to time. Interest shall accrue from day to day.
If The Company receives written notice from any User or from the relevant BSC Agent that an error has occurred in any data forming part of or used within the Initial Volume Allocation Run which affects the costs to The Company of offers and bids in the Balancing Mechanism accepted by The Company in respect of any Settlement Day, and that error has been ratified in accordance with the procedures for ratification set out in the Balancing and Settlement Code it shall use its reasonable endeavours to, as soon as reasonably practicable after receipt of such notice, issue a dispute reconciliation statement (“Dispute Statement”) to the User in respect of that Settlement Day.
Any Dispute Statement issued pursuant to Paragraph 3.17.4 above shall show the amount of Balancing Services Use of System Charges payable by the User on the basis of the ratified data.
In the event that the amount shown in any Dispute Statement exceeds the aggregate amount paid by the User in respect of the Settlement Day to which the Dispute Statement relates under any invoices issued pursuant to Paragraph 3.16.2 and Paragraph 3.17.2 above (after taking into account any credit notes issued) The Company shall submit to the User a further invoice for such excess and interest thereon calculated in accordance with Paragraph 3.17.3;
In the event that the amount shown in any Dispute Statement is less than the aggregate amount paid by the User in respect of the Settlement Day to which the Dispute Statement relates under any invoices issued pursuant to Paragraph 3.16.2 and Paragraph 3.17.2 above (after taking into account any credit notes issued) The Company shall submit to the User a credit note for the amount by which the amount paid exceeds the amount shown in the Dispute Statement together with interest thereon calculated in accordance with Paragraph 3.17.3.
If at any time prior to receipt by The Company of the Final Reconciliation Volume Allocation Run in respect of a Settlement Day The Company receives written notice from any User or the relevant BSC Agent of an error occurring in any data forming part of or used within the Initial Volume Allocation Run or the Reconciliation Volume Allocation Run which in either case affects the data (as specified in the Statement of the Use of System Charging Methodology) used in the calculation of Balancing Services Use of System Charges for that Settlement Day, which error:-
is not taken into account in the Final Reconciliation Volume Allocation Run; and
has been ratified in accordance with the procedures for ratification set out in the Balancing and Settlement Code, then The Company shall use its reasonable endeavours to prepare the Balancing Services Use of System Reconciliation Statement on the basis of the ratified data.
The right to submit Balancing Services Use of System Reconciliation Statements and Dispute Statements and the consequential invoices and/or credit notes shall survive the termination of the User's rights under the CUSC and the parties agree that the provisions of this Part II shall remain in full force and effect and shall continue to bind them after such termination (the version in existence as at the date of termination being the applicable version, in the case of any amendments).
The Company and each User hereby agree and acknowledge that the provisions of Part IIC will apply to all Balancing Services Use of System Charges payable in respect of any Settlement Day on or after the NETA Go-live Date. The provisions of Paragraphs 1.1 to 1.6 inclusive of Part 2 of the form of Appendix E in force on the day prior to the NETA Go-live Date shall continue to apply mutatis mutandis to all Transmission Services Use of System Charges payable in respect of any Settlement Day up to the NETA Go-live Date.
RECONCILIATION PAYMENTS Each User, or as the case may be, The Company, shall pay the amounts set out in any invoice or credit note issued pursuant to Paragraphs 3.16.2 or 3.15.6 respectively above, either in accordance with the applicable requirements for payment of other sums due under that invoice in the case of sums shown in an invoice also dealing with other payments, or in other cases within 5 Business Days of the date of the Balancing Services Use of System Reconciliation Statement or Dispute Statement as appropriate.
Subject to Paragraph 3.21.2 below, The Company shall give the User not less than 2 months prior written notice of any revision to the Statement of the Use of System Charging Methodology which will affect the application and calculation of the Balancing Services Use of System Charges, which notice shall specify the date upon which such revisions become effective (which may be at any time). The User shall pay any such revised charges with effect from the date specified in such notice.
Where in accordance with the ESO Licence, the Authority determines a shorter period than two months for the implementation of a revision to the charges which will affect the application and calculation of the Balancing Services Use of System Charge, the notice period will be determined by the Authority. The notice will specify when the revision is effective and the User shall pay any such revised charges with effect from the date specified in such notice.
Each User required to pay Use of System Charges shall provide Security Cover for Balancing Services Use of System Charges and Transmission Network Use of System Demand Charges from time to time in accordance with this Part III.
Each such User shall not later than the date of its accession to the CUSC Framework Agreement deliver to The Company evidence reasonably satisfactory:-
to establish the User’s Allowed Credit; and
if required, that it has provided and is not in default under the Security Cover referred to in Paragraph 3.22.3 below.
The User shall be required to provide Security Cover where its Security Requirement exceeds its User’s Allowed Credit. If such User is required to provide Security Cover it shall, not later than the date of:-
the date of its becoming a party to the CUSC Framework Agreement; or
two Business Days after The Company notifies the User in writing that the Security Cover required exceeds the Security Amount provided; or
where and to the extent that the amount of Security Cover required exceeds the Security Amount provided as a result of a User’s revised forecast given in accordance with Paragraph 3.10 within one month of such revised forecast being provided to The Company:-
deliver to The Company a Qualifying Guarantee in such amount as shall be notified by The Company to the User in accordance with Paragraph 3.23; and/or
deliver to The Company a Letter of Credit (available for an initial period of not less than 6 months) in such amount as shall be notified by The Company to the User in accordance with Paragraph 3.23; and/or
deliver to The Company cash for credit to the Escrow Account in such amount as shall be notified by The Company in accordance with Paragraph 3.23; and/or
deliver to The Company a Bilateral Insurance Policy in such an amount as shall be notified by The Company to the User in accordance with Paragraph 3.23; and/or
deliver to The Company an Insurance Performance Bond in such an amount as shall be notified by The Company to the User in accordance with Paragraph 3.23; and/or
delivery to The Company an Independent Security Arrangement in such an amount as shall be notified by The Company to the User in accordance with Paragraph 3.23.
The provisions of this Part III shall be in addition to any other requirements to provide security in respect of any other sums due under the terms of the CUSC or any Bilateral Agreement or Construction Agreement.
Maintenance of Security Cover Where a User is required to provide Security Cover in accordance with the terms of this Paragraph 3.22 it shall at all times thereafter maintain a Security Amount equal to or more than the Security Cover applicable to it. Immediately upon any reduction occurring in the Security Amount provided by the User or any Letter of Credit or Qualifying Guarantee or Bilateral Insurance Policy or Insurance Performance Bond or Independent Security Arrangement being for any reason drawn down or demanded respectively, the User will procure that new Letters of Credit or Qualifying Guarantees or Bilateral Insurance Policy or Insurance Performance Bond or Independent Security Arrangement are issued or existing Letters of Credit or Qualifying Guarantees or Bilateral Insurance Policy or Insurance Performance Bond or Independent Security Arrangement are reinstated (to the satisfaction of The Company) to their full value or cash is placed to the credit of the Escrow Account in an amount required to restore the Security Amount to an amount at least equal to the Security Cover applicable to the User, and in such proportions of Letters of Credit, Qualifying Guarantees or Bilateral Insurance Policy or Insurance Performance Bond or Independent Security Arrangement and/or cash as the User may determine. Not later than 10 Business Days before any outstanding Letter of Credit and/or Qualifying Guarantee or Bilateral Insurance Policy or Insurance Performance Bond or Independent Security Arrangement is due to expire, the User shall procure to the satisfaction of The Company that its required Security Amount will be available for a further period of not less than 6 months which may be done in one of the following ways:-
subject to the issuing bank continuing to have an Approved Credit Rating for an amount at least equal to the required Security Amount applicable to it (less the balance of deposits on the Escrow Account in respect of the Security Amount) provide The Company with confirmation from the issuing bank that the validity of the Letter of Credit has been extended for a period of not less than 6 months on the same terms and otherwise for such amount as is required by this Part III; or
provide The Company with a new Letter of Credit issued by an issuing bank with an Approved Credit Rating for an amount at least equal to the required Security Amount applicable to it (less the balance of deposits on the Escrow Account in respect of the Secruity Amount) which Letter of Credit shall be available for a period of not less than 6 months; or
subject to the entity issuing the Qualifying Guarantee continuing to have an Approved Credit Rating or Credit Assessment Score for an amount at least equal to the required Security Amount applicable to it (less the balance of deposits on the Escrow Account in respect of the Security Amount) provide The Company with confirmation from the issuing entity that the validity of the Qualifying Guarantee has been extended for a period of not less than 6 months on the same terms and otherwise for such amount as is required by this Part III; or
provide The Company with a new Qualifying Guarantee for an amount at least equal to the required Security Amount applicable to it (less the its balance of deposits on the Escrow Account in respect of the Security Amount) which Qualifying Guarantee shall be available for a period of not less than 6 months; or
procure such transfer to The Company for credit to the Escrow Account of an amount as shall ensure that the credit balance applicable to the User and standing to the credit of the Escrow Account shall be at least equal to the required Security Amount; or
subject to the entity issuing the Bilateral Insurance Policy or Insurance Performance Bond or Independent Security Arrangement continuing to meet the Requirements provide The Company with confirmation from the issuing entity that the validity of the Bilateral Insurance Policy or Insurance Performance Bond or Independent Security Arrangement has been extended for a period of not less than 6 months on the same terms and otherwise for such amount as is required by this Part III; or
provide The Company with a new Bilateral Insurance Policy or Insurance Performance Bond or Independent Security Arrangement for an amount at least equal to the required Security Amount applicable to it (less the balance of deposits on the Escrow Account in respect of the Secruity Amount) which Bilateral Insurance Policy or Insurance Performance Bond or Independent Security Arrangement shall be available for a period of not less than 6 months.
Failure to supply or maintain Security Cover If the User fails at any time to provide or maintain Security Cover to the satisfaction of The Company in accordance with the provisions of this Part III, The Company may at any time while such default continues, and if at such time any Letter of Credit and/or Qualifying Guarantee and/or Bilateral Insurance Policy and/or Insurance Performance Bond and/or Independent Security Arrangement forming part of the Security Amount is due to expire within 9 Business Days immediately, and without notice to the User, demand payment of the entire amount of any outstanding Letter of Credit and/or Qualifying Guarantee and/or Bilateral Insurance Policy and/or Insurance Performance Bond and/or Independent Security Arrangement and shall credit the proceeds of the Letter of Credit and/or Qualifying Guarantee and/or Bilateral Insurance Policy and/or Insurance Performance Bond and/or Independent Security Arrangement to the Escrow Account.
Substitute Letter of Credit or Qualifying Guarantee
If the bank issuing the User’s Letter of Credit ceases to have the credit rating set out in the definition of Letter of Credit in this CUSC such User shall forthwith procure the issue of a substitute Letter of Credit by a bank that has such a credit rating or a Qualifying Guarantee or a Bilateral Insurance Policy or an Insurance Performance Bond or an Independent Security Arrangement or transfer to The Company cash to be credited to the Escrow Account.
If the entity providing the User’s Qualifying Guarantee ceases to have an Approved Credit Rating or Credit Assessment Score for an amount at least equal to the required Security Amount (less the balance of the User’s deposits on the Escrow Account in respect of the Security Amount) the User shall forthwith procure a replacement Qualifying Guarantee from an entity with such a credit rating or a Letter of Credit or a Bilateral Insurance Policy or an Insurance Performance Bond or an Independent Security Arrangement or transfer to The Company cash to be credited to the Escrow Account.
If the entity providing the User’s Bilateral Insurance Policy or Insurance Performance Bond or Independent Security Arrangement ceases to meet the Requirements the User shall forthwith procure a replacement of the same or a Bilateral Insurance Policy, Insurance Performance Bond, Independent Security Arrangement, Letter of Credit, Qualifying Guarantee or transfer to The Company cash to be credited to the Escrow Account in respect of the Security Amount.
Determination of Security Cover The amount of Security Cover which the User shall be required to maintain shall be determined from time to time by The Company as the User’s Security Requirement less the User’s Allowed Credit.
Determination of Security Requirement The Security Requirement for each User shall be determined as:-
the Balancing Services Use of System Charges provided for in the CUSC, where the User is a Supplier, over a 32 day period or such period as The Company acting reasonably shall specify to the User in writing from time to time taking into account the requirements for Security Cover contained in the Balancing and Settlement Code and where The Company proposes to change such period The Company shall consult with Users; and
the Balancing Services Use of System Charges provided for in the CUSC, where the User is a Generator, over a 29 day period or such period as The Company acting reasonably shall specify to the User in writing from time to time taking into account the requirements for Security Cover contained in the Balancing and Settlement Code and where The Company proposes to change such period The Company shall consult with Users; and
in relation to Transmission Network Use of System Demand Charges calculated in the following manner for each Security Period:-
in the Financial Year in which such charges first become due the greater of zero and the User’s Base Value at Risk; and
in the case of subsequent Financial Years the greater of zero and the sum of (i) the User’s Base Value at Risk and (ii) the User’s Forecasting Performance Related VAR.
interest on the amounts referred to in (a), (b) and (c) above calculated in accordance with the provisions of this CUSC.
any applicable Value Added Tax that would be due on the amounts referred to in this Paragraph 3.23.2
Calculation of HH Base Value at Risk For each Security Period, the sum equal to the HH Base Percentage of the User’s Indicative Annual HH TNUoS Charge calculated on the basis of the latest Demand Forecast received by The Company.
Calculation of NHH Base Value at Risk For each Security Period, the sum equal to the NHH Base Percentage of the User’s Indicative Annual NHH TNUoS Charge calculated on the basis of the latest Demand Forecast received by The Company. 3.23.4a Calculation of FDSC Base Value at Risk For each Security Period, the sum equal to the FDSC Base Percentage of the User’s Indicative Annual FDSC TNUoS Charge calculated by The Company on the basis of the latest FDSC Forecast produced by The Company. 3.23.4b Calculation of UMS Base Value at Risk For each Security Period, the sum equal to the UMS Base Percentage of the User’s Indicative Annual UMS TNUoS Charge calculated by The Company on the basis of the latest Unmetered Supply Volume Forecast produced by The Company.
Notification of Deemed HH Forecasting Performance Following the issue of the Initial Demand Reconciliation Statement in respect of the previous Financial Year, The Company shall notify the User, of the Deemed HH Forecasting Performance to be used in the calculation of the User’s HH Performance Related Var. Such notice shall be given at least two months prior to the first of the Security Periods to which it relates.
Notification of Deemed NHH Forecasting Performance Following the issue of the Initial Demand Reconciliation Statement in respect of the previous Financial Year, The Company shall notify the User, of the Deemed NHH Forecasting Performance to be used in the calculation of the User’s NHH Performance Related Var. Such notice shall be given at least two months prior to the first of the Security Periods to which it relates.
Revision of Deemed HH Forecasting Performance If the User has experienced a significant increase in the amount of Demand taken by its Customers during the last five months of the previous Financial Year and believes that this has had a significant effect on their Deemed HH Forecasting Performance, then no later than one month from the date of the notification given to the User under paragraph 3.23.5, the User may request that The Company revises the Deemed HH Forecasting Performance. Upon raising such a request, the User must provide information to The Company relating to the size of the reported Demand increase and the Reported Period(s) of Increase. Where for any Reported Period of Increase the resulting increase in Demand equates to a level that is in excess of one percent of the Actual Amount of HH Charges in respect of the previous Financial Year, The Company shall, within one month of receiving such a request, recalculate the Deemed HH Forecasting Performance on the basis set out in Appendix 2 Paragraph 4. A User shall not be entitled to raise more than one request by reference to any period or part period covered in another Reported Period of Increase in respect of which a request has been raised under this Paragraph.
Revision of Deemed NHH Forecasting Performance If the User has experienced a significant increase in the amount of Demand taken by its Customers during the last five months of the previous Financial Year and believes that this has had a significant effect on their Deemed NHH Forecasting Performance, then no later than one month from the date of the notification given to the User under paragraph 3.23.6, the User may request that The Company revises the Deemed NHH Forecasting Performance. Upon raising such a request, the User must provide information to The Company relating to the size of the reported Demand increase and the Reported Period(s) of Increase. Where for any Reported Period of Increase the resulting increase in Demand equates to a level that is in excess of one percent of the Actual Amount of NHH Charges in respect of the previous Financial Year, The Company shall within one month of receiving such a request, recalculate the Deemed NHH Forecasting Performance on the basis set out in Appendix 2 Paragraph 7. A User shall not be entitled to raise more than one request by reference to any period or part period covered in another Reported Period of Increase in respect of which a request has been raised under this Paragraph.
Review of Security Cover The Company shall keep under review the Security Cover relating to the User and shall promptly advise the User whenever the Security Amount maintained by the User is more or less than the amount required to be maintained pursuant to this Paragraph 3.23.
Decrease of Security Cover If The Company reasonably determines that the User’s required Security Cover has decreased, it shall so notify the User. The Company shall consent to an appropriate reduction in the available amount of any outstanding Qualifying Guarantee or Letter of Credit or Bilateral Insurance Policy or Insurance Performance Bond or Independent Security Arrangement and/or shall repay to the User such part of the deposit held in the Escrow Account in respect of the Security Cover for the account of the User (together with all accrued interest on the part to be repaid) sufficient to reduce the User’s Security Amount to the level of Security Cover applicable to it within 5 Business Days of the User’s consent.
Notification in respect of Security Cover The Company shall notify each User promptly if:-
that User fails to provide, maintain, extend or renew a Qualifying Guarantee or a Letter of Credit or a Bilateral Insurance Policy or an Insurance Performance Bond or an Independent Security Arrangement which it is required to provide, maintain, extend or renew pursuant to Paragraphs 3.22 or 3.23 inclusive;
The Company shall make a demand under any such Qualifying Guarantee or a call under a Letter of Credit or a Bilateral Insurance Policy or an Insurance Performance Bond or an Independent Security Arrangement; or
The Company becomes aware that that User:
shall cease to have an Approved Credit Rating or shall cease to have an Approved Credit Rating for an amount at least equal to the User’s Security Requirement, or
shall be placed on a credit watch by the relevant credit rating agency (or becomes subject to an equivalent procedure) which in any case casts doubt on the User retaining an Approved Credit Rating or an Approved Credit Rating for an amount at least equal to the User’s Security Requirement or maintaining the Credit Assessment Score given by the User’s Independent Credit Assessment, or
shall be in default under the additional or alternative security required to be provided pursuant to this Part III; or
The Company becomes aware that any bank that has issued a Letter of Credit in relation to that User which has not expired shall cease to have the credit rating required by this Section; or
The Company becomes aware that any entity providing a Qualifying Guarantee or a Bilateral Insurance Policy or an Insurance Performance Bond or an Independent Security Arrangement in relation to that User which has not expired shall cease to meet the Requirements in the case of a Bilateral Insurance Policy or an Insurance Performance Bond or an Independent Security Arrangement or in the case of a Qualifying Guarantee cease to have an Approved Credit Rating or Credit Assessment Score for an amount at least equal to the required Security Amount (less its balance of deposits on the Escrow Account in respect of the Security Amount); or
The Company becomes aware that the User’s Security Requirement exceeds 85% of the User’s Allowed Credit. Provided always that the failure by The Company to notify the User pursuant to Paragraphs 3.23.9, 3.23.10 or 3.23.11 shall not relieve the User of its obligations under and in accordance with the terms of this Section 3 and the Charging Statements.
Release from Security Cover Obligations Upon a User becoming a Dormant CUSC Party or ceasing to be a CUSC Party and provided that all amounts owed by the User in respect of Balancing Services Use of System Charges and Transmission Network Use of System Demand Charges have been duly and finally paid and that it is not otherwise in default in any respect of any Balancing Services Use of System Charges or Transmission Network Use of System Demand Charges (including in each case interest) payable under the CUSC, the User shall be released from the obligation to maintain Security Cover and The Company shall consent to the revocation of any outstanding Qualifying Guarantee or Letter of Credit or a Bilateral Insurance Policy or an Insurance Performance Bond or an Independent Security Arrangement and shall repay to the User the balance of deposits standing to the credit of the User on the Escrow Account in respect of the Security Amount (including interest accruing thereto, whether held in the Escrow Account or any associated bank account in the name of The Company) at that date.
PAYMENT DEFAULT If, by 12.30 hours on any Use of System Payment Date, The Company has been notified by a User or it otherwise has reason to believe that that User will not have remitted to it by close of banking business on the Use of System Payment Date all or any part (“the amount in default”) of any amount which has been notified by The Company to the User as being payable by the User by way of either the Balancing Services Use of System Charges and/or Transmission Network Use of System Demand Charges on the relevant Use of System Payment Date, then The Company shall be entitled to act in accordance with the following provisions (or whichever of them shall apply) in the order in which they appear until The Company is satisfied that the User has discharged its obligations in respect of the Balancing Services Use of System Charges and/or Transmission Network Use of System Demand Charges (as appropriate) under the CUSC which are payable in respect of the relevant Settlement Day (in the case of Balancing Services Use of System Charges) or Financial Year (in the case of Transmission Network Use of System Demand Charges):-
The Company may to the extent that the User is entitled to receive payment from The Company pursuant to the CUSC (unless it reasonably believes that such set-off shall be unlawful) set off the amount of such entitlement against the amount in default;
The Company shall be entitled to set off the amount of funds then standing to the credit of the Escrow Account against Balancing Services Use of System Charges and/or Transmission Network Use of System Demand Charges (as appropriate) unpaid by the User and for that purpose The Company shall be entitled to transfer any such amount from the Escrow Account to any other account of The Company at its absolute discretion and shall notify the User accordingly;
The Company may demand payment under any outstanding Letter of Credit supplied by the User in a sum not exceeding the available amount of all such Letters of Credit;
The Company may demand payment under any outstanding Qualifying Guarantee provided for the benefit of the User pursuant to Paragraph 3.22.3(b);
The Company may demand payment under any outstanding Bilateral Insurance Policy provided for the benefit of the User;
The Company may demand payment under any outstanding Insurance Performance Bond provided for the benefit of the User;
The Company may demand payment under any outstanding Independent Security Arrangement provided for the benefit of the User.
UTILISATION OF FUNDS In addition to the provisions of Paragraph 3.24 above if The Company serves a notice of default under the terms of Paragraph 5.5 or a notice of termination under Paragraph 5.7 then The Company shall be entitled to demand payment of any of the Balancing Services Use of System Charges and/or Transmission Network Use of System Demand Charges which are outstanding from the relevant User whether or not the Use of System Payment Date in respect of them shall have passed and:-
make demand under any outstanding Qualifying Guarantee or a call under any outstanding Letter of Credit, Bilateral Insurance Policy, Insurance Performance Bond or Independent Security Arrangement supplied by the User; and
to set off the funds in the Escrow Account against Balancing Services Use of System Charges and/or Transmission Network Use of System Demand Charges unpaid by the User and for that purpose The Company shall be entitled to transfer any such amount from the Escrow Account to any other account of The Company as it shall in its sole discretion think fit. 3.25A For the avoidance of doubt, the User’s cash deposit in the Escrow Account shall remain the sole property and entitlement of the User until such time when (and to such extent as) the Company exercises its right of set off against the User’s cash deposit in accordance with the terms of the CUSC, and the User shall have no right to have the cash deposit returned to it for so long as it is under any prospective or contingent liability to the Company.
USER’S RIGHT TO WITHDRAW FUNDS If a User is not in default in respect of any amount owed to The Company in respect of the Balancing Services Use of System Charges or Transmission Network Use of System Charges under the terms of the CUSC and any Bilateral Agreement to which the User is a party:-
The Company shall transfer to the User quarterly interest accruing in respect of deposits of principal sums from the User in the Escrow Account (whether held in the Escrow Account or any associated bank account in the name of The Company); and
The Company shall transfer to such User within a reasonable time after such User’s written request therefor any amount of cash provided by the User by way of Security Cover which exceeds the amount which such User is required to provide by way of security in accordance with this Part III.
Each User shall notify The Company promptly if:-
it gains an Approved Credit Rating; or
it ceases to have an Approved Credit Rating; or
where the User holds an Approved Credit Rating, its specific investment grading changes; or
it has reason to believe that its Credit Assessment Score is likely to have changed since the last Independent Credit Assessment.
The User’s Allowed Credit extended by The Company at any time to User with an Approved Credit Rating shall be calculated in accordance with Paragraph 1 of Appendix 1 of this Section 3 subject to a maximum value of the Unsecured Credit Cover.
The User’s Allowed Credit extended by The Company at any time to each User without an Approved Credit Rating shall be at the choice of the User the Payment Record Sum or the Credit Assessment Sum.
Unless the User has notified The Company that it wishes its User’s Allowed Credit to be to be based on the Credit Assessment Sum then, subject to Paragraph 3.27.5, for each successive month in which the User pays its Use of System Charges by the Use of System Payment Date then the User’s Allowed Credit extended to such User at any time shall be calculated in accordance with Paragraph 2 of Appendix 1 of this Section 3.
Where a User fails to pay its Use of System Charges within 2 Business Days of the Use of System Payment Date its Payment Record Sum shall be reduced by 50% on the first such occasion within a twelve month period and shall be reduced to zero on the second occasion in such twelve month period. Upon any such failure to pay, the User’s Allowed Credit (as adjusted following such failure in accordance with this clause) shall be calculated for successive months in accordance with Paragraph 3.27.4.
Where a User has notified The Company that it wishes its User’s Allowed Credit to be based on its Credit Assessment Sum, the Credit Assessment Sum extended to a User at any time shall be calculated be reference to the Credit Assessment Score given by the Independent Credit Assessment in accordance with Paragraph 3 of Appendix 1 of this Section 3.
Where a User has notified The Company that its wishes its User’s Allowed Credit to be based on the Credit Assessment Sum then the User will obtain an Independent Credit Assessment of that User. The first such Independent Credit Assessment will be at The Company’s cost.
Where a User’s Allowed Credit is based on the Credit Assessment Sum then where The Company has reason to believe that the Independent Credit Assessment last obtained is likely to have changed then The Company shall be entitled to request the User to obtain a further independent Credit Assessment. Such Independent Credit Assessment shall be at The Company’s cost.
The User may obtain an Independent Credit Assessment at The Company’s cost provided that The Company has not paid for an earlier Independent Credit Assessment for that User within the previous 12 months. The User may obtain further Independent Credit Assessments within such a 12 month period at the User’s cost.
Recognising the changes to the Security Cover and Security Requirements introduced by the Security Amendment and the consequences for The Company and Users then notwithstanding the provisions of CUSC Section 3 Part III the following transitional provisions shall apply:
the obligation for Users whose Security Requirement will as a result of the Security Amendment increase at the Security Amendment Implementation Date shall be to provide the difference between the Existing Security Cover and the Security Cover in full by no later than the End Date and by increasing the Existing Security Cover each month by equal monthly amounts of the difference between the existing Security Cover and the Security Cover; and
where a User’s Security Requirement at the Security Amendment Implementation Date is less than the Existing Security Cover held for that User then The Company shall release the existing Security Cover by the appropriate amount as soon as practicable and in any event within one calendar month of the Security Amendment Implementation Date.
Recognising the changes to the Security Cover and Security Requirements introduced by the Value At Risk Amendment and the consequences for The Company and Users then notwithstanding the provisions of CUSC Section 3 Part III the following transitional provisions shall apply:
Until the Initial Demand Reconciliation Statement has been issued for the Financial Year ending at least six months following the Value At Risk Amendment Implementation Date, and The Company has calculated the Forecasting Performance Related VAR by reference to this, each User’s Forecasting Performance Related VAR shall be substituted by such percentage of User’s Transmission Network Use of System Demand Charges as reflects the percentage difference between the Actual Amount and the Notional Amount of the User’s Transmission Network Use of System Demand Charges for the previous Financial Year, provided that where the Notional Amount exceeds the Actual Amount, the percentage shall be zero;
the obligation for Users whose Security Requirement will increase at the Value At Risk Amendment Implementation Date as a result of the Value At Risk Amendment shall be to provide the difference between the Pre-Value At Risk Amendment Security Cover and the Security Cover in full by no later than the Value At Risk Amendment Implementation End Date and by increasing the Pre-Value At Risk Amendment Security Cover each month by equal monthly amounts of the difference between the Pre-Value At Risk Amendment Security Cover and the Security Cover; and
where a User’s Security Requirement at the Value At Risk Amendment Implementation Date is less than the Pre-Value At Risk Amendment Security Cover held for that User then The Company shall release the Pre-Value At Risk Amendment Security Cover by the appropriate amount as soon as practicable and in any event within one calendar month of the Value At Risk Amendment Implementation Date.
Where the User meets the Approved Credit Rating that User’s Allowed Credit at any given time shall be calculated as a percentage of Unsecured Credit Cover by reference to the specific investment grade within the User’s Approved Credit Rating as follows:
| Approved Long Term Credit Rating | User’s Allowed Credit as % of Unsecured Credit Cover | ||
|---|---|---|---|
| Standard & Poor’s | Moody’s | Fitch | |
| AAA AA+ AA AA- | Aaa Aa1 Aa2 Aa3 | AAA AA+ AA AA- | 100 |
| A+ A A- | A1 A2 A3 | A+ A A- | 40 |
| BBB+ | Baa1 | BBB+ | 20 |
| BBB | Baa2 | BBB | 19 |
| BBB- | Baa3 | BBB- | 18 |
| BB+ | Ba1 | BB+ | 17 |
| BB | Ba2 | BB | 16 |
| BB- | Ba3 | BB- | 15 |
Where based on the Payment Record Sum, a User’s Allowed Credit at any time shall be calculated on the basis of 0.4% per 12 month period (escalating on an evenly graduated basis each month) of the Unsecured Credit Cover, subject to a maximum of 2% after 60 months of successive payment by the Use of System Payment Date.
Where based on the Credit Assessment Sum, a User’s Allowed Credit at any given time shall be calculated as a percentage of the Unsecured Credit Cover by reference to the Credit Assessment Score as follows: APPENDIX 2 Base Value At Risk
| Credit Assessment Score | User’s Allowed Credit as % of Unsecured Credit Cover |
|---|---|
| 10 | 20 |
| 9 | 19 |
| 8 | 18 |
| 7 | 17 |
| 6 | 16 |
| 5 | 15 |
| 4 | 13.33 |
| 3 | 10 |
| 2 | 6.67 |
| 1 | 3.33 |
| 0 | 0 |
For each Security Period, the HH Base Percentage used in determining the User’s HH Base Value at Risk shall be determined by reference to the following:
| Security Period Start Date (inclusive) | Security Period End Date (inclusive) | HH Base Percentage |
|---|---|---|
| 1st April | 30th June | -8.4% |
| 1st July | 30th September | -33.4% |
| 1st October | 31st December | -49.1% |
| 1st January | 31st March | 7.0% |
For each Security Period, the NHH Base Percentage used in determining the User’s NHH Base Value at Risk shall be determined by reference to the following: 2A. For each Security Period, the FDSC Base Percentage used in determining the User’s FDSC Base Value at Risk shall be determined by reference to the following: 2B. For each Security Period, the UMS Base Percentage used in determining the User’s UMS Base Value at Risk shall be determined by reference to the following: 1st January 31st March 3.7% Deemed HH Forecasting Performance and Revision
| Security Period Start Date (inclusive) | Security Period End Date (inclusive) | (a) NHH Base Percentage |
|---|---|---|
| 1st April | 30th June | (b) 4.3% |
| 1st July | 30th September | (c) -1.5% |
| 1st October | 31st December | (d) -2.8% |
| 1st January | 31st March | (e) 3.7% |
| Security Period Start Date (inclusive) | Security Period End Date (inclusive) | FDSC Base Percentage |
|---|---|---|
| 1st April | 30th June | 5.0% |
| 1st July | 30th September | 5.0% |
| 1st October | 31st December | 5.0% |
| 1st January | 31st March | 5.0% |
| Security Period Start Date (inclusive) | Security Period End Date (inclusive) | UMS Base Percentage |
|---|---|---|
| 1st April | 30th June | 4.3% |
| 1st July | 30th September | -1.5% |
| 1st October | 31st December | -2.8% |
Deemed HH Forecasting Performance, FPP , shall be calculated HH as set out in the following formula: 5 12 AA −IA FPP = max0, HH HH,m *W −CA HH 1333 m=8 AA HH HH,m HH Where: AA is the Actual Amount of User’s HH Charges for the HH previous Financial Year IA is the Indicative Annual HH TNUoS charge calculated HH,m using the Demand Forecast used to determine Transmission Network Use of System Demand Charges made during month m of the previous Financial Year. W The forecast weighting to be applied for each month, HH,m, m by reference to the following: CA is an allowance for extreme conditions equal to 0.06. HH,
| m | Invoice Month | Forecast weighting, W HH,m |
|---|---|---|
| 8 | November | 33.3 |
| 9 | December | 33.3 |
| 10 | January | 33.3 |
| 11 | February | 66.7 |
| 12 | March | 100 |
4 The revised Deemed HH Forecasting Performance, shall be calculated on the basis of Paragraph 3 above, substituting the Indicative Annual HH TNUoS Charge for each month, m prior to the end of the Reported Period of Increase with the Revised Indicative Annual HH TNUoS charge, RIA HH,m
5 The Revised Indicative Annual HH TNUoS charge, RIA shall be HH,m derived as follows: 𝑅𝐼𝐴 = 𝑚𝑖𝑛[(1 𝐻𝐻,𝑚 𝐷𝑈𝐵 𝐷𝑆𝐵 𝐻𝐻,𝑝 𝐻𝐻,𝑝 +[𝑚𝑎𝑥(−,0)∗ 𝑅𝐷]) 𝐷𝑈𝐴 𝐷𝑆𝐴 𝐻𝐻,𝑝 𝐻𝐻,𝑝 𝐻𝐻,𝑝 ∗ 𝐼𝐴,𝐼𝐴] 𝐻𝐻,𝑚 𝐻𝐻,𝑝 Where: DUA is the average half-hourly metered demand taken by HH,p the User’s Customers during the period 17:00 to 17:30 on the twenty Business Days prior to the Reported Period of Increase, p, that do not fall between the two week period commencing 22nd December. DUB is the average half-hourly metered demand taken by HH,p th
| Month in which Reported Period of Increase commences | Remaining proportion of HH Charges |
|---|---|
| October | 100% |
| November | 100% |
| December | 100% |
| January | 66.7% |
| February | 33.3% |
6 Deemed NHH Forecasting Performance, FPP, shall be calculated NHH as set out in the following formula: 1 12 AA −IA FPP = max0, NHH NHH,m *W −CA NHH 300 m=8 AA NHH NHH,m NHH Where: AA is the Actual Amount of User’s NHH Charges for NHH the previous Financial Year. IA is the Indicative Annual NHH TNUoS charge NHH,m calculated using the Demand Forecast used to determine Transmission Network Use of System Demand Charges made during month m of the previous Financial Year. W The forec
| m | Invoice Month | Forecast weighting, W NHH,m |
|---|---|---|
| 8 | November | 41 |
| 9 | December | 49 |
| 10 | January | 59 |
| 11 | February | 70 |
| 12 | March | 81 |
7 The revised Deemed NHH Forecasting Performance shall be calculated on the basis of Paragraph 6 above, substituting the Indicative Annual NHH TNUoS Charge for each month, m prior to the end of the Reported Period of Increase with the Revised Indicative Annual NHH TNUoS charge, RIA. NHH,m
8 The Revised Indicative Annual NHH TNUoS charge, RIA shall NHH,m be derived as follows: 𝐷𝑈𝐵 𝐷𝑆𝐵 𝑁𝐻𝐻,𝑝 𝑁𝐻𝐻,𝑝 𝑅𝐼𝐴 = 𝑚𝑖𝑛[(1+[𝑚𝑎𝑥(−,0)∗ 𝑅𝐷]) 𝑁𝐻𝐻,𝑚 𝐷𝑈𝐴 𝐷𝑆𝐴 𝑁𝐻𝐻,𝑝 𝑁𝐻𝐻,𝑝 𝑁𝐻𝐻,𝑝 ∗ 𝐼𝐴,𝐼𝐴] 𝑁𝐻𝐻,𝑚 𝑁𝐻𝐻,𝑝 Where: DUA is the average non-half-hourly metered demand NHH,p taken by the User’s Customers during the period 16:00 to 19:00 on the twenty Business Days prior to the Reported Period of Increase, p, that do not fall between the two week period commencing 22nd December. DUB is the average non-half-hourly metered deman
| Month in which Reported Period of Increase commences | Remaining proportion of NHH Charges |
|---|---|
| October | 59% |
| November | 51% |
| December | 41% |
| January | 30% |
| February | 19% |
SECTION 4: BALANCING SERVICES
Application
The provisions of this Paragraph 4.1 shall apply to Users which are Generators in respect of Generating Units, DC Converters and Power Park Modules from which they are required to provide the Mandatory Ancillary Services to The Company in accordance with the Grid Code (for the avoidance of doubt, as determined by any direction in force from time to time and issued by the Authority relieving any such User from the obligation under its Licence to comply with such part or parts of the Grid Code or any Distribution Code or, in the case of The Company, the ESO Licence, as may be specified in such direction).
In respect of Generating Unit(s), DC Converter(s) and Power Park Modules which are required to provide Mandatory Ancillary Services to The Company in accordance with the Grid Code and which are not registered as BM Unit(s), the Mandatory Service Agreement shall detail how the provisions of Section 4 and Schedule 3 of the CUSC which refer to BM Unit(s) shall (notwithstanding such Generating Unit(s), DC Converter(s) and Power Park Module(s) are not registered as BM Unit(s)) apply.
Reactive Power Schedule 3, Part I
The Company and each User shall, as between The Company and that User, comply with the provisions regarding the Obligatory Reactive Power Service and any Enhanced Reactive Power Service contained in Schedule 3, Part I. Provision of Obligatory Reactive Power Service
Subject as herein provided, each User hereby agrees, as between The Company and that User, to provide the Obligatory Reactive Power Service from each of the BM Units specified in a Mandatory Services Agreement.
In respect of Generating Unit(s) located Offshore where the Obligatory Reactive Power Service is provided to The Company by an Offshore Transmission Licensee in accordance with the STC, the Mandatory Ancillary Services Agreement shall detail the payments that The Company shall make to the User (not withstanding that the Obligatory Reactive Power Service is provided to The Company by an Offshore Transmission Licensee). Redeclarations
(a) For the avoidance of doubt, nothing in this Paragraph 4.1.2.4 or any Mandatory Services Agreement shall affect the provisions of Grid Code OC 2 and/or BC 1 concerning the redeclaration in relation to any BM Unit (or where applicable, any CCGT Unit or Power Park Unit) of a revised capability to provide Leading and/or Lagging Mvar, where applicable at the generator stator terminals.
All such redeclarations at the generator stator terminals submitted pursuant to Grid Code OC2 and/or BC 1 may include the revised capability (in the case of CCGT Units and Power Park Units of the relevant BM Unit) at Rated MW at the Commercial Boundary. Such capability shall be derived from the capability at the generator stator terminals by application of the applicable formulae set out in Parts 1, 2 or 3 of Appendix 8 to Schedule 3, Part I.
Where a redeclaration of capability to provide Leading and/or Lagging Mvars at Rated MW does not specify such revised capability at the Commercial Boundary, then The Company shall calculate the revised capability at Rated MW at the Commercial Boundary by application of the applicable formulae set out in Parts 1, 2 or 3 of Appendix 8 to Schedule 3, Part I.
Any revised capability of a BM Unit at Rated MW at the Commercial Boundary shall constitute the respective values of QR and QR as referred to in Section 2 of lead lag Appendix 3 of Schedule 3, Part I.
In order to calculate any payments which fall due in accordance with this Paragraph 4.1.2 and a Mandatory Services Agreement, following commencement of the relevant clause of the Mandatory Services Agreement, The Company shall calculate the values of QR and lead QR in accordance with the applicable formulae lag contained in Parts 1, 2 or 3 of Appendix 8 to Schedule 3, Part I. Utilisation
The Company shall have the right (but shall not be obliged) at any time to instruct a User by the issue of a Reactive Despatch Instruction to provide Leading and/or Lagging Mvars from some or all of the BM Units specified in a Mandatory Services Agreement. Monitoring
In order to comply with its obligations contained in Grid Code OC 5, The Company may use Operational Metering Equipment owned by a Relevant Transmission Licensee in accordance with Paragraph 6.7.3 to ensure that, in respect of each BM Unit, a User is complying with its obligations to provide the Obligatory Reactive Power Service both in accordance with the Grid Code and in accordance with the terms of the Mandatory Services Agreement.
Each User acknowledges that The Company may wish to install additional monitoring equipment at a Power Station to monitor the ability of any or all of the BM Units of that User to provide the Obligatory Reactive Power Service, such monitoring equipment to be installed on terms to be agreed with that User (such agreement not to be unreasonably withheld or delayed). The cost of such additional monitoring equipment and its installation shall be borne by The Company. Reactive Testing
Where, in accordance with Grid Code OC 5.4.2.4, The Company shall be entitled to require a Reactive Test, such test shall be in addition to, and shall not prejudice The Company 's right to require, the two annual Reactive Tests referred to in Grid Code OC 5.5.1.1. If a BM Unit or a CCGT Unit (as the case may be) fails a Reactive Test, then The Company shall advise the User that the BM Unit or CCGT Unit (as appropriate) has so failed whereupon, subject always to resolution of any dispute in accordance with Grid Code OC 5.5.4 and (where applicable) OC 5.5.5, the User shall immediately advise The Company of the revised capability of that BM Unit or CCGT Unit (as appropriate) to provide Leading and/or Lagging Mvars (as the case may be) in accordance with the terms of the Mandatory Services Agreement. Grid Code
It is acknowledged by The Company and each User that the provision by that User of the Obligatory Reactive Power Service in accordance with the terms of the CUSC and the Mandatory Services Agreement shall not relieve it of any of its obligations set out in the Grid Code including without limitation its obligation set out in Grid Code CC 8.1 to provide Reactive Power (supplied otherwise than by means of synchronous or static compensators) except in the case of a Power Park Module where synchronous or static compensation within the Power Park Module may be used to provide Reactive Power) in accordance with Grid Code CC
Each User hereby consents to the disclosure and use by The Company of data and other information relating to the provision by that User of the Obligatory Reactive Power Service and the relevant provisions of the Mandatory Services Agreement relating thereto to the extent necessary to enable The Company to comply with its obligations set out in the CUSC. Each User hereby consents to the disclosure and use by The Company of data and other information from any year relating to the provision by that User of the Balancing Service to the extent necessary to enable The Company to carry out its EMR Functions. Hierarchy
If any provision of the Mandatory Services Agreement to the extent relating to the Obligatory Reactive Power Service shall be inconsistent with the provisions of Schedule 3, Part I, the provisions of Schedule 3, Part I shall prevail to the extent of such inconsistency.
Frequency Response Introduction
Each applicable User is obliged to provide (for the avoidance of doubt, as determined by any direction in force from time to time and issued by the Authority relieving that User from the obligation under its Licence to comply with such part or parts of the Grid Code or any Distribution Code or, in the case of The Company, the ESO Licence, as may be specified in such direction) the Mandatory Ancillary Service of Frequency Response referred to in Grid Code CC 8.1 by means of Frequency sensitive generation in accordance with the terms of this Paragraph 4.1.3 and a Mandatory Services Agreement but subject always to and in accordance with the relevant part or parts of the Grid Code applicable thereto. Definitions
For the purposes of this Paragraph 4.1.3:
“Frequency Response Service” means the Mandatory Ancillary Service of Frequency Response and any Commercial Ancillary Service of Frequency Response as may be agreed to be provided by a User from time to time;
the Mandatory Ancillary Service of Frequency Response shall constitute operation of a BM Unit in accordance with Grid Code CC 6.3.7 and BC 3.5 (with the exception of BC 3.5.2), including, without limitation, under normal operating conditions with the speed governor set so that it operates with an overall speed droop of between 3% and 5% so as to provide the applicable levels of Response referred to in Paragraph 4.1.3.7;
the term "instruction" means a communication whether by telephone or automatic logging device or via the Designated Information Exchange System from The Company to the User instructing a User in accordance with Grid Code BC 2.8 and this Paragraph 4.1.3 to provide any Frequency Response Service, and derivations of the term shall be construed accordingly;
the amendment of an existing instruction shall be deemed to be a new instruction;
an instruction will prevail until either it is countermanded by The Company or until the BM Unit to which the instruction relates is De-synchronised (whichever is first to occur). The Company’s Instructions to provide Mode A Frequency Response
For the purposes of instructions and calculation of payments, the Mandatory Ancillary Service of Frequency Response as described in this Paragraph 4.1.3 shall be referred to as “Mode A Frequency Response”.
The Company may at any time instruct a User to operate any one or more BM Unit(s) so as to provide the following components of Mode A Frequency Response:-
Primary Response;
Secondary Response;
High Frequency Response, in any of the permissible combinations set out in the relevant table in the Mandatory Services Agreement.
The Company shall not instruct a User to provide Mode A Frequency Response and any Commercial Ancillary Service of Frequency Response simultaneously.
In the event that any instruction to provide Frequency Response does not state whether the instruction is to provide Mode A Frequency Response or any Commercial Ancillary Service of Frequency Response, such instruction shall be deemed to be an instruction to provide Mode A Frequency Response. User’s Obligation to Provide Response
When a User is instructed in accordance with Paragraphs 4.1.3.4 and/or 4.1.3.6 to operate a BM Unit so as to provide any component(s) of Mode A Frequency Response, that User shall operate that BM Unit so as to provide, for any Frequency Deviation and at any level of De-Load, at least the amount of Primary Response and/or Secondary Response and/or High Frequency Response set out respectively in the relevant Frequency Response Capability Data tables in the Mandatory Services Agreement (as such tables are to be interpreted in accordance with Paragraph 4.1.3.11). 4.1.3.7A For the avoidance of doubt a User shall ensure that the Transmission Entry Capacity, and if relevant the STTEC and\or LDTEC and\or any Temporary Received TEC less any Temporary Donated TEC, for the relevant Connection Site shall be sufficient to enable it to comply with its obligations under Paragraph 4.1.3.7 above at all times and in respect of all BM Units. Calculation of Payments
The payments to be made by The Company to a User hereunder in respect of the provision of any Mode A Frequency Response from a BM Unit shall be comprised of Holding Payments and Response Energy Payments and shall be determined in accordance with the formulae in, respectively, Paragraphs 4.1.3.9 and 4.1.3.9A and in accordance with Paragraphs 4.1.3.10 to 4.1.3.12 inclusive. Payment Formulae - Holding Payments
The Holding Payments for a BM Unit to be made by The Company to a User referred to in Paragraph 4.1.3.8 shall be calculated in accordance with the following formula:- HP = P +H +S M M M M Where: HP is the Holding Payment to be made to the User M calculated in £ per minute. P is the payment per minute to be made by The Company M to the User for the Ancillary Service of Primary Response provided by the User from the BM Unit concerned pursuant to an instruction from The Company to provide Mode A Frequency Response, and is calculated as follows:- 1 P =(P P (1−SF ))K K M PR MW P T GRC 60 H is the payment per minute to be made by The Company M to the User for the Ancillary Service of High Frequency Response provided by the User from the BM Unit concerned pursuant to an instruction from The Company to provide Mode A Frequency Response, and is calculated as follows:- 1 H =(H H (1−SF ))K K M PR MW H T GRC 60 S is the payment per minute to be made by The Company M to the User for the Ancillary Service of Secondary Response provided by the User from the BM Unit concerned pursuant to an instruction from The Company to provide Mode A Frequency Response, and is calculated as follows:- 1 S =(S S (1−SF ))K K M PR MW S T GRC 60 In this Paragraph 4.1.3.9, the following terms shall have the following meanings:- P = the appropriate payment rate for Primary Response PR determined in accordance with Paragraph 4.1.3.13; P = the Primary Response capability (expressed in MW) MW for the level of De-Load of the BM Unit concerned at the end of the minute in which the service is provided. In the case of Power Park Modules this component will not exceed the value of the cap on the level of Primary Response capability (P ) as calculated in CAP 4.1.3.9.1; H = the appropriate payment rate for High Frequency PR Response determined in accordance with Paragraph 4.1.3.13; H = the High Frequency Response capability MW (expressed in MW) for the level of De-Load of the BM Unit concerned at the end of the minute in which the service is provided. In the case of Power Park Modules this component will not exceed the value of the cap on the level of High Frequency Response capability (H ) as calculated in 4.1.3.9.2; CAP S = the appropriate payment rate for Secondary PR Response determined in accordance with Paragraph 4.1.3.13; S = the Secondary Response capability (expressed in MW MW) for the level of De-Load of the BM Unit concerned at the end of the minute in which the service is provided. In the case of Power Park Modules this component will not exceed the value of the cap on the level of Secondary Response capability (S ) as calculated in 4.1.3.9.3; CAP K = the ambient temperature adjustment factor. The T Company and each User acknowledge and agree, as between The Company and that User, that K T shall be deemed to be 1 for the purposes of calculating payments until such time as they agree upon an appropriate formula and a suitable method of measuring the ambient temperature on a minute by minute basis which shall be set out in the Mandatory Services Agreement. In the event that any agreed method of measuring the ambient temperature on a minute by minute basis should fail following its implementation, then The Company and each User acknowledge and agree, as between The Company and that User, that K shall be deemed to T be 1 until the method of measuring the ambient temperature on a minute by minute basis is restored; K = where the BM Unit is a CCGT Module, the plant GRC configuration adjustment factor set out in the relevant table in the Mandatory Services Agreement for the configuration of the BM Unit concerned at the time at which the capability to provide the service is carried, otherwise 1; SF = 0, subject to Paragraph 4.1.3.21 (e); P SF = 0, subject to Paragraph 4.1.3.21 (e); S SF = 0, subject to Paragraph 4.1.3.21 (e). H
Calculation of the Primary Response cap for Power Park Modules A cap on the level of Primary Response capability for the purposes of the Holding Payment calculation is calculated as follows: 𝐶𝑢𝑟𝑟𝑒𝑛𝑡 𝑀𝐸𝐿 𝑃 = 𝑥 𝑅𝑒𝑠𝑝𝑜𝑛𝑠𝑒 𝐶𝑎𝑝𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝐶𝐴𝑃 𝑅𝑒𝑔𝑖𝑠𝑡𝑒𝑟𝑒𝑑 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 Where in this Paragraph the following terms have the following meaning: Current MEL is the Maximum Export Limit as submitted in respect of the Power Park Module by the relevant Generator to The Company. Registered Capacity is that as declared by the Generator in respect of the Power Park Module. Response Capability is that which is set out in the relevant Frequency Response Capability Data tables in the Mandatory Services Agreement for the applicable level of De-load.
Calculation of the High Frequency Response cap for Power Park Modules A cap on the level of High Frequency Response capability for the purposes of the Holding Payment calculation is calculated as follows: 𝐶𝑢𝑟𝑟𝑒𝑛𝑡 𝑀𝐸𝐿 𝐻 = 𝑥 𝑅𝑒𝑠𝑝𝑜𝑛𝑠𝑒 𝐶𝑎𝑝𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝐶𝐴𝑃 𝑅𝑒𝑔𝑖𝑠𝑡𝑒𝑟𝑒𝑑 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 Where in this Paragraph the following terms have the following meaning: Current MEL is the Maximum Export Limit as submitted in respect of the Power Park Module by the relevant Generator to The Company. Registered Capacity is that as declared by the Generator in respect of the Power Park Module. Response Capability is that which is set out in the relevant Frequency Response Capability Data tables in the Mandatory Services Agreement for the applicable level of De-load.
Calculation of the Secondary Response cap for Power Park Modules A cap on the level of Secondary Response capability for the purposes of the Holding Payment calculation is calculated as follows: 𝐶𝑢𝑟𝑟𝑒𝑛𝑡 𝑀𝐸𝐿 𝑆 = 𝑥 𝑅𝑒𝑠𝑝𝑜𝑛𝑠𝑒 𝐶𝑎𝑝𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝐶𝐴𝑃 𝑅𝑒𝑔𝑖𝑠𝑡𝑒𝑟𝑒𝑑 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 Where in this Paragraph the following terms have the following meaning: Current MEL is the Maximum Export Limit as submitted in respect of the Power Park Module by the relevant Generator to The Company. Registered Capacity is that as declared by the Generator in respect of the Power Park Module. Response Capability is that which is set out in the relevant Frequency Response Capability Data tables in the Mandatory Services Agreement for the applicable level of De-load. Payment Formulae – Response Energy Payment 4.1.3.9A (a) The Response Energy Payments for BM Unit i in Settlement Period j to be made by The Company to a User referred to in Paragraph 4.1.3.8 shall be calculated in accordance with the following formulae:- REP = RE Reference Price ij ij But so that where REP is negative such amount shall be ij paid by the User to The Company. Where: REP is the Response Energy Payment to be made to ij or, as the case may be, by the User; and RE is the expected response energy for BM Unit i in ij Settlement Period j calculated as follows:- max(FR (t),0)(1−SF ) SPD ij LF RE = K K dt ij 0 +min(FR ) T GRC (t),0)(1−SF ij H Where: SPD dtis the integral at times t, over the Settlement Period duration. SF is equal to SF in the case of a BM Unit being LF P instructed to deliver Primary Response without Secondary Response or the mean of SF and SF in P S the case of a BM Unit being instructed to deliver Primary Response and Secondary Response. SF , SF , SF , K and K have the meanings ascribed P S H T GRC to them in Paragraph 4.1.3.9. FR (t) is the expected change in Active Power output for ij BM Unit i, at time t (resolved to the nearest integer minute), expressed in MW derived from the relevant Frequency Response Power Delivery Data table in the Mandatory Services Agreement (as such table is interpreted in accordance with Paragraph 4.1.3.11) by reference to the level of De-Load of the BM Unit concerned at the end of the minute and the mean Frequency Deviation over that minute when that BM Unit is providing Mode A Frequency Response and zero at all other times. For this purpose:-
for a positive Frequency Deviation the expected change in Active Power output of BM Unit i shall be derived from the table entitled “High Frequency Response Power Delivery – Mode A” set out in the Mandatory Services Agreement and shall be signed negative; and
for a negative Frequency Deviation, the expected change in Active Power output of BM Unit i shall be derived from: A) the table entitled “Primary Response Power Delivery – Mode A” in the case of a BM Unit being instructed to deliver Primary Response without Secondary Response; or B) the table entitled “Primary and Secondary Response Power Delivery – Mode A” in the case of a BM Unit being instructed to deliver Primary Response and Secondary Response, in each case set out in the Mandatory Services Agreement and shall be signed positive. A User with a “CfD BMU” (a BM Unit registered in respect of a Power Station whose operator is a party to an agreement with the CfD Counterparty) the User can elect, at the outset of the agreement with the CfD Counterparty, to set the Reference Price to Max for Response Energy Payments for that CfD BMU for the duration of that agreement. Until such election, which can only be made once by reference to that CfD agreement, the Reference Price shall be 0 by default. Where: RE is positive then: ij Reference Price = max (∑ {PXP x QXP } / ∑ {QXP } s sj sj s sj x 1.25, 0 ) except in the case of (a) a non-fuel cost BM Unit or (b) a BM Unit registered in respect of a Power Station whose operator is a party to an agreement with the CfD Counterparty still in effect during the relevant Settlement Period, where it = 0 where ∑ represents the sum over all Market Index s Data Providers. Where RE is negative then: ij Reference Price = max (∑ {PXP x QXP } / ∑ {QXP } s sj sj s sj x 0.75, 0 ) except in the case of (a) a non-fuel cost BM Unit or (b) a BM Unit which relates to a Power Station whose operator is a party to an agreement with the CfD Counterparty, still in effect during the relevant Settlement Period, where it = 0 where ∑ represents the sum over all Market Index s Data Providers Where for the purposes of this Paragraph: a non-fuel cost BM Unit means a BM Unit [associated with] [registered in respect of] a non-fuel cost Power Station a non-fuel cost Power Station means: a Power Station of the following type which does not have the facility to store the energy produced) Onshore wind Offshore wind Solar Tidal Wave
In this Paragraph 4.1.3.9A, the following terms shall have the meanings ascribed to them in the Balancing and Settlement Code:- “PXP ” sj “QXP ” sj “SPD” “Market Index Data Provider“
The Company and each User acknowledge and agree, as between The Company and that User, that no Holding Payment or Response Energy Payment shall be payable except in relation to periods in respect of which instructions have been issued by The Company pursuant to this Paragraph 4.1.3. Interpretation of Tables – Levels of Response
The figures for Response set out in the Frequency Response Capability Data tables and Frequency Response Power Delivery Data tables in the Mandatory Services Agreements shall be given in relation to specific Frequency Deviations and to specific levels of De-Load for a BM Unit. Such tables shall, for the purposes of Paragraphs 4.1.3.7 and 4.1.3.9A(a), be construed in accordance with this Paragraph 4.1.3.11. Subject to Paragraphs 4.1.3.11(d) and (e):-
for a Frequency Deviation at a given time differing from the figures given in a table, the level of Response shall be calculated by linear interpolation from the figures specified in the table in respect of Frequency Deviations;
for a level of De-Load at a given time differing from the figures given in a table, the level of Response shall be calculated by linear interpolation from the figures specified in the table in respect of levels of De-Load. For the avoidance of doubt, Frequency Sensitive Mode shall not be instructed for any De-Load greater than the maximum level of De-Load given in the relevant Frequency Response Capability Data table;
in respect of any time in relation to which both Paragraphs 4.1.3.11(a) and (b) apply, the level of Response shall be calculated by dual linear interpolation from the figures specified in the table in respect of Frequency Deviations and in respect of levels of De-Load; and
for any Frequency Deviation greater than the greatest Frequency Deviation given in a table (whether positive or negative), the level of Response shall be calculated by reference to the greatest Frequency Deviation (positive or negative, as the case may be) given in that table; and
for the purposes of calculating levels of Response in respect of Frequency Deviations lower than those specified in a table, the relevant table(s) shall be deemed to specify a level of zero Response for a Frequency Deviation of zero. Interpretation of Tables – Levels of Holding Payment
The Frequency Response Summary Data table in the Mandatory Services Agreement shall set out figures in respect of given levels of De-Load for the purposes of calculating payment in accordance with the formulae in Paragraph 4.1.3.9. Where the level of De-Load of the BM Unit is other than one of the levels given in such table, then, the figure for P , S or H as the case may be, shall be MW MW MW calculated by linear interpolation from the figures in such table in respect of levels of De-Load. User’s submission of Holding Payment Rates
The following terms shall apply to determine the payment rates for Primary Response, High Frequency Response and Secondary Response used in the calculation of Holding Payments in accordance with Paragraph 4.1.3.9 which shall apply in respect of the provision of Mode A Frequency Response by the User to The Company from one or more BM Units in a calendar month (and, for the purposes thereof, all dates specified in this Paragraph 4.1.3.13 unless stated otherwise refer to the immediately preceding calendar month):-
By the fifth Business Day of the calendar month, The Company shall publish on its web-site information relating to The Company’s requirement for Mode A Frequency Response (in MW) in the next following calendar month.
By the fifteenth Business Day of the calendar month, the User may in relation to any of its BM Units identified in a Mandatory Services Agreement to which the User is a party submit a single notification to The Company (in a form and by such method as shall be prescribed by The Company from time to time) specifying in respect of that BM Unit the payment rates to apply in determining the Holding Payments for the provision of Mode A Frequency Response during the next following calendar month, each such notification to specify:-
the BM Unit in question;
the payment rate for Primary Response;
the payment rate for High Frequency Response; and
the payment rate for Secondary Response.
Payment rates submitted by the User in accordance with Paragraph 4.1.3.13(b) must be:-
quoted in pounds sterling to the nearest penny;
quoted in units of £/MW/h; and
no greater than £[9999.99].
Upon receipt of a notification from the User made in accordance with Paragraph 4.1.3.13(b), The Company shall publish details of such notification in a report issued in accordance with Paragraph 4.1.3.13(A)(a) and, subject always to rectification (if any) of payment rates pursuant to Paragraph 4.1.3.13(e), The Company shall apply published payment rates for Primary Response, High Frequency Response and Secondary Response in calculating the Holding Payments for the relevant BM Unit in the next following calendar month.
The User shall have the right, to be exercised within one Business Day of the publication of payment rates in respect of a BM Unit in accordance with Paragraph 4.1.3.13(d), to notify The Company (in a form and by such method as shall be prescribed by The Company from time to time) of any discrepancy between those payment rates and the actual payment rates submitted by the User in respect of that BM Unit in accordance with Paragraph 4.1.3.13(b). Upon receipt of any such notification, The Company shall rectify the report issued in accordance with Paragraph 4.1.3.13A(a) and shall publish the rectified report in accordance with Paragraph 4.1.3.13A(b).
In the absence of a notification from a User in accordance with Paragraph 4.1.3.13(b) in respect of the provision by a BM Unit of Mode A Frequency Response in the next following calendar month, then the payment rates for Primary Response, High Frequency Response and Secondary Response to apply in determining the Holding Payments for that BM Unit in respect of that calendar month shall be determined as follows:-
where the User has never in respect of any previous calendar month submitted a notification in accordance with Paragraph 4.1.3.13(b) in respect of the provision by that BM Unit of Mode A Frequency Response, the payment rate to apply to the provision of each of Primary Response, High Frequency Response and Secondary Response from that BM Unit in that calendar month shall be deemed to be either:-
the payment rates for Primary Response, High Frequency Response and Secondary Response prevailing immediately prior to the date of implementation of Amendment Proposal CAP047; or
where no payment rates as referred to in paragraph (aa) above subsisted at the date of implementation of Amendment Proposal CAP047, £00.00/MW/h; or
in all other cases, the payment rates for Primary Response, High Frequency Response and Secondary Response which shall apply in respect of the provision by that BM Unit of Mode A Frequency Response in that calendar month shall be the payment rates most recently published in accordance with Paragraph 4.1.3.13A(a) or (b) (as the case may be) for that BM Unit in respect of a previous calendar month;
Paragraph 4.4.2.2 shall not apply to the payment rates for Primary Response, High Frequency Response and Secondary Response determined in accordance with this Paragraph 4.1.3.13. Publication of Holding Payment Rates and other information 4.1.3.13A (a) The Company shall use reasonable endeavours to publish on its web-site by the 16th Business Day of each calendar month, a report containing the following information in respect of each applicable User’s BM Unit(s) to apply in respect of the next following calendar month:-
the payment rates for Primary Response, High Frequency Response and Secondary Response to apply in determining the Holding Payments for the next following calendar month as determined in accordance with Paragraph 4.1.3.13;
the available Response volume (in such form and manner as shall be prescribed by The Company from time to time).
Where any payment rates published in a report issued in accordance with Paragraph 4.1.3.13A(a) are rectified by The Company in accordance with Paragraph 4.1.3.13(e), The Company shall as soon as reasonably practicable thereafter publish the rectified report on its web-site.
In respect of each day in a calendar month, The Company shall use reasonable endeavours to publish on its web-site by the third Business Day of the calendar month following that calendar month, provisional data in respect of all BM Units details of instructions issued by The Company in accordance with Paragraph 4.1.3.4 for each of Primary Response, High Frequency Response and Secondary Response (in such form and manner as shall be prescribed by The Company from time to time). The Users recognise that the provisional data may differ from the data to be provided under Paragraph 4.1.3.13A (d) and therefore any reliance upon this provisional data is entirely at the User’s risk.
In respect of each day in a calendar month, The Company shall, by the ninth Business Day of the calendar month following that calendar month, publish on its web-site in respect of all BM Units details of instructions issued by The Company in accordance with Paragraph 4.1.3.4 for each of Primary Response, High Frequency Response and Secondary Response (in such form and manner as shall be prescribed by The Company from time to time).
Each User consents to the disclosure by The Company of the information referred to in Paragraphs 4.1.3.13A(a) and (b) in so far as it relates the provision of Mode A Frequency Response from its BM Unit(s), provided always that The Company shall not be bound to comply with the provisions of Paragraphs 4.1.3.13A(a) and (b) with regard to the provision of information to the extent that to do so would be likely to restrict, distort or prevent competition in the provision of Mode A Frequency Response. Requests to Amend Levels of Response
Where either the User or The Company reasonably considers in light of operating experience that the levels of Response set out in the Frequency Response Capability Data tables and / or the Frequency Power Delivery Data tables in the Mandatory Services Agreement do not represent the true operating capabilities of a BM Unit(s), the User or The Company (as the case may be) shall have the right not more than once every two months (or otherwise at any time with the specific agreement of the other party to the Mandatory Services Agreement) to request (provided always that such request be accompanied by a reasonable justification therefor) that the levels of Response set out in the relevant response table(s) in the Mandatory Services Agreement be reviewed and, if appropriate, amended by agreement with such other party, such agreement not to be unreasonably withheld or delayed. Procedure for Amendments to Levels of Response
Any amendments agreed by The Company and a User pursuant to Paragraph 4.1.3.14 or determined by an arbitrator or panel of arbitrators under the Dispute Resolution Procedure in the circumstances referred to in Paragraph 4.1.3.16 shall not become effective until (in the case of agreed amendments) a date at least five Business Days after an amending agreement is entered into between The Company and the User in accordance with the Mandatory Services Agreement or, in the case of determined amendments, such other date as may be determined by an arbitrator or panel of arbitrators under the Dispute Resolution Procedure subject always to Paragraphs 4.1.3.17 and 4.1.3.18. Failure to Agree Amendments
If The Company and a User are unable to agree any amendments requested pursuant to Paragraph 4.1.3.14 within 28 days of either of them serving on the other notice of its intention to invoke the Dispute Resolution Procedure then either party may initiate the procedure for resolution of the issue as an Other Dispute in accordance with Paragraph 7.4. Dispute Resolution Procedure
The Company and each User acknowledge and agree, as between The Company and that User, that the rules of the London Court of International Arbitration shall apply to any arbitration proceedings initiated pursuant to Paragraph 7.4 in the circumstances referred to in Paragraph 4.1.3.16, but that the changes determined by any arbitrator or panel of arbitrators shall not apply in respect of any period prior to the date on which the Dispute Resolution Procedure is invoked. Implementation of Determinations
Any amendments to levels of Response determined by an arbitrator or panel of arbitrators under the Dispute Resolution Procedure in the circumstances referred to in Paragraph 4.1.3.16 shall take effect from the date five Business Days following the relevant determination. Implementation of Continuous Monitoring System
To the extent the same shall be acceptable to The Company and a User on the basis of a cost benefit analysis, The Company and a User agree, as between The Company and that User, to the implementation of a continuous monitoring system as soon as is reasonably practicable. The continuous monitoring system shall be in accordance with the relevant principles set out in Paragraph 4.1.3.21 for the purposes of confirming performance of the BM Units and adjusting payments pursuant to this Paragraph 4.1.3. Incident Based Monitoring System
Pending implementation of the continuous monitoring system, The Company and each User agree, as between The Company and that User, to implement an incident based monitoring scheme for the purpose of confirming the performance of the BM Units pursuant to this Paragraph 4.1.3. Such incident based monitoring scheme shall be in accordance with the relevant principles set out in Paragraph 4.1.3.21. Neither The Company nor the User shall unreasonably withhold or delay such agreement and/or implementation. Genset Response Monitoring Introduction
(a) This Paragraph 4.1.3.21 sets out the principles relating to:
the proposed continuous monitoring system to be implemented pursuant to Paragraph 4.1.3.19; and
the incident based monitoring system to apply until such time as implementation of the continuous monitoring system takes place. Some elements of the continuous monitoring system are currently undergoing testing and development and it is accepted that if final testing of these elements proves unsatisfactory alternatives will need to be developed. Further, implementation of the continuous monitoring system shall be subject to its acceptability to The Company and Users on the basis of a cost benefit analysis. Wherever possible the technical specification of both the incident based monitoring system and the continuous monitoring system will be designed so as to enable future development or enhancement. Aims of Project
The aim of the monitoring project (which includes, without limitation, the development of the incident based monitoring system and the continuous monitoring system) is to develop a response monitoring system which will measure the response performance of generators against the levels of Frequency Response required to be provided under Mandatory Services Agreements. Incident Based Monitoring Scheme
Details of the incident based monitoring scheme (including without limitation the definitions of Shortfall Period and Incident, the calculation of service delivery and the determination of Incident start and end times) will be more particularly set out in a document entitled "Procedure for Incident Based Response Monitoring" ("the PIRM Document") to be produced by The Company and agreed by all relevant Users (such agreement not to be unreasonably withheld or delayed). For the avoidance of doubt during the period during which the incident based monitoring scheme applies, and prior to the implementation of the continuous monitoring system, for the purposes of the formulae in Paragraphs 4.1.3.9 and 4.1.3.9A, the values of SF , P SF and SF shall be zero, such that no payment S H reduction shall apply during such period in respect of shortfall. Continuous Based Monitoring Scheme – Confirmation of Response Delivery
The main objective of the continuous monitoring scheme is to provide a quantitative measure of Frequency Response delivery against which payment can be justifiably made and to reduce payments if delivery does not comply with the CUSC and the Mandatory Services Agreement. As the capability of a BM Unit to provide the level of Response required pursuant to this Paragraph 4.1.3 for any change in System Frequency occurring during the period of delivery of Response pursuant to a prior change in System Frequency will be affected by the level of Response then being delivered, relevant fluctuations in System Frequency should to this extent be taken into account by the continuous monitoring scheme for the purpose of calculating payment levels. Determination of Response Shortfall
For the purposes of the continuous monitoring system, the Response shortfall may take three forms:-
average Primary Response under-delivery;
average Secondary Response under-delivery;
average High Frequency Response under- delivery, in each case over a Shortfall Period (such term to be defined prior to implementation of the continuous monitoring system). Upon the implementation of the continuous monitoring system, for the purposes of determining any such average under-delivery, SF , SF and SF shall be the P S H average under-delivery of Primary Response, Secondary Response and High Frequency Response respectively during the Shortfall Period in which the Ancillary Service was, or should have been, provided. For the purposes of the formulae in Paragraphs 4.1.3.9 and 4.1.3.9A, such average under- delivery will be determined using a continuous plant response assessment algorithm which is under development and which will be agreed with the User prior to its implementation and expressed in terms of 0 SF 1. Measurement of System Variables
In relation to the continuous monitoring system measurement of System Frequency and generator output power will be required local to the BM Unit. Synchronised time tagging of both power and Frequency will be required. Frequency is required as the fundamental driving variable of the contract model software. Access to a voltage source to enable Frequency to be measured is not expected to cause any difficulty. The measurement of generator output power will also be required every second. Cost effective access to this measurement is, however, less straight forward. Covered below are two options describing how this will be achieved. It is expected that normally the FMS interface unit will be the method used; however, where the BM Unit concerned has derogations from FMS, method two may be used. FMS Interface Unit
The use of the Final Metering System (FMS) represents a logical method of measurement since it eliminates the high cost associated with running cables to access CTs and VTs. The high accuracy integrated data from FMS will be used to re-generate a power profile and curve fitting techniques will be applied to improve accuracy. This instantaneous power curve will then be sampled every second to obtain the required values. Direct Measurement
Where for the reasons detailed in Paragraph 4.1.3.21(f) it is not possible to use the FMS interface unit, the use of 'ISAT' type transducers will be employed to interface between the monitoring equipment and the measurement transformers' secondary circuit. It is envisaged that generators seeking derogations from FMS will be supportive in establishing convenient VT and CT secondary connections for this purpose. Contract Model
The contract model is the heart of the continuous monitoring system and it is crucial to the philosophy behind the system, namely that of modelling the Mandatory Services Agreement and not the BM Unit itself. Given the difficulty in measuring Frequency Response directly on loaded plant, the need to compare changes in power delivery against expectation is evident. Comparison against this model output, which in turn is based on agreed and legally binding contracts, permits an identifiable quantity of non conformity to be measured and payments to be suitably reduced. Therefore, since the Mandatory Services Agreement itself is the quantifying factor, there can be no redress due to assumptions regarding the technical attributes of the BM Unit other than those taken into account in setting the levels of Response. Functional Objective
In relation to the continuous monitoring system, the model will comprise software which uses system and instructed variables to access the contract look-up tables. The look-up tables used will precisely mimic the response tables set out in Mandatory Services Agreements. These variables in turn will be processed using an algorithm to determine the levels of Response expected at any instant in time. It is intended that this process will be effective during both small and large Frequency Deviations. Indeed with regard to reduction in payment and estimated Response capability, response to small Frequency Deviations is extremely important. Input Data
In relation to the continuous monitoring system, inputs to the contract model will include Frequency, all contract table data, target load, Target Frequency, the latest genset availability, the response instruction, LF setting (if electronically despatched) and any other information required which may be specified in the Mandatory Services Agreement. Comparator
In relation to the continuous monitoring system, the comparator will determine the difference between the measured change in the level of Output from the BM Unit by way of Frequency Response and the change in Output level that is specified in the Mandatory Services Agreement.
If, at any time during the term of a Mandatory Services Agreement, there is a variation in the security standards with which The Company is obliged to comply and such variation would, in a User's reasonable opinion, materially affect the operation of the services to be provided under that Mandatory Services Agreement, The Company and that User shall negotiate in good faith with a view to agreeing and implementing appropriate amendments to any relevant Mandatory Services Agreement. If they are unable to reach agreement within 28 days of either of them serving on the other notice of its intention to invoke the Dispute Resolution Procedure, either of them may initiate the procedure for resolution of the issue as an Other Dispute in accordance with Paragraph 7.4.
Each User hereby consents to the disclosure and use by The Company of data and other information from any year relating to the provision by that User of the Balancing Service to the extent necessary to enable The Company to carry out its EMR Functions.
Disclosure and Use of Information
Application The provisions of this Paragraph 4.2 shall apply to The Company and a User in respect of the provision by that User to The Company of Maximum Generation where a Maximum Generation Service Agreement has been entered into and is in force between The Company and that User.
Provision of Maximum Generation Each User hereby agrees, as between The Company and that User, to use reasonable endeavours to make available and provide Maximum Generation from each of the Maximum Generation BM Unit(s) in accordance with the terms of this Paragraph 4.2 in respect of each Operational Day during the term of the Maximum Generation Service Agreement.
Availability of Maximum Generation
By 15.00 hours on each Wednesday, the User may notify The Company via the Designated Information Exchange System in the form set out in Schedule 1 to this Section 4 (a “Weekly Maximum Generation Declaration”) of the availability of Maximum Generation in relation to each of the Maximum Generation BM Unit(s) in the following Week. Failure to submit a Weekly Declaration in accordance with this Paragraph 4.2.3 shall be deemed to be an indication of availability or unavailability (as the case may be) of Maximum Generation for each Operational Day in the following Week as notified by the User in the last Weekly Maximum Generation Declaration submitted in accordance with this Paragraph 4.2.3, if any, or if no previous Weekly Maximum Generation Declaration has been submitted, in the amount of the Indicative Maximum Generation Capability specified in the Maximum Generation Service Agreement between The Company and that User.
The User may indicate in the Weekly Maximum Generation Declaration its best estimate of the amount of Maximum Generation available (the “Indicative Maximum Generation Capability”). If no such indication is given, the User shall be deemed to have notified The Company of the amount of Indicative Maximum Generation Capability set out in the Maximum Generation Service Agreement between The Company and that User.
If at any time the User becomes aware that, in respect of any Maximum Generation BM Unit(s), there are changes to the availability of Maximum Generation and/or the Indicative Maximum Generation Capability for all or part of any Operational Day as specified in the relevant Weekly Maximum Generation Declaration of any Maximum Generation Redeclaration (as the case may be), it shall notify The Company forthwith via the Designated Information Exchange System in the form set out in Schedule 2 to this Section 4 (a "Maximum Generation Redeclaration").
Each Maximum Generation BM Unit in respect of which Maximum Generation is (or is deemed to be) declared or redeclared to be available in all or part of an Operational Day in accordance with this Paragraph 4.2.3 is hereinafter referred to in respect of such Operational Day (or part thereof) as “an Available BM Unit”.
Utilisation of Maximum Generation
The Company may, as between The Company and that User, at any time instruct the User to provide Maximum Generation from an Available BM Unit (a “Maximum Generation Instruction”) and the User shall use reasonable endeavours to provide Maximum Generation from such Available BM Unit.
The Company shall only issue a Maximum Generation Instruction where an Available BM Unit has been instructed to generate or is already generating (in each case) at the prevailing Maximum Export Limit for that Available BM Unit.
If, following the issue by The Company of a Maximum Generation Instruction in respect of an Available BM Unit, the User submits to The Company (in accordance with Grid Code BC 1) a revised Maximum Export Limit for that Available BM Unit, that Available BM Unit shall be deemed to have ceased providing Maximum Generation immediately upon receipt by The Company of such revised Maximum Export Limit.
Any Maximum Generation Instruction issued by The Company shall be an Emergency Instruction. The method of issuing any Maximum Generation Instruction shall be specified in the Maximum Generation Service Agreement.
The Company may instruct the User to cease the provision of Maximum Generation from the instructed Available BM Unit at any time.
On receipt of a Maximum Generation Instruction the User shall use reasonable endeavours to provide Maximum Generation from the Available BM Unit continuously until the earlier of:-
the expiry of a period of 120 minutes; and
the time of issue by The Company of an instruction to cease provision
The provision of Maximum Generation from an Available BM Unit shall not be achieved by the transfer of the Station Demand of the Power Station to the Station Transformer(s).
Payment for Maximum Generation
The Maximum Generation Energy Payment to be made by The Company to the User following the issue of a Maximum Generation Instruction by The Company for the provision of Maximum Generation in Operational Days in calendar month m, (UF ) shall be m calculated in accordance with the following formula:- Units UF = UF m im i=1 Where; ( ) CEC UF = Min Qmax EP ,X EP im ij ij 2 ij jMm In this Paragraph 4.2.5.1, the following terms shall have the following meanings:- Qmax ij Max ( QM − ( FPN + ( QAOn +QABn ) ) ,0 ) ij ij n ij ij
| Units i=1 | the summation over all Available BM Units I | |||||
|---|---|---|---|---|---|---|
| jMm | jMm | the summation over all Settlement Periods j, in the | ||||
| set M of Settlement Periods in Operational Days in m | ||||||
| calendar month m |
| EP ij | the Maximum Generation Energy Fee (£/MWh), | |||||
|---|---|---|---|---|---|---|
| applicable in Settlement Period j, for Available BM | ||||||
| Unit i | ||||||
| CEC | Connection Entry Capacity for the Available BM | |||||
| Unit | ||||||
| X | 0.03 (or such other figure as may be either (i) set out | |||||
| in the Maximum Generation Service Agreement for | ||||||
| the Available BM Unit or (ii) agreed or determined in | ||||||
| accordance with Paragraphs 4.2.5.3 to 4.2.5.5 | ||||||
| (inclusive)) | ||||||
| QM , ij | the meanings ascribed to them in the Balancing and Settlement Code | the meanings ascribed to them in the Balancing and | ||||
| FPN , ij | Settlement Code | |||||
| QAO and ij | ||||||
| QAB ij |
Where an Available BM Unit is at the time of issue of a Maximum Generation Instruction generating at a level below Connection Entry Capacity but the amount of MW delivered as Maximum Generation by such Available BM Unit is greater than 3% (or such other figure as The Company and the User may agree in the Maximum Generation Service Agreement) of the Connection Entry Capacity of that Available BM Unit, the User shall have the right to raise a dispute in accordance with the provisions of Paragraph 4.2.5.3 as to the amount of MW (represented by the value of factor X) by reference to which payment for provision of Maximum Generation shall be determined.
Where the provisions of Paragraph 4.2.5.2 apply:-
the User may notify The Company in writing that it disagrees with the amount of MW (represented by the value of factor X) by reference to which The Company has determined the Maximum Generation Energy Payment set out in the Provisional Statement and the User shall specify in such notification the value of factor X which it considers represents the amount of MW by reference to which payment for provision of Maximum Generation should be determined in accordance with Paragraph 4.2.5.1, provided always that any such notification shall be given within ten Business Days of receipt by the User of the Provisional Monthly Statement; and
this Paragraph 4.2.5.3 and Paragraphs 4.2.5.4 and 4.2.5.5 shall apply to such matter in the place of Paragraphs 4.3.2.3, 4.3.2.7 and 4.3.2.8, and Paragraph 4.3.2 shall be read and construed accordingly. The parties shall discuss and endeavour to resolve the matter prior to The Company sending out the Final Monthly Statement. If The Company and the User reach agreement, The Company shall set out in the Final Monthly Statement the adjustments required but, if it cannot be resolved, the calculations set out in the Provisional Statement and in the Provisional Adjustments Statement shall be binding upon the parties until such time as they are reversed or revised by agreement between the parties or otherwise (in accordance with Paragraphs 4.2.5.4 and 4.2.5.5) pursuant to the Dispute Resolution Procedure.
If a User and The Company fail to reach an agreement within ten Business Days of receipt by The Company of the User's written notification in accordance with Paragraph 4.2.5.5, then either party may, within twenty Business Days of receipt by The Company of the User's written notification, refer the matter to the Authority for determination as a Charging Dispute in accordance with Paragraph 7.3.
Where a dispute is resolved by issuance of a decision of the Authority pursuant to the Dispute Resolution Procedure in accordance with Paragraph 4.2.5.4 above, The Company shall (where appropriate) adjust the account between itself and the User accordingly in the next Provisional Adjustments Statement required to be issued under Paragraph 4.3.2.1. If such decision of the Authority is subsequently reversed or modified following judicial review of the Authority's decision, The Company shall adjust the account between itself and the User accordingly in the next Provisional Adjustments Statement which it issues.
The Maximum Generation Energy Fee for each Available BM Unit of a User will be that detailed in the Maximum Generation Service Agreement between The Company and that User.
The User shall have the right to notify The Company of a revised Maximum Generation Energy Fee, as between The Company and that User, not more than once every month. Such notification must be in writing and must be received by The Company no later than the fifteenth day of the calendar month. The revised Maximum Generation Energy Fee shall apply, as between The Company and that User, with effect on and from the first Operational Day of the calendar month following such notification.
ABSVD Methodology Statement It is a condition of a User entering into a Maximum Generation Service Agreement that Maximum Generation is included in the determination of the Applicable Balancing Services Volume Data in respect of each Contracted BM Unit for the purposes of the ABSVD Methodology Statement and Section Q.6.4 of the Balancing and Settlement Code.
Maximum Generation Event of Default Any failure by the User during the term of the Maximum Generation Service Agreement to comply with its obligations pursuant to Paragraph 4.2.6 in respect of any Available BM Unit and any Settlement Period shall constitute an event of default to which the terms of Paragraph 4.2.8 shall apply.
Consequences of Maximum Generation Event of Default In respect of any event of default incurred by the User in respect of an Available BM Unit pursuant to Paragraph 4.2.7, The Company shall be entitled to withhold the Maximum Generation Energy Payment (if any) applicable to the relevant Available BM Unit and the Settlement Period in which such event of default occurred.
Grid Code The provision by the User of Maximum Generation shall not relieve it of any of its obligations (where applicable) set out in the Grid Code.
Safety Notwithstanding Paragraph 4.2.11, The Company accepts that any decision to keep an Available BM Unit operating above the prevailing Maximum Export Limit for that Available BM Unit is one for the User alone, and accepts that the User may change generation on the Available BM Unit if it believes it is necessary for safety reasons (whether relating to personnel or Plant or Apparatus). The responsibility for injury to personnel and damage to Plant and Apparatus owned and/or operated by the User caused by operation of an Available BM Unit following the issue by The Company of Maximum Generation Instruction pursuant to Paragraph 4.2.4 therefore rests with the User and The Company shall have no liability whatsoever in connection therewith. The User shall indemnify and keep indemnified The Company in respect of liability for death or personal injury and/or damage to Plant and Apparatus owned and/or operated by The Company and arising out of or in connection with such operation of one or more Available BM Unit(s) above the prevailing Maximum Export Limit for such Available BM Unit(s) from time to time, save to the extent that:- 4.2.10.1 the User has operated the Available BM Unit in accordance with Good Industry Practice; and/or 4.2.10.2 such death or personal injury and/or damage to Plant and Apparatus is caused by The Company’s negligent act or omission.
Warranty The User warrants to The Company that it believes that operation of each of its Maximum Generation BM Unit(s) above the prevailing Maximum Export Limit for such Maximum Generation BM Unit(s) will be within its safe operating parameters (whether relating to personnel or Plant or Apparatus).
Publication of Maximum Generation Information
The Company shall use reasonable endeavours to publish on its web- site within five Business Days of signature of a Maximum Generation Service Agreement, or within five Business Days of receipt of any updated information in accordance with this Paragraph 4.2, details of the following information in respect of each Maximum Generation BM Unit specified in such Maximum Generation Service Agreement:-
the Maximum Generation Energy Fee;
the Indicative Maximum Generation Capability;
the amount of factor X (as defined in Paragraph 4.2.5.1) if other than 0.03, in such form and manner as shall be prescribed by The Company from time to time.
In respect of each Operational Day in a calendar month, The Company shall, by the tenth Business Day of the calendar month following that calendar month, publish on its web-site in respect of each relevant Maximum Generation BM Unit(s) the following details of each Maximum Generation Instruction (if any) issued by The Company in accordance with Paragraph 4.2.4:-
the Maximum Generation Energy Fee;
the period(s) for which Maximum Generation has been provided;
the MW level(s) delivered as Maximum Generation, in such form and manner as shall be prescribed by The Company from time to time.
Each User consents to the disclosure by The Company of the information referred to at Paragraphs 4.2.12.1 and 4.2.12.2 above in so far as it relates the provision of Maximum Generation from its Maximum Generation BM Unit(s), provided always that The Company shall not be bound to comply with the provisions of this Paragraph with regard to the provision of information to the extent that to do so would be likely to restrict, distort or prevent competition in the provision of Maximum Generation.
Each User hereby consents to the disclosure and use by The Company of data and other information from any year relating to the provision by that User of the Balancing Service to the extent necessary to enable The Company to carry out its EMR Functions. 4.2A SYSTEM TO GENERATOR OPERATIONAL INTERTRIPPING 4.2A.1 Application The provisions of this Paragraph 4.2A shall apply to The Company and a User in respect of the provision by that User to The Company of System to Generator Operational Intertripping where details of a System to Generator Operational Intertripping Scheme are set out in Appendix F3 of the relevant Bilateral Agreement. 4.2A.2 Provision of System to Generator Operational Intertripping 4.2A.2.1 Each User hereby agrees, as between The Company and that User, to:-
(save where Force Majeure applies) make available its System to Generator Operational Intertripping Scheme for arming at all times when Active Power is being exported to the National Electricity Transmission System from the Connection Site at which such System to Generator Operational Intertripping Scheme is located;
arm, or permit the arming of, the System to Generator Operational Intertripping Scheme in accordance with the terms of the relevant Bilateral Agreement when instructed by The Company (in accordance with Grid Code BC 2.8) by telephone (such instruction to be confirmed via the Designated Information Exchange System substantially in the form set out in Schedule 3, Part I to this Section 4);
(where an instruction from The Company has been confirmed via the Designated Information Exchange System in accordance with Paragraph 4.2A.2.1(b) above) following the tripping of the Circuit Breaker(s) upon receipt of a signal from the System to Generator Operational Intertripping Scheme:-
restrict the export of Active Power from the Connection Site to the National Electricity Transmission System to the level of MW specified in such confirmation (or such increased level(s) as The Company may subsequently notify pursuant to Paragraph 4.2A.2.2(c)(i)) (“the Restricted MW Export Level”); and
maintain such restricted export until such time as the User is notified by The Company in accordance with Paragraph 4.2A.2.2(c)(ii) that the Restricted MW Export Level no longer applies, whereupon the User shall be permitted to increase the export of Active Power from the Connection Site above the Restricted MW Export Level;
comply with any special instructions given by The Company in the performance of its obligations under Paragraph 4.2A.2.1(c); and
disarm the System to Generator Operational Intertripping Scheme when instructed by The Company (in accordance with Grid Code BC2.8) by telephone (such instruction to be confirmed via the Designated Information Exchange System substantially in the form set out in Schedule 3, Part I to this Section 4). 4.2A.2.2 The Company hereby agrees to:-
notify the User as soon as reasonably practicable following The Company becoming aware of the requirement for arming of the System to Generator Operational Intertripping Scheme;
(where relevant) take any steps necessary to arm the System to Generator Operational Intertripping Scheme in accordance with the terms of the relevant Bilateral Agreement;
following the tripping of the Circuit Breaker(s) upon receipt of a signal from the System to Generator Operational Intertripping Scheme, notify the User:-
as soon as the Restricted MW Export Level, whilst still applying, can be increased; and/or
as soon as the Restricted MW Export Level (as may be increased from time to time pursuant to (i) above) no longer applies each such notification to be in accordance with Grid Code BC 2.8 and to be made by telephone (such notification to be confirmed via the Designated Information Exchange System substantially in the form set out in Schedule 3, Part II to this Section 4); and
issue an instruction to disarm, referred to in Paragraph 4.2A.2.1(e), as soon as reasonably practicable following The Company becoming aware that the requirement for arming of the System to Generator Operational Intertripping Scheme has ceased (and such an instruction shall be deemed to have been issued for the purposes of this Paragraph 4.2A upon tripping of the Circuit Breaker(s) upon receipt of a signal from the System to Generator Operational Intertripping Scheme). 4.2A.3 Intertrip Volume Following the tripping of a Circuit Breaker(s) following receipt of a signal from a System to Generator Operational Intertripping Scheme, the resulting reduction in Output for each tripped BM Unit i or (where relevant) any tripped Generating Unit(s) comprised in a BM Unit shall be determined in accordance with the relevant formula set out in the ABSVD Methodology Statement, where such resulting reduction in Output is termed SE . sj 4.2A.4 Payments to the User The Company shall make the following payments to the User in respect of System to Generator Intertripping Schemes:
a Capability Payment shall be paid in respect of each Category
Intertripping Scheme and each Category 4 Intertripping Scheme as follows:-
The Company shall pay to the User an amount (“the Capability Payment”) in consideration of the installation of the System to Generator Operational Intertripping Scheme and the User’s obligations under Paragraphs 4.2A.2.1(a) and (b), being an amount per month determined by reference to the number of Settlement Periods during the month in question (and in respect of which the requirement for System to Generator Operational Intertripping is stated in Appendix F3 of the relevant Bilateral Agreement) and the payment rate (£/Settlement Period) specified in Schedule 4 to this Section 4; and
for the avoidance of doubt, where a System to Generator Operational Intertripping Scheme comprises both a Category 2 Intertripping Scheme and a Category 4 Intertripping Scheme, only one Capability Payment shall be payable by The Company to the User in respect thereof;
subject always to Paragraph 4.2A.5, a Restricted Export Level Payment shall be paid in respect of each Category 2 Intertripping Scheme, each Category 3 Intertripping Scheme and each Category 4 Intertripping Scheme as follows:-
the payment shall only be made where, following the tripping of the Circuit Breaker(s) upon receipt of a signal from the System to Generator Operational Intertripping Scheme, restrictions on the export of Active Power from the Connection Site apply in accordance with the terms of Paragraph 4.2A.2.1(c) above at any time after the period of 24 hours has elapsed following such tripping; and
in such a case, The Company shall pay to the User upon request the Restricted Export Level Payment, by reference to the period from expiry of such 24 hour period until the time when The Company notifies the User in accordance with Paragraph 4.2A.2.2(c)(ii) that the Restricted MW Export Level no longer applies (“the Restricted Export Level Period”); and
subject always to Paragraph 4.2A.5, in respect of each Category 2 Intertripping Scheme and Category 4 Intertripping Scheme, where the Circuit Breaker(s) are tripped upon receipt of a signal from the System to Generator Operational Intertripping Scheme, The Company shall pay to the User an amount (“the Intertrip Payment”) being an amount (£/Intertrip Contracted Unit/trip) specified in Schedule 4 to this Section 4. 4.2A.5 Withholding of payments The Company shall not be obliged to make any Restricted Export Level Payment or Intertrip Payment pursuant to Paragraph 4.2A.4 where the tripping of BM Unit(s) or (where relevant) Generating Unit(s) comprised in a BM Unit occurs:-
during any period where the System to Generator Operational Intertripping Scheme is not instructed by The Company to be armed in accordance with Paragraphs 4.2A.2.2(a) and 4.2A.2.2(d); and/or
where the User has failed to arm, or permit the arming of, the System to Generator Operational Intertripping Scheme in accordance with the terms of Paragraph 4.2A.2.1(b); and/or
where the User has failed to exercise Good Industry Practice to restrict the export of Active Power from the Connection Site to the Restricted MW Export Level as required by Paragraph 4.2A.2.1(c) (ignoring any export above Restricted MW Export Level where pursuant to an instruction from The Company to provide any Balancing Service(s)); and/or
where no signal is received by the Circuit Breaker(s) from the System to Generator Operational Intertripping Scheme. 4.2A.6 Revisions to Appendix F3 of the Bilateral Agreement Where The Company requires Routine Change(s) (as defined below) to be made to Appendix F3 of the Bilateral Agreement, then the User shall not unreasonably withhold or delay providing to The Company written consent to any such Routine Changes and hereby authorises The Company, following receipt of such written consent, to make amendments on its behalf to Appendix F3 of the Bilateral Agreement to reflect such Routine Change(s) and undertakes not to withdraw qualify or revoke such authority or instruction at any time. For the purposes of this Paragraph 4.2A.6, “Routine Change(s)” shall mean changes to the nomenclature of transmission circuits associated with a System to Generator Operational Intertripping Scheme specified in Appendix F3 of the relevant Bilateral Agreement which do not necessitate replacement, renovation, modification, alteration or construction to the User’s Plant or Apparatus. 4.2A.7 No payments for Category 1 Intertripping Schemes For the avoidance of doubt, no payment shall be made by The Company hereunder in respect of a Category 1 Intertripping Scheme. 4.2A.8 Disclosure and Use of Information Each User hereby consents to the disclosure and use by The Company of data and other information from any year relating to the provision by that User of the Balancing Service to the extent necessary to enable The Company to carry out its EMR Functions. 4.2B OTHER BALANCING SERVICES 4.2B.1 Application The provisions of this Paragraph 4.2B shall apply to The Company and a User or other person in respect of the provision by that User or other person to The Company of Balancing Services other than Mandatory Ancillary Services, Maximum Generation and System to Generator Operational Intertripping. 4.2B.2 Form of Agreement Any agreement between The Company and a User or other person in respect of the provision by that User or other person to The Company of Balancing Services other than Mandatory Ancillary Services, Maximum Generation and System to Generator Operational Intertripping shall be in a form to be agreed between them (but, in respect of Commercial Services Agreements, subject always to Paragraph 4.2B.3 where applicable). 4.2B.3 Agreed Ancillary Services Each User and The Company shall enter into a Commercial Services Agreement providing for the payment for and provision of the Agreed Ancillary Services (other than Maximum Generation) and System to Generator Operational Intertripping) (if any) set out in Appendix F1 of the relevant Bilateral Agreement. If, after a period which appears to The Company to be reasonable for the purpose, The Company has failed to enter into a Commercial Services Agreement with such User, The Company shall be entitled to initiate the procedure for resolution of the issue as an Other Dispute in accordance with Paragraph 7.4 to settle the terms of the said Commercial Services Agreement. 4.2B.4 Disclosure and Use of Information Each User or other person who provides Balancing Services to The Company hereby consents to the disclosure and use by The Company of data and other information from any year relating to the provision by that User or other person of the Balancing Service to the extent necessary to enable The Company to carry out its EMR Functions. 4.2B.5 EBR Article 18 Where and to the extent that:-
contractual arrangements for the provision of and payment for Balancing Services which are not set out in CUSC contain EBR Article 18 Terms and Conditions; and
an EBR Amendment to such contractual arrangements is proposed which under the Electricity Balancing Regulation is subject to consultation and prior approval by the Authority, then, to the extent and from such date as is required by the Electricity Balancing Regulation, such EBR Amendment shall be effective only after appropriate consultation and prior approval by the Authority. Accordingly, The Company shall ensure that the amendment processes contained within such contractual arrangements provide for appropriate consultation and prior approval by the Authority before any EBR Amendment becomes effective.
Application The provisions of this Paragraph 4.3 shall apply to payments made by The Company to a User (and by a User to The Company) pursuant to:-
Mandatory Services Agreements in respect of the provision of Mandatory Ancillary Services; and/or 4.3.1.2 (save as provided in Paragraphs 4.2.5.3 to 4.2.5.5 (inclusive)) Maximum Generation Service Agreements in respect of the provision of Maximum Generation; and/or 4.3.1.3 Paragraph 4.2A.4 in respect of the provision of System to Generator Operational Intertripping, and (if agreed between The Company and a User) may also be incorporated by reference into a Balancing Services Agreement as a term thereof so as to apply in respect of the provision of other Balancing Services (but for the avoidance of doubt not so as to thereby create any obligations on The Company and that User under the CUSC in respect thereof).
Payment Procedure
On the third Business Day following receipt from the Settlement Administration Agent of the Interim Information Settlement Run issued in respect of the final day of the previous calendar month The Company shall send to the User a statement ("Provisional Monthly Statement") consisting of:-
a statement ("Provisional Statement") incorporating:-
detailed daily technical reports of all Balancing Services supplied by the User pursuant to the relevant Balancing Services Agreement during the previous calendar month;
a summary of each Balancing Service so supplied; and
if relevant a statement showing adjustments to be made (net of interest) in relation to disputes for Balancing Services concerning any month prior to the previous month ("Provisional Adjustments Statement"), in each case showing the payments due to or from the User as a result thereof.
If the User has failed to supply any Balancing Service in accordance with the Grid Code or any instructions validly and properly issued under the Grid Code or as required by the CUSC or any Balancing Services Agreement, The Company shall set out the times and dates upon which it considers such failure of supply to have occurred and the facts or evidence which it relies upon as constituting such failure in the Provisional Monthly Statement next following the date of such failure or next following the date when The Company first becomes aware of the facts which constitute such failure.
If the User disagrees with any dates, times, facts or calculations set out in the Provisional Statement and/or the Provisional Adjustments Statement, it shall state by notice in writing to The Company the reasons and facts which it relies upon in support of such disagreement. The parties shall discuss and endeavour to resolve the matter prior to The Company sending out the Final Monthly Statement. If they reach agreement The Company shall set out in the Final Monthly Statement the adjustments required but if it cannot be resolved the dates times facts and calculations set out in the Provisional Statement and in the Provisional Adjustments Statement shall be binding upon the parties until such time as they are reversed or revised by agreement between the parties or otherwise (in accordance with Paragraph 4.3.2.8) pursuant to the Dispute Resolution Procedure.
Notwithstanding the provisions of Paragraphs 4.3.2.2 and 4.3.2.3, if any fact or matter set out in the Provisional Statement and/or in the Provisional Adjustments Statement shall be inconsistent with any fact or matter set out in a final run (if any) of the settlement calculation issued by the Settlement Administration Agent, or any change to a previous final run (if any) of a settlement calculation, the facts and matters set out in the settlement calculation or which, following a dispute and subject to Paragraph 4.3.2.5, it is found or agreed should be set out therein shall be binding upon both parties.
If either The Company or the User intends to dispute any fact or matter contained in a final run (if any) of a settlement calculation which is inconsistent with any fact or matter contained in a Provisional Statement and/or a Provisional Adjustments Statement it shall serve notice in writing on the other party to that effect in order that the other party may make such representations as it wishes to the Settlement Administration Agent or exercise such rights as it may have under the Balancing and Settlement Code in relation to such fact or matter.
On the eighteenth Business Day of each calendar month, The Company shall send to the User a statement ("Final Monthly Statement") consisting of:-
a statement ("Final Statement") incorporating:-
in the case of an undisputed Provisional Statement (or where any dispute has been resolved and no changes have been effected to the calculations contained in the Provisional Statement) a further monthly summary of the Balancing Services provided together with an invoice for the amount shown as being due to the User or The Company (as the case may be); or
in the case of a disputed Provisional Statement such that changes are required as a result thereof, a further copy of the detailed daily technical reports referred to at Paragraph 4.3.2.1(a)(i), a revised monthly summary of the Balancing Services provided and an invoice for the amount shown as being due to the User or The Company (as the case may be); and
if a Provisional Adjustments Statement has been issued in accordance with Paragraph 4.3.2.1(b), a statement ("Final Adjustments Statement") showing adjustments to be made in relation to disputes for Balancing Services concerning any month prior to the previous month together with interest thereon up to and including the date of payment referred to in Paragraph 4.3.2.10. Such adjustments will be reflected in the invoice referred to at Paragraph 4.3.2.6(a)(i) above.
Where:-
either The Company or the User discovers that any previous Provisional Monthly Statement or Final Monthly Statement contains an arithmetic error or omission; or
any change is made to a previous final run (if any) of a settlement calculation which includes a change in any of the facts or matters upon which the final settlement run was based which facts or matters formed the basis upon which any previous Provisional Monthly Statement or Final Monthly Statement was prepared; or
either The Company or the User becomes aware of any facts concerning matters provided by this Paragraph 4.3 (other than facts falling within Paragraphs 4.3.2.7(a) and (b)) which show that the payment made by or to the User was incorrect; or
the User establishes to The Company’s reasonable satisfaction that it was entitled to receive any additional payment; then The Company and the User shall agree an adjustment to the account between The Company and the User which adjustment shall be reflected in the next Provisional Adjustments Statement which The Company issues, and the provisions of Paragraphs 4.3.2.3 to 4.3.2.5 shall apply mutatis mutandis to such adjustments. Failing agreement as to the amount of any such adjustment, The Company or the User may refer the matter to an expert for determination (if both of them agree) or otherwise may initiate the procedure for resolution of the issue as an Other Dispute in accordance with Paragraph 7.4.
Where a dispute is resolved by issuance of a decision by an expert or an arbitrator or panel of arbitrators pursuant to the Dispute Resolution Procedure, The Company shall adjust the account between itself and the User accordingly in the next Provisional Adjustments Statement required to be issued under Paragraph 4.3.2.1. If such decision of an expert or an arbitrator or panel of arbitrators is subsequently reversed or modified by a final judicial decision after exhaustion of all appeals if this opportunity is taken, The Company shall adjust the account between itself and the User accordingly in the next Provisional Adjustments Statement which it issues.
Subject to Paragraph 4.3.2.13, the due date of payment for the purposes of Paragraph 4.3.2.12 in respect of any disputed amount subsequently determined or agreed to be payable to the User or to The Company shall be the date for payment of the relevant Provisional Statement from which the dispute arises.
The Company shall pay to the User the amount shown as due from The Company in the Final Monthly Statement within three Business Days of the date on which such statement is or should be issued. The User shall pay to The Company the amount shown as due from the User in such statement within three Business Days of the date on which such statement is issued.
If either party ("Defaulting Party"), in good faith and/or with reasonable cause fails to pay under Paragraph 4.3.2.10 any amount properly due in respect of Balancing Services under the CUSC and the relevant Balancing Services Agreement, then such Defaulting Party shall pay to the other party interest on such overdue amount from and including the due date of such payment to (but excluding) the date of actual payment (as well after as before judgment or determination by an arbitrator or panel of arbitrators) at the Base Rate. Provided that should the Defaulting Party otherwise fail to pay any amount properly due under the CUSC and the relevant Balancing Services Agreement on the due date then the Defaulting Party shall pay to the other party interest on such overdue amount at the Enhanced Rate from the due date on which such payment was properly due to (but excluding) the date of actual payment. Any interest shall accrue from day to day.
If following a dispute or by virtue of Paragraphs 4.3.2.2, 4.3.2.3, 4.3.2.4, 4.3.2.7 or 4.3.2.8 it is determined or agreed that the User was entitled to a further payment from The Company, the User shall be entitled to interest at the Base Rate on the amount of such further payment from the due date calculated in accordance with Paragraph 4.3.2.9 until the date of payment.
If following a dispute or by virtue of the provisions of Paragraphs 4.3.2.2, 4.3.2.3, 4.3.2.4, 4.3.2.7 or 4.3.2.8 it is determined or agreed that The Company or the User was not entitled to any payment it has received, the other party shall be entitled to interest at the Base Rate on the amount so paid from the date of payment until the date of repayment or the date when The Company makes a payment to the User which takes such payment into account.
Notwithstanding any other provision of the CUSC and any Balancing Services Agreement, The Company and a User shall not be limited in any way as to the evidence they may rely upon in any proceedings arising out of or in connection with payment for any Balancing Service under the CUSC and the relevant Balancing Services Agreement and the parties agree that in the event and to the extent that either party succeeds in proving in any such proceedings that any Balancing Service was or was not provided, the successful party shall (without prejudice to any liquidated damages provision of the CUSC and/or the relevant Balancing Services Agreement) be entitled to repayment of the sums already paid or payment of sums not paid as the case may be in respect of such Balancing Service.
Save as otherwise expressly provided in the CUSC or in any Balancing Services Agreement, sums payable by The Company or a User to the other in respect of Balancing Services pursuant to the CUSC or any Balancing Services Agreement whether by way of charges, interest or otherwise shall (except to the extent otherwise required by law) be paid in full, free and clear of and without deduction, set-off or deferment in respect of any disputes or claims whatsoever save for sums the subject of a final award or judgement (after exhaustion of all appeals if this opportunity is taken) or which by agreement between The Company and the relevant User may be so deducted or set off.
The Company represents and warrants to each relevant User, as between The Company and that User, that it enters into each Balancing Services Agreement as principal and not as agent for any other person.
All amounts specified hereunder shall be exclusive of any Value Added Tax or other similar tax and The Company shall pay to the User Value Added Tax at the rate for the time being and from time to time properly chargeable in respect of the making available and/or supply of Balancing Services under the CUSC, the relevant Balancing Services Agreement, the Grid Code, or any Bilateral Agreement.
All payments by The Company to the User (or by the User to The Company) in respect of the provision of Balancing Services will be made by payment to the parties’ bank accounts details of which may be set out in the relevant Balancing Services Agreement or otherwise notified by The Company to the User (or by the User to The Company) from time to time.
The submission of all Provisional Monthly Statements and all Final Monthly Statements and facts and other evidence in support thereof and any questions in connection therewith from The Company to the User and vice versa in accordance with this Paragraph 4.3.2 must be made, in the absence of agreement to the contrary between the parties, by 19.00 hours on the Business Day concerned.
For the purpose of the regulations of HM Revenue and Customs as regards self-billing of Balancing Services and the submission of Value Added Tax invoices, the User hereby consents to the operation of a self-billing system by The Company with regard to the payment for Balancing Services to be provided pursuant to the CUSC and the relevant Balancing Services Agreement and will at all times throughout the term of the relevant Balancing Services Agreement maintain such consent. The User hereby undertakes, as between The Company and that User, to do (at The Company's cost) all acts and things reasonably necessary to enable The Company to comply with the regulations of HM Customs and Excise as regards the self- billing of Balancing Services.
Payment of any sum or the submission of any Provisional Monthly Statement or Final Monthly Statement by The Company to a User under this Paragraph 4.3.2 shall not operate to impair or be construed as a waiver of any right, power, privilege or remedy The Company may have against the User under the CUSC and/or any Balancing Services Agreement and/or the Grid Code and/or any Bilateral Agreement.
For the avoidance of doubt, The Company shall issue a Provisional Monthly Statement to the User for the calendar month following the calendar month in which any Balancing Services Agreement to which the User is a party shall expire or terminate, setting out details of the Balancing Services supplied by the User in respect thereof during that calendar month until expiry or termination, and in respect thereof the provisions of this Paragraph 4.3.2 shall continue to apply notwithstanding such expiry or termination.
Application The provisions of this Paragraph 4.4 shall apply to payments made by The Company to a User pursuant to Mandatory Services Agreements in respect of the provision of the Mandatory Ancillary Service of Frequency Response, and (if agreed between The Company and a User) may also be incorporated by reference into any other Ancillary Services Agreement as a term thereof so as to apply in respect of payments made by The Company to that User in respect of the provision of other Ancillary Services (but for the avoidance of doubt not so as to thereby create any obligations on The Company and that User under the CUSC in respect thereof).
Charging Principles - General
These principles are to be used to establish the basic arrangements but are not intended to stifle innovation in the development of new services or the giving of appropriate economic signals.
Save where otherwise expressly provided in this Paragraph 4.4, the charges shall be "cost reflective" ie. based and founded upon the actual or estimated costs directly incurred or to be incurred by the User for the purpose of providing the service or capability concerned.
Where a capability to provide an Ancillary Service is required by the Grid Code from all BM Units or CCGT Units (as opposed to a capability made available by agreement between The Company and a User from some only of the User’s BM Units or CCGT Units), no Ancillary Service capability payment shall be made.
The cost of "Grandfathering" User's Equipment (i.e. bringing equipment owned by the User on 30th March 1990 to a condition of compliance with the Grid Code) shall not be included in Ancillary Services payments. Where a Derogation is withdrawn or reduced in scope then, except in relation to Frequency Response, the User shall be entitled to take the cost of meeting the withdrawal or reduction in the scope of the Derogation into account in its charges.
Subject to the other provisions of this Paragraph 4.4.2, the charges shall take due account of any change in or amendments to the Grid Code or any other statutory or regulatory obligation coming into force after 30th March 1990 affecting the provision of Ancillary Services.
If as a result of any changes to the Balancing and Settlement Code the User ceases to be entitled to receive payment under the Balancing and Settlement Code in respect of any elements of Ancillary Services provided by it which are expressed in this Paragraph 4.4 to be paid for under the Balancing and Settlement Code, the User shall be entitled to charge for such elements under an Ancillary Services Agreement. Where, however, such change entitles the User to be paid for any elements of Ancillary Services which are expressed in this Paragraph 4.4 to be paid for under an Ancillary Services Agreement the User shall cease to be entitled to charge for such elements under an Ancillary Services Agreement.
Charging Principles – Frequency Response Holding Payments shall be determined in accordance with Paragraph 4.1.3.13 and, as specified in Paragraph 4.1.3.13(g), therefore need not be cost reflective.
Part-loading of a BM Unit at a level other than that specified in a Physical Notification in order to provide Frequency Response will normally be achieved by the issue of a Bid- Offer Acceptance.
In recognition of the energy production costs likely to be incurred or avoided when providing Frequency Response, an additional amount based upon an expected delivery of Frequency Response energy shall be payable under Paragraph 4.1.3.9A.
Application The provisions of this Paragraph 4.5 shall apply to payments made by The Company to a User pursuant to Paragraphs 4.2A.4(a) and (c) in respect of the provision of System to Generator Operational Intertripping, and (if agreed between The Company and a User) may be incorporated by reference into any other Balancing Services Agreement (other than a Mandatory Services Agreement) as a term thereof so as to apply in respect of payments made by The Company to that User in respect of the provision of other Balancing Services (other than Mandatory Ancillary Services) (but for the avoidance of doubt not so as to thereby create any obligations on The Company and that User under the CUSC in respect thereof).
Indexation provisions
The rates and/or prices to be indexed shall be specified in the Balancing Services Agreement or (in the case of System to Generator Operational Intertripping) in Schedule 4 to this Section 4 as applicable for a 12 month period commencing 1st April (“the base year”), and these rates and/or prices will be adjusted annually to take account of general price inflation. The index used will be the Retail Prices Index (RPI) with 1987 = 100 base.
The source of the RPI index is to be the monthly Office for National Statistics “Business Monitor MM23.”
The rates and/or prices to be indexed shall be increased (or reduced as appropriate) for the subsequent 12 month period commencing 1st April by the following factor:- RPI RPI Where RPI is the RPI for March immediately prior to commencement of that 12 month period RPI is the RPI for March immediately prior to commencement of the base year.
In subsequent years indexation will continue in accordance with the above, with always the numerator of the factor representing the RPI of the 12 month period in question and the denominator of the factor being the RPI for March immediately prior to the base year.
In the event that RPI ceases to be published or is not published in respect of any relevant month or it is not practicable to use RPI because of a change in the method of compilation or some other reason, indexation for the purposes of this Paragraph 4.5 shall be calculated by The Company using an index agreed between The Company and the relevant User with a view to determining the relevant price after indexation that would be closest to the relevant price after indexation if RPI had continued to be available. If The Company and a relevant User are unable to agree a suitable index, either of them may initiate the Dispute Resolution Procedure for resolution of the issue as an Other Dispute in accordance with Paragraph 7.4.
For the avoidance of doubt, the provisions of Paragraph 11.3 with regard to determination of an alternative index should the Retail Prices Index not be published or there is a material change to the basis of such index shall not apply with respect to the rates and/or prices the subject of this Paragraph 4.5. SCHEDULE 1
| Operational Day (dd/mm/yy) | Maximum Generation BM Unit | Indicative Maximum Generation Capability | Available? (YES/NO) |
|---|
| OPERATIONAL DAY (dd/mm/yy) | Maximum Generation BM Unit | Indicative Maximum Generation Capability | Available (YES/NO) |
|---|
| Category of Intertrip | |
|---|---|
| Connection Site | |
| Time and date of arming | |
| Restricted MW Export Level (MW) post trip | |
| Special instructions (if any) | |
| Reason(s) for arming | |
| Relevant fault(s) | |
| Generating Unit(s)/BM Unit(s)/Intertrip Contacted Unit(s) to be armed (delete as appropriate) | |
| Connection Site | |
| Time and date of arming |
| Connection Site | |
|---|---|
| Restricted MW Export Level (MW) | |
| No longer applies | Tick if applicable |
| Has been increased to (MW) |
| Category 1 | Category 2 | Category 3 | Category 4 | |
|---|---|---|---|---|
| Capability Payment (£/Settlement Period) | N/A | £ 1.72 | N/A | £ 1.72 |
| Intertrip Payment (£/Intertrip Contracted Unit/Trip) | N/A | £ 400,000 | N/A | £ 400,000 |
SECTION 5: EVENTS OF DEFAULT, DEENERGISATION, AND DISCONNECTION
Licensed CUSC Parties Upon either:
termination of all Bilateral Agreements, Mandatory Services Agreements and Construction Agreements entered into by a User and cessation of any other right to use the National Electricity Transmission System pursuant to Paragraph 3.8 or Paragraph 9.23; or
a User having a Licence but not yet being connected to or otherwise using the National Electricity Transmission System, until such time as the User accepts an Offer to connect to or use the National Electricity Transmission System, a User with a Licence shall be or continue to be a CUSC Party but shall not (except in the case of Paragraph 5.1.5) have any further rights and obligations for the period of such dormancy under the CUSC (and shall be a “Dormant CUSC Party”) until the execution (or other entering into) of a Bilateral Agreement or commencement / recommencement of its right to use the National Electricity Transmission System pursuant to the CUSC. Termination or expiry of a particular Bilateral Agreement, Mandatory Services Agreement or Construction Agreement shall not, of itself, cause the relevant User to become a Dormant CUSC Party.
A Dormant CUSC Party may once it ceases to have a Licence which requires it to be a party to the CUSC Framework Agreement, by prior notice to The Company cease to be a CUSC Party from the date specified in such notice, on which date it shall cease to be a party to the CUSC Framework Agreement.
Non-Licensed CUSC Parties Upon termination of all Bilateral Agreements, Mandatory Services Agreements and Construction Agreements entered into by a User and cessation of any other right to use the National Electricity Transmission System pursuant to 2 Paragraph 3.8 or Paragraph 9.23, a User without a Licence shall cease to be a CUSC Party from the date of cessation of the last such agreement or right to use, and shall on that date cease to be a party to the CUSC Framework Agreement.
A person ceasing to be a CUSC Party or becoming a Dormant CUSC Party shall not affect any rights or obligations of any CUSC Party which may have accrued to the date of termination or dormancy under the CUSC, any Bilateral Agreement or Mandatory Services Agreement or Construction Agreement or the Charging Statements or otherwise and shall not affect any continuing obligations of any other CUSC Party under the CUSC.
Embedded Exemptable Large Power Station and Virtual Lead Parties A User in respect of an Embedded Exemptable Large Power Station or Virtual Lead Party shall (unless The Company agrees otherwise in writing, such agreement not to be unreasonably withheld or delayed), once it has acceded to the CUSC Framework Agreement continue to remain a CUSC Party and shall not be treated as a Dormant CUSC Party notwithstanding the provisions of Paragraph 5.1.1.
Emergency Deenergisation by The Company If, in the reasonable opinion of The Company, the condition or manner of operation of the National Electricity Transmission System or a User's System or an Interconnector poses an immediate threat of injury or material damage to any person or to the Total System or to any User's System or to the National Electricity Transmission System, The Company shall have the right to:
Deenergise that User's Equipment, or
request the owner of the Distribution System to which that User’s Equipment or equipment for which that User is responsible (as defined in Section K of the Balancing and Settlement Code) is connected to Deenergise that User’s Equipment or equipment for which that User is responsible (as defined in Section K of the Balancing and Settlement Code), 3 if it is necessary or expedient to do so to avoid the occurrence of such injury or damage.
Emergency Deenergisation by a User If, in the reasonable opinion of a User, the condition or manner of operation of the National Electricity Transmission System, the Total System or any other User's System poses an immediate threat of injury or material damage to any person or to its User's System or User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) that User shall have the right to Deenergise its User's Equipment or equipment for which that User is responsible (as defined in Section K of the Balancing and Settlement Code), if it is necessary or expedient to do so to avoid the occurrence of such injury or damage.
Post Emergency Reenergisation The Company or, as the case may be, the User shall Reenergise the User's Equipment at the Connection Site (or, in the case of the User the site of connection) or The Company shall request the owner/operator of the Distribution System to which the User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) is connected to Reenergise the User’s Equipment at the site of connection, in each case as quickly as practicable after the circumstances leading to any Deenergisation under this Paragraph 5.2 have ceased to exist.
Generic Events of Default It shall be an Event of Default if:-
a User shall fail to pay (other than by inadvertent error in funds transmission which is discovered by The Company, notified to that User and corrected within 2 Business Days thereafter) any amount properly due or owing from that User to The Company pursuant to the CUSC or any Bilateral Agreement and such failure continues unremedied for 7 Business Days after the due date for payment; or
in respect of a User:-
an order of the High Court in England and Wales or an order of the Court of Session in Scotland is made or an effective resolution passed for its insolvent winding up or dissolution; or 4
a receiver (which expression shall include an administrative receiver within the meaning of section 251 Insolvency Act 1986) of the whole or any material part of its assets or undertaking is appointed; or
an administration order under section 8 of the Insolvency Act 1986 is made or if a voluntary arrangement is proposed under section 1 of that Act; or
a User enters into any scheme of arrangement (other than for the purpose of reconstruction or amalgamation upon terms and within such period as may previously have been approved in writing by the Authority); or
any of the events referred to in (i) to (iv) above has occurred and is continuing and a User is unable to pay its debts (within the meaning of section 123(l) or (2) of the Insolvency Act 1986 save that such sections shall have effect as if for £750 there was inserted £250,000 and a User shall not be deemed to be unable to pay its debts if any demand for payment is being contested in good faith by that User with recourse to all appropriate measures and procedures), and in any such case within 28 days of his appointment the liquidator, receiver, administrative receiver, administrator, nominee or other similar officer has not provided to The Company a guarantee of future performance by the User of the CUSC and all Bilateral Agreements, Construction Agreements and Mandatory Services Agreements to which the User is a party in such form and amount as The Company may reasonably require.
Generic Deenergisation upon an Event of Default Provided that at the time the failure specified in Paragraph 5.3.1(a) is still continuing or the circumstances referred to in Paragraph 5.3.1(b) still exist The Company may having given 48 hours notice of an Event of Default Deenergise all of the User's Equipment which is the subject of a Bilateral Agreement with that User or may as appropriate instruct the operator of a Distribution System to Deenergise such User's Equipment or in the case of an Interconnector User or Interconnector Error Administrator request the relevant Interconnector Owner to cease or procure the cessation of the transport of power across the Interconnector by or on behalf of that User provided that prior to Deenergisation the User may refer the matter to the Dispute Resolution Procedure.
BSC Deenergisation 5 The Company shall Deenergise the User's Equipment if it is so instructed by the BSC Panel at any time in accordance with the provisions of the Balancing and Settlement Code.
Generic Disconnection If the Event of Default under Paragraph 5.3.2 or 5.3.3 is still continuing six months after the later of Deenergisation and the conclusion of the Dispute Resolution Procedure in favour of The Company, The Company may Disconnect all that User's Equipment at each Connection Site where that User's Equipment is connected and:-
the User shall remove any of the User's Equipment:
in the case of Connection Sites Onshore on the Relevant Transmission Licensee's land within 6 months or such longer period as may be agreed between the User and the Relevant Transmission Licensee; or
in the case of Connection Sites Offshore, on or adjacent to the Relevant Transmission Licensee’s Offshore Platform within a period agreed between the User and the Relevant Transmission Licensee.
in the case of
Connection Sites Onshore The Company shall procure that the Relevant Transmission Licensee removes, any of the Transmission Connection Assets on the User’s land within 6 months or such longer period as may be agreed between the User and the Relevant Transmission Licensee; or
Connection Sites Offshore, The Company shall procure that the Relevant Transmission Licensee removes, any of the Transmission Connection Assets on or adjacent to the User’s Offshore Platform within a period agreed between the User and the Relevant Transmission Licensee;
the User shall pay to The Company forthwith all Termination Amounts and, in the case of a User in the category of a Power Station directly connected to the National Electricity Transmission System or with a Bilateral Embedded Generation Agreement the Cancellation Charge;and
the User if unlicensed shall cease to be a CUSC Party or if licensed shall become a Dormant CUSC Party, as the case may be, and Paragraph 5.1 shall apply.
Site Specific Breach by the User If a User shall be in breach of any of the provisions of the relevant Bilateral Agreement, or the provision of the CUSC in relation to that particular connection to and/or use of the National Electricity Transmission System, or (other than in relation to a Supplier, a Small Power Station Trading Party, an Interconnector User or an Interconnector Error Administrator) of the provisions of the CUSC enforcing the provisions of the Grid Code (but subject always to Paragraphs 6.3.3 and 6.3.4), and such breach causes or can reasonably be expected to cause a material adverse effect on the business or condition of The Company, a Relevant Transmission Licensee or other Users or the National Electricity Transmission System or any User Systems then The Company may:-
where the breach is capable of remedy, give written notice to the User specifying in reasonable detail the nature of the breach and requiring the User within 28 days after receipt of such notice, or within any longer period agreed between The Company and the User to remedy the breach, the agreement of The Company not to be unreasonably withheld or delayed; or
where the breach is incapable of remedy, give written notice to the User specifying in reasonable detail the nature of the breach and the reasons why the breach is incapable of remedy and requiring the User within 5 Business Days after receipt of such notice to undertake to The Company not to repeat the breach.
Grid Code Procedures - Future Compliance Whenever The Company serves a notice on a User pursuant to Paragraph 5.4.1, The Company and the User shall discuss in good faith and without delay the nature of the breach and each shall use all appropriate procedures available to it under the Grid Code (including testing rights and the procedures set out in OC5 (Testing and Monitoring)) in an attempt to establish as quickly as reasonably practicable a mutually acceptable way of ensuring future compliance by the User with the relevant provision of the Grid Code.
Site Specific Deenergisation
If:
a User fails to comply with any valid notice served on it by The Company in accordance with 7 Paragraph 5.4.1(a) or is in breach of any undertaking given in accordance with Paragraph 5.4.1(b) and such breach causes or can be reasonably expected to cause a material adverse effect on the business or condition of The Company, a Relevant Transmission Licensee or other Users of the National Electricity Transmission System or any User System; or
five Business Days have elapsed since the date of any valid notice served on the User in accordance with Paragraph 5.4.1(b) and no undertaking is given by the User in accordance with Paragraph 5.4.1(b); The Company may:
provided The Company has first complied with OC5 Monitoring and Testing if appropriate Deenergise the User's Equipment; or
provided The Company has first complied with OC5 Monitoring and Testing if appropriate request the owner/operator of the Distribution System to which the User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) is or to which the User’s Customers are connected to Deenergise the User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) at the relevant site of connection or such User’s Customers (as the case may be); or
in the case of an Interconnector User or Interconnector Error Administrator request the relevant Interconnector Owner to cease or procure the cessation of the transport of power by or on behalf of that User across the Interconnector, upon the expiry of at least 48 hours prior written notice to the User, provided that at the time of expiry of such notice the breach concerned remains unremedied and that neither party has referred the matter to the Dispute Resolution Procedure. In such event The Company may:
Deenergise the User’s Equipment, or
request the owner of the Distribution System to which the User’s Equipment or equipment for 8 which the User is responsible (as defined in Section K of the Balancing and Settlement Code) is or to which the User's Customers are connected to Deenergise the User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) at the relevant site of connection or the User’s Customers (as the case may be), or
in the case of an Interconnector User or Interconnector Error Administrator request the relevant Interconnector Owner to cease or to procure the cessation of the transfer of power by or on behalf of that User across the Interconnector, forthwith following completion of the Dispute Resolution Procedure and final determination of the dispute in The Company's favour, subject to The Company having given, in the case of Deenergisation of an Embedded Small Power Station, the relevant User not less than 24 hours prior written notice and at the expiry of such notice the breach concerned remaining unremedied.
If the User fails to comply with the Grid Code (but subject always to Paragraphs 6.3.3 and 6.3.4 of the CUSC) and the Authority makes a final order or a confirmed provisional order as set out in sections 25 and 26 of the Act against the User in respect of such non-compliance which order the User breaches The Company may in respect of the relevant Connection Site(s) or site(s) of connection:
Deenergise the User's Equipment, or
request the owner of the Distribution System to which the User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) is connected to Deenergise the User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code), upon the expiry of at least 48 hours prior written notice to the User provided that at the time of expiry of the notice the User continues to fail to comply with the order.
Consequence on Transmission Licence and/or the ESO Licence If a breach of the nature referred to in Paragraph 5.4.1 continues to the extent that it places or seriously threatens to place in the immediate future The Company in breach of the ESO Licence and\or places or seriously threatens to place in the immediate future any Relevant Transmission Licensee in breach of its transmission licence The Company may:
Deenergise the User's Equipment, at the relevant Connection Site,
request the owner of the Distribution System to which the User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) is or to which the User’s Customers are connected to Deenergise the User’s Equipment or equipment for which User is responsible (as defined in Section K of the Balancing and Settlement Code) at the relevant site of connection or such User’s Customer (as the case may be), or
request the relevant Interconnector Owner to cease or procure the cessation of the transport of power by or on behalf of that User across the Interconnector, upon the expiry of at least 12 hours, prior written notice to the User, provided that at the time of expiry of such notice the breach concerned remains unremedied.
Generic and Site Specific Reenergisation Disputes
If following any Deenergisation or cessation of use of an Interconnector pursuant to this Paragraph 5.4 or Paragraph 5.3.2 the relevant User applies to The Company for the User's Equipment to be Reenergised or for The Company to issue instructions that the User’s Customers be Re-energised or for The Company to issue instructions to the owner/operator of the Distribution System to which the User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) is connected that it be Re-energised or to the relevant Interconnector Owner that transport of power across the Interconnector can restart, The Company shall notify its consent to the User's Equipment being Re-energised or transport across the Interconnector restarting forthwith upon the breach of the CUSC or the relevant Bilateral Agreement which give rise to the De-energisation either:-
being remedied; or 10
ceasing to be material; or
in the case of a De-energisation under 5.4.3 ceasing to be of a nature which can reasonably be expected to cause a material adverse effect on the business or condition of The Company, a Relevant Transmission Licensee or other Users of the National Electricity Transmission System; or
in the case of a De-energisation under Paragraph 5.4.4 ceasing in The Company’s opinion to place or seriously threaten to place in the immediate future The Company in material breach of the ESO Licence and\or places or seriously threatens to place in the immediate future any Relevant Transmission Licensee in material breach of its transmission licence, and shall forthwith Re-energise the User’s Equipment or issue instructions.
If The Company shall refuse to Re-energise the Users Equipment or to issue instructions that the User’s Customers be Reenergised or to issue instructions to the owner/operator of the Distribution System to which the User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) is connected that it be Reenergised, or to the relevant Interconnector Owner that transport of power can restart, or if the User is offered terms by The Company which the User does not accept, this shall be recognised as a dispute over the terms for connection and use of system which may be referred by the User to the Authority for determination under condition E13 of the ESO Licence. If the User accepts any terms offered by The Company or determined by the Authority The Company shall Reenergise the Users Equipment, or request the owner of the Distribution System to which either the User’s Customers or the User’s Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) is/are connected to Reenergise the same or the relevant Interconnector Owner to restart that transport of power, forthwith after any request from the User for The Company to do so.
Specific Events of Default Events of Default
Any of the following events shall constitute an Event of Default:
If the breach which led to any Deenergisation pursuant to this Paragraph 5.4 remains unremedied at the expiry of at least 6 months after the date of such Deenergisation, The Company may declare by notice in writing to the User that such breach has become an Event of Default provided that:
all disputes arising out of the subject-matter of this Paragraph 5.4 which are referred to the Dispute Resolution Procedure have been finally determined in favour of The Company; and
any reference to the Authority pursuant to Paragraph 5.4.5(b) hereof has then been finally determined in favour of The Company or any terms settled pursuant to such procedure have not been accepted by the User.
If any or all of the Events of Default in Paragraph 5.3.1 has or have occurred. Security Event of Default - User Meets The Company Credit Rating
In the case where a User meets The Company Credit Rating on signing a Bilateral Connection Agreement any of the following events shall constitute an Event of Default:-
If the User fails to provide or procure that there is provided to The Company within the requisite time any relevant security satisfactory to The Company pursuant to Part III of Section 2 or Paragraph 5.4.6.2(c) or Section 14 of the CUSC.
If having provided security satisfactory to The Company pursuant to Part III of Section 2 and Paragraph 5.4.6.2(c) or Section 14 of the CUSC:
the User or any shareholder (whether direct or indirect) of the User or any other party who may at any time be providing security to The Company pursuant to the requirements of the CUSC (or the relevant Bilateral Connection Agreement) takes any action whether by way of proceedings or 12 otherwise designed or calculated to prevent, restrict or interfere with the payment to The Company of any amount so secured whether or not there shall be a dispute between the parties;
any party who may at any time be providing security to The Company pursuant to the provisions of the CUSC (or the relevant Bilateral Connection Agreement) fails to pay to The Company any sum demanded pursuant thereto.
(i) There is a material adverse change in the financial condition of the User such as to give The Company reasonable grounds for concluding that there is a substantial probability that the User will default in the payment of any sums due or to become due to The Company within the next following period of 12 months, in terms of or on termination of the relevant Bilateral Connection Agreements; or
an event of default has occurred under any banking arrangements (as may be more particularly described in the relevant Bilateral Connection Agreement) (an event of default being for these purposes anything defined as such in such banking arrangements) put in place by the User in connection with a project for which security under this CUSC is required by The Company and as a result the banks who are party to such banking arrangement have taken steps to declare the principal of the advances under such arrangement immediately due and payable; or
any other indebtedness of the User for the repayment of borrowed money (in a principal outstanding amount of not less than £1,000,000 (pounds sterling one million) or such greater figure specified in any Bilateral Connection Agreement) has become due and payable prior to the stated date of maturity thereof by reason of any default 13 or breach on the part of the User and the amount in question has not been paid by the User or re-financed by the User within a period of 28 days following the date upon which it was so declared due and payable, and in any of (i) or (ii) or (iii) the User fails, within a period of 7 (seven) days following the date on which The Company gives the User notice in writing of one or other of the above events occurring to provide The Company with such security as The Company shall require to cover the User's payment obligations to The Company arising in the event of or which have arisen prior to termination of the relevant Bilateral Connection Agreement and which arise under the CUSC. The security to be provided shall be in a form satisfactory to The Company in accordance with its then current policy and procedures and in such amount as The Company shall specify to the User in the aforesaid notice. Provided that (in relation to Paragraphs (i) or (ii) or (iii) above) if at any time after the putting in place of security under this Paragraph the User shall produce to The Company evidence to The Company's reasonable satisfaction that there is not a substantial probability of the User not being able to make payment to The Company of such sums within the next following period of twelve (12) months, The Company shall not require the User to provide the aforesaid security and shall release any such security then in place. This waiver is without prejudice to The Company's right to require security at any time thereafter in the event of any of the circumstances set out in Paragraph (i) and/or (ii) and/or
subsequently occurring. Security Event of Default - User Does Not Meet The Company Credit Rating
In the case where a User does not meet The Company Credit Rating on signing a Bilateral Connection Agreement any of the following events shall constitute an Event of Default:-
(i) There is a material adverse change in the financial condition of the User such as to give The Company reasonable grounds for concluding that there is a substantial probability that the User will default in the payment of any unsecured sums due or to become due to The 14 Company within the next period of 12 months, in terms of or on termination of the relevant Bilateral Connection Agreements; or
an event of default has occurred under any banking arrangements (as may be more particularly described in the relevant Bilateral Connection Agreement), (an event of default being for these purposes anything defined as such in such banking arrangements) put in place by the User in connection with a project for which security under this CUSC is required by The Company and as a result the banks who are party to such banking arrangement have taken steps to declare the principal of the advances under such arrangement immediately due and payable; or
any other indebtedness of the User for the repayment of borrowed money (in a principal outstanding amount of not less than £1,000,000 (pounds sterling one million) or such greater amount specified in any Bilateral Connection Agreement) has become due and payable prior to the stated date of maturity thereof by reason of any default or breach on the part of the User and the amount in question has not been paid by the User or refinanced by the User within a period of 28 days following the date upon which it was so declared due and payable. And in any one of (i) or (ii) or (iii) the User fails:-
within a period of 14 (fourteen) days following the date on which The Company gives notice of such circumstances to provide to The Company a cash deposit in a Bank Account, a Performance Bond or a Letter of Credit in favour of The Company and Valid at least up to the last day of the Financial Year in which the event occurs for such amount representing The Company's reasonable estimate of all unsecured 15 sums to become due to The Company in the period up to the end of the Financial Year in which the event occurs such sum to be specified in the said notice; or
to subsequently provide such cash deposit or renew such Performance Bond or Letter of Credit (or such renewed Performance Bond or Letter of Credit provided under this paragraph) not less than 45 days prior to its stated expiry date for such amount representing The Company's reasonable estimate of the unsecured sums to become due to The Company in the next following Financial Year valid at least up to the last day of the next following Financial Year and to continue the provision of cash deposit, a Performance Bond or Letter of Credit in a similar manner, to such estimate of unsecured sums. Provided that regarding any one of (i) or (ii) or
if at any time after the putting in place of security under this Paragraph 5.4.6.3(a) the User shall provide to The Company evidence to The Company's reasonable satisfaction that there is not a substantial probability of the User being unable to make payment to The Company of any unsecured sums within the next following period of twelve (12) months, The Company shall not require the User to provide the aforesaid security and shall release any such security then in place. This waiver is without prejudice to The Company's right to require security at any time thereafter in the event of any of the circumstances set out in paragraph (i) and/or (ii) and/or (iii) in this Paragraph 5.4.6.3(a) subsequently occurring.
If the User fails to provide or procure that there is provided to The Company or at any time fails to maintain or procure that there is maintained in full force and effect the relevant security arrangement required under Part III of Section 2 or Paragraph 5.4.6.3(a) or to renew or revise such security or to substitute any security with the required replacement security or to maintain or procure that there is maintained in full force 16 and effect any such renewed, revised or substituted security as so required or if the User is otherwise in breach of any of its obligations under Paragraph 2.22.
If the User or any shareholder (whether direct or indirect) of the User takes any action whether by way of proceedings or otherwise designed or calculated to prevent restrict or interfere with the payment to The Company of any amount so secured or seeks or permits or assists others to do so, whether or not there shall be a dispute between the parties.
If any party who may at any time be providing or holding security in favour of The Company pursuant to Part III of Section 2 or Paragraph 5.4.6.3(a) fails to pay The Company any sum demanded in any Notice of Drawing pursuant thereto.
Specific Event of Default Disconnection Once The Company has given a valid notice of an event of default pursuant to Paragraph 5.4.6 provided that the Event of Default is continuing The Company may give notice of termination to that User whereupon the relevant Bilateral Agreement or right to use the system shall terminate and:
The Company shall in relation to such an Event of Default of a User in relation to a Connection Site:
Disconnect all the User’s Equipment at the Connection Site; and
the User concerned shall remove any of the User’s Equipment:
in the case of Connection Sites Onshore within six (6) months of the date of termination or such longer period as may be agreed between the Relevant Transmission Licensee and the relevant User; or
in the case of Connection Sites Offshore, on or adjacent to the Relevant Transmission Licensee’s Offshore Platform within a period agreed between the User and the Relevant Transmission Licensee; and 17
in the case of Connection Sites Onshore, The Company shall procure that the Relevant Transmission Licensee removes, any of the Transmission Connection Assets on the land of the User concerned within 6 months or such longer period as may be agreed between the User and the Relevant Transmission Licensee; and,
in the case of Connection Sites Offshore, The Company shall procure that the Relevant Transmission Licensee removes any of the Transmission Connection Assets on or adjacent to the User’s Offshore Platform within a period agreed between the User and the Relevant Transmission Licensee. Such User shall (notwithstanding any longer time for payment which but for such termination the User may have for payment pursuant to the CUSC or the relevant Bilateral Agreement) within 14 days from the date of termination pay to The Company all amounts due and owing on the date of such termination and be liable to pay to The Company Termination Amounts applicable to the Connection Site and, in the case of a User in the category of a Power Station directly connected to the National Electricity Transmission System the Cancellation Charge, such payments to be made within 14 days of the date of The Company's invoice(s) in respect thereof;
(i) The Company shall request the owner of any Distribution System to which the User is connected to Disconnect all the User's Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) at the site of connection;
The Company shall in relation to such an event of default of a User acting as a Supplier request the owner of the Distribution System to which any of that User’s Customer’s are connected to Disconnect such User’s Customer’s;
The Company shall in relation to such an Event of Default of a User acting as an Interconnector User or Interconnector Error Administrator request the relevant Interconnector Owner to cease or procure the cessation of the transfer of power across the 18 Interconnector by or on behalf of that Interconnector User; and the User shall be obliged to pay to The Company forthwith the Use of System Charges due under the CUSC or the relevant Bilateral Agreement up to the end of the Financial Year in which Termination occurs and, in the case of a User with Bilateral Embedded Generation Agreement the Cancellation Charge.
Breaches Notwithstanding any other provisions of this Paragraph 5.5 and/or Paragraph 5.3 of the CUSC, in relation to the payment of the Balancing Services Use of System Charges the following shall constitute breaches under the CUSC and/or the relevant Bilateral Agreement:-
the User in question shall fail to provide or maintain or renew in accordance with Paragraph 3.21 or Paragraph 9.22.3 (as appropriate) the requisite amount of Security Cover; or
the User shall fail to pay any sum payable by the User in respect of Balancing Services Use of System Charges to The Company within 3 Business Days of its due date; or
an event of default under Paragraph 5.3.1(b) of the CUSC has occurred provided always that the final Paragraph of Paragraph 5.3.1(b) of the CUSC referring to the provision of guarantees shall not apply.
Events of Default Forthwith upon the occurrence of any of the breaches specified in Paragraph 5.5.1 then notwithstanding any other provisions of the CUSC or of any Bilateral Agreement to which the User is a party, and in addition to any rights it may have under the terms of the CUSC, The Company may upon reaching a bona fide conclusion that the reason for the failure by the User under Paragraph 5.5.1 is other than an administrative or banking error (having taken into account representations if any of the User made within 24 hours after the request therefor is made to the User by The Company, which request The Company shall be obliged to make) by notice to the User declare such breach an event of default.
Deenergisation by User If The Company declares an Event of Default under Paragraph 5.5.2 the User shall forthwith and in compliance with the instructions of The Company or (in the case of any connection to a User System) the owner of the User System to which the User's Customers are connected, Deenergise itself and/or its Customers or in the case of a User acting as an Interconnector User or Interconnector Error Administrator cease or procure the cessation of the transport of power by or on behalf of that User across the Interconnector as the case may be.
Deenergisation by The Company/User System Owner If the User shall fail to take such action as is referred to in Paragraph 5.5.3 within 48 hours after the date of any such notice referred to therein The Company shall be entitled to:-
request the owner of the User System to which the User's Customers and/or the User are connected, to Deenergise the User's Customers and/or the User (as the case may be) and to use all reasonable endeavours to effect or (as the case may be) give instructions to give effect to such De-energisation as quickly as practicable having regard to all the circumstances affecting such De-energisation (including any operational difficulties and relevant Licence duties); and/or
Deenergise the User's Equipment or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) at any Connection Site(s) which serves only the User or a customer of the User; and/or
where the User is an Interconnector User request the relevant Interconnector Owner to cease or procure the cessation of the transfer of power by or on behalf of the User across the Interconnector.
BSUoS Event of Default
The Company may terminate the relevant Bilateral Agreement and all others to which the User is a party and revoke the Use of System Supply Confirmation Notice and Use of System Interconnector Confirmation Notice forthwith by notice to the User if:-
The Company has given a valid notice of default pursuant to Paragraph 5.5.2; and
such event of default remains unremedied at the expiry of the later of:- 20
the period of 6 months from the date of such notice; and
where the User disputes bona fide the event of default and has promptly brought and is actively pursuing proceedings against The Company to determine the dispute, the date on which the dispute is resolved or determined. Upon termination pursuant to this Paragraph the User shall pay to The Company the Termination Amounts calculated in accordance with the Charging Statements and, in the case of a User in the category of a Power Station directly connected to the National Electricity Transmission System or with a Bilateral Embedded Generation Agreement, the Cancellation Charge and shall disconnect all the User's Equipment at the Connection Site and: aa) the User concerned shall remove any of the User's Equipment:
in the case of Connection Sites Onshore on the Relevant Transmission Licensee’s land within 6 months of the date of termination or such longer period as may be agreed between the Relevant Transmission Licensee and the User; or
in the case of Connection Sites Offshore, on or adjacent to the Relevant Transmission Licensee’s Offshore Platform within a period agreed between the Relevant Transmission Licensee and the User; and bb) in the case of Connection Sites Onshore, The Company shall procure that the Relevant Transmission Licensee removes, any of the Transmission Connection Assets on the land of the User concerned within 6 months or such longer period as may be agreed between the User and the Relevant Transmission Licensee; and cc) in the case of Connection Sites Offshore, The Company shall procure that the Relevant Transmission Licensee removes any of the Transmission Connection Assets on or adjacent to the User’s Offshore Platform within a period agreed 21 between the User and the Relevant Transmission Licensee; and dd) the provisions of Paragraph 5.4.7 shall apply mutatis mutandis.
The service of a notice under Paragraph 5.5.5.1 and/or the expiry of a notice given under Paragraph 5.6 shall not relieve the User of its obligation under Paragraph 3.9.3 or Paragraph 9.10 or any Bilateral Agreement to which the User is a party to pay any outstanding Balancing Services Use of System Charges in respect of any Settlement Day which fell prior to the issue or expiry of (as the case may be) such a notice but for which the Payment Date fell after the date of the termination of the relevant Bilateral Agreement (or use of system not subject to a Bilateral Agreement).
NOTICE TO DISCONNECT Without prejudice to Paragraph 5.2.2, each User shall, as between The Company and that User, give to The Company not less than 6 months written notice of any intention of the User to Disconnect the User's Equipment. In the absence of any specific notice to the contrary, any notice of Disconnection shall also be treated as a notice under CUSC Paragraph 6.30.1 decreasing Transmission Entry Capacity to zero with effect from the expiry of the period specified in the notice of Disconnection
If notice to Disconnect is given by the User under Paragraph 5.6 hereof the User may upon expiry of the period specified in such notice and not before Disconnect the User's Equipment. At the expiry of such period the relevant Bilateral Agreement shall terminate and the following provisions shall apply.
The User shall be liable forthwith on the date the relevant Bilateral Agreement so terminates to pay to The Company:-
Connection Charges and/or Use of System Charges to the end of the Financial Year in which termination occurs all such charges becoming immediately due and payable upon the termination of the relevant Bilateral Agreement; and
Termination Amounts applicable to the Connection Site; and
where the User is in the category of a Power Station directly connected to the National Electricity Transmission System or with a Bilateral Embedded Generation Agreement Cancellation Charge, 22 such payments to be made within 28 (twenty eight) days of the date of The Company 's invoice in respect thereof.
Within 6 months of the date of such termination or such longer period as may be agreed between the Relevant Transmission Licensee and the User in the case of Connection Sites Onshore:
the User shall remove any of the User's Equipment on the Relevant Transmission Licensee’s land; and
The Company shall procure that the Relevant Transmission Licensee removes, any of the Transmission Connection Assets on the land of the User concerned.
In the case of Connection Sites Offshore within a period agreed between the Relevant Transmission Licensee and the User:
the User shall remove any of the User’s Equipment on or adjacent to the Relevant Transmission Licensee’s Offshore Platform; and
The Company shall procure that the Relevant Transmission Licensee removes any of the Transmission Connection Assets on or adjacent to the User’s Offshore Platform .
This Paragraph 5.9 provides for additional Deenergisation provisions which only apply in relation to Users acting in their category of connection and/or use as Non-Embedded Customers.
If the following condition ceases to be satisfied in respect of the Supplier supplying the Connection Site The Company may give written notice of that fact to the User and unless within 5 days of receipt of such notice the User advises The Company that it has contracted with an alternative Supplier, The Company shall be entitled to Deenergise the Non-Embedded Customer’s User's Equipment:- “the Supplier being authorised by a current Supply Licence to supply electricity to the premises to be supplied with electricity through the Connection Site.”
If there ceases to be a subsisting right of Use of System by a Supplier at the Connection Site who is liable to The Company for Use of System Charges in respect of Demand attributable to the 23 Connection Site, The Company shall be entitled to Deenergise the User's Equipment.
Where:
the Supplier is in breach of the CUSC relating to the supply to the Connection Site and accordingly The Company is permitted under the CUSC to Deenergise the User's Equipment; or
an Event of Default under Paragraph 5.6 has occurred in relation to the Supplier with whom the User has a Supply Agreement and the relevant event is still continuing or the relevant circumstances still exist, The Company may Deenergise the User's Equipment upon the expiry of at least 48 hours prior written notice to the User provided that at the time of expiry of such notice the breach concerned remains unremedied or (as the case may be) the reason permitting Deenergisation continues or the relevant Event of Default is still continuing and neither The Company nor the Supplier has referred the matter to the Dispute Resolution Procedure. In such event, The Company may Deenergise the User's Equipment forthwith following completion of the Dispute Resolution Procedure and final determination of the dispute in The Company 's favour.
If a breach of the nature referred to in Paragraph 5.9.4 continues to the extent that it places or seriously threatens to place in the immediate future The Company in breach of the ESO Licence and\or places or seriously threatens to place in the immediate future any Relevant Transmission Licensee in breach of its transmission licence, The Company may Deenergise the Non-Embedded Customer’s Equipment at the Connection Site upon the expiry of at least five (5) Business Days prior written notice to the User, provided that at the time of expiry of such notice the breach concerned remains unremedied.
In the event of a Relevant Interruption, unless 5.10.7 applies, where the Affected User has not otherwise received compensation under the Balancing and Settlement Code The Company shall be liable to pay the Affected User upon request the Interruption Payment for the Interruption Period.
The Interruption Payment shall be paid by The Company to the Affected User within 28 days of the date of agreement as to the amount of the Interruption Payment.
The Affected User will take all reasonable steps to minimise the effect (and therefore the amount of the Interruption Payment sought as a consequence) of the Relevant Interruption on the operation of its business.
Subject to 5.10.10, the Affected User must request an Interruption Payment for a Relevant Interruption within 30 days of the end of the Relevant Interruption by submitting to The Company a completed Loss of Transmission Access Compensation Claim Form. No Interruption Payment will be payable by The Company if the Interruption Payment request falls outside this period.
The Company shall as soon as reasonably practicable after the end of the Interruption Period notify the Affected User where the Relevant Interruption was in accordance with Emergency Deenergisation Instruction.
The Company shall confirm to the Affected User whether or not an Interruption is a Relevant Interruption and confirm the Interruption Payment value within 60 days of that Affected User requesting an Interruption Payment, or use reasonable endeavours to agree with the Affected User when it shall provide such confirmation.
No Interruption Payment will be payable by The Company if the total agreed value of a claim under this Section 5.10 is less than the Interruption Payment Threshold unless the Interruption Payment is for a Relevant Interruption arising as result of a Planned Outage
The “Interruption Payment threshold” shall be £1, or such amount up to a maximum of £5,000 as may be determined by the CUSC Modification Panel from time to time. In the event of the CUSC Modification Panel varying the Interruption Payment Threshold such revised thereshold shall apply from 30 days after such variation being notified to all Users.
If an Affected User and The Company cannot reach agreement under Section 5.10.2 or 5.10.6 the Dispute Resolution Procedure shall apply.
The Company shall report to the CUSC Modification Panel in respect of the claims processed under this Section 5.10, such report to detail the number of claims received, under investigation, validated or rejected in the reporting period. The frequency of the reporting will be decided by the CUSC Modification Panel and may be varied from time to time.
In respect of any Relevant Interruptions occurring before the date and time of implementation of CUSC Modification Proposal CMP212, the Affected User must request an Interruption Payment for a Relevant Interruption within 30 days of the date and time of implementation of CUSC Modification Proposal CMP212.
SECTION 6: GENERAL PROVISIONS
INTRODUCTION This General Provisions Section contains those provisions which are generic, but which do not relate directly to the specific areas dealt with in other sections.
The Company OBLIGATIONS The Company agrees with each User to (and in respect of licence obligations contained within Section D or Section E of a transmission licence, procure that a Relevant Transmission Licensee shall) make available, plan, develop, operate and maintain the National Electricity Transmission System in accordance with the ESO Licence and the Transmission Licences and with the Grid Code subject to any Derogations from time to time.
Subject to Paragraph 6.3.3 each CUSC Party agrees with each other CUSC Party to be bound by and to comply in all respects with the provisions of the Grid Code in so far as applicable to that CUSC Party.
Subject to Paragraph 6.3.3 each CUSC Party agrees with each other CUSC Party to be bound by and to comply in all respects with the provisions of the relevant Distribution Code(s) in so far as applicable to that CUSC Party except as may be otherwise provided in any agreement for connection to a Distribution System.
Neither The Company nor a User need comply with the Grid Code or any relevant Distribution Code(s) to the extent (if any) that:-
either the Authority has issued directions relieving The Company or that User from the obligation under its respective licence to comply with the Licence Standards, the Grid Code or any relevant Distribution Code(s) in respect of such parts of the Grid Code or any relevant Distribution Code(s) respectively as may be specified in those directions or to the extent that The Company and a User which does not have a Licence under the Act can and have so agreed in any Bilateral Agreement or in relation to any Connection Site or New Connection Site or Transmission Interface Site and/or Derogated Plant; or
in the case of a User the Grid Code relates to the provision by that User of any Ancillary Services unless there is an Ancillary Services Agreement in force between that User and The Company for the payment by The Company for such Ancillary Services.
Each User undertakes to The Company and The Company undertakes to each User to use all reasonable endeavours to carry out such works as are necessary to ensure that each item of Derogated Plant owned or operated by that User or The Company (as appropriate) is brought up to the Required Standard applicable to it no later than the Back-Stop Date applicable to it.
The terms and provisions of the Fuel Security Code shall prevail to the extent that they are inconsistent with the Grid Code or any Distribution Code and the CUSC Parties’ obligations under the CUSC shall be construed accordingly.
Without prejudice to Paragraph 6.3.1, where a User who does not hold a Licence, so requests The Company in respect of an Embedded Exemptable Large Power Station that the CUSC Party owns or operates:
The Company shall apply to the Authority for a direction under condition E3.24 of the ESO Licence relieving The Company from the obligation to implement or comply with the Grid Code in respect of that Embedded Exemptable Large Power Station; and
that User shall provide such information and assistance as The Company may reasonably request to enable The Company to make such an application to the Authority.
An application by The Company pursuant to paragraph 6.3.6(i) shall inter alia include any grounds which The Company, in its reasonable opinion, may have why the Authority should not issue a direction under condition E3.24 of the ESO Licence in respect of that Embedded Exemptable Large Power Station.
JOINT SYSTEM INCIDENTS This paragraph applies to all Users other than: -
Users acting as Suppliers; and
Users who are Trading Parties and are responsible (as defined in the Balancing and Settlement Code) for Embedded Small Power Station(s); Each such User confirms to The Company (and The Company confirms to each such User) that as between The Company and that User its Senior Management Representatives whose names are nominated and notified to the other pursuant to OC9 of the Grid Code are fully authorised to make binding decisions on its behalf for the purposes of OC9.
Any User who owns or operates a Distribution System shall submit a request to The Company for an Evaluation of Transmission Impact: i. in the case of a Transmission Evaluation Application under Paragraph 6.5.1 (e) i upon an application for or acceptance of (as agreed between The Company and the User) for a connection to and/or for the use of that User’s Distribution System from a Relevant Embedded Power Station ii. in the case of a Modification Application under Paragraph 6.5.1 (e) ii to establish the Transmission Impact Assessment process (‘Appendix G’) in the Bilateral Connection Agreement. For the avoidance of doubt this Modification Application does not go through the Gated Application and Offer Process. For the purposes of this section 6.5, Relevant Embedded Power Station shall also include a group of Embedded Power Stations which collectively would be considered equivalent to a Relevant Embedded Power Station.
Should the User be uncertain as to whether an Embedded Power Station (either singularly or as part of a group) has a significant impact on the NETS and should be classed as a Relevant Embedded Power Station, the User shall submit a request to The Company for an Evaluation of Transmission Impact on behalf of the Embedded Power Station as per Paragraph 6.5.1(c). For avoidance of doubt, such significant impact will be deemed if the Embedded Power Station involves an Active Power, Apparent Power, Reactive Power, kiloamp or kilovolt value larger than as advised by The Company to the User.
Any User who owns or operates a Distribution System shall not Energise the connection between a Relevant Embedded Power Station or Embedded Large Power Station and its Distribution System nor permit the use of its Distribution System by the same until , in the case of a Relevant Embedded Power Station an Evaluation of Transmission Impact has concluded (as per paragraphs 6.5.5.6, 6.5.5.7, 6.5.8.5), and otherwise; i. The Company has confirmed to the User that all Transmission Reinforcement Works associated with the Relevant Embedded Power Station or Embedded Large Power Station listed in the relevant Construction Agreement (if any were identified) have been completed, and ii. in the case of a Relevant Embedded Power Station, The Company and the User have confirmed that the requirements of the Evaluation of Transmission Impact have been fulfilled, or iii. in the case of a Relevant Embedded Power Station which is the subject of a Bilateral Agreement, The Company has confirmed to the User who owns or operates the relevant Distribution System that the person owning or operating the plant has, where required, completed the Use of System Application (Generators) for a Gate 2 Offer and has entered into a Bilateral Agreement in the appropriate form with The Company, or iv. in the case of an Embedded Large Power Station, the Embedded Large Power Station has made a Gate 2 Application and entered into a Bilateral Agreement in the appropriate form with The Company and (if such person is not already a party to CUSC) has entered into an Accession Agreement.
Sub-paragraph (a) shall not apply to any User who owns or operates a Distribution System that is not directly or indirectly connected to the National Electricity Transmission System.
The User shall request that the Evaluation of Transmission Impact is undertaken by The Company using one of the following options; i. Transmission Evaluation Application (as documented in paragraph 6.5.5) ii. Transmission Impact Assessment (establishing “Appendix G”) (as documented in paragraph 6.5.8)
In England and Wales, an Embedded Small Power Station which has an Export Capacity of 5MW or above or (if there is less than 1kA of fault level headroom as set out in the Appendix G for the relevant Grid Supply Point at the time of a request for a connection to and/or for the use of the User’s Distribution System) 1MW or above is a Relevant Embedded Small Power Station requiring the submission of an Evaluation of Transmission Impact to The Company in accordance with Paragraph 6.5.1(a) above. For the avoidance of doubt, an Embedded Small Power Station with an Export Capacity below the Evaluation of Transmission Impact threshold will not be required to undergo an Evaluation of Transmission Impact.
Any User who owns or operates a Distribution System shall not Energise the connection between any Customer of another Authorised Electricity Operator connected to such Distribution System if the Authorised Electricity Operator is responsible for Demand (Active Power) being supplied to such Customer pursuant to the Balancing and Settlement Code unless such Authorised Electricity Operator has first submitted a Use of System Application, has received a Use of System Offer Notice which has been accepted by the User, and (if the Authorised Electricity Operator is not already a party to the CUSC Framework Agreement) has become a party to the CUSC Framework Agreement.
The Company shall notify the relevant owner or operator of the Distribution System in writing as soon as the conditions set out in Paragraph 6.5.1 and Paragraph 6.5.2 have been satisfied in any particular case together with, if appropriate, a copy of any list provided under Paragraph 3.5. The Company undertakes to each CUSC Party that, for so long as it is the case, The Company shall from time to time forthwith upon receipt of any written request from that CUSC Party to do so, confirm in writing to any person specified in such request that that CUSC Party is a party to the CUSC Framework Agreement and any Bilateral Agreement specified in such request.
Each owner or operator of a Distribution System shall De-energise the connection equipment of any such User the subject of Paragraph 6.5.1 or Customer the subject of Paragraph 6.5.2 as soon as reasonably practicable following the instruction of The Company in accordance with the terms of the CUSC. The Company shall reimburse such owner or operator any expense incurred in relation to such act of De-energisation, if any, and shall indemnify such owner or operator against any liability, loss or damage suffered by it as a result of such De-energisation. Details of any circumstances likely to lead to such a De-energisation shall be notified promptly by The Company to the said owner or operator. The owner or operator of a Distribution System shall promptly notify The Company when the connection equipment of any User or Customer the subject of Paragraph 6.5.1 or 6.5.2 is De-energised or Disconnected from its Distribution System or ceases to use its Distribution System as the case may be following the instruction of The Company in accordance with the terms of the CUSC. 6.5.4A If The Company receives a request to use the NETS which it believes could impact upon The User, The Company shall follow (unless it is a Gated Application) the Interactivity Policy adopted by The Company for the purposes of managing Interactivity and published on its website as it may be amended from time to time.
Transmission Evaluation Application
Any User who owns or operates a Distribution System shall in the timescales specified in the Gated Application and Offer Process after being notified by Relevant Embedded Power Station(s) that has an agreement for connection to and/or use of that User’s Distribution System and wants the User to submit (and has met any requirements of the User in this respect) an Evaluation of Transmission Impact in the form of a Transmission Evaluation Application. Such a submission by a User who owns or operates a Distribution System of a Transmission Evaluation Application will be substantially in the form of Exhibit U.
The Transmission Evaluation Application must include the Technical Information in respect of such Power Station(s) and its proposed date of connection to and / or for the use of the Distribution System.
Not Used.
Not Used.
The Transmission Evaluation Application shall be deemed to be a Modification Application for the purposes of the Charging Statements and Paragraphs 1.3.2, 6.9.2, 6.9.4 and 6.10 of the CUSC which shall apply thereto.
Where The Company believes the Power Station(s) has no significant impact on the National Electricity Transmission System or The Company’s assessment of the Transmission Evaluation Application indicates that no works are required nor any Site Specific Requirements are necessary, The Company shall notify the User in the form at Exhibit V as soon as reasonably practical and in any event prior to the end of the Gated Design Process and in such circumstances the Transmission Evaluation Application shall be concluded. For the purposes of Paragraph 6.5.1(c) the User who owns or operates a Distribution System may Energise the connection of the Power Station(s) or permit the use of its Distribution System by the Power Station(s).
Except where The Company confirms otherwise under Paragraph 6.5.5.6, (or it is otherwise provided for under the Transmission Impact Assessment process in the Bilateral Connection Agreement) the User who owns or operates a Distribution System shall not energise the connection of nor permit the use of its Distribution System by the Power Station(s) other than in accordance with the Gate 2 Agreements.
The User who owns or operates a Distribution System shall notify The Company in writing if the proposed date of connection or any other of the details included in or provided pursuant to the Transmission Evaluation Application for such Relevant Embedded Power Station(s), changes and the User who owns or operates a Distribution System shall (except where The Company agrees in writing that a revised Transmission Evaluation Application is not reasonably required) submit a revised Transmission Evaluation Application.
Where pursuant to Paragraph 6.5.5.6, The Company has notified the User that Site Specific Requirements are necessary at the site of connection of the Power Station(s) any such Site Specific Requirements notified to the User shall be incorporated through an agreement to vary the Bilateral Agreement between The Company and the User for the appropriate Grid Supply Point of such User.
If Site Specific Requirements are necessary and a Transmission Evaluation Application has been submitted pursuant to Paragraph 6.5.5.1 and not concluded under Paragraph 6.5.5.6, then any such Site Specific Requirements shall be included in the Modification Offer.
Offshore Transmission Implementation
Any User who owns or operates a Distribution System and has a Relevant Offshore Agreement with an Existing Offshore Generator shall cooperate with The Company to contribute to the full and timely completion of the Offshore Transmission Implementation Plan
Any User who owns or operates a Distribution System and has a Relevant Offshore Agreement with an Existing Offshore Generator shall provide The Company with information including:
The terms that have been agreed between the User who owns or operates a Distribution System and the Existing Offshore Generator;
Technical information about the connection arrangements that have been agreed between the User who owns or operates a Distribution System and the Existing Offshore Generator; and
Technical information about the Existing Offshore Generator’s Power Station provided as part of the Existing Offshore Generator’s application to the User who owns or operates a Distribution System.
The Company shall treat the information provided by any User who owns or operates a Distribution System under Paragraph 6.5.6.2, as an application for connection and use of the National Electricity Transmission System from the Existing Offshore Generator, for the purposes of standard condition C8.
Report on Distributed Generation Within one month of the end of a Financial Year, each User who owns or operates a Distribution System shall send a written report [(in a format specified by The Company)] to The Company in respect of Distributed Generation which is yet to connect to its Distribution System or which has been Energised during that Financial Year detailing the following information by reference to each category of Distributed Generation:
number of Distribution Agreements terminated;
any reduction in, as appropriate, Developer Capacity or Transmission Entry Capacity;
whether such termination or reduction occurred prior to (and including) or after the Key Consents in Place Date
Transmission Impact Assessment
A User who owns or operates a Distribution System can submit a Modification Application to The Company to establish a process for Transmission Impact Assessment (“Appendix G”) into the Bilateral Connection Agreement for the purposes of then undertaking the Evaluation of Transmission Impact at a Grid Supply Point.
The Modification Application for the Transmission Impact Assessment must include the technical information in respect of each Power Station and its proposed date of connection to and/or for the use of the Distribution System.
The Company will provide a Modification Offer to the User who owns or operates a Distribution System in accordance with Paragraphs 6.9.2.2 and 6.9.2.3, this Modification Offer will be substantially in the form of Schedule 2 Exhibit 1A to introduce and which includes the process for administering the Transmission Impact Assessment.
Should the User not accept the Modification Offer, the Evaluation of Transmission Impact will not be concluded for the purposes of Paragraph 6.5.1(c) and a new request under Paragraph 6.5.1(e) shall be required.
Should the User accept the Modification Offer, the Evaluation of Transmission Impact will be concluded for the purposes of Paragraph 6.5.1(c). Thereafter, the User will provide The Company with monthly updates (or a frequency of updates as agreed between The Company and the User) and follow the Transmission Impact Assessment obligations in accordance with the Bilateral Connection Agreement.
The Company will review the changes to the Transmission Impact Assessment and the requirements of Paragraph 6.5.1(c) in relation to a Relevant Embedded Power Station shall be deemed as completed unless The Company states otherwise as per the provisions of the Bilateral Connection Agreement. The Company shall notify the User of any changes The Company believe do not meet the criteria detailed in the Bilateral Connection Agreement (as amended by the Modification Offer described in Paragraph 6.5.8.5) within [5] business days.
Should the Bilateral Connection Agreement be subsequently modified to remove the Transmission Impact Assessment, any new requests to connect to and/or use the User’s Distribution System by a Power Station(s) shall be required undertake a Evaluation of Transmission Impact as per Paragraph 6.5.1(e).
The Company will invoice Users for Connection Charges and/or Use of System Charges due under the CUSC and/or each Bilateral Agreement and/or as notified to the User where there is no Bilateral Agreement, in accordance with the CUSC and/or the Charging Statements in the following manner:
in the case of recurrent monthly charges identified in the relevant Charging Statements The Company shall despatch an invoice on or before the 15th day of the month for the charges due in relation to that month;
in the case of the STTEC Charge The Company shall invoice the User on or before the 15th day of the month for the full STTEC Charge;
In the case of the LDTEC Charge NGC shall invoice the User on or before the 15th day of the month for the full LDTEC Charge;”
in the case of ET Use of System Charges, The Company shall invoice the User on the dates specified in the Bilateral Connection Agreement;
unless otherwise specified in the CUSC where charges are payable other than monthly The Company shall despatch an invoice not less than 30 days prior to the due date for payment.
Users shall pay Connection Charges and/or Use of System Charges and the STTEC Charge and the LDTEC Charge and due to The Company under the CUSC and/or each Bilateral Agreement and/or as otherwise notified to the User where there is no Bilateral Agreement, in accordance with the CUSC and/or the Charging Statements in the following manner:
in the case of recurrent monthly charges and the STTEC Charge and the LDTEC Charge on the later of:
15th day of the month to which the invoiced charges relate; and
the 14th day following the day that The Company's invoice was despatched unless, in any such case, the said date is not a Business Day in which case payment shall be made on the next Business Day;
in the case of ET Use of System Charges, by the date specified for payment in The Company’s invoice therefor;
unless otherwise specified in the CUSC where charges are payable other than monthly within 30 days of the date of The Company's invoice therefor.
All payments under this Paragraph 6.6 shall be made by the variable direct debit method or such other form of bankers automated payment as shall be approved by The Company to the account number, bank and branch as The Company or a User may from time to time notify in writing to the other.
All sums payable by one CUSC Party to the other pursuant to this CUSC, the Bilateral Agreements and/or the Mandatory Services Agreements, whether of charges, interest or otherwise shall (except to the extent otherwise required by law) be paid in full, free and clear of and without deduction set off or deferment in respect of sums the subject of any disputes or claims whatsoever save for sums the subject of a final award or judgement (after exhaustion of all appeals if this opportunity is taken) or which by agreement between The Company and those CUSC Parties may be so deducted or set-off.
Where a User wishes to pay its Use of System Charges payments in advance of the due date for such payment then The Company will discuss and agree arrangements for this with the User.
Subject to Section 4, if any CUSC Party fails to pay on the due date any amount properly due under the CUSC or any Bilateral Agreement such CUSC Party shall pay to the CUSC Party to whom such amount is due interest on such overdue amount from and including the date of such failure to (but excluding) the date of actual payment (as well after as before judgement) at the Prescribed Rate. Interest shall accrue from day to day.
All amounts specified hereunder or under any Bilateral Agreement shall be exclusive of any Value Added Tax or other similar tax.
Each User consents to The Company having access to and copies of all meter readings taken from Energy Metering Equipment pursuant to the Balancing and Settlement Code in any Financial Year for the purposes of calculating Connection Charges and Use of System Charges due from Users or for the purpose of operating the National Electricity Transmission System or of carrying out its EMR Functions. Such access and copies shall be obtained from the relevant BSC Agent appointed under the Balancing and Settlement Code from time to time provided always that if the relevant BSC Agent fails to provide such access and copies at The Company's request the User shall supply any such meter readings in the possession of the User direct to The Company.
The relationship between the CUSC Parties with respect to Energy Metering Equipment shall be regulated by Section L of the Balancing and Settlement Code.
In respect of Operational Metering Equipment owned by one CUSC Party and in respect of which access and rights to deal with such Operational Metering Equipment are not set down in any other document the CUSC Parties shall grant each other such access and other rights as are reasonably necessary to enable them to perform their obligations under the CUSC and the Grid Code upon presentation of a suitable indemnity and the CUSC Parties shall take such action as may be necessary to regularise the position forthwith thereafter.
The voltage at which the tariff metering is connected and its location shall be referred by The Company to the BSC Panel. The Company shall inform the relevant User of the voltage requirements specified by the BSC Panel as soon as possible thereafter.
Meter Operator Agent Where a Connection Site is a Grid Supply Point, and the User is or will be Registrant in relation to the Energy Metering Equipment required by the Balancing and Settlement Code at the Grid Supply Point and/or at the bulk supply point(s) which are related to that Grid Supply Point, The Company shall install and be the Meter Operator Agent of all such Energy Metering Equipment from the date of the relevant Construction Agreement until the FMS Date and thereafter:-
The Company may resign as Meter Operator Agent of such Energy Metering Equipment on giving no less than 12 months’ notice in writing; and
the User may remove The Company as Meter Operator Agent upon giving no less than 12 months’ notice in writing, Provided that where the User agrees to become owner of any such Energy Metering Equipment The Company may resign as Meter Operator Agent upon such transfer of ownership and shall agree such terms as shall be reasonably necessary to enable the User to perform its obligations as Meter Operator Agent of such Energy Metering Equipment.
Charges The Company shall recover its charges for acting as Meter Operator Agent of any Energy Metering System, which is a Transmission Connection Asset charged for under the CUSC, as part of such charges. Where The Company acts as Meter Operator Agent of any other Energy Metering System owned by The Company for which the User is Registrant The Company shall charge and the User shall pay such amount which is reasonable in all the circumstances.
Interference The User shall ensure that its employees, agents and invitees will not interfere with any Energy Metering Equipment in respect of which The Company is Meter Operator Agent or the connections to such Energy Metering Equipment, without the prior written consent of The Company (except to the extent that emergency action has to be taken to protect the health and safety of persons or to prevent serious damage to property proximate to the Energy Metering Equipment or to the extent that such action is authorised under the CUSC or any other agreement between The Company and the User.)
Pulse Data The User shall have the right to collect and record pulses from the meters comprised in the Energy Metering System(s) at the Connection Site. The Company shall procure that the Relevant Transmission Licensee shall give the User access in accordance with the Interface Agreement to collect and record such pulses and to install and maintain such lines and equipment as may be reasonably necessary.
Where a User is acting as a Supplier to a Non-Embedded Customer the User shall register the Energy Metering System at the Connection Site in accordance with the Balancing and Settlement Code and shall otherwise act as Registrant.
If the User is a BSC Trading Party, then the following provision[s] must be met:
Trading Point Electronic Data Transfer (CC.6.5.8) If required under Grid Code CC.6.5.8, the User must provide electronic data communication facilities approved by The Company to permit the submission of data required by the Grid Code, from the User’s Trading Point (as defined in the Grid Code) to The Company. The User can elect to send data to two locations depending upon the level of diversity required by the User. The Company will provide the necessary “router” connection equipment at both Wokingham and Warwick House.
If the User chooses to participate in the Balancing Mechanism then the following provisions must be met:
Control Telephony (CC.6.5.2 to CC.6.5.5) The requirements of Control Telephony are specified in Appendix 1 of this Section 6. This encompasses Additional Communication Requirements (CC.6.5.7 and CC.6.5.9).
Operational Metering (CC.6.5.6)
The Operational Metering requirements are contained in Appendix 2 to this Section 6. The Operational Metering Summator (OMS) is detailed in NGTS 3.9.11.
The Company shall supply and install the OMS Front End (FE) unit in a position close to the high accuracy meters, to be agreed with the User, preferably within the high accuracy metering cubicle. The OMS FE links to the OMS Processing End (PE) unit via a serial data link and this may need to be connected via User supplied cabling depending on the agreed positions of the two units.
Where User’s Equipment or equipment for which the User is responsible (as defined in the Balancing and Settlement Code) is located immediately adjacent to the Grid Entry Point ( Transmission Substation), Telecoms Room accommodation shall be provided by the User for the Transmission Marshalling Cubicles, Telemetry, System Monitoring, Signalling and Telephone equipment required to collect and return the information required, and to provide voice communication. This will require space for between three and five 600mm square cubicles to contain equipment, supplies (e.g. 48-volt dc) and marshalling. The equipment will be provided and installed by The Company. The User will be responsible for providing the site connections and cabling to the plant/peripherals. The User should ensure that signals are wired out to the appropriate cubicle.
Where User’s Equipment or Equipment for which the User is responsible (as defined in the Balancing and Settlement Code) is located immediately adjacent to the Grid Entry Point (Transmission Substation),and the two sites have their earthing bonded together, the data required by The Company (from the OMS-FE and other plant) will be cabled directly between the two sites and The Company equipment located in the User bay in the Transmission substation.
The requirements as specified in Appendix 2 to this Section 6 must be met for all generating plant, including any plant specifically installed for Black Start, that is the subject of bids or offers to the Balancing Mechanism.
The requirements as specified in Appendix 2 to this Section 6, to the extent that they are applicable, must be met where reasonably required by The Company for demand supplied by the User that is the subject of bids or offers to the Balancing Mechanism. The Company will not require the requirements of Appendix 2 to this Section 6 to be met where it is impracticable or unreasonable to do so, for example where the demand is a disparate collection of small demands aggregated to form a BM Unit.
Control Point Electronic Dispatch & Logging (CC.6.5.8) Electronic data communication facilities approved by The Company to permit the submission of Bid Offer Acceptance data from The Company to the User’s Control Point (as defined in the Grid Code) and to permit the submission data required by the Grid Code, from the User’s Control Point to The Company. The Company will provide the necessary communication links and “router” connection equipment at the User’s Control Point. The requirements for Control Point Electronic Dispatch & Logging are specified in Appendix 1 to this Section 6 (Communications Plant).
No Modification may be made by or on behalf of a User or The Company otherwise than in accordance with the provisions of this Paragraph 6.9.
Modifications Proposed by Users
If a User wishes to make a Modification it shall complete and submit to The Company a Modification Application (and if this is a Gated Application, in accordance with the Gated Application and Offer Process) comply with the terms thereof.
Where the Modification Application:
is not a Gated Application, The Company shall make the Modification Offer to that User as soon as practicable and (save where the Authority consents to a longer period) in any event not more than 3 months after receipt by The Company of the Modification Application.
is a Gated Application, The Company shall make the Modification Offer to the User in accordance with the Gated Application and Offer Process.
The Modification Offer shall include details of any variations The Company proposes to make to the Bilateral Agreement or, where applicable, the Construction Agreement which applies to the Connection Site or Transmission Interface Site in question. During such period The Company and the User concerned shall discuss in good faith the implication of the proposed Modifications.
The Modifications Offer shall remain open for acceptance (subject to CUSC Paragraph 6.10.4.4) for 3 months from the date of its receipt by that User unless either that User or The Company makes an application to the Authority under condition E13 of the ESO Licence, in which event the Modification Offer shall remain open for acceptance by that User until the date 14 days after any determination by the Authority pursuant to such application.
If the Modification Offer is accepted by that User the Bilateral Agreement or Construction Agreement relating to the Connection Site or Transmission Interface Site in question shall be varied to reflect the terms of the Modification Offer and the Modification shall proceed according to the terms of the Bilateral Agreement or Construction Agreement as so varied.
Modifications Proposed by The Company
If The Company wishes to make a Modification to the National Electricity Transmission System, The Company shall complete and submit to each User a Modification Notification and shall advise each User of any works (including where applicable any OTSDUW or changes to OTSDUW) which The Company reasonably believes that User may have to carry out as a result.
Any User which considers that it shall be required to make a Modification as a result of the Modification proposed by The Company (a “Modification Affected User”) may as soon as practicable after receipt of the Modification Notification and (save where the Authority consents to a longer period) within the period stated therein (which shall be sufficient to enable the User to assess the implications of the proposed Modification and in any event shall not be less than 3 months) may make an application to the Authority under condition E13 of the ESO Licence.
As soon as practicable after the receipt of the Modification Notification or, if an application to the Authority has been made, the determination by the Authority, and in any event within two months thereof, each Modification Affected User shall complete and submit a Modification Application to The Company and comply with the terms thereof. No fee shall be payable by any User to The Company in respect of any such Modification Application.
Once a Modification Application has been made by a User pursuant to Paragraph 6.9.3.2 the provisions of Paragraph 6.9.2.2, 6.9.2.3 and 6.9.2.4 shall thereafter apply.
Modification Notification and Modification Applications relating to owners/operators of Distribution Systems triggered by Embedded Power Stations
The provisions of this Paragraph 6.9 apply to Modification Notification and Modification Applications relating to owners/operators of Distribution Systems triggered by Embedded Power Stations but adapted as required on the following basis.
Where a Modification Notification is issued by The Company to the User under Paragraph 6.9.3 on receipt by The Company of a Gate 1 Application for a BEGA for a Embedded Large Power Station or BELLA, the notice is solely to inform the User of the Gate 1 Application and no details of the impact on the National Electricity Transmission System will be provided or Modification Application required from the User as provided for in that Paragraph.
Where a Modification Notification is issued by The Company to the User under Paragraph 6.9.3 on receipt by The Company of a Gate 2 Application by an Embedded Power Station for a BEGA or BELLA, the Modification Application by the User will be made in accordance with the Gated Application and Offer Process.
Modifications Required for Offshore Transmission Implementation
The Company shall notify Existing Offshore Generators on or before go-active if The Company is required to make a Modification to a Relevant Offshore Agreement to meet the requirements of the Offshore Transmission Implementation Plan. Such notification by The Company shall be treated as a Modification Application from the Existing Offshore Generator.
Any Existing Offshore Generator that The Company has notified under Paragraph 6.9.4.1, shall cooperate with The Company to contribute to the full and timely completion of the Offshore Transmission Implementation Plan
Once a Modification Application has been made by a User pursuant to Paragraph 6.9.4.1 the provisions of Paragraph 6.9.2.2, 6.9.2.3 and 6.9.2.4 shall thereafter apply.
To the extent that the provisions of any Nuclear Site Licence Provisions Agreement relate to Modifications (either by a User or by The Company) as (and only as) between User and The Company, they shall prevail over the provisions of this Paragraph 6.9 to the extent that they are inconsistent.
Modifications relating to OTSDUW Where a Construction Agreement has been entered into on the basis of OTSDUW Arrangements, then any actual or proposed replacement, renovation, modification, alteration, or construction by or on behalf of the User to the OTSUA, the scope of the OTSDUW or the manner of the operation of the OTSUA which may have a Material Effect on another CUSC Party at the particular Connection Site and/or Transmission Interface Site shall be deemed to be a Modification proposed by the User for the purposes of the CUSC.
Subject to the payment of its Reasonable Charges, if any, as provided for in this Paragraph 6.10 The Company undertakes to each User to provide all advice and assistance reasonably requested by that User to enable that User adequately to assess the implications (including the feasibility) of making a Modification to the User's Equipment, the User's System or the OTSUA (whether such Modification is to be made at the request of The Company or of the User) or of constructing a New Connection Site or undertaking Offshore Transmission System Development User Works (including adequately assessing the feasibility of making any Connection Application or considering the terms of any Connection Offer). If the proposed Modification by the User is or may be required as a result of a Modification proposed by The Company then The Company shall provide such advice and assistance free of charge. If the proposed Modification is or may be proposed by the User or if the advice and assistance is in respect of a New Connection Site The Company may charge the User Reasonable Charges for such advice and assistance. The provision of such advice and assistance shall be subject to any confidentiality obligations binding on The Company and that User.
When giving such advice and assistance The Company shall comply with Good Industry Practice.
The Company shall have no obligation to compensate any User (the "First User") for the cost or expense of any Modification required to be made by any User as a result of any The Company Modification under Paragraph 6.9.3.1. Where such The Company Modification is made as a result of the construction of a New Connection Site or a Modification for another User (the "Other User"), the Other User shall compensate the First User for the reasonable and proper cost and expense of any Modifications required to be made by the First User as a result of that The Company Modification. Such compensation shall be paid to the First User by the Other User within thirty days of production to the Other User of a receipted invoice (together with a detailed breakdown of such reasonable costs and expenses) for the expenditure which has been incurred by the First User. Modification Offer and Connection Offer conditional upon other Modification and Connection Offers
This Paragraph does not apply in the case of Gated Offers and references within it shall be construed accordingly. If at the time of making any Offer or Modification Offer or Connection Offer to a User (the "Second Offer") there is an outstanding Modification Offer(s) or Connection Offer(s) to another User(s) (the "First Offer") which if accepted would affect the terms of the Second Offer The Company shall at the time of making the Second Offer:
inform the recipient(s) of both the First Offer(s) and Second Offer(s) in writing that there is another Offer outstanding which might affect them; and 6.10.4.2 be entitled to make the First Offer(s) and Second Offer(s) conditional upon other outstanding Offers not having been or being accepted; and 6.10.4.3 be entitled to vary the terms of either Offer if the other Offer is accepted first on the same procedures as those set out in Paragraphs 6.9.2.2 to 6.9.2.4 or 2.13.3 to 2.13.5 inclusive as the case may be.
If Interactivity is confirmed in accordance with the Interactivity Policy, The Company shall be entitled to vary the Offer Acceptance Period as provided for in the Interactivity Policy
Save as provided in Paragraph 6.11.2 below notwithstanding anything to the contrary contained in the CUSC (but subject to the following provison), in circumstances affecting a generator of nuclear electricity (a "Nuclear Generator") in which:
a breach of any of the matters specified in Paragraph 6.11.4 below may be reasonably anticipated; and
there is no defence (other than that provided for under this Paragraph) available to the Nuclear Generator in respect of the breach referred to in Paragraph (a); the Nuclear Generator shall be entitled to take any action or refrain from taking any action which is reasonably necessary in order to avert the breach referred to in Paragraph 6.11.1(a) and each and every provision of the CUSC shall be read and construed subject to this Paragraph 6.11.1, Provided that the Nuclear Generator shall:-
make reasonable efforts to verify the factors that it takes into account in its assessment of the circumstances and anticipated breach referred to above; and
use its best endeavours to comply with the relevant provision in a manner which will not cause the Nuclear Generator to breach any of the matters specified in Paragraph 6.11.4 below.
Paragraphs 6.11.1 and 6.11.3 shall not apply in relation to the provisions of the Balancing Codes which will apply with full force and effect notwithstanding the occurrence of the circumstances referred to in 6.11.1(a) (including those provisions specified in Paragraph 6.11.4 which relate to Safety of Personnel and Plant).
Save as provided in Paragraph 6.11.2 above notwithstanding anything in the CUSC, the Nuclear Generator shall be entitled upon giving reasonable notice to all affected CUSC Parties to require any CUSC Party to take any reasonable and proper action whatsoever to the extent necessary in order to comply with (or avert an anticipated breach of) any of the matters specified in Paragraph 6.11.4 below.
The matters referred to in Paragraphs 6.11.1 and 6.11.3 above are any covenant, agreement, restriction, stipulation, instruction, provision, condition or notice contained, or referred to, in a licence for the time being in force, granted in accordance with the Nuclear Installations Act 1965 (or legislation amending, replacing or modifying the same) or any consent, or approval issued, or to take effect from time to time under such licence, any emergency arrangements, operating rules or other matters from time to time under such licence, any emergency arrangements, operating rules or other matters from time to time approved by the relevant authority under, or pursuant to, any such agreements, restrictions, stipulations, instructions, provisions, conditions or notices.
The Nuclear Generator shall indemnify and keep indemnified any CUSC Party for any loss, damage, costs and expenses incurred by that CUSC Party as a consequence of any action of that CUSC Party pursuant to Paragraph 6.11.3 (to the extent that the action was not required by any licence or agreement binding on that CUSC Party).
Notwithstanding the fact that any action or inaction allowed by Paragraph 6.11.1 above does not constitute a breach of the CUSC or an Event of Default under Paragraph 5.3, the Nuclear Generator shall be liable to the other CUSC Parties to the CUSC for any loss, claims, costs, liabilities and expenses arising from such action or inaction to the extent only that such loss, claims, costs, liabilities and expenses (had it arisen as a result of a breach of the CUSC) would not have been limited or excluded under the provisions of Paragraph 6.12.
Subject to Paragraphs 4.3, 5.10.1, 6.12.6, 6.5.4 and 6.11.5 and any liquidated damages provisions of any Construction Agreement or Bilateral Agreement or Mandatory Services Agreement and the payment adjustment provisions of the relevant Mandatory Services Agreement and save where any provision of the CUSC, any Bilateral Agreement or any Mandatory Services Agreement provides for an indemnity each CUSC Party agrees and acknowledges that no CUSC Party (the "Party Liable") nor any of its officers, employees or agents shall be liable to any of the other CUSC Parties for loss arising from any breach of the CUSC and any such agreements other than for loss directly resulting from such breach and which at the date hereof was reasonably foreseeable as not unlikely to occur in the ordinary course of events from such breach in respect of:- 6.12.1.1 physical damage to the property of any of the other CUSC Parties, or its or their respective officers, employees or agents; and/or 6.12.1.2 the liability of any such other CUSC Party to any other person for loss in respect of physical damage to the property of any other person, subject, for the avoidance of doubt, to the requirement that the amount of such liability claimed by such other CUSC Party should be mitigated in accordance with general law. provided that the liability of any CUSC Party in respect of all claims for such loss shall not exceed £5million per incident or series of related incidents and that in cases where an incident or series of related incidents occur on an Onshore Distribution System affects Users of an ET Offshore Transmission System or on an ET Transmission System affecting Users of an Onshore Distribution System, the liability of all CUSC Parties in respect of all claims for such loss shall not exceed £1million per incident or series of related incidents.
Nothing in the CUSC shall exclude or limit the liability of the Party Liable in respect of fraudulent misrepresentation or death or personal injury resulting from the negligence of the Party Liable or any of its officers, employees or agents and the Party Liable shall indemnify and keep indemnified each of the other CUSC Parties, its officers, employees or agents, from and against all such and any loss or liability which any such other CUSC Party may suffer or incur by reason of any claim on account of fraudulent misrepresentation, death or personal injury resulting from the negligence of the Party Liable or any of its officers, employees or agents.
In consideration of the rights conferred upon each CUSC Party (other than The Company) under the CUSC, the right of such CUSC Party (other than The Company to claim in negligence, other tort, or otherwise howsoever against a Relevant Transmission Licensee in respect of any act or omission of such Relevant Transmission Licensee in relation to the subject matter of the STC is hereby excluded and each CUSC Party (other than The Company) agrees not to pursue any such claim save that nothing in this paragraph 6.12.3 shall restrict the ability of such CUSC Party to claim in respect of fraudulent misrepresentation or death or personal injury resulting from the negligence of a Relevant Transmission Licensee.
Subject to Paragraphs 4.3, 5.10.1, 6.12.6, 6.5.4 and 6.11.5 and any liquidated damages provision of any Construction Agreement or Bilateral Agreement or Mandatory Services Agreement and save where any provision of the CUSC, any Bilateral Agreement or any Mandatory Services Agreement provides for an indemnity, neither the Party Liable nor any of its officers, employees or agents shall in any circumstances whatsoever be liable to any of the other CUSC Parties for:- 6.12.4.1 any loss of profit, loss of revenue, loss of use, loss of contract or loss of goodwill; or 6.12.4.2 any indirect or consequential loss; or 6.12.4.3 loss resulting from the liability of any other CUSC Party to any other person howsoever and whensoever arising save as provided in Sub Paragraphs 6.12.1.1 and 6.12.1.2.
The rights and remedies provided by the CUSC to the CUSC Parties are exclusive and not cumulative and exclude and are in place of all substantive (but not procedural) rights or remedies express or implied and provided by common law or statute in respect of the subject matter of the CUSC, including without limitation any rights any CUSC Party may possess in tort which shall include actions brought in negligence and/or nuisance. Accordingly, each of the CUSC Parties hereby waives to the fullest extent possible all such rights and remedies provided by common law or statute, and releases a CUSC Party which is liable to another (or others), its officers, employees and agents to the same extent from all duties, liabilities, responsibilities or obligations provided by common law or statute in respect of the matters dealt with in the CUSC and undertakes not to enforce any of the same except as expressly provided herein.
Save as otherwise expressly provided in the CUSC, this Paragraph 6.12 insofar as it excludes or limits liability shall override any other provision in the CUSC provided that nothing in this Paragraph 6.12 shall exclude or restrict or otherwise prejudice or affect any of:- 6.12.6.1 the rights, powers, duties and obligations of any CUSC Party which are conferred or created by the Act, the Licence or the Regulations; or 6.12.6.2 the rights, powers, duties and obligations of the Authority or the Secretary of State under the Act, any Licence or otherwise howsoever.
Each of the Paragraphs of this Paragraph 6.12 shall:- 6.12.7.1 be construed as a separate and severable contract term, and if one or more of such Paragraphs is held to be invalid, unlawful or otherwise unenforceable the other or others of such Paragraphs shall remain in full force and effect and shall continue to bind the CUSC Parties; and 6.12.7.2 survive termination of the CUSC and/or the CUSC Framework Agreement.
Each CUSC Party acknowledges and agrees that each of the other CUSC Parties holds the benefit of Paragraphs 6.12.1 and 6.12.2 and 6.12.3 above for itself and as trustee and agent for its officers, employees and agents.
Each CUSC Party acknowledges and agrees that the provisions of this Paragraph 6.12 have been the subject of discussion and negotiation and are fair and reasonable having regard to the circumstances as at the date hereof. 6.12.10For the avoidance of doubt, nothing in this Paragraph 6.12 shall prevent or restrict any CUSC Party enforcing any obligation (including suing for a debt) owed to it under or pursuant to the CUSC.
The CUSC Parties shall admit as an additional party to the CUSC Framework Agreement any person who accepts a Connection Offer or Use of System Offer from The Company (the ‘New CUSC Party’) and who is not at the time a CUSC Party. Such admission shall take effect by way of an Accession Agreement prepared by The Company at the expense and cost of the New CUSC Party and to be executed by The Company for itself and on behalf of all other CUSC Parties. Upon execution of the Accession Agreement by The Company, subject to and in accordance with the terms and conditions of that Accession Agreement, the New Party shall become a CUSC Party for all purposes of the CUSC Framework Agreement.
Each CUSC Party hereby authorises and instructs The Company to sign any such Accession Agreement on its behalf and undertakes not to withdraw, qualify or remove any such authority or instruction at any time.
The Company shall promptly notify all Users that the New CUSC Party has become a CUSC Party. Such notification shall be by both publication on The Company Website and written notice (which may be sent electronically) of the name, registered address and capacities in which the new CUSC Party will, or intends to, be connected to or use the National Electricity Transmission System.
The rights, powers, duties and obligations of a User under the CUSC or the CUSC Framework Agreement and/or any Bilateral Agreement (and associated Construction Agreement) or Mandatory Services Agreement are personal to that User and that User may not assign or transfer the benefit or burden of those documents save in the following circumstances:
upon the disposal by that User of the whole of its business or undertaking it shall have the right to transfer its rights and obligations under the CUSC, all Bilateral Agreements (and associated Construction Agreements) and all Mandatory Services Agreements to the purchaser thereof on condition that the purchaser if not already a User enters into an Accession Agreement with The Company pursuant to Paragraph 6.13 and confirms to The Company in writing either that all of the technical or related conditions, data, information, operational issues or other matters specified in or pursuant to the relevant Bilateral Agreement (and associated Construction Agreement) or Grid Code by the User seeking the transfer will remain unchanged or, (except in the case of a Mandatory Services Agreement) if any such matters are to be changed, the purchaser first notifies The Company in writing of such changes which The Company will consider promptly and in any event within 28 days of receiving notice of such change, and until such consideration is complete the transfer shall not be effective. If having considered such changes The Company in its reasonable opinion does not consider the proposed changes reasonably satisfactory to The Company it shall consult with the User seeking to undertake such transfer and pending the outcome thereof to The Company’s reasonable satisfaction the transfer shall not be effective; provided always that the User may refer any dispute to the Dispute Resolution Procedure. Such transfer shall become effective once the changes are reasonably satisfactory to The Company or have been determined to be so under the Dispute Resolution Procedure;
upon the disposal by a User of part of its business undertaking comprising User's Equipment at one or more Connection Sites that User shall have the right to transfer its rights and obligations under all relevant Bilateral Agreements (and associated Construction Agreements) and all relevant Mandatory Services Agreements to the purchaser thereof on condition that the purchaser (if not already a User) enters into an Accession Agreement with The Company under Paragraph 6.13 and confirms to The Company in writing either that all of the technical or related conditions, data, information, operational issues or other matters specified in or pursuant to the relevant Bilateral Agreement (and associated Construction Agreement) or Grid Code by the User seeking the transfer will remain unchanged or, (except in the case of a Mandatory Services Agreement) if any such matters are to be changed, the purchaser first notifies The Company in writing of such changes which The Company will consider promptly and in any event within 28 days of receiving notice of such change and until such consideration is complete the assignment shall not be effective. If having considered such changes The Company in its reasonable opinion does not consider the proposed changes reasonably satisfactory to The Company it shall consult with the User seeking to undertake such transfer and pending the outcome thereof to The Company's reasonable satisfaction the transfer shall not be effective provided always that the User may refer any dispute to the Dispute Resolution Procedure. Such transfer shall become effective once the changes are reasonably satisfactory to The Company or have been determined to be so under the Dispute Resolution Procedure;
a User may assign or charge its benefit under the CUSC and any Bilateral Agreements (and associated Construction Agreement) or any Mandatory Services Agreements in whole or in part by way of security. Each CUSC Party shall have the right to sub-contract or delegate the performance of any of its obligations or duties arising under the CUSC or any Bilateral Agreement, associated Construction Agreement or Mandatory Services Agreements including activities envisaged by the Grid Code without the prior consent of any other CUSC Party. The sub-contracting by a CUSC Party of the performance of any obligations or duties under the CUSC or any Bilateral Agreement, Construction Agreements or Mandatory Services Agreements or of any activities envisaged by the Grid Code shall not relieve that CUSC Party from liability for performance of such obligation or duty.
Nothing in Paragraph 6.14.1 shall prevent a transfer of OTSUA (and transfer or assignment of all associated property and rights) by the relevant User to an Offshore Transmission Licensee.
Confidentiality for The Company and its subsidiaries
The Company and its subsidiaries in each of their capacities in the CUSC shall secure that Protected Information is not:
divulged by Business Personnel to any person unless that person is an Authorised Recipient;
used by Business Personnel for the purposes of obtaining for The Company or any of its subsidiaries or for any other person:
any electricity licence; or
any right to purchase or otherwise acquire (including to enter into or acquire the benefit of a contract conferring rights or obligations, including rights or obligations by way of option, in relation to or by reference to the sale, purchase or delivery of electricity at any time or the price at which electricity is sold or purchased at any time), or to distribute electricity; or
any contract or arrangement for the supply of electricity to Customers or Suppliers; or
any contract for the use of any electrical lines or electrical plant belonging to or under the control of a Public Distribution System Operator, except and to the extent that The Company is required to do so pursuant to a request by a User in its application for connection to the National Electricity Transmission System at a Connection Site located Offshore; or
control of any body corporate which, whether directly or indirectly, has the benefit of any such licence, contract or arrangement; and
used by Business Personnel for the purpose of carrying on any activities other than Permitted Activities except with the prior consent in writing of the CUSC Party to whose affairs such Protected Information relates.
Nothing in Paragraph 6.15.1.1 shall apply:
to any Protected Information which, before it is furnished to Business Personnel, is in the public domain; or
to any Protected Information which, after it is furnished to Business Personnel:
is acquired by The Company or any subsidiary of The Company in circumstances in which Paragraph 6.15.1 does not apply; or
is acquired by The Company or any subsidiary of The Company in circumstances in which Paragraph 6.15.1.1 does apply and thereafter ceases to be subject to the restrictions imposed by such Paragraph; or
enters the public domain, and in any such case otherwise than as a result of a breach by The Company or any subsidiary of The Company of its obligations in Paragraph 6.15.1.1, or a breach by the person who disclosed the Protected Information of that person's confidentiality obligation and The Company or any of its subsidiaries is aware of such breach; or
to the disclosure of any Protected Information to any person if The Company or any subsidiary of The Company is required or expressly permitted to make such disclosure to such person:
in compliance with the duties of The Company or any subsidiary under the Act or any other requirement of a Competent Authority; or
in compliance with the conditions of the ESO Licence or any document referred to in the ESO Licence with which The Company or any subsidiary of The Company is required by virtue of the Act or the ESO Licence to comply; or
in compliance with any other requirement of law; or
in response to a requirement of any stock exchange or regulatory authority or the Panel on Take-overs and Mergers; or
pursuant to the rules for the London Court of International Arbitration or pursuant to any judicial or other arbitral process including where determination is by an expert or tribunal having jurisdiction in relation to The Company or any of its subsidiaries; or
in compliance with the requirements of section 35 of the Act and with the provisions of the Fuel Security Code; or
pursuant to an EMR Document and if an EMR Document requires the disclosure of data from previous years, The Company may disclose that data also; or
to any Protected Information to the extent that The Company or any of its subsidiaries is expressly permitted or required to disclose that information under the terms of any agreement or arrangement (including the CUSC, the Grid Code, the Distribution Codes and the Fuel Security Code) with the CUSC Party to whose affairs such Protected Information relates.
The Company and each of its subsidiaries may use all and any information or data supplied to or acquired by it, from or in relation to Users in performing Permitted Activities including for the following purposes:
the operation and planning of the National Electricity Transmission System;
the calculation of charges and preparation of offers of terms for connection to or use of the National Electricity Transmission System;
the operation and planning in relation to the utilisation of Balancing Services and the calculation of charges therefor;
the provision of information under the British Grid Systems Agreement and EdF Documents, and may pass the same to subsidiaries of The Company which carry out such activities and the CUSC Parties agree to provide all information to The Company and its subsidiaries for such purposes. 6.15.1.3A In addition, and without prejudice, to the provisions of paragraph 6.15.1.3, The Company and each of its subsidiaries may use all and any information or data supplied to or acquired by it in any year, from or in relation to Users, for the purpose of carrying out its EMR Functions
The Company undertakes to each of the other CUSC Parties that, having regard to the activities in which any Business Person is engaged and the nature and effective life of the Protected Information divulged to them by virtue of such activities, neither The Company nor any of its subsidiaries shall unreasonably continue (taking into account any industrial relations concerns reasonably held by it) to divulge Protected Information or permit Protected Information to be divulged by any subsidiary of The Company to any Business Person who has notified The Company or the relevant subsidiary of their intention to become engaged as an employee or agent of any other person (other than of The Company or any subsidiary thereof) who is:
authorised by licence or exemption to generate, transmit, distribute or supply electricity; or
an electricity broker or is known to be engaged in the writing of electricity purchase contracts (which shall include the entering into or acquiring the benefit of a contract conferring rights or obligations including rights and obligations by way of option, in relation to or by reference to the sale, purchase or delivery of electricity at any time or the price at which electricity is sold or purchased at any time); or
known to be retained as a consultant to any such person who is referred to in (i) or (ii) above.
Without prejudice to the other provisions of this Paragraph 6.15 The Company shall procure that any additional copies made of the Protected Information whether in hard copy or computerised form, will clearly identify the Protected Information as protected.
The Company undertakes to use all reasonable endeavours to procure that no employee is a Corporate Functions Person unless the same is necessary for the proper performance of their duties.
Without prejudice to Paragraph 6.15.1.3, The Company and each of its subsidiaries may use and pass to each other all and any period metered demand data supplied to or acquired by it and all and any information and data supplied to it pursuant to OC6 of the Grid Code for the purposes of Demand Control (as defined in the Grid Code), but in each case only for the purposes of its estimation and calculation from time to time of the variable "system maximum ACS demand" (as defined in the ESO Licence).
Any information regarding, or data acquired by the relevant BSC Agent or its agent from Energy Metering Equipment at Sites which are a point of connection to a Distribution System shall and may be passed by the relevant BSC Agent or their agent to the operator of the relevant Distribution System. The said operator of the relevant Distribution System may only use the same for the purposes of the operation of such Distribution System and the calculation of charges for use of and connection to the Distribution System. Confidentiality other than for The Company and its subsidiaries
Each User undertakes with each other User and with The Company and its subsidiaries that it shall preserve the confidentiality of, and not directly or indirectly reveal, report, publish, disclose or transfer or use for its own purposes Confidential Information except in the circumstances set out in Paragraph 6.15.7 or to the extent otherwise expressly permitted by the CUSC or with the prior consent in writing of the CUSC Party to whose affairs such Confidential Information relates.
The circumstances referred to in Paragraph 6.15.6 are: (a) where the Confidential Information, before it is furnished to the User, is in the public domain; or
where the Confidential Information, after it is furnished to the User:
is acquired by the User in circumstances in which Paragraph 6.15.6 does not apply; or
is acquired by the User in circumstances in which Paragraph 6.15.6 does apply and thereafter ceases to be subject to the restrictions imposed by Paragraph 6.15.6; or
enters the public domain, and in any such case otherwise than as a result of a breach by the User of its obligations in Paragraph 6.15.6 or a breach by the person who disclosed that Confidential Information of that person's confidentiality obligation and the User is aware of such breach; or
if the User is required or permitted to make disclosure of the Confidential Information to any person:
in compliance with the duties of the User under the Act or any other requirement of a Competent Authority; or
in compliance with the conditions of any Licence or any document referred to in any Licence with which the User is required to comply or
in compliance with any other requirement of law; or
in response to a requirement of any stock exchange or regulatory authority or the Panel on Take-overs and Mergers; or
pursuant to the rules for the London Court of International Arbitration or pursuant to any judicial or other arbitral process (including where determination is by an expert) or tribunal having jurisdiction in relation to the User; or
pursuant to an EMR Document; or
where Confidential Information is furnished by the User to its Affiliates or Related Undertakings or to the employees, directors, agents, consultants and professional advisors of the User or those of its Affiliates or Related Undertakings, in each case on the basis set out in Paragraph 6.15.8.
With effect from the date of the MCUSA the User shall adopt procedures within its organisation for ensuring the confidentiality of all Confidential Information which it is obliged to preserve as confidential under Paragraph 6.15.6 These procedures are:
the Confidential Information will be disseminated within the User only on a "need to know" basis;
employees, directors, agents, consultants and professional advisers of the User or those of its Affiliates or Related Undertakings in receipt of Confidential Information will be made fully aware of the User's obligations of confidence in relation thereto; and 6.15.8.3 any copies of the Confidential Information, whether in hard copy or computerised form, will clearly identify the Confidential Information as confidential.
Each User shall procure that its Affiliates, Related Undertakings, consultants and professional advisers observe the restrictions set out in this Paragraph 6.15 (as if references to “User” were references to such Affiliates, Related Undertakings, consultants and professional advisers) and shall be responsible under the CUSC for any failure by such persons to observe such restrictions.
For the avoidance of doubt, data and other information which any CUSC Party is permitted or obliged to divulge or publish to any other CUSC Party pursuant to the CUSC shall not necessarily be regarded as being in the public domain by reason of being so divulged or published.
Notwithstanding any other provision of the CUSC, the provisions of this Paragraph 6.15 shall continue to bind a person after its cessation as a CUSC Party for whatever reason.
Where The Company and a User are parties to an Interface Agreement in relation to a connection under the CUSC, the confidentiality provision in that agreement shall be deemed to include the changes which have been made to this Paragraph 6.15 consequent to the introduction of the EMR Documents.
DATA Data of a technical or operational nature collected recorded or otherwise generated pursuant to the CUSC or any relevant Bilateral Agreement shall be deemed data lodged pursuant to the Grid Code to the extent that the Grid Code makes provision therefore.
Not Used
INTELLECTUAL PROPERTY Subject to Paragraph 8.15.7, all Intellectual Property relating to the subject matter of the CUSC or any Bilateral Agreement or Mandatory Services Agreement conceived, originated, devised, developed or created by a CUSC Party, its officers, employees, agents or consultants during the currency of the CUSC or any Bilateral Agreement or Mandatory Services Agreement shall vest in such CUSC Party as sole beneficial owner thereof save where the CUSC Parties agree in writing otherwise.
FORCE MAJEURE If any CUSC Party (the "Non-Performing Party") shall be unable to carry out any of its obligations under the CUSC, the relevant Bilateral Agreement and/or Mandatory Services Agreement due to a circumstance of Force Majeure the CUSC and the relevant Bilateral Agreements or Mandatory Services Agreements shall remain in effect but:
the Non-Performing Party's relevant obligations;
the obligations of each of the other CUSC Parties owed to the Non-Performing Party under the CUSC and/or the relevant Bilateral Agreements or Mandatory Services Agreements as the case may be; and 6.19.3 any other obligations of such other CUSC Parties under the CUSC owed between themselves which the relevant CUSC Party is unable to carry out directly as a result of the suspension of the Non-Performing Party's obligations shall be suspended for a period equal to the circumstance of Force Majeure provided that:
the suspension of performance is of no greater scope and of no longer duration than is required by the Force Majeure;
no obligations of any CUSC Party that arose before the Force Majeure causing the suspension of performance are excused as a result of the Force Majeure; (c ) the Non-Performing Party gives the other CUSC Parties prompt notice describing the circumstance of Force Majeure, including the nature of the occurrence and its expected duration, and continues to furnish regular reports with respect thereto during the period of Force Majeure;
the Non-Performing Party uses all reasonable efforts to remedy its inability to perform; and
as soon as practicable after the event which constitutes Force Majeure the CUSC Parties shall discuss how best to continue their operations so far as possible in accordance with the CUSC, any Bilateral Agreements or Mandatory Services Agreements and the Grid Code.
WAIVER No delay by or omission of a CUSC Party in exercising any right power, privilege or remedy under this CUSC, any Bilateral Agreement or any Construction Agreement or any Mandatory Services Agreement or the Grid Code shall operate to impair such right, power, privilege or remedy or be construed as a waiver thereof. Any single or partial exercise of any such right, power, privilege or remedy shall not preclude any other or future exercise thereof or the exercise of any other right, power, privilege or remedy.
Save to the extent otherwise expressly provided in the CUSC, any Mandatory Services Agreement or Bilateral Agreement, any notice or other communication to be given by one CUSC Party to another under, or in connection with the matters contemplated by, the CUSC shall be addressed to the recipient and sent to the address, or email address of such other CUSC Party as that CUSC Party may have notified the other for the purpose and marked for the attention of the company secretary or to such other address, and/or email address and/or marked for such other attention as such other CUSC Party may from time to time specify by notice given in accordance with this Paragraph 6.21 to the CUSC Party giving the relevant notice or other communication to it.
Save as otherwise expressly provided in the CUSC, any notice or other communication to be given by any CUSC Party to any other CUSC Party under, or in connection with the matters contemplated by, the CUSC shall be in writing and shall be given by letter delivered by hand or sent by first class prepaid post (airmail if overseas) or email, and shall be deemed to have been received:
in the case of delivery by hand, when delivered; or 6.21.2.2 in the case of first class prepaid post, on the second day following the day of posting or (if sent airmail from overseas) on the fifth day following the day of posting; or 6.21.2.3 in the case of email, when delivered to the email address (where such delivery occurs before 17.00 hours on the day of delivery) and in any other case on the day of following the day of delivery.
Where CUSC expressly provides for notices or other communication to be by electronic means or a CUSC Party otherwise agrees this with another CUSC Party, the electronic communication shall be addressed and sent to the address provided for this purpose and shall, subject to Paragraph 6.21.4, be deemed to have been received one hour after it has been sent in the absence of an undeliverable return receipt received by the sender during that period.
If the time at which any notice or communication sent by e-mail is deemed to have been received falls after 17.00 hours on a day, the notice or communication shall be deemed to have been received at the start of the next Business Day.
Where a notice or communication is sent by e-mail, the CUSC Party giving the notice or communication shall (but without prejudice to Paragraph 6.21.3), if requested by the recipient CUSC Party resend, as soon as reasonably practicable, the notice or communication by e-mail
This Paragraph shall apply only to Users acting in their capacity as Trading Parties (as defined in the Balancing and Settlement Code) who are responsible for Small Power Stations which are Embedded. In addition to the other provisions of this Paragraph 6.21 of the CUSC, any notice or other communications to be served upon the User under the provisions of Paragraph 5.4 shall in each case be served by any one of the senior managers of The Company whose names, posts, locations, telephone and email addresses have been provided to the User by The Company for that purpose. In the case where an application, notice or other communication is to be made by the User to The Company under the provisions of Section 5 such application, notice or other communication shall be made by any one of the senior managers whose names, posts, location, telephone and email addresses have been provided to The Company by the User for that purpose. Both parties shall be under an obligation to keep each other notified in writing of changes to the lists of senior managers exchanged between them.
Subject to the remainder of this Paragraph 6.22, a Relevant Transmission Licensee may rely upon and enforce the terms of Paragraph 6.12.3, against a CUSC Party (other than The Company) as specified therein.
The third party rights referred to in Paragraph 6.22.1 (and any other terms of the CUSC which expressly provide that a third party may in their own right enforce a term of the CUSC) may only be enforced by the relevant third party subject to and in accordance with the provisions of the Contracts (Rights of Third Parties) Act 1999 and all other relevant terms of this CUSC.
Notwithstanding any other provisions of the CUSC, the CUSC Parties may (pursuant to section 8), amend the CUSC without recourse to the consent of a third party and accordingly, section 2(1) of the Contracts (Rights of Third Parties) Act 1999 shall not apply, save that, where and to the extent that any amendment to the CUSC would have an impact on the rights of third parties conferred under Paragraph 6.22.1, then The Company shall bring such impact to the attention of CUSC Parties and third persons to the extent that such impact is not already brought to their attention in an Amendment Proposal by the Proposer.
Except as provided in Paragraph 6.22.1 (or insofar as the CUSC otherwise expressly provides that a third party may in its own right enforce a term of the CUSC), a person who is not a CUSC Party has no right under the Contracts (Rights of Third Parties) Act 1999 to rely upon or enforce any term of the CUSC but this does not affect any right or remedy of a third party which exists or is available apart from that Act.
Subject and without prejudice to Section 7 and to Paragraph 6.23.4 below, all the CUSC Parties irrevocably agree that only the courts of England and Wales and the courts of Scotland are to have jurisdiction to settle any disputes which may arise out of or in connection with the CUSC including the Grid Code and any Bilateral Agreement or Mandatory Services Agreement and that accordingly any suit, action or proceeding (together in this Paragraph 6.23 referred to as "Proceedings") arising out of or in connection with the CUSC and any Bilateral Agreement or Mandatory Services Agreement may be brought in such courts.
Each CUSC Party irrevocably waives any objection which it may have now or hereafter to the laying of the venue of any Proceedings in any such court as is referred to in this Paragraph 6.23 and any claim that any such Proceedings have been brought in an inconvenient forum and further irrevocably agrees that judgement in any Proceedings brought in the courts of England and Wales or the courts of Scotland shall be conclusive and binding upon such CUSC Party and may be enforced in the courts of any other jurisdiction.
Each CUSC Party which is not incorporated in any part of Great Britain agrees that if it does not have, or shall cease to have, a place of business in Great Britain it will promptly appoint, and shall at all times maintain, a person in Great Britain irrevocably to accept service of process on its behalf in any Proceedings in Great Britain. For the avoidance of doubt nothing contained in Paragraphs 6.23.1 to 6.23.3 above shall be taken as permitting a CUSC Party to commence Proceedings in the courts where the CUSC otherwise provides for Proceedings to be referred to arbitration or to the Authority.
COUNTERPARTS Any Bilateral Agreement or Mandatory Services Agreement or Accession Agreement may be executed in any number of counterparts and by the different parties on separate counterparts, each of which when executed and delivered shall constitute an original, but all the counterparts shall together constitute one and the same instrument.
GOVERNING LAW The CUSC and each Bilateral Agreement and Mandatory Services Agreement shall be governed by and construed in all respects in accordance with English law.
SEVERANCE OF TERMS If any provision of the CUSC or any Bilateral Agreement or Mandatory Services Agreement is or becomes or is declared invalid, unenforceable or illegal by the courts of any competent jurisdiction to which it is subject or by order of any other Competent Authority such invalidity, unenforceability or illegality shall not prejudice or affect the remaining provisions of the CUSC or any Bilateral Agreement or Mandatory Services Agreement which shall continue in full force and effect notwithstanding such invalidity, unenforceability or illegality.
LANGUAGE Each notice, instrument, certificate or other document to be given by one CUSC Party to another under the CUSC shall be in the English language.
MCUSA The CUSC Parties agree that for the purposes of cross references in documents existing as at the date of the introduction of the CUSC, the CUSC, Bilateral Agreements, Construction Agreements and Agreements to Vary shall be regarded as the MCUSA and the relevant “Supplemental Agreements” and any relevant Agreements for Construction Works and relevant Agreements to Vary.
BSC Each and every User connected to or using the National Electricity Transmission System shall be a BSC Party except for:
Non-Embedded Customers being supplied by a Trading Party;
A User acting in the category of Exempt Power Station where another party is responsible under the BSC for the export from such Exempt Power Station;
A User acting in the category of an Embedded Exemptable Large Power Station where another party is responsible under the BSC for the export from such Embedded Exemptable Large Power Station.
Transmission Entry Capacity
Decrease in Transmission Entry Capacity
Subject to payment of the Cancellation Charge, each User shall be entitled to decrease the Transmission Entry Capacity for the Connection Site or site of Connection once the Power Station to which it relates has been Commissioned upon giving The Company not less than five Business Days notice in writing.
The Company shall as soon as practicable after receipt of such notice issue a revised Appendix C for the purposes of the relevant Bilateral Agreement reflecting the decrease in the Transmission Entry Capacity.
The decrease in the Transmission Entry Capacity shall take effect on the first of April following the expiry of the notice period stated in the notice from the User.
In addition to its obligation to pay the Use of System Charges until the reduction in Transmission Entry Capacity takes effect, the User shall, depending on the length of notice given, pay to The Company the Cancellation Charge. The Company shall calculate any Cancellation Charge due from the User on receipt of the notice of reduction of Transmission Entry Capacity from the User and advise the User accordingly. Unless a User wishes to make alternative arrangements regarding earlier payment, The Company shall invoice the User for the Cancellation Charge by (but no earlier than) 28 days prior to the end of the Financial Year in which the decrease in Transmission Entry Capacity is to take effect. The Cancellation Charge shall be payable within 28 days of the date of The Company’s invoice in respect thereof.
Increase in Transmission Entry Capacity Each User shall be entitled to request an increase in its Transmission Entry Capacity for a Connection Site up to a maximum of the Connection Entry Capacity for the Connection Site and such request shall be deemed to be a Modification for the purposes of the CUSC but with the words “as soon as practicable… not more than 3 months after” being read in the context of such Modification as being “within 28 days where practicable and in any event not more than 3 months (save where the Authority consents to a longer period) after”.
Exchange Rate Requests
The Company shall establish and maintain a TEC Register published on The Company Website recording the details set out in 6.30.3.2.
The TEC Register shall set out the name of the User, the Connection Site (or in the case of an Embedded Generator site of connection), the Transmission Entry Capacity, the year of connection to (or in the case of an Embedded Generator the year of the use of) the National Electricity Transmission System in respect of any Bilateral Agreements (and whether they are Gate 1 Agreements or Gate 2 Agreements) or agreements to change a User’s Transmission Entry Capacity.
The details of the Bilateral Agreement or agreements to change a User’s Transmission Entry Capacity shall be recorded on the TEC Register within 5 Business Days of the completion of such agreements.
Subject to the payment of the fee as outlined in the Charging Methodology Statements, The Company shall, after receipt of an Exchange Rate Request calculate the Exchange Rate as soon as practicable but in any event not more than 3 months after such request is received.
In the event that the parties which to proceed with a TEC Trade on the basis of the Exchange Rate then the User shall notify The Company and effective from the following 1 April, The Company shall revise the Bilateral Agreements (as appropriate) provided.
Background A User, who is party to a Bilateral Connection Agreement or Bilateral Embedded Generation Agreement may make a STTEC Request to The Company in accordance with this Paragraph of the CUSC.
Form of STTEC Request
A STTEC Request must be received by The Company by the relevant date specified in Paragraph 6.31.6.5.
A STTEC Request must be made by email and must attach the STTEC Request Form duly completed and signed on behalf of the User.
A STTEC Request shall not be deemed received by The Company until the non-refundable STTEC Request Fee has been paid to The Company and until the emailed copy of the STTEC Request is received in accordance with Paragraph 6.21.2.3 of the CUSC.
The STTEC Request must specify whether it is a Request for a STTEC Authorisation or an Application for a STTEC Offer.
Each STTEC Request must state one STTEC Period only.
A STTEC Request must be for a STTEC Period within a 12 month period of receipt by The Company of the STTEC Request and the STTEC Period must not include any days within more than one Financial Year. The STTEC Request must include the minimum and maximum level of MW for the STTEC Period.
In respect of Power Stations directly connected to the National Electricity Transmission System, a User' s Transmission Entry Capacity plus the maximum figure requested (plus any STTEC previously granted for any part of the STTEC Period) must not exceed its total station Connection Entry Capacity.
Assessment by The Company of STTEC Requests
The Company may reject any STTEC Request that is not made in accordance with the provisions of this Paragraph 6.31.
The Company will assess STTEC Requests and whether or not to grant STTEC Requests at its absolute discretion.
The Company will start assessing a STTEC Request no later than the relevant date specified in Paragraph 6.31.6.5.
If The Company has received more than one STTEC Request for a STTEC Period with the same start date, The Company will:
assess any Requests for a STTEC Authorisation before assessing any Applications for a STTEC Offer;
assess Requests for a STTEC Authorisation on a first come first served basis such that the Request for a STTEC Authorisation received earliest in time by The Company (as recorded by The Company) will be assessed first and then the Request for a STTEC Authorisation received next in time after that, and so on;
assess Applications for a STTEC Offer on a first come first served basis such that the Application for a STTEC Offer received earliest in time by The Company (as recorded by The Company) will be assessed first and then the Application for a STTEC Offer received next in time after that, and so on.
No priority will be given to any Users who have previously made successful STTEC Requests or LDTEC Requests.
Notification by The Company
Each User confirms and agrees that The Company shall have no liability to it for any STTEC Request which The Company does not grant in accordance with this Paragraph 6.31.
The Company is not obliged to grant any STTEC Request submitted.
A STTEC Request will only be granted at a level within the maximum and minimum range in MW submitted by the User.
STTEC Requests will be granted for a uniform amount of MW for the STTEC Period.
No STTEC Request will be granted if the maximum figure in the STTEC Request would together with the User's Transmission Entry Capacity (plus any STTEC previously granted for any part of the STTEC Period) exceeds the total station Connection Entry Capacity.
The Company shall notify a User who has made a STTEC Request by no later than the relevant date referred to at Paragraph 6.31.6.6, whether or not The Company grants the User's STTEC Request.
Charging, Invoicing and Payment
Each User must pay the STTEC Charge even if the User does not use the corresponding STTEC.
The provisions of Section 3 shall apply in respect of the STTEC Charge.
The provisions of Section 6.6 shall apply in respect of payment of the STTEC Charge.
General
Each Request for a STTEC Authorisation will constitute an unconditional and irrevocable offer by the User to The Company to buy Short Term Capacity (on a station basis) up to the quantity (in whole MW) stated in the STTEC Request for the STTEC Period and at the relevant price per MW set out in the Statement of Use of System Charges and upon the terms and conditions of CUSC. A Request for a STTEC Authorisation is capable of being accepted by The Company. Notification by The Company that it has granted the Request for a STTEC Authorisation in accordance with Paragraph 6.31.4.6 constitutes acceptance by The Company of the Request for a STTEC Authorisation. The notification of STTEC Authorisation will:-
state the level in MW (within the maximum and minimum range requested by the User) granted for the STTEC Period;
include a revised Appendix C to the relevant Bilateral Connection Agreement or Bilateral Embedded Generation Agreement (as appropriate) which will detail the STTEC and the STTEC Period for which this applies and The Company and the User agree that Appendix C to the relevant Bilateral Agreement will be deemed to be that notified in accordance with this Paragraph 6.31.6 for the STTEC Period, unless otherwise amended in accordance with such Bilateral Agreement or the CUSC. Upon expiry of the STTEC Period the provisions in Appendix C that relate to such STTEC for that STTEC Period shall cease to have effect;
state the STTEC Charge.
Each Application for a STTEC Offer is an application for the right to buy Short Term Capacity (on a station basis) up to the quantity (in whole MW) stated in the STTEC Request for the STTEC Period at the relevant price per MW set out in the Statement of Use System Charges and upon the terms and conditions of CUSC. Once an Application for a STTEC Offer has been received by The Company it cannot be withdrawn without the written consent of The Company. Notification by The Company that it has granted the Application for a STTEC Offer in accordance with Paragraph 6.31.4.5 will constitute a STTEC Offer.
A STTEC Offer shall:
state the level in MW of STTEC (within the maximum and minimum range requested by the User) offered for the STTEC Period;
include a revised Appendix C to the relevant Bilateral Connection Agreement or Bilateral Embedded Generation Agreement (as appropriate) which will detail the STTEC and the STTEC Period for which this applies and The Company and the User agree that, if the User accepts the STTEC Offer in accordance with Paragraph 6.31.6.4, Appendix C to the relevant Bilateral Agreement will be deemed to be that notified in accordance with this Paragraph 6.31 for the STTEC Period, unless otherwise amended in accordance with such Bilateral Agreement or the CUSC. Upon expiry of the STTEC Period the provisions in Appendix C that relate to such STTEC for that STTEC Period shall cease to have effect;
state the STTEC Charge.
be open for acceptance by the User within 24 hours of receipt of the emailed copy of the STTEC Offer.
A User may accept a STTEC Offer within 24 hours of receipt of the emailed copy of the STTEC Offer. Acceptance of a STTEC Offer shall be made by the User executing and emailing back the Appendix C sent to the User as part of the STTEC Offer. A STTEC Offer lapses if not accepted within such period.
The dates referred to at Paragraphs 6.31.2.1 and 6.31.3.3 are:-
in the case of a Request for a STTEC Authorisation, six weeks before the start date for the STTEC Period; and
in the case of an Application for a STTEC Offer, two weeks before the start date for the STTEC Period.
The date referred to at Paragraph 6.31.4.6 is:-
in the case of a Request for a STTEC Authorisation, four weeks before the start date for the STTEC Period;
in the case of an Application for a STTEC Offer, seven days before the start date for the STTEC Period.
The Company may publish the following information in respect of STTEC Authorisations, and STTEC Offers which are accepted:- 1. details of the STTEC Period;
maximum and minimum amount in MW requested;
identity of the User;
the Connection Site or site of Connection, in such form and manner as shall be prescribed by The Company from time to time.
The Company may publish the following information in respect of Requests for a STTEC Authorisation and Applications for a STTEC Offer which in either case are not granted and STTEC Offers which are not accepted:- 1. details of the STTEC Period;
maximum and minimum amount in MW requested, in such form and manner as shall be prescribed by The Company from time to time.
The User consents to the publication by The Company of the information referred to above.
Background A User, who is party to a Bilateral Connection Agreement or Bilateral Embedded Generation Agreement may make an LDTEC Request to NGC in accordance with this Paragraph of the CUSC.
Form of LDTEC Request
An LDTEC Request must be received by NGC no later than:
in cases where the requested LDTEC Period is 9 months or exceeds 9 months, 7 weeks and one Business Day before the start date for the LDTEC Period;
in cases where the requested LDTEC Period is 6 months or exceeds 6 months but is less than 9 months, 5 weeks and one Business Day before the start date for the LDTEC Period;
in cases where the requested LDTEC Period is 3 months or exceeds 3 months but is less than 6 months, 4 weeks and one Business Day before the start date for the LDTEC Period;
in cases where the requested LDTEC Period is less than 3 months, 3 weeks and one Business Day before the start date for the LDTEC Period.
An LDTEC Request must be made by email and must attach the LDTEC Request Form duly completed and signed on behalf of the User.
An LDTEC Request shall not be deemed received by NGC until the LDTEC Request Fee has been paid to NGC and until the emailed copy of the LDTEC Request is received in accordance with Paragraph 6.32.2.2 of the CUSC.
Each LDTEC Request must state whether it is for an LDTEC Block Offer only, an LDTEC Indicative Block Offer only or for both an LDTEC Block Offer and an LDTEC Indicative Block Offer and must specify one LDTEC Period only.
An LDTEC Request cannot be made prior to the start of the Financial Year to which it relates. The LDTEC Request must state the LDTEC Period and include the minimum and maximum level of MW for the LDTEC Period which, for the avoidance of doubt, must be the same for any LDTEC Block Offer and LDTEC Indicative Block Offer in the same LDTEC Request.
In respect of Power Stations directly connected to the National Electricity Transmission System, a User’s Transmission Entry Capacity plus the maximum MW figure requested in any LDTEC Request (plus any STTEC or LDTEC previously granted for any part of the LDTEC Period) must not exceed its total station Connection Entry Capacity.
Assessment by NGC of LDTEC Requests
NGC may reject any LDTEC Request that is not made in accordance with the provisions of this Paragraph 6.32.
NGC will assess LDTEC Requests and whether or not to grant LDTEC Requests at its absolute discretion.
Subject to Paragraphs 6.32.3.4 and 6.32.3.5, NGC will start assessing an LDTEC Request no later than:
in cases where the requested LDTEC Period is 9 months or exceeds 9 months, 7 weeks and one Business Day before the start date for the LDTEC Period;
in cases where the requested LDTEC Period is 6 months or exceeds 6 months but is less than 9 months, 5 weeks and one Business Day before the start date for the LDTEC Period;
in cases where the requested LDTEC Period is 3 months or exceeds 3 months but is less than 6 months, 4 weeks and one Business Day before the start date for the LDTEC Period;
in cases where the requested LDTEC Period is less than 3 months, 3 weeks and one Business Day before the start date for the LDTEC Period.
If NGC receives more than one LDTEC Request for an LDTEC Period or a STTEC Request or a TEC Increase Request which NGC believes will impact on each other, NGC will assess such requests and the capacity available on the National Electricity Transmission System on a first come first served basis such that the request received earliest in time by NGC (as recorded by NGC) will be considered first in terms of capacity available and then the request received next in time after that, and so on.
Where Paragraph 6.32.3.4 applies and the TEC Increase Request was received before the LDTEC Request NGC shall be entitled to suspend the assessment and making of the LDTEC Offer in respect of such LDTEC Request as necessary to enable it to make an offer in respect of the TEC Increase Request.
Where the circumstances in Paragraph 6.32.3.5 apply NGC shall as soon as practicable advise the User of such suspension giving an indication of the timescale for the LDTEC Offer. The User shall be entitled to withdraw its LDTEC Request in such circumstances.
No priority will be given to any Users who have previously made successful STTEC Requests or LDTEC Requests.
Notification by NGC
Each User confirms and agrees that NGC shall have no liability to it for any LDTEC Request which NGC does not grant in accordance with this Paragraph 6.32.
NGC is not obliged to grant any LDTEC Request submitted.
An LDTEC Request will only be granted within the maximum and minimum range in MW submitted by the User.
No LDTEC Request will be granted if the maximum MW figure in the LDTEC Request would together with the User’s Transmission Entry Capacity (plus any STTEC or LDTEC previously granted for any part of the LDTEC Period) exceed the total station Connection Entry Capacity.
NGC shall no later than seven days and one Business Day before the start date for the LDTEC Period, either make an LDTEC Offer in response to the User’s LDTEC Request or notify such User that it does not intend to grant an LDTEC Request.
Charging, Invoicing and Payment
Each User must pay the LDTEC Charge even if the User does not use the corresponding LDTEC.
The provisions of Section 3 shall apply in respect of the LDTEC Charge.
The provisions of Section 6.6 shall apply in respect of payment of the LDTEC Charge.
LDTEC Offers
An LDTEC Block Offer shall:
state the LDTEC Profile ;
include a revised Appendix C to the relevant Bilateral Connection Agreement or Bilateral Embedded Generation Agreement (as appropriate) which will detail the LDTEC Profile and the LDTEC Period for which this applies; and
be open for acceptance by the User within one Business Day of receipt of the emailed copy of the LDTEC Offer.
An LDTEC Indicative Block Offer shall:
state the LDTEC Indicative Profile ;
include a revised Appendix C to the relevant Bilateral Connection Agreement or Bilateral Embedded Generation Agreement (as appropriate) which will detail the LDTEC Indicative Profile and the LDTEC Period for which this applies;
state the Available LDTEC for the first seven LDTEC Weeks within the LDTEC Indicative Profile; and
and be open for acceptance by the User within one Business Day of receipt of the emailed copy of the LDTEC Offer.
Where the LDTEC Offer comprises both an LDTEC Block Offer and an LDTEC Indicative Block Offer a User may only accept one or the other but not both.
A User may accept an LDTEC Block Offer within one Business Day of receipt of the emailed copy of the LDTEC Block Offer. Acceptance of an LDTEC Block Offer shall be made by the User executing and emailing back the accepted LDTEC Block Offer in which the User shall have either confirmed acceptance of the LDTEC Profile in full or confirmed acceptance of the LDTEC Profile with a cap throughout the profile at a specific MW figure (not exceeding the maximum MW figure in the LDTEC Profile). An LDTEC Block Offer lapses if not accepted within such period.
A User may accept an LDTEC Indicative Block Offer within one Business Day of receipt of the emailed copy of the LDTEC Indicative Block Offer. Acceptance of an LDTEC Indicative Block Offer shall be made by the User accepting the LDTEC Indicative Block Offer in which the User shall have completed the Requested LDTEC figure in MW (which figure shall not exceed the maximum level of MW in the LDTEC Request). An LDTEC Indicative Block Offer lapses if not accepted within such period. Notification of weekly available LDTEC
Where NGC has made an LDTEC indicative Block Offer to a User and this has been accepted in accordance with Paragraph 6.31.6.5 NGC will by 17.00 on the Friday prior to the eighth LDTEC Week and each subsequent Friday during the LDTEC Period send to the User by email an LDTEC Availability Notification which will state the Available LDTEC up to the Requested LDTEC for the LDTEC Week eight weeks ahead.
If the User accepts the LDTEC Offer made in accordance with Paragraph 6.32.6.4 or 6.32.6.5, for the LDTEC Period Appendix C to the relevant Bilateral Agreement will be that accepted by the User in accordance with Paragraph 6.32.6.4 or 6.32.6.5 as appropriate unless otherwise subsequently amended in accordance with such Bilateral Agreement or the CUSC. Upon expiry of the LDTEC Period such Appendix C as it relates to that LDTEC shall cease to have effect.
LDTEC reporting provisions
NGC may publish the following information in respect of LDTEC Requests which are accepted:- 1. details of the LDTEC Period;
maximum and minimum amount in MW requested;
identity of the User;
the Connection Site or site of Connection, in such form and manner as shall be prescribed by NGC from time to time.
NGC may publish the following information in respect of LDTEC Requests which in either case are not withdrawn and not granted and LDTEC Offers which are not accepted:- 1. details of the LDTEC Period;
maximum and minimum amount in MW requested, in such form and manner as shall be prescribed by NGC from time to time.
The User consents to the publication by NGC of the information referred to above.
Change from “NGC” to “The Company” The CUSC Parties agree that references to “NGC” in any relevant document as at the time and date for implementation of the Authority’s direction under CUSC Paragraph 8.23.1 approving the Proposed Amendment in respect of the change from “NGC” to “The Company” shall be read as reference to “The Company”.
Background Two Users that are party to a Bilateral Connection Agreement or Bilateral Embedded Generation Agreement may make a Temporary TEC Exchange in accordance with this Paragraph of the CUSC.
Form of Temporary TEC Exchange Rate Request
A Temporary TEC Exchange Rate Request must be received by The Company no later than:
in cases where the requested Temporary TEC Exchange Period is 9 months or more, 10 weeks and one Business Day before the start date for the Temporary TEC Exchange Period;
in cases where the requested Temporary TEC Exchange Period is 6 months or more but is less than 9 months, 7 weeks and one Business Day before the start date for the Temporary TEC Exchange Period;
in cases where the requested Temporary TEC Exchange Period is 3 months or more but is less than 6 months, 6 weeks and one Business Day before the start date for the Temporary TEC Exchange Period;
in cases where the requested Temporary TEC Exchange Period is less than 3 months, 4 weeks and one Business Day before the start date for the Temporary TEC Exchange Period.
A Temporary TEC Exchange Rate Request must be made by email and must attach the Temporary TEC Exchange Rate Request Form duly completed and signed by the Joint Temporary TEC Exchange Users.
A Temporary TEC Exchange Rate Request shall not be deemed received by The Company until the Temporary TEC Exchange Rate Request Fee has been paid to The Company and until the emailed copy of the Temporary TEC Exchange Rate Request is received in accordance with Paragraph 6.34.2.2 of the CUSC.
Each Temporary TEC Exchange Rate Request must state one Temporary TEC Exchange Period only. Each Temporary TEC Exchange Rate Request must be by reference to whole MW only.
A Temporary TEC Exchange Rate Request cannot be made prior to the start of the Financial Year to which it relates.
A Temporary TEC Exchange Rate Request cannot be made unless The Company has published within that Financial Year a Temporary TEC Exchange Notification of Interest Form from the Temporary TEC Exchange Donor User.
In respect of Power Stations directly connected to the National Electricity Transmission System, a User’s Transmission Entry Capacity plus any Temporary Received TEC plus any STTEC or LDTEC less any Temporary Donated TEC must not exceed its total station Connection Entry Capacity.
A Temporary TEC Exchange Rate Request can be withdrawn at any time upon written notice from the Joint Temporary TEC Exchange Users.
The Temporary Donated TEC stated in a Temporary TEC Exchange Rate Request shall not exceed the Transmission Entry Capacity of the Temporary TEC Exchange Donor User.
Assessment by The Company of Temporary TEC Exchange Rate Requests
The Company may reject any Temporary TEC Exchange Rate Request that is not made in accordance with the provisions of this Paragraph 6.34.
The Company will assess Temporary TEC Exchange Rate Requests and whether or not to grant Temporary TEC Exchange Rate Requests at its absolute discretion.
Subject to Paragraph 6.34.3.4 and 6.34.3.5 The Company will start assessing an Temporary TEC Exchange Rate Request no later than:
in cases where the requested Temporary TEC Exchange Period is 9 months or more, 10 weeks and one Business Day before the start date for the Temporary TEC Exchange Period;
in cases where the requested Temporary TEC Exchange Period is 6 months or more but is less than 9 months, 7 weeks and one Business Day before the start date for the Temporary TEC Exchange Period;
in cases where the requested Temporary TEC Exchange Period is 3 months or more but is less than 6 months, 6 weeks and one Business Day before the start date for the Temporary TEC Exchange Period;
in cases where the requested Temporary TEC Exchange Period is less than 3 months, 4 weeks and one Business Day before the start date for the Temporary TEC Exchange Period.
If The Company receives more than one Temporary TEC Exchange Rate Request for a Temporary TEC Exchange Period or a STTEC Request or an LDTEC Request or a TEC Increase Request which The Company believes will impact on each other, The Company will assess such requests and the capacity available on the National Electricity Transmission System on a first come first served basis such that the request received earliest in time by The Company (as recorded by The Company) will be considered first in terms of capacity available and then the request received next in time after that, and so on.
Where Paragraph 6.34.3.4 The Company shall be entitled to suspend the assessment and making of the Temporary TEC Exchange Rate Offer in respect of such Temporary TEC Exchange Rate Request or the LDTEC Offer in respect of such LDTEC Request or the STTEC Offer in respect of such STTEC Request or the Offer in respect of such TEC Increase Request.
Where the circumstances in Paragraph 6.34.3.5 apply The Company shall as soon as practicable advise the Joint Temporary TEC Exchange Users of such suspension giving an indication of the timescale for the Temporary Exchange Rate Offer. Where both Joint Temporary TEC Exchange Users agree, the Temporary TEC Exchange Rate Request can be withdrawn in such circumstances.
No priority will be given to any Users who have previously made successful STTEC Requests or LDTEC Requests or Temporary TEC Exchange Rate Requests.
Notification by The Company
Each User confirms and agrees that The Company shall have no liability to it for any Temporary TEC Exchange Rate Request which The Company does not grant in accordance with this Paragraph 6.34.
The Company is not obliged to grant any Temporary TEC Exchange Rate Request submitted.
Any Temporary TEC Exchange Rate Request will only be granted provided that during the Temporary TEC Exchange Period the User’s Transmission Entry Capacity plus the Temporary Received TEC plus any STTEC or LDTEC less any Temporary Donated TEC does not exceed its total station Connection Entry Capacity.
The Company shall no later than seven days and one Business Day before the start date for the Temporary TEC Exchange Period, by 17:00 on a Business Day either make an Temporary TEC Exchange Rate Offer in response to the Temporary TEC Exchange Rate Request or notify the Joint Temporary TEC Exchange Users that it does not intend to grant a Temporary TEC Exchange Rate Request.
Charging, Invoicing and Payment
Each Temporary TEC Exchange Recipient User must pay the LDTEC Charge in respect of the Temporary Received TEC even if the User does not use the corresponding Temporary Received TEC.
Temporary TEC Exchange Rate Offers
A Temporary TEC Exchange Rate Offer shall:
be made to both the Temporary TEC Exchange Donor User and the Temporary TEC Exchange Recipient User and state the Temporary Donated TEC and Temporary TEC Exchange Rate;
include in the offer sent to the Temporary TEC Exchange Donor User a revised Appendix C to the relevant Bilateral Connection Agreement or Bilateral Embedded Generation Agreement (as appropriate) of the Temporary TEC Exchange Donor User which will detail the Temporary Donated TEC and the Temporary TEC Exchange Period for which this applies; (iiii) include in the offer sent to the Temporary TEC Exchange Recipient User a revised Appendix C to the relevant Bilateral Connection Agreement or Bilateral Embedded Generation Agreement (as appropriate) of the Temporary TEC Exchange Recipient User which will detail the Temporary Received TEC and the Temporary TEC Exchange Period for which this applies; and
be open for acceptance by receipt of the emailed copy of the Temporary TEC Exchange Rate Offer up to 17:00 the following Business Day.
A Temporary TEC Exchange Rate Offer must be accepted by both the Joint Temporary TEC Exchange Users within the timescales in Paragraph 6.34.6.2(iii). Acceptance of a Temporary TEC Exchange Rate Offer shall be made by executing and emailing back the accepted Temporary TEC Exchange Rate Offer. A Temporary TEC Exchange Rate Offer lapses if not accepted by both Temporary TEC Exchange Users within such period.
If the Temporary TEC Exchange Rate Offer is accepted in accordance with Paragraph 6.34.6.2, for the Temporary TEC Exchange Period Appendix C to the relevant Bilateral Agreements will be that accepted by the Joint Temporary TEC Exchange Users, unless otherwise subsequently amended in accordance with such Bilateral Agreement or the CUSC. Upon expiry of the Temporary TEC Exchange Period such Appendix C as it relates to that Temporary TEC Exchange Period shall cease to have effect.
Temporary TEC Exchange reporting and information provisions
The Company may publish the following information in respect of Temporary TEC Exchange Rate Offers which are accepted:- 1. details of the Temporary TEC Exchange Period;
details of the Temporary Donated TEC and Temporary Received TEC;
the identity of the Temporary TEC Exchange Donor User and the Temporary TEC Exchange Recipient User;
the Connection Site or site of Connection, in such form and manner as shall be prescribed by The Company from time to time.
The Company may publish the following information in respect of Temporary TEC Exchange Rate Offers which are made are not accepted:- 1. details of the Temporary TEC Exchange Period;
details of the Temporary Donated TEC and Temporary Received TEC;
the identity of the Temporary TEC Exchange Donor User;
the Connection Site or site of Connection, in such form and manner as shall be prescribed by The Company from time to time.
The Company may publish the following information in respect of Temporary TEC Exchange Rate Offers not made:- 1. details of the Temporary TEC Exchange Period;
details of the Temporary Donated TEC;
the identity of the Temporary TEC Exchange Donor User;
the Connection Site or site of Connection, in such form and manner as shall be prescribed by The Company from time to time.
The Temporary TEC Exchange Donor User and the Temporary TEC Exchange Recipient User consent to the publication by The Company of the information referred to above.
A User may also from time to time request that The Company advise other Users that such User is interested in making a Temporary TEC Exchange. Such request must be sent by email using the Temporary TEC Exchange Notification of Interest Form.
The Company shall publish such Temporary TEC Exchange Notification of Interest Form on its TEC Register within 10 Business Days of its receipt.
Embedded Generator MW Register
The Company shall establish and maintain the Embedded Generator MW Register published on The Company Website recording the details set out in 6.34.2.
The Embedded Generator MW Register shall set out: - the name of Embedded Generator’s who have a BELLA (and whether it is a Gate 1 Agreement or Gate 2 Agreement) or who are a Relevant Embedded Power Station, - the site of connection to the Distribution System and the relevant Grid Supply Point, - the proposed year of connection to the Distribution System and - the maximum output of the Embedded Generator’s in MW’s as set out in the BELLA or provided by the Authorised Electricity Operator to whose Distribution System that Embedded Generator is to connect.
The Company shall record the details of any new BELLA’s or any changes to existing BELLA’s on the Embedded Generator MW Register within 5 Business Days of such agreements being entered into by The Company.
The Company shall record the details provided by the Authorised Electricity Operator in respect of a Relevant Embedded Power Station or any changes on the Embedded Generator MW Register within 5 Business Days of the relevant agreements being entered into relating to such Relevant Embedded Power Station between the Authorised Electricity Operator and The Company.
The Company shall establish and maintain a Transmission Works Register in respect of Transmission Works set out in (where they are Gate 2 Agreements) Generators’ and Interconnector Owners’ Construction Agreements and/or set out in the relevant Construction Agreement with the owner/operator of the Distribution System in respect of an Embedded Exemptable Large Power Station which is the subject of a BELLA (until such Transmission Works are completed) which it shall publish on The Company Website recording the details set out in Paragraph 6.36.2.
The Transmission Works Register shall in respect of each such Construction Agreement set out the name of the Generator or Interconnector Owner, the Connection Site or, where applicable, the Transmission Interface Site (or in the case of an Embedded Generator the site of connection), the Completion Date(s), and the Transmission Works which relate to such Construction Agreement (each as amended from time to time).
The details referred to a Paragraph 6.36.2 shall be recorded on the Transmission Works Register within 10 Business Days of the completion of such agreements or any changes to an existing agreement if such change affects any item in the Transmission Works Register.
All CUSC Users that are Generators that are not Restoration Contractors (as defined in the Grid Code) may submit claims during the annual claims submission month for the recovery of the cost of compliance with the new obligations imposed on them via Grid Code modification GC0156. Claims will be assessed by The Company as described in paragraph 6.37.5. All costs that are assessed as being payable shall be paid out as described in paragraph 6.37.7.
Generators that first sign a new Bilateral Agreement with The Company after the date of implementation of Grid Code GC0156, are not permitted to submit a claim
The claims submission month will initially be September in each year, save that claims shall not be possible in September 2023. However, in 2026, the claims submission month will be December 2026, and this will be the last ever claims window. From 31st December 2026, no more claims will be accepted.
The claims assessment process will involve a case-by-case assessment of claims for capital expenditure incurred in complying with the new obligations, with accompanying evidence to demonstrate that the costs incurred were necessary, reasonable, efficiently-incurred, and proportionate.
The Company will recover the costs of successful claims via Balancing Services Use of System Charges.
When a claim is approved, The Company will pay the claim over the following 12 month period that begins in April the year after the submission of the claim, in 12 equal monthly amounts. If a claim is approved after April in the calendar year after the submission of the claim, payment of the claim will be made in equal monthly amounts over the months remaining to the following March, inclusive.
Each claimant shall use reasonable endeavours, exercising Good Industry Practice, to identify if compliance with the GC0156 Grid Code requirements could be achieved at a materially lower cost by meeting a lesser technical requirement (such as by providing resilience at their asset for fewer than 72 hours) and if so, then they shall advise The Company accordingly and liaise with The Company about possible solutions associated with a request to The Authority for a derogation against the Grid Code to the lesser level of resilience. If appropriate, The Company shall seek a derogation from The Authority on that basis. If the derogation request has been denied, or has not been granted by 1st December 2026, then a claim can be submitted before 31st December 2026 for assessment by The Company as per this section 6.37.
The Secretary of State may issue a direction to The Company as referred to in condition B4 of The Company’s ESO Licence where in the opinion of the Secretary of State there is a risk relating to national security that may detrimentally impact the resilience, safety or security of the energy system, or the continuity of essential services, and it is in the interest of national security that a direction should be issued to The Company.
The Company must comply with any such direction that has been issued by the Secretary of State. Users should note that The Company is not required to comply with any other obligation in the ESO licence, where and to the extent that compliance with that obligation would be inconsistent with the requirement to comply with such a direction, for the period set out in the direction. This includes the requirement set out in condition E3 of The Company’s ESO licence to comply with this Grid Code.
The Company is required under condition B4 of its ESO Licence to inform the Secretary of State of any conflict with the obligations as identified in 6.38.2 as soon as reasonably practicable after the conflict is identified. The Company will include in such a notice, details of any identified impact or non-compliance that will be caused or will be likely to be caused to Users, and in such a case will also seek clarification of whether this can be shared with the affected User.
Where reasonably practicable and subject to the agreement of the Secretary of State to share any such specific details, The Company will inform affected Users as identified in 6.38.3 of what actions The Company will or has taken, or not taken, to comply with a direction or amended direction (including when such a direction is revoked) and what identified impact or non-compliance this will or is likely to cause to the User.
The Company's obligations under this code and any contracts made under this code shall be suspended without liability where and to the extent that compliance with any such obligation would be inconsistent with the requirement upon The Company to comply with a direction.
A User's obligations under this code and any contracts made under this code shall be suspended without liability where and to the extent that the User is unable to comply with any such obligation as a result of any action taken, or not taken, by The Company to comply with a direction.
The Secretary of State may at any time amend or revoke any direction issued to The Company as referred to in condition B4 of The Company’s ESO Licence.
Each Existing CUSC Contract shall be read and construed, with effect from the date on which The Company was designated as the ISOP, as if the defined terms within it, and the effect of those defined terms, had been amended in accordance with the changes to its corresponding proforma exhibit to the CUSC. Each User acknowledges and agrees that the provisions of this paragraph shall apply notwithstanding the provisions in the Existing CUSC Contract as to variation of those agreements.
The term “Existing CUSC Contract” means any one or more, as applicable for a particular User, of those contracts made under the CUSC and including but not limited to a Bilateral Connection Agreement, Bilateral Embedded Generation Agreement, Construction Agreement, Mandatory Services Agreement, Use of System Supply Confirmation Notice and Use of System Interconnector Confirmation Notice.
Advisory and Information Requests
The Company is required to provide advice, analysis or information to the Authority or to a Minister of the Crown when requested in accordance with section 171 of the Energy Act 2023 and condition D1 of the ESO Licence and GSP Licence.
The Company may by notice request from Users such information as it reasonably requires in connection with the exercise of any of its functions, in accordance with section 172 of the Energy Act 2023. It will do so by the issue of an Information Request Notice. The purposes of this may include to assist in the fulfilment of a request for advice, analysis or information as set out in 6.39.1.
The Company is required by condition D2 of the ESO Licence and GSP Licence to prepare, submit for approval by the Authority and publish on its website once approved an Information Request Statement that sets out further detail on the process The Company expects to follow when requesting information from other parties. The Information Request Statement must include, but need not be limited to, the following matters as set out in condition D2.5 of the ESO Licence and GSP Licence:
the process The Company expects to follow when issuing an Information Request Notice, including any further detail around the expected engagement between The Company and recipient of an Information Request Notice; and
the details to be included in an Information Request Notice issued by The Company.
A User to whom a request is made under 6.39.2 must, so far as reasonably practicable, provide the requested information within such reasonable period, and in such reasonable form and manner, as may be specified in the Information Request Notice.
The Company must, unless the Authority otherwise consents, maintain for a period of 6 years and provide to the Authority where required a record of information requests as detailed in condition D2.12 of the ESO Licence and GSP Licence including
a copy of the Information Request Notice;
any subsequent variations to the original information requested;
the recipient’s response to the notice, including any refusal or challenges to the notice or requested information;
the time taken for the recipient to provide the requested information;
the manner and form the information was provided in; and
the information provided in response to the notice, and whether such information complied, in The Company’s view, with the Information Request Notice. Communications Plant (CC.6.5) - Appendix 1 Power Station Located Adjacent to the Transmission Substation Communications Plant (CC.6.5) - Appendix 1 Power Station Not Located Adjacent to the Transmission Substation Electronic Communication Platform The Company. Create an account to access the The Company will provide registration (CC.6.5.9) Electronic Communication Platform information for the User to access the using the registration information Electronic Communications Platform. provided by The Company. The User will provide a stable internet connection which will be required to access the Electronic Communications Platform. Communications Plant (CC.6.5) - Appendix 1 Demand Electronic Communication Platform The Company. Create an account to access the The Company will provide registration (CC.6.5.9) Electronic Communication Platform information for the User to access the using the registration information Electronic Communications Platform. provided by The Company. The User will provide a stable internet connection which will be required to access the Electronic Communications Platform. Appendix 2 Operating Metering (CC.6.5.6)
| Description | Source | Work | Provided By | Notes |
|---|---|---|---|---|
| Control Telephone (CC.6.5.2) | Transmission Substation Exchange. | User to install free issue handset on dedicated communications circuit. User to install wiring from User control room to Transmission substation exchange. | Wiring to be provided by User. The Company to provide handset only. | Where the power station is located immediately adjacent to the Transmission substation. |
| Extension Bell (CC.6.5.3) | Transmission Substation Exchange. | User to install free issue extension bell on dedicated communications circuit (separate cores from the control telephone). User to install wiring from User control room to Transmission substation exchange. | Wiring to be provided by User. The Company to provide bell only. | |
| PSTN (or other off-site communications circuits) for Telephony. (CC.6.5.2 to CC.6.5.5) | Public Telecommunications Operator (PTO). | The User shall provide their own off site communications paths. Data and speech required by The Company shall be cabled from the User site to the Transmission Substation Exchange. | Wiring to be provided by User. | |
| Telegraph Instructor (CC.6.5.7) | Transmission Marshalling Cubicles. | Wire out and install free issue display unit and driver (free issue) and communication connections to the Transmission Marshalling Cubicles. The Company to commission. | Wiring to be provided by User. The Company to provide display unit and driver. | |
| Electronic Data Communication Facilities (Electronic Despatch & Logging) (CC.6.5.8) | PTO. | User to install EDL terminal for submission of MEL and dynamics re- declarations and for bid and offer acceptance instructions. | User to provide EDL terminal. The Company to provide communications path to a site router associated with the EDL terminal in conjunction with the User. | |
| Facsimile Machine (CC.6.5.9) | PTO. | Install facsimile machine on dedicated communications circuit. | User to provide facsimile machine and wiring to PTO. | |
| Electronic Communication Platform (CC.6.5.9) | The Company. | Create an account to access the Electronic Communication Platform using the registration information provided by The Company. | The Company will provide registration information for the User to access the Electronic Communications Platform. The User will provide a stable internet connection which will be required to access the Electronic Communications Platform. |
| Description | Source | Work | Provided By | Notes |
|---|---|---|---|---|
| Control Telephone (CC.6.5.2) | Remote Telephone Equipment (RTE) unit. | User to install free issue handset on dedicated communications circuit. User to install wiring from User control room to Transmission Marshalling Cubicles. | Wiring to be provided by User. The Company to provide handset only. | Where the Power Station is not located immediately adjacent to the Transmission substation. |
| Extension Bell (CC.6.5.3) | RTE unit. | User to install free issue extension bell on dedicated communications circuit (separate cores from the control telephone). User to install wiring from User control room to Transmission Marshalling Cubicles. | Wiring to be provided by User. The Company to provide bell only. | |
| PSTN (or other off-site communications circuits) for Telephony. (CC.6.5.2 to CC.6.5.5) | Public Telecommunications Operator (PTO). | Duplicate offsite communications are preferred for security of data and speech transmission. If two outlet cables do not exist then the matter must be resolved on a site specific basis, to the satisfaction of The Company. | User to provide own outlet cables. | |
| Telegraph Instructor (CC.6.5.7) | Transmission Marshalling Cubicles. | Wire out and install free issue display unit and driver (free issue) and communication connections to the Transmission Marshalling Cubicles. The Company to commission. | Wiring to be provided by User. The Company to provide display unit and driver. | |
| Electronic Data Communication Facilities (Electronic Despatch & Logging) (CC.6.5.8) | PTO. | User to install EDL terminal for submission of MEL and dynamics re- declarations and for bid and offer acceptance instructions. | User to provide EDL terminal. The Company to provide communications path to a site router associated with the EDL terminal in conjunction with the User. | |
| Facsimile Machine (CC.6.5.9) | PTO. | Install facsimile machine on dedicated communications circuit. | User to provide facsimile machine and wiring to PTO. |
| Description | Source | Work | Provided By | Notes |
|---|---|---|---|---|
| Control Telephone (CC.6.5.2) | Remote Telephone Equipment (RTE) unit. | User to install free issue handset on dedicated communications circuit. User to install wiring from User control room to Transmission Marshalling Cubicles. | Wiring to be provided by User. The Company to provide handset only. | Demand Control Points (as defined in the Grid Code) |
| Extension Bell (CC.6.5.3) | RTE unit. | User to install free issue extension bell on dedicated communications circuit (separate cores from the control telephone). User to install wiring from User control room to Transmission Marshalling Cubicles. | Wiring to be provided by User. The Company to provide bell only. | |
| PSTN (or other off-site communications circuits) for Telephony. (CC.6.5.2 to CC.6.5.5) | Public Telecommunications Operator (PTO). | Duplicate offsite communications are preferred for security of data and speech transmission. If two outlet cables do not exist then the matter must be resolved on a site specific basis, to the satisfaction of The Company. | User to provide own outlet cables. | |
| Telegraph Instructor (If required by The Company) (CC.6.5.7) | Transmission Marshalling Cubicles. | Wire out and install free issue display unit and driver (free issue) and communication connections to the Transmission Marshalling Cubicles. The Company to commission. | Wiring to be provided by User. The Company to provide display unit and driver. | |
| Electronic Data Communication Facilities (Electronic Despatch & Logging) (CC.6.5.8) | PTO. | User to install EDL terminal for submission of MEL and dynamics re- declarations and for bid and offer acceptance instructions. | User to provide EDL terminal. The Company to provide communications path to a site router associated with the EDL terminal in conjunction with the User. | |
| Facsimile Machine (CC.6.5.9) | PTO. | Install facsimile machine on dedicated communications circuit. | User to provide facsimile machine and wiring to PTO. |
| Description | Source | Type | Work | Provided by | Notes |
|---|---|---|---|---|---|
| MW and MVAr for Balancing Mechanism Unit. | Settlement Metering (FMS). | Unit per Pulse | Provide dedicated outputs from the FMS (Final Metering Scheme) ‘check’ meters. Supply and install wiring to the OMS-FE. | User. | Used for Despatch Instructions and Ancillary Services Monitoring (ASM). For information, FMS meters are required under the Balancing and Settlement Code. Refer to the BSC. |
| Individual alternator MW and MVAr (applicable to multi-shaft machines). | Transducer or high accuracy output from User metering. | Unit per Pulse | Provide MW and MVAr transducer or high accuracy outputs. Supply and install wiring to the OMS-FE / Transmission Marshalling Cubicles. | User | Used for Network Modelling and ASM. If the User chooses to use transducers, the quality is to be agreed with The Company. LV monitoring is acceptable. |
| Individual unit transformer MW and MVAr. | Transducer or high accuracy output from User metering. | Unit per Pulse | Provide MW and MVAr transducer or high accuracy outputs. Supply and install wiring to the OMS-FE / Transmission Marshalling Cubicles. | User. | Used for Network Modelling. If the User chooses to use transducers, the quality is to be agreed with The Company. |
| Voltage for each generator connection to the Transmission substation. | Single Phase VT (usually a CVT) | AC Waveform | Provide VT secondary output (single phase). Supply and install transducer and wiring to the Transmission Marshalling Cubicles. | User. | For indication purposes. To feed Substation Voltage Selection Scheme. The Company to install Voltage Selection Scheme at Transmission substation as required. |
| Frequency for each Balancing Mechanism Unit. | High accuracy VT output (single phase). | AC Waveform | Provide high accuracy VT secondary output (single phase). Supply and install wiring to the Transmission Marshalling Cubicles. | User. | Used for ASM. |
| All generator circuit(s) LV circuit breaker(s) and disconnector(s) | Double point off dedicated auxiliary contacts (1 n/o and 1 n/c). | Status Indication | Wire out and cable between auxiliary contacts and Transmission Marshalling Cubicles. | User, in switchgear. | Dedicated auxiliary contacts are required. Repeat relays are not normally acceptable. |
| Unit transformer circuit breaker(s). | Double point off dedicated auxiliary contacts (1 n/o and 1 n/c). | Status Indication | Wire out and cable between auxiliary contacts and Transmission Marshalling Cubicles. | User, in switchgear. | Dedicated auxiliary contacts are required. Repeat relays are not normally acceptable. |
| All generator circuit(s) HV circuit breaker(s) and disconnector(s). | Double point off dedicated auxiliary contacts (1 n/o and 1 n/c). | Status Indication | Wire out and cable between auxiliary contacts and Transmission Marshalling Cubicles. | User, in switchgear. | Dedicated auxiliary contacts are required. Repeat relays are not normally acceptable. |
| Each generator transformer Tap Position Indication (TPI) | Dedicated tap changer auxiliary contact arm. | Tap Position Indication | Provide >one out of (up to) 19' position indications or TPI transducer indication. Wire out and cable between dedicated auxiliary contact arm and Transmission Marshalling Cubicles. | User, in transformer tap-changer. | Used for Network Modelling and ASM. |
SECTION 7: CUSC DISPUTE RESOLUTION
This section of the CUSC sets out how disputes under the CUSC, Bilateral Agreements, Mandatory Services Agreements and Construction Agreements are to be dealt with.
Under the ESO Licence, and in accordance with the power within section 7(3)(c) of the Act, it is provided for such matters arising under the CUSC as may be specified in the CUSC to be referred to the Authority for determination. Determining such matters also reflects consideration of utilisation of the power the Authority has under section 25 of the Act to take enforcement action in respect of any contravention of a licence obligation which would include any contravention of the obligations in respect of Connection Charges and Use of System Charges contained in the ESO Licence. The Charging Disputes provisions of the CUSC reflect the role under section 7(3)(c) of the Act and provide for such issues to be so referred to the Authority.
DISPUTES Subject to any contrary provision of the Act, any Licence or the Regulations, or an EMR Document, or the rights, powers, duties and obligations of the Authority or the Secretary of State under the Act, any Licence or otherwise howsoever, any dispute or difference between CUSC Parties of whatever nature howsoever arising under, out of or in connection with:- 7.2.1 whether Connection and/or Use of System Charges have been applied and/or calculated in accordance with the Charging Statements (including in all cases whether the dispute or difference does arise under, out of or in connection with such issues and therefore falls within this Paragraph 7.2.1) utilising the Authority’s role under section 7 of the Act (a “Charging Dispute”) shall be resolved in accordance with Paragraph 7.3;
the Construction Agreement shall be resolved in accordance with the specific provisions in that Construction Agreement;
the CUSC and Bilateral Agreements, and Mandatory Services Agreements not being a dispute of a type described in Paragraph 7.2.1 or 7.2.2 above (an "Other Dispute") shall be resolved in accordance with Paragraph 7.4;
a matter which relates to issues where a Customer has raised a dispute which may involve another CUSC Party (a “Third Party Dispute”) shall be resolved in accordance with Paragraph 7.5, and insofar as The Company and a User are parties to an agreement related to the CUSC and that agreement contains any dispute resolution provision to which the procedure in this section 7 does not apply, The Company and that User agree that such provision shall be subject to any contrary provision of an EMR Document.
Initial Discussions Where a Charging Dispute arises, a representative of The Company and each User concerned who has authority to resolve the dispute shall meet (including by agreement by telephone) within 10 Business Days of a request by either party (or within such longer period as may be agreed, acting reasonably) and seek to resolve it. If the parties to the dispute are unable to resolve it within 10 Business Days of the meeting (or within such longer period as they may agree within that initial 10 Business Day period, both parties acting reasonably as to the length of the period), then the parties’ obligations under this paragraph to undertake such discussions shall no longer apply in relation to that Charging Dispute. Reference to Authority
Subject to Paragraph 7.3.1, Charging Disputes shall be referred by either CUSC Party to the Authority for determination in accordance with Paragraph 7.2.1 above and shall not be capable of being referred to arbitration pursuant to the rules of the London Court of International Arbitration or otherwise, or to any court.
Charging Disputes During Other Disputes
Where, in conducting an arbitration under this Section 7, an arbitrator or panel of arbitrators finds themselves or itself considering a Charging Dispute (whether or not forming part of an Other Dispute), they or it shall have no jurisdiction to determine such Charging Dispute (with any dispute on whether it is a Charging Dispute being determined by the Authority as soon as reasonably practicable in accordance with the definition of Charging Dispute) and the parties shall immediately refer such Charging Dispute to the Authority for determination pursuant to Paragraph 7.2.1 above.
In such circumstances, if there are issues (the “Discrete Issues") under the Other Dispute which are entirely discrete from and can be determined without reference to the issues in the Charging Dispute, then resolution of the Discrete Issues can continue in accordance with the provisions of Paragraph 7.4; provided that if there is no Discrete Issue or issues under the Other Dispute the resolution of the Other Dispute shall be suspended until after the determination of the Charging Dispute. Application of Determination
It is expected that in most circumstances the Authority’s determination of a Charging Dispute will set out the effect of the determination in terms of the charges in dispute. Where such effect is not set out in detail (for example where a clear principle is stated which should be capable of clear application) then if there is a dispute as to the quantification of any amounts to be calculated by applying the determination that dispute shall be an Other Dispute. However, any dispute on the principles reflected in the determination shall be a Charging Dispute.
If the determination of the Charging Dispute is that there has been an over or under payment of a Connection Charge and/or Use of System Charge, The Company shall, subject to what the determination may state, pay to the relevant User, or the User shall pay to The Company, as the case may be, an amount equal to the over or under payment, together with interest thereon from the date the charges were paid until the date of payment of such interest. Such interest shall accrue from day to day at the rate specified in Paragraph 6.6.5.
The Authority's determination of a Charging Dispute shall (without prejudice to any ability to apply for judicial review of any determination) be final and binding on the parties to the dispute and shall be enforceable in the courts.
OTHER DISPUTES Initial Discussions
Where an Other Dispute arises, a representative of The Company and each User concerned who has authority to resolve the dispute shall meet (including by agreement by telephone) within 10 Business Days of a request by either party (or within such longer period as may be agreed, acting reasonably) and seek to resolve it. If the parties to the dispute are unable to resolve it within 10 Business Days of the meeting (or within such longer period as they may agree within that initial 10 Business Day period, both parties acting reasonably as to the length of the period), then the parties’ obligations under this paragraph to undertake such discussions shall no longer apply in relation to that Other Dispute. Either party may then refer the Other Dispute to arbitration pursuant to the rules of the London Court of International Arbitration in force from time to time.
Whatever the nationality, residence or domicile of any CUSC Party and wherever the Other Dispute or any part of it arose, the law of England shall be the proper law of reference to arbitration under this paragraph and in particular (but not so as to derogate from the generality of the foregoing) the provisions of the Arbitration Act 1996 shall apply to any such arbitration wherever it or any part of it shall be conducted.
Any arbitrator or panel of arbitrators appointed under this Paragraph 7.4 shall determine such issues as are referred to them consistently with any determination by the Authority of a Charging Dispute, whether or not relating to the same or different facts.
Subject to paragraph 7.4.5 the CUSC Parties hereby consent to the President of the London Court of International Arbitration deciding, at their discretion and ensuring, so far as practicable, that the proceedings relating to such a decision are managed effectively, fairly and expeditiously:
following the same process as set out in the London Court of International Arbitration rules in respect of pending arbitrations, that two or more disputes referred to it for arbitration (whether pending or underway), be consolidated or otherwise heard together (whether or not such disputes are all Other Disputes or an Other Dispute and any dispute(s) referred under the STC), where The Company or a CUSC Party (or a party to a dispute under the STC) so requests in writing to the London Court of International Arbitration copied to each of The Company and/or the other CUSC Parties (as the case may be) and relevant STC parties setting out the reasons for such consolidation; or
that a dispute referred to it (whether pending or underway and whether another dispute or a dispute referred to it under the STC) be stayed for a period not exceeding three months after the referral of such dispute to the London Court of International Arbitration, pending resolution of another dispute referred to it (whether pending or underway and whether an Other Dispute or a dispute referred under the STC).
The consent of the CUSC Parties under paragraph 7.4.4(a) shall be deemed not to have been given where a request for consolidation thereunder is received by the London Court of International Arbitration more than three months (or such other period as the London Court of International Arbitration may at its discretion determine) after the referral of any Other Dispute or the STC dispute to the London Court of International Arbitration which is the subject of such request.
Subject to Paragraph 7.5.4, if any Customer brings any legal proceedings in any court against one or more persons, any of which is a CUSC Party (“Defendant Party”) and the Defendant Party wishes to make a Third Party Claim (as defined in Paragraph 7.5.3 below) against any CUSC Party (“Other Party”) which would but for this paragraph have been a dispute or difference referred to arbitration by virtue of Paragraph 7.4 above then, notwithstanding the provisions of Paragraph 7.4, which shall not apply and in lieu of arbitration, the court in which the legal proceedings have been commenced shall hear and completely determine and adjudicate upon the legal proceedings and the Third Party Claim not only between the Customer and the Defendant Party, but also between either or both of them and any Other Party whether by way of third party proceedings or otherwise as may be ordered by the court.
Where a Defendant Party makes a Third Party Claim against any Other Party and such Other Party wishes to make a Third Party Claim against a further CUSC Party, the provisions of Paragraph 7.5.1 shall apply mutatis mutandis as if such CUSC Party had been the Defendant Party and similarly in relation to any such further CUSC Party.
For the purpose of this Paragraph 7.5, “Third Party Claim” shall mean:
any claim by a Defendant Party against any Other Party (whether or not already a party to the legal proceedings) for any contribution or indemnity; or
any claim by a Defendant Party against such an Other Party for any relief or remedy relating to or connected with the subject matter of the legal proceedings and substantially the same as some relief or remedy claimed by the Customer; or
any requirement by a Defendant Party that any question or issue relating to or connected with the subject matter of the legal proceedings should be determined not only as between the Customer and the Defendant Party, but also as between either or both of them and an Other Party (whether or not already a party to the legal proceedings).
Paragraph 7.5.1 shall apply only if at the time the legal proceedings are commenced no arbitration under Paragraph 7.4 has been commenced between the Defendant Party and an Other Party raising or involving the same or substantially the same issues as would be raised by or involved in the Third Party Claim. The tribunal in any arbitration or the Authority in any determination which has commenced before the commencement of the legal proceedings shall determine the question, in the event of dispute, whether the issues raised or involved are the same or substantially the same.
SECTION 8: CUSC MODIFICATION
Part A
This section of the CUSC sets out how the CUSC is to be amended and the procedures set out in this section, to the extent that they are dealt with in the Code Administration Code of Practice, are consistent with the principles contained in the Code Administration Code of Practice. Where inconsistencies or conflicts exist between the CUSC and the Code Administration Code of Practice, the CUSC shall take precedence. A modification to the CUSC may necessitate a modification to relevant Bilateral Agreements and/or to the Mandatory Services Agreements (and/or in certain circumstances the relevant Construction Agreement) and in those circumstances those agreements contain provisions for such alterations to be effected to those agreements.
There is a need to bring proposed amendments to the attention of CUSC Parties and others, to discuss such proposals and to report on them to the Authority and in furtherance of this, Section 8 provides for the establishment of a CUSC Modifications Panel, Workgroups and Standing Groups and for consultation by the Code Administrator.
Change Routes
A CUSC Modification Proposal may either proceed directly along the standard CUSC Modification Process, or it may be subject to additional process steps, if raised during a Significant Code Review.
If a CUSC Modification Proposal is deemed by the CUSC Modifications Panel to meet the Self-Governance Criteria, it will be subject to a slightly different process.
If a CUSC Modification Fast Track Proposal is determined by the CUSC Modifications Panel to meet the Fast Track Criteria, it will be subject to the process set out at Paragraph 8.29.
an EBR Amendment will always be a Standard CUSC Modification Proposal unless an Urgent CUSC Modification Proposal or where it meets the Fast Track Criteria.
Significant Code Review
A Significant Code Review is a code review process initiated and led by the Authority, on one of a number of potential triggers. The Authority will launch a Significant Code Review on publication of a notice setting out matters such as the scope of the review, reasons for it and announcing the start date.
A Significant Code Review Phase begins on the start date set out in the Authority’s notice, during which time CUSC Modification Proposals that relate to the subject matter of the review are restricted, to ensure the process is as efficient as possible. Once the Authority has published its Significant Code Review conclusions, the Authority may direct The Company to raise CUSC Modification Proposals to put into effect the results of the Significant Code Review.
A process is set out in this Section 8 for analysing and consulting on CUSC Modification Proposals with a view to referring to the Authority those that may be restricted during a Significant Code Review. Subject to Paragraph 8.1.5, those CUSC Modification Proposals that are not so restricted proceed along the standard CUSC Modification Process of consultation with the industry followed by approval or non-approval by the Authority.
Self-Governance In addition, Self-Governance Criteria are set out against which CUSC Modification Proposals must also be evaluated and consulted upon. If a proposal meets the criteria, it may proceed without Authority approval, and the CUSC Modifications Panel may consult on and determine itself whether to implement the CUSC Modification Proposal.
Fast Track If the CUSC Modifications Panel unanimously determine that a CUSC Modification Fast Track Proposal meets the Fast Track Criteria¸ it will proceed without Authority approval, and will be subject to the process set out at Paragraph 8.29.
Where a CUSC Modification Proposal constitutes an EBR Amendment, The Company, when undertaking its role in the CUSC Panel or Working Groups during the CUSC Modification Process, shall provide justification for including or not including the views of stakeholders resulting from the Code Administrator consultation. PART B
The Company shall establish and maintain a Code Administrator function, which shall carry out the roles referred to in Paragraph 8.2.2 and 8.3.3. The Company shall ensure the functions are consistent with the Code Administration Code of Practice.
The Code Administrator shall in conjunction with other code administrators, maintain, publish, review and (where appropriate) amend from time to time the Code Administration Code of Practice approved by the Authority provided that any amendments to the Code Administration Code of Practice proposed by the Code Administrator are approved by the CUSC Modifications Panel prior to being raised by the Code Administrator, and any amendments to be made to the Code Administration Code of Practice are approved by the Authority.
Market-wide Half-Hourly Settlement Implementation The Company shall (and shall ensure that the Code Administrator shall) comply with the obligations expressed to apply to The Company (either specifically or generally as a category of participant) under section C12 (Market-wide Half Hourly Settlement Implementation) of the Balancing and Settlement Code.
Establishment and Composition
The CUSC Modifications Panel shall be the standing body to carry out the functions referred to in Paragraph 8.3.3.
The CUSC Modifications Panel shall comprise the following members:
the person appointed as the chairperson of the CUSC Modifications Panel (the “Panel Chairperson”) in accordance with Paragraph 8.4.1, who shall (subject to Paragraph 8.11.4) be a non-voting member;
not more than seven persons appointed by Users in accordance with Paragraph 8.4.2(a);
two persons appointed by The Company in accordance with Paragraph 8.4.2(c);
The Consumer Representative, appointed in accordance with Paragraph 8.4.2(b); and
the person appointed (if the Authority so decides) by the Authority in accordance with Paragraph 8.4.3.
The CUSC Modifications Panel shall be assisted by a secretary (“Panel Secretary”), who shall be a person appointed and provided by the Code Administrator and who shall be responsible for the administration of the CUSC Modifications Panel and CUSC Modification Proposals.
Authority’s Representative A representative of the Authority shall be entitled to attend CUSC Modifications Panel meetings as an observer and may speak at any meeting. The Authority shall from time to time notify the Panel Secretary of the identity of the observer.
Functions of the CUSC Modifications Panel and the Code Administrator’s Role
The CUSC Modifications Panel shall have the functions assigned to it in this Section 8.
Without prejudice to Paragraph 8.3.3(a) and to the further provisions of this Section 8, the CUSC Modifications Panel shall endeavour at all times to operate:
in an efficient, economical and expeditious manner, taking account of the Prioritisation Criteria, and whether particular CUSC Modification Proposals are Urgent CUSC Modification Proposals or not; and
with a view to ensuring that the CUSC facilitates achievement of the Applicable CUSC Objectives.
The Company shall be responsible for implementing or supervising the implementation of Approved CUSC Modifications and Approved CUSC Modification Self Governance Proposals and Approved CUSC Modification Fast Track Proposals in accordance with the provisions of the CUSC which shall reflect the production of the revised CUSC. The Code Administrator and The Company shall be responsible for implementing and supervising the implementation of any amendments to their respective systems and processes necessary for the implementation of the Approved CUSC Modification. and, the Approved CUSC Modification Self-Governance Proposals provided there is no successful appeal and, , the Approved CUSC Modification Fast Track Proposals provided no objections are received in accordance with Paragraph 8.29. However, it will not include the implementation of Users’ systems and processes. The Code Administrator will carry out its role in an efficient, economical and expeditious manner and (subject to any extension granted by the Authority where the Code Administrator has applied for one in accordance with Paragraph 8.3.3(d) or (e) in accordance with the Implementation Date.
Subject to notifying Users, the Code Administrator will, with the Authority’s approval, apply to the Authority for a revision or revisions to the Implementation Date where the Code Administrator becomes aware of any circumstances which is likely to mean that the Implementation Date is unachievable, which shall include as a result of a Legal Challenge, at any point following the approval of the CUSC Modification Proposal.
In the event that the Authority’s decision to approve or not to approve a CUSC Modification Proposal is subject of Legal Challenge (and the party raising such Legal Challenge has received from the relevant authority the necessary permission to proceed) then the Code Administrator will, with the Authority’s approval, apply to the Authority for a revision or revisions to the Proposed Implementation Date in the CUSC Modification Report in respect of such CUSC Modification Proposal as necessary such that if such CUSC Modification Proposal were to be approved following such Legal Challenge the Proposed Implementation Date would be achievable.
Prior to making any request to the Authority for any revision pursuant to Paragraphs 8.3.3(d) (where it is necessary as a result of a Legal Challenge) or 8.3.3(e) the Code Administrator shall consult on the revision with CUSC Parties and such other person who may properly be considered to have an appropriate interest in it in accordance with Paragraphs 8.22.2 and 8.22.6. The request to the Authority shall contain copies of (and a summary of) all written representations or objections made by consultees during the consultation period.
The CUSC Modifications Panel shall allocate a Prioritisation Category to every CUSC Modification Proposal, other than those that are treated as Urgent CUSC Modification Proposals or CUSC Modification Fast-Track Proposals. In determining the Prioritisation Category, the CUSC Modification Panel shall assess the relevant CUSC Modification Proposal against the Prioritisation Criteria and shall take into account (without limitation) the Prioritisation Categories awarded to other Pending CUSC Modification Proposals as well as the assessment made by the relevant Proposer under paragraph 8.16.4(m).
Duties of Panel Members
A person appointed as a Panel Member, or an Alternate Member, by Users under Paragraph 8.3.1 or 8.7.2, by the Authority under Paragraph 8.4.3 and the person appointed as Panel Chairperson under Paragraph 8.4.1, and each of their alternates when acting in that capacity:
shall act impartially and in accordance with the requirements of the CUSC; and
shall not be representative of, and shall act without undue regard to the particular interests of the persons or body of persons by whom they were appointed as Panel Member and any Related Person from time to time.
Such a person shall not be appointed as a Panel Member or an Alternate Member (as the case may be) unless they shall have first:
confirmed in writing to the Code Administrator for the benefit of all CUSC Parties that they agree to act as a Panel Member or Alternate Member in accordance with the CUSC and acknowledges the requirements of Paragraphs 8.3.4(a) and 8.3.4(c);
where that person is employed, provided to the Panel Secretary a letter from their employer agreeing that they may act as a Panel Member or Alternate Member, and that the requirement in Paragraph 8.3.4(a)(ii) shall prevail over their duties as an employee; and
declared in writing to the Code Administrator for publication for the benefit of all CUSC Parties any interests (in relation to the CUSC) as are referred to in Paragraph 8.3.4(e).
A Panel Member or Alternate Member shall, upon any change in the interests referred to in Paragraph 8.3.4(b)(iii), disclose such changes (in writing) to the Panel Secretary).
Upon a change in employment of a Panel Member or Alternate Member, they shall so notify the Panel Secretary and shall endeavour to obtain from their new employer and provide to the Panel Secretary a letter in the terms required in Paragraph 8.3.4(b)(ii); and they shall be removed from office if they do not do so within a period of sixty (60) days after such change in employment.
The interests of any Panel Member or Alternate Member referred to in Paragraph 8.3.4(b)(iii) are:
any interests (in relation to the CUSC) as are referred to in Paragraph 8.3.4(a)(ii); and
any shares owned or acquired in any CUSC Party or CUSC Parties at a total aggregate value of over £10,000.
Panel Chairperson
The Panel Chairperson shall be an executive director (or other senior employee) of The Company until 30 September 2011. Thereafter the Panel Chairperson shall be a person appointed (or re-appointed) by The Company, having particular regard to the views of the CUSC Modifications Panel, and shall be independent of The Company.
A person shall be appointed or re-appointed as the Panel Chairperson where the Authority has approved such appointment or re-appointment and The Company has given notice to the Panel Secretary of such appointment, with effect from the date of such notice or (if later) with effect from the date specified in such notice.
Other Panel Members
Users may appoint Panel Members (and Alternate Members) by election in accordance with Annex 8A.
The Citizens Advice or the Citizens Advice Scotland may appoint one person as a Panel Member representing customers by giving notice of such appointment to the Panel Secretary, and may remove and re-appoint by notice.
The Company may appoint two persons as Panel Members by giving notice of such appointment to the Panel Secretary, and may remove and re-appoint by notice.
Appointment of Further Member
If in the opinion of the Authority there is a class or category of person (whether or not a CUSC Party or a BSC Party) who have interests in respect of the CUSC but whose interests:
are not reflected in the composition of Panel Members for the time being appointed; but
would be so reflected if a particular person was appointed as an additional Panel Member, then the Authority may at any time appoint (or re-appoint) that person as a Panel Member by giving notice of such appointment to the Panel Secretary but in no event shall the Authority be able to appoint more than one person so that there could be more than one such Panel Member.
A person appointed as a Panel Member pursuant to this Paragraph 8.4.3 shall remain appointed, subject to Paragraphs 8.5 and 8.6, notwithstanding that the conditions by virtue of which they were appointed (for example that the interests they reflect are otherwise reflected) may cease to be satisfied.
Natural Person No person other than an individual shall be appointed a Panel Member or their alternate.
TERM OF OFFICE The term of office of a Panel Member, the Panel Chairperson and Alternate Members shall be a period expiring on 30 September every second year following the CUSC Implementation Date. A Panel Member, the Panel Chairperson and Alternate Member shall be eligible for reappointment on expiry of their term of office.
A person shall cease to hold office as the Panel Chairperson, a Panel Member or an Alternate Member:
upon expiry of their term of office unless re-appointed;
if they:
resign from office by notice delivered to the Panel Secretary;
become bankrupt or make any arrangement or composition with their creditors generally;
are or may be suffering from mental disorder and either is admitted to hospital in pursuance of an application under the Mental Health Act 1983 or the Mental Health (Scotland) Act 1960 or an order is made by a court having jurisdiction in matters concerning mental disorder for their detention or for the appointment of a receiver, curator bonis or other person with respect to their property or affairs;
become prohibited by law from being a director of a company under the Companies Act 1985;
die; or
are convicted on an indictable offence; or
as provided for in Paragraph 8.3.4(d);
if the CUSC Modifications Panel resolves (and the Authority does not veto such resolution by notice in writing to the Panel Secretary within fifteen (15) Business Days) that they should cease to hold office on grounds of their serious misconduct;
if the CUSC Modifications Panel resolves (and the Authority does not veto such resolution by notice in writing to the Panel Secretary within fifteen (15) Business Days) that they should cease to hold office due to a change in employer notwithstanding compliance with Paragraph 8.3.4(d).
A CUSC Modifications Panel resolution under Paragraph 8.6.1(d) or (e) shall, notwithstanding any other paragraph, require the vote in favour of at least all Panel Members less one (other than the Panel Member or Alternate Member who is the subject of such resolution) and for these purposes an abstention shall count as a vote cast in favour of the resolution. A copy of any such resolution shall forthwith be sent to the Authority by the Panel Secretary.
A person shall not qualify for appointment as a Panel Member or Alternate Member if at the time of the proposed appointment they would be required by the above paragraph to cease to hold that office.
The Panel Secretary shall give prompt notice to all Panel Members, all CUSC Parties and the Authority of the appointment or re- appointment of any Panel Member or Alternate Member or of any Panel Member or Alternate Member ceasing to hold office and publication on the Website and (where relevant details are supplied to the Panel Secretary) despatch by electronic mail shall fulfil this obligation.
Alternate: Panel Chairperson The Panel Chairperson shall preside at every meeting of the CUSC Modifications Panel at which they are present. If they are unable to be present at a meeting, they may appoint an alternate (who shall be a senior employee of The Company) to act as the Panel Chairperson, who may or may not be a Panel Member. If neither the Panel Chairperson nor their alternate is present at the meeting within half an hour of the time appointed for holding the meeting, the Panel Members present may appoint one of their number to be the chairperson of the meeting.
Alternate(s): Users Panel Members
At the same time that Users appoint Panel Members under Paragraph 8.4.2(a), they shall appoint up to five (5) alternate members for Panel Members appointed pursuant to Paragraph 8.3.1(b)(ii) (“Alternate Members”) by election in accordance with Annex 8A.
Such Alternate Members will form a group from which the Panel Chairperson shall select a person to act as an alternate in accordance with this Paragraph 8.7.
Where any Panel Member appointed pursuant to Paragraph 8.3.1(b)(ii) gives the notice referred to in Paragraph 8.8.12 the Panel Chairperson shall select through a rota system an Alternate Member to act as the absent Panel Member for the relevant CUSC Modifications Panel meeting, and may remove a person so appointed as alternate, by giving notice of such appointment or removal to the Panel Secretary. If there are no Alternate Members left on the rota who have not already been selected to act as alternate for the relevant CUSC Modifications Panel meeting the Panel Chairperson shall select through a rota system a Panel Member or Alternate Member to act as alternate for the absent Panel member.
All information to be sent by the Panel Secretary to Panel Members pursuant to this Section 8 shall also be sent by the Panel Secretary to each Alternate Member (whether or not currently selected as an alternate for a Panel Member) by electronic mail (where relevant details shall have been provided by each Alternate Member).
Alternates: Other Panel Members A Panel Member appointed pursuant to Paragraphs 8.3.1(b)(iii), 8.3.1(b)(iv) or 8.3.1(b)(v) may appoint a person (whether or not a Panel Member) to be their alternate, and may remove a person so appointed as alternate, by giving notice of such appointment or removal to the Panel Secretary.
Alternates: General Provisions
The appointment or removal of an alternate shall be effective from the time when such notice is given to the Panel Secretary or (if later) the time specified in such notice.
The Panel Secretary shall promptly notify all Panel Members and CUSC Parties of appointment or removal by any Panel Member of any alternate and publication on the Website and (where relevant details have been provided to the Panel Secretary) despatch by electronic mail shall fulfil this obligation.
In accordance with Paragraph 8.7.2, an alternate may act as alternate for more than one Panel Member.
Alternates: Rights, Cessation and References
Where an alternate has been selected under this Paragraph 8.7:
the alternate shall be entitled:
to receive notices of meetings of the CUSC Modifications Panel;
to attend, speak and vote at any meeting of the CUSC Modifications Panel at which the Panel Member for whom they are acting as an alternate is not present, and at such meeting to exercise and discharge all of the functions, duties and powers of such Panel Member;
the alternate shall cast one vote for each Panel Member for whom they are acting as alternate in addition (where they are a Panel Member themself) to their own vote;
Paragraphs 8.8, 8.9, 8.10, 8.11 and 8.12 shall apply to the alternate as if they were the Panel Member for whom they are acting as an alternate and a reference to a Panel Member elsewhere in the CUSC shall, unless the context otherwise requires, include their duly appointed alternate.
for the avoidance of doubt, the Panel Member for whom an alternate has been selected shall not enjoy any of the rights transferred to the alternate at any meeting at which, or in relation to any matter on which, the alternate acts on their behalf.
A person appointed as an alternate under paragraph 8.7.3 shall automatically cease to act as such an alternate:
if the Panel Member for whom they are acting as an alternate ceases to be a Panel Member provided that, where such person is an Alternate Member, they shall continue to be an Alternate Member available for appointment under paragraph 8.7.2; or
if any of the circumstances in Paragraph 8.6.1(b) applies in relation to such person.
Meetings of the CUSC Modifications Panel shall be held at regular intervals and at least every month at such time and such place as the CUSC Modifications Panel shall decide.
A regular meeting of the CUSC Modifications Panel may be cancelled if:
the Panel Chairperson considers, having due regard to the lack of business in the agenda, that there is insufficient business for the CUSC Modifications Panel to conduct and requests the Panel Secretary to cancel the meeting;
the Panel Secretary notifies all Panel Members, not less than five (5) Business Days before the date for which the meeting is to be convened, of the proposal to cancel the meeting; and
by the time three (3) Business Days before the date for which the meeting is or is to be convened, no Panel Member has notified the Panel Secretary that they object to such cancellation.
If any Panel Member wishes, acting reasonably, to hold a special meeting (in addition to regular meetings under Paragraph 8.8.1) of the CUSC Modifications Panel:
they shall request the Panel Secretary to convene such a meeting and inform the Panel Secretary of the matters to be discussed at the meeting;
the Panel Secretary shall promptly convene the special meeting for a day as soon as practicable but not less than five (5) Business Days after such request.
Any meeting of the CUSC Modifications Panel shall be convened by the Panel Secretary by notice (which will be given by electronic mail if the relevant details are supplied to the Panel Secretary) to each Panel Member (and to the Authority):
setting out the date, time and place of the meeting and (unless the CUSC Modifications Panel has otherwise decided) given at least five (5) Business Days before the date of the meeting;
accompanied by an agenda of the matters for consideration at the meeting and any supporting papers available to the Panel Secretary at the time the notice is given (and the Panel Secretary shall circulate to Panel Members any late papers as and when they are received by them).
The Panel Secretary shall send a copy of the notice convening a meeting of the CUSC Modifications Panel, and the agenda and papers accompanying the notice, to each CUSC Party and each BSC Party at the same time at which notice is given to the Panel Members, and publication on the Website and despatch by electronic mail (if the relevant details are supplied to the Panel Secretary) shall fulfil this obligation.
Any Panel Member (or, at the Panel Member’s request, the Panel Secretary) may notify matters for consideration at a meeting of the CUSC Modifications Panel in addition to those notified by the Panel Secretary under Paragraph 8.8.4 by notice to all Panel Members and persons entitled to receive notice under Paragraph 8.8.5, not less than three (3) Business Days before the date of the meeting.
The proceedings of a meeting of the CUSC Modifications Panel shall not be invalidated by the accidental omission to give or send notice of the meeting or a copy thereof or any of the accompanying agenda or papers to, or failure to receive the same by, any person entitled to receive such notice, copy, agenda or paper.
A meeting of the CUSC Modifications Panel may consist of a conference between Panel Members who are not all in one place (although at least one must be at the venue in the notice of meeting) but who are able (by telephone or otherwise) to speak to each of the others and to be heard by each of the others simultaneously.
With the consent of all Panel Members (whether obtained before, at or after any such meeting) the requirements of this Paragraph 8.8 as to the manner in and notice on which a meeting of the CUSC Modifications Panel is convened may be waived or modified provided that no meeting of the CUSC Modifications Panel shall be held unless notice of the meeting and its agenda has been sent to the persons entitled to receive the same under Paragraph 8.8.5 at least 24 hours before the time of the meeting.
Subject to Paragraph 8.8.11, no matter shall be resolved at a meeting of the CUSC Modifications Panel unless such matter was contained in the agenda accompanying the Panel Secretary’s notice under Paragraph 8.8.4 or was notified in accordance with Paragraph 8.8.6.
Where:
any matter (not contained in the agenda and not notified pursuant to Paragraphs 8.8.4 and 8.8.6) is put before a meeting of the CUSC Modifications Panel, and
in the opinion of the CUSC Modifications Panel it is necessary (in view of the urgency of the matter) that the CUSC Modifications Panel resolve upon such matter at the meeting, the CUSC Modifications Panel may so resolve upon such matter, and the CUSC Modifications Panel shall also determine at such meeting whether the decision of the CUSC Modifications Panel in relation to such matter should stand until the following meeting of the CUSC Modifications Panel, in which case (at such following meeting) the decision shall be reviewed and confirmed or (but not with effect earlier than that meeting, and only so far as the consequences of such revocation do not make implementation of the CUSC or compliance by CUSC Parties with it impracticable) revoked.
Where any Panel Member is unable to attend a CUSC Modifications Panel they shall use reasonable endeavours to give at least five (5) Business Days’ prior notice to the Panel Secretary. In the event such absence is unforeseen (such as through illness) then the Panel Member shall use reasonable endeavours to give notice to the Panel Secretary no later than 07:00 on the day of the planned meeting.
Subject as provided in the CUSC, the CUSC Modifications Panel may regulate the conduct of and adjourn and reconvene its meetings as it sees fit.
Meetings of the CUSC Modifications Panel shall be open to attendance by a representative of any CUSC Party, any BSC Party, the Citizen Advice or the Citizens Advice Scotland and any person invited by the Panel Chairperson and/or any other Panel Member.
The Panel Chairperson and any other Panel Member may invite any person invited by them under Paragraph 8.9.2, and/or any attending representative of a CUSC Party, to speak at the meeting (but such person shall have no vote).
As soon as practicable after each meeting of the CUSC Modifications Panel, the Panel Secretary shall prepare and send (by electronic mail or otherwise) to Panel Members the minutes of such meeting, which shall be (subject to Paragraph 8.9.5) approved (or amended and approved) at the next meeting of the CUSC Modifications Panel after they were so sent, and when approved (excluding any matter which the CUSC Modifications Panel decided was not appropriate for such publication) shall be placed on the Website.
If, following the circulation of minutes (as referred to in Paragraph 8.9.4), the meeting of the CUSC Modifications Panel at which they were to be approved is cancelled pursuant to Paragraph 8.8.2, such minutes (including any proposed changes thereto which have already been received) shall be re-circulated with the notification of the cancellation of the meeting of the CUSC Modifications Panel. Panel Members shall confirm their approval of such minutes to the Panel Secretary (by electronic mail) no later than five (5) Business Days following such minutes being re-circulated. If no suggested amendments are received within such five (5) Business Days period, the minutes will be deemed to have been approved. If the minutes are approved, or deemed to have been approved, (excluding any matter which the CUSC Modifications Panel decided was not appropriate for such publication) they shall be placed on the Website. If suggested amendments are received within such five (5) Business Days period, the minutes shall remain unapproved and the process for approval (or amendment and approval) of such minutes at the next meeting of the CUSC Modifications Panel, as described in Paragraph 8.8.4, shall be followed.
No business shall be transacted at any meeting of the CUSC Modifications Panel unless a quorum is present throughout the meeting.
Subject to Paragraph 8.10.4, a quorum shall be 6 Panel Members who have a vote present (subject to 8.8.8) in person or by their alternates, of whom at least one shall be appointed by The Company.
If within half an hour after the time for which the meeting of the CUSC Modifications Panel has been convened a quorum is not present (and provided the Panel Secretary has not been notified by Panel Members that they have been delayed and are expected to arrive within a reasonable time):
the meeting shall be adjourned to the same day in the following week (or, if that day is not a Business Day the next Business Day following such day) at the same time;
the Panel Secretary shall give notice of the adjourned meeting as far as practicable in accordance with Paragraph 8.8.
If at the adjourned meeting there is not a quorum present within half an hour after the time for which the meeting was convened, those present shall be a quorum.
At any meeting of the CUSC Modifications Panel any matter to be decided which shall include the CUSC Modifications Panel Recommendation Vote shall be put to a vote of Panel Members upon the request of the Panel Chairperson or any Panel Member.
Subject to Paragraphs 8.7.5, 8.11.4 and 8.11.5, in deciding any matter at any meeting of the CUSC Modifications Panel each Panel Member other than the Panel Chairperson shall cast one vote.
Except as otherwise expressly provided in the CUSC, and in particular Paragraph 8.6.2, any matter to be decided at any meeting of the CUSC Modifications Panel shall be decided by simple majority of the votes cast at the meeting (an abstention shall not be counted as a cast vote).
The Panel Chairperson shall not cast a vote as a Panel Member but shall have a casting vote on any matter (except in a CUSC Modifications Panel Recommendation Vote) where votes are otherwise cast equally in favour of and against the relevant motion including, for the avoidance of doubt, in the CUSC Modifications Panel Self-Governance Vote, where the Panel Chairperson is obliged to exercise their casting vote if votes are otherwise cast equally in favour of or against a CUSC Modification Proposal, but where any person other than the actual Panel Chairperson or their alternate is acting as chairperson they shall not have a casting vote.
The two Panel Members appointed by The Company pursuant to Paragraph 8.3.1(b)(iii) shall together have one vote in relation to each matter which shall be cast jointly by agreement between them or, where only one of The Company Panel Members is present at a meeting, by that The Company Panel Member.
Any resolution in writing signed by or on behalf of all Panel Members shall be valid and effectual as if it had been passed at a duly convened and quorate meeting of the CUSC Modifications Panel. Such a resolution may consist of several instruments in like form signed by or on behalf of one or more Panel Members.
Subject to Paragraph 8.12.2 all CUSC Parties shall jointly and severally indemnify and keep indemnified each Panel Member, the Panel Secretary and each member of a Workgroup and Standing Group (“Indemnified Persons”) in respect of all costs (including legal costs), expenses, damages and other liabilities properly incurred or suffered by such Indemnified Persons when acting in or in connection with their office under the CUSC, or in what they in good faith believe to be the proper exercise and discharge of the powers, duties, functions and discretions of that office in accordance with the CUSC, and all claims, demands and proceedings in connection therewith other than any such costs, expenses, damages or other liabilities incurred or suffered as a result of the wilful default or bad faith of such Indemnified Person.
The indemnity provided in Paragraph 8.12.1 shall not extend to costs and expenses incurred in the ordinary conduct of being a Panel Member or Panel Secretary, or member of a Workgroup or Standing Group including, without limitation, accommodation costs and travel costs or any remuneration for their services to the CUSC Modifications Panel or Workgroup or Standing Group.
The CUSC Parties agree that no Indemnified Person shall be liable for anything done when acting properly in or in connection with their office under the CUSC, or anything done in what they in good faith believe to be the proper exercise and discharge of the powers, duties, functions and discretions of that office in accordance with the CUSC. Each CUSC Party hereby irrevocably and unconditionally waives any such liability of any Indemnified Person and any rights, remedies and claims against any Indemnified Person in respect thereof.
Without prejudice to Paragraph 8.12.2, nothing in Paragraph 8.12.3 shall exclude or limit the liability of an Indemnified Person for death or personal injury resulting from the negligence of such Indemnified Person. PART C
The Code Administrator shall establish and maintain a register (“CUSC Modification Register”) which shall record the matters set out in Paragraph 8.13.3.
The purpose of the CUSC Modification Register shall be to assist the CUSC Modifications Panel and to enable the CUSC Modifications Panel, CUSC Parties and any other persons who may be interested to be reasonably informed of the progress of CUSC Modification Proposals and Approved CUSC Modifications from time to time.
The CUSC Modification Register shall record in respect of current outstanding CUSC Modifications Panel business:
details of each CUSC Modification Proposal (including the name of the Proposer, the date of the CUSC Modification Proposal and a brief description of the CUSC Modification Proposal);
whether such CUSC Modification Proposal is an Urgent CUSC Modification Proposal, or, where such CUSC Modification Proposal isn’t an Urgent CUSC Modification Proposal or a CUSC Modification Fast Track Proposal, the Prioritisation Category of such CUSC Modification Proposal, and the reasons for the CUSC Modifications Panel’s determination of its Prioritisation Category; and;
the current status and progress of each CUSC Modification Proposal, if appropriate the anticipated date for reporting to the Authority in respect thereof, and whether it has been withdrawn, rejected or implemented for a period of three (3) months after such withdrawal, rejection or implementation or such longer period as the Authority may determine;
the current status and progress of each Approved CUSC Modification, each Approved CUSC Modification Self-Governance Proposal, and each Approved CUSC Modification Fast Track Proposal;
such other matters as the CUSC Modifications Panel may consider appropriate from time to time to achieve the purpose of Paragraph 8.13.2; and
where the Prioritisation Category of a CUSC Modification Proposal is changed, confirmation of the change alongside the reasons for the change
The CUSC Modification Register (as updated from time to time and indicating the revisions since the previous issue) shall be published on the Website or (in the absence, for whatever reason, of the Website) in such other manner and with such frequency (being not less than once per month) as the Code Administrator may decide in order to bring it to the attention of the CUSC Modifications Panel, CUSC Parties and other persons who may be interested.
The Code Administrator shall prepare and submit to the Authority each month (or such less often period if there is no material matter arising to report) a progress report (“Progress Report”) setting out the matters referred to in Paragraph 8.14.2 in respect of the preceding month and send a copy of the Progress Report to each Panel Member.
The Progress Report shall contain:
details of any proposal which has been refused pursuant to Paragraph 8.16.5 or Paragraph 8.16.6;
the current version of the CUSC Modification Register;
details of:
whether each CUSC Modification Proposal in the CUSC Modification Register is accorded to be an Urgent CUSC Modification Proposal, or unless it is an Urgent CUSC Modification Proposal or a CUSC Modification Fast Track Proposal, the Prioritisation Category proposed to be accorded or that is accorded to each CUSC Modification Proposal in the CUSC Modification Register (in accordance with Paragraph 8.19.1);
the scheduling and timetable for consideration of each CUSC Modification Proposal and completion of the CUSC Modification Report in respect thereof in the context of all other current CUSC Modification Proposals;
the impact of whether each CUSC Modification Proposal is accorded to be an Urgent CUSC Modification Proposal, or, where it is not an Urgent CUSC Modification Proposal or a CUSC Modification Fast Track Proposal, the Prioritisation Category accorded to each such CUSC Modification Proposal by reference to each other pending CUSC Modification Proposal
details of any decision to amalgamate CUSC Modification Proposals in accordance with Paragraph 8.19.2;
details of any circumstances which lead The Company and/or the CUSC Modifications Panel to believe that the implementation date for an Approved CUSC Modification is unlikely to be met and, if so, why;
such other matters as the Authority may request to be included from time to time; and
the basis for each of the decisions referred to above.
If, following discussion with the CUSC Modifications Panel, the Authority issues a notice to the Panel Secretary requesting the Code Administrator and the CUSC Modifications Panel (in relation to developments and changes highlighted in the monthly Progress Report):
not to reject a CUSC Modification Proposal which does not satisfy Paragraph 8.16.4; and/or
not to amalgamate CUSC Modification Proposals as set out in the monthly Progress Report; and/or
to accord a different Prioritisation Category to particular CUSC Modification Proposals from that set out in the monthly Progress Report; and/or
to amend the timetable for a CUSC Modification Proposal, the Panel Secretary shall send a copy of the notice to each Panel Member and Alternate Member. The CUSC Modifications Panel and the Code Administrator shall comply with such notice.
The Panel Secretary shall publish each Progress Report on the Website within seven (7) Business Days after it is sent to the Authority, provided that the Panel Secretary shall exclude there from any matters in respect of which the Authority issues a notice to the Panel Secretary for the purpose of this Paragraph 8.14.4. Copies shall be sent to those Panel Members, Alternate Members and CUSC Parties who have provided electronic mail addresses to the Code Administrator.
The Code Administrator shall establish (and, where appropriate, revise from time to time) joint working arrangements for change co- ordination with each Core Industry Document Owner, with the STC committee, the CM Administrative Parties and with the Secretary of State to facilitate the identification, co-ordination, making and implementation of change to Core Industry Documents and the STC, and facilitate the identification of potential inconsistencies between CUSC Modification Proposals and the Capacity Market Documents and the CFD Documents respectively consequent on a CUSC Modification, including, but not limited to, changes that are appropriate in order to avoid conflict or inconsistency as between the CUSC and any Core Industry Document and the STC, in a full and timely manner.
The working arrangements referred to in Paragraph 8.15.1 shall be such as to enable the consideration, development and evaluation of CUSC Modification Proposals, and the implementation of Approved CUSC Modifications, to proceed in a full and timely manner and enable changes to Core Industry Documents and the STC and for potential inconsistencies between CUSC Modification Proposals and the Capacity Market Documents and/or the CfD Documents to be raised with the CM Administrative Parties and the Secretary of State consequent on an amendment to be made and given effect wherever possible (subject to any necessary consent of the Authority) at the same time as such CUSC Modification is made and given effect.
A proposal to modify the CUSC (excluding the Charging Methodologies) may be made:
by a CUSC Party, by the Citizens Advice, by the Citizens Advice Scotland, or by a BSC Party; or
under Paragraph 8.28.5, by the CUSC Modifications Panel; or
by a Relevant Transmission Licensee in relation to Exhibit O Part IB Exhibit O Part IIB, Exhibit O Part IC and Exhibit O Part IIC only; or
by the Authority or by The Company under the direction of the Authority, pursuant to Paragraph 8.17A.1.
A proposal to modify the Charging Methodologies may be made:
by a CUSC Party, by the Citizens Advice, by the Citizens Advice Scotland or by a BSC Party; or
under Paragraph 8.28.5, by the CUSC Modifications Panel ; or
by a Relevant Transmission Licensee in relation to Exhibit O Part IB, Exhibit O Part IIB, Exhibit O Part IC and Exhibit O Part IIC only; or
by a Materially Affected Party, unless otherwise permitted by the Authority.
by the Authority, or by The Company under the direction of the Authority, pursuant to Paragraph 8.17A.1.
a proposal which constitutes an EBR Amendment may be made under (a) or (b) above even where not made by The Company and the Authority may make a proposal under
and (b) above to the extent that it constitutes an EBR Amendment .
A proposal to modify the Charging Methodologies must be made by means of a CUSC Modification Proposal, which may not contain any proposal to modify any other section of the CUSC, and must comply (as applicable) with condition E10.6 ‘Use of System charging and methodology’ and conditions E11.4 and E11.10 Connection charging methodology of the ESO Licence. When making a CUSC Modification Proposal in respect of the Charging Methodologies, the Proposer may make specific reference to any link with another CUSC Modification Proposal.
A Standard CUSC Modification Proposal shall follow the procedure set out in Paragraphs 8.18 to 8.23.
A CUSC Modification Proposal shall be submitted in writing to the Panel Secretary and, subject to the provisions of Paragraph 8.16.4A below, shall contain the following information in relation to such proposal:
the name of the Proposer;
the name of the representative of the Proposer (and their alternate) who shall represent the Proposer in person for the purposes of this Paragraph 8.16;
a description (in reasonable but not excessive detail) of the issue or defect which the proposed modification seeks to address;
a description (in reasonable but not excessive detail) of the proposed modification and of its nature and purpose;
where possible, an indication of those parts of the CUSC which would require amendment in order to give effect to (and/or would otherwise be affected by) the proposed modification and an indication of the nature of those amendments or effects;
the reasons why the Proposer believes that the proposed modification would better facilitate achievement of the Applicable CUSC Objectives as compared with the current version of the CUSC together with background information in support thereof;
the reasoned opinion of the Proposer as to why the proposed modification should not fall within a current Significant Code Review, whether the proposed modification meets the Self-Governance Criteria or whether the proposed modification should proceed along the Standard CUSC Modification Proposal route;
the reasoned opinion of the Proposer as to whether that impact is likely to be material and if so an assessment of the quantifiable impact of the proposed modification on greenhouse gas emissions, to be conducted in accordance with such current guidance on the treatment of carbon costs and evaluation of the greenhouse gas emissions as may be issued by the Authority from time to time;
where possible, an indication of the impact of the proposed modification on Core Industry Documents and the STC, and an indication of potential inconsistencies between the CUSC Modification Proposal and the Capacity Market Documents and/or the CfD Documents;
where possible, an indication of the impact of the proposed modification on relevant computer systems and processes used by CUSC Parties;
a statement to the effect that the Proposer acknowledges that on acceptance of the proposal for consideration by the CUSC Modifications Panel a Proposer which is not a CUSC Party shall grant a licence in accordance with Paragraph 8.16.9;
whether or not (and to the extent) that in the Proposer’s view the CUSC Modification Proposal constitutes an EBR Amendment; and
an assessment by the Proposer of the CUSC Modification Proposal against the Prioritisation Criteria. 8.16.4A The Proposer of a CUSC Modification Fast Track Proposal, is not required to provide the items referenced at Paragraph 8.16.4 (f) – (j) inclusive, unless either:
the CUSC Modifications Panel has, pursuant to Paragraphs 8.29.5 or 8.29.6, not agreed unanimously that the CUSC Modification Fast Track Proposal meets the Fast Track Criteria, or has not unanimously approved the CUSC Modification Fast Track Proposal; or
there has been an objection to the Approved CUSC Modification Fast Track Proposal pursuant to Paragraph 8.29.12, whereupon the Proposer shall be entitled to provide the additional information required pursuant to Paragraph 8.16.4 for a CUSC Modification Proposal within 28 days of the Panel Secretary’s request. Where the Proposer fails to provide the additional information in accordance with such timescales, the Panel Secretary may reject such proposal in accordance with Paragraph 8.16.5.
if a proposal fails in any material respect to provide the information in Paragraph 8.16.4 (excluding Paragraphs (e), (i) and (j) thereof), the Panel Secretary may, subject to Paragraphs 8.14.3(a) and 8.17A.8, reject such proposal provided that:
the Panel Secretary shall furnish the Proposer with the reasons for such rejection;
the Panel Secretary shall report such rejection to the CUSC Modifications Panel at the next CUSC Modifications Panel meeting, with details of the reasons;
if the CUSC Modifications Panel decides to reverse the Panel Secretary’s decision to refuse the submission, the Panel Secretary shall notify the Proposer accordingly and the proposal shall be dealt with in accordance with this Section 8;
nothing in this Section 8 shall prevent a Proposer from submitting a revised proposal in compliance with the requirements of Paragraph 8.16.4 in respect of the same subject-matter.
Subject to Paragraph 8.17A.8 and without prejudice to the development of a Workgroup Alternative CUSC Modification(s) pursuant to Paragraphs 8.20.13 and 8.20.18, the CUSC Modifications Panel shall direct in the case of (a), and may direct in the case of (b), the Panel Secretary to reject a proposal pursuant to Paragraph 8.16, other than a proposal submitted by The Company pursuant to a direction issued by the Authority following a Significant Code Review in accordance with Paragraph 8.17.6, if and to the extent that such proposal has, in the opinion of the CUSC Modifications Panel, substantially the same effect as:
a Pending CUSC Modification Proposal; or
a Rejected CUSC Modification Proposal, where such proposal is made at any time within two (2) months after the decision of the Authority not to direct The Company to modify the CUSC pursuant to the ESO Licence in the manner set out in such CUSC Modification Proposal, and the Panel Secretary shall notify the Proposer accordingly.
Promptly upon receipt of a CUSC Modification Proposal, the Panel Secretary shall:
allocate a unique reference number to the CUSC Modification Proposal;
enter details of the CUSC Modification Proposal on the CUSC Modification Register; (c ) reserve the right to modify the title or summary of the CUSC Modification Proposal to better reflect the content or intent of the proposal. If such changes are made these shall be agreed by the Proposer, or where this cannot be achieved by the CUSC Modifications Panel at their next meeting; and
note whether in the Proposer’s view the CUSC Modification Proposal constitutes an EBR Amendment.
Subject to Paragraphs 8.8.6, 8.29 and 8.17B, where the CUSC Modification Proposal is received more than 10 (ten) Business Days prior to the next CUSC Modifications Panel meeting, the Panel Secretary shall place the CUSC Modification Proposal on the agenda of the next CUSC Modifications Panel meeting and otherwise shall place it on the agenda of the next succeeding CUSC Modifications Panel meeting.
It shall be a condition to the right to make a proposal to modify the CUSC under this Paragraph 8.16 that the Proposer:
grants a non-exclusive royalty free licence to all CUSC Parties who request the same covering all present and future rights, IPRs and moral rights it may have in such proposal (as regards use or application in Great Britain); and
warrants that, to the best of its knowledge, information and belief, no other person has asserted to the Proposer that such person has any IPRs or normal rights or rights of confidence in such proposal, and, in making a proposal, a Proposer which is a CUSC Party shall be deemed to have granted the licence and given the warranty in (a) and (b) above. The provisions of this Paragraph 8.16.9 shall apply to any WG Consultation Alternative Request, and also to a Relevant Party supporting a CUSC Modification Proposal in place of the original Proposer in accordance with Paragraph 8.16.10 (a) for these purposes the term Proposer shall include any such Relevant Party or a person making such a WG Consultation Alternative Request.
Subject to Paragraph 8.17A.8 (which deals with rejection by the Panel Secretary of CUSC Modification Proposals which are necessary to comply with or implement the Electricity Regulation and/or any relevant Legally Binding Decisions of the European Commission and/or The Agency, Paragraph 8.17A.4 (which deals with withdrawal of an CUSC Modification Proposal in relation to a Significant Code Review) and Paragraph 8.17C.1 (which deals with the withdrawal of a CUSC Modification Proposal following a Backstop Direction) and Paragraph 8.17.7, (which deals with the withdrawal of a CUSC Modification Proposal made pursuant to a direction following a Significant Code Review), a Proposer may withdraw their support for a Standard CUSC Modification Proposal by notice to the Panel Secretary at any time prior to the CUSC Modifications Panel Recommendation Vote undertaken in relation to that Standard CUSC Modification Proposal pursuant to Paragraph 8.23.4, and a Proposer may withdraw their support for a CUSC Modification Proposal that meets the Self-Governance Criteria by notice to the Panel Secretary at any time prior to the CUSC Modifications Panel Self-Governance Vote undertaken in relation to that CUSC Modification Proposal pursuant to Paragraph 8.25.9, and a Proposer may withdraw their support for a CUSC Modification Fast Track Proposal by notice to the Panel Secretary at any time prior to the Panel’s vote on whether to approve the CUSC Modification Fast Track Proposal pursuant to Paragraph 8.29 in which case the Panel Secretary shall forthwith:
notify those parties specified in Paragraph 8.16.1 as relevant in relation to the CUSC Modification Proposal in question (a “Relevant Party”) that they have been notified of the withdrawal of support by the Proposer by publication on the Website and (where relevant details are supplied) by electronic mail. A Relevant Party may within five (5) Business Days notify the Panel Secretary that it is prepared to support the CUSC Modification Proposal in place of the original Proposer. If such notice is received, the name of such Relevant Party shall replace that of the original Proposer as the Proposer, and the CUSC Modification Proposal shall continue. If more than one notice is received, the first received shall be utilised;
if no notice of support is received under (a), the matter shall be discussed at the next CUSC Modifications Panel meeting. If the CUSC Modifications Panel so agrees, it may notify Relevant Parties that the CUSC Modification Proposal is to be withdrawn, and a further period of five (5) Business Days shall be given for support to be indicated by way of notice;
if no notice of support is received under (a) or (b), the CUSC Modification Proposal shall be marked as withdrawn on the CUSC Modification Register; Code Administrator as Critical Friend
The Code Administrator shall provide assistance insofar as is reasonably practicable and on reasonable request to parties with an interest in the CUSC Modification Process (including, in particular, Small Participants and consumer representatives, and, for the purposes of preparing modifications to the Charging Methodologies only, Materially Affected Parties) that request it in relation to the CUSC, as provided for in the Code Administration Code of Practice, including, but not limited to, assistance with:
Drafting a CUSC Modification Proposal including, in relation to Materially Affected Parties, drafting a CUSC Modification Proposal in respect of the Charging Methodologies;
Understanding the operation of the CUSC;
Their involvement in, and representation during, the CUSC Modification Process (including but not limited to CUSC Modifications Panel, and/or Workgroup meetings) as required or as described in the Code Administration Code of Practice; and
Assisting the Proposer and Workgroup by producing draft legal text once a clear solution has been developed to support the discussion and understanding of a CUSC Modification Proposal; and
Accessing information relating to the Charging Statements (subject to any charge made by The Company to cover its reasonable costs of providing the Charging Statements in accordance with Paragraph 8.16.12), and any amendment, revision or notice of proposed amendment to the Charging Statements, CUSC Modification Proposals and/or CUSC Modifications Proposals that have been implemented.
The Company may provide information in accordance with conditions E10.10 and E10.11 ‘Use of System Charging and methodology’ and conditions E11.12 and E11.13 ‘Connection charging methodology’ of the ESO Licence; and insofar as reasonably practicable, the provision by The Company of such other information or assistance as a Materially Affected Party may reasonably request for the purposes of preparing a proposal to modify the Charging methodologies.
SIGNIFICANT CODE REVIEW Significant Code Review Phase
If any party specified under Paragraph 8.16.1 makes a CUSC Modification Proposal during a Significant Code Review Phase, unless exempted by the Authority or unless Paragraph 8.17.4(b) applies, the CUSC Modifications Panel shall assess whether the CUSC Modification Proposal falls within the scope of a Significant Code Review and the applicability of the exceptions set out in Paragraph 8.17.4 and shall notify the Authority of its assessment, its reasons for that assessment and any representations received in relation to it as soon as practicable.
The CUSC Modifications Panel shall proceed with the CUSC Modification Proposal made during a Significant Code Review Phase in accordance with Paragraph 8.18 (notwithstanding any consultation undertaken pursuant to Paragraph 8.17.5 and its outcome), unless directed otherwise by the Authority pursuant to Paragraph 8.17.3.
Subject to Paragraph 8.17.4, the Authority may at any time direct that a CUSC Modification Proposal made during a Significant Code Review Phase falls within the scope of a Significant Code Review and must not be made during the Significant Code Review Phase. If so directed, the CUSC Modifications Panel will not proceed with that CUSC Modification Proposal, and the Proposer shall decide whether the CUSC Modification Proposal shall be withdrawn or suspended until the end of the Significant Code Review Phase. If the Proposer fails to indicate its decision whether to withdraw or suspend the CUSC Modification Proposal within twenty-eight (28) days of the Authority’s direction, it shall be deemed to be suspended. If the CUSC Modification Proposal is suspended, it shall be open to the Proposer at the end of the Significant Code Review Phase to indicate to the CUSC Modifications Panel that it wishes that CUSC Modification Proposal to proceed, and it shall be considered and taken forward in the manner decided upon by the CUSC Modifications Panel at the next meeting, and it is open to the CUSC Modifications Panel to take into account any work previously undertaken in respect of that CUSC Modification Proposal. If the Proposer makes no indication to the CUSC Modifications Panel within twenty-eight (28) days of the end of the Significant Code Review Phase as to whether or not it wishes the CUSC Modification Proposal to proceed, it shall be deemed to be withdrawn.
A CUSC Modification Proposal that falls within the scope of a Significant Code Review may be made where:
the Authority so determines, having taken into account (among other things) the urgency of the subject matter of the CUSC Modification Proposal; or
the CUSC Modification Proposal is made by The Company pursuant to Paragraph 8.17.6.
Where a direction under Paragraph 8.17.3 has not been issued, paragraph 8.17.4 does not apply and the CUSC Modifications Panel considers that a CUSC Modification Proposal made during a Significant Code Review Phase falls within the scope of a Significant Code Review, the CUSC Modifications Panel may consult on its suitability as part of the Standard CUSC Modification Proposal route set out in Paragraphs 8.19, 8.20, 8.22 and 8.23. End of Significant Code Review Phase
Within twenty-eight (28) days after the Authority has published its Significant Code Review conclusions, the Authority may:
issue to The Company directions, including directions to The Company to make CUSC Modification Proposals; or
itself make a CUSC Modification Proposal arising from the relevant Significant Code Review 8.17.6A If the Authority issues a statement that it will continue work and/or issues a direction in accordance with Paragraph 8.17.C.1 then the Significant Code Review Phase will be deemed to have ended when:
the Authority issues a statement that the Significant Code Review Phase has ended;
one of the circumstances in Paragraphs 8.17.6(a) or 8.17.8 occurs (irrespective of whether such circumstance occurs within 28 days after the Authority has published its Significant Code Review conclusions); or 8.17.7 Where the Authority issues directions pursuant to Paragraph 8.17.6(a) The Company shall comply with those directions and the Significant Code Review Phase shall be deemed to have ended on the date on which The Company makes a CUSC Modification Proposal in accordance with the Authority’s directions.
Where the Authority makes a CUSC Modification Proposal pursuant to 8.17.6(b), the Significant Code Review Phase shall be deemed to have ended on the date on which the Authority makes such CUSC Modification Proposal.
Where a CUSC Modification Proposal is raised pursuant to Paragraph 8.17.6, that CUSC Modification Proposal shall be treated as a Standard CUSC Modification Proposal and shall proceed through the process for Standard CUSC Modification Proposals set out in Paragraphs 8.18, 8.19, 8.20, 8.22 and 8.23. Such Authority conclusions and directions shall not fetter the voting rights of the Panel Members or any recommendation it makes in relation to any CUSC Modification Proposal or the recommendation procedures informing the CUSC Modification Report.
The Company may not, without the prior consent of the Authority, withdraw a CUSC Modification Proposal made pursuant to a direction issued by the Authority pursuant to Paragraph 8.17.6 (a).
If within twenty-eight (28) days after the Authority has published its Significant Code Review conclusions, the Authority issues to The Company a statement that no directions will be issued in relation to the CUSC, then the Significant Code Review Phase shall be deemed to have ended on the date of such statement.
Unless the Authority issues a statement in accordance with Paragraph 8.17.6A, if up to and including twenty-eight (28) days from the Authority’s publication of its Significant Code Review conclusions, the Authority has issued to The Company neither directions pursuant to Paragraph 8.17.6(a) nor a statement pursuant to Paragraph 8.17.11, nor has the Authority made a CUSC Modification Proposal as described in Paragraph 8.17.6(b) then the Significant Code Review Phase will be deemed to have ended. 8.17A AUTHORITY RAISED OR DIRECTED MODIFICATION 8.17A.1 The Authority may:
itself; or
direct The Company to raise a CUSC Modification Proposal where the Authority reasonably considers that such CUSC Modification Proposal is necessary to comply with or implement the Electricity Regulation and/or any relevant Legally Binding Decisions of the European Commission and/or The Agency or in respect of Significant Code Review. 8.17A.2 The Company shall comply with any directions from the Authority in relation to setting and/or amending a timetable for;
the raising of a CUSC Modification Proposal pursuant to Paragraph 8.17A.1(b); and/or
where the Authority has approved a CUSC Modification Proposal raised pursuant to Paragraph 8.17A.1, implementation of such CUSC Modification Proposal. 8.17A.3 In respect of a CUSC Modification Proposal raised pursuant to Paragraph 8.17A.1, the CUSC Modification Panel shall comply with any timetable(s) directed by the Authority in relation to setting and/or amending a timetable for the completion of all relevant steps of the CUSC Modification Process or such other processes set out in this Section 8. 8.17A.4 Notwithstanding any other Paragraphs in this Section 8, a CUSC Modification Proposal raised pursuant to Paragraph 8.17A.1:
shall not be withdrawn by the Transmission Company and/or the CUSC Modification Panel without the prior consent of the Authority. (b)shall not be amalgamated with any other CUSC Modification Proposal without the prior consent of the Authority. 8.17A.5 If, pursuant to paragraph 8.17A.4(a), the Authority consents to the withdrawal of a CUSC Modification Proposal, the provisions of Paragraph 8.16.10 shall apply to such CUSC Modification Proposal. 8.17A.6 In respect of any CUSC Modification Proposal which has been raised pursuant to Paragraph 8.17A.9, the views of the relevant Workgroup, the voting rights of the CUSC Modifications Panel or the recommendation of the CUSC Modifications Panel shall not be fettered or restricted notwithstanding that such CUSC Modification Proposal has been raised under Paragraph 8.17A.9. 8.17A.7 A CUSC Modification Proposal shall still be assessed against the Self Governance Criteria and Fast Track Criteria notwithstanding that it has been raised pursuant to Paragraph 8.17A.1. 8.17A.8 A CUSC Modification Proposal raised pursuant to Paragraph 8.17A.1 shall not be rejected by the Panel Secretary pursuant to Paragraphs 8.16.5 or 8.16.6. 8.17A.9 In relation to any CUSC Modification Proposal raised by The Company other than pursuant to Paragraph 8.17A.1, where the Authority reasonably considers such CUSC Modification Proposal to be necessary to comply with or implement the Electricity Regulation and/or any relevant Legally Binding Decisions of the European Commission and/or The Agency , the provisions of Paragraphs 8.17A.2 to 8.17A.8 shall apply. 8.17B AUTHORITY LED SCR MODIFICATION 8.17B.1 Where the Authority has issued a statement in accordance with Paragraph 8.17.6A and/or a Backstop Direction in accordance with Paragraph 8.17C, the Authority may submit an Authority Led CUSC Modification Proposal for an Authority Led CUSC Modification directly to the CUSC Panel. 8.17B.2 In response to an Authority Led CUSC Modification Proposal the CUSC Panel shall prepare an Authority Led CUSC Modification Report which shall include all the items listed in 8.23.2 (a)-(k) and in particular, as identified in the Licence:
an evaluation of the proposed modification; and
an assessment of the extent to which the proposed modification would better facilitate achievement of the applicable CUSC objective(s); and
a detailed explanation of the CUSC Panel’s reasons for that assessment (such assessment to include, where the impact is likely to be material, an assessment of the proposal on greenhouse gas emissions, to be conducted in accordance with such guidance on the treatment of carbon costs and evaluation of the greenhouse gas emissions as may be issued by the Authority from time to time); and
a timetable for implementation of the proposed modification, including the date with effect from which such proposed modification could take effect. 8.17B.3 The Authority Led CUSC Modification Report shall be submitted to the Authority taking into account the Prioritisation Criteria, and whether the proposed modification is an Urgent CUSC Modification Proposal or not, or, where it is not Urgent CUSC Modification Proposal or a CUSC Modification Fast Track Proposal, the Prioritisation Category of the proposed modification, and in accordance with the time periods specified in the CUSC, which shall not be extended unless approved by the Panel and not objected to by the Authority after receiving notice in accordance with the timetable set by the Authority in Paragraph 8.17B.6. 8.17B.4 The Authority can require the revision and re-submission of the Authority Led CUSC Modification Report, such resubmission to be made, if required by a direction issued by the Authority in accordance with Paragraph 8.23.12, as soon after the Authority’s direction as is appropriate taking into account the Prioritisation Criteria, and whether the proposed modification is an Urgent CUSC Modification Proposal or not, or, where it is not an Urgent CUSC Modification Proposal or a CUSC Modification Fast Track Proposal, the Prioritisation Category of the proposed modification and in accordance with the time periods specified in the CUSC, which shall not be extended unless approved by the Panel and not objected to by the Authority after receiving notice in accordance with the timetable set by the Authority in Paragraph 8.17B.6. 8.17B.5 The timetable referred to in Paragraph 8.17B.2 (d) for implementation of any proposed modification shall be in accordance with any direction(s) issued by the Authority for the implementation of a proposed modification where no such direction has been issued by the Authority, the timetable shall be such as will enable the modification to take effect as soon as practicable after the Authority has directed that such modification should be made, account being taken of the Prioritisation Criteria, and whether the proposed modification is an Urgent CUSC Modification Proposal or not, or where it isn’t an Urgent CUSC Modification Proposal or a CUSC Modification Fast Track Proposal, the Prioritisation Category of the proposed modification and in accordance with the time periods specified in the CUSC, which shall not be extended unless approved by the Panel and not objected to by the Authority after receiving notice with the Authority having discretion to change the timetable. 8.17B.6 The timetable for the completion of the procedural steps for an Authority Led CUSC Modification, as outlined in Paragraphs 8.17B.2, 8.17B.3, 8.17B.4, shall be set by the Authority in its sole discretion. 8.17B.7 The Authority’s published conclusions and directions and the Authority Led CUSC Modification Proposal shall not fetter the voting rights of the Panel Members or any recommendation it makes in relation to any Authority Led CUSC Modification Proposal or the procedures informing the report described at Paragraph 8.17B.2. 8.17C BACKSTOP DIRECTION 8.17C.1 Where a CUSC Modification Proposal has been made in relation to a Significant Code Review in accordance with Paragraph 8.17A.1 the Authority may issue a direction (a “Backstop Direction”), which requires such proposal(s) and any alternatives to be withdrawn and which causes the Significant Code Review phase to recommence.
This Paragraph 8.18 is subject to the Urgent CUSC Modification Proposals procedures set out in Paragraph 8.24 and the Significant Code Review procedures set out in Paragraph 8.17.
A CUSC Modification Proposal shall, subject to Paragraph 8.16.8, be discussed by the CUSC Modifications Panel at the next following CUSC Modifications Panel meeting convened.
The Proposer’s representative shall attend such CUSC Modifications Panel meeting and the CUSC Modifications Panel may invite the Proposer’s representative to present their CUSC Modification Proposal to the CUSC Modifications Panel.
The CUSC Modifications Panel shall evaluate each CUSC Modification Proposal against the Self-Governance Criteria.
The CUSC Modifications Panel shall follow the procedure set out in Paragraph 8.25 in respect of any CUSC Modification Proposal that the CUSC Modifications Panel considers meets the Self- Governance Criteria unless the Authority makes a direction in accordance with Paragraph 8.25.2 and in such a case that CUSC Modification Proposal shall be a Standard CUSC Modification Proposal and shall follow the procedure set out in Paragraphs 8.19, 8.20, 8.22 and 8.23.
Unless the Authority makes a direction in accordance with Paragraph 8.25.4, a CUSC Modification Proposal that the CUSC Modifications Panel considers does not meet the Self-Governance Criteria shall be a Standard CUSC Modification Proposal and shall follow the procedure set out in Paragraphs 8.19, 8.20, 8.22 and 8.23.
The CUSC Modifications Panel shall evaluate each CUSC Modification Fast Track Proposal against the Fast Track Criteria.
The CUSC Modifications Panel shall follow the procedure set out in Paragraph 8.29 in respect of any CUSC Modification Fast Track Proposal. The provisions of Paragraphs 8.19 to 8.25 shall not apply to a CUSC Modification Fast Track Proposal. 8.18.8A The CUSC Modification Panel shall evaluate each CUSC Modification Proposal and determine whether the CUSC Modification Proposal constitutes an EBR Amendment and its expected impact on the objectives of the Electricity Balancing Regulation (and in the event of disagreement The Company’s view shall prevail).
Unless a Modification Proposal has been determined to be an Urgent CUSC Modification Proposal or a CUSC Modification Fast Track Proposal, the CUSC Modifications Panel shall evaluate each CUSC Modification Proposal against the Prioritisation Criteria to determine the relevant Prioritisation Category of the modification, taking into account the views of the Proposer as established in sub-paragraph 8.16.4 (m).
(a) The Code Administrator and the CUSC Modifications Panel shall together establish a timetable to apply for the CUSC Modification Process.
The CUSC Modifications Panel shall establish the part of the timetable for the consideration by the CUSC Modifications Panel and by a Workgroup (if any) which shall be no longer than four months unless in any case the particular circumstances of the CUSC Modification Proposal (taking due account of the Prioritisation Criteria, and whether the CUSC Modification Proposal is an Urgent CUSC Modification Proposal or, where the CUSC Modification Proposal isn’t an Urgent CUSC Modification Proposal or a CUSC Modification Fast Track Proposal, its Prioritisation Category) justify an extension of such timetable, and provided the Authority, after receiving notice, does not object, taking into account all those issues.
The Code Administrator shall establish the part of the timetable for the consultation to be undertaken by the Code Administrator under this Section 8 and separately the preparation of a CUSC Modification Report to the Authority. Where the particular circumstances of the CUSC Modification Proposal (taking due account the Prioritisation Criteria, and whether the CUSC Modification Proposal is an Urgent CUSC Modification Proposal or, where the CUSC Modification Proposal isn’t an Urgent CUSC Modification Proposal or a CUSC Modification Fast Track Proposal, its Prioritisation Category) justify an extension of such timescales and provided the Authority, after receiving notice, does not object, taking into account all those issues, the Code Administrator may revise such part of the timetable.
In setting such a timetable, the CUSC Modifications Panel and the Code Administrator shall exercise their respective discretions such that, in respect of each CUSC Modification Proposal, a CUSC Modification Report may be submitted to the Authority as soon after the CUSC Modification Proposal is made as is consistent with the proper evaluation of such CUSC Modification Proposal, taking due account of the Prioritisation Criteria, and whether the CUSC Modification Proposal is an Urgent CUSC Modification Proposal, or where it isn’t an Urgent CUSC Modification Proposal or a CUSC Modification Fast Track Proposal, its Prioritisation Category.
Unless particular CUSC Modification Proposals have been determined to be Urgent CUSC Modification Proposals or CUSC Modification Fast Track Proposals, and having regard to the Prioritisation Criteria and the assessment provided by the Proposer in paragraph 8.16.4 (m), the CUSC Modifications Panel may determine the Prioritisation Category of CUSC Modification Proposals and may (subject to any objection from the Authority taking into account all those issues) adjust the Prioritisation Category of the relevant CUSC Modification Proposal accordingly.
where the CUSC Modification Proposal constitutes an EBR Amendment the timetable shall be such that the Code Administrator’s consultation is not less than one month.
In relation to each CUSC Modification Proposal, the CUSC Modifications Panel shall determine at any meeting of the CUSC Modifications Panel whether to:
amalgamate the CUSC Modification Proposal with any other CUSC Modification Proposal;
invite the Proposer to further develop their CUSC Modification Proposal before presenting to a subsequent meeting of the CUSC Modifications Panel or to withdraw their CUSC Modification proposal;
establish a Workgroup of the CUSC Modifications Panel, to consider the CUSC Modification Proposal;
review the evaluation made pursuant to Paragraph 8.18.4, taking into account any new information received; or
proceed directly to wider consultation (in which case the Proposer’s right to vary their CUSC Modification Proposal shall lapse).
Subject to Paragraphs 8.14.3 and 8.17A.4(b), the CUSC Modifications Panel may decide to amalgamate a CUSC Modification Proposal with one or more other CUSC Modification Proposals where the subject-matter of such CUSC Modification Proposals is sufficiently proximate to justify amalgamation on the grounds of efficiency and/or where such CUSC Modification Proposals are logically dependent on each other.
Without prejudice to each Proposer’s right to withdraw their CUSC Modification Proposal prior to the amalgamation of their CUSC Modification Proposal where CUSC Modification Proposals are amalgamated pursuant to Paragraph 8.19.3:
such CUSC Modification Proposals shall be treated as a single CUSC Modification Proposal;
references in this Section 8 to a CUSC Modification Proposal shall include and apply to a group of two or more CUSC Modification Proposals so amalgamated;
the Proposers of each such CUSC Modification Proposal shall co-operate in deciding which of them is to provide a representative for any Workgroup in respect of the amalgamated CUSC Modification Proposal and, in default of agreement, the Panel Chairperson shall nominate one of the Proposers for that purpose; and
where CUSC Modification Proposals are amalgamated and the resultant amalgamated CUSC Modification Proposal is not an Urgent CUSC Modification Proposal or a CUSC Modification Fast Track Proposal, the Panel shall determine the amalgamated CUSC Modification Proposal to have a single Prioritisation Category. When determining a Prioritisation Category for an amalgamated CUSC Modification Proposal, the Panel shall consider the Prioritisation Categories, and the relevant assessments undertaken in determining these Prioritisation Categories, accorded to the original CUSC Modification Proposals that have been amalgamated.
In respect of any CUSC Modification Proposal that the CUSC Modifications Panel determines to proceed directly to wider consultation in accordance with Paragraph 8.19.2, the CUSC Modifications Panel, may at any time prior to the CUSC Modifications Panel Recommendation Vote having taken place decide to establish a Workgroup of the CUSC Modifications Panel and the provisions of Paragraph 8.20 shall apply. In such case the CUSC Modifications Panel shall be entitled to adjust the timetable referred to at Paragraph 8.19.1(b) and the Code Administrator shall be entitled to adjust the timetable referred to at Paragraph 8.19.1(c), provided that the Authority, after receiving notice, does not object.
Where the CUSC Modifications Panel in accordance with Paragraph to 8.19.2(b) invites the Proposer to further develop their CUSC Modification Proposal, and the Proposer agrees, on the Proposer presenting this to a subsequent meeting of the CUSC Modifications Panel, the Panel will determine a way forward from the options in 8.19.2 (a), (c), (d) and (e) or invite the Proposer to withdraw their modification proposal.
Where the CUSC Modifications Panel in accordance with Paragraphs 8.19.2(b) or 8.19.6 invites the Proposer to further develop or withdraw their CUSC Modification Proposal and this is declined, the Panel will determine a way forward from the options in
(a), (c), (d) or (e).
If the CUSC Modifications Panel has decided not to proceed directly to wider consultation (or where the provisions of Paragraph 8.19.5 apply), a Workgroup will be established, or an existing Standing Group identified and actioned, by the CUSC Modifications Panel to assist the CUSC Modifications Panel in evaluating whether a CUSC Modification Proposal better facilitates achieving the Applicable CUSC Objectives and whether a Workgroup Alternative CUSC Modification(s) would, as compared with the CUSC Modification Proposal, better facilitate achieving the Applicable CUSC Objectives in relation to the issue or defect identified in the CUSC Modification Proposal. Where a Standing Group is identified and actioned in relation to a CUSC Modification Proposal, a reference to Workgroup in this Section 8 shall, in relation to that CUSC Modification Proposal, be deemed to be a reference to that Standing Group acting in that capacity. Unless specifically appointed pursuant to this Paragraph or permitted pursuant to Paragraph 8.22, a Standing Group shall not comment upon any CUSC Modification Proposal.
A single Workgroup may be responsible for the evaluation of more than one CUSC Modification Proposal at the same time,but need not be so responsible.
A Workgroup shall comprise at least five (5) persons (who may be Panel Members) selected by the CUSC Modifications Panel from those nominated by CUSC Parties, BSC Parties, the Citizens Advice or the Citizens Advice Scotland for their relevant experience and/or expertise in the areas forming the subject-matter of the CUSC Modification Proposal(s) to be considered by such Workgroup (and the CUSC Modifications Panel shall ensure, as far as possible, that an appropriate cross-section of representation, experience and expertise is represented on such Workgroup) provided that there shall always be at least one member representing The Company and if, and only if, the CUSC Modifications Panel is of the view that a CUSC Modification Proposal is likely to have an impact on the STC, the CUSC Modifications Panel may invite the STC committee to appoint a representative to become a member of the Workgroup. A representative of the Authority may attend any meeting of a Workgroup as an observer and may speak at such meeting.
The Code Administrator shall in consultation with the CUSC Modifications Panel appoint the chairperson of the Workgroup who shall act impartially and as an independent chairperson.
No Workgroup or meeting of a Workgroup will be considered quorate with less than five (5) persons, in addition to the Code Administrator representative or the chairperson of the Workgroup. Where insufficient persons are nominated to a Workgroup for it to be quorate, the Code Administrator will report this to the next meeting of the CUSC Modifications Panel. The Panel may:
Request the Code Administrator to seek further nominations;
Reconsider their decision on how to progress the CUSC Modification Proposal as allowed under 8.19.2; or
Request that those parties that have nominated themselves to a Workgroup which is less than quorate should proceed as a Limited Membership Workgroup, subject to the following additional checks and balances:
A Limited Membership Workgroup shall always hold a Workgroup Consultation in addition to the mandatory Code Administrator Consultation.
Prior to the Workgroup Consultation, a draft of this shall be circulated to the CUSC Modifications Panel for five (5) days or another timescale as agreed by the CUSC Modifications Panel for approval.
At the same time as the Workgroup Consultation is initiated, the Code Administrator shall again formally seek nominations and if quoracy is not established then again seek advice from the CUSC Modifications Panel on how to proceed from the options set out in this 8.20.5. Where a Workgroup remains non-quorate, and with the permission of the CUSC Modifications Panel, a Limited Membership Workgroup may (subject to Paragraph 8.20.6) continue following a Workgroup Consultation as if it were a standard Workgroup.
A Limited Membership Workgroup may at any point be instructed by the Authority to either:
Stop work: or
To provide a report on progress to the next meeting of the CUSC Modifications Panel The Authority may also at any point instruct the Code Administrator to seek further nominations for membership
Where a specific meeting of an otherwise quorate Workgroup is not quorate, or where member(s) of a Limited Membership Workgroup are unable to attend a meeting:
A member of the Workgroup unable to attend will be invited by the Code Administrator to send an alternate
All members will be invited to participate by telephone, webinar or other equivalent if not able to attend in person
A meeting may proceed as a Workgroup meeting as long as none of the members either present or absent raise an objection to this, however no voting can take place unless the Code Administrator has obtained enough votes to be quorate from members not in attendance or from all members of a Limited Membership Workgroup. This shall include where there has not been an opportunity to check with all Workgroup members to see if they have an objection (typically where a change of plans or circumstances has occurred too late to achieve this),
If any Workgroup member objects to the progressing of a Workgroup without them, they must communicate this to the Code Administrator at least 24 hours before the meeting indicating that they will not be present and do not wish the meeting to take place. The Code Administrator will then endeavour to rearrange the meeting to accommodate such a member’s availability.
Where a Workgroup member is repeatedly unavailable, as guidance on 3 consecutive occasions, and does not give permission for the Workgroup to proceed without them as in (d), under 8.20.9 the CUSC Modifications Panel may choose to replace or remove them.
The CUSC Modifications Panel may add further members or the Workgroup chairperson may add or vary members to a Workgroup.
The CUSC Modifications Panel may (but shall not be obliged to) replace any member or observer of a Workgroup appointed pursuant to Paragraph 8.20.3 at any time if such member is unwilling or unable for whatever reason to fulfil that function and/or is deliberately and persistently disrupting or frustrating the work of the Workgroup.
The CUSC Modifications Panel shall determine the terms of reference of each Workgroup and may change those terms of reference from time to time as it sees fit.
The terms of reference of a Workgroup must include provision in respect of the following matters:
those areas of a Workgroup’s powers or activities which require the prior approval of the CUSC Modifications Panel;
the seeking of instructions, clarification or guidance from the CUSC Modifications Panel, including on the suspension of a Workgroup Alternative CUSC Modification(s) during a Significant Code Review Phase;
the timetable for the work to be done by the Workgroup, in accordance with the timetable established pursuant to Paragraph 8.19.1 (save where Paragraph 8.19.5 applies); and
the length of any Workgroup Consultation. In addition, prior to the taking of any steps which would result in the undertaking of a significant amount of work (including the production of draft legal text to modify the CUSC in order to give effect to a CUSC Modification Proposal and/or Workgroup Alternative CUSC Modification(s), with the relevant terms of reference setting out what a significant amount of work would be in any given case), the Workgroup shall seek the views of the CUSC Modifications Panel as to whether to proceed with such steps and, in giving its views, the CUSC Modifications Panel may consult the Authority in respect thereof.
whether, and the extent to which, the CUSC Modification Proposal may constitute an amendment to the EBR Article 18 Terms and Conditions; and
where the Workgroup considers that a CUSC Modification Proposal may constitute an amendment to the EBR Article 18 Terms and Conditions, the impact of those amendments on the objectives of the Electricity Balancing Regulation.
Subject to the provisions of this Paragraph 8.20.12 and unless otherwise determined by the CUSC Modifications Panel, the Workgroup shall develop and adopt its own internal working procedures for the conduct of its business and shall provide a copy of such procedures to the Panel Secretary in respect of each CUSC Modification Proposal for which it is responsible. Unless the CUSC Modifications Panel otherwise determines, meetings of each Workgroup shall be open to attendance by a representative of any CUSC Party, any BSC Party, the Citizens Advice, the Citizens Advice Scotland and any person invited by the chairperson, and the chairperson of a Workgroup may invite any such person to speak at such meetings.
After development by the Workgroup of the CUSC Modification Proposal, and (if applicable) after development of any draft Workgroup Alternative CUSC Modification(s), the Workgroup will (subject to the provisions of Paragraph 8.20.19) consult (“Workgroup Consultation”) on the CUSC Modification Proposal and, if applicable, on any draft Workgroup Alternative CUSC Modification(s) with:
CUSC Parties; and
such other persons who may properly be considered to have an appropriate interest in it. Where following the establishment of a Workgroup in relation to a CUSC Modification Proposal, the terms of reference of a Standing Group have been amended by the CUSC Modifications Panel to include the ability to comment on that CUSC Modification Proposal, that Standing Group as a body shall be deemed to fall within sub- paragraph (b) above and therefore shall be able to respond to the Workgroup Consultation. It shall not, however, in so doing undertake the functions of a Workgroup. In the absence of such a change in terms of reference, the Standing Group as a body shall have no ability to respond to any Workgroup Consultation.
The Workgroup Consultation will be undertaken by issuing a Workgroup Consultation paper (and its provision in electronic form on the Website and in electronic mails to CUSC Parties and such other persons, who have supplied relevant details, shall meet this requirement). Such Workgroup Consultation paper will include: (a)Issues which arose in the Workgroup discussions
Details of any draft Workgroup Alternative CUSC Modification(s)
The date proposed by the Code Administrator as the Proposed Implementation Date.
Workgroup Consultation papers will be copied to Core Industry Document Owners, the CM Administrative Parties, the CfD Administrative Parties and the secretary of the STC committee.
Any CUSC Party, BSC Party, the Citizens Advice or the Citizens Advice Scotland may (subject to Paragraph 8.20.20) raise a Workgroup Consultation Alternative Request in response to the Workgroup Consultation. Such Workgroup Consultation Alternative Request must include:
the information required by Paragraph 8.16.4 (which shall be read and construed so that any references therein to “amendment proposal” or “proposal” shall be read as “request” and any reference to “Proposer” shall be read as “requester”); and
sufficient detail to enable consideration of the request including details as to how the request better facilitates the Applicable CUSC Objectives than the current version of the CUSC, than the CUSC Modification Proposal and than any draft Workgroup Alternative CUSC Modification(s).
The Workgroup shall consider and analyse any comments made or any Workgroup Consultation Alternative Request made by any CUSC Party in response to the Workgroup Consultation.
If a majority of the members of the Workgroup or the chairperson of the Workgroup believe that the Workgroup Consultation Alternative Request may better facilitate the Applicable CUSC Objectives than the CUSC Modification Proposal, the Workgroup shall develop it as a Workgroup Alternative CUSC Modification(s) or, where the chairperson of the Workgroup agrees, amalgamate it with one or more other draft Workgroup Alternative CUSC Modification(s) or Workgroup Consultation Alternative Request(s);
Unless the CUSC Modifications Panel directs the Workgroup otherwise pursuant to Paragraph 8.20.,20 and provided that a Workgroup Consultation has been undertaken in respect of the CUSC Modification Proposal, no further Workgroup Consultation will be required in respect of any Workgroup Alternative CUSC Modification(s) developed in respect of such CUSC Modification Proposal.
The CUSC Modifications Panel may, at the request of the chairperson of the Workgroup, direct the Workgroup to undertake further Workgroup Consultation(s). At the same time as such direction the CUSC Modifications Panel shall adjust the timetable referred to at Paragraph 8.19.1(b) and the Code Administrator shall be entitled to adjust the timetable referred to at Paragraph 8.19.1 (c), provided that the Authority, after receiving notice, does not object. No Workgroup Consultation Alternative Request may be raised by any CUSC Party during any second or subsequent Workgroup Consultation.
The Workgroup shall finalise the Workgroup Alternative CUSC Modification(s) for inclusion in the report to the CUSC Modifications Panel.
Each Workgroup chairperson shall prepare a report to the CUSC Modifications Panel responding to the matters detailed in the terms of reference in accordance with the timetable set out in the terms of reference.
If a Workgroup is unable to reach agreement on any such matter, the report must reflect the views of the members of the Workgroup.
The report will be circulated in draft form to Workgroup members and a period of not less than five (5) Business Days or if all Workgroup members agree three (3) Business Days given for comments thereon. Any unresolved comments made shall be reflected in the final report.
The chairperson or another member (nominated by the chairperson) of the Workgroup shall attend the next CUSC Modifications Panel meeting following delivery of the report and may be invited to present the findings and/or answer the questions of Panel Members in respect thereof. Other members of the Workgroup may also attend such CUSC Modifications Panel meeting.
At the meeting referred to in Paragraph 8.20.23 the CUSC Modifications Panel shall consider the Workgroup’s report and shall determine whether to:-
refer the CUSC Modifications Proposal back to the Workgroup for further analysis (in which case the CUSC Modifications Panel shall determine the timetable and terms of reference to apply in relation to such further analysis); or
proceed then to wider consultation as set out in Paragraph 8.22; or
decide on another suitable course of action.
Subject to paragraph 8.17.4 if, at any time during the assessment process carried out by the Workgroup pursuant to this Paragraph 8.20, the Workgroup considers that a CUSC Modification Proposal or any Workgroup Alternative CUSC Modification(s) falls within the scope of a Significant Code Review, it shall consult on this as part of the Workgroup Consultation and include its reasoned assessment in the report to the CUSC Modifications Panel prepared pursuant to Paragraph 8.20.22. If the CUSC Modifications Panel considers that the CUSC Modification Proposal or the Workgroup Alternative CUSC Modification(s) falls within the scope of a Significant Code Review, it shall consult with the Authority. If the Authority directs that the CUSC Modification Proposal or Workgroup Alternative CUSC Modification(s) falls within the scope of the Significant Code Review, the CUSC Modification Proposal and any Workgroup Alternative CUSC Modification(s) shall be suspended or withdrawn during the Significant Code Review Phase, in accordance with Paragraph 8.17.3.
The Proposer may, at any time prior to the final evaluation by the Workgroup (in accordance with its terms of reference and working practices) of that CUSC Modification Proposal against the Applicable CUSC Objectives, vary their CUSC Modification Proposal on notice (which may be given verbally) to the chairperson of the Workgroup provided that such varied CUSC Modification Proposal shall address the same issue or defect originally identified by the Proposer in their CUSC Modification Proposal.
The CUSC Modifications Panel may (but shall not be obliged to) require a CUSC Modification Proposal to be withdrawn in accordance with paragraph 8.17.6 if, in the Panel’s opinion, the Proposer of that CUSC Modification Proposal is deliberately and persistently disrupting or frustrating the work of the Workgroup and that CUSC Modification Proposal shall be deemed to have been so withdrawn. In the event that a CUSC Modification Proposal is so withdrawn, the provisions of paragraph 8.16.10 shall apply in respect of that CUSC Modification Proposal.
The CUSC Modifications Panel may set up one or more standing groups (each a “Standing Group”) to consider and report to the CUSC Modifications Panel on issues specified by the CUSC Modifications Panel relating to the connection and use of system arrangements in Great Britain, including the Charging Methodologies. The CUSC Modifications Panel may change issues specified from time to time as it sees fit. In setting up a Standing Group, the CUSC Modifications Panel shall determine the terms of reference of the Standing Group (and may change those terms of reference from time to time as it sees fit) and specify a time period within which the Standing Group is to report to it on the issue it is to consider and may establish other timetable requirements in relation to the intended scope of the Standings Group’s considerations. At the end of the time period by which the Standing Group is to report, the CUSC Modifications Panel shall decide whether the Standing Group is to continue and, if it is to continue, shall specify a time period in which it is to further report.
A Standing Group shall comprise at least five (5) persons (who may be Panel Members) selected by the CUSC Modifications Panel from those nominated by CUSC Parties for their relevant experience and/or expertise in the aspect or issue to be considered by such Standing Group (and the CUSC Modifications Panel shall ensure, as far as possible, that an appropriate cross-section of representation, experience and expertise is represented on such Standing Group) provided that there shall always be at least one member representing The Company and if, and only if, the CUSC Modifications Panel is of the view that a CUSC Modification Proposal is likely to have an impact on the STC, the CUSC Modifications Panel may invite the STC committee to appoint a representative to become a member of the Standing Group. A representative of the Authority may attend any meeting of a Standing Group as an observer and may speak at such meeting.
The Code Administrator shall in consultation with the CUSC Modifications Panel appoint the chairperson of each Standing Group who shall act impartially and as an independent chairperson.
The CUSC Modifications Panel may add further members or the Standing Group chairperson may add or vary members to a Standing Group after it is established.
The CUSC Modifications Panel may (but shall not be obliged to) replace any member of a Standing Group appointed pursuant to Paragraph 8.21.2 at any time if such member is unwilling or unable for whatever reason to fulfil that function and/or is deliberately and persistently disrupting or frustrating the work of the Standing Group.
Each Standing Group chairperson shall prepare a report to the CUSC Modifications Panel responding to the matter detailed in the terms of reference in accordance with the time period set by the CUSC Modifications Panel.
If a Standing Group is unable to reach agreement on any such matter, the report must reflect the views of the members of the Standing Group.
The report will be circulated in draft form to Standing Group members and a period of not less than five (5) Business Days given for comments thereon. Any unresolved comments made shall be reflected in the final report.
The chairperson or another member (nominated by the chairperson) of the Standing Group shall attend the next CUSC Modifications Panel meeting following delivery of the report and may be invited to present the findings and/or answer the questions of Panel Members in respect thereof. Other members of the Standing Group may also attend such CUSC Modifications Panel meeting.
Subject to the provisions of this Paragraph 8.21 and unless otherwise determined by the CUSC Modifications Panel, the Standing Group shall develop and adopt its own internal working procedures for the conduct of its business and shall provide a copy of such procedures to the Panel Secretary. Unless the CUSC Modifications Panel otherwise determines, meetings of each Standing Group shall be open to attendance by a representative of any CUSC Party, any BSC Party, the Citizens Advice, the Citizens Advice Scotland and any person invited by the chairperson or any other member of that Standing Group, and the chairperson or any other member of that Standing Group may invite any person to speak at such meetings.
In respect of any CUSC Modification Proposal where a Workgroup has been established or a Standing Group identified and actioned Paragraph 8.22.2 to 8.22.6 shall apply.
After consideration of any Workgroup report on the CUSC Modification Proposal and if applicable any Workgroup Alternative CUSC Modification(s) by the CUSC Modifications Panel and a determination by the CUSC Modifications Panel to proceed to wider consultation, the Code Administrator shall bring to the attention of and consult on the CUSC Modification Proposal and if applicable any Workgroup Alternative CUSC Modification(s) with:
CUSC Parties; and
such other persons who may properly be considered to have an appropriate interest in it, including Small Participants, the Citizens Advice and the Citizens Advice Scotland; and
where the CUSC Modification Proposal, and if applicable, any Workgroup Alternative CUSC Modification(s) constitutes an EBR Amendment with the Authority and other relevant stakeholders.
Where the CUSC Modification Proposal, and if applicable, any Workgroup Alternative CUSC Modification (s) constitutes an EBR Amendment the Code Administrator’s consultation will be not less than one month. Where following the establishment of a Workgroup, the terms of reference of a Standing Group have been amended by the CUSC Modifications Panel to include the ability to comment on that CUSC Modification Proposal, that Standing Group as a body shall be deemed to fall within sub-paragraph (ii) above and therefore shall be able to respond to the Code Administrator’s consultation. It shall not, however, in so doing undertake the functions of a Workgroup. In the absence of such a change in terms of reference, the Standing Group as a body shall have no ability to respond to any consultation.
The consultation will be undertaken by issuing a Consultation Paper (and its provision in electronic form on the Website and in electronic mails to CUSC Parties and such other persons, who have supplied relevant details, shall meet this requirement).
The Consultation Paper will contain:
the proposed drafting for the CUSC Modification Proposal and any Workgroup Alternative CUSC Modification(s) (unless the Authority decides none is needed in the CUSC Modification Report under Paragraph 8.22.5) and will indicate the issues which arose in the Workgroup discussions, where there has been a Workgroup and will incorporate The Company’s and the CUSC Modifications Panel’s initial views on the way forward; and
the date proposed by the Code Administrator as the Proposed Implementation Date and, where the Workgroup terms of reference require and the dates proposed by the Workgroup are different from those proposed by the Code Administrator, those proposed by the Workgroup. In relation to a CUSC Modification Proposal that meets the Self- Governance Criteria, the Code Administrator may not propose an implementation date earlier than the sixteenth (16) Business Day following the publication of the CUSC Modifications Panel’s decision to approve or reject the CUSC Modification Proposal. Views will be invited on these dates.
Where the CUSC Modifications Panel is of the view that the proposed text to amend the CUSC for a CUSC Modification Proposal or Workgroup Alternative CUSC Modification(s) is not needed in the CUSC Modification Report (and provided the CUSC Modification Proposal and/or Workgroup Alternative CUSC Modification(s) does not constitute an EBR Amendment), the CUSC Modifications Panel shall consult (giving its reasons as to why it is of this view) with the Authority as to whether the Authority would like the CUSC Modification Report to include the proposed text to amend the CUSC. If it does not, no text needs to be included. If it does, and no detailed text has yet been prepared, the Code Administrator shall prepare such text to modify the CUSC in order to give effect to such CUSC Modification Proposal or Workgroup Alternative CUSC Modification(s) and shall seek the conclusions of the relevant Workgroup before consulting those identified in Paragraph 8.22.2.
Consultation Papers will be copied to Core Industry Document Owners, the CM Administrative Parties, the CfD Administrative Parties and the secretary of the STC committee.
In respect of any CUSC Modification Proposal where a Workgroup has not been established nor a Standing Group identified and actioned Paragraph 8.22.7 to 8.22.11 shall apply.
After determination by the CUSC Modifications Panel to proceed to wider consultation, such consultation shall be conducted by the Code Administrator on the CUSC Modification Proposal with:
CUSC Parties; and
such other persons who may properly be considered to have an appropriate interest in it, including Small Participants, the Citizens Advice and the Citizens Advice Scotland.; and
where the CUSC Modification Proposal and if applicable, any Workgroup Alternative CUSC Modification(s) constitutes an EBR Amendment with the Authority and other relevant stakeholders.
Where the CUSC Modification Proposal and if applicable, any Workgroup Alternative CUSC Modification(s) constitutes an EBR Amendment the Code Administrator’s consultation will be not less than one month. Where following the decision of the CUSC Modifications Panel to proceed directly to consultation by the Code Administrator, in relation to a CUSC Modification Proposal, the terms of reference of a Standing Group have been amended by the CUSC Modifications Panel to include the ability to comment on that CUSC Modification Proposal, that Standing Group as a body shall be deemed to fall within sub-paragraph (ii) above and therefore shall be able to respond to the Code Administrator’s consultation. It shall not, however, in so doing undertake the functions of a Workgroup. In the absence of such a change in terms of reference, the Standing Group as a body shall have no ability to respond to any consultation.
The consultation will be undertaken by issuing a Consultation Paper (and its provision in electronic form on the Website and in electronic mails to CUSC Parties and such other persons, who have supplied relevant details, shall meet this requirement). The Consultation Paper will be copied to the CM Administrative Parties and the CFD Administrative Parties.
The Consultation Paper will contain:
the proposed drafting for the CUSC Modification Proposal (unless the Authority decides none is needed in the CUSC Modification Report under Paragraph 8.22.11) and will incorporate The Company’s and the CUSC Modifications Panel’s initial views on the way forward; and
the date proposed by the Code Administrator as the Proposed Implementation Date. Views will be invited on this date.
where a CUSC Modification Proposal or any Workgroup Alternative CUSC Modification(s) constitutes an EBR Amendment, the expected impact on the objectives of the Electricity Balancing Regulation.
Where the CUSC Modifications Panel is of the view that the proposed text to amend the CUSC for a CUSC Modification Proposal is not needed (and provided the CUSC Modification Proposal, and if applicable, any Workgroup Alternative CUSC Modification(s), does not constitute an EBR Amendment), the CUSC Modifications Panel shall consult (giving its reasons to why it is of this view) with the Authority as to whether the Authority would like the CUSC Modification Report to include the proposed text to amend the CUSC. If it does not, no text needs to be included. If it does, and no detailed text has yet been prepared, the Code Administrator shall prepare such text to modify the CUSC in order to give effect to such CUSC Modification Proposal and consult those identified in Paragraph 8.22.2.
Subject to the Code Administrator’s consultation having been completed, the CUSC Modifications Panel shall prepare and submit to the Authority a report (the "CUSC Modification Report") in accordance with this Paragraph 8.23 for each CUSC Modification Proposal which is not withdrawn. 8.23.1.A Where a CUSC Modification Proposal or any Workgroup Alternative CUSC Modification constitutes an EBR Amendment, the Panel will consider any consultation responses received and any further work required to assess these as required under CUSC Paragraph 8.18.8A
The matters to be included in a CUSC Modification Report shall be the following (in respect of the CUSC Modification Proposal):
A description of the CUSC Modification Proposal and any Workgroup Alternative CUSC Modification(s), including the details of, and the rationale for, any variations made (or, as the case may be, omitted) by the Proposer together with the views of the Workgroup;
the Panel Members’ Recommendation;
a summary (agreed by the CUSC Modifications Panel) of the views (including any recommendations) from Panel Members in the CUSC Modifications Panel Recommendation Vote and the conclusions of the Workgroup (if there is one) in respect of the CUSC Modification Proposal and of any Workgroup Alternative CUSC Modification(s);
an analysis of whether (and, if so, to what extent) the CUSC Modification Proposal and any Workgroup Alternative CUSC Modification(s) would better facilitate achievement of the Applicable CUSC Objective(s) with a detailed explanation of the CUSC Modifications Panel’s reasons for its assessment, including, where the impact is likely to be material, an assessment of the quantifiable impact of the CUSC Modification Proposal and any Workgroup Alternative CUSC Modification(s) on greenhouse gas emissions, to be conducted in accordance with such current guidance on the treatment of carbon costs and evaluation of the greenhouse gas emissions as may be issued by the Authority from time to time, and providing a detailed explanation of the CUSC Modifications Panel’s reasons for that assessment;
an analysis of whether (and, if so, to what extent) any Workgroup Alternative CUSC Modification(s) would better facilitate achievement of the Applicable CUSC Objective(s) as compared with the CUSC Modification Proposal and any other Workgroup Alternative CUSC Modification(s) and the current version of the CUSC, with a detailed explanation of the CUSC Modifications Panel’s reasons for its assessment, including, where the impact is likely to be material, an assessment of the quantifiable impact of the Workgroup Alternative CUSC Modification(s) on greenhouse gas emissions, to be conducted in accordance with such current guidance on the treatment of carbon costs and evaluation of the greenhouse gas emissions as may be issued by the Authority from time to time, and providing a detailed explanation of the CUSC Modifications Panel’s reasons for that assessment;
the Proposed Implementation Date taking into account the views put forward during the process described at Paragraph 8.22.4(b) such date to be determined by the CUSC Modifications Panel in the event of any disparity between such views and those of the Code Administrator;
an assessment of:
the impact of the CUSC Modification Proposal and any Workgroup Alternative CUSC Modification(s) on the Core Industry Documents and the STC and an indication of potential inconsistencies between the CUSC Modification Proposal and the Capacity Market Documents and/or the CfD Documents;
the changes which would be required to the Core Industry Documents and the STC in order to give effect to the CUSC Modification Proposal and any Workgroup Alternative CUSC Modification(s);
the mechanism and likely timescale for the making of the changes referred to in Paragraph (ii);
the changes and/or developments which would be required to central computer systems and, if practicable, processes used in connection with the operation of arrangements established under the Core Industry Documents, the STC, the Capacity Market Documents and the CfD Documents;
the mechanism and likely timescale for the making of the changes referred to in Paragraph (iv);
an estimate of the costs associated with making and delivering the changes referred to in Paragraphs (ii) and (iv), such costs are expected to relate to: for (ii) the costs of amending the STC and for (iv) the costs of changes to computer systems and possibly processes which are established for the operation of the Core Industry Documents, the STC, the Capacity Market Documents and the CfD Documents. together with an analysis and a summary of representations in relation to such matters, including any made by Small Participants, the Citizens Advice and the Citizens Advice Scotland;
to the extent such information is available to the Code Administrator, an assessment of the impact of the CUSC Modification Proposal and any Workgroup Alternative CUSC Modification(s) on CUSC Parties in general (or classes of CUSC Parties in general), including the changes which are likely to be required to their internal systems and processes and an estimate of the development, capital and operating costs associated with implementing the changes to the CUSC and to Core Industry Documents and the STC;
copies of (and a summary of) all written representations or objections made by consultees during the consultation in respect of the CUSC Modification Proposal and any Workgroup Alternative CUSC Modification(s) and subsequently maintained;
a copy of any impact assessment prepared by Core Industry Document Owners and the STC committee and a copy of any impact assessment related to the CUSC Modification Proposal prepared by the CM Administrative Parties in relation to the Capacity Market Rules, the Secretary of State in relation to the Capacity Market Documents, the CfD Administrative Parties in relation to the AF Rules, or the Secretary of State in relation to the CfD Documents, and the views and comments of the Code Administrator in respect thereof;
whether or not, in the opinion of The Company, the CUSC Modification Proposal (or any Workgroup Alternative CUSC Modification(s)) should be made;
whether the CUSC Modification Proposal and if applicable, any Workgroup Alternative CUSC Modification(s) constitutes an EBR Amendment and if so, and in addition to
above, The Company’s justification for including or not including the views resulting from the relevant consultation in the CUSC Modification Proposal and if applicable, any Workgroup Alternative CUSC Modification (s);
where a CUSC Modification Proposal or any Workgroup Alternative CUSC Modification(s) constitutes an EBR Amendment, the expected impact on the objectives of the Electricity Balancing Regulation; and
details of the assessment of the CUSC Modification Proposal against the Prioritisation Criteria to determine its Prioritisation Category (except where the relevant CUSC Modification Proposal has been determined to be an Urgent CUSC Modification Proposal or a CUSC Modification Fast Track Proposal).
A draft of the CUSC Modification Report will be circulated by the Code Administrator to CUSC Parties, Panel Members and such other persons who may properly be considered to have an appropriate interest in it, which for these purposes will include the CM Administrative Parties and the CfD Administrative Parties (and its provision in electronic form on the Website and in electronic mails to CUSC Parties and Panel Members, who must supply relevant details, shall meet this requirement) and a period of no less than five (5) Business Days given for comments to be made thereon. Any unresolved comments made shall be reflected in the final CUSC Modification Report.
A draft of the CUSC Modification Report shall be tabled at a meeting of the CUSC Modifications Panel prior to submission of that CUSC Modification Report to the Authority held in accordance with the timetable established pursuant to Paragraph 8.19.1, and at which the CUSC Modifications Panel may consider any minor changes to the legal drafting, which may include any issues identified through the Code Administrator’s consultation and:
if the change required is a typographical error the CUSC Modifications Panel may instruct the Code Administrator to make the appropriate change and the Panel Chairperson will undertake the CUSC Modifications Panel Recommendation Vote; or
if the change required is not considered to be a typographical error then the CUSC Modifications Panel may direct the Workgroup to review the change. If the Workgroup unanimously agree that the change is minor the CUSC Modifications Panel may instruct the Code Administrator to make the appropriate change and the Panel Chairperson will undertake the CUSC Modifications Panel Recommendation Vote. For changes that are not considered by the Workgroup to be minor the Code Administrator shall issue the CUSC Modification Proposal for further Code Administrator consultation after which the Panel Chairperson will undertake the CUSC Modifications Panel Recommendation Vote.
if a change is not required after consideration, the Panel Chairperson will undertake the CUSC Modifications Panel Recommendation Vote.
In the case of a modification that had been directed pursuant to CUSC 8.19.2(e) to proceed directly to wider consultation without the formation of a Workgroup, and if the change required is not considered to be a typographical error, then the CUSC Modifications Panel may direct the Code Administrator in conjunction with the Proposer to review the change. If the CUSC Modifications Panel, the Code Administrator and the Proposer agree that the change is minor the CUSC Modifications Panel may instruct the Code Administrator to make the appropriate change and the Panel Chairperson will undertake the CUSC Modifications Panel Recommendation Vote, otherwise for changes that are not considered to be minor the Code Administrator shall issue the CUSC Modification Proposal for further Code Administrator consultation after which the Panel Chairperson will undertake the CUSC Modifications Panel Recommendation Vote. In the case of a change that is not considered to be minor, the CUSC Modifications Panel may also consider whether to establish a Workgroup of the CUSC Modifications Panel, to further consider the CUSC Modification Proposal, in which case the procedures set out within CUSC 8.20 will be followed as required.
if a change is not required after consideration by the CUSC Modifications Panel, the Panel Chairperson will undertake the CUSC Modifications Panel Recommendation Vote.
A draft of the CUSC Modification Report following the CUSC Modifications Panel Recommendation Vote will be circulated by the Code Administrator to Panel Members (and in electronic mails to Panel Members, who must supply relevant details, shall meet this requirement) and a period of no less than five (5) Business Days given for comments to be made on whether the CUSC Modification Report accurately reflects the views of the Panel Members as expressed at the CUSC Modifications Panel Recommendation Vote. Any unresolved comments made shall be reflected in the final CUSC Modification Report.
Each CUSC Modification Report shall be addressed and furnished to the Authority and none of the facts, opinions or statements contained in such CUSC Modification Report may be relied upon by any other person.
Subject to Paragraphs 8.23.9 to 8.23.13, in accordance with the ESO Licence, the Authority may approve the CUSC Modification Proposal or a Workgroup Alternative CUSC Modification(s) contained in the CUSC Modification Report (which shall then be an "Approved CUSC Modification" until implemented). If the Authority believes that neither the CUSC Modification Proposal (nor any Workgroup Alternative CUSC Modification(s)) would better facilitate achievement of the Applicable CUSC Objectives, then there will be no approval. In such a case, the Code Administrator will notify CUSC Parties and will raise the issue at the next CUSC Modifications Panel meeting.
The Code Administrator shall copy (by electronic mail to those persons who have supplied relevant details to the Code Administrator) the CUSC Modification Report to:
each CUSC Party;
each Panel Member;
any person who may request a copy and shall place a copy on the Website; and
the CM Administrative Parties and the CfD Administrative Parties
Revised Fixed Proposed Implementation Date
Where the Proposed Implementation Date included in a CUSC Modification Report is a Fixed Proposed Implementation Date and the Authority considers that the Fixed Proposed Implementation Date is or may no longer be appropriate or might otherwise prevent the Authority from making such decision by reason of the effluxion of time the Authority may direct the CUSC Modifications Panel to recommend a revised Proposed Implementation Date.
Such direction may:
specify that the revised Proposed Implementation Date shall not be prior to a specified date;
specify a reasonable period (taking into account a reasonable period for consultation) within which the CUSC Modifications Panel shall be requested to submit its recommendation; and
provide such reasons as the Authority deems appropriate for such request (and in respect of those matters referred to in Paragraphs 8.23.9.2(a) and (b) above).
Before making a recommendation to the Authority, the CUSC Modifications Panel will consult on the revised Proposed Implementation Date, and may in addition consult on any matters relating to the CUSC Modification Report which in the CUSC Modifications Panel’s opinion have materially changed since the CUSC Modification Report was submitted to the Authority and where it does so the CUSC Modifications Panel shall report on such matters as part of its recommendation under CUSC Paragraph 8.23.9.4, with:
CUSC Parties; and
such other persons who may properly be considered to have an appropriate interest in it. Such consultation will be undertaken in accordance with CUSC Paragraphs 8.22.3 and 8.22.6.
Following the completion of the consultation held pursuant to CUSC Paragraph 8.23.9.3 the CUSC Modifications Panel shall report to the Authority with copies of all the consultation responses and recommending a Revised Proposed Implementation Date.
The Authority shall notify the CUSC Modifications Panel as to whether or not it intends to accept the Revised Proposed Implementation Date and where the Authority notifies the CUSC Modifications Panel that it intends to accept the Revised Proposed Implementation Date, the Revised Proposed Implementation Date shall be deemed to be the Proposed Implementation Date as specified in the CUSC Modification Report.
Authority Approval If:
the Authority has not given notice of its decision in respect of a CUSC Modification Report within two (2) calendar months (in the case of an Urgent CUSC Modification Proposal), or four (4) calendar months (in the case of all other CUSC Modification Proposals) from the date upon which the CUSC Modification Report was submitted to it; or
the CUSC Modifications Panel is of the reasonable opinion that the circumstances relating to the CUSC Modification Proposal and/or Workgroup Alternative CUSC Modification which is the subject of a CUSC Modification Report have materially changed, the CUSC Modifications Panel may request the Panel Secretary to write to the Authority requesting the Authority to give an indication of the likely date by which the Authority’s decision on the CUSC Modification Proposal will be made.
CUSC Paragraphs 8.23.9 and 8.23.10 shall only apply in respect of any CUSC Modification Proposals submitted after the CAP 179 Implementation Date.
If the Authority determines that the CUSC Modification Report is such that the Authority cannot properly form an opinion on the CUSC Modification Proposal and any Workgroup Alternative CUSC Modification(s), or where the CUSC Modification Proposal and/or any Workgroup Alternative CUSC Modification(s) constitutes an EBR Amendment where the Authority requires an amendment to CUSC Modification Proposal and/or any Workgroup Alternative CUSC Modification(s) in order to approve it, it may issue a direction to the CUSC Modifications Panel:
specifying the additional steps (including drafting or amending existing drafting associated with the CUSC Modification Proposal and any Workgroup Alternative CUSC Modification(s)), revision (including revision to the timetable), analysis or information that it requires in order to form such an opinion; and
requiring the CUSC Modification Report to be revised and to be re-submitted.
If a CUSC Modification Report is to be revised and re-submitted in accordance with a direction issued pursuant to Paragraph 8.23.12, it shall be re-submitted as soon after the Authority’s direction as is appropriate, (and in the case of an EBR Amendment within 2 months), taking into account the Prioritisation Criteria, and whether the CUSC Modification Proposal is an Urgent CUSC Modification Proposal, or where it isn’t an Urgent CUSC Modification Proposal or a CUSC Modification Fast Track Proposal, its Prioritisation Category and, where any Workgroup Alternative CUSC Modification(s) aren’t Urgent Workgroup Alternative CUSC Modification(s) or Workgroup CUSC Modification Fast Track Proposal(s), the Prioritisation Category of any Workgroup Alternative CUSC Modification(s). The CUSC Modifications Panel shall decide on the level of analysis and consultation required in order to comply with the Authority’s direction and shall agree an appropriate timetable for meeting its obligations. Once the CUSC Modification Report is revised, the CUSC Modifications Panel shall carry out its CUSC Modifications Panel Recommendation Vote again in respect of the revised CUSC Modification Report and re-submit it to the Authority in compliance with Paragraphs 8.23.4 to 8.23.6.
where Paragraph 8.23.9 and/or Paragraph 8.23.10 is applied to a CUSC Modification Proposal which constitutes an EBR Amendment the process and timetable adopted shall meet the minimum consultation requirements of the Electricity Balancing Regulation.
If a Relevant Party recommends to the Panel Secretary that a proposal should be treated as an Urgent CUSC Modification Proposal in accordance with this Paragraph 8.24, the Panel Secretary shall notify the Panel Chairperson who shall then, in accordance with Paragraphs 8.24.2(a) to (e) inclusive, and notwithstanding anything in the contrary in this Section 8, endeavour to obtain the views of the CUSC Modifications Panel as to the matters set out in Paragraph 8.24.3. If for any reason the Panel Chairperson is unable to do that, the Panel Secretary shall attempt to do so (and the measures to be undertaken by the Panel Chairperson in the following paragraphs shall in such case be undertaken by the Panel Secretary).
The Panel Chairperson shall determine the time by which, in their opinion, a decision of the CUSC Modifications Panel is required in relation to such matters, having regard to the degree of urgency in all circumstances, and references in this Paragraph 8.24.1 to the “time available” shall mean the time available, based on any such determination by the Panel Chairperson;
The Panel Secretary shall, at the request of the Panel Chairperson, convene a meeting or meetings (including meetings by telephone conference call, where appropriate) of the CUSC Modifications Panel in such manner and upon such notice as the Panel Chairperson considers appropriate, and such that, were practicable within the time available, as many Panel Members as possible may attend;
Each Panel Member shall be deemed to have consented, for the purposes of Paragraph 8.8.9. to the convening of such meeting or meetings in the manner and on the notice determined by the Panel Chairperson. Paragraph 8.8.10 shall not apply to any such business.
Where:
it becomes apparent, in seeking to convene a meeting of the CUSC Modifications Panel within the time available, that quorum will not be present; or
it transpires that the meeting of the CUSC Modifications Panel is not quorate and it is not possible to rearrange such meeting within the time available The Panel Chairperson shall endeavour to contact each Panel Member individually in order to ascertain such Panel Member’s vote, and (subject to paragraph 8.24.2(e)) any matter to be decided shall be decided by a majority of those Panel Members who so cast a vote. Where, for whatever reason no decision is reached, the Panel Chairperson shall proceed to consult with the Authority in accordance with Paragraph 8.24.5;
Where the Panel Chairperson is unable to contact a least four Panel Members within the time available and where:
It is only The Company who has recommended that the proposal should be treated as an Urgent CUSC Modification Proposal, then those Panel Members contacted shall decide such matters, such decision may be a majority decision. Where in such cases no decision is made for whatever reason, the Panel Chairperson shall proceed to consult with the Authority in accordance with Paragraph 8.24.5; or
any CUSC Party (other than, and/or in addition to, The Company), the Citizens Advice, the Citizens Advice Scotland or any BSC Party has recommended that the proposal should be treated as an Urgent CUSC Modification Proposal, then the Panel Chairperson may decide the matter (in consultation with those Panel Members (if any) which they managed to contact) provided that the Panel Chairperson shall include details in the relevant CUSC Modification Report of the steps which they took to contact other Panel Members first.
The matters referred to in Paragraph 8.24.1 are:
whether such proposal should be treated as an Urgent CUSC Modification Proposal in accordance with this Paragraph 8.24 and
the procedure and timetable to be followed in respect of such Urgent CUSC Modification Proposal which in the case of a CUSC Modification Proposal and, if applicable, any Workgroup Alternative CUSC Modification(s) which constitutes an EBR Amendment shall meet the minimum consultation requirements of the Electricity Balancing Regulation.
The Panel Chairperson or, in their absence, the Panel Secretary shall forthwith provide the Authority with the recommendation (if any) ascertained in accordance with Paragraphs 8.24.2(a) to (e) inclusive, of the CUSC Modifications Panel as to the matters referred to in Paragraph 8.24.2, and shall consult the Authority as to whether such CUSC Modification Proposal is an Urgent CUSC Modification Proposal and, if so, as to the procedure and timetable which should apply in respect thereof.
If the CUSC Modifications Panel has been unable to make a recommendation in accordance with Paragraph 8.24.2.(d) or Paragraph 8.24.2(e) as to the matters referred to in Paragraph 8.24.3 then the Panel Chairperson or, in their absence, the Panel Secretary may recommend whether they consider that such proposal should be treated as an Urgent CUSC Modification Proposal shall forthwith consult the Authority as to whether such CUSC Modification Proposal is an Urgent CUSC Modification Proposal and, if so, as to the procedure and timetable that should apply in respect thereof.
The CUSC Modifications Panel shall:
not treat any CUSC Modification Proposal as an Urgent CUSC Modification Proposal except with the prior consent of the Authority;
comply with the procedure and timetable in respect of any Urgent CUSC Modification Proposal approved by the Authority; and
comply with any direction of the Authority issued in respect of any of the matters on which the Authority is consulted pursuant to Paragraph 8.24.4 or Paragraph 8.24.5.
For the purposes of this Paragraph 8.24.7, the procedure and timetable in respect of an Urgent CUSC Modification Proposal may (with the approval of the Authority pursuant to Paragraph 8.24.4 or Paragraph 8.24.5) deviate from all or part of the CUSC Modification Procedures or follow any other procedure or timetable approved by the Authority, excepting in the case of a CUSC Modification Proposal or any Workgroup Alternative CUSC Modification(s) which constitute an EBR Amendment , which shall meet the minimum consultation requirements of the Electricity Balancing Regulation. The CUSC Modifications Panel must notify the CM Administrative Parties and the CfD Administrative Parties of any Urgent CUSC Modification Proposal and when approving any alternative procedure or timetable, the Authority must consider whether or not such procedure and timetable should allow for the CM Administrative Parties and the CfD Administrative Parties to be consulted on the Urgent CUSC Modification Proposal and if so how much time should be allowed. Where the procedure and timetable approved by the Authority in respect of an Urgent CUSC Modification Proposal do not provide for the establishment (or designation) of a Workgroup the Proposer’s right to vary the CUSC Modification Proposal pursuant to paragraphs 8.16.10 and 8.20.26 shall lapse from the time and date of such approval.
The CUSC Modification Report in respect of an Urgent CUSC Modification Proposal shall include:
a statement as to why the Proposer believes that such CUSC Modification Proposal should be treated as an Urgent CUSC Modification Proposal;
any statement provided by the Authority as to why the Authority believes that such CUSC Modification Proposal should be treated as an Urgent CUSC Modification Proposal;
any recommendation of the CUSC Modifications Panel (or any recommendation of the Panel Chairperson) provided in accordance with Paragraph 8.24 in respect of whether any CUSC Modification Proposal should be treated as an Urgent CUSC Modification Proposal; and
the extent to which the procedure followed deviated from the CUSC Modification Procedures (other than the procedures in this Paragraph 8.24).
The Company’s justification for including or nor including the views resulting from the relevant consultation in the CUSC Modification Proposal and if applicable, any Workgroup Alternative CUSC Modification (s)
Each CUSC Party and each Panel Member shall take all reasonable steps to ensure that an Urgent CUSC Modification Proposal is considered, evaluated and (subject to the approval of the Authority) implemented as soon as reasonably practicable, having regard to the urgency of the matter and, for the avoidance of doubt, an Urgent CUSC Modification Proposal may (subject to the approval of the Authority) result in the CUSC being amended on the day on which such proposal is submitted.
Where an Urgent CUSC Modification Proposal results in an amendment being made in accordance with Paragraph 8.28, the CUSC Modifications Panel may or (where it appears to the CUSC Modifications Panel that there is a reasonable level of support for a review amongst CUSC Parties shall following such amendment, action a Standing Group in accordance with Paragraph 8.21 on terms specified by the CUSC Modifications Panel to consider and report as to whether any alternative amendment could, as compared with such amendment better facilitate achieving the Applicable CUSC Objectives in respect of the subject matter of that Urgent CUSC Modification Proposal.
For the avoidance of doubt, the Panel shall not determine a Prioritisation Category for Urgent CUSC Modification Proposals and accordingly no Urgent CUSC Modification Proposal shall have a Prioritisation Category.
If the CUSC Modifications Panel, having evaluated a CUSC Modification Proposal against the Self-Governance Criteria, pursuant to Paragraph 8.18.4, considers that the CUSC Modification Proposal meets the Self-Governance Criteria, the CUSC Modifications Panel shall submit to the Authority a Self- Governance Statement setting out its reasoning in reasonable detail.
The Authority may, at any time prior to the CUSC Modifications Panel’s determination made pursuant to Paragraph 8.25.9, give written notice that it disagrees with the Self-Governance Statement and may direct that the CUSC Modification Proposal proceeds through the process for Standard CUSC Modification Proposals set out in Paragraphs 8.19, 8.20, 8.22 and 8.23.
Subject to Paragraph 8.25.2, after submitting a Self-Governance Statement, the CUSC Modifications Panel shall follow the procedure set out in Paragraphs 8.19, 8.20 and 8.22.
The Authority may issue a direction to the CUSC Modifications Panel in relation to a CUSC Modification Proposal to follow the procedure set out for CUSC Modification Proposals that meet the Self-Governance Criteria, notwithstanding that no Self- Governance Statement has been submitted or a Self-Governance Statement has been retracted and the CUSC Modifications Panel shall follow the procedure set out in Paragraphs 8.19, 8.20 and 8.22.
Subject to the Code Administrator’s consultation having been completed pursuant to Paragraph 8.22, the CUSC Modification Panel shall prepare a report (the “CUSC Modification Self- Governance Report”).
The matters to be included in a CUSC Modification Self- Governance Report shall be the following (in respect of the CUSC Modification Proposal):
details of its analysis of the CUSC Modification Proposal against the Self-Governance Criteria;
copies of all consultation responses received;
the date on which the CUSC Modifications Panel Self- Governance Vote shall take place, which shall not be earlier than seven (7) days from the date on which the CUSC Modification Self-Governance Report is furnished to the Authority in accordance with Paragraph 8.25.7; and
such other information that is considered relevant by the CUSC Modifications Panel.
A draft of the CUSC Modification Self-Governance Report will be circulated by the Code Administrator to CUSC Parties and Panel Members and the CM Administrative Parties and the CfD Administrative Parties (and its provision in electronic form on the Website and in electronic mails to CUSC Parties and Panel Members, who must supply relevant details, shall meet this requirement) and a period of no less than five (5) Business Days given for comments to be made thereon. Any unresolved comments made shall be reflected in the final CUSC Modification Self- Governance Report.
Each CUSC Modification Self-Governance Report shall be addressed and furnished to the Authority and none of the facts, opinions or statements contained in such CUSC Modification Self- Governance Report may be relied upon by any other person.
Subject to Paragraph 8.25.11, if the Authority does not give written notice that its decision is required pursuant to Paragraph 8.25.2, or if the Authority determines that the Self-Governance Criteria are satisfied in accordance with Paragraph 8.25.4, then the CUSC Modification Self-Governance Report shall be tabled at the Panel Meeting following submission of that CUSC Modification Self- Governance Report to the Authority at which the Panel Chairperson will undertake the CUSC Modifications Panel Self- Governance Vote and the Code Administrator shall give notice of the outcome of such vote to the Authority as soon as possible thereafter.
If the CUSC Modifications Panel vote to approve the CUSC Modification Proposal pursuant to Paragraph 8.25.9 (which shall then be an “Approved CUSC Modification Self-Governance Proposal”) until implemented), then subject to the appeal procedures set out in Paragraphs 8.25.14 to Paragraph 8.25.19 the CUSC Modification Proposal may be implemented by The Company without the Authority’s approval and brought to the attention of CUSC Parties and such other persons as may properly be considered to have an appropriate interest in it.
The CUSC Modifications Panel may at any time prior to the CUSC Modification Panel’s determination retract a Self-Governance Statement subject to Paragraph 8.25.4, or if the Authority notifies the CUSC Modifications Panel that it has determined that a CUSC Modification Proposal does not meet the Self-Governance Criteria the CUSC Modifications Panel shall treat the CUSC Modification Proposal as a Standard CUSC Modification Proposal and shall comply with Paragraph 8.23, using the CUSC Modification Self-Governance Report as a basis for its CUSC Modification Report.
Except where the Authority has issued a direction pursuant to Paragraph 8.25.4, the CUSC Modifications Panel may remove a CUSC Modification Proposal from the process detailed in this Paragraph 8.25 before making its determination pursuant to Paragraph 8.25.9. In that circumstance, the CUSC Modification Proposal shall be treated as a Standard CUSC Modification Proposal and shall proceed through the process for Standard CUSC Modification Proposals set out in Paragraphs 8.19, 8.20, 8.22 and 8.23.
The Code Administrator shall make available on the Website and copy (by electronic mail to those persons who have supplied relevant details to the Code Administrator) the CUSC Modification Self- Governance Report prepared in accordance with Paragraph 8.25 to:
each CUSC Party;
each Panel Member; and
any person who may request a copy, and shall place a copy on the Website.
A CUSC Party, the Citizens Advice or the Citizens Advice Scotland or any BSC Party or (where the CUSC Modification Proposal and any related Workgroup Alternative CUSC Modification(s) is a proposal to modify the Charging Methodologies) a Materially Affected Party may appeal to the Authority the approval or rejection by the CUSC Modifications Panel of a CUSC Modification Proposal and any Workgroup Alternative CUSC Modification(s) in accordance with Paragraph 8.25.9, provided that the Panel Secretary is also notified, and the appeal has been made up to and including fifteen (15) Business Days after the CUSC Modifications Panel Self-Governance Vote has been undertaken pursuant to Paragraph 8.25.9. If such an appeal is made, implementation of the CUSC Modification Proposal shall be suspended pending the outcome. The appealing CUSC Party, the Citizens Advice, the Citizens Advice Scotland, BSC Party or Materially Affected Party must notify the Panel Secretary of the appeal when the appeal is made.
The Authority shall consider whether the appeal satisfies the following criteria:
The appealing party is, or is likely to be, unfairly prejudiced by the implementation or non-implementation of that CUSC Modification Proposal or Workgroup Alternative CUSC Modification(s); or
The appeal is on the grounds that, in the case of implementation, the CUSC Modification Proposal or Workgroup Alternative CUSC Modification(s) may not better facilitate the achievement of at least one of the Applicable CUSC Objectives; or
The appeal is on the grounds that, in the case of non- implementation, the CUSC Modification Proposal or Workgroup Alternative CUSC Modification(s) may better facilitate the achievement of at least one of the Applicable CUSC Objectives; and
It is not brought for reasons that are trivial, vexatious or have no reasonable prospect of success. and if the Authority considers that the criteria are not satisfied, it shall dismiss the appeal.
Following any appeal to the Authority, a CUSC Modification Proposal or Workgroup Alternative CUSC Modification(s) shall be treated in accordance with any decision and/or direction of the Authority following that appeal.
If the Authority quashes the CUSC Modifications Panel’s determination in respect of a CUSC Modification Proposal or Workgroup Alternative CUSC Modification(s) made in accordance with Paragraph 8.25.9 and takes the decision on the relevant CUSC Modification Proposal and any Workgroup Alternative CUSC Modification(s) itself, following an appeal to the Authority, the CUSC Modifications Panel’s determination of that CUSC Modification Proposal and any Workgroup Alternative CUSC Modification(s) contained in the relevant CUSC Modification Self-governance Report shall be treated as a CUSC Modification Report submitted to the Authority pursuant to Paragraph 8.23.6 (for the avoidance of doubt, subject to Paragraphs 8.23.9 to 8.23.13) and the CUSC Modifications Panel’s determination shall be treated as its recommendation pursuant to Paragraph 8.23.4.
If the Authority quashes the CUSC Modifications Panel’s determination in respect of a CUSC Modification Proposal or Workgroup Alternative CUSC Modification(s) made in accordance with paragraph 8.25.9, the Authority may, following an appeal to the Authority, refer the CUSC Modification Proposal back to the CUSC Modifications Panel for further re-consideration and a further CUSC Modifications Panel Self-Governance Vote.
Following an appeal to the Authority, the Authority may confirm the CUSC Modifications Panel’s determination in respect of a CUSC Modification Proposal or Workgroup Alternative CUSC Modification(s) made in accordance with Paragraph 8.25.9.
A Transmission Charging Methodology Forum shall be established by The Company and shall be chaired by The Company.
The CUSC Modifications Panel shall adopt the terms of reference of the Transmission Charging Methodology Forum and may change those terms of reference from time to time as it sees fit.
The Transmission Charging Methodology Forum shall provide a forum for regular communication and discussion of issues relating to the Transmission Charging Methodologies and their development between The Company and CUSC Parties, BSC Parties and any Materially Affected Parties.
Any representations submitted by a person pursuant to the CUSC Modification Procedures may be made publicly available save as otherwise expressly requested by such person by notice in writing to the Code Administrator. A Workgroup Consultation Alternative Request may in all cases be made publicly available.
The CUSC Modifications Panel, The Company and the Code Administrator shall not be liable for any accidental publication of a representation which is the subject of a request made under Paragraph 8.27.1.
For the avoidance of doubt, all representations (whether or not marked confidential) shall be sent to the Authority.
The CUSC shall be modified either in accordance with the terms of the direction by the Authority relating to, or other approval by the Authority of, the CUSC Modification Proposal or any Workgroup Alternative CUSC Modification(s) contained in the relevant CUSC Modification Report, or in respect of CUSC Modification Proposals or any Workgroup Alternative CUSC Modification(s)s that are subject to the determination of the CUSC Modifications Panel pursuant to Paragraph 8.25.9, in accordance with the relevant CUSC Modification Self-Governance Report subject to the appeal procedures set out in Paragraphs 8.25.14 to 8.25.19.
The Code Administrator shall forthwith notify (by publication on the Website and, where relevant details are supplied by electronic mail):
each CUSC Party;
each Panel Member;
the Authority;
each Core Industry Document Owner,
the secretary of the STC committee;
the CM Administrative Parties;
CfD Administrative Parties;
each BSC Party via ELEXON;
each Materially Affected Party; and
the Citizens Advice and the Citizens Advice Scotland of the change so made and the effective date of the change.
Except where a CUSC Modification Proposal would amend any of the Charging Methodologies, a modification of the CUSC shall take effect from the time and date specified in the direction, or other approval, from the Authority referred to in Paragraph 8.28.1 or, in the absence of any such time and date in the direction or approval, from 00:00 hours on the day falling ten (10) Business Days after the date of such direction, or other approval, from the Authority. A modification of the Charging Methodologies shall take effect as follows:
from 1 April of any given year unless otherwise directed by the Authority in accordance with Paragraphs 8.23.9, 8.23.12, 8.23.13 or 8.28.3A and following consultation with the Panel;
subject to (iii) below, the 1 April shall be determined by reference to date of the Authority decision to approve the modification as follows: a) where the Authority decision is more than 6 (six) months prior to the end of a Charging Year (Charging Year t), implementation of that CUSC Modification Proposal shall take effect such that it is implemented in Charging Year t+1. b) where the Authority decision is less than 6 (six) months prior to the end of Charging Year t, implementation of that CUSC Modification Proposal shall be deferred such that it is implemented in Charging Year t+2.
Paragraph (ii) above shall not apply in respect of a CUSC Modification Proposal to the Charging Methodologies:
where the Authority has directed otherwise;
where there is at least a Charging Year between the date of the Authority decision and the Implementation Date;
where the CUSC Modification is an Urgent CUSC Modification; or
which The Company has raised at the direction of the Authority or which the Authority has raised. A modification of the CUSC pursuant to Paragraph 8.25.10 shall take effect , subject to the appeal procedures set out in Paragraphs 8.25.14 to 8.25.19, from the time and date specified by the Code Administrator in its notice given pursuant to Paragraph 8.28.2, which shall be given after the expiry of the fifteen (15) Business Day period set out in Paragraph 8.25.14 to allow for appeals, or where an appeal is raised in accordance with Paragraph 8.25.14, on conclusion of the appeal in accordance with Paragraphs 8.25.15 or 8.25.19 but where conclusion of the appeal is earlier than the fifteen (15) Business Day period set out in Paragraph 8.25.14, notice shall be given after the expiry of this period. A modification of the CUSC pursuant to Paragraph 8.29 shall take effect, from the date specified in the CUSC Modification Fast Track Report. 8.28.3A Where the Authority considers that taking into account Prioritisation Criteria, and whether the modification is an Urgent CUSC Modification Proposal , or, where it isn’t an Urgent CUSC Modification Proposal or a CUSC Modification Fast Track Proposal, the Prioritisation Category of the modification exceptional circumstances apply the Authority may, having set out in writing its reasons for this, direct a modification of the CUSC in respect of the Charging Methodologies to take effect from a date other than 1 April.
A modification made pursuant to and in accordance with Paragraph 8.28.1 shall not be impaired or invalidated in any way by any inadvertent failure to comply with or give effect to this Section.
If a modification is made to the CUSC in accordance with the ESO Licence but other than pursuant to the other CUSC Modification Procedures in this Section 8, the CUSC Modifications Panel shall determine whether or not to submit the modification for review by a Standing Group in accordance with Paragraph 8.21 on terms specified by the CUSC Modifications Panel to consider and report as to whether any alternative modification could, as compared with such modification better facilitate achieving the Applicable CUSC Objectives in respect of the subject matter of the original modification. Transitional Issues
Notwithstanding the provisions of Paragraph 8.28.3, CUSC Modification Proposal CAP 160 changes the CUSC Modification Process and therefore may affect other CUSC Modification Proposals which have not yet become Approved CUSC Modifications. Consequently, this Paragraph deals with issues arising out of the implementation of CUSC Modification Proposal CAP 160. In particular this Paragraph deals with which version of the CUSC Modification Process will apply to CUSC Modification Proposal(s) which were already instigated prior to the implementation of CUSC Modification Proposal CAP 160. In respect of any CUSC Modification Proposal which the CUSC Modification Panel has determined, as at the date and time of implementation of CUSC Modification Proposal CAP 160 (as directed by the Authority), should proceed to wider consultation by The Company is known as an “Old CUSC Modification Proposal”. In respect of any CUSC Modification Proposal where the CUSC Modification Panel has not determined, as at the date and time of implementation of CUSC Modification Proposal CAP 160 (as directed by the Authority), that it should proceed to wider consultation by The Company is known as a “New CUSC Modification Proposal”. The provisions of Section 8 and the associated definitions in Section 11 which will apply to any Old CUSC Modification Proposal(s) are the provisions of Section 8 and the associated definitions in Section 11 of the CUSC which are in force immediately prior to the implementation of CAP 160. The provisions of Section 8 and the associated definitions in Section 11 which will apply to any New CUSC Modification Proposals are the provisions of the CUSC in force from time to time.
Notwithstanding the provisions of Paragraph 8.28.3, CUSC Modification Proposals CAP 183, 184, 185 and 188 change the CUSC Modification Process and therefore may affect other CUSC Modification Proposals which have not as at the last date of the implementation of these changes become Approved CUSC Modifications. Consequently, this Paragraph deals with issues arising out of the implementation of CUSC Modification Proposals CAP 183, 184, 185 and 188. In particular this Paragraph deals with which version of the CUSC Modification Process will apply to CUSC Modification Proposal(s) which were already instigated prior to the implementation of the last of CUSC Modification Proposals CAP 183, 184, 185 and 188. Any CUSC Modification Proposal that was submitted pursuant to Paragraph 8.16.4 prior to the implementation of the last of CUSC Modification Proposals CAP 183, 184, 185 and 188 is known as an “Old CUSC Modification Proposal”. Any CUSC Modification Proposal that was submitted pursuant to Paragraph 8.16.4 on the date of or any date following implementation of the last of CUSC Modification Proposals CAP 183, 184, 185 and 188 is known as a “New CUSC Modification Proposal”. The provisions of Section 8 and the associated definitions in Section 11 that will apply to any Old CUSC Modification Proposal(s) are the provisions of Section 8 and the associated definitions in Section 11 of the CUSC that are in force immediately prior to the implementation of the last of CAP 183, 184, 185 and 188. The provisions of Section 8 and the associated definitions in Section 11 that will apply to any New CUSC Modification Proposals are the provisions of the CUSC in force from time to time.
Modification CMP365 changes the CUSC process for CUSC Modification Proposals and therefore may affect other CUSC Modification Proposals which have not yet become Approved CUSC Modifications. Consequently, this 8.28.8 deals with issues arising out of the implementation of Modification CMP365. In particular this deals with which version of the CUSC process for CUSC Modification Proposals will apply to CUSC Modification Proposal(s) which were already instigated prior to the implementation of Modification CMP365. Any CUSC Modification Proposal in respect of which a CUSC Modification Report has been sent to the Authority prior to the date and time of implementation of Modification CMP365 is known as an “Old CMP365 CUSC Modification”. Any CUSC Modification Proposal in respect of which a CUSC Modification Report has not been sent to the Authority as at the date and time of implementation of Modification CMP365 is known as a “New CMP365 CUSC Modification”. The CUSC provisions which will apply to any Old CMP365 CUSC Modification(s) are the provisions of the CUSC in force immediately prior to the implementation of CMP365. The provisions of the CUSC which will apply to any New CMP365 CUSC Modifications are the provisions of the CUSC in force from time to time.
Where a Proposer believes that a modification to the CUSC which meets the Fast Track Criteria is required, a CUSC Modification Fast Track Proposal may be raised. In such case the Proposer is only required to provide the details listed in Paragraph 8.16.4 (a), (b), (c), (d), (e) and (k).
Provided that the Panel Secretary receives any modification to the CUSC which the Proposer considers to be a CUSC Modification Fast Track Proposal, not less than ten (10) Business Days (or such shorter period as the Panel Secretary may agree, provided that the Panel Secretary shall not agree any period shorter than five (5) Business Days) prior to the next CUSC Modifications Panel meeting, the Panel Secretary shall place the CUSC Modification Fast Track Proposal on the agenda of the next CUSC Modifications Panel meeting, and otherwise, shall place it on the agenda of the next succeeding CUSC Modifications Panel meeting.
To facilitate the discussion at the CUSC Modifications Panel meeting, the Code Administrator will circulate a draft of the CUSC Modification Fast Track Report to CUSC Parties, the Authority and Panel Members (and its provision in electronic form on the Website and in electronic mails to CUSC Parties, the Authority and Panel Members, who must supply relevant details, shall meet this requirement) for comment not less than five (5) Business Days ahead of the CUSC Modifications Panel meeting which will consider whether or not the Fast Track Criteria are met and whether or not to approve the CUSC Modification Fast Track Proposal.
It is for the CUSC Modifications Panel to decide whether or not a CUSC Modification Fast Track Proposal meets the Fast Track Criteria and if it does, to determine whether or not to approve the CUSC Modification Fast Track Proposal.
The CUSC Modifications Panel’s decision that a CUSC Modification Fast Track Proposal meets the Fast Track Criteria pursuant to Paragraph 8.29.4 must be unanimous.
The CUSC Modifications Panel’s decision to approve the CUSC Modification Fast Track Proposal pursuant to Paragraph 8.29.4 must be unanimous.
If the CUSC Modifications Panel vote unanimously that the CUSC Modification Fast Track Proposal meets the Fast Track Criteria and to approve the CUSC Modification Fast Track Proposal (which shall then be an “Approved CUSC Modification Fast Track Proposal”) until implemented, or until an objection is received pursuant to Paragraph 8.29.12), then subject to the objection procedures set out in paragraph 8.29.12 the CUSC Modification Fast Track Proposal will be implemented by The Company without the Authority’s approval. If the CUSC Modifications Panel do not unanimously agree that the CUSC Modification Proposal meets the Fast Track Criteria and/or do not unanimously agree that the CUSC Modification Fast Track Proposal should be made, then the Panel Secretary shall, in accordance with Paragraph 8.16.4A notify the Proposer that additional information is required if the Proposer wishes the CUSC Modification Proposal to continue.
Provided that the CUSC Modifications Panel have unanimously agreed to treat a CUSC Modification Proposal as a CUSC Modification Fast Track Proposal and unanimously approved that CUSC Modification Fast Track Proposal, the CUSC Modifications Panel shall prepare and approve the CUSC Modification Fast Track Report for issue in accordance with Paragraph 8.29.11.
The matters to be included in a CUSC Modification Fast Track Report shall be the following (in respect of the CUSC Modification Fast Track Proposal):
a description of the proposed modification and of its nature and purpose;
details of the changes required to the CUSC, including the proposed legal text to modify the CUSC to implement the CUSC Modification Fast Track Proposal;
details of the votes required pursuant to Paragraphs 8.29.5 and 8.29.6
the intended implementation date, from which the Approved CUSC Modification Fast Track Proposal will take effect, which shall be no sooner than fifteen (15) Business Days after the date of notification of the CUSC Modifications Panel’s decision to approve; and
details of how to object to the Approved CUSC Modification Fast Track Proposal being made.
Upon approval by the CUSC Modifications Panel of the CUSC Modification Fast Track Report, the Code Administrator will issue the report in accordance with Paragraph 8.29.11.
The Code Administrator shall copy (by electronic mail to those persons who have supplied relevant details to the Code Administrator) the CUSC Modification Fast Track Report prepared in accordance with Paragraph 8.29 to:
each CUSC Party;
each Panel Member;
the Authority; and
any person who may request a copy, and shall place a copy on the Website.
A CUSC Party, a BSC Party, the Citizens Advice, the Citizens Advice Scotland or the Authority may object to the Approved CUSC Modification Fast Track Proposal being implemented, and shall include with such objection an explanation as to why the objecting person believes that it does not meet the Fast Track Criteria. Any such objection must be made in writing (including by email) and be clearly stated to be an objection to the Approved CUSC Modification Fast Track Proposal in accordance with this Paragraph 8.29 of the CUSC and be notified to the Panel Secretary by the date up to and including fifteen (15) Business Days after notification of the CUSC Modifications Panel’s decision to approve the CUSC Modification Fast Track Proposal. If such an objection is made the Approved CUSC Modification Fast Track Proposal shall not be implemented. The Panel Secretary will notify each Panel Member, each CUSC Party and the Authority of the objection. The Panel Secretary shall notify the Proposer, in accordance with Paragraph 8.16.4A that additional information is required if the Proposer wishes the CUSC Modification Proposal to continue.
For the avoidance of doubt, the Panel shall not determine a Prioritisation Category for CUSC Modification Fast Track Proposals and accordingly no CUSC Modification Fast Track Proposals shall have a Prioritisation Category.
The CUSC Modifications Panel shall review the Prioritisation Category of CUSC Modification Proposals on a bi-annual basis and adjust the relevant modification timetable for each CUSC Modification Proposal accordingly.
in relation to each year (the "Election Year") in which the term of office of Users’ Panel Members and Alternate Members expires, for the purposes of electing Users’ Panel Members and Alternate Members to hold office with effect from 1st October in that year;
subject to and in accordance with Paragraph 8A.4, upon a Users’ Panel Member and/or Alternate Members ceasing to hold office before the expiry of their term of office. 8A.1.1.3 For the purposes of an election under Paragraph 8A.1.1.2(a) references to Users are to persons who are Users as at 20th June in the election year. 8A.1.1.4 On or around 20th June in each election year the Code Administrator shall publish a list of Users (in accordance with Paragraph 8A.1.1.3) and their associated Voting Groups (as defined in Paragraph 8A.3.1.2). 8A.1.1.5 All Users shall provide reasonable assistance to the Code Administrator to ensure that the list referred to in Paragraph 8A.1.1.4 is complete, accurate and up to date. 8A.1.1.6 Where and to the extent that any User identifies an error or omission in such list (including in respect of the allocated Voting Groups), the User shall use best endeavours to notify the Code Administrator as soon as reasonably practicable and in any case in advance of the date identified under Paragraph 8A1.2.1(b). The Code Administrator shall use reasonable endeavours to investigate any errors or omissions of which it has received notice and to make the relevant rectifications in advance of the date identified under Paragraph 8A1.2.1(b). 8A.1.1.7 The Code Administrator shall administer each election of Users’ Panel Members and Alternate Members pursuant to this Annex 8A. 8A.1.2 Election timetable 8A.1.2.1 The Code Administrator shall not later than 1st July in the election year prepare and circulate to all Users (by publication on the Website and, where relevant details are supplied, by electronic mail), with a copy to the Authority, an invitation to nominate candidates who must be willing to be either a User Panel Member or an Alternate Member and a timetable for the election (the “Election Timetable”), setting out:
the date by which nominations of candidates are to be received, which shall not be less than three (3) weeks after the timetable is circulated;
the date by which the Code Administrator shall circulate a list of candidates and voting papers;
the date by which voting papers are to be submitted, which shall not be less than three (3) weeks after the date for circulating voting papers;
the date by which the results of the election will be made known, which shall not be later than 15th September in the Election Year. 8A.1.2.2 If for any reason it is not practicable to establish an election timetable in accordance with Paragraph 8A.2.1.1 or to proceed on the basis of an election timetable which has been established, the Code Administrator may establish a different timetable, or revise the election timetable, by notice to all Users, the CUSC Modifications Panel and the Authority, provided that such timetable or revised timetable shall provide for the election to be completed before 1st October in the Election Year. 8A.1.2.3 A nomination or voting paper received by the Code Administrator later than the respective required date under the election timetable (subject to any revision under Paragraph 8A.1.2.2) shall be disregarded in the election. 8A.2. CANDIDATES 8A.2.1 Nominations 8A.2.1.1 Nominations for candidates shall be made in accordance with the Election Timetable. 8A.2.1.2 Subject to Paragraph 8A.1.1.3, each User may nominate one candidate for election by giving notice to the Code Administrator. 8A.2.2 List of candidates 8A.2.2.1 The Code Administrator shall draw up a list of the nominated candidates and circulate the list to all Users by the date specified in the Election Timetable. 8A.2.2.2 The list shall specify the User by whom each candidate was nominated and any affiliations which the candidate may wish to have drawn to the attention of Users. 8A.2.2.3 Except where Paragraphs 8A.4.3 or 8A.4.4 apply, if seven (7) or fewer candidates are nominated no further steps in the election shall take place and such candidate(s) shall be treated as elected as Users’ Panel Members and Paragraph 8A.3.2.4 shall apply in relation to such candidate(s). 8A2.2.4 Where Paragraph 8A.4.3 applies, if only one (1) candidate is nominated, no further steps in the election shall take place and such candidate shall be treated as elected as a Panel Member and Paragraph 8A.3.2.4 shall apply in relation to such candidate. 8A.2.2.5 Where the election has resulted in zero (0) Alternate Members, Alternate Members shall be elected in accordance with the Alternate Election Process as set out in Paragraph 8A.4.4. 8A.2.2.6 Where Paragraph 8A.4.4 applies, if five (5) or fewer candidates are nominated, no further steps in the election shall take place and such candidate(s) shall be treated as elected as Alternate Members and Paragraph 8A.3.2.4 shall apply in relation to such candidate(s). 8A.2.2.7 Each nominated candidate shall make the declaration referred to in Paragraph 8.3.4(b)(iii) in order for such candidate’s relevant interests to be published alongside the list of nominated candidates pursuant to Paragraphs 8A2.2.1 and 8A.2.2.2. Failure to make such a declaration shall result in the relevant candidate becoming an ineligible candidate who shall not be included on the list of nominated candidates. 8A.3. VOTING 8A.3.1 Voting papers 8A.3.1.1 Voting papers shall be submitted in accordance with the election timetable. 8A.3.1.2 In accordance with the process set out in Paragraph 8A.1.1 the Code Administrator will allocate each User to a Voting Group. For the purposes of this Annex 8A, a “Voting Group” means a User who is eligible to vote and all Affiliates of that User who are eligible to vote 8A.3.1.3 Each Voting Group shall be entitled to submit one voting paper in respect of each of the following Voting Sub-Groups, provided that one or more Users in such Voting Group fall within the relevant Voting Sub-Group:
the Generation Voting Sub-Group;
the Supply Voting Sub-Group;
the Demand Voting Sub-Group; and
the Interconnector Voting Sub-Group. For the avoidance of doubt, each Voting Group will therefore be entitled to submit up to four (4) voting papers, being one paper per Voting Sub-Group. 8A.3.1.4 All Users eligible to vote within a Voting Group shall receive voting papers. Each Voting Group shall be responsible for designating which specific User(s) within their Voting Group shall submit voting paper(s) on behalf of the relevant Voting Sub-Group(s) in accordance with Paragraph 8A.3.1.3. 8A.3.1.5 In the event that the number of voting papers submitted by Users within a Voting Group exceeds the entitlement set out in Paragraph 8A.3.1.3:
the Code Administrator shall use reasonable endeavours to contact each of the relevant Users to establish which voting paper(s) shall be deemed valid and which voting paper(s) shall be deemed invalid and disregarded; and
where the Code Administrator has not been able to contact the relevant Users using reasonable endeavours, the Code Administrator shall select from the voting papers at random. Any voting paper(s) selected by the Code Administrator shall be deemed valid and all other voting paper(s) from the relevant Voting Group shall be deemed invalid and disregarded 8A.3.2 Preference votes and voting rounds 8A.3.2.1 Each Voting Group submitting a voting paper or voting papers shall vote by indicating on each eligible voting paper a first, second and third preference ("Preference Votes") among the candidates. 8A.3.2.2 A voting paper need not indicate a second, or a third, preference, but the same candidate may not receive more than one Preference Vote in a single voting paper. 8A.3.2.3 Candidates shall be elected in three voting rounds (together where necessary with a further round under Paragraph 8A.3.6) in accordance with the further provisions of this Paragraph 8A.3. 8A.3.2.4 The Code Administrator shall determine which candidates are elected and announce (to the Authority and all Users) the results of the election in accordance with the election timetable. 8A.3.2.5 The Code Administrator shall not disclose the Preference Votes cast by Users within any Voting Group or received by candidates; but a User may by notice to the Authority require that the Authority scrutinise the conduct of the election, provided that such User shall bear the costs incurred by the Authority in doing so unless the Authority recommends that the election results should be annulled. 8A.3.2.6 Further references to voting papers in this Paragraph 8A.3 do not include voting papers which are invalid or are to be disregarded (i.e. voting papers not made or submitted in accordance with the CUSC.) 8A.3.3 First voting round 8A.3.3.1 In the first voting round:
the number of first Preference Votes allocated under all voting papers to each candidate shall be determined.
the first round qualifying total shall be: (T / N) + 1 where T is the total number of first Preference Votes in all voting papers; N is the number of Users’ Panel Members and/or Alternate Members to be elected. 8A.3.3.2 If the number of first Preference Votes allocated to any candidate is equal to or greater than the first round qualifying total, that candidate shall be elected. 8A.3.4 Second voting round 8A.3.4.1 In the second voting round:
the remaining candidates are those which were not elected in the first voting round;
the remaining voting papers are voting papers other than those under which the first Preference Votes were for candidates elected in the first voting round;
the number of first and second Preference Votes allocated under all remaining voting papers to each remaining candidate shall be determined;
the second round qualifying total shall be ( T' / N' ) + 1 where T' is the total number of first Preference Votes and second Preference Votes allocated under all remaining voting papers; N' is the number of Panel Members and/or Alternate Members remaining to be elected after the first voting round. 8A.3.4.2 If the number of first and second Preference Votes allocated to any remaining candidate is equal to or greater than the second round qualifying total, that candidate shall be elected. 8A.3.5 Third voting round 8A.3.5.1 In the third voting round:
the remaining candidates are those which were not elected in the first or second voting rounds;
the remaining voting papers are voting papers other than those under which the first or second Preference Votes were for candidates elected in the first or second voting rounds;
the number of first, second and third Preference Votes allocated under all remaining voting papers to each remaining candidate shall be determined;
the third round qualifying total shall be ( T" / N'' ) + 1 where T'' is the total number of first Preference Votes, second Preference Votes and third Preference Votes allocated under all remaining voting papers; N'' is the number of Panel Members remaining to be elected after the first and second voting rounds. 8A.3.5.2 If the number of first, second and third Preference Votes allocated to any remaining candidate is equal to or greater than the third round qualifying total, that candidate shall be elected. 8A.3.6 Further provisions 8A.3.6.1 If after any voting round the number of candidates achieving the required Preference Votes threshold exceeds the number of persons remaining to be elected, the following tie-break provisions shall apply between the tied candidates. In addition, if after the third voting round any Panel Member(s) or Alternate Member(s) remain to be elected the following tie- break provisions shall apply between the remaining candidates:
the tied or remaining candidates (as applicable) shall be ranked in order of the number of first Preference Votes allocated to them, and the candidate(s) with the greatest number of such votes shall be elected;
in the event of a tie between two or more candidates within Paragraph (a), the candidate(s) (among those tied) with the greatest number of second Preference Votes shall be elected;
in the event of a tie between two or more candidates within Paragraph (b), the Code Administrator shall select the candidate(s) (among those tied) to be elected by drawing lots. 8A.3.6.2 As soon as reasonably practicable after any election process has concluded the Code Administrator shall publish an election report including but not limited to the following: i) the total number of voting papers distributed to Users eligible to vote; ii) the total number of voting papers received; iii) the total number of first, second and third preference votes allocated to each candidate in all voting papers; iv) the total number of remaining voting papers in each voting round; v) the total number of remaining Panel Members to be elected in each voting round; vi) the value of the qualifying total in each voting round; and vii) the total number of qualifying Preference Votes allocated to each remaining candidate under all remaining voting papers in each voting round. 8A.3.7 Alternate Members and Panel Members 8A.3.7.1 Except where Paragraphs 8A.4.3 or 8A.4.4 apply, the seven (7) candidates receiving the greatest number of votes shall be elected as Users’ Panel Members and the next five (5) shall be elected as Alternate Members. 8A.3.7.2 Where Paragraph 8A.4.3 applies the number of candidate(s) up to and including the number of Panel Member Interim Vacancies receiving the greatest number of votes pursuant to the Interim Panel and Alternate Election Process shall be elected as Users’ Panel Member(s) and the remaining candidates up to and including the number of Alternate Member Interim Vacancies receiving the greatest number of votes shall be elected as Alternate Member(s). 8A.3.7.3 Where Paragraph 8A.4.4 applies the five (5) candidates receiving the greatest number of votes pursuant to the Alternate Election Process shall be elected as Alternate Members. 8A.4. VACANCIES 8A.4.1 General 8A.4.1.1 If a Panel Member ceases to hold office pursuant to Paragraph 8.6.1 (b)
then Paragraph 8A.4.2 shall apply. 8A.4.1.2 [Not used] 8A.4.1.3 If an Alternate Member ceases to hold office pursuant to Paragraph 8.6 (the “Resigning” Alternate Member) then Paragraph 8A.4.4 shall apply. 8A.4.1.4 The provisions of Paragraph 8A.2.1.2 shall apply, mutatis mutandis, to any replacement Panel Member or any replacement Alternate Member under this Paragraph 8A.4. 8A.4.2 [Not used] 8A.4.3 Replacement of a Panel Member who ceases to hold office pursuant to Paragraph 8.6.1 8A.4.3.1 Subject to Paragraph 8A.4.3.2, such Panel Member shall, where one or more Alternate Member(s) hold office, be replaced by the Alternate Member who previously received the highest number of cumulative Preference Votes but if there were a tie-break in relation to such Preference Votes then the tie-break provisions set out in Paragraph 8A.3.6.1 shall apply, in either circumstance such Alternate Member selected to be a Panel Member shall then become a Resigning Alternate Member and be replaced in accordance with Paragraph 8A.4.4. 8A.4.3.2 If there are no Alternate Members in office upon a Panel Member ceasing to hold office then:
Where there are not less than six (6) months remaining until the next full election further Panel Members shall be elected in accordance with Paragraphs 8A.2, 8A.3 and subject to the following Paragraphs 8A.4.3.3 to 8A.4.3.5 (inclusive) (the “Interim Panel and Alternate Election Process”).
Where there are less than six (6) months remaining until the next full election no further Panel Members or Alternate Members shall be elected pursuant to this Paragraph 8A.4.3 and the positions shall remain vacant until the next full election. 8A.4.3.3 Where this Paragraph 8A.4.3.3 applies the Code Administrator shall indicate in the invitation referred to at Paragraph 8A.1.2.1 the number of vacancies for both Panel Member(s) (“Panel Member Interim Vacancies”) and Alternate Member(s) (“Alternate Member Interim Vacancies”) for which the Interim Panel and Alternate Election Process is being held. 8A.4.3.4 Any Panel Member(s) or Alternate Member(s) elected pursuant to the Interim Panel and Alternate Election Process shall cease to hold office at the next full election. 8A.4.3.5 The timetable for the Interim Panel and Alternate Election Process shall be expedited and the Code Administrator shall prepare a timetable accordingly. 8A.4.4 Alternate Election Process 8A.4.4.1 Where there are no Alternate Members in office following an election, as set out in 8A.2.2.5, Alternate Members shall be elected in accordance with Paragraphs 8A.2, 8A.3 and subject to the following paragraphs 8A.4.4.3 to 8A.4.4.5 (inclusive) (the “Alternate Election Process”). 8A.4.4.2 A Resigning Alternate Member shall not be replaced, except where there are no Alternate Members remaining in office following the resignation of an Alternate Member or their appointment as Panel Member in accordance with 8A.4.3, then
Where there are not less than six (6) months remaining until the next full election further Alternate Members shall be elected in accordance with Paragraphs 8A.2, 8A.3 and subject to the following paragraphs 8A.4.4.3 to 8A.4.4.5 (inclusive) (the “Alternate Election Process”).
Where there are less than six (6) months remaining until the next full election no further Alternate Members shall be elected and the positions shall remain vacant until the next full election 8A.4.4.3 Where this paragraph 8A.4.4.3 applies, a reference in Paragraphs 8A.2 and 8A.3 to a Users’ Panel Member or Panel Member shall not apply except in the case of Paragraph 8A.3.5.1 (d) where the reference to “Panel Members” shall be read and construed as a reference to “Alternate Members”. 8A.4.4.4 Any Alternate Member(s) elected pursuant to the Alternate Election Process shall cease to hold office at the next full election. 8A.4.4.5 The timetable for the Alternate Election Process shall be expedited and the Code Administrator shall prepare a timetable accordingly, setting out:
the date by which nominations of candidates are to be received, which shall not be less than one (1) week after the timetable is circulated;
the date by which the Code Administrator shall circulate a list of candidates and voting papers;
the date by which voting papers are to be submitted, which shall not be less than one (1) week after the date for circulating voting papers;
the date by which the results of the election will be made known.
SECTION 9: INTERCONNECTORS
INTRODUCTION This Section 9 of the CUSC deals with Interconnectors other than Distribution Interconnector Owners (which are dealt with in Section 3). Part I provides for connection to the National Electricity Transmission System by an Interconnector Owner and Part II for use of the National Electricity Transmission System by Interconnector Users and Interconnector Error Administrators.
CONNECTION - INTRODUCTION This Part I deals with connection to the National Electricity Transmission System by an Interconnector Owner. The User for the purposes of this Part I will therefore be the Interconnector Owner.
Right to Remain Connected Subject to the other terms and conditions of the relevant Bilateral Connection Agreement and the Grid Code and any Operating Agreement, each User as between The Company and that User shall have the right for the User’s Equipment to remain connected to the National Electricity Transmission System at the Connection Site of an Interconnector specified in the relevant Bilateral Connection Agreement once Commissioned and then for the duration of the relevant Bilateral Connection Agreement in relation to that Connection Site.
Right to Remain Energised and Operational Subject to the other provisions of the CUSC, the relevant Bilateral Connection Agreement and the Grid Code and any Operating Agreement each User as between The Company and that User shall have the right for the User’s Equipment at the Connection Site of an Interconnector to remain Energised 9-3 and Operational once Commissioned for the duration of the Bilateral Connection Agreement in relation to that Connection Site.
Obligation to Remain Connected
Without prejudice to its rights to make Modifications to the User’s Plant (and/or User’s Equipment as the case may be) pursuant to the CUSC and subject to the provisions of Paragraph 5.2 and the other provisions of the CUSC, the Grid Code and any Operating Agreement, the User shall keep the User’s Equipment at the Connection Site of an Interconnector connected to the National Electricity Transmission System until Decommissioning or Disconnection is permitted pursuant to the CUSC and the relevant Bilateral Connection Agreement.
For as long as the User is connected to the National Electricity Transmission System and the User’s Equipment is Energised and Operational the User shall ensure:
that there is an Interconnector Error Administrator appointed in respect of that Interconnector; and
that any party with whom it enters into an agreement for use of that Interconnector is a party to the CUSC and is in receipt of a Use of System Interconnector Confirmation Notice prior to and during its use of that Interconnector.
EXPORT OF POWER FROM THE INTERCONNECTOR CONNECTION SITE Subject to the other provisions of the CUSC, the relevant Bilateral Connection Agreement and the Grid Code and any Operating Agreement, The Company shall accept into the National Electricity Transmission System at the Connection Site of an Interconnector power up to the Transmission Entry Capacity and (if any) STTEC and\or LDTEC and\or any Temporary Received TEC less any Temporary Donated TEC for the relevant Period as specified in Appendix C to the relevant Bilateral Connection Agreement except to the extent (if any) that The Company is prevented from doing so by transmission constraints which could not be avoided by the exercise of Good Industry Practice.
IMPORT OF POWER TO THE INTERCONNECTOR CONNECTION SITE 9-4 Subject to the other provisions of the CUSC, the relevant Bilateral Connection Agreement, the Grid Code and any Operating Agreement, The Company shall transport a supply of power to a Connection Site of an Interconnector through the National Electricity Transmission System up to the amount specified in the Bilateral Connection Agreement except to the extent (if any) that The Company is prevented from doing so by transmission constraints which could not be avoided by the exercise of Good Industry Practice by The Company.
The User shall not permit the transfer of any amount of electricity onto the National Electricity Transmission System in excess of the Transmission Entry Capacity and (if any) STTEC and\or LDTEC and\or any Temporary Received TEC less any Temporary Donated TEC for the relevant Period specified in Appendix C to the relevant Bilateral Connection Agreement or permit the taking of any amounts of electricity off the National Electricity Transmission System in excess of the value as specified in Appendix C to the relevant Bilateral Connection Agreement save as expressly permitted or instructed pursuant to an Emergency Instruction under the Grid Code or save as expressly permitted pursuant to any Operating Agreement or the Fuel Security Code or as may be necessary or expedient in accordance with Good Industry Practice. 9.6A Connection Entry Capacity With respect to a particular connection to the National Electricity Transmission System, each User, as between The Company and that User, shall not operate its User’s Equipment such that any of it exceeds the Connection Entry Capacity specified for each Generating Unit or the Connection Entry Capacity to the Connection Site such figures being set out in Appendix C to the relevant Bilateral Connection Agreement save as expressly permitted pursuant to an Emergency Instruction under the Grid Code or save as expressly permitted pursuant to any Operating Agreement or the Fuel Security Code or as may be necessary or expedient in accordance with Good Industry Practice.
MAINTENANCE OF TRANSMISSION CONNECTION ASSETS Subject to the other provisions of the CUSC, the relevant Bilateral Connection Agreement, the Grid Code and any Operating Agreement, The Company shall use all reasonable endeavours to maintain the Transmission Connection Assets at each Connection Site of an Interconnector in the condition necessary to render the same fit for the purpose of passing power up to the Connection Entry Capacity specified in Appendix C to the Bilateral Connection Agreement as appropriate between the 9-5 User’s Equipment and the National Electricity Transmission System.
OUTAGES Subject to the provisions of the Grid Code and any Operating Agreement, The Company and the User shall as between themselves be entitled to plan and execute outages of parts of, in the case of The Company, the National Electricity Transmission System or Transmission Plant or Transmission Apparatus and, in the case of the User, its System or Plant or Apparatus at any time and from time to time.
Connection Charges Subject to the provisions of the CUSC, and the relevant Bilateral Connection Agreement, each User shall, as between The Company and that User, with effect from the relevant date set out in the relevant Bilateral Connection Agreement be liable to pay to The Company the Connection Charges calculated and applied in accordance with the Statement of the Connection Charging Methodology and as set out in the relevant Bilateral Connection Agreement. The User shall make those payments in accordance with the provisions of the CUSC. The Company shall apply and calculate the Connection Charges in accordance with the Statement of the Connection Charging Methodology.
Obligation to provide Security The User shall provide The Company with Security Cover in respect of Termination Amounts in respect of Transmission Connection Assets commissioned after the Transfer Date in accordance with the provisions of Part III of Section 2.
Outturn Reconciliation
The following provisions relate to the ability for invoices to be issued for Connection Charges based on an estimate of the cost of Transmission Connection Asset Works, and for a reconciliation once those costs are known.
The Company shall be entitled to invoice the User for Connection Charges payable in accordance with the CUSC in respect of any Plant and Apparatus installed as part of the Transmission Connection Asset Works on the basis set out in the Statement of the Connection Charging Methodology, until the final cost of carrying out the said Transmission Connection Asset Works shall have been determined. 9-6
As soon as practicable after the Completion Date and in any event within one year thereof The Company shall provide to the User a written statement specifying the Connection Charges calculated in accordance with the Charging Statements based on the cost of carrying out the Transmission Connection Asset Works (the “Cost Statement”). The Company shall be entitled to revise Appendix B to the relevant Bilateral Connection Agreement accordingly.
In the event that the Connection Charges specified in the Cost Statement are greater than the amount paid by the User based on The Company’s estimate under Paragraph 2.14.3(b), the User shall pay to The Company the difference between the two amounts plus interest on a daily basis from the date of payment by the User of the amounts calculated on The Company’s estimate to the date of payment by the User of the difference at the Base Rate. In the event that the Connection Charges specified in the Cost Statement are less than the amount paid by the User based on The Company’s estimate, The Company shall pay to the User the difference between the two amounts plus interest on a daily basis from the date of payment by the User of the amounts calculated on The Company’s estimate to the date of repayment by The Company at the Base Rate. Such payment of reconciliation shall be made by one party to the other within 28 (twenty eight) days of the Cost Statement.
Connection Charges – One-off Charges
The following provisions relate to the payment for certain One-off Works, which arise in relation to the construction of a Connection Site.
The User shall forthwith on the relevant date set out in the relevant Bilateral Connection Agreement be liable to pay to The Company the One-off Charge (if any) as set out in the relevant Bilateral Connection Agreement.
The Company shall invoice the User for an amount equal to The Company’s estimate of the One-off Charge before, on or after the relevant date set out in the relevant Bilateral Connection Agreement and the User shall pay to The Company the amount stated in The Company invoice at the later of such relevant date or 28 (twenty eight) days after the date of the said invoice.
As soon as practicable thereafter The Company shall provide the User with a statement of the One-off Charge. 9-7 In the event of the amount specified in the statement being more than the amount paid by the User to The Company in terms of Paragraph 2.14.4(c), the User shall pay to The Company the difference plus interest on a daily basis from the date of the invoice under Paragraph 2.14.4(c) to the date of invoice for the difference at the Base Rate from time to time within 28 days (twenty eight) days of the date of The Company’s invoice. In the event of the amount specified in the statement being less than the amount paid by the User under the terms of Paragraph 2.14.4(c), The Company shall forthwith pay to the User an amount equal to the difference plus interest calculated on a daily basis at the Base Rate from the date of payment by the User under Paragraph 2.14.4(c) to the date on which the difference is repaid by The Company.
Connection Charges – Site Specific Maintenance Charge
The Company shall be entitled to invoice each User for the indicative Site Specific Maintenance Charge in each Financial Year as set out in the Statement of the Connecting Charging Methodology.
As soon as reasonably practicable and in any event by 31 July in each Financial Year The Company shall:
in accordance with the Statement of the Connection Charging Methodology calculate the actual Site Specific Maintenance Charge that would have been payable by the User during the preceding Financial Year (the “Actual Charge”) and compare this with the indicative Site Specific Maintenance Charge received from the User during the preceding Financial Year (the “Notional Charge”) and
prepare and send to the User a Maintenance Reconciliation Statement specifying the Actual Charge and the Notional Charge for the preceding Financial Year.
Two months after the date of issue of the Maintenance Reconciliation Statement and in any event by 30 September The Company shall issue a credit note in relation to any sums shown by the Maintenance Reconciliation Statement to be due to the User or an invoice in respect of sums due to The Company (such invoice to be payable within 30 days of the date of the invoice) and in each case interest thereon calculated pursuant to Paragraph 9.9.5(e) below. 9-8
Interest on all amounts due under this Paragraph 9.9.5 shall be payable by the paying CUSC Party to the other on such amounts from the date of payment applicable to the month concerned until the date of invoice for such amounts and such interest shall be calculated on a daily basis at a rate equal to the Base Rate during such period.
Payment The Connection Charges in the Financial Year in which the Charging Date occurs shall be apportioned as follows:- For each complete calendar month from Charging Date to the end of the Financial Year in which the Charging Date occurs the User shall be liable to pay one twelfth of the Connection Charges and for each part of a calendar month the User shall be liable to pay to The Company one twelfth of the Connection Charges prorated by a factor determined by the number of days for which the User is liable divided by the total number of days in such calendar month.
The provisions of Paragraphs 2.15 (Revision of Charges), 2.16 (Data Requirements), 2.17 (Replacement of Transmission Connection Assets), 2.18 Termination Amounts Re-use) and 2.19 to 2.22 inclusive (Security and Termination Amounts) of the CUSC shall apply to this Section 9 as if set out herein in full.
SPECIAL AUTOMATIC FACILITIES The Company and each User shall, as between The Company and that User operate respectively the National Electricity Transmission System and the User’s Equipment in accordance with the schemes set out in Appendix F3 to the relevant Bilateral Connection Agreement and/or any Operating Agreement.
PROTECTION AND CONTROL RELAY SETTINGS/FAULT CLEARANCE TIMES The Company and the User shall record the respective protection and control relay settings and fault clearance times to be operated by each of them in documents in the format set out in Appendix F4 to the relevant Bilateral Connection Agreement and shall operate them accordingly.
The User shall ensure that, in the case of a Connection Site Commissioned prior to the Transfer Date, on the Transfer Date, 9-9 and in the case of a Connection Site Commissioned after the Transfer Date, on the Completion Date(s), the User's Equipment complies with the site specific technical conditions set out in Appendix F5 to the relevant Bilateral Connection Agreement and/or in the relevant Operating Agreement.
The User shall use all reasonable endeavours to ensure during the period in which it is a party to a particular Bilateral Connection Agreement that the User's Equipment which is subject to that Bilateral Connection Agreement shall continue to comply with the site-specific technical conditions set out in Appendix F5 to that Bilateral Connection Agreement and/or in the relevant Operating Agreement.
If the User or The Company wishes to modify, alter or otherwise change the site specific technical conditions relating to a Connection Site or the manner of their operation:
under Appendix F4 to the relevant Bilateral Connection Agreement it may do so upon obtaining the agreement of the other party such agreement not to be unreasonably withheld;
under Appendices F1 or F3 or F5 to the relevant Bilateral Connection Agreement it shall be deemed to be a Modification for the purposes of the CUSC.
Where, in the case of a Connection Site Commissioned in England and Wales prior to the Transfer Date, on or immediately prior to the Transfer Date a User's Equipment subject to a particular Bilateral Connection Agreement has any of the following technical attributes or facilities:
circuit breaker fail protection
pole slipping protection
fault disconnection facilities
automatic switching equipment
control arrangements
voltage and current signals for system monitoring
control telephony
operational metering, the User shall, as between The Company and that User, use all reasonable endeavours to ensure that during the period of such 9-10 Bilateral Connection Agreement the User's Equipment which is subject to that Bilateral Connection Agreement retains such technical attributes or facilities provided always that if the User wishes to modify alter or otherwise change the same or their operation it may do so by following the procedures relating to a Modification in accordance with the CUSC.
In relation to a Connection Site Onshore The Company shall procure that the Relevant Transmission Licensee supplies to the User a copy of their Safety Rules current from time to time, including any site-specific Safety Rules, and also a copy of the Local Safety Instructions applicable at each Connection Site from time to time.
In relation to a Connection Site Onshore each User will supply to the Relevant Transmission Licensee a copy of their Safety Rules current from time to time, including any site-specific Safety Rules, and also a copy of the Local Safety Instructions applicable at each Connection Site from time to time.
In relation to Connection Sites and New Connection Sites Onshore The Company shall procure that the Relevant Transmission Licensee shall enter into an Interface Agreement with a User in either case in a form to be agreed between them but based substantially on the forms set out in Schedule 2 as appropriate where such Interface Agreement(s) is/are required pursuant to the applicable Bilateral Connection Agreement or otherwise.
In relation to Connection Sites and New Connection Sites Onshore the User undertakes to enter into an Interface Agreement with the Relevant Transmission Licensee in a form to be agreed between them but based substantially on the forms set out in Exhibit O to the CUSC as appropriate where such Interface Agreement(s) is/are required pursuant to the applicable Bilateral Connection Agreement or otherwise.
Subject to any contrary agreement in any Bilateral Connection Agreement or elsewhere, the division of ownership of Plant and Apparatus shall be at the electrical boundary, such boundary to be in relation to Plant and Apparatus located between the National Electricity Transmission System and an Interconnector at the busbar clamp on the busbar side of the 9-11 busbar isolators in the Interconnector transformer circuits at a Connection Site.
For the avoidance of doubt nothing in this Paragraph 9.16 shall effect any transfer of ownership in any Plant or Apparatus.
Where The Company has given notice of event of default to an Interconnector User or Interconnector Error Administrator in accordance with Section 5 The Company shall be entitled to request the User to cease or procure the cessation of the transfer of power across the relevant Interconnector by or on behalf of that Interconnector User or Interconnector Error Administrator.
As soon as practicable after such request from The Company the User shall cease or procure the cessation of the transfer of power across the relevant Interconnector by or on behalf of that Interconnector User.
If the User wishes to connect a New Connection Site it shall complete and submit to The Company a Connection Application in accordance with the Gated Application and Offer Process and comply with the terms thereof.
The Connection Application and Connection Offer shall be processed in accordance with the Gated Application and Offer Process. 9.17.2A An application for a New Connection Site which is a Gate 1 Application shall include the provision of a Letter of Acknowledgement. The Applicant shall ensure that a Letter of Acknowledgement shall pertain to the New Connection Site if this is known and otherwise shall be a general acknowledgement of the project and its offshore nature as set out in the Connection Application by reference to the offshore specific guidance in the LoA Guidance.
The Connection Offer shall remain open for acceptance (subject to CUSC Paragraph 6.10.4.4) for 3 months from its receipt by that User unless either that User or The Company makes an application to the Authority under condition E13 of the ESO Licence, in which event the Connection Offer shall remain open for acceptance until the date 14 days after any determination by the Authority pursuant to such application. 9-12
If the Connection Offer is accepted by that User the connection shall proceed according to the terms of the CUSC and the relevant Bilateral Connection Agreement and Construction Agreement entered into consequent upon acceptance of the Offer.
INTRODUCTION This Part II deals with rights and obligations relating to use of the National Electricity Transmission System by Interconnector Users and Interconnector Error Administrators. An Interconnector Error Administrator is deemed to be using the National Electricity Transmission System because of its registered BM Units. The User for the purposes of this Part II will therefore be an Interconnector User and/or an Interconnector Error Administrator. Where the Interconnector Error Administrator is The Company, the User for the purposes of this Part II will be The Company.
Subject to the provisions of the CUSC, the Grid Code and any relevant Operating Agreement The Company shall as between The Company and that User transport a supply of power through the National Electricity Transmission System together with such margin as The Company shall in its reasonable opinion consider necessary having due regard to The Company’s duties under the ESO Licence except to the extent (if any) that The Company is prevented from doing so by transmission constraints or by insufficiency of generation which, in either case, could not have been avoided by theexercise of Good Industry Practice by The Company.
This right is subject to there being a Bilateral Connection Agreement between the Interconnector Owner and The Company for the Connection Site of the relevant Interconnector.
The User acknowledges that breach of the provisions of the CUSC by an Interconnector Owner may give rise to Deenergisation or Disconnection of the Connection Site of that Interconnector pursuant to Section 5.
Subject to the provisions of the Grid Code and any Operating Agreement The Company shall be entitled to plan and execute 9-13 outages of parts of the National Electricity Transmission System or Transmission Plant or Transmission Apparatus at any time and from time to time.
If a User wishes to use the National Electricity Transmission System in accordance with this Part II, it shall complete and submit to The Company a Use of System Application and comply with the terms thereof.
Without prejudice to condition E12 of the ESO Licence, The Company shall make a Use of System Offer to that prospective User as soon as practicable after receipt of the Use of System Application and (save where the Authority commits to a longer period) in any event not more than 28 days after receipt by The Company or the Use of System Application.
The Use of System Offer shall be in the form of Use of System Interconnector Offer Notice. The provisions of condition E12 of the ESO Licence shall apply to an application by a User under this Section 9 Part II as if the Use of System Interconnector Offer Notice and Use of System Interconnector Confirmation Notice was an agreement for the purposes of that condition.
The Use of System Interconnector Offer shall remain open for acceptance for 28 days from its receipt by that User unless either that User or The Company makes an application to the Authority under condition E13 of the ESO Licence, in which event the Use of System Interconnector Offer Notice shall remain open for acceptance until the date 14 days after any determination by the Authority pursuant to such application.
Upon acceptance of the Use of System Interconnector Offer (as offered by The Company or determined by the Authority) by the User and the issuing by The Company of a Use of System Interconnector Confirmation Notice, the User shall have the right to use the National Electricity Transmission System in accordance with this Section. Such right shall continue until a Use of System Termination Notice is submitted pursuant to Paragraph 9.23.1 or the use ceases in accordance with 9.23.2.
Such rights shall be conditional upon the Applicant, if it is not already a party to the CUSC Framework Agreement, becoming a party to the CUSC Framework Agreement.
A User may terminate its use of the National Electricity Transmission System by giving The Company a Use of System Termination Notice not less than 28 days prior to such termination of use and the right to use the National Electricity Transmission System shall cease upon the termination date in the Use of System Termination Notice.
Use shall cease forthwith upon:
There ceasing to be a Bilateral Connection Agreement for the Connection Site of the relevant Interconnector;
disconnection of the Connection Site of the relevant Interconnector pursuant to Section 5;
an Event of Default by the User as provided for in Section 5.
Use shall be suspended for the period of any Deenergisation of the Connection Site of the relevant Interconnector pursuant to the CUSC.
INTRODUCTION This Part III deals with Interconnector Adjustment Payments. The User for the purposes of this Part III will therefore be the Interconnector Owner.
This section sets out when a User shall provide its best estimates of the Interconnector Adjustment Payments to The Company which is required so that The Company can calculate Transmission Network Use of System Charges and the date by which the User shall provide a statement to the Authority of the estimates sent to The Company.
By 1 November 2017 and then by 1 November in each subsequent Financial Year, each User will provide The Company with a best forecast of its Interconnector Adjustment Payments for that Financial Year and the following Financial Year. The User will update and provide a final forecast of the Interconnector Adjustment Payments for that and the following Financial Year by each 25 January. 9-15
On or before 25 January in 2018 and each following Financial Year (or such later date as the Authority may direct) the User shall provide a statement to the Authority of the forecast provided to The Company under Paragraph 9.23.2 for the previous Financial Year.
This section describes the data exchange process between The Company and the User, which is required so that The Company can regularly publish the forecast annual revenue used in the calculation of Transmission Network Use of System Charges over a five year period, so that parties that pay Transmission Network Use of System Charges can understand future changes.
Each User will report or forecast their Interconnector Adjustment Payments for the current Financial Year and each of the next five Financial Years on a nominal price basis (money of the day), and provide this data and narrative by e-mail no later than the close of the 5th business day each February and October.
All financial values will be supplied to the nearest £100k.
Each User will provide contact details with respect to answering any query with regards to their data.
Each User shall provide all necessary assistance in response to any reasonable query from The Company regarding the data submitted by that User.
Under Paragraphs 9.23 and 9.24 where no data is provided by the User or the data is subject to dispute, The Company shall use, for the purposes of calculating or forecasting the Transmission Network Use of System Charges, the data that it believes to be the most accurate until The Company is satisfied with the data provided or any dispute has been resolved.
For the avoidance of doubt, the use of substitute data as referred to in paragraph 9.25.1 will not affect the invoicing of The Company by the User, or the User by The Company.
Where The Company has used substitute data, The Company shall notify the relevant User. 9-16
If applicable, once any dispute has been resolved, charges shall be revised on the basis of the appropriate data.
This section describes the process applied when Interconnector Adjustment Payments are made from The Company to the User in a given Financial Year.
The User shall receive payment from The Company for the Interconnector Adjustment Payments in monthly instalments. By 1 October each year The Company shall email the User requesting a forecast of their Interconnector Adjustment Payments for the following Financial Year only. The Interconnector shall email The Company, on or before 1st November each year, their forecast of the Interconnector Adjustment Payments for the following Financial Year. Revisions to the Interconnector Adjustment Payments can be made up to 25th January each year for the following Financial Year.
The amount forecast in Paragraph 9.26.2 shall be accompanied by an invoicing schedule to detail the annual and monthly amounts for Interconnector Adjustment Payments as defined in the Interconnector Licences.
The User shall invoice The Company equal amounts over the remaining months of the Financial Year, matching the amounts shown in the schedule provided under Paragraph 9.26.3 and totalling the annual Interconnector Adjustment Payments. The Company shall pay the recurrent monthly User invoice on the later of
the 15th day following the day that the User’s invoice was despatched; and
the 16th day of the month to which the invoiced payments relate,
unless, in such case, such payment day is not a Business Day in which case payment shall be made on the next Business Day.
Paper invoices will be despatched by post, and supported by email, where feasible, to The Company. The User’s bank account details shall be included with each monthly invoice. 9-17
All payments will be by BACS.
Only under exceptional circumstances, can Interconnector Adjustment Payments from The Company be changed after final notification on 25th January. Exceptional circumstances mean an event or circumstance that is beyond the reasonable control of the licensee and for which it should not reasonably bear the financial risk.
This section describes the process for when Interconnector Adjustment Payments are made from the User to The Company in a given Financial Year.
The Company shall receive payment of the Interconnector Adjustment Payments from the User in monthly instalments. By
October each year The Company shall email the User requesting a forecast of their Interconnector Adjustment Payments for the following Financial Year. The User shall email The Company, on or before 1st November each year, their forecast of the Interconnector Adjustment Payments for the following Financial Year only. Revisions to the Interconnector Adjustment Payments can be made up to 25th January each year for the following Financial Year.
The amount forecast in Paragraph 9.27.2 shall be accompanied by an invoicing schedule to detail the annual and monthly amounts for Interconnector Adjustment Payments.
The Company shall invoice the User equal amounts over the remaining months of the Financial Year, matching the amounts shown in the schedule provided under Paragraph 9.27.3 and totalling the annual Interconnector Adjustment Payments. The User shall pay the recurrent monthly Company invoice on the later of
the 15th day following the day that The Company’s invoice was despatched; and
the 16th day of the month to which the invoiced payments relate,
unless, in such case, such payment day is not a Business Day in which case payment shall be made on the next Business Day.
Paper invoices will be despatched by post, and supported by email, where feasible, to the User. The Company’s bank account details shall be included with each monthly invoice. 9-18
All payments will be by BACS.
Only under exceptional circumstances, can Interconnector Adjustment Payments to The Company be changed after final notification on 25th January. Exceptional circumstances mean an event or circumstance that is beyond the reasonable control of the licensee and for which it should not reasonably bear the financial risk.
SECTION 10: TRANSITION ISSUES
INTRODUCTION
This Section 10, Part 1, deals with issues arising out of the transition associated with the approval and implementation of CMP 223. For the purposes of this Section 10, Part 1, the version of the CUSC as amended by CMP 223 shall be referred to as the “Post CMP223 CUSC” and the version of the CUSC prior to amendment by CMP 223 shall be referred to as the “Pre CMP 223 CUSC”.
CMP 223 affects Users in the category of (a) an Embedded Power Station which is the subject of a Bilateral Embedded Generation Agreement and (b) a Distribution System directly connected to the National Electricity Transmission System where there is an Associated DNO Construction Agreement and references to User in this Section 10, Part 1, shall be construed accordingly.
Part 1 of this Section sets out the arrangements such that by the CMP223 Transition Period End Date:
Existing Associated DNO Construction Agreements have been amended in line with the provisions introduced under CMP223;
The Cancellation Charge Secured Amount Statement issued by The Company for the CMP 223 Security Period in respect of Existing Associated DNO Construction Agreements and Existing BEGA Construction Agreements reflects the adjusted % introduced under CMP223;
Where an Existing Associated DNO Construction Agreement provides for more than one of a Relevant Embedded Small Power Station and/or Relevant Embedded Medium Power Station and/or Embedded Large Power Station which is the subject of a BELLA, Users have received the necessary information in respect of the Cancellation Charge and the Cancellation Charge Secured Amount in respect of each such project.
This Section 10, Part 1, comprises:
this Introduction; and
CMP 223 transition issues.
The provisions of the Post CMP 223 CUSC shall be suspended (except as specifically provided for in this Section 10, Part 1,and for the purposes of interpretation and definitions and for enabling the doing of anything which may require to be done in relation to but in advance of the CMP 223 Transition Period End Date to achieve the objectives at 10.1.4) in respect of the Users until the CMP 223 Transition Period End Date. Any termination of an Existing Associated DNO Construction Agreement or Existing BEGA Construction Agreement or reduction in Transmission Entry Capacity or Developer Capacity which takes effect prior to or on the CMP 223 Transition Period End Date shall therefore be dealt with, and the rights and obligations of The Company and the User to each other, shall be as provided for in the Existing Associated DNO Construction Agreement or Existing BEGA Construction Agreement.
In this Section 10, Part 1:
the term “Applicants”; shall mean Users who apply for an offer of a type referred to in (j) during the CMP 223 Transition Period;
the term “CMP 223”, shall mean CUSC Modification Proposal 223 (Arrangements for Relevant Distributed Generators under the Enduring Generation User Commitment);
the term “CMP 223 Implementation Date”, shall mean the Implementation Date for CMP 223;
the term “CMP 223 Security Period”, shall mean the Security Period immediately following the CMP 223 Transitional Period End Date;
the term “CMP 223 Transition Period End Date” shall mean the day before the day of the first Security Period which is not less than 6 months from the CMP 223 Implementation Date;
the term “CMP 223 Transition Period”, shall mean the period from the CMP 223 Implementation Date ending on and including the CMP 223 Transition Period End Date and is the period with which this Section 10, Part 1 deals;
the term “Existing Associated DNO Construction Agreement”, shall mean an Associated DNO Construction Agreement where the Construction Works will not be completed prior to the CMP 223 Transition Period End Date;
the term “Existing BEGA Construction Agreement”, shall mean a Construction Agreement with a User who is party to a Bilateral Embedded Generation Agreement where the Construction Works under this or the Associated DNO Construction Agreement will not be completed prior to the CMP 223 Transition Period End Date ;
the term “Existing Construction Agreement”, shall mean, as appropriate, an Existing Associated DNO Construction Agreement or an Existing BEGA Construction Agreement;
the term “New Applications”, shall mean a Request for a Statement of Works or Modification Application associated with Distributed Generation or Use of System Application by a User or prospective User or a Modification Application to vary any such agreements made during the CMP 223 Transition Period;
the term “Outstanding Applications”, shall mean an offer of a type referred to in (j) where the application was made prior to the CMP 223 Implementation Date;
the term “Outstanding Offers”, shall mean an offer to a User or prospective User of a type referred to in (j) which has not been accepted at the CMP 223 Implementation Date but is still capable of being accepted.
Without prejudice to any specific provision under this Section 10, Part 1 as to the time within which or the manner in which The Company or a User should perform its obligations under this Section 10, Part 1, where The Company or a User is required to take any step or measure under this Section 10, Part 1, such requirement shall be construed as including any obligation to:
take such step or measure as quickly as reasonably practicable; and
do such associated or ancillary things as may be necessary to complete such step or measure as quickly as reasonably practicable.
CMP 223 TRANSITION Existing Construction Agreements
The Company shall offer to amend each Existing Associated DNO Construction Agreement such that it is consistent at the CMP 223 Transition Period End Date with the amendments introduced by CMP 223.
The Company shall make the offer in respect of each Existing Associated DNO Construction Agreement to each User as soon as reasonably practicable after the CMP 223 Implementation Date.
If The Company and a User fail to agree changes to an Existing Associated DNO Construction Agreement either such person may refer the matter to the Authority under Condition E13 Paragraph 5 of the ESO Licence.
In respect of the CMP 223 Security Period, the Cancellation Charge Secured Amount Statement sent to each User with an Existing Associated DNO Construction Agreement or Existing BEGA Construction Agreement shall reflect the provisions introduced by CMP 223 and each such User shall put security arrangements in place in accordance with CUSC Section 15 such security arrangements to be effective from the start of the CMP 223 Security Period. Outstanding Applications and New Applications
The Company shall make Offers such that prior to the CMP 223 Transition Period End Date the arrangements for security and liability within the agreements are consistent with those under the Pre CMP 223 CUSC but such that on CMP 223 Transition Period End Date the arrangements for security and liability within the agreements are consistent with those under the Post CMP 223 CUSC and shall to the extent practicable make such Offers within the original or standard timescales. Part 2
Introduction
This Section 10, Part 2 deals with issues arising out of the transition associated with the approval and implementation of CMP293 and CMP294 (Modifications relating to the transfer of the system operator role from National Grid Electricity Transmission plc to The Company).
This Section 10, Part 2 sets out the arrangements such that:
the rights and obligations of National Grid Electricity Transmission plc (No: 2366977 whose registered office is at 1-3 Strand, London WC2N 5EH) under the CUSC and the CUSC Agreements were novated to The Company (No: 11014226 to reflect the Transfer of System Operator Role;
certain amendments were made to the CUSC Agreements to reflect the Transfer of the System Operator Role; and
each CUSC Party will co-operate in relation to the transition.
The provisions of the Post CMP293 and CMP294 CUSC shall be suspended until the SO Transfer Date expect for this Section 10, Part 2 (which will take immediate effect).
In this Section 10, Part 2:
the term “CMP293 and CMP294” shall mean CUSC Modification Proposal 293 and 294 (Modifications relating to the transfer of the system operator role from National Grid Electricity Transmission plc to The Company);
the term “CUSC Agreement” shall mean each or any of the agreements listed in Paragraph 10.4.3;
the term “Post CMP293 and CMP294 CUSC” means the version of the CUSC as amended by CMP293 and CMP294;
the term “Pre CMP293 and CMP294 CUSC” means the version of the CUSC prior to amendments by CMP293 and CMP294;
the term “SO Transfer Date” means the date and time on which the Transmission Licence granted to National Grid Electricity Transmission plc was transferred in part to The Company to effect the Transfer of the System Operator Role; and
the term “Transfer of the System Operator Role” means the transfer, by means of the transfer in part of the Transmission Licence granted to National Grid Electricity Transmission plc, of the system operator role to The Company.
Without prejudice to any specific provision under this Section10, Part 2 as to the time within which or the manner in which any CUSC Party should perform its obligations under this Section 10, Part 2, where a CUSC Party is required to take any step or measure under this Section, Part 2, such requirement shall be construed as including any obligation to:
take such step or measure as quickly as reasonable practicable; and
do such associated or ancillary things as may be necessary to complete such step or measure as quickly as reasonably practicable.
CMP293 and CMP294: NOVATION OF CUSC AGREEMENTS
National Grid Electricity Transmission plc and The Company shall each enter into a novation agreement in the form published by National Grid Electricity Transmission plc as part of the CMP293 and CMP294 process.
Such novation agreement will, with effect from the SO Transfer Date, novate to The Company all rights and obligations of National Grid Electricity Transmission plc under the agreements referred to in Paragraph 10.4.4 (including all rights, obligations and liabilities of National Grid Electricity Transmission plc that may have accrued in respect of the period prior to the SO Transfer Date) as more specifically provided for in the novation agreement.
Such novation agreement shall be in respect of each CUSC Agreement, being the following: the CUSC Framework Agreement; all Bilateral Agreements all Construction Agreements; all Mandatory Services Agreements; and all Transmission Related Agreements.
National Grid Electricity Transmission plc shall enter into such novation agreement in (to the extent applicable) its own right, and also (to the extent applicable) on behalf of the CUSC Parties.
Each CUSC Party hereby irrevocably and unconditionally authorises National Grid Electricity Transmission to execute and deliver, on behalf of such CUSC Party, a novation agreement as envisaged by this section.
Each CUSC Party shall do all such things as The Company may reasonably request in relation to the novation of the agreements referred to in Paragraph 10.4.3 from National Grid Electricity Transmission plc to The Company, whether before or after the Transfer Date, including to such things as may be necessary or desirable to facilitate the novation.
CMP293 and CMP294: AMENDMENTS TO CUSC AGREEMENTS
Each CUSC Agreement shall be read and construed, with effect from SO transfer Date, as if it had been amended in accordance with any changes to its corresponding proforma exhibit to the Post CMP293 and CMP294 CUSC and The Company will enter into the necessary agreements in this respect with National Grid Electricity Transmission plc pursuant to the STC. Each CUSC Party acknowledges and agrees that the provisions of this Paragraph 10.5.1 shall apply notwithstanding the provisions in the CUSC Agreements as to variation of those agreements.
Each CUSC Agreement shall be read and construed such that any obligation, arising prior to the SO Transfer Date, to provide or renew security in respect of the Security Period commencing on the SO Transfer Date shall be construed to require the security to be provided to or renewed in the name of The Company in accordance with the process notified by National Grid Electricity Transmission plc.
The CUSC and each CUSC Agreement shall be read and construed such that any general obligations regarding the provision of security shall be construed to require the replacement of any existing security to be provided in the name of National Grid Electricity Transmission System Operator Limited not less than 75 (seventy five) days (or if such day is not a Business Day the next following Business Day) prior to 31 March 2019 and effective from the SO Transfer Date in accordance with the process notified by National Grid Electricity Transmission plc.
In the context of any Site Responsibility Schedule in existence at the SO Transfer Date which would require, following the Transfer of the System Operator Role, the signature of either The Company instead of National Grid Electricity Transmission plc or both the signature of The Company and National Grid Electricity Transmission plc, National Grid Electricity System Operator Limited and National Grid Electricity Transmission plc acknowledge and the other Parties agree that the signature of National Grid Electricity Transmission plc on such Site Responsibility Schedule shall be considered to be the signature of The Company and/or National Grid Electricity Transmission plc as appropriate.
CMP293 and CMP294: TRANSITIONAL ISSUES
Each CUSC Party shall take such steps and do such things in relation to the CUSC and the CUSC Agreements as are within its power and as are necessary or appropriate in order to give full and timely effect to the Transfer of the System Operator Role.
Each CUSC Party agrees that all things done by National Grid Electricity Transmission plc pursuant to CUSC prior to the SO Transfer Date (including but not limited to the making of offers, the provision of reports and statements and the serving of notices) shall be deemed to have been done by National Grid Electricity System Operator Limited and all things received by National Grid Electricity Transmission plc pursuant to CUSC (including but not limited to applications and notices) shall be deemed to have been received by The Company.
In particular:
Users acknowledge and agree that National Grid Electricity Transmission plc can exchange information and data submitted by Users under the CUSC prior to the SO Transfer Date with The Company to the extent necessary to enable the transition of the system operator role from National grid Electricity Transmission plc to The Company;
National Grid Electricity Transmission plc will identify and publish as soon as practicable [and in any event prior to [x] January 2019] any requirements on Users necessary to manage the transition of the operations, systems, process and procedures and the rights and obligations relating to the Transfer of the SO Role under the CUSC from National Grid Electricity Transmission plc to The Company.
SECTION 11: INTERPRETATION AND DEFINITIONS
INTRODUCTION This Section sets out general rules to be applied in interpreting the CUSC, Bilateral Agreements, Construction Agreements and Mandatory Services Agreements. It also sets out the defined terms used by the CUSC (other than those defined elsewhere in the CUSC) and other agreements. Those other agreements may, in accordance with Paragraph 11.2.2, have their own further interpretation rules and defined terms which apply only to the individual agreements.
In the CUSC and in each Bilateral Agreement and in each Mandatory Services Agreement and each Construction Agreement:
the interpretation rules in this Paragraph 11.2; and
the words and expressions defined in Paragraph 11.3, shall, unless the subject matter or context otherwise requires or is inconsistent therewith, apply.
Save as otherwise expressly provided in the CUSC, in the event of any inconsistency between the provisions of any Bilateral Agreement, Mandatory Services Agreement or Construction Agreement and the CUSC, the provisions of the Bilateral Agreement or Mandatory Services Agreement or Construction Agreement shall prevail in relation to the Connection Site which is the subject thereof to the extent that the rights and obligations of Users not party to that Bilateral Agreement, Mandatory Services Agreement or Construction Agreement are not affected.
If in order to comply with any obligation in the CUSC, any Bilateral Agreement or any Construction Agreement any CUSC Party is under a duty to obtain the consent or approval (including any statutory licence or permission) ("the Consent") of a third party (or the Consent of another CUSC Party) such obligation shall be deemed to be subject to the obtaining of such Consent which the CUSC Party requiring the Consent shall use its reasonable endeavours to obtain including (if there are reasonable grounds therefor) pursuing any appeal in order to obtain such Consent.
If such Consent is required from any CUSC Party then such CUSC Party shall grant such Consent unless it is unable to do so or it would be unlawful for it to do so provided that such grant by such CUSC Party may be made subject to such reasonable conditions as such CUSC Party shall reasonably determine.
For the avoidance of doubt if the CUSC Party who is under a duty to obtain such Consent fails to obtain such Consent having complied with this Paragraph 11.2 the obligation on that CUSC Party (in relation to which such Consent is required) shall cease.
In the CUSC and in each Bilateral Agreement and in each Mandatory Services Agreement and each Construction Agreement:
unless the context otherwise requires all references to a particular Paragraph, Part, Section, Schedule or Exhibit shall be a reference to that Paragraph, Part, Section, Schedule or Exhibit in or to the CUSC and all references to a particular Appendix shall be a reference to that Appendix to a Bilateral Agreement or Mandatory Services Agreement or Construction Agreement (as the case may be);
a table of contents and headings are inserted for convenience only and shall be ignored in construing the CUSC or a Bilateral Agreement, Construction Agreement or Mandatory Services Agreement as the case may be;
references to the words "include" or "including" are to be construed without limitation to the generality of the preceding words;
unless the context otherwise requires any reference to an Act of Parliament or any part or section or other provision of or schedule to an Act of Parliament shall be construed, at the particular time, as including a reference to any modification, extension or re-enactment thereof then in force and to all instruments, orders or regulations then in force and made under or deriving validity from the relevant Act of Parliament; and
references to the masculine shall include the feminine and references in the singular shall include the plural and vice versa and words denoting persons shall include any individual, partnership, firm, company, corporation, joint venture, trust, association, organisation or other entity, in each case whether or not having separate legal personality.
In the case of OTSDUW Build, if the Transmission Interface Site is Operational prior to the OTSUA Transfer Time the User’s Equipment will be connected to the National Electricity Transmission System through the connection of the OTSUA to the National Electricity Transmission System at the Transmission Interface Point until the OTSUA Transfer Time. In such case and until the OTSUA Transfer Time, where provisions of the CUSC apply in relation to (a) User’s Equipment; such provisions and references to User’s Equipment shall be construed where the context requires as being instead references to or including (as the context requires) OTSUA unless the context otherwise requires; and (b) User’s Equipment by reference to the Connection Site; such provisions and references to User’s Equipment and Connection Site in the CUSC shall be construed as being instead references to or including (as the context requires) OTSUA and Transmission Interface Site respectively unless the context otherwise requires;
Obligations on The Company shall be interpreted as obligations to procure that the Relevant Transmission Licensee fulfils such obligations, where relevant.
DEFINITIONS The following terms shall have the following meanings: “5 Business Days in the context of Section 17, the 5 Business Days after closure of Period” a Gate 2 Application Window; “10 Clear Days” defined as 10 complete periods of 24 hours from 00:00hrs to 24:00hrs; “15 Business Days in the context of Section 17, the 15 Business Days after closure Period” of a Gate 2 Application Window; "ABSVD Methodology the document entitled "Applicable Balancing Services Volume Data Statement" Methodology Statement", as published by The Company as the same may be amended from time to time; "Accession Agreement" an agreement in or substantially in the form of Exhibit A to the CUSC whereby an applicant accedes to the CUSC Framework Agreement; "Acceptance Volume" as defined in the Balancing and Settlement Code; "Act" the Electricity Act 1989; "Active Power" the product of voltage and the in-phase component of alternating current measured in units of watts and standard multiples thereof i.e. 1000 watts = 1kW 1000 kW = 1MW 1000 MW = 1GW 1000 GW = 1TW; "Actual Amount" as defined in Paragraph 3.13; “Actual Attributable where the Attributable Works Cancellation Charge is calculated Works Cancellation in accordance with Paragraph 3.5.2 of Part Two of the User Charge” Commitment Methodology; “Additional Load” Site Load other than Station Load and importing Generating Units for processes other than the production of electricity; "Additional Scheduling as defined in the Grid Code on the day prior to the NETA Go-live Data" Date; "Adjusted LDTEC the LDTEC Profile as adjusted by the MW cap specified by the Profile" User in its acceptance of the LDTEC Block Offer in accordance with CUSC Paragraph 6.32.6.4; “Adjustment Revenue” a positive or negative adjustment to overall Generator TNUoS charges to ensure compliance with the Limiting Regulation; “Adjustment Tariff” the non locational £/kW tariff that applies Adjustment Revenue to Generators liable for TNUoS charges to ensure compliance with the Limiting Regulation; “Advancement” advancement of the Construction Programme to enable an earlier Completion Date for connection to or use of the National Electricity Transmission System or Energisation in the case of Embedded Power Stations; “Advancement a request for Advancement in the form set out in the Gate 2 Request” Criteria Methodology; "Affected User" a User: a) with Transmission Entry Capacity for the Connection Site against which the affected Export BM Unit or Associated Export BM Unit BM Unit is registered and who is paying or in receipt of generator Transmission Network Use of System Charges by reference to such Transmission Entry Capacity; or b) an Interconnector Owner; "Affiliate" in relation to The Company (and in relation to Paragraphs 3.6.9.8, 6.14, 8A.3.1.2 and 8A.4.2.2, any User) means any holding company or subsidiary of The Company (or the User as the case may be) or any subsidiary of a holding company of The Company (or the User as the case may be), in each case within the meaning of sections 736, 736A and 736B of the Companies Act 1985 as substituted by section 144 of the Companies Act 1989; “AF Rules” has the meaning given to “allocation framework” in section 13(2) of the Energy Act 2013; “Agency” the Agency for the Cooperation of the Energy Regulators established under 2009/713/EC of the European Parliament and of the Council of the 13 July 2009 establishing an Agency for the Cooperation of Energy Regulators as amended from time to time; "Agency Business" any business of The Company or any Affiliate or Related Undertaking in the purchase or other acquisition or sale or other disposal of electricity as agent for any other Authorised Electricity Operator; "Agreed Ancillary Part 2 System Ancillary Services and Commercial Ancillary Services" Services; "Agreed Value" the value attributed by The Company to the form of security provided that if The Company and the User cannot agree on such value then the value will be determined by an expert appointed by The Company and the User or, failing their agreement as to the expert, the expert nominated by the Director General of The Institute of Credit Management; "Alternate Election as defined in Paragraph 8A.4.4.2; Process" "Alternate Member(s)" persons appointed as such pursuant to Paragraph 8.7.2; "Alternate Member as defined in Paragraph 8A.4.3.3; Interim Vacancies" "Allowed Interruption" shall mean an Interruption as a result of any of the following: a) an Event other than an Event on the National Electricity Transmission System; b) an event of Force Majeure pursuant to Paragraph 6.19 of the CUSC; c) (i) a Total Shutdown
a Partial Shutdown, but only for any period of Interruption which coincides with a Market Suspension Period; d) action taken under the Fuel Security Code; e) Disconnection or Deenergisation by or at the request of The Company under Section 5 of the CUSC, except in the case of an Emergency Deenergisation Instruction; f) the result of a direction of the Authority or Secretary of State; g) tripping of the User’s Circuit Breaker(s) following receipt of a signal from a System to Generator Operational Intertripping Scheme which has been armed in accordance with Paragraph 4.2A.2.1(b). or if provided for in a Bilateral Agreement with the affected User; "Ancillary Services" System Ancillary Services and/or Commercial Ancillary Services as the case may be; "Ancillary Services an agreement between The Company and a User or other person Agreement" to govern the provision of and payment for one or more Ancillary Services, which term shall include without limitation a Mandatory Services Agreement; "Annual Average Cold a particular combination of weather elements which gives rise to a Spell (ACS) level of peak Demand within an The Company Financial Year Conditions" which has a 50% chance of being exceeded as a result of weather variation alone; “Annual Wider the statement published by The Company each Financial Year Cancellation Amount in accordance with the User Commitment Methodology; Statement” "Apparatus" all equipment in which electrical conductors are used, supported or of which they may form a part; “Apparent Power” as defined in the Grid Code; Applicant" a person applying for connection and/or use of system under the CUSC; "Applicable CUSC as defined in the ESO Licence; Objectives" "Applicable PCF" the amount calculated in accordance with Paragraphs 4.3 to 4.6 of Part Five of the User Commitment Methodology; “Applicable Value” the highest contractual Transmission Entry Capacity figure for year “t” provided to The Company up to and including 31 October in year “t-1” for publication in the October update of the Electricity Ten Year Statement; "Application for a an application made by a User in accordance with the Offer"` STTEC" Paragraph 6.31 for Short Term Capacity for a STTEC Period; "Approved Agency" the panel of three independent assessment agencies appointed by The Company and other network operators from time to time for the purpose of providing Independent Credit Assessments details of such agencies to be published on the The Company Website; "Approved CUSC as defined in Paragraph 8.23.7; Modification" “Approved CUSC as defined in Paragraph 8.29.7,provided that no objection is Modification Fast Track received pursuant to Paragraph 8.29.12; Proposal” “Approved CUSC as defined in Paragraph 8.25.10; Modification Self- Governance Proposal” "Applicable Balancing has the meaning given in the Balancing and Settlement Code; Services Volume Data" "Approved Credit a long term debt rating of not less than BB- by Standard and Poor’s Rating" Corporation or a rating not less than Ba3 by Moody’s Investor Services, or a short term rating which correlates to those long term ratings, or an equivalent rating from any other reputable credit agency approved by The Company; or such other lower rating as may be reasonably approved by The Company from time to time; Assimilated Law has the same meaning as that given by section 6(7) of the European Union (Withdrawal) Act 2018; “Associated DNO a Construction Agreement between The Company and a User Construction in the category of a Distribution System directly connected to Agreement” the National Electricity Transmission System in respect of works required on the National Electricity Transmission System as a consequence of the connection of Distributed Generation to the Distribution System; “Associated Export BM an Export BM Unit where: Unit”
that Export BM Unit and an Import BM Unit are comprised in the User’s Equipment are both registered as being associated with each other by being listed in Appendix C of the same Bilateral Connection Agreement; and the Import BM Unit is Deenergised and as a direct consequence of the Deenergisation of the Import BM Unit the Export BM Unit is also Deenergised; “Attributable Works” those components of the Construction Works which are required
to connect a Power Station or Interconnector which is to be connected at a Connection Site to the nearest suitable MITS Node; or (b) in respect of an Embedded Power Station from the relevant Grid Supply Point to the nearest suitable MITS Node; (and in any case above where the Construction Works include a Transmission substation that once constructed will become the MITS Node, the Attributable Works will include such Transmission substation) but excluding in each case (a) and (b) any Excepted Works, and which in relation to a particular User are as specified in its Construction Agreement; “Attributable Works the component of the Cancellation Charge which applies on and Cancellation Charge” after the Trigger Date and prior to the Charging Date as more particularly described in Part Two of the User Commitment Methodology; “Attributable Works the fees, expenses and costs of whatever nature reasonably and Capital Cost” properly incurred or due in respect of each component within the Attributable Works; "Authorised Recipient" in relation to any Protected Information, means any Business Person who, before the Protected Information had been divulged to them by The Company or any Subsidiary of The Company, had been informed of the nature and effect of Paragraph 6.15.1 and who requires access to such Protected Information for the proper performance of their duties as a Business Person in the course of Permitted Activities; "Authority" the Director General of Electricity Supply appointed for the time being pursuant to section 1 of the Act or, after the coming into force of section 1 of the Utilities Act 2000, the Gas and Electricity Markets Authority established by that section; “Authority Guidance means the guidance published by the Authority from time to time on Code Modification on code modification prioritisation; Prioritisation” "Available LDTEC" is the level of MW for an LDTEC Week as notified by The Company to a User in (in the case of the first seven LDTEC Weeks) the LDTEC Indicative Block Offer and for subsequent LDTEC Weeks in an LDTEC Availability Notification; "Back Stop Date" in relation to an item of Derogated Plant, the date by which it is to attain its Required Standard, as specified in or pursuant to the relevant Derogation; "Balancing and as defined in the ESO Licence; Settlement Code" or "BSC" "Balancing Code" or as defined in the Grid Code; "BC" "Balancing Mechanism" as defined in the ESO Licence; "Balancing Services" as defined in the ESO Licence; "Balancing Services as defined in the ESO Licence; Activity" "Balancing Services an agreement between The Company and a User or other person Agreement" governing the provision of and payment for one or more Balancing Services; "Balancing Services the element of Use of System Charges payable in respect of the Use of System Balancing Services Activity; Charges" "Balancing Services The Company’s estimate of the average expected Balancing Use of System Charges Services Use of System Charges for each month in the Current Forecast Information" Financial Year and each month of the following Financial Year. "Balancing Services as defined in Paragraph 3.15.1; Use of System Reconciliation Statement" “Balancing Services the component of the working capital facility, which is capped to a Use of System Working level as agreed between The Company and The Authority, Capital Facility” available to The Company which is ringfenced for the purposes of BSUoS Charges; "Bank Account" a bank account in the name of The Company at such branch of Barclays Bank PLC, or such branch of any other bank, in the City of London as is notified by The Company to the User in which deposits of principal sums from the User shall be ascertainable, bearing interest from (and including) the date of deposit of principal sums to (but excluding) the date of withdrawal of principal sums from such account, mandated for withdrawal of principal solely by The Company against delivery of a Notice of Drawing for the amount demanded therein and mandated for the transfer of any interest accrued to the Bank Account to such account to: a) an associated bank account in the name of The Company in which the interest accruing in respect of the principal sums deposited by the User shall be ascertainable; or b) such bank account as the User may specify; "Base Rate" in respect of any day, the rate per annum which is equal to the base lending rate from time to time of Barclays Bank PLC as at the close of business on the immediately preceding Business Day; "Base Value at Risk" the sum of HH Base Value at Risk, NHH Base Value at Risk, FDSC Base Value at Risk and the UMS Base Value at Risk; "BELLA Application" an application for a BELLA in the form or substantially in the form set out in Exhibit Q; "BELLA Offer" an offer for a BELLA in the form or substantially the form set out in Exhibit R including any revision or extension of such offer; "Bi-annual Estimate" an estimate pursuant to Paragraph 2.21.2 of all payments to be made or which may be required to be made by the User in any relevant period, such estimate to be substantially in the form set out in Exhibit L to the CUSC; “Bid” as defined in the Balancing and Settlement Code; "Bid-Offer Acceptance" as defined in the Balancing and Settlement Code; "Bid-Offer Volume" as defined in the Balancing and Settlement Code; "Bilateral Agreement" in relation to a User, a Bilateral Connection Agreement or a Bilateral Embedded Generation Agreement, or a BELLA or a Virtual Lead Party Agreement between The Company and the User; "Bilateral Connection an agreement entered into pursuant to Paragraph 1.3.1 a form of Agreement" which is set out in Exhibit 1 to Schedule 2; "Bilateral Embedded an agreement entered into pursuant to Paragraph 1.3.1, a form of Generation Agreement" which is set out in Exhibit 2 to Schedule 2; "Bilateral Embedded an agreement in respect of an Embedded Exemptable Large Licence exemptable Power Station entered into pursuant to Paragraph 1.3.1, a form of Large power station which is set out in Exhibit 5 to Schedule 2; Agreement" or "BELLA" "Bilateral Insurance a policy of insurance taken out by the User with a company in the Policy" business of providing insurance who meets the Requirements for the benefit of The Company and upon which The Company can claim if the circumstances set out in CUSC Paragraph 5.3.1(b) (i) to (v) arise in respect of such User and which shall provide security for the Agreed Value. In addition The Company may accept such a policy from such a company who does not meet the Requirements up to an Agreed Value where The Company agrees or where The Company does not agree as determined by an expert appointed by The Company and the User or failing their agreement as to the expert the expert nominated by the Director General of The Institute of Credit Management; "Block LDTEC" is at any given time the lower of the MW figure in the LDTEC Profile or Adjusted LDTEC Profile for an LDTEC Period; "BM Unit" as defined in the Balancing and Settlement Code; "BM Unit Identifiers" the identifiers (as defined in the Balancing and Settlement Code) of the BM Units; "BM Unit Metered as defined in the Balancing and Settlement Code; Volume" "Boundary Point as defined in the Balancing and Settlement Code; Metering System" "British Grid Systems the agreement made on 30 March 1990 of that name between The Agreement" Company, Scottish Hydro Electric plc, and Scottish Power plc; "BSC Agent" as defined in the Balancing and Settlement Code; "BSC Framework as defined in the ESO Licence; Agreement" "BSC Panel" the Panel as defined in the Balancing and Settlement Code; "BSC Party" a person who is for the time being bound by the Balancing and Settlement Code by virtue of being a party to the BSC Framework Agreement; "Business Day" any week-day other than a Saturday on which banks are open for domestic business in the City of London; "Business Person" any person who is a Main Business Person or a Corporate Functions Person and "Business Personnel" shall be construed accordingly; “Cancellation Charge” the charge payable by certain Users in the event of termination of a Bilateral Connection Agreement or Bilateral Embedded Generation Agreement or Construction Agreement or a reduction in Transmission Entry Capacity or a reduction in Interconnector User Commitment Capacity or a reduction in Developer Capacity as calculated in accordance with the User Commitment Methodology; “Cancellation Charge the profile as applied to the Fixed Attributable Works Profile” Cancellation Charge and Wider Cancellation Charge in accordance with Part Two of the User Commitment Methodology; “Cancellation Charge the amount to be secured by a User from the start of and during a Secured Amount” Security Period as such amount is applied and calculated in accordance with Part Three of the User Commitment Methodology; “Cancellation Charge the statement issued by The Company to a User in accordance Secured Amount with Part Two of the User Commitment Methodology showing the Statement” Cancellation Charge Secured Amount for a given Security Period such statement to be in substantially the form set out in Exhibit MM2 to the CUSC; “Cancellation Charge the difference between (a) the Cancellation Charge Secured Shortfall” Amount (or such higher sum as paid by the Developer to the User in respect of the Cancellation Charge) and (b) the Cancellation Charge payable by the User; “Cancellation Charge the statement issued by The Company to a User in accordance Statement” with Part Two of the User Commitment Methodology such statement to be in substantially the form set out in Exhibit MM1 to the CUSC; "CAP 179 shall mean the date specified as the Implementation Date in the direction issued by the Authority approving CUSC Amendment Implementation Date" Proposal 179 (Prevention of Timing Out of Authority Decisions on Amendment Proposals); "Capability Payment" as defined in Paragraph 4.2A.4(a)(i); “Capacity Market the Capacity Market Rules, The Electricity Capacity Regulations Documents” 2014 and any other Regulations made under Chapter 3 of Part 2 of the Energy Act 2013 which are in force from time to time; “Capacity Market the rules made under section 34 of the Energy Act 2013 as Rules” modified from time to time in accordance with that section and The Electricity Capacity Regulations 2014; "Category 1 as defined in the Grid Code; Intertripping Scheme" "Category 2 as defined in the Grid Code; Intertripping Scheme" "Category 3 as defined in the Grid Code; Intertripping Scheme" "Category 4 as defined in the Grid Code; Intertripping Scheme" "CCGT Unit" a Generating Unit within a CCGT Module; “Central Volume as defined in the Balancing and Settlement Code; Allocation” “CfD Administrative The Secretary of State, a CfD Counterparty and any CfD Parties” Settlement Services Provider; “CfD Counterparty” a person designated as a “CfD counterparty” under section 7(1) of the Energy Act 2013; “CfD Documents” the AF Rules, The Contracts for Difference (Allocation) Regulations 2014, The Contracts for Difference (Definition of Eligible Generator) Regulations 2014 and The Contracts for Difference (Electricity Supplier Obligations) Regulations 2014 and any other regulations made under Chapter 2 of Part 2 of the Energy Act 2013 which are in force from time to time; “CfD Settlement means any person: Services Provider”
appointed for the time being and from time to time by a CfD Counterparty; or
who is designated by virtue of Section C1.2.1B of the Balancing and Settlement Code, in either case to carry out any of the CFD settlement activities (or any successor entity performing CFD settlement activities); “Charges for Physical shall mean charges paid by producers for physical assets required Assets Required for for connection to the system or the upgrade of the connection; Connection” “Charging Band” a band containing sites from one of the Residual Charging Groups created for the purpose of Transmission Demand Residual charging in accordance with 14.15.137 of the Connection and Use of System Code; “Charging Date” as defined in the Construction Agreement; "Charging Dispute" as defined in Paragraph 7.2.1; “Charging (a) the Use of System Charging Methodology; and/or Methodologies”
the Connection Charging Methodology; "Charging Statements" the Statement of the Connection Charging Methodology, the Statement of the Use of System Charging Methodology, and the Statement of Use of System Charges; "Circuit Breaker" a mechanical switching device, capable of making, carrying and breaking currents under normal circuit conditions and also of making, carrying for a specified time and breaking currents under specified abnormal circuit conditions, such as those of short circuit; “Citizens Advice” the National Association of Citizens Advice Bureaux; “Citizens Advice the Scottish Association of Citizens Advice Bureaux; Scotland” “CM Administrative the Secretary of State, the CM Settlement Body, and any CM Parties” Settlement Services Provider; “CMP434” CUSC Modification Proposal 434: Implementing Connections Reform; “CMP434 shall mean the date specified as the Implementation Date Implementation Date" for CMP434 in the direction issued by the Authority approving CMP434; "CMP434 Gate 1 the form of Gate 1 Agreement introduced through CMP434; Agreement” “CMP434 Gate 2 the form of Gate 2 Agreement introduced through CMP434; Agreement” “CMP435” CUSC Modification Proposal 435: Application of Gate 2 Criteria to existing contracted background; “CMP435 the date specified as the Implementation Date for CMP435 in the Implementation Date" direction issued by the Authority approving CMP435; "CMRS" as defined in the Balancing and Settlement Code; “CM Settlement Body” the Electricity Settlements Company Ltd or such other person as may from time to time be appointed as Settlement Body under regulation 80 of the Electricity Capacity Regulations 2014; “CM Settlement any person with whom the CM Settlement Body has entered into Services Provider” a contract to provide services to it in relation to the performance of its functions under the Capacity Market Documents; “Code Administration the code of practice approved by the Authority and: Code of Practice”
developed and maintained by the code administrators in existence from time to time;
amended subject to the Authority’s approval from time to time; and
re-published from time to time; “Code Administrator” The Company carrying out the role of Code Administrator pursuant to Section 8; "Code of Practice" as defined in the Balancing and Settlement Code; "Combined Cycle Gas a collection of Generating Units (registered under the Grid Code Turbine Module" or PC) comprising one or more Gas Turbine Units (or other gas "CCGT Module" based engine units) and one or more Steam Units where, in normal operation, the waste heat from the Gas Turbine Units is passed to the water/steam system of the associated Steam Units and where the component units within the CCGT Module are directly connected by steam or hot gas lines to enable those units to contribute to the efficiency of the combined cycle operation of the CCGT Module; "Commercial Ancillary as defined in the Grid Code; Services" "Commercial (unless otherwise defined in the relevant Mandatory Services Boundary" Agreements), the commercial boundary between either The Company or a Public Distribution System Operator (as the case may be) and the User at the higher voltage terminal of the generator step-up transformer; "Commercial Services an agreement between The Company and a User or other person Agreement" to govern the provision of and payment for one or more Agreed Ancillary Services; "Commissioned" in respect of Plant and Apparatus commissioned before the Transfer Date means Plant and Apparatus recognised as having been commissioned according to the commissioning procedures current at the time of commissioning and in respect of Plant and Apparatus commissioned after the Transfer Date means Plant and/or Apparatus certified by the Independent Engineer as having been commissioned in accordance with the relevant Commissioning Programme; "Commissioning in relation to a particular user, as defined in its Construction Programme" Agreement; "Commissioning as defined in relation to a particular User in the Construction Programme Agreement; Commencement Date" “Competent” a Gate 1 Application or Gate 2 Application is competent when in the opinion of The Company acting reasonably the Gate 1 Application or Gate 2 Application form has been completed as required, the required data has been provided and the application fee paid to The Company; "Competent Authority" the Secretary of State, the Authority and any local or national agency, authority, department, inspectorate, minister (including Scottish ministers), ministry, official or public or statutory person (whether autonomous or not) of, or of the government of, the United Kingdom; “Competitively such person who has been awarded a Transmission Licence on Appointed the basis of an Onshore Tender Process and in relation to whose Transmission Owner Transmission Licence the Standard Conditions in Section D (CATO)” (transmission owner standard conditions) have been given effect; "Completion Date" in relation to a particular User, as defined in its Construction Agreement; "Composite Demand in respect of a User its Demand related Transmission Network Charges" Use of System Charges for each Transmission Network Use of System Demand Zone; “Conditional those User Progression Milestones categorised as such in Progression CUSC Section 16; Milestones” "Confidential all data and other information supplied to a User by another CUSC Information" Party under the provisions of the CUSC or any Bilateral Agreement, Construction Agreement or Mandatory Services Agreement; “Connect and Manage the arrangements whereby pursuant to Standard Condition C11 of Arrangements” the ESO Licence and Standard Condition D16 of a Relevant Transmission Licensee’s transmission licence connection to and or use of the National Electricity Transmission System is permitted by virtue of a Connect and Manage Derogation on completion of the Enabling Works but prior to completion of the Wider Transmission Reinforcement Works; “Connect and Manage the temporary derogation from the NETS SQSS available to The Derogation” Company pursuant to Standard Condition E7 of the ESO Licence and/or a Relevant Transmission Licensee pursuant to Standard Condition D3 of its transmission licence; “Connect and Manage the criteria detailed as such in CUSC Section 13.2.4; Derogation Criteria” “Connect and Manage the report required to be prepared by The Company and/or a Derogation Report” Relevant Transmission Licensee in respect of a Connect and Manage Derogation; “Connect and Manage the date which the Secretary of State determines shall be the Implementation Date” connect and manage implementation date; “Connect and Manage a Power Station which is directly connected to the National Power Station” Electricity Transmission System or which is Distributed Generation; “Connect and Manage the period ending 6 months after the Connect and Manage Transition Period” Implementation Date; "Connected Planning in relation to a particular user, as defined in its Construction Data" Agreement; "Connection" a direct connection to the National Electricity Transmission System by a User; "Connection an application for a New Connection Site in the form or Application" substantially in the form set out in Exhibit B to the CUSC; “Connection shall be the boundary defined by Paragraph 14.2.6 of the Boundary” Statement of the Connection Charging Methodology; "Connection Charges" charges made or levied or to be made or levied for the carrying out (whether before or after the date on which the ESO Licence comes into force) of works and provision and installation of electrical plant, electric lines and ancillary meters in constructing entry and exit points on the National Electricity Transmission System, together with charges in respect of maintenance and repair of such items in so far as not otherwise recoverable as Use of System Charges, all as more fully described in the ESO Licence, whether or not such charges are annualised, including all charges provided for in the statement of Connection Charging Methodology (such as Termination Amounts and One-off Charges); "Connection Charging as defined in the ESO Licence and set out in Section 14; Methodology" "Connection that portion of the Grid Code which is identified as the Connection Conditions" or "CC" Conditions; "Connection Entry the figure specified as such for the Connection Site and each Capacity" Generating Units as set out in Appendix C of the relevant Bilateral Connection Agreement; "Connection Offer" an offer or (where appropriate) the offers for a New Connection Site in the form or substantially in the form set out in Exhibit C including any revision or extension of such offer or offers; "Connection Site" each location more particularly described in the relevant Bilateral Agreement at which a User's Equipment and Transmission Connection Assets required to connect that User to the National Electricity Transmission System are situated (or, in the case of OTSDUW Build, each location that will become such from the OTSUA Transfer Time and, until the OTSUA Transfer Time, is the location where the User’s Equipment connects to the OTSUA). If two or more Users own or operate Plant and Apparatus which is connected at any particular location that location shall constitute two (or the appropriate number of) Connection Sites; "Connection Site the capability of a Connection Site to take power to the maximum Demand Capability" level forecast by the User from time to time and forming part of the Forecast Data supplied to The Company pursuant to the Grid Code together with such margin as The Company shall in its reasonable opinion consider necessary having regard to The Company’s duties under the ESO Licence; “Connections Network the methodology developed or to be developed in accordance with Design Methodology” the ESO Licence and Transmission Licences as approved by the Authority and published on The Company’s Website as such methodology may be revised from time to time; "Consents" in relation to a particular User, as defined in its Construction Agreement; In relation to any Works:- a) all such planning and other statutory consents; and b) all wayleaves, easements, rights over or interests in land or any other consent; or for commencement and carrying on of any activity proposed to be undertaken at or from such Works when completed c) permission of any kind as shall be necessary for the construction of the Works; "Construction an agreement entered into pursuant to Paragraph 1.3.2; Agreement" "Construction in relation to a particular User, as defined in its Construction Programme" Agreement; “Construction those User Progression Milestones categorised as such in Progression CUSC Section 16; Milestones” "Construction Works" In relation to a particular User, as defined in its Construction Agreement; “Consumer the person appointed by the Citizens Advice or the Citizens Representative” Advice Scotland (or any successor body) representing all categories of customers, appointed in accordance with Paragraph 8.4.2(b); “Consumption” as defined in the Balancing and Settlement Code in relation to a Consumption BM Unit; "Control Telephony" as defined in the Grid Code; "Contract Test" a test (not being a Reactive Test) described in a Market Agreement; "Contract Start Days" as defined in Paragraph 3.3 of Schedule 3, Part I; "Core Industry as defined in the Transmission Licence; Documents" "Core Industry in relation to a Core Industry Document, the body(ies) or Document Owner" entity(ies) responsible for the management and operation of procedures for making changes to such document; "Corporate Functions any person who is: Person"
a director of The Company; or
an employee of The Company or any of its subsidiaries carrying out any administrative, finance or other corporate services of any kind which in part relate to the Main Business; or
engaged as an agent of or adviser to or performs work in relation to or services for the Main Business; “Cost Adjustment” a payment whose value and timing has been approved by the Authority and which is made by a Licensed Distribution Network Operator as a contribution to the cost of a Transmission infrastructure investment made by a Licensed Transmission Owner that recognises the shared value to the different parties; "Cost Statement" as defined in Paragraph 2.14.3; "Credit Assessment a score between zero and ten given by an Approved Agency in Score" the Independent Credit Assessment; "Credit Assessment the proportion of the Unsecured Credit Cover extended by The Sum" Company to a User who does not meet the Approved Credit Rating and calculated in accordance with Paragraph 3.26.6; "Credit Rating" the credit requirements set by The Company from time to time in relation to Termination Amounts; "CUSC" this Connection and Use of System Code; "CUSC Framework as defined in the Transmission Licence; Agreement" "CUSC Implementation 00.01 on the 18 September 2001; Date" "CUSC Modification a proposal to modify the CUSC which is raised pursuant to Fast Track Proposal" Paragraph 8.29 and has not yet been approved or rejected by the CUSC Modifications Panel; “CUSC Modification a report prepared pursuant to Paragraph 8.29; Fast Track Report” "CUSC Modification the procedures for the modification of the CUSC (including the Procedures" implementation of Approved CUSC Modifications) as set out in Section 8; "CUSC Modification the part of the CUSC Modification Procedures relating to Process" consideration by the CUSC Modifications Panel and Workgroups, consultation by the Workgroups and The Company and preparation of a CUSC Modification Report by the CUSC Modifications Panel; "CUSC Modification a proposal to modify the CUSC which is not rejected pursuant to Proposal" Paragraphs 8.16.5 or 8.16.6 and has not yet been implemented; "CUSC Modification as defined in Paragraph 8.13.1; Register" "CUSC Modification a report prepared pursuant to Paragraph 8.23; Report" “CUSC Modification a report prepared pursuant to Paragraph 8.25; Self-Governance Report” "CUSC Modifications the body established and maintained pursuant to Paragraph 8.3; Panel" "CUSC Modifications the vote of Panel Members undertaken by the Panel Chairperson Panel in accordance with Paragraph 8.23.4 as to whether in their view Recommendation Vote" they believe each CUSC Modification Proposal, or Workgroup Alternative CUSC Modification would better facilitate achievement of the Applicable CUSC Objective(s) and so should be made; "CUSC Modifications the vote of Panel Members undertaken by the Panel Chairperson Panel Self-Governance in accordance with Paragraph 8.25.9 as to whether they believe Vote" each CUSC Modification Proposal, as compared with the then existing provisions of the CUSC and any Workgroup Alternative CUSC Modification set out in the CUSC Modification Self- Governance Report, would better facilitate achievement of the Applicable CUSC Objective(s); "CUSC Party" as defined in the ESO Licence; "Customer" a person to whom electrical power is provided (whether or not they are the provider of such electrical power) other than power to meet Station Demand of that person; “Customer Services the customer services team identified within The Company which Team” manages the commercial interface with parties connected to the transmission network, as identified on the Website; “CVA Storage Facility” is an Electricity Storage Facility that: i. performs Electricity Storage as its sole function; ii. is operated by a Storage Facility Operator iii. has its imports and exports measured only by Half Hourly Metering Systems which are registered in the Central Meter Registration Service (CMRS), and as a BM Unit within the Central Registration Service (CRS) and where those Half Hourly Metering Systems only measure activities necessary for performing Electricity Storage; iv. comprises plant and apparatus registered as part of a BM Unit or BM Units which only perform activities necessary for Electricity Storage, and the BM Units are listed within a bi-lateral agreement; and v. is the subject of a valid Declaration “DC Converter” as defined in the Grid Code; "Data Registration the portion of the Grid Code which is identified as the Data Code" or "DRC" Registration Code; “DCLF” Direct Current Load Flow; “Declaration” is a statement to be submitted by the Registrant of the relevant BM Unit(s) or Single Site; "Deemed HH the sum calculated in accordance with Section 3, Appendix 2 Forecasting Paragraph 3 as it may be revised in accordance with paragraph Performance" 3.22.7; "Deemed NHH the sum calculated in accordance with Section 3, Appendix 2 Forecasting Paragraph 6 as it may be revised pursuant to Paragraph 3.22.8; Performance" "Deenergisation" or the movement of any isolator, breaker or switch or the removal of "Deenergise(d)" any fuse whereby no electricity can flow to or from the relevant System through the User's Equipment; "Defaulting Party" as defined in Paragraph 4.3.2.11; "Defendant Party" as defined in Paragraph 7.5.1; “Delivering” as defined in the Balancing and Settlement Code; “Delivery Body” the person designated as the delivery body pursuant to regulations made under section 6BB of the Act; "De-Load" the difference (expressed in MW) between the Maximum Export Limit and Final Physical Notification Data as adjusted by the Acceptance Volume in respect of a Bid-Offer Acceptance (if any), and “De-Loaded” shall be construed accordingly; except in the case of a Power Park Module, where De-Load is the difference (expressed in MW) between Power Available and the Final Physical Notification Data as adjusted by the Acceptance Volume in respect of a Bid-Offer Acceptance (if any), and “De- Loaded” shall be construed accordingly; "Demand" the demand of MW and Mvar of electricity (i.e. both Active Power and Reactive Power), unless otherwise stated; "Demand Forecast" a User’s forecast, in accordance with paragraph 14.17.19. of its Demand submitted to The Company in accordance with paragraphs 3.10, 3.11 and 3.12; “Depreciation Period” in relation to a Transmission Connection Asset for a particular User, the period which commences on the asset’s initial effective charging date, and which expires after the appropriate duration, which unless otherwise agreed upon connection is 40 years excluding FMS metering electronics that are agreed between the User and The Company; "Derogation" (a) a direction issued by the Authority relieving a CUSC Party from the obligation under its Licence to comply with such parts of the Grid Code or any Distribution Code or in the case of The Company the ESO Licence as may be specified in such direction and/or
a Connect and Manage Derogation as the context requires and “Derogated” shall be construed accordingly; "Derogated Plant" Plant or Apparatus which is the subject of a Derogation; "Design Variation" is a connection design (which provides for connection to the National Electricity Transmission System) which fails to satisfy the relevant deterministic criteria detailed for an Onshore Connection in paragraphs 2.5 to 2.13 and for an Offshore Connection in 7.7 to 7.19, as appropriate, of the NETS SQSS; “Designated as defined in the Grid Code; Information Exchange System” “Designated Sum” such sum as shall be directed by the Authority as soon as practicable after the determination of an approved Use of System Charging Methodology; “Designated sum” as defined in Standard Condition C13 of the Transmission Licence; "De-synchronisation" the act of taking a BM Unit off a System to which it has been Synchronised, by opening any connecting circuit breaker, and "De-synchronised" shall be construed accordingly; "Detailed Planning detailed additional data which The Company requires under the Data" PC in support of Standard Planning Data; “Developer” in the context of the connection agreements between The Company and the owner/operator of a Distribution System where those agreements or Modifications to those agreements are triggered by Embedded Power Stations means the developer of the Embedded Power Station as more particularly described in those agreements; “Developer Capacity” the MW figure as specified as such by a User in a BELLA or in a Construction Agreement entered into between The Company and a User in the category of a Distribution System directly connected to the National Electricity Transmission System as a consequence of a Request for a Statement of Works; "Directive" includes any present or future directive, requirement, instruction, direction or rule of any Competent Authority, (but only, if not having the force of law, if compliance with the Directive is in accordance with the general practice of persons to whom the Directive is addressed) and includes any modification, extension or replacement thereof then in force; “Directly-Connected A large, usually industrial, consumer of electricity who is directly User” or “Directly- connected to the National Electricity Transmission System; Connected Customer” "Disconnect" or without prejudice to the interpretation of the terms "Disconnect" or "Disconnection" "Disconnection" to Users acting in capacities other than those detailed, the following definitions shall apply:
for Users acting in their capacity as Generators with Embedded Large Power Stations or Embedded Medium Power Stations, passing power on to a Distribution System through a connection to a Distribution System which had not been commissioned as at the Transfer Date, means permanent physical disconnection of the User's Equipment at the site of connection to the Distribution System;
for Users who are Trading Parties (as defined in the Balancing and Settlement Code) acting in their capacity as responsible for Small Power Stations which are Embedded, means, permanent physical disconnection of the User’s Equipment or Equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) at the site of connection to the Distribution System;
for Users acting in a capacity other than those detailed in (a) or (b), means permanent physical disconnection of a User's Equipment at any given Connection Site which permits removal thereof from the Connection Site or removal of all Transmission Connection Assets there from (as the case may be); "Dispute Resolution the procedures set out in Section 7; Procedure" "Dispute Statement" as defined in Paragraph 3.17.4; “Distributed for the purposes of the Connect and Manage Arrangements, Generation” Section 6 and Section 15 of the CUSC:
(a) an Embedded Power Station which is the subject of a Bilateral Embedded Generation Agreement;
an Embedded Power Station which is the subject of a Bilateral Embedded Licence Exemptable Large Power Station Agreement;
a Relevant Embedded Medium Power Station;
a Relevant Embedded Small Power Station. "Distribution an agreement entered into by a User with the owner/operator of Agreement" the Distribution System for the connection of the User’s Equipment (or equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code) to and use of such Distribution System; "Distribution Code(s)" the Distribution Code(s) drawn up by Public Distribution System Operators pursuant to the terms of their respective Licence(s) as from time to time revised in accordance with those Licences; "Distribution in the context of the Distribution Queue Management Process Connection and the User Commitment Methodology means, as appropriate, Agreement" the agreements between the owner/operator of a Distribution System and (a) a User for the connection of a User’s project to that Distribution System or (b) a developer for the connection of it’s project to the Distribution System; “Distribution the Distribution Connection and Use of System Agreement Connection and Use of established pursuant to the Distribution Licence as revised from System Agreement or time to time; “DCUSA” “Distribution EG a Connection Application or Modification Application made by Related Application” the owner/operator of a Distribution System where triggered by Embedded Power Stations (and including in this context a Transmission Evaluation Application); "Distribution as defined in the Balancing and Settlement Code; Interconnector" "Distribution the Owner of a Distribution Interconnector or of that part of a Interconnector Owner" Distribution Interconnector directly connected to a Distribution System; "Distribution Licence" a licence issued under section 6(1)(c) of the Act; “Distribution Queue the queue management process adopted by the owner/operator of Management Process” a Distribution System in respect of connections to the Distribution System; "Distribution System" the system consisting (wholly or mainly) of electric lines owned or operated by any Authorised Electricity Operator and used for the distribution of electricity from Grid Supply Points or generation sets or other entry points to the point of delivery to Customers or Authorised Electricity Operators, and includes any Remote Transmission Assets operated by such Authorised Electricity Operator and any electrical plant and meters owned or operated by the Authorised Electricity Operator in connection with the distribution of electricity, but shall not include any part of the National Electricity Transmission System; “Distribution Voltage” a voltage of 132kV or below in England & Wales. A voltage of below 132kV in Scotland. Generally taken to be voltages lower than those defined as transmission voltages; “Demand Voting Sub- all User(s) in a Voting Group who fall within any one or more of Group” the following categories:
Directly Connected Users with a Bilateral Agreement; and
a User with a Bilateral Agreement in respect of a Distribution System; "Dormant CUSC Party" a CUSC Party which does not enjoy any ongoing rights and/or obligations for the period of its dormancy under the CUSC, as provided for in Section 5; “Downstream Party” a third party connected to a Non-Embedded Customer’s System; “EA Cut Off Date” 23:59 on the date before the CMP435 Implementation Date being the date which determines what are categorised as Existing Agreements for a Project for the purposes of this Section 18; "EA Gated Design the one off design process run by The Company in accordance Process” with the Gated Process for Projects with Existing Agreements starting and finishing on the dates for this as set out in the EA Timetable; “EA Request” a request by a User under Paragraph 18.8 for Existing Agreements for a Project to be given the status of Gate 2 Existing Agreements; “EA Request Window” the period of time determined by The Company in accordance with the Gated Process for Projects with Existing Agreements starting and finishing on the dates for this as set out in the EA Timetable with the start date not being less than 4 weeks from the CMP435 Implementation Date and the duration being not less 2 weeks; "EA Timetable” the timetable setting out the timings (start and end dates and durations) of the various stages of the Gated Process for Projects with Existing Agreements; "Earthing" as defined in the Grid Code; “EBR Amendment” (a) any amendment to contractual arrangements for the provision of and payment for Balancing Services referred to in Section 4.2B5 or
any amendment to CUSC which amends the EBR Article 18 Terms or Conditions in, as the case may be, such contractual arrangements or CUSC including to introduce a new provision for the purposes of Article 18 into, as the case may be, such contractual arrangements or CUSC; “EBR Article 18 Terms terms and conditions which have been approved by the Authority and Conditions pursuant to and for the purposes of Article 18 of the Electricity Balancing Regulation. In the context of CUSC these terms and conditions are identified for convenience in CUSC Exhibit Y as such Exhibit Y is amended from time to time; "EdF Documents" as defined in the Balancing and Settlement Code; “Effective” an EA Request is effective when in the opinion of The Company acting reasonably the EA Request meets the requirements at Paragraph 18.8; "Election Timetable" as defined in Paragraph 8A.1.2.1; "Election Year" as defined in Paragraph 8A.1.1.2; “Electricity Balancing the English version of Commission Regulation (EU) 2017/2195 Regulation” as converted into Assimilated Law; “Electricity the process of generating electricity by a Generator; Generation” “Electricity Generation is a facility where Electricity Generation occurs as its sole Facility” function. “Electricity Regulation” the English version of Commission Regulation (EU) 2019/943 (being the recast of (EU) 714/2009) as converted into Assimilated Law; “Electricity Storage” is the conversion of electrical energy into a form of energy which can be stored, the storing of that energy, and the subsequent reconversion of that energy back into electrical energy; “Electricity Storage is a facility where Electricity Storage occurs; Facility” “Electricity System a licence granted or treated as granted under section 6(1)(da) of Operator Licence” or the Electricity Act 1989; “ESO Licence” “Electricity Ten Year as defined in the Grid Code; Statement (ETYS)” “Electricity the English version of Commission Regulation (EU) 2017/1485 as Transmission System converted into Assimilated Law; Operation Regulation” “Electronic as defined in the Grid Code; Communication Platform” “Eligible Services” any Balancing Service or Ancillary Service which imports or exports Reactive Energy but does not result in the production or export of any Active Power to the NETS; “Eligible Services for the purposes of CUSC Section 14 shall mean a Single Site that Facility” can only and solely provide Eligible Services to The Company and does not undertake Electricity Storage or Electricity Generation or consume any Active Power other than for the provision of the Eligible Services; "Embedded" a direct connection to a Distribution System or the System of any other User to which Customers and/or Power Stations are connected; in the context of the Charging Methodologies it shall mean a direct connection to a Distribution System or the System of any other User to which Customers and/or Power Stations are connected, such connection being either a direct connection or a connection via a busbar of another User or of a Relevant Transmission Licensee (but with no other connection to the National Electricity Transmission System); "Embedded Generator the Register set up by The Company pursuant to Paragraph 6.35; MW Register" "Emergency an instruction issued by The Company to a User to either: Deenergisation (a) Deenergise that User’s Equipment, or Instruction"
request the owner of the Distribution System to which the User’s Equipment or equipment for which that User is responsible (as defined in Section K of the Balancing and Settlement Code) is connected to Deenergise that User’s Equipment or equipment for which that User is responsible (as defined in Section K of the Balancing and Settlement Code or ;
declare its Maximum Export Limit in respect of the BM Unit(s) associated with such User’s Equipment to zero and to maintain it at that level during the Interruption Period, where in The Company’s reasonable opinion:
the condition or manner of operation of any Transmission Plant and/or Apparatus is such that it may cause damage or injury to any person or to the National Electricity Transmission System; and
if the User’s Equipment connected to such Transmission Plant and/or Apparatus was not Deeenergised and/or the Maximum Export Limit of such User’s Equipment connected to such Transmission Plant and/or Apparatus was not reduced to zero then it is likely that the Transmission Plant and/or Apparatus would automatically trip; and
if such Transmission Plant and/or Apparatus had tripped automatically, then
the BM Unit comprised in such User’s Equipment (other than an Interconnector Owner); or
an Interconnector of an Affected User who is an Interconnector Owner, would, solely as a result of Deenergisation of Plant and Apparatus forming part of the National Electricity Transmission System, have been Deenergised; "Emergency as defined in the Grid Code; Instruction" “EMR Documents” The Energy Act 2013, The Electricity Capacity Regulations 2014, the Capacity Market Rules, The Contracts for Difference (Allocation) Regulations 2014, The Contracts for Difference (Definition of Eligible Generator) Regulations 2014, The Contracts for Difference (Electricity Supplier Obligations) Regulations 2014, The Electricity Market Reform (General) Regulations 2014, the AF Rules and any other regulations or instruments made under Chapter 2 (contracts for difference), Chapter 3 (capacity market) or Chapter 4 (investment contracts) of Part 2 of the Energy Act 2013 which are in force from time to time; “EMR Functions” has the meaning given to “EMR functions” in Chapter 5 of Part 2 of the Energy Act 2013; “Enabling Works” those elements of the Transmission Reinforcement Works identified as such in accordance with CUSC Section 13 and which in relation to a particular User are as specified and by its acceptance of the Offer or Modification Offer, agreed by the User in the relevant Construction Agreement; "End Date" shall mean 5.00pm on the date 12 months from (and not including) the Security Amendment Implementation Date; "Energisation" or the movement of any isolator, breaker or switch or the insertion of "Energise(d)" any fuse so as to enable Energy to flow from and to the relevant System through the User's Equipment (and in the case of OTSDUW Build, the OTSUA prior to the OTSUA Transfer Time); "Energy" the electrical energy produced, flowing or supplied by an electric circuit during a time interval, being the integral with respect to time of the power, measured in units of watt-hours or standard multiples thereof i.e. 1000 Wh = 1KWh 1000 KWh = 1MWh 1000 MWh = 1GWh 1000 GWh = 1TWh; “Energy Density the tables of this name set out in the section of the LoA Guidance Tables” dealing with Connection Applications for a New Connection Site Onshore as such tables may be updated by The Company from time to time but where any changes will not be made without prior engagement with industry; "Energy Metering as the phrase "Metering Equipment" is defined in the Balancing Equipment" and Settlement Code; "Energy Metering as the phrase "Metering System" is defined in the Balancing and System" Settlement Code; "Enforceable" The Company (acting reasonably) is satisfied that the security is legally enforceable and in this respect the User shall obtain such legal opinion at its expense as The Company (acting reasonably shall require); “Engineering Charge” as set out in the Statement of Use of System Charges from time to time; "Enhanced Reactive as defined in Paragraph 1.2 of Schedule 3, Part I; Power Service" "Enhanced Rate" in respect of any day the rate per annum which is 4% per annum above the Base Rate; “Equivalent Unmetered as defined in the Balancing and Settlement Code; Supply” "Escrow Account" a bank account in the name of The Company at such branch of Barclays Bank PLC or such branch of any other bank, in the City of London as is notified by The Company to the User in which deposits of principal sums from the User shall be ascertainable, bearing interest from (and including) the date of deposit of principal sums to (but excluding) the date of withdrawal of principal sums from such account, mandated for withdrawal of any sums solely by The Company and mandated for the transfer of any interest accrued to such account to: a) an associated bank account in the name of The Company in which the interest accruing in respect of the principal sums deposited by the User shall be ascertainable; or b) such bank account as the User may specify; "Estimated Demand" the forecast Demand (Active Power) data filed with The Company pursuant to the Charging Statements; "ET Interface Operator" the operator of the Onshore Distribution System to which an ET Offshore Transmission System connects; “ET Interface Point” the electrical point of connection between an Offshore Transmission System and an Onshore Distribution System and in relation to a particular User as defined in its Bilateral Connection Agreement; “ET Offshore an Offshore Transmission System connected at an ET Interface Transmission System” Point; "ET Restrictions on is in the context of an ET Offshore Transmission System the Availability" reduction in capability as set out in the relevant Notification of ET Restrictions on Availability; "ET Use of System the element of Use of System Charges consisting of charges Charges" payable by The Company to the ET Interface Operator in respect of the connection to a Distribution System by an Offshore Transmission System and use of such Distribution System by means of such Offshore Transmission System; “European the institution of that name established under The Treaty on Commission” European Union as amended from time to time; “Evaluation of The process undertaken by The Company to understand the effect Transmission Impact” of a Relevant Embedded Power Station on the National Electricity Transmission System; "Event" as defined in the Grid Code; "Event of Default" any of the events set out in Section 5 as constituting an event of default; “Excepted Works” any Construction Works which have been designated as “onshore transmission (reinforcement)” by the Authority, either in its decision of 19 October 2022 titled ‘Offshore Transmission Network Review: Decision on asset classification’ included in The Company’s ‘Pathway to 2030 (Holistic Network Design)’ report published in July 2022 or in any decisions by the Authority on the classification of assets included in The Company’s ‘Beyond 2030’ report published in March 2024, or otherwise so designated by the Authority; "Exchange Rate" the Transmission Entry Capacity available to a specific party as a direct result of a specific reduction in the Transmission Entry Capacity available to another party; "Exchange Rate a joint request from a User and another User to calculate the Request" Exchange Rate that would apply were they to agree to a TEC Trade; "Excitation System" the equipment providing the field current of a machine, including all regulating and control elements as well as field discharge or suppression equipment and protective devices; "Exemptable" where the person generating electricity at the relevant Power Station is, or would be (if it generated electricity at no other Power Station and/or did not hold a Generation Licence) exempt from the requirement to hold a Generation Licence under the Act; “Exempt Export BM as defined in the Balancing and Settlement Code; Unit” “Exempt Generator” any generator who, under the terms of the Electricity (Class Exemptions from the Requirement for a Licence) Order 2001, is not obliged to hold a generation licence; “Exemptible generating plant where the party generating electricity at that Generation” generating plant is, or would (if it generated electricity at no other generating plant and/or did not hold a generation licence) be, exempt from the requirement to hold a generation licence (including Scottish generation that export between 50 and 100MW that was connected on or before 30 September 2000); "Exempt Power a Power Station where the person generating electricity at that Station" Power Station is exempt from the requirement to hold a Generation Licence under the Act; “Existing Agreements” the agreements of the type determined according to Paragraph 18.5; “Existing ICM a Construction Agreement entered into between The Company Construction and a User prior to the Connect and Manage Implementation Agreement” Date and which is on the basis of the Interim Connect and Manage Arrangements; “Existing Offshore any Bilateral Connection Agreement and Construction Agreement” Agreement entered into under the OTSDUW Arrangements and where the User is undertaking OTSDUW Build on or before the OTSUA Commissioning Period Effective Date; “Existing Offshore as defined in the Transmission Licence; Generator” "Existing Security the Security Cover held by The Company in respect of a User Cover" pursuant to CUSC Section 3 Part III immediately prior to the Security Amendment Implementation Date; “Export” as defined in the Balancing and Settlement Code; “Export BM Unit” a BM Unit registered in accordance with Section K of the BSC in respect of Export; “Export Capacity” for the purpose of paragraph 6.5.1(f) Export Capacity is the maximum continuous Active Power expressed in MW which is permitted to flow from a Power Station to a Distribution System; “Ex-Post the charge or credit to Demand and Generator Users in respect of Reconciliation” TNUoS charges in the event of a breach of the Limiting Regulation; "External as defined in the Grid Code; Interconnection" "Externally as defined in the Grid Code; Interconnected System Operator" “Fast Track Criteria” a CUSC Modification Proposal that, if implemented,
would meet the Self-Governance Criteria; and
is properly a housekeeping modification required as a result of some error or factual change, including but not limited to:
updating names or addresses listed in the CUSC;
correcting any minor typographical errors;
correcting formatting and consistency errors, such as paragraph numbering; or
updating out of date references to other documents or paragraphs. “FDSC” shall mean the same as Final Demand Site Count; “FDSC Base the % value for the relevant Security Period as specified in the Percentage” table in paragraph 2A of Section 3, Appendix 2; “FDSC Base Value at the sum as calculated in accordance with Paragraph 3.23.4a; Risk” “FDSC Charges” that element of Transmission Network Use of System Demand Charges relating to Final Demand Site Count; “FDSC Forecast” the forecast, produced by The Company, of the FDSC; "Final Adjustments as defined in Paragraph 4.3.2.6(b); Statement” “Final Demand” electricity which is consumed other than for the purposes of generation or export onto the electricity network; "Final Demand as defined in Paragraph 3.13.7(a); Reconciliation Statement" “Final Demand Site” Shall mean;
For Users with a Bilateral Connection Agreement, a Single Site which has associated Final Demand, except Single Sites which are for; a. Users who own or operate a Distribution System, or b. Interconnector Users, or c. Users of a Non-Final Demand Site with a valid Declaration
For Users with a Bilateral Embedded Generation Agreement or BELLA, as defined as ‘Final Demand Site’ in the DCUSA except Non-Final Demand Site with a valid Declaration For all other parties, as defined as ‘Final Demand Site’ in the DCUSA; “Final Demand Site a count of individual Final Demand Sites for each Charging Count or FDSC” Band; "Final Monthly as defined in Paragraph 4.3.2.6; Statement" "Final Reconciliation as defined in the Balancing and Settlement Code; Settlement Run" "Final Reconciliation as defined in the Balancing and Settlement Code; Volume Allocation Run" "Final Physical as defined in the Balancing and Settlement Code; Notification Data" "Final Statement" as defined in Paragraph 4.3.2.6(a); "Final Sums" in relation to a particular User, as defined in its Construction Agreement; "Financial Year" the period of 12 months ending on 31st March in each calendar year; “First Gated the first run of the Gated Application Window and Offer Process Application Window following the CMP434 Implementation Date; and Offer Run” "First Offer" as defined in Paragraph 6.10.4; “First Security Period” from the date of Construction Agreement to the 31 March or 30 September, whichever is the first to occur; "First User" as defined in Paragraph 6.10.3; “Fixed Attributable where the Attributable Works Cancellation Charge is Works Cancellation calculated in accordance with Paragraph 3.5.1 of Part TWO of the Charge” User Commitment Methodology; “Fixed BSUoS Price” the volumetric fixed price (in £/MWh) for BSUoS Charges calculated and published by The Company for each Fixed Price Period; “Fixed Price Period” the period of time during which the Fixed BSUoS Price applies. Each Fixed Price Period shall apply for 12 months, from 1st April to 31st March, comprising:
the Spring Summer Tariff (1st April to 30th September); and
the Autumn Winter Tariff (1st October to 31st March). “Fixed Proposed the proposed date(s) for the implementation of a CUSC Implementation Date” Modification Proposal or Workgroup Alternative CUSC Modification such date to be a specific date by reference to an assumed date by which a direction from the Authority approving the CUSC Modification Proposal or Workgroup Alternative CUSC Modification is required in order for the CUSC Modification Proposal or any Workgroup Alternative CUSC Modification, if it were approved, to be implemented by the proposed date; "FMS Date" 1st April 1993; "Force Majeure" in relation to any CUSC Party any event or circumstance which is beyond the reasonable control of such CUSC Party and which results in or causes the failure of that CUSC Party to perform any of its obligations under the CUSC including act of God, strike, lockout or other industrial disturbance, act of the public enemy, war declared or undeclared, threat of war, terrorist act, blockade, revolution, riot, insurrection, civil commotion, public demonstration, sabotage, act of vandalism, lightning, fire, storm, flood, earthquake, accumulation of snow or ice, lack of water arising from weather or environmental problems, explosion, fault or failure of Plant and Apparatus (which could not have been prevented by Good Industry Practice), governmental restraint, Act of Parliament, other legislation, bye law and Directive (not being any order, regulation or direction under section 32, 33, 34 and 35 of the Act) provided that lack of funds shall not be interpreted as a cause beyond the reasonable control of that CUSC Party and provided, for the avoidance of doubt, that weather conditions which are reasonably to be expected at the location of the event or circumstance are also excluded as not being beyond the reasonable control of that CUSC Party; "Forecasting the sum of HH Forecasting Performance Related VAR and NHH Performance Related Forecasting Performance Related VAR; VAR " "Frequency" the number of alternating current cycles per second (expressed in Hertz) at which a System is running; "Frequency Deviation" a positive or negative deviation from Target Frequency; "Frequency Response" an automatic response by a BM Unit or CCGT Unit to a change in Frequency with the aim of containing System Frequency within the limits provided for under the Grid Code; "Frequency Sensitive as defined in the Grid Code; Mode" "Fuel Security Code" the document of that title designated as such by the Secretary of State as from time to time amended; "Full TEC Reduction one Financial Year and 5 Business Days prior to the beginning Notice Period" of the Financial Year from which the decrease in Transmission Entry Capacity or Disconnection (as appropriate) is to take effect; “Gas Insulated SF6 switchgear where the substation busbars (and the interfacing Switchgear” or “GIS” switchgear between those busbars and any connecting circuits) are of an integrated metal enclosed, gas insulated construction; "Gas Turbine Unit" a Generating Unit driven by a gas turbine (for instance an aero- engine); “Gas System Planner a licence granted or treated as granted under section 7AA(1) of the Licence” or “GSP Gas Act 1986; Licence” “Gate 1 Agreements” the (a) agreements (including, as required, the Bilateral Agreement) entered into between the Gated Applicant and The Company on acceptance of a Gate 1 Offer and (b) the Gate 1 Existing Agreements; “Gate 1 Application” an application for a Gate 1 Offer; “Gate 1 ATV” the Agreement to Vary issued by The Company to the User in respect of Existing Agreements for a Project in accordance with Paragraph 18.13; “Gate 1 Conditional the clause included in a Gate 1 Offer making the Gate 1 Clause” Agreements conditional until a Gate 2 Offer is accepted and in the Gate 1 ATV making the Gate 1 Existing Agreements conditional until a Gate 2 Offer is accepted; “Gate 1 Existing the Existing Agreements for a Project (as amended by the Gate Agreements” 1 ATV) on the execution of the Gate 1 ATV; “Gate 1 Offer” the offer made by The Company to a Gated Applicant in response to a Gate 1 Application; “Gate 1 Notification” a notification in writing by a User to The Company that it does not intend to submit an EA Request in respect of Existing Agreements for a Project; “Gate 2 Agreements” the (a) agreements (including, as required, the Bilateral Agreement) entered into between the Gated Applicant and The Company on acceptance of a Gate 2 Offer; and (b) the Gate 2 Existing Agreements; “Gate 2 Application” an application for a Gate 2 Offer; “Gate 2 Criteria” the criteria which a Gate 2 Application and EA Request has to meet as set out in the Gate 2 Criteria Methodology; “Gate 2 Criteria the methodology developed or to be developed by The Company Methodology” in accordance with the ESO Licence and approved by the Authority and published by The Company on the Website as such methodology may be revised from time to time; “Gate 2 Existing the Existing Agreements for a Project (as amended by the Gate Agreements” 2 Modification Offer) on the acceptance of the Gate 2 Modification Offer; “Gate 2 Offer” the offer made by The Company to a Gated Applicant in response to a Gate 2 Application; “Gate 2 Modification the Modification Offer made by The Company to the User in Offer” respect of Existing Agreements for a Project in accordance with Paragraph 18.14 above; “Gated Agreements” the Gate 1 Agreements or Gate 2 Agreements as appropriate; “Gated Applicant” an applicant for a Gated Application; “Gated Application” an application of a type referred to as such in Section 17; “Gated Application and the process as set out in Section 17; Offer Process” “Gated Application as generally defined in the Gated Application and Offer Process Window” with the specific timing for such specified in the relevant Gated Application Window and Offer Run; “Gated Application the First Gated Application Window and Offer Run and each Window and Offer Run” subsequent run of the Gated Application Window and Offer Process opened by The Company; “Gated Design as generally defined in the Gated Application and Offer Process Process” with the specific timing for such specified in the relevant Gated Application Window and Offer Run; “Gated Modification” a Modification of a type specified as such in the Gated Modification Guidance; “Gated Modification a Modification Application for a Gated Modification; Application” “Gated Modification the guidance (as it may be amended from time to time) published Guidance” by The Company on the type of Modifications that The Company will treat as being Gated Modification Applications; “Gated Modification a Modification Offer made by The Company in response to a Offer” Gated Modification Application; “Gated Offers” offers made by The Company in response to a Gated Application; “Gated Process for the process as set out in CUSC Section 18; Projects with Existing Agreements” “Gated Timetable” the timetable for each Gated Application Window and Offer Run setting out the timings (start and end dates and durations) of the various stages in the Gated Application Window and Offer Run as published by The Company on the Website. In each Gated Application Window and Offer Run, the Gated Application Window shall open no earlier than 4 weeks after the publication of the timetable (and in the case of the First Gated Application Window and Offer Run, with publication being no earlier than 4 weeks after the CMP434 Implementation Date) and shall be of a duration not less than 4 weeks; “GB Transmission for the purposes of Section 12 means the system consisting (wholly System” or “GBTS” or mainly) of high voltage electric wires owned or operated by transmission licensees within Great Britain and used for the transmission of electricity from one Power Station to a sub-station or to another Power Station or between sub-stations or to or from any External Interconnection and includes any Plant and Apparatus or meters owned or operated by any transmission licensee within Great Britain in connection with the transmission of electricity but shall not include Remote Transmission Assets; "Generating Plant" a Large Power Station; "Generating Unit" unless otherwise provided in the Grid Code any Apparatus which produces electricity; "Generation Capacity" the normal full load capacity of a Generating Unit as declared by the Generator, less the MW consumed by the Generating Unit through the Generating Unit’s unit transformer when producing the same; "Generation Licence" the licence granted to a Generator pursuant to section 6(1)(a) of the Act; “Generation Licensee” A User who holds a Generation Licence "Generation as defined in Paragraph 3.12.2; Reconciliation Statement" “Generation Voting all User(s) in a Voting Group who fall within any one or more of Sub-Group” the following categories: 1) a User with a Bilateral Agreement in respect of a Directly Connected Power Station; 2) a User with a Bilateral Agreement in respect of an Embedded Exemptable Large Power Station; and 3) a User with a Bilateral Agreement in respect of an Embedded Power Station; "Generator" a person who generates electricity under licence or exemption under the Act; “Generator” As defined in the Grid Code "Genset" as defined in the Grid Code; “GIS Asset Outage as defined in the relevant Bilateral connection Agreement; "Good Industry in relation to any undertaking and any circumstances, the exercise Practice" of that degree of skill, diligence, prudence and foresight which would reasonably and ordinarily be expected from a skilled and experienced operator engaged in the same type of undertaking under the same or similar circumstances; "Great Britain" the landmass of England and Wales and Scotland, including internal waters; "Grid Code" the Grid Code drawn up pursuant to the ESO Licence, as from time to time revised; "Grid Supply Point" a point of delivery from the National Electricity Transmission (“GSP”) System to a Distribution System or a Non-Embedded Customer; "Gross Asset Value" the value calculated by The Company in accordance with recognised accounting principles and procedures as published by The Company from time to time; "Group" as defined in the Grid Code; “GSP Group” as defined in the Balancing and Settlement Code; "HH Base Percentage" the % value for the relevant Security Period as specified in the table in paragraph 1 of Section 3, Appendix 2; "HH Base Value at the sum as calculated in accordance with Paragraph 3.22.3; Risk" "HH Charges" that element of Transmission Network Use of System Demand Charges relating to half-hourly metered Demand; "HH Forecasting the amount resulting from multiplying the Deemed HH Performance Related Forecasting Performance and the Indicative Annual HH VAR " TNUoS Charge calculated on the basis of the latest Demand Forecast received by The Company; "High Frequency as defined in the Grid Code; Response" "High Voltage" or "HV" a voltage exceeding 650 volts; "Holding Payment" that component of the payment for Mode A Frequency Response calculated in accordance with Paragraph 4.1.3.9; “ICRP” Investment Cost Related Pricing; “Identified Onshore a single transmission HVDC subsea circuit or a single transmission Circuit” AC subsea circuit between two MITS Nodes where there is only one route for the power to flow between the two MITS Nodes; "Implementation Date" is the date and time for implementation of an Approved CUSC Modification as specified in accordance with Paragraph 8.28.3; “Import” as defined in the Balancing and Settlement Code; “Import BM Unit” a BM Unit registered in accordance with Section K of the BSC in respect of Import; "Indemnified Persons" as defined in Paragraph 8.12.1; "Independent in relation to a particular User, as defined in its Construction Engineer" Agreement; "Independent Credit an assessment of the creditworthiness of a User or entity by an Assessment" Approved Agency as nominated by the User or entity obtained in accordance with Paragraph 3.26.7, 3.26.8 and 3.26.9; "Independent Security a guarantee in favour of The Company in a form satisfactory to Arrangement" The Company and which is provided by an entity which meets the Requirements. In addition The Company may accept such a policy from an entity who does not meet the Requirements up to an Agreed Value where The Company agrees or where The Company does not agree as determined by an expert appointed by The Company and the User or failing their agreement as to the expert the expert nominated by the Director General of The Institute of Credit Management; “Indicative Annual The Company’s forecast of the User’s total FDSC Charges FDSC TNUoS charge relating to a Financial Year; "Indicative Annual HH The Company’s forecast of the User’s total HH Charges relating TNUoS charge" to a Financial Year; "Indicative Annual NHH The Company’s forecast of the User’s total NHH Charges TNUoS charge" relating to a Financial Year; “Indicative Annual The Company’s forecast of the User’s total UMS Charges UMS TNUoS charge” relating to a Financial Year; "Indicative Block is the Available LDTEC; LDTEC" "Indicative Maximum has the meaning attributed to it in Paragraph 4.2.3.2; Generation Capability" “Industry Code” a multilateral code or agreement created and maintained pursuant to a licence granted by the Authority under section 6 of the Act or under sections 7, 7ZA or 7A of the Gas Act 1986; “Information Request a notice that will be issued by The Company to a relevant party Notice” setting out The Company’s reasonable requirements for relevant information in accordance with section 172 of the Energy Act 2023. This will be prepared in accordance with The Company's published Information Request Statement; “Information Request a statement prepared and published by The Company, in Statement” accordance with section 172 of the Energy Act 2023 and condition D2.5 of the ESO Licence and GSP Licence, setting out the process that The Company will follow when requesting information from relevant parties by the issue of an Information Request Notice; "Initial Charge" as defined in Paragraph 3.16.2; "Initial Demand as defined in Paragraph 3.13.4; Reconciliation Statement" "Initial Volume as defined in the Balancing and Settlement Code; Allocation Run" “Initial Settlement Run” as defined in the Balancing and Settlement Code; “Insolvency shall mean any action or step taken: Proceedings”
for the administration, winding up, dissolution or bankruptcy of the Developer; or
for the appointment of a receiver or administrative receiver in respect of any of the Developer’s assets; or
for making a proposal to any of the Developer’s creditors with a view to avoiding insolvency; or
for the taking of possession by anyone with an interest in any asset of the Developer; or
any analogous procedure or step is taken in any jurisdiction in relation to any matter referred to in clause (a) to (d) (inclusive) above; “Installed Capacity” the figure, in the context of the Original Red Line Boundary only, being the intended maximum amount of Active Power that the, as appropriate, User’s Equipment or Developer’s Equipment sited within the Original Red Line Boundary would be capable of exporting and/or importing (independent of the Connection Entry Capacity and/or Transmission Entry Capacity and/or Developer Capacity, and any limitations to the maximum amount of Active Power related to such capacities) expressed in whole MW, or in MW to one decimal place as declared (for each technology type, if more than one) by the User on the Original Red Line Boundary; "Insurance a Performance Bond provided by a company in the business of Performance Bond" providing insurance which meets the Requirements. In addition The Company may accept such a policy from such a company who does not meet the Requirements up to an Agreed Value where The Company agrees or where The Company does not agree as determined by an expert appointed by The Company and the User or failing their agreement as to the expert the expert nominated by the Director General of The Institute of Credit Management; "Intellectual Property" patents, trade marks, service marks, rights in designs, trade or "IPRs" names, copyrights and topography rights (whether or not any of the same are registered and including applications for registration of any of the same) and rights under licences and consents in relation to any of the same and all rights or forms of protection of a similar nature or having equivalent or similar effect to any of the same which may subsist anywhere in the world; “Interactivity” where there are two or more applications for connection and/or use of system which would be using or connecting to the same part of the Total System which comprises the existing or future NETS and/or Distribution System where not all the applicants can be connected, Interactivity is the process that determines the queue position of the applications that can be connected with or without further changes to the network; “Interactivity Policy” the policy adopted by The Company for the purposes of managing Interactivity and published on its website as it may be amended from time to time; "Interconnected as defined in the Balancing and Settlement Code; System Operator" "Interconnector" as defined in the Balancing and Settlement Code; “Interconnector the payments (whether positive or negative) as notified by the Adjustment Payments” Interconnectors to The Company pursuant to the conditions in their respective licences for the purposes of the ESO Licence condition F3 Part C Pass-through (PTt); “Interconnector Asset the owner of an Interconnector; Owner” "Interconnector Error as defined in the Balancing and Settlement Code; Administrator" "Interconnector the owner of an Interconnector, or of that part of an Owner" Interconnector, directly connected to the National Electricity Transmission System; "Interconnector User" (a) in relation to an Interconnector connected to the National Electricity Transmission System, as defined in the Balancing and Settlement Code; and
in relation to a Distribution Interconnector, a Lead Party (as defined in the Balancing and Settlement Code) in respect of a single BM Unit where under Section K5 of the Balancing and Settlement Code the BM Unit has been allocated in relation to that Distribution Interconnector or if there is no such allocation, as defined in the Balancing and Settlement Code; “Interconnector User (a) for Interconnectors whose Connection Site is below the Commitment Capacity” B11 boundary as set out in the annual Electricity Ten Year Statement, this is the figure for the purposes of CUSC Paragraph 9.5 as specified in Appendix C of the User’s Bilateral Connection Agreement; and
for Interconnectors whose Connection Site is above the B11 boundary as set out in the annual Electricity Ten Year Statement, this is the figure for the purposes of CUSC Paragraph 9.4 as specified in Appendix C of the User’s Bilateral Connection Agreement; “Interconnector Voting all User(s) in a Voting Group who fall within any one or more of Sub-Group” the following categories:
Interconnector Owners with a Bilateral Agreement; and
Interconnector Users "Interface Agreement" the agreement(s) entered into pursuant to Paragraph 2.11 and Paragraph 9.13 based substantially on the forms set out in Exhibit O to the CUSC; “Interim Connect and the arrangements in place between 8 May 2009 and the Connect Manage and Manage Implementation Date whereby Offers were made by Arrangements” The Company on the basis that a Derogation would be obtained from the Authority such that identified Transmission Reinforcement Works did not need to completed prior to connection and/or use of system; “Interim Operational as defined in the Grid Code; Notification” or “ION” “Interim Operational as defined in the Grid Code; Notification Part A” or “ION Part A” “Interim Operational as defined in the Grid Code; Notification Part B” or “ION Part B” "Interim Panel and As defined in Paragraph 8A.4.3.2 Alternate Election process" “Interruption” where either:-
solely as a result of Deenergisation of Plant and Apparatus forming part of the National Electricity Transmission System; or
in accordance with an Emergency Deenergisation Instruction; or
solely as a result of an User Emergency Deenergisation; a) An Export BM Unit comprised in the User’s Equipment of an Affected User (other than an Interconnector Owner) is Deenergised; or b) an Associated Export BM Unit of an Affected User is (other than an Interconnector Owner) Deenergised from the National Electricity Transmission System; or c) an Interconnector of an Affected User who is an Interconnector Owner is Deenergised.; or d) The Maximum Export Limit in respect of the BM Unit(s) associated with such User’s Equipment is zero. “Interruption the payment for a Relevant Interruption calculated as follows: Payment” 1) In the case of a Relevant Interruption arising as a result of a Planned Outage; In the case of an Affected User other than an Interconnector Owner i=n Maximum(Average daily £ per MW rate,Actual daily £ per MW rate)*Affected MW i i i i=k In the case of an Affected User who is an Interconnector Owner i= n i= A v e r a g e d a i l y £ p e r M W r a t e * M W s p e c i f i e d a s t h e i k T r a n s m i s s i o n E n t r y C a p a c i t y f o r t h e C o n n e c t i o n S i t e where: i = calendar days k = 1, representing the first calendar day associated with a Relevant Interruption. n = number of complete or part complete calendar days of a Relevant Interruption 2) In the case of a Relevant Interruption arising as a result of either an Emergency Deenergisation Instruction or a User Emergency Deenergisation In the case of an Affected User other than an Interconnector Owner j = p ∑ S y s te m B u y P ric e *0 j.5 * A ffe c te d M W j j = Plus (if applicable) j = m ∑ M a rk e t P ric e *0.5 * A j ffe c te d M W j j = In the case of an Affected User who is an Interconnector Owner j = p ∑ System Buy Pricej *0.5 * MW specified as the Transmission Entry Capacity for the Connection Site j = 1 Plus (if applicable) j = m ∑ Market Pricej *0.5 * MW specified as the Transmission Entry Capacity for the Connection Site j = 4 where; j = Settlement Periods from the time when the Emergency Deenergisation Instruction was issued by The Company or commencement of the User Emergency Deenergisation (as applicable), with 1 representing the first Settlement Period. m = The duration of the Relevant Interruption (being the Interruption Period), in Settlement Periods for which Gate Closure has not yet occurred (which shall be greater than 3, up to a maximum value of 48) p = The duration of the Relevant Interruption in Settlement Periods for which Gate Closure has occurred (up to a maximum value of 3). and after the first 24 hours of a Relevant Interruption a sum calculated as 1 above save that k shall be equal to 2. 3) In the case of all other Relevant Interruptions: In the case of an Affected User other than an Interconnector Owner j = p ∑ S y s te m B u y P ric e *0 j.5 * A ffe c te d M W j j = Plus (if applicable) j = m ∑ M a rk e t P ric e *0.5 * A j ffe c te d M W j j = In the case of an Affected User who is an Interconnector Owner j = p ∑ System Buy Pricej *0.5 * MW specified as the Transmission Entry Capacity for the Connection Site j = 1 Plus (if applicable) j=m Market Price *0.5*MW specified as the Transmissi on j j=4 Entry Capacity for the Connection Site where; j = Settlement Periods from the start of the Relevant Interruption, with 1 representing the first Settlement Period. m = The duration of the Relevant Interruption (being the Interruption Period), in Settlement Periods for which Gate Closure has not yet occurred (which shall be greater than 3, up to a maximum value of 48) p = The duration of the Relevant Interruption in Settlement Periods for which Gate Closure has occurred (up to a maximum value of 3). and after the first 24 hours of a Relevant Interruption a sum calculated in accordance with paragraph 1 above save that k shall be equal to 2. Provided always that an Affected User shall not receive payment in respect of more than one Relevant Interruption for the same period.
In the event of the relevant Market Price being zero then for purpose of paragraphs 2 or 3 above the Market Price shall be deemed to be the most recent preceding positive price. Throughout this definition of Interruption Payment: Average daily £ per MW rate = (TNUoS income derived from generators/ total system Transmission Entry Capacity) / 365, calculated by reference in each case to figures for the Financial Year prior to that in which the Relevant Interruption occurs to give a daily £ per MW rate; Actual daily £ per MW rate = (Annual TNUoS charge of an Affected User for the Financial Year /Transmission Entry Capacity for the Connection Site) / 365 calculated by reference to the tariff in the Statement of Use of System Charges for the Financial Year in which the Relevant Interruption occurs; Affected MW = in the case of either Export BM Units or Associated Export BM Units , the MW arrived at after deducting from the Transmission Entry Capacity for the Connection Site the sum of the Connection Entry Capacity of the unaffected Export BM Units at the Connection Site; System Buy Price is as defined in the Balancing and Settlement Code; Market Price is as defined in the Balancing and Settlement Code. “Interruption Period” For a Planned Outage, shall mean the period in whole calendar days commencing with the notification of the Affected User by The Company of the start of Relevant Interruption and ending on the notification of the Affected User by The Company that the Relevant Interruption has ended; For a Relevant Interruption arising as a result of:
an Emergency Deenergisation Instruction, shall mean the period from the start of the Settlement Period in which The Company gave notification to the Affected User of the start of such Relevant Interruption; or
a User Emergency Deenergisation, shall mean the period from the start of the Settlement Period in which the User Emergency Deenergisation commenced, until the end of the Settlement Period in respect of which (i)The Company gave notification to the Affected User by The Company that the Relevant Interruption has ended or (ii), in the case of a User Emergency Deenergisation, means the earlier of (a) when the Export BM Unit is Reenergised or (b) when the issue on the National Electricity Transmission System giving rise to the User Emergency Denergisation is resolved, which shall be measured in: i) whole Settlement Periods for the first 24 hours from the time of either notification by The Company to the Affected User of the start of such Relevant Interruption or when the User Emergency Deenergisation commenced (as applicable); and ii) whole calendar days for any time after the first 24 hour period referred to in i) above. In the case of all other Relevant Interruptions the duration, shall mean the period from the start of such Relevant Interruption which shall be measured in: i) whole Settlement Periods for the first 24 hours from the start of such Relevant Interruption; and ii) whole calendar days for any time after the first 24 hour period referred to in i) above. "Intertrip Contracted (i) in the case of a Power Park Module, the collection of Non- Unit" Synchronous Generating Units which are registered as a Power Park Module under the Grid Code; and
all other cases, a Generating Unit, unless, in either case, the Bilateral Agreement specifies otherwise. "Intertrip Payment" as defined in Paragraph 4.2A.4(c); "Isolation" as defined in the Grid Code; “ISOP” Independent System Operator and Planner, means a person designated by the Secretary of State under section 162 of the Energy Act 2023 as the holder of the ESO Licence, and the GSP Licence. For the time being that person is NESO; "Joint System Paragraphs (a) and (b) below are without prejudice to the Incident" application of Paragraph 6.4 to Users acting in capacities other than those detailed in Paragraphs (a) and (b),
for Users in respect of their Connection Sites which were not Commissioned as at the Transfer Date, shall have the meaning given to that term in the Grid Code;
for Users acting in their capacity as Generators with Embedded Large Power Stations or Embedded Medium Power Stations and who are passing power onto a Distribution System through a connection with a Distribution System which was not Commissioned as at the Transfer Date, means an event wherever occurring (other than on an Embedded Medium Power Station or Embedded Small Power Station) which, in the opinion of The Company or a User has or may have a serious and/or widespread effect, being (in the case of an event on a User(s) System(s)) (other than on an Embedded Medium Power Station or Embedded Small Power Station), on the National Electricity Transmission System, and (in the case of an event on the National Electricity Transmission System), on a User(s) System(s) (other than on an Embedded Independent Generating Plant); "Joint Temporary TEC the Temporary TEC Exchange Donor User and the Temporary Exchange Users" TEC Exchange Recipient User; “Key Consents” those Consents a User requires in respect of its Power Station project which are identified by The Company as key for the purposes of Part Three of the User Commitment Methodology and in relation to a particular User as defined in its Construction Agreement; “Key Consents In Place the date that The Company confirms in writing to the User that The Date” Company is satisfied, for the purposes of Part Three of the User Commitment Methodology, that the User has been granted the Key Consents; "Land Charge" the charge (if any) set out in Appendix B to a Bilateral Connection Agreement; "Large Power Station" as defined in the Grid Code; "LDTEC" Is, in the case of an accepted LDTEC Block Offer, Block LDTEC or, in the case of an accepted LDTEC Indicative Block Offer, Indicative Block LDTEC; "LDTEC Availability the form set out in Exhibit T to the CUSC; Notification" "LDTEC Block Offer" is an offer made by The Company for Short Term Capacity in accordance with the terms of Paragraphs 6.32.4.6 and 6.32.6.1 in response to an LDTEC Request; "LDTEC Charge" being a component of the Use of System Charges which is made or levied by The Company and to be paid by the User, in the case of an accepted LDTEC Block Offer, for Block LDTEC and in the case of an accepted LDTEC Indicative Block Offer for Requested LDTEC and in the case of an accepted Temporary TEC Exchange Rate Offer for Temporary Received TEC, in each case calculated in accordance with the Charging Statements; "LDTEC Indicative is an offer made by The Company for Short Term Capacity in Block Offer" accordance with the terms of Paragraphs 6.32.6.4 and 6.32.6.2 in response to an LDTEC Request; "LDTEC Indicative is a profile in MW that indicates The Company’s assessment of Profile" the MW capacity that may be available to a User for the LDTEC Period which has been prepared solely for the purpose of enabling a User to make its assessment of an LDTEC Indicative Block Offer; "LDTEC Offer" is an LDTEC Block Offer and\or an LDTEC Indicative Offer; "LDTEC Period" is,
a period of weeks or part thereof within a Financial Year as specified by the User in its LDTEC Request Form for a minimum period of seven weeks commencing on a Monday at 0.00 hours and finishing at 23.59 on any given day no later than the last day of such Financial Year, or
in the case of an accepted Temporary TEC Exchange Offer, the Temporary TEC Exchange Period; "LDTEC Profile" is a profile in MW of The Company’s assessment of the MW capacity that is available to a User for the LDTEC Period (not exceeding the maximum level in the LDTEC Request) in an LDTEC Block Offer; "LDTEC Request" is an application made by a user for an LDTEC Block Offer and\or an LDTEC Indicative Block Offer made using an LDTEC Request Form; "LDTEC Request Fee" the fee to be paid by the User to The Company for an LDTEC Request as detailed in the Charging Statements; "LDTEC Request is the form set out in Exhibit S to the CUSC; Form" "LDTEC Week" is a week or part thereof within an LDTEC Period commencing on Monday at 0.00 and finishing on 23:59 on the last day within such week; "Leading" in relation to Reactive Power, importing Mvar; "Legal Challenge" an appeal to the Competition Commission or a judicial review in respect of the Authority’s decision to approve or not to approve a CUSC Modification Proposal; “Legally Binding any relevant legally binding decision or decisions of the European Decisions of the Commission and/or the Agency, but a binding decision does not European Commission include a decision that is not, or so much of a decision as is not, and/or the Agency Assimilated Law; “Less than 100MW” Is defined as not having the capability to export 100MW to the Total System; “Letter of the letter to be provided with the Connection Application for a Acknowledgement” New Connection Site Offshore or New Connection Site for an Offshore Project and obtained from either The Crown Estate or Crown Estate Scotland; “Letter of Authority” the letter to be provided with the Connection Application, such letter to be in the appropriate format as found at Section 2 Schedule 2; "Letter of Credit" (a) in respect of Paragraph 2.22 shall mean an irrevocable standby letter of credit in a form reasonably satisfactory to The Company but in any case expressed to be governed by the Uniform Customs and Practice for Documentary Credits 1993 Revision ICC Publication No. 500 or such other form as may be reasonably satisfactory to The Company and allowing for partial drawings and providing for the payment to The Company on demand forthwith on and against The Company’s delivery to the issuer thereof of a Notice of Drawing of the amount demanded therein;
in all other cases shall mean an unconditional irrevocable standby letter of credit in such form as The Company may reasonably approve issued for the account of the User in sterling in favour of The Company, allowing for partial drawings and providing for the payment to The Company forthwith on demand by any United Kingdom clearing bank or any other bank which in each case has a long term debt rating of not less than single "A" by Standard and Poor’s Corporation or by Moody’s Investors Services, or such other bank as The Company may approve and which shall be available for payment at a branch of the issuing bank; "Licence" any licence granted pursuant to Section 6 of the Act; "Licence Standards" the standards to be met by The Company under condition E7 of the ESO Licence; “Licensable generating plant that is not Exemptible Generation; Generation” Limited Membership a Workgroup having less than five (5) but more than two (2) Workgroup persons that have nominated themselves for membership in addition to the Code Administrator representative and the chairperson of the Workgroup. Members of a Limited Membership Workgroup where employed by companies that are considered to be an Affiliate of each other will be considered to be a single workgroup member for the purposes of fulfilling this minimum requirement. “Limiting Regulation” European Commission Regulation 838/2010 in the context of setting limits on annual average transmission charges payable by Generators (or any subsequent UK law specifying such limits); "Liquidated Damages" in relation to a particular User, as defined in its Construction Agreement; “LoA Guidance” the guidance on the requirements for the Letter of Authority and Letter of Acknowledgment published by The Company on the Website (as it may be amended from time to time); "Local Safety as defined in the Grid Code; Instructions" “London Court of the leading London-based arbitral institution and not-for-profit International company limited by guarantee of that name with a registered Arbitration” company number of 0204767 providing for the resolution of commercial disputes in accordance with its arbitration rules; “Loss of Transmission a form amended from time to time by agreement between the Access Compensation CUSC Modification Panel and The Company, to be completed Claim Form” by a claimant for submission of Relevant Interruption claims and available on a website maintained by The Company; "MCUSA" the Master Connection and Use of System Agreement dated 30 March 1990 (now amended to become the CUSC Framework Agreement); "Main Business" any business of The Company or any of its subsidiaries which it is required to carry on under the ESO Licence; "Main Business any employee of The Company or any director or employee of its Person" subsidiaries who is engaged solely in the Main Business and "Main Business Personnel" shall be construed accordingly; “Main System Circuits” Transmission Circuits but excluding a Grid Supply Point transformer; "Maintenance the statement prepared in accordance with Paragraph 2.14.5 and Reconciliation Paragraph 9.9.5; Statement" "Mandatory Ancillary Part 1 System Ancillary Services; Services" "Mandatory Services an agreement between The Company and a User to govern the Agreement" provision of and payment for Mandatory Ancillary Services or to govern the payment by The Company to a User for Obligatory Reactive Power Service provided by an Offshore Transmission Licensee in accordance with the STC; "Market Agreement" as defined in Paragraph 3.1 of Schedule 3, Part I; "Market Day" as defined in Paragraph 3.3 of Schedule 3, Part I; “Market Suspension as defined in the Balancing and Settlement Code; Period” "Material Effect" an effect causing The Company or a Relevant Transmission Licensee to effect any works or to alter the manner of operation of Transmission Plant and/or Transmission Apparatus at the Connection Site or the site of connection or a User to effect any works or to alter the manner of operation of its Plant and/or Apparatus at the Connection Site or the site of connection which in either case involves that party in expenditure of more than £10,000; “Materially Affected any person or class of persons designated by the Authority as Party” such, in relation to the Charging Methodologies; “Maximum Export as defined in the Grid Code and in relation to a particular User, as Capacity” defined in its Bilateral Connection Agreement; "Maximum Export as defined in the Grid Code; Limit" "Maximum Generation" a Balancing Service provided from the Available BM Units by generating at a level above the MEL so as to increase the total export of Active Power from the Power Station to the National Electricity Transmission System, contributing towards The Company’s requirement for additional short-term generation output, all as more particularly described in Paragraph 4.2; "Maximum Generation as between The Company and a User, the BM Units, specified in BM Unit" the Maximum Generation Service Agreement; "Maximum Generation the amount (£/MWh) set out in the Maximum Generation Service Energy Fee" Agreement as the same may be revised from time to time in accordance with Paragraph 4.2.5; "Maximum Generation has the meaning attributed to it in Paragraph 4.2.5.1; Energy Payment" "Maximum Generation has the meaning attributed to it in Paragraph 4.2.4.1; Instruction" "Maximum Generation has the meaning attributed to it in Paragraph 4.2.3.3; Redeclaration" "Maximum Generation an agreement between The Company and a User specifying, Service Agreement" amongst other things, the BM Units and the Maximum Generation Energy Fee applicable to the provision of Maximum Generation; “Maximum Import as defined in the Grid Code and in relation to a particular User, as Capacity” defined in its Bilateral Connection Agreement in the context of the Charging Methodologies it shall mean as defined in the Distribution Connection and Use of System Agreement; "Medium Power as defined in the Grid Code; Station" "Meters" as defined in the Balancing and Settlement Code; "Metering Equipment" as defined in the Balancing and Settlement Code; "Meter Operator Agent" as defined in the Balancing and Settlement Code; "Metering System" as defined in the Balancing and Settlement Code; "Methodology" the Statement of the Use of System Charging Methodology or the Statement of the Connection Charging Methodology (and "Methodologies" shall be construed accordingly); “Milestone Default the notice issued by The Company to a User for the purposes of Notice” Paragraph 16.4.4 of the Queue Management Process; “Milestone 1” the User Progression Milestone “Milestone 1 Initiated Statutory Consents and Planning Permission”, set out in the table in Paragraph 16.3 of Section 16 or, where the Distribution Queue Management Process applies, the equivalent milestone (relating to the initiation of statutory consents and planning permission) under the relevant Distribution Connection Agreement; “Minister of the Crown” as defined in the ESO Licence; “MITS Connection those Transmission Reinforcement Works (inclusive of Works” substation works) that are required from the Connection Site to connect to a MITS Substation (and in the context of an Embedded Power Station, “connection site” shall mean the associated Grid Supply Point identified as such in the relevant Bilateral Agreement); “MITS Node”” in the context of ascertaining the Attributable Works, a node with
more than four Transmission circuits or (ii) two or more Transmission circuits and a Grid Supply Point; “MITS Substation” in the context of the definition of MITS Connection Works, a Transmission substation with more than 4 Main System Circuits connecting at that substation; “Mixed Demand Site” a Final Demand Site which also contains Electricity Generation and/or Electricity Storage and/or provides an Eligible Service; "Mode A Frequency as defined in Paragraph 4.1.3.3; Response" "Modification" any actual or proposed replacement, renovation, modification, alteration, or construction by or on behalf of a User or The Company to either the User’s Plant or Apparatus or the manner of its operation or Transmission Plant or Transmission Apparatus or the manner of its operation which in either case has or may have a Material Effect on another CUSC Party at a particular Connection Site; "Modification Affected as defined in Paragraph 6.9.3.2; User" "Modification an application in the form or substantially in the form set out in Application" Exhibit I to the CUSC; "Modification a notification in the form or substantially in the form set out in Exhibit Notification" K to the CUSC; "Modification Offer" an offer in the form or substantially in the form set out in Exhibit J to the CUSC, including any revision or extension of such offer; “Multi-Purpose as defined in the Energy Act 2023; Interconnector” "National Electricity the system consisting (wholly or mainly) of high voltage electric Transmission System" wires owned or operated by transmission licensees within Great or “NETS” Britain and Offshore and used for the transmission of electricity from one Power Station to a sub-station or to another Power Station or between sub-stations or to or from any External Interconnection and includes any Plant and Apparatus or meters owned or operated by any transmission licensee within Great Britain and Offshore in connection with the transmission of electricity but shall not include Remote Transmission Assets; "National Electricity is the National Electricity Transmission System Security and Transmission System Quality of Supply Standards as referred to in condition E7 of the SQSS" or "NETS ESO Licence; SQSS" “National Energy The Company with registered number 11014226, as the System Operator or designated ISOP and holder of the ESO Licence and the GSP NESO” Licence; "Natural Demand" the Demand (Active Power) which is necessary to meet the needs of Customers excluding that Demand (Active Power) met by Embedded Generating Units whose generation is not traded by Trading Parties through Energy Metering Systems registered under the Balancing and Settlement Code; "Net Asset Value" the Gross Asset Value of the Transmission Connection Asset in question less depreciation over the Replacement Period calculated in accordance with recognised accounting principles and procedures; "New Connection Site" a proposed Connection Site in relation to which there is no Bilateral Agreement in force between the CUSC Parties; "New CUSC Party" as defined in Paragraph 6.13; “Net Demand” Sum of the BM Unit Metered Volumes (QM ) of the Trading Unit ij during the three Settlement Periods of the Triad expressed as a positive number (i.e. ∑QM.); ij “NGET” National Grid Electricity Transmission plc (No: 2366977) whose registered office is at 1-3 Strand, London, WC2N 5EH: "NHH Base the % value for the relevant Security Period as specified in the Percentage" table in paragraph 2 of Section 3, Appendix 2; "NHH Charges" that element of Transmission Network Use of System Demand Charges relating to non-half-hourly metered Demand; "NHH Base Value at the sum as calculated in accordance with Paragraph 3.22.4; Risk" "NHH Forecasting the amount resulting from multiplying the Deemed NHH Performance Related Forecasting Performance and the Indicative Annual HH TNUoS VAR " Charge calculated on the basis of the latest Demand Forecast received by The Company; "Nominated Registered as defined in Appendix 5 of Schedule 3, Part I; Capacity" "Non-Embedded a Customer except for a Public Distribution System Operator Customer" receiving electricity direct from the National Electricity Transmission System irrespective of from whom it is supplied; “Non-Embedded User” a User, except for a Public Distribution System Operator, receiving electricity direct from the National Electricity Transmission System irrespective of from whom it is supplied; “Non-Final Demand a Single Site (whether commissioning, operating, maintaining or Site” decommissioning) which is either a; i. Electricity Storage Facility and/or an Electricity Generation Facility ii. Eligible Services Facility The Non-Final Demand Site shall have an export Metering System and an import Metering System with associated metering equipment which only measures export from Electricity Generation and/or Electricity Storage or Eligible Services and import for, or directly relating to Electricity Generation and/or Electricity Storage or Eligible Services (and not export from another source or import for another activity), which is subject to a Declaration. "Non- Performing as defined in Paragraph 6.19; Party" "Non Standard where the division of ownership of Plant and Apparatus is contrary Boundary" to the principles of ownership set out in CUSC Paragraph 2.12; “Non-Standard an Interconnector which is connected to an offshore converter Interconnector” station in the connecting jurisdiction and which does not subsist for the purposes of offshore transmission activities in Great Britain as such definition may evolve for regulatory purposes; "Non-Synchronous as defined in the Grid Code; Generating Unit" "Notice of Drawing" a notice of drawing signed by or on behalf of The Company substantially in the form set out in Exhibit N to the CUSC; "Notification Date" as defined in the Balancing and Settlement Code; "Notification of Circuit as defined in the relevant Bilateral Connection Agreement or Outage" Bilateral Embedded Generation Agreement; "Notification of Circuit as defined in the relevant Bilateral Connection Agreement or Restriction" Bilateral Embedded Generation Agreement; “Notification of Fixed the notification issued by The Company to a User, in accordance Attributable Works with Part Two of the User Commitment Methodology showing the Cancellation Charge” Fixed Attributable Works Cancellation Charge such statement to be in substantially the form set out in Exhibit MM3 to the CUSC; "Notification of as defined in the relevant Bilateral Connection Agreement or Restrictions on Bilateral Embedded Generation Agreement; Availability" "Notification of ET as defined in the relevant Bilateral Connection Agreement; Restrictions on Availability" "Notional Amount" as defined in Paragraph 3.13; "Nuclear Generator" as defined in Paragraph 6.11; "Nuclear Site Licence shall mean each of the following agreements (as from time to time Provisions amended) (a) the agreement between NGET and Magnox Electric Agreement"1 plc (formally called Nuclear Electric plc) dated 30 March 1990, (b) the agreement between NGET and British Energy Generation Limited dated 31 March 1996, (c) the agreement between SP Transmission Limited and British Energy Generation (UK) Limited dated 29 May 1991 in relation to Hunterston power station and Torness power station, and (d) the agreement between SP Transmission Limited and British Nuclear Fuels plc in relation to Chapelcross power station; "Obligatory Reactive as defined in Paragraph 1.1 of Schedule 3, Part I or provided by an Power Service Offshore Transmission Licensee in accordance with the STC; "Offer" an offer for connection to and/or use of the National Electricity Transmission System made by The Company in relation to the CUSC; In the context of the Charging Methodologies it shall have the meaning as defined in the BSC; “Offer Acceptance the period for acceptance as set out in CUSC Paragraphs 1.7.3, Period” 2.13.4, 3.7.4, 6.9.2.3 and 9.17.3;
The dates and names of parties with NSLPAs need to be updated in due course. "Offshore" means wholly or partly in the Offshore Waters and when used in conjunction with another defined term and the terms together are not otherwise defined means that the associated term is to be read accordingly; “Offshore Construction in relation to a particular User means those elements of the Works” Construction Works to be undertaken by an Offshore Transmission Licensee on the Offshore Transmission System as defined in its Construction Agreement; "Offshore Grid Entry as defined in the Grid Code; Point" "Offshore Platform" a single structure comprising of Plant and Apparatus located Offshore which includes one or more Offshore Grid Entry Points; “Offshore Project” an Interconnector, Power Station located in Offshore Waters, Multi-Purpose Interconnector, Non-Standard Interconnector or other project which has leases awarded to it in Offshore Waters by the Crown Estate or Crown Estate Scotland or any other project which connects to the National Electricity Transmission System Onshore but has or involves assets outside of the jurisdiction of Great Britain and which is not caught by any of the aforementioned categories; "Offshore Standard is a connection design (which provides for connection to the Design" National Electricity Transmission System) of a Connection Site located Offshore which satisfies the minimum deterministic criteria detailed in paragraphs 7.7 to 7.19 of the NETS SQSS but does not satisfy the deterministic criteria detailed in paragraphs 2.5 to 2.13 of the NETS SQSS; "Offshore Tender that process followed by the Authority to make, in prescribed Process" cases, a determination on a competitive basis of the person to whom an offshore transmission licence is to be granted; "Offshore Tender those regulations made by the Authority in accordance with Regulations" section 6C of the Act to facilitate the determination on a competitive basis of the person to whom an offshore transmission licence is to be granted; “Offshore as defined in the Energy Act 2004; Transmission” “Offshore as defined in the Transmission Licence; Transmission Implementation Plan” "Offshore such person in relation to whose Licence the standard conditions Transmission in Section E (offshore transmission owner standard conditions) of Licensee" such Licence have been given effect or any person in that prospective role; “Offshore either (a) such person in relation to whose Licence the standard Transmission Owner” conditions in Section E (offshore transmission owner standard conditions) of such Licence have been given effect; or (b) a party who has acceded to the STC prior to the grant of a Licence referred to in (a) above as a requirement of the Offshore Tender Regulations; “Offshore in relation to a particular User, as defined in its Construction Transmission Agreement; Reinforcement Works” "Offshore a System used (or to be used) for the purposes of Offshore Transmission System" Transmission and for which there is (or where the OTSDUW Arrangements apply, will be) an Offshore Transmission Licensee; "Offshore in relation to a particular User where the OTSDUW Arrangements Transmission System apply means those activities and/or works to be undertaken by the Development User User as identified in Part 2 of Appendix I of the relevant Works" or "OTSDUW" Construction Agreement; "Offshore in relation to a particular User, any Plant and Apparatus resulting Transmission System from OTSDUW Build which form the Offshore Transmission User Assets" or System to which the User’s Equipment is to be or is connected, "OTSUA" as identified in its Construction Agreement; "Offshore Waters" has the meaning given to "offshore waters" in Section 90(9) of the Energy Act 2004; “Offtaking” as defined in the Balancing and Settlement Code; "One Off Charge" the costs, including profits and overheads of carrying out the One Off Works, together with the Net Asset Value of any asset made redundant as a result of the Construction Works an estimate of which is specified in Appendix B1 to the relevant Construction Agreement and/or Bilateral Agreement; "One Off Works" the works described in Appendix B1 to the relevant Construction Agreement and/or Bilateral Agreement; “Onshore” within Great Britain and when used in conjunction with another defined term and the terms together are not otherwise defined means that the associated term is to be read accordingly; “Onshore Tender the process followed by the Delivery Body to make, in prescribed Process” cases, a determination on a competitive basis of the person to whom an onshore transmission licence is recommended to be granted by the Authority or a Relevant Contract is recommended to be awarded, as more particularly described in the Onshore Tender Regulations; “Onshore Tender those regulations made by the Authority in accordance with Regulations” section 6C of the Act to facilitate the determination on a competitive basis of the person to whom an onshore transmission licence is to be granted; “Onshore NGET, Scottish Hydro Electric Transmission plc, SP Transmission Transmission plc, a Competitively Appointed Transmission Owner or such Licensee” other person in relation to whose transmission licence the Standard Conditions in Section D (transmission owner standard conditions) have been given effect; “Onshore the part of the National Electricity Transmission System which Transmission System” is not an Offshore Transmission System; “Onshore Construction in relation to a particular User, means those elements of the Works” Construction Works to be undertaken other than on the Offshore Transmission System as defined in its Construction Agreement; “Onshore in relation to a particular User, as defined in its Construction Transmission Agreement; Reinforcement Works” "Operating the operating agreements or arrangements identified in the Agreement(s)" Bilateral Connection Agreement between The Company and the Interconnector Owner of the relevant Interconnector and made between either The Company and the relevant Interconnector Owner and/or The Company and the relevant Interconnected System Operator; "Operating Code" or the portion of the Grid Code which is identified as the Operating "OC" Code; "Operation Diagrams" as defined in the Grid Code; "Operational" in relation to a Connection Site means that the same has been Commissioned (which for the avoidance of doubt does not necessarily include commissioning of Generating Units connected at the Connection Site) and that the User can use such User's Equipment to undertake those acts and things capable of being undertaken by BSC Parties and in relation to a Transmission Interface Site means, in the case of OTSDUW Build, that the same has been Commissioned and that the User can use the OTSUA; "Operational Date" the date on which The Company issues the Operational Notification; "Operational Effect" any effect on the operation of any System which causes that System to operate (or be at a materially increased risk of operating) differently to the way in which it would have normally operated in the absence of that effect; "Operational the automatic tripping of circuit breakers to prevent abnormal Intertripping" system conditions occurring, such as over voltage, overload, system instability etc. after the tripping of other circuit breakers following power system fault(s) which includes System to Power Station and System to Demand intertripping schemes; "Operational Metering meters, instrument transformers (both voltage and current), Equipment" transducers, metering protection equipment including alarms circuitry and their associated outstations as may be necessary for the purpose of CC.6.5.6 of the Grid Code and the corresponding provision of the relevant Distribution Code; "Operational the notice of that name given to the User by The Company under Notification" Paragraphs 1.5.5 or 3.2.6 as appropriate; "Original Party" as defined in the CUSC Framework Agreement; “Original Red Line the red line boundary provided (a) with a Gate 2 Application or (b) Boundary” EA Request in accordance with the Gate 2 Criteria Methodology; “Original Red Line the clause introduced to Schedule 2 Exhibit 3 and 3A under Boundary Reduction CMP434 and in the context of directly connected parties only to Clause” address the consequences of non-compliance with the ongoing obligations in respect of the Original Red Line Boundary under the Queue Management Process; "Other Dispute" as defined in Paragraph 7.2.3; "Other Party" as defined in Paragraph 7.5.1; "Other User" as defined in Paragraph 6.10.3; "OTSDUW the arrangements whereby (a) OTSDUW Build or (b) the design, Arrangements" planning and consenting of assets that are to comprise an Offshore Transmission System are capable of being undertaken by a User; “OTSDUW Build” the design, planning, consenting, construction, installation and commissioning by (or on behalf of) a User of OTSUA which forms an Offshore Transmission System which at the OTSUA Transfer Time will be owned by an Offshore Transmission Licensee; “OTSDUW Staged OTSDUW Build that is to be undertaken by the User in stages Build” but which is part of a single Qualifying Project; “OTSUA has the meaning given to commissioning period in Section 6G(1) Commissioning of the Act; Period” “OTSUA the date upon which, in accordance with the modification issued by Commissioning Period the Authority to The Company pursuant to Section 6H of the Act, Effective Date” the amendments to the CUSC as provided for in such modification take effect; “OTSUA Completion the notice to be issued by The Company to the Authority in Notice” respect of OTSUA or OTSUA Operational at the OTSUA Commissioning Period Effective Date, in accordance with condition D4 of the ESO Licence and Section 6G of the Act; “OTSUA Completion means: Notice Trigger Date” a) other than in the case of OTSDUW Staged Build, the date upon which The Company, having already issued the Energisation Operational Notification and Interim Operational Notification Part A, issues the Interim Operational Notification Part B to the User; and c) in the case of OTSDUW Staged Build, the date upon which, by reference to the last stage of OTSDUW Build, The Company, having already issued the Energisation Operational Notification and Interim Operational Notification Part A, issues the Interim Operational Notification Part B for such stage to the User provided that all such documentation has already been issued in respect of all earlier stages of the OTSDUW Staged Build. “OTSUA Operational at means OTSUA in respect of which: the OTSUA Commissioning Period a) other than in the case of OTSDUW Staged Build, The Effective Date” Company, has already issued the Energisation Operational Notification and Interim Operational Notification to the User (recognising that they may be in different form but where they achieve the same effect as the Interim Operational Part A and Interim Operation Notification Part B); and b) in the case of OTSDUW Staged Build, the date, by reference to the last stage of OTSDUW Build, The Company, has already issued the Energisation Operational Notification and Interim Operational Notification to the User (recognising that they may be in different form but where they achieve the same effect as the Interim Operational Part A and Interim Operation Notification Part B) provided that such documentation has already been issued in respect of all earlier stages of the OTSDUW Staged Build, on or before the OTSUA Commissioning Period Effective Date and where the OTSUA Transfer Time has not occurred at the OTSUA Commissioning Period Effective Date; "OTSUA Transfer the time and date at which the OTSUA are transferred by the Time" relevant User to an Offshore Transmission Licensee; "Output" the actual Active Power or Reactive Power output achieved by a BM Unit; "Output Useable" shall have the meaning given to that term in the Grid Code; "Panel Chairperson" a person appointed as such in accordance with Paragraph 8.4.1; "Panel Member" any of the persons listed in Paragraph 8.3.1(b); "Panel Member Interim as defined in Paragraph 8A.4.3.3; Vacancies" “Panel Members’ the recommendation in accordance with the CUSC Modifications Recommendation” Panel Recommendation Vote; "Panel Secretary" a person appointed as such in accordance with Paragraph 8.3.1(c); "Part 1 System as defined in Grid Code CC 8.1; Ancillary Services" "Part 2 System as defined in Grid Code CC 8.1; Ancillary Services" "Partial Shutdown " as defined in the Grid Code; "Party Liable" as defined in Paragraph 6.12.1; "Payment Date" as defined in the Balancing and Settlement Code; "Payment Record the proportion of the Unsecured Credit Cover extended by The Sum" Company to a User who does meeting the Approved Credit Rating calculated in accordance with Paragraph 3.26.4 and 3.26.5; “PCF Activation Date” the date set out by The Company in a PCF Determination Notice, which must be not less than three months following a determination by the Authority under Paragraph 2.4 of Part Five of the User Commitment Methodology or, where there is no such determination, not less than three months following the end of the period set out in that Paragraph 2.4; “PCF Activation the cumulative total (in MW) of Transmission Entry Capacity, Metric” Developer Capacity and Interconnector User Commitment Capacity where Relevant Construction Agreements between it and The Company:
were terminated (by The Company) due to a failure by the User to meet Milestone 1; or
had Transmission Entry Capacity or Interconnector User Commitment Capacity reduced (by The Company) due to a failure by the User to meet Milestone 1; or
were terminated as a result of termination (by the owner/operator of a Distribution System) of a related Distribution Connection Agreement due to a failure by the developer to meet Milestone 1; or
had Developer Capacity reduced as a result of termination or reduction of capacity (by the owner/operator of a Distribution System) of a related Distribution Connection Agreement due to a failure by the developer to meet Milestone 1, during the PCF Metric Period in which the calculation is undertaken; “PCF Activation 6,500MW; Threshold” “PCF Determination the notice issued by The Company in accordance with Paragraph Notice” 2.5 of Part Five of the User Commitment Methodology; “PCF Distribution (a) in the case of the first notification provided in accordance with Notice Period” Paragraph 5.5 of Part Five of the User Commitment Methodology, the period from the date of the notification provided in accordance with Paragraph 5.1 of Part Five of the User Commitment Methodology to the 14th day of the month before the notification in accordance with Paragraph 5.5; and then
in the case of any subsequent such notifications, the period from the 15th day of the month two months before the notification to the 14th day of the month before the notification; “PCF Metric Period” (a) the period from the date Part Five of the User Commitment Methodology takes effect until 31 December 2030; and then
each subsequent period of five years commencing on 1 January and ending on 31 December; “PCF Period” each six month period commencing on the 1 April or 1 October; "Pending CUSC a CUSC Modification Proposal in respect of which, at the relevant Modification Proposal" time, the Authority has not yet made a decision as to whether to direct such Proposed CUSC Modification to be made pursuant to the ESO Licence (whether or not a CUSC Modification Report has been submitted in respect of such CUSC Modification Proposal); "Performance Bond" an on first demand without proof or conditions irrevocable performance bond or performance guarantee executed as a deed in a form reasonably satisfactory to The Company but in any case allowing for partial drawings and providing for the payment to The Company on demand forthwith on and against The Company’s delivery to the issuer thereof of a Notice of Drawing of the amount demanded therein; "Permitted Activities" activities carried on for the purposes of the Main Business; "Physical Notification" as defined in the Balancing and Settlement Code; "Planned Outage" as defined in the Grid Code; "Planning Code" or PC that portion of the Grid Code which is identified as the Planning Code; "Plant" fixed and moveable items used in the generation and/or supply and/or transmission of electricity other than Apparatus; "Pool Member" as defined in the Balancing and Settlement Code; "Pooling and as defined in the Balancing and Settlement Code; Settlement Agreement" "Power Park Module" as defined in the Grid Code; “Power Park Unit” as defined in the Grid Code; "Power Station" as defined in the Grid Code; "Practical Completion in relation to a particular User, as defined in its Construction Date" Agreement; "Preference Votes" as defined in Paragraph 8A.3.2.1; "Prescribed Rate" the rate of interest set for the relevant period as the statutory interest rate for the purposes of the Late Payment of Commercial Debts (interest) Act 1998; “Pre Trigger Amount” the component of the Cancellation Charge that applies before the Trigger Date and which is more particularly described in Part Two of the User Commitment Methodology; "Primary Response" as defined in the Grid Code; “Prioritisation has the meaning given to that term by the Authority Guidance on Category” Code Modification Prioritisation; “Prioritisation Criteria” has the meaning given to that term by the Authority Guidance on Code Modification Prioritisation; "Proceedings" as defined in Paragraph 6.23.1; “Production” as defined in the Balancing and Settlement Code in relation to a Production BM Unit; “Profiled Unmetered as defined in the Balancing and Settlement Code; Supply” "Progress Report" as defined in Paragraph 8.14; “Progression the component of the Cancellation Charge which applies from the Commitment Fee” or PCF Activation Date as more particularly described in Parts One, “PCF” Two and Five of the User Commitment Methodology; “Project” in the context of Section 18 this is the User’s (or as context requires Developer’s) project which is the subject of the existing Agreements (and in the case of existing Agreements which provide for more than one existing Project in respect of Embedded Power Stations, existing Project shall be construed accordingly by reference to each existing Project); “Project Designation the methodology developed or to be developed by The Company Methodology” in accordance with the ESO Licence and approved by the Authority and published by The Company on the Website as such methodology may be revised from time; “Project Milestone the period starting on the date that the Milestone Default Notice Remedy Period” is issued and ending on the date which is 60 days from the date of issue of this notice; "Proposed the proposed date(s) for the implementation of a CUSC Implementation Date" Modification Proposal or Workgroup Alternative CUSC Modification such date(s) to be either (i) described by reference to a specified period after a direction from the Authority approving the CUSC Modification Proposal or Workgroup Alternative CUSC Modification or (ii) a Fixed Proposed Implementation Date; "Proposer" in relation to a particular CUSC Modification Proposal, the person who makes such CUSC Modification Proposal; "Protected any information relating to the affairs of a CUSC Party which is Information" furnished to Business Personnel pursuant to the CUSC or a Bilateral Agreement or a Mandatory Services Agreement or a Construction Agreement or pursuant to a direction under section 34 of the Act or pursuant to the provisions of the Fuel Security Code unless, prior to such information being furnished, such CUSC Party has informed the recipient thereof by notice in writing or by endorsement on such information, that the said information is not to be regarded as Protected Information; "Provisional as defined in Paragraph 4.3.2.1(a); Statement" "Provisional Monthly as defined in Paragraph 4.3.2.1; Statement" "Provisional as defined in Paragraph 4.3.2.1(b); Adjustments Statement" "Public Distribution a holder of a Distribution Licence who was the holder, or is a System Operator" successor to a company which was the holder of a Public Electricity Supply Licence relating to distribution activities in Great Britain on the CUSC Implementation Date; "Public Electricity a licence issued under section 6(1)(c) of the Act prior to the coming Supply Licence" in force of section 30 of the Utilities Act 2000; "Qualified Bank" or means either: "Qualifying Bank"
a City of London branch of a bank, its successors and assigns, which has throughout the validity period of the Performance Bond or Letter of Credit it issues in favour of The Company, a rating of at least A- in Standard and Poor’s long term debt rating or A3 in Moody’s long term debt rating provided that such bank is not during such validity period put on any credit watch or any similar credit surveillance which gives The Company reasonable cause to doubt that such bank may not be able to maintain the aforesaid rating throughout the validity period and no other event has occurred which gives The Company reasonable cause to have such doubt; or
a branch in Great Britain of a regulated insurance company, its successors and assigns, which throughout the validity period of the Performance Bond or Letter of Credit it issues in favour of The Company, is authorised or licensed to provide arrangements of this type in the United Kingdom, and has a rating of at least A- in Standard and Poor’s long term debt rating or A3 in Moody’s long term debt rating provided that such regulated insurance company is not during such validity period put on any credit watch or any similar credit surveillance which gives The Company reasonable cause to doubt that such regulated insurance company may not be able to maintain the aforesaid rating throughout the validity period and no other event has occurred which gives The Company reasonable cause to have such doubt. "Qualified Company" a company which is a public company or a private company within or the meaning of section 1(3) of the Companies Act 1985 and which is either: "Qualifying Company"
a shareholder of the User or any holding company of such shareholder or
any subsidiary of any such holding company, but only where the subsidiary
demonstrates to The Company’s satisfaction that it has power under its constitution to give a Performance Bond other than in respect of its subsidiary;
provides an extract of the minutes of a meeting of its directors recording that the directors have duly concluded that the giving of the Performance Bond is likely to promote the success of that subsidiary for the benefit of its members;
provides certified copies of the authorisation by every holding company of the subsidiary up to and including the holding company of the User, of the giving of the Performance Bond, (the expressions "holding company" and "subsidiary" having the respective meanings assigned thereto by section 736, Companies Act 1985 as supplemented by section 144(3), Companies Act 1989) and which has throughout the validity period of the Performance Bond it gives in favour of The Company, a rating of at least A- in Standard and Poor’s long term debt rating or A3 in Moody’s long term debt rating or such lesser rating which The Company may in its absolute discretion allow by prior written notice given pursuant to a resolution of its board of directors for such period and on such terms as such resolution may specify provided that such company is not during such validity period put on any credit watch or any similar credit surveillance procedure which gives The Company reasonable cause to doubt that such company may not be able to maintain the aforesaid rating throughout the validity period of the Performance Bond and no other event has occurred which gives The Company reasonable cause to have such doubt; "Qualifying a guarantee in favour of The Company in a form proposed by the Guarantee" User and agreed by The Company (whose agreement shall not be unreasonably withheld or delayed) and which is provided by
an entity which holds an Approved Credit Rating provided that such guarantee cannot secure a sum greater than the level of User’s Allowed Credit that would be available to that entity in accordance with Paragraph 3.26.2 if it was a User; or
an entity with an Independent Credit Assessment provided that such guarantee cannot secure a sum greater than the level of User’s Allowed Credit that would be available to that entity in accordance with Paragraph 3.26.6 if it was a User; and
which in either case does not, when aggregated with all other Qualifying Guarantees provided by that entity, exceed (a) the level of User’s Allowed Credit that would be available to that entity in accordance with Paragraph 3.26 if it was a User or (b) if the entity is a User the level of User’s Allowed Credit available to it in accordance with Paragraph 3.26 less any amount relied on by the User in respect of its own requirements. “Qualifying Project” has the meaning ascribed to it in the Act; “Queue Management the guidance on the Queue Management Process (as it may be Guidance” amended from time to time) published by The Company on the Website; “Queue Management the process as set out in CUSC Section 16 to measure and provide Process” a status (“On Track” or “Termination” as set out within that process) of the progress of a User’s project against the User Progression Milestones; "Rated MW" as defined in the Grid Code; "Reactive Despatch an instruction relating to Reactive Power given by The Company Instruction" to a Generator in accordance with Grid Code BC2; “Reactive Despatch to as defined in the Grid Code; Zero Mvar Network Restriction” "Reactive Energy" as defined in the Balancing and Settlement Code; "Reactive Power" the product of voltage and current and the sine of the phase angle between them measured in units of voltamperes reactive and standard multiples thereof i.e.:- 1000 Var = 1Kvar 1000 Kvar = 1Mvar; "Reactive Test" a test conducted pursuant to Grid Code OC 5.5.1; “Readiness the declaration provided with a Gate 2 Application or EA Request Declaration” in the form and with the detail as required in accordance with the Gate 2 Criteria Methodology; "Reasonable Charges" reasonable cost reflective charges comparable to charges for similar services obtainable in the open market; "Reconciled Charge" as defined in Paragraph 3.15.1 and like terms shall be construed accordingly; “Reconciliation as defined in the Balancing and Settlement Code; Settlement Run” "Reenergisation" or any Energisation after a Deenergisation; "Reenergised" "Registered Capacity" has the meaning given in the Grid Code; "Registered Data" those items of Standard Planning Data and Detailed Planning Data which upon connection become fixed (subject to any subsequent changes); "Registrant" as defined in the Balancing and Settlement Code; "Regulations" the Electricity Supply Regulations 1988 or any amendment or re- enactment thereof; "Rejected CUSC a CUSC Modification Proposal in respect of which the Authority Modification Proposal" has decided not to direct The Company to modify the Code pursuant to the ESO Licence in the manner set out herein; “Related Person” in relation to an individual, any member of their immediate family, their employer (and any former employer of theirs within the previous 12 months), any partner with whom they are in partnership, and any company or Affiliate of a company in which they or any member of their immediate family controls more than 20% of the voting rights in respect of the shares of the company; "Related Undertaking" in relation to The Company (and for the purposes of Paragraph 6.15, a User) means any undertaking in which The Company has a participating interest as defined by section 260(1) of the Companies Act 1985 as substituted by section 22 of the Companies Act 1989; "Release Date" as defined in Paragraph 2.22.2; “Relevant Construction a Construction Agreement in relation to which the Cancellation Agreement” Charge is payable in accordance with the User Commitment Methodology; “Relevant Contract” has the meaning given to that term in section 6BA of the Act; “Relevant Embedded a Relevant Embedded Small Power Station or a Relevant Power Station” Embedded Medium Power Station; "Relevant Embedded an Embedded Medium Power Station which is an Exempt Medium Power Station" Power Station; "Relevant Embedded an Embedded Small Power Station that the User who owns or Small Power Station" operates the Distribution System to which the Embedded Small Power Station intends to connect reasonably believes may have a significant system effect on the National Electricity Transmission System.; "Relevant Interruption" an Interruption other than an Allowed Interruption; “Relevant Offshore as defined in the Transmission Licence; Agreement” “Relevant Party” as defined in Paragraph 8.16.10(a); "Relevant in respect of the Onshore Transmission System each Onshore Transmission Transmission Licensee in respect of its part of the Onshore Licensee" Transmission System and in respect of each Offshore Transmission System the Offshore Transmission Licensee for that Offshore Transmission System; "Remote Transmission any Plant and Apparatus or meters owned by NGET which (a) are Assets" embedded in a Distribution System or a User System and which are not directly connected by Plant and/or Apparatus owned by NGET to a sub-station owned by NGET and (b) are by agreement between NGET and such Public Distribution System Operator or User under the direction and control of such Public Distribution System Operator or User; "Replacement Period" in relation to a Transmission Connection Asset, the period commencing on the date on which such Transmission Connection Asset is or was originally Commissioned, after which it is assumed for accounting purposes such Transmission Connection Asset will need to be replaced, which shall be 40 years except
in the case of Transmission Connection Assets located Offshore where it shall be 20 years, or
unless otherwise agreed between the CUSC Parties to a Bilateral Agreement and recorded in the relevant Bilateral Agreement; "Reported Period(s) of the period of time during which a User’s Demand and/or FDSC Increase" and/or Unmetered Supply Volume increased not being more than 20 Business Days, as notified to The Company under paragraph 3.23.7, paragraph 3.23.8 or paragraph 3.23.8A; "Request for a STTEC a request made by a User in accordance with the terms Paragraph Authorisation" 6.31 for Short Term Capacity for a STTEC Period; "Requested LDTEC" the figure in MW for the LDTEC Period (not exceeding the maximum level in the LDTEC Request) specified in the User’s acceptance of the LDTEC Indicative Block Offer in accordance with paragraph 6.32.6.5; "Required Amount" as defined in Paragraph 2.21.2(c); "Required Sovereign a long term debt rating of not less than A by Standard and Poor’s Credit Rating" Corporation or a rating not less than A2 by Moody’s Investor Services or a short term rating which correlates to those long term ratings or an equivalent rating from any other reputable credit agency approved by The Company in respect of non local currency obligations; "Required Standard" in relation to an item of Derogated Plant, the respective standard required of that item (which shall not exceed that required by the Grid Code or the Licence Standards, as the case may be) as specified in or pursuant to the relevant Derogation; "Requirements" shall mean an entity who throughout the validity period of the Bilateral Insurance Policy, Insurance Performance Bond or Independent Security Arrangement:
holds a rating of at least A- in Standard and Poor’s long term debt rating or A3 in Moody’s long term debt rating provided that such entity is not during such validity period put on any credit watch or any similar credit surveillance which gives The Company reasonable cause to doubt that such entity may not be able to retain the aforesaid rating throughout the validity period; and
the country of residence of such entity meets the Required Sovereign Credit Rating; and
the security provided is Enforceable; and
there are no material conditions preventing the exercise by The Company of its rights under the Bilateral Insurance Policy, Insurance Performance Bond or Independent Security Arrangement; “Reservation” where for the purposes of a Gate 1 Offer or Gate 1 ATV for a New Connection Site or new Large Embedded Power Station with a BEGA or BELLA as appropriate a connection point to and/or capacity on the National Electricity Transmission System and/or a completion date for that New Connection Site or new Large Embedded Power Station with a BEGA or BELLA is reserved by The Company (and reference to Reservation and Reserved in any Gate 1 Agreements shall be construed accordingly); "Residual Charging a group of Final Demand Sites or Unmetered Supplies with Group” similar connection characteristics for which Charging Bands may or may not be set for the purposes of recovering the revenue related to the Transmission Demand Residual. The list of Residual Charging Groups are; • Domestic, • Low Voltage No Maximum Import Capacity (LV No MIC), • Low Voltage with Maximum Import Capacity (LV MIC), • High Voltage (HV), • Extra High Voltage (EHV), • Transmission • Unmetered Supplies (UMS); "Resigning Alternate as defined in Paragraph 8A.4.1.3; Member" "Resigning Panel as defined in Paragraph 8A.4.1; Member" "Response" Primary Response, Secondary Response and High Frequency Response or any of them as the case may be; "Response Energy that component of the payment for Mode A Frequency Response Payment" calculated in accordance with Paragraph 4.1.3.9A; "Restricted Export in respect of each Restricted Export Level Period, the payment for Level Payment" each day comprised within the Restricted Export Level Period or (where the Restricted Export Level Period starts or ends during a day) part of a day calculated as follows: The higher of: A. the £ per MW calculated by reference to the total TNUoS income derived from generators divided by the total system Transmission Entry Capacity, in each case using figures for the Financial Year prior to that in which the System to Generator Operational Intertripping Scheme trips, this is then divided by 365 to give a daily £ per MW rate; or B. the actual £ per MW of the User (who requests in accordance with Clause 4.2A.4) by reference to the tariff in the Use of System Charging Statement for the Financial Year in which the System to Generator Operational Intertripping Scheme trips divided by 365 to give a daily £ per MW rate. A or B are then multiplied by: the MW arrived at after deducting from the Transmission Entry Capacity for the Connection Site the Restricted MW Export Level; "Restricted Export as defined in Paragraph 4.2A.4(b)(ii); Level Period" "Restricted MW Export as defined in Paragraph 4.2A.2.1(c)(i); Level" "Restrictions on is, in the context of a Design Variation or an Offshore Availability" Connection, the outage or reduction in capability as set out in the relevant Notification of Restrictions on Availability; "Retail Price Index" the general index of retail prices published by the Office for National Statistics each month in respect of all items or:
if the said index for any month in any year shall not have been published on or before the last day of the third month after such month such index for such month or months as the parties hereto agree produces as nearly as possible the same result shall be substituted or in default of the parties reaching agreement within six weeks after the last day of such three month period then as determined by a sole Chartered Accountant appointed by agreement by both parties or in the absence of agreement on the application of either party by the President of the London Court of International Arbitration who shall act as an expert and whose decision shall be final and binding on the parties; or
if there is a material change in the basis of the said index, such other index as the parties agree produces as nearly as possible the same result shall be substituted or in default of the parties reaching agreement within six weeks after the occurrence of the material change in the basis of the said index then as determined by the sole Chartered Accountant appointed by agreement by both parties or in the absence of agreement on the application of either party by the President of the London Court of International Arbitration who shall act as an expert and whose decision shall be final and binding on the parties; "Revised Indicative the value calculated in accordance with Appendix 2 paragraph 5; Annual HH TNUoS charge" "Revised Indicative the value calculated in accordance with Appendix 2 paragraph 8; Annual NHH TNUoS charge" “Revised Proposed the revision to a Fixed Proposed Implementation Date Implementation Date” recommended to the Authority by the CUSC Modifications Panel pursuant to CUSC Paragraph 8.23.9.4; "Safety a person or persons nominated by the Relevant Transmission Coordinator(s)" Licensee and each User in relation to Connection Points (or in the case of OTSUA operational prior to the OTSUA Transfer Time, Transmission Interface Points) to be responsible for the co- ordination of Safety Precautions (as defined in the Grid Code) at each Connection Point when work and/or testing is to be carried out on a system which necessitates the provision of Safety Precautions on HV Apparatus, pursuant to OC8; "Safety Rules" the rules of a Relevant Transmission Licensee or a User that seek to ensure that persons working on Plant and/or Apparatus to which the rules apply are safeguarded from hazards arising from the System; "Second Offer" as defined in Paragraph 6.10.4; “Secondary BM Unit” as defined in the Balancing and Settlement Code "Secondary Response" as defined in the Grid Code; "Secretary of State" has the meaning given to that term in the Act; "Secured Amount a statement accompanying the Bi-annual Estimate setting out the Statement" amount to be secured by the User under Paragraph 2.21 based on figures contained in the Bi-annual Estimate being the amount for which security shall be provided to The Company pursuant to that Paragraph such statement to be substantially in the form set out in Exhibit M to the CUSC; "Secured Event" as defined in the Grid Code; "Security Amendment" the Proposed Amendment in respect of Amendment Proposal 089\090\091; "Security Amendment the Implementation Date of the Security Amendment; Implementation Date" "Security Amount" in respect of the User the aggregate of available amounts of each outstanding (a) Letter of Credit, (b) Qualifying Guarantee and (c) the principal amount (if any) of cash that the User has paid to the credit of the Escrow Account (and which has not been repaid to the User); for the purpose of this definition, in relation to a Letter of Credit or Qualifying Guarantee "available amount" means the face amount thereof less (i) payments already made thereunder and (ii) claims made thereunder but not yet paid; "Security Cover" for each User, the User’s Security Requirement less the User’s Allowed Credit; "Security Period" the First Security Period and each 6 month period thereafter commencing on the 1 April or 1 October until 30 days after the relevant Charging Date; "Security and Quality as defined in the Grid Code; of Supply Standard" "Security Requirement" the aggregate amount for the time being which the User shall be required by The Company to provide and maintain by way of Security Cover and its User’s Allowed Credit in accordance with Paragraph 3.22; “Security Standard” the Security and Quality of Supply Standard; “Self-Governance a CUSC Modification Proposal that, if implemented, Criteria”
is unlikely to have a material effect on:
existing or future electricity consumers; and
competition in the generation, distribution, or supply of electricity or any commercial activities connected with the generation, distribution or supply of electricity; and
the operation of the National Electricity Transmission System; and
matters relating to sustainable development, safety or security of supply, or the management of market or network emergencies; and
the CUSC’s governance procedures or the CUSC’s modification procedures, and
is unlikely to discriminate between different classes of CUSC Parties; c) other than where the modification meets the Fast Track Criteria will not constitute an EBR Amendment. “Self-Governance the statement made by the CUSC Modifications Panel and Statement” submitted to the Authority:
confirming that, in its opinion, the Self-Governance Criteria are met and the CUSC Modification Proposal is suitable for the self- governance route; and
providing a detailed explanation of the CUSC Modification Panel’s reasons for that opinion; "Separate Business" the Transmission Business taken separately from any other business of The Company, but so that where all or any part of such business is carried out by an Affiliate or Related Undertaking of The Company such part of the business as is carried out by that Affiliate or Related Undertaking shall be consolidated with any other such business of The Company (and of any other Affiliate or Related Undertaking) so as to form a single Separate Business; "Settlement as defined in the Balancing and Settlement Code; Administration Agent (SAA)" "Settlement Day" as defined in the Balancing and Settlement Code; "Settlement Period" as defined in the Balancing and Settlement Code; "Settlement Run" as defined in the Balancing and Settlement Code; “Shortfall Action the amount as notified by the Authority to The Company from Threshold time to time; Amount” “Shortfall Application shall mean, as appropriate: Date”
the date by which the User has issued and served court proceedings on the Developer for the recovery of the Cancellation Charge Shortfall; or
the date by which the User has instigated Insolvency Proceedings against the Developer for the recovery of the Cancellation Charge Shortfall; or
where the Developer is the subject of Insolvency Proceedings instigated other than by the User, the date by which the User has submitted its claim for the Cancellation Charge Shortfall under these; or 2. such date (being an alternative to the dates in 1 above) as approved by the Authority following a request from the User; or 3. where the Cancellation Charge Shortfall is less than the Shortfall Action Threshold Amount and the User has undertaken all preparatory steps necessary to undertake the activity in 1 above; the date which is 30 days (or the first Business Day following this) from the date of payment of the Cancellation Charge by the User; "Short Term Capacity" the right to export on to the National Electricity Transmission System power in accordance with the provisions of CUSC; “Significant Code a review of one or more matters which the Authority considers is Review” likely to:
relate to the CUSC (either on its own or in conjunction with other Industry Codes); and
be of particular significance in relation to its principal objective and/or general duties (under section 3A of the Act), statutory functions and/or relevant obligations arising under Assimilated Law, and concerning which the Authority has issued a notice to the CUSC Parties (among others, as appropriate) stating:
that the review will constitute a significant code review;
the start date of the significant code review; and
the matters that will fall within the scope of the review; “Significant Code the period Review Phase” commencing either:
on the start date of a Significant Code Review as stated in the noticed issued by the Authority; or
on the date the Authority makes a direction under Paragraph 8.17C (a “Backstop Direction”) and ending either:
(a) on the date on which the Authority issues a statement that no directions will be issued in relation to the CUSC; or
(b) If no statement is made under Paragraph 8.17.11 or 8.17.6A, on the date which The Company has made a CUSC Modification Proposal in accordance with Paragraph 8.17.6, or the Authority makes a modification proposal in respect of a Significant Code Review under Paragraph 8.17A.1: or
Immediately, if neither a statement, a modification proposal nor directions are made by the Authority up to and including twenty eight (28) days from the Authority’s publication of its Significant Code Review conclusions; or
if a statement has been made under Paragraph 8.17.6A or a direction has been made under Paragraph 8.17C (a “Backstop Direction”), on the date specified in accordance with Paragraph 8.17.6A. “Single Site” Shall mean either;
For Users with a Bilateral Connection Agreement, the Connection Site as defined in the Bilateral Connection Agreement, or 2. For all other parties, as defined as ‘Single Site’ in the DCUSA "Site Common as defined in the Grid Code; Drawings" “Site Load” the sum of the BM Unit Metered Volumes (QM ), expressed as a ij positive number, of BM Units within the Trading Unit with QM less i than zero during the three Settlement Periods of the Triad (i.e. ∑QM where QM <0), which may comprise Station Load and ij ij Additional Load; "Site Responsibility a schedule containing the information and prepared on the basis of Schedule" the provisions set out in Appendix 1 of the CC; "Site Specific the element of the Connection Charges relating to maintenance Maintenance Charge" and repair calculated in accordance with the Connection Charging Methodology; "Site Specific those requirements reasonably required by The Company in Requirements" accordance with the Grid Code at the site of connection of a Relevant Embedded Power Station; "Small Independent a Medium Power Station; Generating Plant" “Small Participant” (a) a generator, supplier, distributor, or new entrants to the electricity market in Great Britain that can demonstrate to the Code Administrator that it is resource-constrained and, therefore in particular need of assistance;
any other participant or class of participant that the Code Administrator considers to be in particular need of assistance; and
a participant or class of participant that the Authority has notified to the Code Administrator as being in particular need of assistance; "Small Power Station" as defined in the Grid Code; "Small Power Station a Trading Party trading on behalf of one or more Small Power Trading Party" Stations whether owned by the Trading Party or another person; "SMRS" as defined in the Balancing and Settlement Code; “Sole Trading Unit” as defined in the Balancing and Settlement Code; “Standard CUSC a CUSC Modification Proposal that does not fall within the scope Modification Proposal” of a Significant Code Review subject to any direction by the Authority pursuant to Paragraphs 8.17.3 and 8.17.4, nor meets the Self-Governance Criteria subject to any direction by the Authority pursuant to Paragraph 8.25.4 and in accordance with any direction under Paragraph 8.25.2; "Statement of the the statement produced pursuant to and in accordance with Connection Charging condition E11 of the ESO Licence, as modified from time to time; Methodology" "Statement of Use of the statement produced pursuant to and in accordance with System Charges" condition E10 of the ESO Licence, as modified from time to time; "Statement of the Use the statement produced pursuant to condition E10 of the ESO of System Charging Licence, as modified from time to time; Methodology" "Station Demand" in respect of any generating station and Generator, means that consumption of electricity (excluding any supply to any Customer of the relevant Generator who is neither such Generator nor a member of a qualifying group of which such Generator is a part) from the National Electricity Transmission System or a Distribution System at premises on the same site as such generating station, with premises being treated as on the same site as each other if they are:
the same premises;
immediately adjoining each other;
separated from each other only by road, railway or watercourse or by other premises (other than a pipe-line, electric line or similar structure) occupied by the consumer in question or by any other person who together with that consumer forms a qualifying group; and for the purpose of this definition "generating station" and "qualifying group" shall have the meanings given those expressions when used in the Electricity (Class Exemptions from the Requirement for a Licence) Order 1990; “Station Load” the Station Load is equal to the sum of the demand of BM Units solely comprising the Station Transformers within the Power Station. For the avoidance of doubt, Station Load excludes BM Units comprising Additional Load; "Station Transformer" has the meaning given in the Grid Code; "Steam Unit" a Generating Unit whose prime mover converts the heat energy in steam to mechanical energy; "STC" the System Operator - Transmission Owner Code entered into by The Company pursuant to the ESO Licence and by Transmission Licensees pursuant to the Transmission Licence respectively, and as from time to time revised in accordance with these Licences; “Storage Facility is a User or other entity who is responsible for the operation Operator” of an Electricity Storage Facility “Storage Tariff” the Transmission Network Use of System charge of that name as published by the Company in the Statement of Use of System Charges "STTEC" the figure in MW (if any) for the STTEC Period granted by The Company in accordance with Paragraph 6.31 of the CUSC and specified as such in Appendix C of the relevant Bilateral Connection Agreement or Bilateral Embedded Generation Agreement; "STTEC Authorisation" the authorisation notified by The Company for Short Term Capacity in accordance with the terms of Paragraph 6.3.1.6.1 in response to a Request for a STTEC Authorisation; "STTEC Charge" being a component of the Use of System Charges which is made or levied by The Company and to be paid by the User for STTEC calculated in accordance with the Charging Statements; "STTEC Offer" an offer made by The Company for Short Term Capacity in accordance with the terms of Paragraphs 6.31.6.2 and 6.31.6.3 in response to an Application for a STTEC Offer; "STTEC Period" in the case of a STTEC Authorisation, a period of 28 days commencing on a Monday at 00.00 hours and finishing at 23.59 on a Sunday. In the case of a STTEC Offer, a period of either 28, 35, or 42 days (as specified by the User in its STTEC Request Form) commencing on a Monday at 0.00 hours and finishing at 23.59 on a Sunday; "STTEC Request" either a Request for a STTEC Authorisation or an Application for a STTEC Offer; "STTEC Request Fee" the non-refundable fee to be paid by the User to The Company as detailed in the Charging Statements; "STTEC Request Form" the form set out in Exhibit P to the CUSC; "Subsidiary" has the meaning given to that term in section 736A of the Companies Act 1985; "Supplemental an agreement entered into pursuant to clause 2 of the MCUSA; Agreement" "Supplier" a person who holds a Supply Licence; "Supply Agreement" an agreement between a Non-Embedded Customer and a Supplier for the supply of electricity to the Non-Embedded Customer’s Connection Site; “Supplier Half Hourly BM Unit Metered Volumes (QM ) expressed as a positive number ij Demand” (i.e. ∑QM ) of the Trading Unit during the three Settlement ij Periods of the Triad due to half-hourly metered imports; "Supply Licence" a licence granted under section 6(1)(d) of the Act; “Supplier Non Half- BM Metered Volumes (QM ) expressed as a positive number ij Hourly Demand” (i.e.∑QM ) of the Trading Unit over the charging year between ij Settlement Periods 33 to 38 due to Non-half-hourly metered imports; “Supplier Volume as defined in the Balancing and Settlement Code; Allocation” “Supplier Voting Sub- all User(s) in a Voting Group who are Suppliers; Group” “SVA Storage Facility” is an Electricity Storage Facility that: i. performs Electricity Storage as its sole function; ii. is operated by a Storage Facility Operator iii. has its imports and exports, measured only by Half Hourly Metering Systems which are registered in the Supplier Meter Registration Service (SMRS) as part of a Supplier BM Unit, and where those Half Hourly Metering Systems only measure activities necessary for performing Electricity Storage; and iv. is the subject of a valid Declaration. "Synchronous the operation of rotating synchronous apparatus for the specific Compensation" purpose of either generation or absorption of Reactive Power; "Synchronised" the condition where an incoming BM Unit or CCGT Unit or System is connected to the busbars of another System so that the Frequencies and phase relationships of that BM Unit or CCGT Unit or the System, as the case may be, and the System to which it is connected are identical; "System Ancillary Mandatory Ancillary Services and Part 2 System Ancillary Services" Services; "System" any User System or the National Electricity Transmission System as the case may be; “System Restoration” as defined in the Grid Code; "System to Generator as defined in the Grid Code; Operational Intertripping" "System to Generator as defined in the Grid Code; Operational Intertripping Scheme" "Target Frequency" the Frequency determined by The Company in its reasonable opinion as the desired operating Frequency of the Total System. This will normally be 50.00 Hz plus or minus 0.05 Hz, except in exceptional circumstances as determined by The Company in its reasonable opinion. An example of exceptional circumstances may be difficulties caused in operating the System during disputes affecting fuel supplies; "TEC Increase a request for an increase in Transmission Entry Capacity Request" pursuant to CUSC paragraph 6.30.2; "TEC Register" the register set up by The Company pursuant to Paragraph 6.30.3.1; "TEC Trade" a trade between parties of their respective Transmission Entry Capacity; "Tendered Capability as defined in Paragraph 1.4 of Appendix 5 of Schedule 3, Part I; Breakpoints" "Temporary Donated is the temporary MW reduction in the export rights of the TEC" Temporary TEC Exchange Donor User arising from acceptance of a Temporary TEC Exchange Offer; "Temporary Received is at any time the Temporary TEC Exchange Rate; TEC" "Temporary TEC is a User that has jointly made a Temporary TEC Exchange Rate Exchange Donor User" Request to reduce its rights to export for the duration of the Temporary TEC Exchange Period; "Temporary TEC is the form set out in Exhibit X to the CUSC; Exchange Notification of Interest Form" "Temporary TEC is an offer made by The Company for a Temporary TEC Exchange Offer" Exchange Rate in accordance with the terms of Paragraphs 6.34.4.6; "Temporary TEC is a period within a Financial Year as specified in the Temporary Exchange Period" TEC Exchange Rate Request Form being for a minimum of four weeks and commencing at 0.00 hours on a Monday and finishing at 23.59 on any given day no later than the last day of such Financial Year; "Temporary TEC is the single fee to be paid to The Company for a Temporary Exchange Rate TEC Exchange Rate Request as detailed in the Charging Request Fee" Statements; "Temporary TEC is the form set out in Exhibit W to the CUSC; Exchange Rate Request Form" "Temporary TEC is a joint application made by a Temporary TEC Exchange Exchange Rate Donor User and a Temporary TEC Exchange Recipient User Request" for a Temporary TEC Exchange Rate Offer; "Temporary TEC is a weekly profile of the additional export rights in MW available Exchange Rate" to the Temporary TEC Exchange Recipient User as a direct result of the temporary reduction in export rights in MW of the Temporary TEC Exchange Donor User; "Temporary TEC is a User that has jointly made a Temporary TEC Exchange Rate Exchange Recipient Request to increase its rights to export for the duration of the User" Temporary TEC Exchange Period; "Temporary TEC Trade a trade made pursuant to CUSC Paragraph 6.34; Exchange" "Tenders" as defined in Paragraph 3.3 of Schedule 3, Part I; "Tenderers" as defined in Paragraph 3.3 of Schedule 3, Part I; "Tender Period" as defined in Paragraph 3.3 of Schedule 3, Part I; "Term" without prejudice to the interpretation of Term in respect of Users acting in other capacities, for Users acting in respect of their Connection Sites which were not Commissioned at the Transfer Date, it means the term of the relevant Bilateral Connection Agreement commencing on the date of the Bilateral Connection Agreement and ending in accordance with Clause 9 of that agreement; "Termination Amount" in relation to a Connection Site, the amount calculated in accordance with the Charging Statements; "The Company" has the meaning given to NESO or National Energy System Operator; "The Company Credit any one of the following:- Rating"
a credit rating for long term debt of A- and A3 respectively as set by Standard and Poor’s or Moody’s respectively;
an indicative long term private credit rating of A- and A3 respectively as set by Standard and Poor’s or Moody’s as the basis of issuing senior unsecured debt;
a short term rating by Standard and Poor’s or Moody’s which correlates to a long term rating of A- and A3 respectively; or
where the User’s Licence issued under the Electricity Act 1989 requires that User to maintain a credit rating, the credit rating defined in that User’s Licence; "The Company’s the charges levied by The Company in relation to an application Engineering Charges" for connection and/or use of the National Electricity Transmission System; "The Company the forecast value of the regulatory asset value of NGET for a Prescribed Level" Financial Year as set out in the document published from time to time by Ofgem setting this out and currently know as "Ofgem’s Transmission Price Control Review of The Company – Transmission Owner Final Proposals" such values to be published on The Company Website by reference to The Company credit arrangements no later than 31 January prior to the beginning of the Financial Year to which such value relates; "Third Party Claim" as defined in Paragraph 7.5.3; "Third Party Works" in relation to a particular User those works, defined as such in its Construction Agreement; being works undertaken on assets belonging to someone other than a Relevant Transmission Licensee or the User where such works are required by The Company to enable it to provide the connection to and\or use of the National Electricity Transmission System by the User or required as a consequence of connection to and\or use of the National Electricity Transmission System by the User; “TNUoS Tariff Forecast an annual timetable prepared and published by The Company by Timetable” the end of January of each Financial Year (t) which sets out when The Company will publish updates in Financial Year (t+1) (being not less than quarterly) to the forecast of Transmission Network Use of System Charges for the Financial (t+2); "Total System" the National Electricity Transmission System and all User Systems in Great Britain and Offshore; "Total System the total of all half-hourly metered Demands for which HH Charges Chargeable HH are paid, taken over a period of time which may or may not be that Demand" to which HH Charges relate; "Total System the total of all half-hourly metered Demands for which NHH Chargeable NHH Charges are paid, taken over a period of time which may or may Demand" not be that to which NHH Charges relate; "Trading Party" as defined in the Balancing and Settlement Code; "Trading Unit" as defined in the Balancing and Settlement Code; "Transfer Date" "24.00" hours on 30th March 1990; "Transfer Scheme" schemes made under sections 65 and 66 of the Act and effected on the Transfer Date; “Transitional those Existing Agreements which have been entered into Agreements” following the Authority’s decision of 21 August 2024 on the transitional approach to offers provided for in the decision (and any subsequent extension to the time period for this approach) and which as a consequence have not been studied and so do not contain the usual detail and commitments regarding Construction Works and Construction Programme; "Transmission" when used in conjunction with another term relating to equipment, whether defined or not, that the associated term is to be read as being part of or directly associated with the National Electricity Transmission System and not of or with the User System; "Transmission the authorised business of The Company or any Affiliate or Business" Related Undertaking in the planning, development, construction and maintenance of the National Electricity Transmission System (whether or not pursuant to directions of the Secretary of State made under section 34 or 35 of the Act) and the operation of such system for the transmission of electricity, including any business in providing connections to the National Electricity Transmission System but shall not include (i) any other Separate Business or (ii) any other business (not being a Separate Business) of The Company or any Affiliate or Related Undertaking in the provision of services to or on behalf of any one or more persons; “Transmission the charging methodology forum (and related arrangements) Charging Methodology established to facilitate meetings between The Company and any Forum” other persons whose interests are materially affected by the applicable Charging Methodologies for the purpose of discussing the further development of the applicable Charging Methodologies; “Transmission as defined in the NETS SQSS; Circuits” "Transmission the Transmission Plant and Transmission Apparatus Connection Assets" necessary to connect the User's Equipment to the National Electricity Transmission System at any particular Connection Site in respect of which The Company charges Connection Charges (if any) as listed or identified in Appendix A to the Bilateral Connection Agreement relating to each such Connection Site; “Transmission the total sum of annual Transmission Network Use of Demand Residual” System revenue to be recovered through the Transmission Demand Residual Tariffs from Final Demand Sites and Unmetered Supplies only; “Transmission the £/site Transmission Network Use of System tariffs or Demand Residual £/kWh UMS Tariff that are levied on Final Demand Sites Tariffs” and Unmetered Supplies only; "Transmission in relation to a particular User, as defined in its Construction Connection Asset Agreement; Works" "Transmission Entry the figure specified as such as set out in Appendix C of the relevant Capacity" Bilateral Connection Agreement or Bilateral Embedded Generation Agreement; “Transmission where a Relevant Embedded Power Station with an agreement Evaluation” for connection to and/or for the use of a User’s Distribution System wants the User to make a Gate 2 Application in respect of its project; “Transmission an application by the owner/operator of a Distribution System for Evaluation Application” Transmission Evaluation (which application can be for one or more Relevant Embedded Power Stations) in the form or substantially the form set out in Appendix U; “Transmission Impact a means of conducting an Evaluation of Transmission Impact as Assessment” more fully described in the Bilateral Connection Agreement; "Transmission as defined in the Grid Code in the context of a Construction Interface Point" Agreement means the electrical point of connection between the Offshore Transmission System and an Onshore Transmission System as set out in the Offshore Works Assumptions; "Transmission the site at which the Transmission Interface Point is located; Interface Site" “Transmission the transmission licence or licences granted to one or all of the Licence(s)” Licensees: NGET, SP Transmission Limited, Scottish Hydro Electric Transmission Limited, any Competitively Appointed Transmission Owner and any Offshore Transmission Licensee under section 6(1)(b) of Act. References to “transmission licensee” and “transmission licensees” will be construed in the CUSC accordingly; "Transmission Network as defined in the Transmission Licence; Services" “Transmission the Plant and Apparatus owned by the Relevant Transmission Licensees Assets” Licensees necessary to connect the User's Equipment to the National Electricity Transmission System at any particular Connection Site in respect of which The Company charges Connection Charges (if any) as listed or identified in [Appendix A] to the Bilateral Agreement relating to each such Connection Site; "Transmission Network the element of Use of System Charges payable in respect of Use of System Transmission Network Services (including for the avoidance of Charges" doubt Transmission Network Use of System Demand Reconciliation Charges and ET Use of System Charges); "Transmission Network that element of Transmission Network Use of System Charges Use of System Demand relating to Demand, Final Demand Sites and Unmetered Charges" Supply; "Transmission Network each of the zones identified by The Company in the Charging Use of System Demand Statements for charging of Transmission Network Use of Zone" System Charges in relation to Demand; "Transmission Network sums payable by the User to The Company under invoices issued Use of System Demand to the User pursuant to Paragraph 3.12.7; Reconciliation Charges" “Transmission Owner the Function of the Relevant Transmission Licensees’ Activity” Transmission Business as defined in the Transmission Licences; “Transmission Owner the price index adjustment method as described in Part F of Special Price Index (TOPI)” Condition 2.1 of the Relevant Transmission Licensee’s Transmission Licence; "Transmission Related an agreement between The Company and a User substantially in Agreement" the form of Schedule 2 Exhibit 5; "Transmission as defined in the Transmission Licence; Services Activity" "Transmission the element of Use of System Charges payable in respect of the Services Use of System Transmission Services Activity; Charges" "Transmission in relation to a particular User, as defined in its Construction Reinforcement Works" Agreement or BELLA as appropriate; “Transmission in Scotland voltages of 132kV and above; in England and Wales Voltage” voltages above 132kV – usually 275kV and 400kV; "Transmission Works the register set up by The Company pursuant to Paragraph 6.36.1; Register" "Transmission Works" in relation to a particular User, those works which are specified in Appendix H or identified as OTSDUW in to the relevant Construction Agreement; “Triad” is used as a short hand way to describe the three Settlement Periods of highest transmission systems Demand, namely the half hour Settlement Period of system peak Demand and the two half hour Settlement Periods of next highest Demand, which are separated from the system peak Demand and from each other by at least 10 Clear Days, between November to February inclusive; “Trigger Date” as identified by The Company in accordance with Part Two of the User Commitment Methodology and in relation to a particular User as defined in its Construction Agreement; “UMS Base the % value of the relevant Security Period as specified in the Percentage” table in paragraph 2B Section 3, Appendix 2; “UMS Charges” that element of Transmission Network Use of System Demand Charges relating to Unmetered Supply; “UMS Base Value at the sum as calculated in accordance with Paragraph 3.23.4b; Risk” “UMS Tariff” a Transmission Demand Residual Tariff levied on Unmetered Supplies; “Unmetered Supply the amount of Energy associated with Unmetered Supply; Volume” “Unmetered Supply the forecast, produced by The Company, of the Unmetered Volume Forecast” Supply Volume; Unacceptable a failure of Plant and Apparatus forming part of the National Operating Electricity System Transmission System that results in the Condition following effect at the Connection Site: i) the loss of one or more phases causing an energy unbalance (Grid Code CC6.1.6); ii) frequency being outside the ranges listed in Grid Code CC6.1.3; iii) voltages being outside values stated in Grid Code CC6.1.4; iv) loss of synchronising signal to an Export BMU Unit; "Undertaking" as defined in section 259 of the Companies Act 1985; “Unmetered Supply” as defined in the Balancing and Settlement Code; "Unsecured Credit the maximum amount of unsecured credit available to each User Cover" for the purposes of Part III of Section 3 of the CUSC at any time which shall be a sum equal to 2% of the The Company Prescribed Level in the relevant Financial Year; "Unusual Load loads which have characteristics which are significantly different Characteristics" from those of the normal range of domestic, commercial and industrial loads (including loads which vary considerably in duration or magnitude); "Urgent CUSC an CUSC Modification Proposal treated or to be treated as an Modification Proposal" Urgent CUSC Modification Proposal in accordance with Paragraph 8.24; "Use of System" use of the National Electricity Transmission System for the transport of electricity by any Authorised Electricity Operator or Interconnector User or Interconnector Error Administrator; "Use of System an application for a Bilateral Embedded Generation Agreement Application" or for Use of System in the form or substantially in the form set out in Exhibit D or F to the CUSC as appropriate; "Use of System charges made or levied or to be made or levied by The Company Charges" for the provision of services as part of the Transmission Business to any Authorised Electricity Operator as more fully described at condition E10 of the ESO Licence and in the Bilateral Agreements and Section 3 and Section 9 Part II but which shall not include Connection Charges; “Use of System as defined in the Transmission Licence and set out in Section 14; Charging Methodology” "Use of System the part of the Use of System Interconnector Offer and Interconnector Confirmation Notice by which The Company confirms the use of Confirmation Notice" the National Electricity Transmission System by an Interconnector User or an Interconnector Error Administrator; "Use of System the notice which combines the offer and confirmation in relation to Interconnector Offer the use of the National Electricity Transmission System by an and Confirmation Interconnector User or an Interconnector Error Administrator, Notice" in the form set out in Exhibit H to the CUSC; "Use of System the part of the Use of System Interconnector Offer and Interconnector Offer Confirmation Notice by which The Company offers an Notice" Interconnector User or an Interconnector Error Administrator use of the National Electricity Transmission System; "Use of System Offer" an offer (or in the case of a use of system generation offer and where appropriate, offers) made by The Company to a User pursuant to Paragraph 3.7 or 9.19 substantially in the form of Exhibit G (Use of System Supply Offer) or Exhibit E (Use of System Generation Offer) or Exhibit H (Use of System Interconnector Offer) or Exhibit 7 Schedule 2 (Use of System Virtual Lead Party Offer) to the CUSC; "Use of System the date for payment of Use of System Charges; Payment Date" "Use of System Supply the part of the Use of System Supply Offer and Confirmation Confirmation Notice" Notice by which The Company confirms the use of the National Electricity Transmission System by a Supplier; "Use of System Supply the notice which combines the offer and confirmation in relation to Offer and Confirmation the use of the National Electricity Transmission System by a Notice" Supplier, in the form set out in Exhibit G to the CUSC; "Use of System Supply the part of the Use of System Supply Offer and Confirmation Offer Notice" Notice by which The Company offers a Supplier use of the National Electricity Transmission System; "User" a person who is a party to the CUSC Framework Agreement other than The Company; “User Commitment the methodology and principles applied by The Company in the Methodology” application and calculation of the Cancellation Charge and Cancellation Charge Secured Amount such principles being set out in CUSC Section 15; "User Development" shall have the meaning set out in the Connection Application or the Use of System Application as the case may be; “User Progression the Conditional Progression Milestones and Construction Milestones” Progression Milestones used for the purposes of the Queue Management Process to demonstrate that a User is progressing with that User’s project to the required timescales for that User’s project, the User Progression Milestones for a User (derived in accordance with CUSC Section 16) being set out in Appendix Q of the Construction Agreement relating to a specific User’s project; "User’s Allowed Credit" that proportion of the Unsecured Credit Cover extended to a User by The Company as calculated in accordance with Paragraph 3.26; "User Emergency the Deenergisation of the User’s Equipment or equipment for Deenergisation" which that User is responsible (as defined in Section K of the Balancing and Settlement Code) by a User pursuant to CUSC Paragraph 5.2.2 or by automatic means as a direct consequence of an Unacceptable Operating Condition; "User's Equipment" means; 1) the Plant and Apparatus owned by a User (ascertained in the absence of agreement to the contrary by reference to the rules set out in Paragraph 2.12) which: (a) is connected to (or in the case of OTSDUW Build will, at the OTSUA Transfer Time, be connected to) the Transmission Connection Assets forming part of the National Electricity Transmission System at any particular Connection Site to which that User wishes so to connect, or (b) is connected to a Distribution System to which that User wishes so to connect but excluding for the avoidance of doubt any OTSUA; 2) VLP Assets "User's Licence" a User's licence to carry on its business granted pursuant to Section 6 of the Act; "User System" any system owned or operated by a User comprising Generating Units and/or Distribution Systems (and/or other systems consisting (wholly or mainly) of electric lines which are owned or operated by a person other than a Public Distribution System Operator and Plant and/or Apparatus (including in the case of OTSDUW Build, any OTSUA prior to the OTSUA Transfer Time) connecting Generating Units, Distribution Systems (and/or other systems consisting wholly or mainly of electric lines which are owned or operated by a person other than a Public Distribution System Operator or Non-Embedded Customers to the National Electricity Transmission System or (except in the case of Non- Embedded Customers) to the relevant other User System, as the case may be, including any Remote Transmission Assets operated by such User or other person and any Plant and/or Apparatus and meters owned or operated by such User or other person in connection with the distribution of electricity but does not include any part of the National Electricity Transmission System; “Utilities Act 2000” Electricity Act 1989, as amended by the Utilities Act 2000; "Valid" valid for payment to be made thereunder against delivery of a Notice of Drawing given within the period stated therein; "Value Added Tax" United Kingdom value added tax or any tax supplementing or replacing the same; "Value At Risk the Proposed Amendment in respect of Amendment Proposal Amendment" 127; "Value At Risk the Implementation Date of the Value At Risk Amendment; Amendment Implementation Date" "Value At Risk the date one year following the Value At Risk Amendment Amendment Implementation Date; Implementation End Date" “Variations Clause” the clause in the Existing Agreements that requires The Company and the User to effect any amendment required to be made to those by the Authority as a result of a change in the CUSC, the ESO Licence or Transmission Licence, an order or direction made pursuant to the Act or a Licence or as a result of settling any of the terms thereof; “Voting Group” as defined in Paragraph 8A.3.1.2; "Voting Sub-Group” the Demand Voting Sub-Group, Generation Voting Sub-Group, Interconnector Voting Sub-Group and/or Supply Voting Sub- Group; “Virtual Lead Party as defined in the Balancing and Settlement Code (VLP)” “Virtual Lead Party an agreement entered into pursuant to Paragraph 1.3.1 a form of Agreement (VLPA)” which is set out in Exhibit 7 to Schedule 2; “VLP Assets” equipment owned or operated by a Virtual Lead Party which is part of a Secondary BM Unit; "Website" the site established by The Company on the World-Wide Web for the exchange of information among CUSC Parties and other interested persons in accordance with such restrictions on access as may be determined from time to time by The Company; "Week" a period of seven Calendar Days commencing at 05.00 hours on a Monday and terminating at 05.00 hours on the next following Monday; "Weekly Maximum has the meaning attributed to it in Paragraph 4.2.3.1; Generation Declaration" “Wider Cancellation a component of the Cancellation Charge that applies on and after the Trigger Date as more particularly described in Part Two of the Charge” User Commitment Methodology; “Wider Transmission in relation to a particular User means those Transmission Reinforcement Works” Reinforcement Works other than the Enabling Works and which are specified in the relevant Construction Agreement; "Workgroup" a Workgroup established by the CUSC Modifications Panel pursuant to Paragraph 8.20.1; "Workgroup as defined in Paragraph 8.20.13, and any further consultation Consultation" which may be directed by the CUSC Modifications Panel pursuant to Paragraph 8.20.20; "Workgroup any request from a CUSC Party, a BSC Party the Citizens Advice Consultation or the Citizens Advice Scotland for a Workgroup Alternative Alternative Request" CUSC Modification to be developed by the Workgroup expressed as such and which contains the information referred to at Paragraph 8.20.16. For the avoidance of doubt any WG Consultation Alternative Request does not constitute either a CUSC Modification Proposal or a Workgroup Alternative CUSC Modification; "Workgroup Alternative an alternative modification to the CUSC Modification Proposal CUSC Modification" developed by the Workgroup under the Workgroup terms of reference (either as a result of a Workgroup Consultation or otherwise) and which is believed by a majority of the members of the Workgroup or by the chairperson of the Workgroup to better facilitate the Applicable CUSC Objectives than the CUSC Modification Proposal or the current version of the CUSC. ANNEX 1 – INTERPRETATION AND DEFINITIONS Insert the following new definitions in alphabetical order: “Authority Led CUSC a proposal to modify the CUSC which directly arises Modification” from a Significant Code Review and where the process of the modification is led by the Authority in accordance with its SCR Guidance; “Authority Led CUSC a proposal for an Authority Led CUSC Modification Modification Proposal” which has been submitted pursuant to and in accordance with Section 8 Paragraph 8.17B; “Authority Led CUSC in relation to an Authority Led CUSC Modification Modification Report” Proposal, the report prepared pursuant to and in accordance with Section 8 Paragraph 8.17B.2; “Backstop Direction” has the meaning given to it in Section 8 Paragraph 8.17C; “SCR Guidance” any document of that title created, published as amended from time to time, by the Authority to provide guidance to interested parties on the conduct of a Significant Code Review by the Authority;
SECTION 12: NOT USED
SECTION 13: ENABLING WORKS
This Section 13 deals with the identification and assessment of the Enabling Works to be included in an Offer made under the Connect and Manage Arrangements and the assessment of the need for and scope of a Connect and Manage Derogation.
In making an Offer, the Construction Works (if any) which are required to be completed prior to connection and/or use of system are identified and set out in a Construction Agreement. Under the Connect and Manage Arrangements the Construction Agreement will identify:
in the case of an Onshore Connection Site or Onshore site of connection, which of the Transmission Reinforcement Works are the Enabling Works relevant to that Applicant; and
in the case of an Offshore Connection Site, which of the Onshore Transmission Reinforcement Works are the Enabling Works relevant to that Applicant. For the avoidance of doubt, any Offshore Transmission Reinforcement Works shall be in addition to and will not be affected by the Enabling Works identified pursuant to the Connect and Manage Arrangements.
The Connect and Manage Derogation Criteria shall be used to identify the extent and nature of the Enabling Works required in each offer of a Construction Agreement. Subject to Paragraph 13.2.5, it is anticipated that the Enabling Works shall not generally be greater than the MITS Connection Works. The Enabling Works shall not be less than those works required to satisfy the criteria set out in Paragraph 13.2.4.
Where the Enabling Works in any case as assessed in accordance with 13.2.2 above are such that connection and/or use of system on completion of such works but in advance of any identified Wider Transmission Reinforcement Works does not comply with the requirements of the NETS SQSS a Connect and Manage Derogation will be required. The Connect and Manage Derogation Criteria will be used to justify the need for and scope of such a Connect and Manage Derogation in the Connect and Manage Derogation Report.
The Enabling Works will as a minimum include (and, subject to 13.2.5.1 shall not exceed) those Transmission Reinforcement Works (in the case of an Onshore Connection Site or Onshore site of connection) or Onshore Transmission Reinforcement Works (in the case of an Offshore Connection Site) required to meet the following criteria (the Connect and Manage Derogation Criteria):
achieve compliance with the “Pre-fault Criteria” set out in Chapter 2 (Generation Connection Criteria Applicable to the Onshore Transmission System) of the NETS SQSS;
achieve compliance with the “Limits to Loss of Power Infeed Risks” set out in Chapter 2 (Generation Connection Criteria Applicable to the Onshore Transmission System) of the NETS SQSS;
enable The Company to operate the National Electricity Transmission System in a safe manner;
resolve any fault level issues associated with the connection and/or use of system by the Connect and Manage Power Station;
comply with the minimum technical, design and operational criteria and performance requirements under the Grid Code;
meet other statutory obligations including but not limited to obligations under any Nuclear Site Licence Provisions Agreement; and 13.2.4.7 avoid any adverse impact on other Users.
The Enabling Works set out in a Construction Agreement may only be greater than:
the works assessed as being required under 13.2.4 above where and to the extent that the Applicant or User has requested that this be the case (in its application or otherwise); and/or 13.2.5.2 the MITS Connection Works where and to the extent that 13.2.5.2.1 the Applicant or User has requested that this be the case (in its application or otherwise); or 13.2.5.2.2 The Company and/or the Relevant Transmission Licensee consider it necessary in order to satisfy the criteria set out in Paragraph 13.2.4.
MITS MAP The Company will include within the Electricity Ten Year Statement (ETYS) a map of the National Electricity Transmission System identifying the relevant MITS Substations for the purposes of the MITS Connection Works.
REPORT On or before the end of each Financial Year The Company shall publish a report showing:
by reference to the number of Offers made under the Connect and Manage Arrangements during that Financial Year, the percentage of Offers where the Enabling Works were above the MITS Connection Works and the percentage of Offers where the Enabling Works were below the MITS Connection Works; and
by reference to each Construction Agreement where the Enabling Works were completed during that Financial Year, the period of time that it took to complete those Enabling Works and the transmission owner that undertook them.
SECTION 14: CHARGING METHODOLOGIES
This section of the CUSC sets out the statement of the Connection Charging Methodology and the Statement of the Use of System Methodology Part 1 - The Statement of the Connection Charging Methodology
Principles Costs and their Allocation
Connection charges enable The Company to recover, with a reasonable rate of return, the costs involved in providing the assets that afford connection to the National Electricity Transmission System.
Connection charges relate to the costs of assets installed solely for and only capable of use by an individual User. These costs may include civil costs, engineering costs, and land clearance and preparation costs associated with the connection assets, but for the avoidance of doubt no land purchase costs will be included.
Connection charges are designed not to discriminate between Users or classes of User. The methodology is applied to both connections that were in existence at Vesting (30 March 1990) and those that have been provided since. Connection/Use of System Boundary
The first step in setting charges is to define the boundary between connection assets and transmission system infrastructure assets.
In general, connection assets are defined as those assets solely required to connect an individual User to the National Electricity Transmission System, which are not and would not normally be used by any other connected party (i.e. “single user assets”). For the purposes of this Statement, all connection assets at a given location shall together form a connection site.
Connection assets are defined as all those single user assets which: a) for Double Busbar type connections, are those single user assets connecting the User’s assets and the first transmission licensee owned substation, up to and including the Double Busbar Bay; b) for teed or mesh connections, are those single user assets from the User’s assets up to, but not including, the HV disconnector or the equivalent point of isolation; c) for cable and overhead lines at a transmission voltage, are those single user connection circuits connected at a transmission voltage equal to or less than 2km in length that are not potentially shareable.
Shared assets at a banked connection arrangement will not normally be classed as connection assets except where both legs of the banking are single user assets under the same Bilateral Connection Agreement.
Where customer choice influences the application of standard rules to the connection boundary, affected assets will be classed as connection assets. For example, in England & Wales NGET does not normally own busbars below 275kV, where The Company and the customer agree that NGET will own the busbars at a low voltage substation, the assets at that substation will be classed as connection assets and will not automatically be transferred into infrastructure.
The design of some connection sites may not be compatible with the basic boundary definitions in 14.2.6 above. In these instances, a connection boundary consistent with the principles described above will be applied.
The Calculation of the Basic Annual Connection Charge for an Asset Pre and Post Vesting Connections
Post Vesting connection assets are those connection assets that have been commissioned since 30 March 1990. Pre Vesting connection assets are those that were commissioned on or before the 30 March 1990.
The basic connection charge has two components. A non-capital component, for which both pre and post vesting assets are treated in the same way and a capital component for which there are slightly different options available for pre and post vesting assets. These are detailed below. Calculation of the Gross Asset Value (GAV)
The GAV represents the initial total cost of an asset to the transmission licensee. For a new asset it will be the costs incurred by the transmission licensee in the provision of that asset. Typically, the GAV is made up of the following components: Construction Costs - Costs of bought in services Engineering - Allocated equipment and direct engineering cost Interest During Construction – Financing cost Liquidated Damages Premiums - Premium required to cover Liquidated Damages if applicable. Some of these elements may be optional at the User’s request and are a matter of discussion and agreement at the time the connection agreement is entered into.
The GAV of an asset is re-valued each year normally using one of two methods. For ease of calculation, April is used as the base month. • In the Modern Equivalent Asset (MEA) revaluation method, the GAV is indexed each year with reference to the prevailing price level for an asset that performs the same function as the original asset; • In the Transmission Owner Price Index (TOPI) revaluation method, the original cost of an asset is indexed each year by the TOPI formula set out in paragraph 14.3.6. For Pre Vesting connection assets commissioned on or before 30 March 1990, the original cost is the 1996/97 charging GAV (MEA re-valued from vesting). The original costs of Post Vesting assets are calculated based on historical cost information provided by the transmission licensee’s.
In the MEA revaluation method, the MEA value is based on a typical asset. An MEA ratio is calculated to account for specific site conditions, as follows: • The outturn GAV (as calculated in paragraph 14.3.4 above) is re-indexed by TOPI to the April of the Financial Year the Charging Date falls within; • This April figure is compared with the MEA value of the asset in the Financial Year the Charging Date falls within and a ratio calculated; • If the asset was commissioned at a Connection Site where, due to specific conditions, the asset cost more than the standard MEA value, the ratio would be greater than 1. For example, if an asset cost 10% more to construct and commission than the typical asset the MEA ratio would be 1.1. If, however, the asset was found only to cost 90% of the typical MEA value the ratio would be 0.9; • The MEA ratio is then used in all future revaluations of the asset. The April GAV of the asset in any year is thus the current MEA value of the asset multiplied by the ratio calculated for the Financial Year the Charging Date falls within.
The TOPI revaluation method is as follows: • The outturn GAV (as calculated in paragraph 14.3.4 above) is re-indexed by TOPI to the April of the Financial Year the Charging Date falls within. This April GAV is thus known as the Base Amount; • The Base Amount GAV is then indexed to the following April by using the TOPI formula used in the Transmission Owner’s Price Control. April GAVs for subsequent Financial years are found using the same process of indexing by TOPI. i.e. GAV = GAV * TOPI n n-1 n • TOPI calculation for year n is as follows: Calculation of Net Asset Value
The Net Asset Value (NAV) of each asset for year n, used for charge calculation, is the average (mid year) depreciated GAV of the asset. The following formula calculates the NAV of an asset, where A is the age of the asset (number of n completed Financial Years old) in year n: D e p r e c i a t i o n P e r i o d − ( A + 0 . 5 ) n N A V = G A V * n n D e p r e c i a t io n P e r i o d
In constant price terms an asset with an initial GAV of £1m and a depreciation period of 40 years will normally have a NAV in the year of its commissioning of £0.9875m (i.e. a reduction of 1.25%) and in its second year of £0.9625m (i.e. a further reduction of 2.5% or one fortieth of the initial GAV). This process will continue with an annual reduction of 2.5% for each year of the asset's life. Capital Components of the Connection charge for Post Vesting Connection Assets
The standard terms for a connection offer will be: • 40 year life (with straight line depreciation); • TOPI indexation
In addition a number of options exist: • a capital contribution based on the allocated GAV at the time of commissioning will reduce capital. Typically a capital contribution made in advance of or at the time of commissioning will include costs to cover the elements outlined below and charges are calculated as set out in the equations below; − Construction costs − Engineering costs (Engineering Charge x job hours) − Interest During Construction (IDC) − Return element (6%) − Liquidated Damages Premium (LD) (if applicable) General Formula: Capital Contribution Charge = (Construction Costs + Engineering Charges) x (1+Return %) + IDC + LD Premium • The MEA and TOPI revaluation methods are described further in 14.3.21. As an example, we will assume MEA revaluation is a 7.5% rate of return, AND 6% on the TOPI revaluation basis; • annual charges based on depreciation periods other than 40 years; • annuity based charging; • indexation of GAVs based on principles other than MEA revaluation and TOPI indexation. No alternative forms of indexation have been employed to date.
For new connection assets, should a User wish to agree to one or more of the options detailed above, instead of the standard connection terms, the return elements charged by the transmission licensee may also vary to reflect the re-balancing of risk between the transmission licensee and the User. For example, if Users choose a different indexation method, an appropriate rate of return for such indexation method will be derived.
A User can choose to make a capital contribution based on the allocated and depreciated NAV of a commissioned asset. For a capital contribution to take account at the start of Financial Year n, the User may, at most once per year, make a full or partial capital contribution of at least 10% of the NAV prevailing as of 31st March in year n-1. The User shall notify The Company of the capital contribution amount no later than 1st September in year n-1, and pay the capital contribution 45 days prior to the start of Financial Year n which will be applied to the NAV prevailing at the start of year n. As the capital component of the connection charge for year n will reduce as a result of the capital contribution, a reduced rate of return element will be payable and a lower security requirement will be required in Financial Year n and subsequent years. Capital Components of the Connection charge for Pre Vesting Connection Assets
The basis of connection charges for GB assets commissioned on or before 30 March 1990 is broadly the same as the standard terms for connections made since 30 March 1990. Specifically charges for pre vesting connection assets are based on the following principles: • The GAV is the 1996/97 charging GAV (MEA re-valued from vesting) subsequently indexed by the same measure of TOPI as used in the Transmission Owner’s Price Control; • 40 year life (with straight line depreciation); • 6% rate of return
Pre-vesting 1996 MEA GAVs for Users’ connection sites are available from The Company on request from the Charging Team. Non-Capital Components - Charging for Maintenance and Transmission Running Costs
The non-capital component of the connection charge is divided into two parts, as set out below. Both of these non-capital elements will normally be identified in the charging appendices of relevant Bilateral Agreements. Part A: Site Specific Maintenance Charges
This is a maintenance only component that recovers a proportion of the costs and overheads associated with the maintenance activities conducted on a site-specific basis for connection assets of the transmission licensees.
Site-specific maintenance charges will be calculated each year based on the forecast total site specific maintenance for NETS divided by the total GAV of the transmission licensees NETS connection assets, to arrive at a percentage of total GAV. For 2010/11 this will be 0.52%. For the avoidance of doubt, there will be no reconciliation of the site-specific maintenance charge. Part B: Transmission Running Costs
The Transmission Running Cost (TRC) factor is calculated at the beginning of each price control to reflect the appropriate amount of other Transmission Running Costs (rates, operation, indirect overheads) incurred by the transmission licensees that should be attributed to connection assets.
The TRC factor is calculated by taking a proportion of the forecast Transmission Running Costs for the transmission licensees (based on operational expenditure figures from the latest price control) that corresponds with the proportion of the transmission licensees’ total connection assets as a function of their total business GAV. This cost factor is therefore expressed as a percentage of an asset's GAV and will be fixed for the entirety of the price control period. The currently applicable TRC factor, calculated as above, is detailed in the Statement of Use of System Charges which is available from the Website.
To illustrate the calculation, the following example uses the average operating expenditure from the published price control and the connection assets of each transmission licensee expressed as a percentage of their total system GAV to arrive at the 2010/11 GB TRC value of 1.45%: Example: Connection assets as a percentage of total system GAV for each TO: Published current price control average annual operating expenditure (£m):
| Scottish Power Transmission Ltd | 15.1% |
|---|---|
| Scottish Hydro Transmission Ltd | 8.6% |
| NGET | 12.5% |
| Scottish Power Transmission Ltd | 29.1 |
|---|---|
| Scottish Hydro Transmission Ltd | 11.3 |
The charge for each connection asset in Financial Year n can be derived from the general formula below. This is illustrated more fully by the examples in Appendix 2: Examples of Connection Charge Calculations. Annual Connection Charge = D (GAV ) + R (NAV ) + SSF (TOPIGAV ) + n n n n n n n TC (GAV ) n n Where: For n = year to which charge relates within the Depreciation Period n = year to which charge relates GAV = GAV for year n re-valued by relevant indexation method n TOPIGAV = GAV for year n re-valued by TOPI indexation n NAV = NAV for year n based on re-valued GAV n n D = Depreciation rate as percentage (equal to 1/Depreciation n Period(typically 1/40 = 2.5% of GAV) R = For assets subject to TOPI indexation, the real pre-tax Weighted n Average Cost of Capital for the Relevant Transmission Licensee for year n (WACCn). For asset subject to MEA indexation, the real pre-tax Weighted Average Cost of Capital for the Relevant Transmission Licensee for year n (WACCn) plus 1.5 percentage points. Where for the year n: 𝑟𝑒𝑎𝑙 𝑝𝑜𝑠𝑡 𝑡𝑎𝑥 𝑐𝑜𝑠𝑡 𝑜𝑓 𝑒𝑞𝑢𝑖𝑡𝑦 𝑊𝐴𝐶𝐶𝑛 = (( ) × (1−𝑛𝑜𝑡𝑖𝑜𝑛𝑎𝑙 𝑔𝑒𝑎𝑟𝑖𝑛𝑔 %)) 1−𝑐𝑜𝑟𝑝𝑜𝑟𝑎𝑡𝑖𝑜𝑛 𝑡𝑎𝑥 𝑟𝑎𝑡𝑒 + (𝑟𝑒𝑎𝑙 𝑐𝑜𝑠𝑡 𝑜𝑓 𝑑𝑒𝑏𝑡 ×𝑛𝑜𝑡𝑖𝑜𝑛𝑎𝑙 𝑔𝑒𝑎𝑟𝑖𝑛𝑔 %) And where for the calculation of WACCn: The real post-tax cost of equity, notional gearing %, real cost of debt and the corporation tax rate, are as specified in the latest published Ofgem Price Control Financial Model (PCFM) relating to year n, or should Ofgem fail to publish or cease to publish a PCFM, those specified in the latest public regulatory determination(s) or decision(s) should be used. SSF = Site Specific Factor for year n as a % (equal to the Site n Specific Cost/Total Site GAV) TC = Transmission Running Cost component for year n (other n Transmission Owner Activity costs). For n = year to which charge relates beyond the Depreciation Period n = year to which charge relates GAV = GAV for year n re-valued by relevant indexation method n TOPIGAV = GAV for year n re-valued by TOPI indexation n NAV = 0 n D = 0 n R = 0 n SSF = Site Specific Factor for year n as a % (equal to the Site n Specific Cost/Total Site GAV) TC = Transmission Running cost component for year n (other n Transmission Owner Activity costs).
Note that, for the purposes of deriving asset specific charges for site-specific maintenance, the TOPI re-valued GAV is used. This is to ensure that the exact site charges are recovered from the assets at the site. The site costs are apportioned to the assets on the basis of the ratio of the asset GAV to total Site GAV. Adjustment for Capital Contributions
If a User chooses to make a 100% capital contribution (either pre-commissioning or post-commissioning) to The Company towards their allocation of a connection asset then no capital charges will be payable and hence the connection charges for that asset would be calculated as follows: Annual Connection Charge = SSF (TOPIGAV ) + TC (GAV ) n n n n n
If a User chooses to make a partial capital contribution(s) (either pre-commissioning or post-commissioning) to The Company towards their allocation of a connection asset, for example PCCF = 50%, then the connection charges for that asset would be calculated as follows: Annual Connection Charge = D (GAV *PCCF) + R (NAV *PCCF) + SSF n n n n n n (TOPIGAV ) + TC (GAV ) n n n PCCF = Partial Capital Contribution Factor taking into account a capital contribution made pre-commissioning compared to the GAV (as outlined in 14.3.10), and any capital contributions made post-commissioning compared to the appropriate NAV (as outlined in 14.3.12) as appropriate. Modification of Connection Assets
Where a modification to an existing connection occurs at the User’s request or due to developments to the transmission system, their annual connection charges will reflect any additional connection assets that are necessary to meet the User's requirements. Charges will continue to be levied for existing assets that remain in service. Termination charges as described in Chapter 5 below will be charged for any existing connection assets made redundant as a result of the modification.
In addition to the basic annual connection charges set out above, the User may pay The Company for certain other costs related to their connection. These will be set out in the Bilateral and Construction Agreements where appropriate and are described below. One-off Works
To provide or modify a connection, the transmission licensee may be required to carry out works on the transmission system that, although directly attributable to the connection, may not give rise to additional connection assets. These works are defined as “one-offs”. Liability for one-off charges is established with reference to the principles laid out below: • Where a cost cannot be capitalised into either a connection or infrastructure asset, typically a revenue cost • Where a non-standard incremental cost is incurred as a result of a User's request, irrespective of whether the cost can be capitalised • Termination Charges associated with the write-off of connection assets at the connection site. Consistent with these principles and in accordance with Connection Charging Methodology modification GB ECM-01, which was implemented on 1 December 2005, a one-off charge will be levied for a Category 1 Intertripping Scheme or a Category
Intertripping Scheme. A one-off charge will not be levied for a Category 2 Intertripping Scheme or a Category 4 Intertripping Scheme.
The one-off charge is a charge equal to the cost of the works involved, together with a reasonable return, as shown in 14.4.4 below.
For information, the general formula for the calculation of the one-off charge for works is outlined below. One-off Charge = (Construction Costs + Engineering Charges) x (1 + Return %) + IDC + LD Premium Where: Engineering Charges = “Engineering Charge” x job hours Return % = 6% IDC = Interest During Construction LD Premium = The Company Liquidated Damages Premium (if applicable)
The calculation of the one-off charge for write-off of assets is outlined below: Write-off Charge = 100% of remaining NAV of redundant assets
One-offs are normally paid on an agreed date, which is usually upon completion of the works. However, arrangements may be agreed between the transmission licensee and the User to pay the charge over a longer period. If a one-off is paid over a longer period it is termed a Transmission Charge. It is usually a depreciating finance charge or annuity based charge with a rate of return element and may include agreement on a schedule of termination payments if the agreement is terminated before the end of the annuity period. The charge is usually inflated annually by the same TOPI figure that is used to inflate GAVs, though Users can request alternative indexation methods.
Where an infrastructure asset has been subject to One-off Works, and a User has paid a relating charge calculated in accordance with paragraph 14.4.4, The Company may adjust the treatment of the assets within the TNUoS transport model as set out in paragraphs 14.15.15 to 14.15.22. Miscellaneous Charges
Other contract specific charges may be payable by the User, these will be set out in the Bilateral and Construction Agreements where appropriate. Rental sites
Where The Company owns a site that is embedded within a distribution network, the connection charge to the User is based on the capital costs and overheads but does not include maintenance charges. Final Metering Scheme (FMS)/Energy Metering Systems
Charges for FMS metering are paid by the registrant of the FMS metering at the connection site. It is charged on a similar basis as other Connection Assets. The electronic components of the FMS metering have a replacement and depreciation period in line with those advised by the transmission licensees, whilst the non- electronic components normally retain a 40 year replacement and depreciation period (or a User specified depreciation period as appropriate).
Connection Agreements Indicative Agreement
The standard connection agreement offered by The Company is an indicative price agreement. From the Charging Date as set out in the User's Bilateral Connection Agreement, the User's initial connection charge is based on a fair and reasonable estimate of the expected costs of the connection. Outturning the Indicative Agreement
Once the works required to provide a new or modified connection are completed and the costs finalised, the connection scheme is "outturned". The Company reconciles the monies paid by the User on the indicative charge basis against the charges that would have been payable based on the actual costs incurred in delivering the project together with any relevant interest. This process involves agreeing a new charging GAV (The Base Amount) with the User in line with the elements stated in paragraph 14.3.3 and then calculating connection charges with this GAV.
In addition, for Users that have chosen MEA revaluation their MEA ratios are agreed at outturn and this ratio is used for MEA revaluation in subsequent years.
In the case of connection asset replacement where there is no initiating User, the outturn is agreed with the User at the site. Firm Price Agreement
In addition to the options stated in paragraph 14.3.10 above, firm price agreements are also available. Typically with this option the charges to be incurred, and any indexation, are agreed between The Company and the User and connection charges are not recalculated once outturn costs are known. A typical example of a firm price agreement is: − Capital Contribution − Firm Price GAV − Running Costs (based on a firm price GAV) − Fixed Schedule of Termination Amounts
When a User selects a firm price agreement some or all of the above elements can be made firm. Any elements of the agreement that have not been made firm will be charged on an indicative basis in accordance with this statement.
Final Sums and Consents costs are never made firm in a Firm Price Agreement. Details of both are set out in the Construction Agreement. Monthly Connection Charges
The connection charge is an annual charge payable monthly.
If the initial Charging Date does not fall within the current Financial Year being charged for and there are no revisions to charges during the year, the monthly connection charge will equal the annual connection charge divided by twelve.
For the Financial Year in which the Charging Date occurs (as set out in the User's Bilateral Agreement) or for any Financial Year in which a revision to charges has occurred during the Financial Year, for each complete calendar month from the Charging Date (or effective date of any charge revision) to the end of the Financial Year in which the Charging Date (or charge revision) occurs, the monthly connection charge shall be equal to the annual connection charge divided by twelve.
For each part of a calendar month, the charge will be calculated as one twelfth of the annual connection charge prorated by the ratio of the number of days from and including the Charging Date to the end of the month that the Charging Date falls in and the number of days in that month.
For example, say the annual connection charge for Financial Year 2010/11 is £1.2m and the Charging Date falls on the 15th November 2010, the monthly charges for the Financial Year 2010/11 would be as follows: • November = £1,200,000/12 * (16/30) = £53,333.33 • Dec 10, Jan 11, Feb 11, Mar 11 = £1,200,000/12 = £100,000.00
The above treatment does not apply to elements such as Miscellaneous Charges (as defined in 14.4.8) and Transmission Charges (annuitised one-offs, as defined in 14.4.6). If the Charging Date falls within a Financial Year, then the full annual charge will remain payable and will be spread evenly over the remaining months. This is because these payments are an annuitisation of charges that would normally be paid up-front as one-off payments.
Termination Charges Charges Liable
Where a User wholly or partially disconnects from the transmission system they will pay a termination charge. The termination charge will be calculated as follows: • Where the connection assets are made redundant as a result of the termination or modification of a Bilateral Connection Agreement, the User will be liable to pay an amount equal to the NAV of such assets as at the end of the Financial Year in which termination or modification occurs, plus: • The reasonable costs of removing such assets. These costs being inclusive of the costs of making good the condition of the connection site • If a connection asset is terminated before the end of a Financial Year, the connection charge for the full year remains payable. Any remaining Use of System Charges (TNUoS and BSUoS) also remain payable • For assets where it has been determined to replace upon the expiry of the relevant Replacement Period in accordance with the provisions set out in the CUSC and in respect of which a notice to Disconnect or terminate has been served in respect of the Connection Site at which the assets were located; and due to the timing of the replacement of such assets, no Connection Charges will have become payable in respect of such assets by the User by the date of termination; the termination charges will include the reasonable costs incurred by the transmission licensee in connection with the installation of such assets • Previous capital contributions paid to The Company will be taken into account
The Calculation of Termination amounts for Financial Year n is as follows: Termination Charge = UoS + C + NAV + R - CC n n n an Where: UoS = Outstanding Use of System Charge for year (TNUoS and BSUoS) n C = Outstanding Connection Charge for year n NAV = NAV of Type A assets as at 31 March of Financial Year n an R = Reasonable costs of removal of redundant assets and making good CC = An allowance for previously paid capital contributions
Examples of reasonable costs of removal for terminated assets and making good the condition of the site include the following: • If a circuit breaker is terminated as a result of a User leaving a site, this may require modifications to the protection systems. • If an asset were terminated and its associated civils had been removed to 1m below ground then the levels would have to be made up. This is a common condition of planning consent. Repayment on Re-Use of Assets
If any assets in respect of which a termination charge was made to The Company are re-used at the same site or elsewhere on the system, including use as infrastructure assets, The Company will make a payment to the original terminating User to reflect the fact that the assets are being reused.
The arrangements for such repayments for re-use of Assets are that The Company will pay the User a sum equal to the lower of: i.) the Termination Amount paid in respect of such Assets; or ii.) the NAV attributed to such Assets for charging purposes upon their re-use less any reasonable costs incurred in respect of the storage of those assets.
The definition of re-use is set out in the CUSC. Where The Company decides to dispose of a terminated asset where it is capable of re-use, The Company shall pay the User an appropriate proportion of the sale proceeds received. Valuation of Assets that are re-used as connection assets or existing infrastructure assets re-allocated to connection
If an asset is reused following termination or allocated to connection when it has previously been allocated to TNUoS, a value needs to be determined for the purposes of connection charges. In both instances the connection charge will be based on the standard formula set out in paragraph 14.3.21. The Gross Asset Value will be based on the original construction costs and indexed by TOPI. Where original costs are not known a reasonable value will be agreed between The Company and the User based on similar types of asset in use. The Net Asset Value will be calculated as if the asset had been in continuous service as a connection asset from its original commissioning date taking into account the depreciation period.
Where an asset has been refurbished or updated to bring it back into service a new value and an appropriate replacement period will be agreed between The Company and the User. This will be based on the value of similar types of asset in service and the costs of the refurbishment.
Some connection activities may be undertaken by the User. The activities are the provision, or construction, of connection assets, the financing of connection assets and the ongoing maintenance of those assets. While some Users have been keen to see contestability wherever possible, contestability should not prejudice system integrity, security and safety. These concerns have shaped the terms that are offered for contestability in construction and maintenance. Contestability in Construction
Users have the option to provide (construct) connection assets if they wish. Formal arrangements for Users exercising this choice are available and further information on User choice in construction can be obtained from The Company.
Appendix A of a User's Bilateral Connection Agreement specifies the age (number of complete Financial Years old), for charging purposes, of each of the NETS connection assets at the Connection Site for the corresponding Financial Year. Connection charges are calculated on the assumption that the assets will not need to be replaced until the charging age has reached the duration of the asset’s Replacement Period. If a connection asset is to be replaced, The Company will enter into an agreement for the replacement with the User. Where replacement occurs before the original asset’s charging age has reached the duration of its Replacement Period, The Company will continue to charge for the original asset and make no charge to the existing User for the new asset until the original asset’s charging age has reached the duration of its Replacement Period. Where the replacement occurs after the original asset’s charging age has reached the duration of its Replacement Period, The Company will charge on the basis of the original asset until replaced and on the basis of the new asset on completion of the works.
When the original asset’s charging age has reached the duration of its Replacement Period the User’s charge will be calculated on the then Net Asset Value of the new asset. The new asset begins depreciating for charging purposes upon completion of the asset replacement. The Basic Annual Connection Charge Formulae are set out in Chapter 2: The Basic Annual Connection Charge Formula. Asset Replacement that includes a change of Voltage
There are a number of situations where an asset replacement scheme may involve a change in the voltage level of a User's connection assets. These replacement schemes can take place over a number of years and may involve a long transitory period in which connection assets are operational at both voltage levels.
These situations are inevitably different from case to case and hence further charging principles will need to be developed over time as more experience is gained. Set out below, are some generic principles. This methodology will be updated as experience develops.
The general principles used to date are to ensure that, in the transitory period of an asset replacement scheme, the User does not pay for two full transmission voltage substations and that the charges levied reflect the Replacement Period of the original connection assets. In addition, in line with paragraph 14.8.1 above, charges will only be levied for the new assets once the original assets would have required replacement.
For example, a transmission licensee in investing to meet a future Security Standard need on the main transmission system, may require the asset replacement of an existing 275kV substation with a 400kV substation prior to the expiry of the original assets’ Replacement Period. In this case, The Company will seek to recover the connection asset component via connection charges when the assets replaced were due for asset replacement. Prior to this, the User should not see an increase in charges and therefore the investment costs would be recovered through TNUoS charges. In addition, if in the interim stage the User has, say, one transformer connected to the 275kV substation and one transformer connected to the 400kV substation, the charge will comprise an appropriate proportion of the HV assets at each site and not the full costs of the two substations. Note that the treatment described above is only made for transitory asset replacement and not enduring configurations where a User has connection assets connected to two different voltage substations.
Under the connection charging methodology no data is required from Users in order to calculate the connection charges payable by the User.
Application fees are payable in respect of applications for new connection agreements and modifications to existing agreements based on the reasonable costs transmission licensees incur in processing these applications. Users can opt to pay a fixed price application fee in respect of their application or pay the actual costs incurred. The fixed price fees for applications are detailed in the Statement of Use of System Charges.
If a User chooses not to pay the fixed fee, the application fee will be based on an advance of transmission licensees’ Engineering and out-of pocket expenses and will vary according to the size of the scheme and the amount of work involved. Once the associated offer has been signed or lapses, a reconciliation will be undertaken. Where actual expenses exceed the advance, The Company will issue an invoice for the excess. Conversely, where The Company does not use the whole of the advance, the balance will be refunded.
The Company will refund the first application fee paid (the fixed fee or the amount post-reconciliation) made under the Construction Agreement for new or modified existing agreements. The refund shall be made either on commissioning or against the charges payable in the first three years of the new or modified agreement. The refund will be net of external costs.
The Company will not refund application fees for applications to modify a new agreement or modified existing agreement at the User’s request before any charges become payable. For example, The Company will not refund an application fee to delay the provision of a new connection if this is made prior to charges becoming payable.
Illustrative Connection Charges From 2021/22 First Year Connection Charges based on the TOPI Method (6% rate of return used as an example)
The following table provides an indication of typical charges for new connection assets. Before using the table, it is important to read through the notes below as they explain the assumptions used in calculating the figures. Calculation of Gross Asset Value (GAV)
The GAV figures in the following table were calculated using the following assumptions: • Each asset is new • The GAV includes estimated costs of construction, engineering, Interest During Construction and Liquidated Damages premiums For details of the Calculation of the Gross Asset Value, see Chapter 2 of this Statement. Calculation of first year connection charge
The first year connection charges in the following table were calculated using the following assumptions: • The assets are new • The assets are depreciated over 40 years • The rate of return is assumed to be 6% for TOPI indexation • The connection charges include maintenance costs at a rate of 0.52% of the GAV • The connection charges include Transmission Running Costs at a rate of 1.45% of the GAV For details of the Basic Annual Connection Charge Formula, see Chapter 2 of this Statement. Please note that the actual charges will depend on the specific assets at a site. Agreement specific NAVs and GAVs for each User will be made available on request. Notes on Assets The charges for Double and Single Busbar Bays include electrical and civil costs. Transformer cable ratings are based on winter soil conditions. In this example, transformer charges include civil costs of plinth and noise enclosure and estimated transport costs, but not costs of oil dump tank and fire trap moat. Transport costs do not include hiring heavy load sea transportation or roll-on roll-off ships. Connection Examples Example 1
| £000’s | ||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 400kV | 275kV | 132kV | ||||||||||||||||
| GAV | Charge | GAV | Charge | GAV | Charge | |||||||||||||
| Double Busbar Bay Single Busbar Bay | 2300 1830 | 239 190 | 1890 | 197 | 630 460 | 65 50 | ||||||||||||
| Transformer Cables 100m (incl. Cable sealing ends) 120MVA 180MVA 240MVA 750MVA | 970 970 980 1135 | 100 101 102 118 | 310 320 355 | 30 30 37 | ||||||||||||||
| 1480 1520 1540 | 150 158 160 | |||||||||||||||||
| Transformers 45MVA 132/66kV 90MVA 132/33kV 120MVA 275/33kV 180MVA 275/66kV 180MVA 275/132kV 240MVA 275/132kV 240MVA 400/132kV | 1060 102 0 | 110 106 | ||||||||||||||||
| 2110 2560 2180 2630 | 219 266 227 273 | |||||||||||||||||
| 3180 | 340 |
0 0 /1 3 2 k V
3 2 /3 3 k V F irs t Y e a r F irs t Y e a r C h a rg e s C h a rg e s R e f D e s c rip tio n D e s c rip tio n (£ 0 0 0 s ) (£ 0 0 0 s ) K E Y : A
3 0 4 7 8 2 x D o u b le B u s b a r 2 x D o u b le B u s b a r E xis tin g T ra n s m is s io n A s s e ts (in fra s tru c tu re ) T ra n s fo rm e r B a ys T ra n s fo rm e r B a ys N e w T ra n s m is s io n A s s e ts (in fra s tru c tu re ) B
1 2 6 8 0 2 x 9 0 M V A T ra n s fo rm e rs 2 x 2 4 0 M V A T ra n s fo rm e rs N e w c o n n e c tio n a s s e ts w h o lly c h a rg e d to C 2 0 7 4 2 x 1 0 0 m 9 0 M V A C a b le s 2 x 1 0 0 m 2 4 0 M V A C a b le s c u s to m e r D 2 0
3 0 2 x D o u b le B u s b a r 2 x D o u b le B u s b a r C u s to m e r A s s e ts T ra n s fo rm e r B a ys T ra n s fo rm e r B a ys 3 8 2
3 6 2 T o ta l T o ta l Example 3 E X T E N S I O N O F S I N G L E S W I T C H M E S H T O F Oi Un R S W I T C H M E S H ( e x t e n s o t o s i n g l e u s e r s i t e ) T r a n s m i s s i o n V o l t a g e A A B B C C L o w e r V o l t a g e D D S C H E D U L E F O R N E W C O N N E C T IO N 4 0 0 /1 3 2 k V
3 2 /3 3 k V F irs t Y e a r F irs t Y e a r C h a rg e s C h a rg e s K E Y : D e s c rip tio n f (£ 0 0 0 s ) R e D e s c rip tio n (£ 0 0 0 s ) E xis tin g T ra n s m is s io n A s s e ts (in fra s tru c tu re ) N e w T ra n s m is s io n A s s e ts (in fra s tru c tu re ) A 7 4 2 x 1 0 0 m 2 4 0 M V A C a b le s 3 1 6 2 x 1 0 0 m 2 4 0 M V A C a b le s N e w c o n n e c tio n a s s e ts w h o lly c h a rg e d to c u s to m e r B
1 2 2 x 9 0 M V A T ra n s fo rm e rs 6 8 0 2 x 2 4 0 M V A T ra n s fo rm e rs E xis tin g c o n n e c tio n a s s e ts w h o lly c h a rg e d to C 2 0 2 x 1 0 0 m 9 0 M V A C a b le s 7 4 2 x 1 0 0 m 2 4 0 M V A C a b le s a n o th e r u s e r C u s to m e r A s s e ts D 2 0 2 x D o u b le B u s b a r
3 0 2 x D o u b le B u s b a r T ra n s fo rm e r B a y s T ra n s fo rm e r B a y s O th e r U s e rs A s s e ts 3 2 6 T o ta l
2 0 0 T o ta l
Examples of Connection Charge Calculations The following examples of connection charge calculations are intended as general illustrations. Example 1
This example illustrates the method of calculating the first year connection charge for a given asset value. This method of calculation is applicable to indicative price agreements for new connections, utilising the TOPI method of charging, and assuming: i) the asset is commissioned on 1 April 2010 ii) there is no inflation from year to year i.e. GAV remains constant iii) the site specific maintenance charge component remains constant throughout the 40 years at 0.52% of GAV iv) the Transmission Running Cost component remains constant throughout the 40 years at 1.45% of GAV v) the asset is depreciated over 40 years vi) the rate of return charge remains constant at 6% for the 40 year life of the asset vii) the asset is terminated at the end of its 40 year life For the purpose of this example, the asset on which charges are based has a Gross Asset Value of £3,000,000 on 1 April 2010. Charge Calculation Site Specific Maintenance Charge 3,000,000 x 0.52% £15,600 (0.52% of GAV) Transmission Running Cost 3,000,000 x 1.45% £43,500 (1.45% of GAV) Capital charge 3,000,000 x 2.5% £75,000 (40 year depreciation 2.5% of GAV) Return on mid-year NAV 2,962,500 x 6% £177,750 (6%) TOTAL £311,850 The first year charge of £311,850 would reduce in subsequent years as the NAV of the asset is reduced on a straight-line basis. This gives the following annual charges over time (assuming no inflation): Year Charge
£311,850
£307,350 10 £271,350 40 £136,350 Based on this example, charges of this form would be payable until 31 March 2050. Example 2
The previous example assumes that the asset is commissioned on 1 April 2010. If it is assumed that the asset is commissioned on 1 July 2010, the first year charge would equal 9/12th of the first year annual connection charge i.e. £233,887.50 This gives the following annual charges over time: Year Charge
£233,887.50 (connection charge for period July to March)
£307,350 10 £271,350 40 £136,350 Example 3
In the case of a firm price agreement, there will be two elements in the connection charge, a finance component and a running cost component. These encompass the four elements set out in the examples above. Using exactly the same assumptions as those in example 1 above, the total annual connection charges will be the same as those presented. These charges will not change as a result of the adoption of a different charging methodology by The Company, providing that the connection boundary does not change. Example 4
If a User has chosen a 20-year depreciation period for their Post Vesting connection assets and subsequently remains connected at the site beyond the twentieth year their charges are calculated as follows. For years 21-40 they will pay a connection charge based on the following formula: Annual Connection Charge = SSF (TOPIGAV )+ TC (GAV ) n n n n n The NAV will be zero and the asset will be fully depreciated so there will be no rate of return or depreciation element to the charge.
Nominally Over Equipped Connection Sites
This chapter outlines examples of ways in which a connection site can be considered as having connection assets that exceed the strict, theoretical needs of the individual Users at the connection site. These can be described as: Historical
This is where the connection assets at the connection site were installed to meet a requirement of the Users for connection capacity that no longer exists. An example would be where a User, at one time, had a requirement for, say, 270 MW. This would allocate three 240 MVA 400/132kV transformers to the User. Due to reconfiguration of that User’s network only 200 MW is now required from the connection site. The lower requirement would only allocate two transformers, but all the transformers are kept in service. The connection assets will continue to be assigned to the User’s connection, and charged for as connection, until the User makes a Modification Application to reduce the historical requirement. In some cases the Modified requirement will mean that Termination Payments will have to be made on some connection assets. Early Construction
If a User has a multi-phase project, it may be necessary to install connection assets for the latter phases at the time of the first phase. These connection assets could be charged from the first phase charging date. Connection site Specific Technical or Economic Conditions
In circumstances where the transmission licensee has identified a wider requirement for development of the transmission system, it may elect to install connection assets of greater size and capacity than the practicable minimum scheme required for a particular connection. In these circumstances, however, connection charges for the party seeking connection will normally be based on the level of connection assets consistent with the practicable minimum scheme needed to meet the applicant's requirements.
There may be cases where there are specific conditions such that the practicable minimum scheme at a site has to be greater than the strict, theoretical interpretation of the standards. In these cases all assets will still be assigned to connection and connection charges levied.
A practicable minimum scheme is considered in terms of the system as a whole and may include a change in voltage level. Part 2 - The Statement of the Use of System Charging Methodology Section 1 – The Statement of the Transmission Use of System Charging Methodology
Transmission Network Use of System Charges reflect the cost of installing, operating and maintaining the Transmission System for the Transmission Owner (TO) (including Competitively Appointed Transmission Owners (CATOs)) activity functions of the Transmission Businesses of each Relevant Transmission Licensee. These activities are undertaken to the standards prescribed by the ESO Licence and the Transmission Licences, to provide the capability to allow the flow of bulk transfers of power between Connection Sites and to provide transmission system security.
The allowed revenue defined for these activities agreed with the Authority at the time of the Transmission Owners’ price control review for the succeeding price control period. The allowed revenue can be adjusted during the price control period. Transmission Network Use of System Charges are set to recover the allowed revenue as set by the price control (where necessary, allowing for any K adjustment for under or over recovery in a previous year t net of the income recovered through pre-vesting connection charges). 14.14.2a The payments made to Competitively Appointed Transmission Owners (CATOs) are not set via a price control of the same form as incumbent Transmission Owners; instead, the payment to each CATO takes the form of a Tender Revenue Stream (TRS). The method for determining the TRS for a CATO will be prescribed within its licence. Transmission Network Use of System Charges are set to recover the Allowed Revenue which is determined in accordance with the terms of the CATO’s licence, such Allowed Revenue may include amongst other things the TRS, adjustments for indexation and incentivisation, and other payments provided for under its licence.
The basis of charging to recover the allowed revenue is the Investment Cost Related Pricing (ICRP) methodology, which was initially introduced by The Company in 1993/94 for England and Wales. The principles and methods underlying the ICRP methodology were set out in The Company document "Transmission Use of System Charges Review: Proposed Investment Cost Related Pricing for Use of System (30 June 1992)".
In December 2003, The Company published the Initial Thoughts consultation for a GB methodology using the England and Wales methodology as the basis for consultation. The Initial Methodologies consultation published by The Company in May 2004 proposed two options for a GB charging methodology with a Final Methodologies consultation published in August 2004 detailing The Company’s response to the Industry with a recommendation for the GB charging methodology. In December 2004, The Company published a Revised Proposals consultation in response to the Authority’s invitation for further review on certain areas in The Company’s recommended GB charging methodology.
In April 2004 The Company introduced a DC Loadflow (DCLF) ICRP based transport model for the England and Wales charging methodology. The DCLF model has been extended to incorporate Scottish network data with existing England and Wales network data to form the GB network in the model. In April 2005, the GB charging methodology implemented certain proposals which have been further expanded so that the model now includes the following: i.) The application of multi-voltage circuit expansion factors with a forward- looking Expansion Constant that does not include substation costs in its derivation. ii.) The application of locational security costs, by applying a multiplier to the Expansion Constant reflecting the difference in cost incurred on a secure network as opposed to an unsecured network. iii.) The application of a de-minimus level demand charge of £0/kW for Half Hourly and £0/kWh for Non-Half Hourly metered demand and £0/KWh for Unmetered Supplies and £0/site/day for Transmission Demand Residual Tariffs, to avoid the application of negative demand charges. iv.) The application of 132kV expansion factor on a Transmission Owner basis reflecting the regional variations in network upgrade plans. v.) The Company will set tariffs in a manner so that the locationally varying element, as established by the DCLF ICRP model and, where appropriate, local substation and local circuit charges, are levied on all Generator and Demand Users. Any remaining Transmission Owner revenues will be recovered from demand only in a non-locational manner through the Transmission Demand Residual Tariffs vi.) For the purpose of compliance with the Limiting Regulation in the context of setting limits on the annual charges paid by generation The Company will exclude Charges for Physical Assets Required for Connection when calculating the total amount to be recovered from Generators (GCharge (Forecast)). vii.) If having applied the exclusion of Charges for Physical Assets Required for Connection The Company identifies that an adjustment to TNUoS Charges is required to remain compliant with the Limiting Regulation then an Adjustment Tariff will be applied to all Generators in the following circumstances. a) The Adjustment Tariff will be applied if The Company identifies that either:
Annual average TNUoS charges payable by Generator Users will fall below €0/MWh OR 2. Annual average TNUoS charges payable by Generator Users will exceed €2.50/MWh adjusted by a risk margin to allow for error in tariff setting. b) Where annual average TNUoS charges to Generators are positive under the GCharge (Forecast) the Adjustment Tariff will be applied if the Adjustment Revenue is less than £0. The Adjustment Revenue is expressed as: 𝐴𝑑𝑗𝑅𝑒𝑣𝑒𝑛𝑢𝑒 = (𝐺𝑂 ∗ ((𝐶𝑎𝑝𝐸𝐶 ∗ (1 − 𝑦)) ∗ 𝐸𝑅)) – 𝐺𝐶ℎ𝑎𝑟𝑔𝑒(𝐹𝑜𝑟𝑒𝑐𝑎𝑠𝑡) c) Where annual average TNUoS charges to Generators are negative under the GCharge (Forecast) the Adjustment Revenue will be the difference between £0 and the total recovered from Generators. The Adjustment Revenue will be expressed as: 𝐴𝑑𝑗𝑅𝑒𝑣𝑒𝑛𝑢𝑒 = 0 − 𝐺𝐶ℎ𝑎𝑟𝑔𝑒(𝐹𝑜𝑟𝑒𝑐𝑎𝑠𝑡) d) The total adjusted revenue expected to be recovered from Generators (AdjGenRev) through TNUoS tariffs can therefore be expressed as: 𝐴𝑑𝑗𝐺𝑒𝑛𝑅𝑒𝑣 = 𝐺𝐶ℎ𝑎𝑟𝑔𝑒(𝐹𝑜𝑟𝑒𝑐𝑎𝑠𝑡) + 𝐴𝑑𝑗𝑅𝑒𝑣𝑒𝑛𝑢𝑒 e) The error margin used in calculating TNUoS tariffs for the Financial Year is expressed as: y = (1+ ErrorGenRev) / (1 - ErrorGO) -1 f) Where: y = error margin expressed in %. ErrorGenRev = the highest absolute percentage error in generation revenue collection, adjusted by systemic error, from the past 5 full years (year t-6 to t-2 inclusive). Systemic error is the average of %error in generation revenue collection for the past 5 full years. Systemic error can be positive or negative. ErrorGO = the highest absolute percentage error in generation TWh outputs, from the past 5 full years (year t-6 to t-2 inclusive). g) The Company will use the latest OBR Forecast of £/€ exchange rate published prior to the 31st October in the year preceding the relevant Financial Year to convert average annual TNUoS charges payable by Generators in the GCharge (Forecast) to a comparable value for the purposes of assessing compliance with the Limiting Regulation. h) The Adjustment Tariff used in the calculation will be either:
a negative £/kW tariff that reduces annual average TNUoS charges to Generators to below the risk adjusted upper limit of the Limiting Regulation in accordance with 14.14.5 (f). OR 2. a positive £/kW tariff that increases annual average TNUoS charges to Generators to above the lower limit of the Limiting Regulation in accordance with 14.14.5 (f). Expressed in either case as: 𝐴𝑑𝑗𝑅𝑒𝑣𝑒𝑛𝑢𝑒 𝐴𝑑𝑗𝑇𝑎𝑟𝑖𝑓𝑓 = 𝐶ℎ𝑎𝑟𝑔𝑒𝑎𝑏𝑙𝑒 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 Where; CapEC = Upper limit of the range specified in the Limiting Regulation y = Error margin built in to adjust CapEC GO = Forecast GB Generation Output for generation liable for Transmission charges (i.e. energy injected into the transmission network in MWh) for the Financial Year ER = The latest OBR Forecast €/£ Exchange Rate published prior to the 31st October in the year preceding the relevant Financial Year GCharge (Forecast) = The total forecast TNUoS revenue to be recovered from Generators in the Financial Year minus Charges for Physical Assets Required for Connection. AdjRevenue = Adjustment Revenue Chargeable Capacity = as per paragraph 14.18.6 AdjTariff = Any Adjustment Tariff required to remain compliant with the Limiting Regulation. viii.) The currently applicable number of generation zones, determined in accordance with 14.15.37 and using the criteria outlined in paragraph 14.15.42, is detailed in the Statement of Use of System Charges which is available from the Website. ix.) The number of demand zones has been determined as 14, corresponding to the 14 GSP groups.
The underlying rationale behind Transmission Network Use of System charges is that efficient economic signals are provided to Users when services are priced to reflect the incremental costs of supplying them. Therefore, charges should reflect the impact that Users of the transmission system at different locations would have on the Transmission Owner's costs, if they were to increase or decrease their use of the respective systems. These costs are primarily defined as the investment costs in the transmission system, maintenance of the transmission system and maintaining a system capable of providing a secure bulk supply of energy. The ESO Licence requires The Company to operate the National Electricity Transmission System to specified standards. In addition The Company and transmission licensees are required to plan and develop the National Electricity Transmission System to meet these standards. These requirements mean that the system must conform to a particular Security Standard and capital investment requirements are largely driven by the need to conform to both the deterministic and supporting cost benefit analysis aspects of this standard. It is this obligation, which provides the underlying rationale for the ICRP approach, i.e. for any changes in generation and demand on the system, The Company must ensure that it satisfies the requirements of the Security Standard.
The Security Standard identifies requirements on the capacity of component sections of the system given the expected generation and demand at each node, such that demand can be met and Generators’ output over the course of a year (capped at their Transmission Entry Capacity, TEC) can be accommodated in the most economic and efficient manner. The derivation of the incremental investment costs at different points on the system is therefore determined against the requirements of the system both at the time of peak demand and across the remainder of the year. The Security Standard uses a Demand Security Criterion and an Economy Criterion to assess capacity requirements. The charging methodology therefore recognises both these elements in its rationale.
The Demand Security Criterion requires sufficient transmission system capacity such that peak demand can be met through generation sources as defined in the Security Standard, whilst the Economy Criterion requires sufficient transmission system capacity to accommodate all types of generation in order to meet varying levels of demand efficiently. The latter is achieved through a set of deterministic parameters that have been derived from a generic Cost Benefit Analysis (CBA) seeking to identify an appropriate balance between constraint costs and the costs of transmission reinforcements.
The TNUoS charging methodology seeks to reflect these arrangements through the use of dual backgrounds in the Transport Model, namely a Peak Security background representative of the Demand Security Criterion and a Year Round background representative of the Economy Criterion.
To recognise that various types of generation will have a different impact on incremental investment costs the charging methodology uses a generator’s TEC, Peak Security flag, and Annual Load Factor (ALF) when determining Transmission Network Use of System charges relating to the Peak Security and Year Round backgrounds respectively. For the Year Round background the diversity of the plant mix (i.e the proportion of low carbon and carbon generation) in each charging zone is also taken into account.
In setting and reviewing these charges The Company has a number of further objectives. These are to: • offer clarity of principles and transparency of the methodology; • inform existing Users and potential new entrants with accurate and stable cost messages; • charge on the basis of services provided and on the basis of incremental rather than average costs, and so promote the optimal use of and investment in the transmission system; and • be implementable within practical cost parameters and time-scales.
The Company will typically calculate TNUoS tariffs annually, publishing final tariffs in respect of a Financial Year by the end of the preceding January. However The Company may update the tariffs part way through a Financial Year.
Derivation of the Transmission Network Use of System Tariff
The Transmission Network Use of System (TNUoS) Tariff comprises two separate elements. Firstly, a locationally varying element derived from the DCLF ICRP transport model to reflect the costs of capital investment in, and the maintenance and operation of, a transmission system to provide bulk transport of power to and from different locations. Secondly, a non-locationally varying element related to the provision of residual revenue recovery from demand only.
For generation TNUoS tariffs the locational element itself is comprised of five separate components. Three wider components – o Wider Peak Security Component o Wider Year Round Not-shared component o Wider Year Round component These components reflect the costs of the wider network under the different generation backgrounds set out in the Demand Security Criterion (for Peak Security component) and Economy Criterion (for both Year Round components) of the Security Standard. The two Year Round components reflect the unshared and shared costs of the wider network based on the diversity of generation plant types. Two local components – o Local substation, and o Local circuit These components reflect the costs of the local network. Accordingly, the wider tariff represents the combined effect of the three wider locational tariff components and the local tariff represents the combination of the two local locational tariff components. Finally, an Adjustment Tariff component may also be charged to Generators as per paragraph 14.14.5.
The process for calculating the TNUoS tariff is described below. The Transport Model Model Inputs
The DCLF ICRP transport model calculates the marginal costs of investment in the transmission system which would be required as a consequence of an increase in demand or generation at each connection point or node on the transmission system, based on a study of peak demand conditions using both Peak Security and Year Round generation backgrounds on the transmission system. One measure of the investment costs is in terms of MWkm. This is the concept that ICRP uses to calculate marginal costs of investment. Hence, marginal costs are estimated initially in terms of increases or decreases in units of kilometres (km) of the transmission system for a 1 MW injection to the system.
The transport model requires a set of inputs representative of the Demand Security and Economy Criterion set out in the Security Standards. These conditions on the transmission system are represented in the Peak Security and Year Round background respectively as follows: • Nodal generation information per node (TEC, plant type and SQSS scaling factors) • Nodal net demand information • Transmission circuits between these nodes • The associated lengths of these routes, the proportion of which is overhead line or cable and the respective voltage level • The cost ratio of each of 132kV overhead line, 132kV underground cable, 275kV overhead line, 275kV underground cable and 400kV underground cable to 400kV overhead line to give circuit expansion factors • The cost ratio of each separate sub-sea AC circuit and HVDC circuit to 400kV overhead line to give circuit expansion factors • 132kV overhead circuit capacity and single/double route construction information is used in the calculation of a generator’s local charge. • Offshore transmission cost and circuit/substation data
For a given Financial Year "t", the nodal generation TEC figure and generation plant types at each node will be based on the Applicable Value for year "t" in the NETS Electricity Ten Year Statement (ETYS) in year "t-1" plus updates to the October of year "t-1". The contracted TECs and generation plant types in the NETS Electricity Ten Year Statement (ETYS) include all plant belonging to Generators who have a Bilateral Agreement with the TOs. For example, for 2010/11 charges, the nodal generation data is based on the forecast for 2010/11 in the 2009 NETS Electricity Ten Year Statement (ETYS) plus any data included in the quarterly updates in October 2009.
Scaling factors for different generation plant types are applied on their aggregated capacity for both Peak Security and Year Round backgrounds. The scaling is either Fixed or Variable (depending on the generation plant type as referenced in the table below) and based on the factors used in the Security Standard, which are referenced in the same table. A 10% floor for the Year Round Background variable scaling factor is used for charging purposes. If the methodology set out in the SQSS for calculating the variable scaling factor results in a lower number, the variable factor will be set at 10%, and fixed scaling factors adjusted by a uniform amount. This adjustment will be based on the SQSS principle that the total scaled output of all generation plant shall equal the ACS (Annual Average Cold Spell) peak demand minus total imports from external systems, and can be calculated using the following equation. 𝐴𝐶𝑆 −∑(𝑇𝐸𝐶 ×10%) 𝑃𝑒𝑎𝑘 𝐷𝑒𝑚𝑎𝑛𝑑 𝑉𝑎𝑟𝑖𝑎𝑏𝑙𝑒 𝑃𝑙𝑎𝑛𝑡 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡 = ∑(𝑇𝐸𝐶 ×𝑌𝑒𝑎𝑟 𝑅𝑜𝑢𝑛𝑑 𝑆𝑐𝑎𝑙𝑖𝑛𝑔 𝐹𝑎𝑐𝑡𝑜𝑟) 𝐹𝑖𝑥𝑒𝑑 𝑃𝑙𝑎𝑛𝑡 𝐴𝑑𝑗𝑢𝑠𝑡𝑒𝑑 𝐹𝑖𝑥𝑒𝑑 𝑆𝑐𝑎𝑙𝑖𝑛𝑔 𝐹𝑎𝑐𝑡𝑜𝑟= 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡×𝑆𝑐𝑎𝑙𝑖𝑛𝑔 𝐹𝑎𝑐𝑡𝑜𝑟
| Generation Plant Type | Peak Security Background | Year Round Background |
|---|---|---|
| Intermittent | Fixed (0%) | Fixed (70%) |
| Nuclear & CCS | Variable | Fixed (85%) |
| Interconnectors | Fixed (0%) | Fixed (100%) |
| Hydro | Variable | Variable (>10%) |
| Pumped Storage | Variable | Fixed (50%) |
| Peaking | Variable | Fixed (0%) |
| Other (Conventional) | Variable | Variable (>10%) |
The Company will categorise plant based on the categorisations described in the Security Standard. Peaking plant will include oil and OCGT technologies and Other (Conv.) represents all remaining conventional plant not explicitly stated elsewhere in the table. In the event that a power station is made up of more than one technology type, the type of the higher Transmission Entry Capacity (TEC) would apply.
Nodal net demand data for the transport model will be based upon the GSP net demand that Users have forecast to occur at the time of Annual Average Cold Spell (ACS) Demand for year "t" in the April Electricity Ten Year Statement (ETYS) for year "t-1" plus updates to the October of year "t-1".
Subject to paragraphs 14.15.15 to 14.15.22, Transmission circuits for Financial Year "t" will be defined as those with existing wayleaves for the year "t" with the associated lengths based on the circuit lengths indicated for year "t" in the April NETS Electricity Ten Year Statement (ETYS) for year "t-1" plus updates to October of year "t-1". If certain circuit information is not explicitly contained in the NETS Electricity Ten Year Statement (ETYS), The Company will use the best information available.
The circuit lengths included in the transport model are solely those, which relate to assets defined as 'Use of System' assets.
For HVDC circuits, the impedance will be calculated to provide flows based on a ratio of the capacity provided by the HVDC link relative to the capacities on all major transmission system boundaries that it parallels.
The transport model employs the use of circuit expansion factors to reflect the difference in cost between (i) AC Circuits and HVDC circuits, (ii) underground and sub-sea circuits, (iii) cabled circuits and overhead line circuits, (iv) 132kV and 275kV circuits, (v) 275kV circuits and 400kV circuits, and (vi) uses 400kV overhead line (i.e. the 400kV overhead line expansion factor is 1). As the transport model expresses cost as marginal km (irrespective of cables or overhead lines), some account needs to be made of the fact that investment in these other types of circuit (specifically HVDC and sub-sea cables of various voltages, 400kV underground cable, 275kV overhead line, 275kV underground cable, 132kV overhead line and 132kV underground cable) is more expensive than for 400kV overhead line. This is done by effectively 'expanding' these more expensive circuits by the relevant circuit expansion factor, thereby producing a larger marginal kilometre to reflect the additional cost of investing in these circuits compared to 400kV overhead line. When calculating the local circuit tariff for a generator, alternative 132kV and offshore expansion factors to those used in the remainder of the tariff calculation are applied to the generator’s local circuits.
The circuit expansion factors for HVDC circuits and AC subsea cables are determined on a case by case basis using the costs which are specific to individual projects containing HVDC or AC subsea circuits. Adjustments to Model Inputs associated with One-off Works
Where, following the implementation of CUSC Modification CMP203, a User has paid a One-Off Charge that related to One-off Works carried out on an onshore circuit, and such One-off Works would affect the value of a TNUoS tariff paid by the User, the transport model inputs associated with the onshore circuit shall be adjusted by The Company to reflect the asset value that would have been modelled if the works had been undertaken on the basis of the original asset design rather than the One-off Works.
Subject to paragraphs 14.15.17 to 14.15.19, where, prior to the implementation of CUSC Modification CMP203, a User has paid a One-Off Charge (or has paid a charge to the relevant TO prior to 1st April 2005 on the same principles as a One-Off Charge) that related to works equivalent to those described under paragraph 14.15.15, an adjustment equivalent to that under paragraph 14.15.15 shall be made to the transport model inputs as follows.
Such adjustment shall be made following a User’s request, which must be received by The Company no later than the second occurrence of 31st December following the implementation of CUSC Modification CMP203.
The Company shall only make an adjustment to the transport model inputs, under paragraph 14.15.16 where the charge was paid to the relevant TO prior to 1st April 2005 where evidence has been provided by the User that satisfies The Company that works equivalent to those under paragraph 14.15.15 were funded by the User.
Where a User has sufficient reason to believe that adjustments under paragraph 14.15.18 should be made in relation to specific assets that affect a TNUoS tariff that applies to one of its sites and outlines its reasoning to The Company, The Company shall (upon the User’s request and subject to the User’s payment of reasonable costs incurred by The Company in doing so) use its reasonable endeavours to assist the User in obtaining any evidence The Company or a TO may have to support its position.
Where a request is made under paragraph 14.15.16 on or prior to 31st December in a Financial Year, and The Company is satisfied based on the accompanying evidence provided to The Company under paragraph 14.15.17 that it is a valid request, the transport model inputs shall be adjusted accordingly and taken into account in the calculation of TNUoS tariffs effective from the year commencing on the 1st April following this and otherwise from the next subsequent 1st April.
The following table provides examples of works for which adjustments to transport model inputs would typically apply:
| Ref Description of works Adjustments | ||
|---|---|---|
| 1 | Undergrounding - A User requests to underground an overhead line at a greater cost. | As the cable cost will be more expensive than the overhead line (OHL) equivalent, the circuit will be modelled as an OHL. |
| 2 | Substation Siting Decision - A User requests to move the existing or a planned substation location to a place that means that the works cannot be justified as economic by the TO. | As the revised substation location may result in circuits being extended. If this is the case, the originally designed circuit lengths (as per the originally designed substation location) would be used in the transport model. |
| 3 | Circuit Routing Decision - A User asks to move an existing or a planned circuit route in a way in which the works cannot be justified as economic by the TO. | As any circuit route changes that extend circuits are likely to result in a greater TNUoS tariff, the originally designed circuit lengths would be used in the transport model. |
| 4 | Building circuits at lower voltages - A User requests lower tower height and therefore a different voltage. | As lower voltage circuits result in a higher expansion factor being used, the circuits would be modelled at the originally designed higher voltage. |
The following table provides examples of works for which adjustments to transport model typically would not apply:
| Ref Description of works Reasoning | ||
|---|---|---|
| 1 | Undergrounding - A User chooses to have a cable installed via a tunnel rather than buried. | Cable expansion factors are applied in the transport model regardless of whether a cable is tunnelled and buried, so there is no increased TNUoS cost. |
| 2 | Additional circuit route works - A User asks for screening to be provided around a new or existing circuit route. | Circuit expansion factors are applied in the transport model irrespective of these works, so there is no increased TNUoS cost. |
| 3 | Additional circuit route works - A User requests that a planned overhead line route is built using alternative transmission tower designs. | Circuit expansion factors are applied in the transport model irrespective of these works, so there is no increased TNUoS cost. |
| 4 | Additional substation works - A User asks for screening to be provided around a new or existing substation. | The additional substation works will not affect the User’s TNUoS charge as there is no effect on power flows or circuit costs within the transport model. |
| 5 | Additional substation works - Changes to connection assets (e.g. HV-LV transformers and associated switchgear), metering, additional LV supplies, additional protection equipment, additional building works, etc. | The additional substation works will not affect the User’s TNUoS charge as there is no effect on power flows or circuit costs within the transport model. |
| 6 | Diversion - A User asks to temporarily move an existing or a planned circuit route in a way in which the works cannot be justified as economic by the TO. | The temporary circuit changes will not be incorporated into the transport model. |
| 7 | Connection Entry Capacity (CEC) before Transmission Entry Capacity (TEC). A User asks for a connection in a year prior to the relating TEC; i.e. physical connection without capacity. | No additional works are being undertaken, works are simply being completed well in advance of the generator commissioning. The One-Off Charge reflects the depreciated value of the assets prior to commissioning (and any TNUoS being charged). |
| 8 | Early asset replacement - An asset is replaced prior to the end of its expected life. | As the asset is simply replaced, no data in the transport model is expected to change. |
| 9 | Additional Engineering/ Mobilisation costs - A User requests changes to the planned works, that results in additional operational costs. | The data in the transport model is unaffected. |
| 10 | Offshore (Generator Build) - Any of the works described above or under paragraph 14.15.18. | The value of the works will not form part of the asset transfer value therefore will not be used as part of the offshore tariff calculation. |
| 11 | Offshore (Offshore Transmission Owner (OFTO) Build) - Any of the works described above or under paragraph 14.15.18. | As part of determining the TNUoS revenue associated with each asset, the value of the One-Off Works would be excluded when pro-rating the OFTO’s allowed revenue against assets by asset value. |
The Company shall publish any adjusted transport model inputs that it intends to use in the calculation of TNUoS tariffs effective from the year commencing on the following 1st April in the NETS Electricity Ten Year Statement (ETYS) October Update. Any further adjustments that The Company makes shall be published by The Company upon the publication of the final TNUoS tariffs for the year concerned. Model Outputs
The transport model takes the inputs described above and carries out the following steps individually for Peak Security and Year Round backgrounds.
Depending on the background, the TEC of the relevant generation plant types are scaled by a percentage as described in 14.15.7, above. The TEC of the remaining generation plant types in each background are uniformly scaled such that total national generation (scaled sum of contracted TECs) equals total national ACS Demand.
For each background, the model then uses a DCLF ICRP transport algorithm to derive the resultant pattern of flows based on the network impedance required to meet the nodal net demand using the scaled nodal generation, assuming every circuit has infinite capacity. Flows on individual transmission circuits are compared for both backgrounds and the background giving rise to the highest flow is considered as the triggering criterion for future investment of that circuit for the purposes of the charging methodology. Therefore all circuits will be tagged as Peak Security or Year Round depending upon the background resulting in the highest flow. In the event that both backgrounds result in the same flow, the circuit will be tagged as Peak Security. Then it calculates the resultant total network Peak Security MWkm and Year Round MWkm, using the relevant circuit expansion factors as appropriate.
Using these baseline networks for Peak Security and Year Round backgrounds, the model then calculates for a given injection of 1MW of generation at each node, with a corresponding 1MW offtake (net demand) distributed across all demand nodes in the network, the increase or decrease in total MWkm of the whole Peak Security and Year Round networks. The proportion of the 1MW offtake allocated to any given demand node will be based on total background nodal net demand in the model. For example, with a total net GB demand of 60GW in the model, a node with a net demand of 600MW would contain 1% of the offtake i.e. 0.01MW.
Given the assumption of a 1MW injection, for simplicity the marginal costs are expressed solely in km. This gives a Peak Security marginal km cost and a Year Round marginal km cost for generation at each node (although not that used to calculate generation tariffs which considers local and wider cost components). The Peak Security and Year Round marginal km costs for demand at each node are equal and opposite to the Peak Security and Year Round nodal marginal km respectively for generation and this is used to calculate demand tariffs. Note the marginal km costs can be positive or negative depending on the impact the injection of 1MW of generation has on the total circuit km.
Using a similar methodology as described above in 14.15.27, the local and wider marginal km costs used to determine generation TNUoS tariffs are calculated by injecting 1MW of generation against the node(s) the generator is modelled at and increasing by 1MW the offtake across the distributed reference node. It should be noted that although the wider marginal km costs are calculated for both Peak Security and Year Round backgrounds, the local marginal km costs are calculated on the Year Round background.
In addition, any circuits in the model, identified as local assets to a node will have the local circuit expansion factors which are applied in calculating that particular node’s marginal km. Any remaining circuits will have the TO specific wider circuit expansion factors applied.
An example is contained in 14.21 Transport Model Example. Calculation of local nodal marginal km
In order to ensure assets local to generation are charged in a cost reflective manner, a generation local circuit tariff is calculated. The nodal specific charge provides a financial signal reflecting the security and construction of the infrastructure circuits that connect the node to the transmission system.
Main Interconnected Transmission System (MITS) nodes are defined as: • Grid Supply Point connections with 2 or more transmission circuits connecting at the site; or • connections with more than 4 transmission circuits connecting at the site.
Where a Grid Supply Point is defined as a point of supply from the National Electricity Transmission System to network operators or non-embedded customers excluding generator or interconnector load alone. For the avoidance of doubt, generator or interconnector load would be subject to the circuit component of its Local Charge. A transmission circuit is part of the National Electricity Transmission System between two or more circuit- breakers which includes transformers, cables and overhead lines but excludes busbars and generation circuits.
Generators directly connected to a MITS node will have a zero local circuit tariff.
Generators not connected to a MITS node will have a local circuit tariff derived from the local nodal marginal km for the generation node i.e. the increase or decrease in marginal km along the transmission circuits connecting it to all adjacent MITS nodes (local assets). Calculation of zonal marginal km
Given the requirement for relatively stable cost messages through the ICRP methodology and administrative simplicity, nodes are assigned to zones. The currently applicable number of generation zones is detailed in the Statement of Use of System Charges which is available from the Website.
Demand zone boundaries have been fixed and relate to the GSP Groups used for energy market settlement purposes.
The nodal marginal km are amalgamated into zones by weighting them by their relevant generation or demand capacity.
Generators will have zonal tariffs derived from both, the wider Peak Security nodal marginal km; and the wider Year Round nodal marginal km for the generation node calculated as the increase or decrease in marginal km along all transmission circuits except those classified as local assets. The zonal Peak Security marginal km for generation is calculated as: NMkm Gen WNMkm = jPS j jPS Gen j jGi ZMkm = WNMkm GiPS jPS jGi Where Gi = Generation zone j = Node NMkm = Peak Security Wider nodal marginal km from transport PS model WNMkm = Peak Security Weighted nodal marginal km PS ZMkm = Peak Security Zonal Marginal km PS Gen = Nodal Generation (scaled by the appropriate Peak Security Scaling factor) from the transport model Similarly, the zonal Year Round marginal km for generation is calculated as NMkm Gen WNMkm = jYR j jYR Gen j jGi = j Z M k m W N M k m G iY R jY R G i Where NMkm = Year Round Wider nodal marginal km from transport YR model WNMkm = Year Round Weighted nodal marginal km YR ZMkm = Year Round Zonal Marginal km YR Gen = Nodal Generation (scaled by the appropriate Year Round Scaling factor) from the transport model
The zonal Peak Security marginal km for demand zones are calculated as follows. If Nodal Demand from a node is less than 0 (Exporting) the nodal demand will be set to zero and therefore not contribute to the Zonal marginal km −1NMkm Dem jPS j WNMkm = jPS Dem j jDi ZMkm = WNMkm DiPS jPS jDi Where: Di = Demand zone Dem = Positive Nodal Net Demand from transport model Similarly, the zonal Year Round marginal km for demand zones are calculated as follows: − N M k m D e m jY R j W N M k m = jY R j D e m j D i j Z M k m = W N M k m D iY R jY R D i
The number of generation zones will be fixed to 27 zones and the assignment of existing relevant nodes to these 27 generation zones will be fixed to those that are effective as of 31st March 2021 based on methodology in effect during the 2020/21. Relevant nodes are considered to be those with generation connected to them. Financial Year. Any newly created relevant nodes will be assigned to one of the 27 generation zones.
Not Used
Not Used
Not Used Accounting for Sharing of Transmission by Generators
A proportion of the marginal km costs for generation are shared incremental km reflecting the ability of differing generation technologies to share transmission investment. This is reflected in charges through the splitting of Year Round marginal km costs for generation into Year Round Shared marginal km costs and Year Round Not-Shared marginal km which are then used in the calculation of the wider £/kW generation tariff.
The sharing between different generation types is accounted for by (a) using transmission network boundaries between generation zones set by connectivity between generation charging zones, and (b) the proportion of Low Carbon and Carbon generation behind these boundaries.
The zonal incremental km for each generation charging zone is split into each boundary component by considering the difference between it and the neighbouring generation charging zone using the formula below; BIkm = ZIkm − ZIkm ab b a Where; BIkm = boundary incremental km between generation charging ab zone A and generation charging zone B ZIkm = generation charging zone incremental km.
The table below shows the categorisation of Low Carbon and Carbon generation. This table will be updated by The Company in the Statement of Use of System Charges as new generation technologies are developed. Determination of Connectivity
| Carbon | Low Carbon |
|---|---|
| Coal | Wind |
| Gas | Hydro (excl. Pumped Storage) |
| Biomass | Nuclear |
| Oil | Marine |
| Pumped Storage | Tidal |
| Interconnectors |
Connectivity is based on the existence of electrical circuits between TNUoS generation charging zones that are represented in the Transport model. Where such paths exist, generation charging zones will be effectively linked via an incremental km transmission boundary length. These paths will be simplified through in the case of; • Parallel paths – the longest path will be taken. An illustrative example is shown below with x, y and z representing the incremental km between zones. • Parallel zones – parallel zones will be amalgamated with the incremental km immediately beyond the amalgamated zones being the greater of those existing prior to the amalgamation. An illustrative example is shown below with a, b, c, and d representing the initial incremental km between zones, and x and y representing the final incremental km following zonal amalgamation.
An illustrative Connectivity diagram is shown below: The arrows connecting generation charging zones and amalgamated generation charging zones represent the incremental km transmission boundary lengths towards the notional centre of the system. Generation located in charging zones behind arrows is considered to share based on the ratio of Low Carbon to Carbon cumulative generation TEC within those zones.
The Company will review Connectivity at the beginning of a new price control period, and under exceptional circumstances such as major system reconfigurations. If any such reassessment is required, it will be undertaken against a background of minimal change to existing Connectivity and in line with the notification process set out in the ESO Licence, the Transmission Licence and the CUSC. Calculation of Boundary Sharing Factors
Boundary sharing factors (BSFs) are derived from the comparison of the cumulative proportion of Low Carbon and Carbon generation TEC behind each of the incremental MWkm boundary lengths using the following formulae – L C 0 .5 If , then all Year round marginal km costs are shared i.e. the L C + C BSF is 100%. Where: LC = Cumulative Low Carbon generation TEC behind the relevant transmission boundary C = Cumulative Carbon generation TEC behind the relevant transmission boundary L C 0 .5 If then the BSF is calculated using the following formula: - L C + C L C B S F = − + L C + C Where: BSF = boundary sharing factor.
The shared incremental km for each boundary are derived from the multiplication of the boundary sharing factor by the incremental km for that boundary; S B I k m = B I I k m x B S F a b a b a b Where; SBIkm = shared boundary incremental km between generation ab charging zone A and generation charging zone B BSF = generation charging zone boundary sharing factor. ab
The shared incremental km is discounted from the incremental km for that boundary to establish the not-shared boundary incremental km. The not- shared boundary incremental km reflects the cost of transmission investment on that boundary accounting for the sharing of power stations behind that boundary. N S B I k m = B I k m − S B I k m a b a b a b Where; NSBIkm = not shared boundary incremental km between ab generation charging zone A and generation charging zone B.
The shared incremental km for a generation charging zone is the sum of the appropriate shared boundary incremental km for that generation charging zone as derived from the connectivity diagram. n N S B I k m = Z M k m a b n Y R S a Where; ZMkm = Year Round Shared Zonal Marginal km for generation nYRS charging zone n.
The not-shared incremental km for a generation charging zone is the sum of the appropriate not-shared boundary incremental km for that generation charging zone as derived from the connectivity diagram. n NSBIkm = ZMkm a ab nYRNS Where; ZMkm = Year Round Not-Shared Zonal Marginal km for nYRNS generation zone n. Deriving the Final Local £/kW Tariff and the Wider £/kW Tariff
The zonal marginal km (ZMkm ) are converted into costs and hence a tariff Gi by multiplying by the Expansion Constant and the Locational Security Factor (see below). The nodal local marginal km (NLMkmL) are converted into costs and hence a tariff by multiplying by the Expansion Constant and a Local Security Factor. The Expansion Constant
The expansion constant, expressed in £/MWkm, represents the annuitised value of the transmission infrastructure capital investment required to transport 1 MW over 1 km. Its magnitude is derived from the projected cost of 400kV overhead line, including an estimate of the cost of capital, to provide for future system expansion.
In the methodology, the expansion constant is used to convert the marginal km figure derived from the transport model into a £/MW signal. The tariff model performs this calculation, in accordance with 14.15.96 – 14.15.121, and also then calculates the residual element of the overall tariff (to ensure correct revenue recovery in accordance with the price control), in accordance with 14.15.137.
The transmission infrastructure capital costs used in the calculation of the expansion constant are provided via an externally audited process. They also include information provided from all onshore Transmission Owners (TOs). They are based on historic costs and tender valuations adjusted by a number of indices (e.g. global price of steel, labour, inflation, etc.). The objective of these adjustments is to make the costs reflect current prices, making the tariffs as forward looking as possible. This cost data represents The Company’s best view; however it is considered as commercially sensitive and is therefore treated as confidential. The calculation of the expansion constant also relies on a significant amount of transmission asset information, much of which is provided in the Electricity Ten Year Statement (ETYS).
For each circuit type and voltage used onshore, an individual calculation is carried out to establish a £/MWkm figure, normalised against the 400KV overhead line (OHL) figure, these provide the basis of the onshore circuit expansion factors discussed in 14.15.70 – 14.15.77. In order to simplify the calculation a unity power factor is assumed, converting £/MVAkm to £/MWkm. This reflects that the fact tariffs and charges are based on real power.
The table below shows the first stage in calculating the onshore expansion constant. A range of overhead line types is used and the types are weighted by recent usage on the transmission system. This is a simplified calculation for 400kV OHL using example data: *These are circuit km of types that have been provided in the previous 10 years. If no information is available for a particular category the best forecast will be used.
| 400kV OHL expansion constant calculation | ||
|---|---|---|
| MW Type £(000)/km Circuit km* £/MWkm Weight A B C D E = C/A F=E*D 6500 La 700 500 107.69 53846 6500 Lb 780 0 120.00 0 3500 La/b 600 200 171.43 34286 3600 Lc 400 300 111.11 33333 4000 Lc/a 450 1100 112.50 123750 5000 Ld 500 300 100.00 30000 5400 Ld/a 550 100 101.85 10185 Sum 2500 (G) 285400 (H) | ||
| Weighted Average 114.160 (J) (J= H/G): |
| 6500 | La | 700 | 500 |
|---|---|---|---|
| 6500 | Lb | 780 | 0 |
| 3500 | La/b | 600 | 200 |
| 3600 | Lc | 400 | 300 |
| 4000 | Lc/a | 450 | 1100 |
| 5000 | Ld | 500 | 300 |
| 5400 | Ld/a | 550 | 100 |
The weighted average £/MWkm (J in the example above) is then converted in to an annual figure by multiplying it by an annuity factor. The formula used to calculate of the annuity factor is shown below: A n n u i t y f a c t o r = (1 ) − (1 + W ) − A sse tL ife A C C W A C C
The Weighted Average Cost of Capital (WACC) and asset life are established at the start of a price control and remain constant throughout a price control period. The WACC used in the calculation of the annuity factor is NGET’s regulated rate of return, this assumes that it will be reasonably representative of all licensees. The asset life used in the calculation is 50 years; the appropriateness of this is reviewed when the annuity factor is recalculated at the start of a price control period. These assumptions, applied in accordance with 14.15.64, provide a current annuity factor, as set out in the Statement of Use of System Charges which is available from the Website.
The final step in calculating the expansion constant is to add a share of the annual transmission overheads (maintenance, rates etc). This is done by multiplying the average weighted cost (J) by an ‘overhead factor’. The ‘overhead factor’ represents the total business overhead in any year divided by the total Gross Asset Value (GAV) of the transmission system. This is recalculated at the start of each price control period. The currently applicable overhead factor used in the calculation of the current expansion constant is, calculated as above, and detailed in the Statement of Use of System Charges which is available from the Website. The overhead and annuitised costs are then added to give the expansion constant.
Using the previous example, and the 2009/10 values for the annuity factor (6.6%) and overhead factor (1.8%), the final steps in establishing the expansion constant are demonstrated below:
| 400kV OHL expansion constant calculation | Ave £/MWkm |
|---|---|
| OHL | 114.160 |
| Annuitised | 7.535 |
| Overhead | 2.055 |
| Final | 9.589 |
This process is carried out for each voltage onshore, along with other adjustments to take account of upgrade options, see 14.15.73, and normalised against the 400KV overhead line cost (the expansion constant) the resulting ratios provide the basis of the onshore expansion factors. The process used to derive circuit expansion factors for Offshore Transmission Owner networks is described in 14.15.80.
This process of calculating the incremental cost of capacity for a 400kV OHL, along with calculating the onshore expansion factors is carried out for the first year of the price control and is increased by inflation, TOPI, (May–October average increase, as defined in the ESO Licence and/or Transmission Licence) each subsequent year of the price control period. The currently applicable expansion constant is detailed in the Statement of Use of System Charges which is available from the Website. 14.15.69A Notwithstanding Paragraph 14.15.69 from the first year of (and during) the T2 price control (which starts on 1st April 2021), until a further change is made, the Expansion Constant will be that used in the 2020/21 Financial Year inflated in accordance with TOPI as per paragraph 14.15.69; and plus inflation as defined in the ESO License and/or Transmission Licence for each subsequent year of the T2 price control. Onshore Wider Circuit Expansion Factors
Base onshore expansion factors are calculated by deriving individual expansion constants for the various types of circuit, following the same principles used to calculate the 400kV overhead line expansion constant. The factors are then derived by dividing the calculated expansion constant by the 400kV overhead line expansion constant. The factors will be fixed for each respective price control period.
In calculating the onshore underground cable factors, the forecast costs are weighted equally between urban and rural installation, and direct burial has been assumed. The operating costs for cable are aligned with those for overhead line. An allowance for overhead costs has also been included in the calculations.
The 132kV onshore circuit expansion factor is applied on a TO basis. This is to reflect the regional variation of plans to rebuild circuits at a lower voltage capacity to 400kV. The 132kV cable and line factor is calculated on the proportion of 132kV circuits likely to be uprated to 400kV. The 132kV expansion factor is then calculated by weighting the 132kV cable and overhead line costs with the relevant 400kV expansion factor, based on the proportion of 132kV circuitry to be uprated to 400kV. For example, in the TO areas of NGET and Scottish Power where there are no plans to uprate any 132kV circuits, the full cable and overhead line costs of 132kV circuit are reflected in the 132kV expansion factor calculation.
The 275kV onshore circuit expansion factor is applied on a GB basis and includes a weighting of 83% of the relevant 400kV cable and overhead line factor. This is to reflect the averaged proportion of circuits across all three Onshore Transmission Licensees which are likely to be uprated from 275kV to 400kV across GB within a price control period.
The 400kV onshore circuit expansion factor is applied on a GB basis and reflects the full costs for 400kV cable and overhead lines.
AC sub-sea cable and HVDC circuit expansion factors (Specific Circuit Expansion Factors) are calculated on a case by case basis using actual project costs net of any cost adjustments.
Calculation of Specific Circuit Expansion Factors shall include only: the cost of the converters (where applicable); and the cost of the cable; and a percentage of the total overhead project costs, defined as the combined costs of the cables and converters (as relevant) divided by the total capital cost of the project minus a percentage of the cost adjustment, defined as the combined costs of the cables, converters (as relevant) and appropriate overhead costs, as calculated above, all divided by the total capital cost of the project. Specific Circuit Expansion Factors in RIIO-T3 14.15.76A) The Specific Circuit Expansion Factors calculated as of 1 April 2025 and used in the 2025/26 Financial Year will remain fixed and be used in subsequent Financial Years until a further change is made. For clarity, the Specific Expansion Factors calculated and applied after 1st April 2025 will remain fixed once calculated, until a further change is made.
The TO specific onshore circuit expansion factors which are currently applicable, are detailed in the Statement of Use of System Charges which is available from the Website. Onshore Local Circuit Expansion Factors
The local onshore circuit tariff is calculated using local onshore circuit expansion factors. These expansion factors are calculated using the same methodology as the onshore wider expansion factor but without taking into account the proportion of circuit kms that are planned to be uprated.
In addition, the 132kV onshore overhead line circuit expansion factor is sub divided into four more specific expansion factors. This is based upon maximum (winter) circuit continuous rating (MVA) and route construction whether double or single circuit. The 132kV onshore overhead line circuit expansion factors which are currently applicable, are detailed in the Statement of Use of System Charges which is available from the Website. Onshore Expansion Factors in RIIO-T2 14.15.79A Notwithstanding Paragraph 14.15.69, the previous paragraphs and following the same intent as adopted at Paragraph 14.15.69A, from the first year of (and during) the T2 price control (which starts on 1st April 2021), until a further change is made, the Onshore expansion factors (being the Onshore local circuit factors and the Onshore wider circuit expansion factors, except those used for HVDC circuits and sub-sea AC cable) will be the value used in the 2020/21 Financial Year. For clarity HVDC circuits and sub-sea AC cable will continue to be calculated in accordance with 14.15.75. Offshore Circuit Expansion Factors
Offshore expansion factors (£/MWkm) are derived from information provided by Offshore Transmission Owners for each offshore circuit. Offshore expansion factors are Offshore Transmission Owner and circuit specific. Each Offshore Transmission Owner will periodically provide, via the STC, information to derive an annual circuit revenue requirement. The offshore circuit revenue shall include revenues associated with the Offshore Transmission Owner’s reactive compensation equipment, harmonic filtering equipment, asset spares and HVDC converter stations.
In the year that the offshore transmission assets are transferred to the Offshore Transmission Owner, the offshore circuit expansion factor would be calculated as follows: C R e v O F T O O n s h o r e k V O H L E x p a n s i o n C o n s t a n t L C i r c R a t Where: CRevOFTO1 = The offshore circuit revenue in £ for Year 1 L = The total circuit length in km of the offshore circuit CircRat = The continuous rating of the offshore circuit
In all subsequent years, the offshore circuit expansion factor would be calculated as follows: A v C R e v O F T O O n s h o r e k V O H L E x p a n s i o n C o n s t a n t L C i r c R a t Where: AvCRevOFTO = The annual offshore circuit revenue averaged over the remaining years of the onshore National Electricity Transmission System Operator (NETSO) price control L = The total circuit length in km of the offshore circuit CircRat = The continuous rating of the offshore circuit
For the avoidance of doubt, the offshore circuit revenue values, CRevOFTO1 and AvCRevOFTO shall be determined using asset values after the removal of any One-Off Charges.
Prevailing Offshore Transmission Owner specific expansion factors will be published in the Statement of Use of System Charges which is available from the Website. These shall be recalculated for the start of each price control period using the formula in paragraph 14.15.82. For each subsequent year within the price control period, these expansion factors will be adjusted by the annual Offshore Transmission Owner specific indexation factor, OFTOInd, calculated as follows; where: OFTOInd = the indexation factor for Offshore Transmission t,f Owner f in respect of Financial Year t; OFTORevInd = the indexation rate applied to the revenue of t,f Offshore Transmission Owner f under the terms of its transmission licence in respect of Financial Year t; and TOPI = the indexation rate applied to the expansion t constant in respect of Financial Year t. Offshore Interlinks
The revenue associated with an Offshore Interlink shall be divided entirely between those Generators benefiting from the installation of that Offshore Interlink. Each of these Users will be responsible for their charge from their charging date, meaning that a proportion of the Offshore Interlink revenue may be socialised prior to all relevant Users being chargeable. The proportion associated with each User will be based on the Measure of Capacity to the MITS using the Offshore Interlink(s) in the event of a single circuit fault on the User’s circuit from their offshore substation towards the shore, compared to the Measure of Capacity of the other Users. Where: An Offshore Interlink is a circuit which connects two offshore substations that are connected to a Single Common Substation. It is held in open standby until there is a transmission fault that limits the User’s ability to export power to the Single Common Substation. In the Transport Model, they are to be modelled in open standby. A Single Common Substation is a substation where: i. each substation that is connected by an Offshore Interlink is connected via at least one circuit without passing through another substation; and ii. all routes connecting each substation that is connected by an Offshore Interlink to the MITS pass through. The Measure of Capacity to the MITS for each Offshore substation is the result of the following formula or zero whichever is larger. For the situation with only one interlink, all terms relating to C should be set to zero: For Substation A: min { Cap , ILF × TEC - RCap , Cap - ILF × TEC + min (Cap , Cap - IAB A A A B B B IBC C ILF × TEC ) } C C For Substation B: min { ILF × TEC - RCap min (Cap , Cap - ILF × TEC ) B B B, IAB A A A + min ( Cap , Cap - ILF × TEC ) } IBC C C C For Substation C: min { Cap , ILF × TEC - RCap , Cap - ILF × TEC + min (Cap , Cap – IBC C C - C B B B IAB A ILF × TEC ) } A A and Cap = total capacity of the Offshore Interlink between substations A IAB and B Cap = total capacity of the Offshore Interlink between substations B IBC and C Cap = total capacity of the circuit between offshore substation X and X the Single Common Substation, where X is A, B or C. RCap = remaining capacity of the circuit between offshore substation X X and the Single Common Substation in the event of a single cable fault, where X is A, B or C. TEC = the sum of the TEC for the Users connected, or contracted to X connect, to offshore substation X, where X is A, B or C, where the value of TEC will be the maximum TEC that each User has held since the initial charging date, or is contracted to hold if prior to the initial charging date. ILF = Offshore Interlink Load Factor, where X is A, B or C. X The Offshore Interlink Load Factor (ILF) is based on the Annual Load Factor (ALF). Until all the Users connected to a Single Common Substation have a station specific Annual Load Factor based on five years of data, the generic ALF for the fuel type will be used as the ILF for all stations. When all Users have a station specific ALF, the value of the ALF in the first such year will be used as the ILF in the calculation for all subsequent Financial Years.
The apportionment of revenue associated with Offshore Interlink(s) in 14.15.85 applies in situations where the Offshore Interlink was included in the design phase, or if one or more User(s) has already financially committed or been commissioned then only where that User(s) agrees to the Offshore Interlink.
Alternatively to the formula specified in 14.15.85 the proportion of the OFTO revenue associated with the Offshore Interlink allocated to each generator benefiting from the installation of an Offshore Interlink may be agreed between these Users. In this event: a. All relevant Users shall notify The Company of its respective proportions three months prior the OTSDUW asset transfer in the case of a generator build, or the charging date of the first generator, in the case of an OFTO build. b. All relevant Users may agree to vary the proportions notified under (a) by each writing to The Company three months prior to the charges being set for a given Financial Year. c. Once a set of proportions of the OFTO revenue associated with the Offshore Interlink has been provided to The Company, these will apply for the next and future Financial Years unless and until The Company is informed otherwise in accordance with (b) by all of the relevant Users. d. If all relevant Users are unable to reach agreement on the proportioning of the OFTO revenue associated with the Offshore Interlink they can raise a dispute. Any dispute between two or more Users as to the proportioning of such revenue shall be managed in accordance with CUSC Section 7 Paragraph 7.4.1 but the reference to the ‘London Court of International Arbitration’ shall instead be to the ‘Authority’ and the Authority’s determination of such dispute shall, without prejudice to apply for judicial review of any determination, be final and binding on the Users. The Locational Onshore Security Factor
The locational onshore security factor for everything other than Identified Onshore Circuits is derived by running a secure DCLF ICRP transport study of the network excluding local circuits and Identified Onshore Circuits based on the same market background as used for Zoning in the DCLF ICRP transport model. This calculates the nodal marginal costs where peak net demand can be met despite the Security and Quality of Supply Standard contingencies (simulating single and double circuit faults) on the network. Essentially the calculation of secured nodal marginal costs is identical to the process outlined above except that the secure DCLF study additionally calculates a nodal marginal cost taking into account the requirement to be secure against a set of worse case contingencies in terms of maximum flow for each circuit.
For the purposes of 14.15.88 the secured nodal cost differential is compared to that produced by the DCLF ICRP transport model and the resultant ratio of the two determines the locational security factor using the Least Squares Fit method. Further information may be obtained from the Website.
For the purposes of 14.15.88 the locational onshore security factor, derived in accordance with paragraphs 14.15.88 and 14.15.89 and expressed to two decimal places, is based on an average from a number of studies conducted by The Company to account for future network developments. This security factor is reviewed for each price control period and fixed for the duration. The locational onshore security factor which is currently applicable, is detailed in the Statement of Use of System Charges. 14.15.90A An Identified Onshore Circuit shall be defined as a single transmission HVDC subsea circuit or a single transmission AC subsea circuit between two MITS Nodes where there is only one route for the power to flow between the two MITS Nodes. The expansion factors for Identified Onshore Circuits are adjusted by dividing the applicable expansion factor for the Identified Onshore Circuits, calculated as per Sections 14.15.70 to 14.15.77, by the locational onshore security factor calculated in 14.15.90. When the locational onshore security factor is applied as per Section 14.15.94 and 14.15.95, this would result in an effective locational onshore security factor for Identified Onshore Circuits of 1.0. Local Security Factors
Local onshore security factors are generator specific and are applied to a generator’s local onshore circuits. If the loss of any one of the local circuits prevents the export of power from the generator to the MITS then a local security factor of 1.0 is applied. For generation with circuit redundancy, a local security factor is applied that is equal to the locational security factor, derived in accordance with paragraphs 14.15.88 and 14.15.90.
Where a Transmission Owner has designed a local onshore circuit (or otherwise that circuit once built) to a capacity lower than the aggregated TEC of the generation using that circuit, then the local security factor of 1.0 will be multiplied by a Counter Correlation Factor (CCF) as described in the formula below; D + T m in c a p C C F = G c a p Where; D = minimum annual net demand (MW) supplied via that circuit in min the absence of that generation using the circuit T = transmission capacity built (MVA) cap G = aggregated TEC of generation using that circuit cap CCF cannot be greater than 1.0.
A specific offshore local security factor (LocalSF) will be calculated for each offshore connection using the following methodology: N e t w o r k E x p o r t C a p a c i ty L o c a l S F = G e n k k Where: NetworkExportCapacity = the total export capacity of the network disregarding any Offshore Interlinks k = the generation connected to the offshore network
The local offshore security factor for single circuits with a single cable will be 1.0 and for multiple circuit connections will be capped at the locational onshore security factor, derived in accordance with 14.15.88-14.15.90.
The offshore local security factor for configurations with one or more Offshore Interlinks is updated so that the offshore circuit tariff will include the proportion of revenue associated with the Offshore Interlink(s). The specific offshore local security factor for configurations involving an Offshore Interlink, which may be greater than the locational onshore security factor, will be calculated for each offshore connection using the following methodology: I R e v O F T O N e t w o r k E x p o r t C a p a c i ty L o c a l S F = + L o c a l S F in itia l C R e v O F T O G e n k k Where: IRevOFTO = The appropriate proportion of the Offshore Interlink(s) revenue in £ associated with the offshore connection calculated in 14.15.85 CRevOFTO = The offshore circuit revenue in £ associated with the circuit(s) from the offshore substation to the Single Common Substation. LocalSF = Initial Local Security Factor calculated in 14.15.93 and 14.15.94 initial And other definitions as in 14.15.93. Initial Transport Tariff
First an Initial Transport Tariff (ITT) must be calculated for both Peak Security and Year Round backgrounds. For Generation, the Peak Security zonal marginal km (ZMkm ), Year Round Not-Shared zonal marginal km PS (ZMkm ) and Year Round Shared zonal marginal km (ZMkm ) are simply
Similarly, for demand the Peak Security zonal marginal km ( ZMkm ) and PS Year Round zonal marginal km (ZMkm ) are simply multiplied by the YR expansion constant and the locational security factor to give the Peak Security ITT and Year Round ITT respectively: Z M k m E C L S F = I T T D i P S D i P S ZMkm ECLSF = ITT DiYR DiYR Where ZMkm = Peak Security Zonal Marginal km for each demand zone DiPS ZMkm = Year Round Zonal Marginal km for each demand zone DiYR ITT = Peak Security Initial Transport Tariff (£/MW) for each demand DiPS zone ITT = Year Round Initial Transport Tariff (£/MW) for each demand zone DiYR
The next step is to multiply these ITTs by the expected metered triad gross GSP group demand and generation capacity to gain an estimate of the initial revenue recovery for both Peak Security and Year Round backgrounds. The metered triad gross GSP group demand and generation capacity are based on analysis of forecasts provided by Users and are confidential. Metered triad gross GSP group demand is net demand for all GSP groups less embedded exports for all GSP groups. Where ITRR = Initial Transport Revenue Recovery for generation G G = Total forecast Generation for each generation zone (based on analysis Gi of confidential User forecasts) ITRR = Initial Transport Revenue Recovery for gross GSP group demand D D = Total forecast Metered Triad gross GSP group Demand for each Di demand zone (based on analysis of confidential User forecasts) In addition, the initial tariffs for generation are also multiplied by the Peak Security flag when calculating the initial revenue recovery component for the Peak Security background. When calculating the initial revenue recovery for the Shared component of the Year Round background, the initial tariffs are multiplied by the Annual Load Factor (see below). When calculating the initial revenue recovery for the Not Shared component of the Year Round background, the initial tariffs are multiplied by the Year Round Not Shared Flag. Peak Security (PS) Flag
The revenue from a specific generator due to the Peak Security locational tariff needs to be multiplied by the appropriate Peak Security (PS) flag. The PS flags indicate the extent to which a generation plant type contributes to the need for transmission network investment at peak demand conditions. The PS flag is derived from the contribution of differing generation sources to the demand security criterion as described in the Security Standard. In the event of a significant change to the demand security assumptions in the Security Standard, The Company will review the use of the PS flag. Year Round Not Shared (YRNS) Flag
| Generation Plant Type | PS flag |
|---|---|
| Intermittent | 0 |
| Other | 1 |
The revenue from a specific generator due to the Year Round Not Shared locational tariff needs to be multiplied by the appropriate Year Round Not Shared (YRNS) flag. The YRNS flag indicates the extent to which a generation plant type contributes to the need for transmission network investment at year round demand conditions in areas of the System where the proportion of Low Carbon generation exceeds Carbon generation as defined in 14.15.49. Annual Load Factor (ALF)
| Generation Plant Type | YRNS flag |
|---|---|
| Non Conventional Carbon | 1 |
| Conventional Carbon | ALF |
The ALF for each individual Power Station is calculated using the relevant TEC (MW) and corresponding output data. Where output data is not available for a Power Station, including for new Power Stations and emerging Power Station technologies, generic data for the appropriate generation plant type will be used.
For a given Financial Year “t” the Power Station ALF will be based on information from the previous five Financial Years, calculated for each Financial Year as set out below. 17520 GMWh p ALF = p=1 17520 TECp0.5 p=1 Where: GMWh is the maximum of FPN or actual metered output in a Settlement p Period related to the power station TEC (MW); and TEC is the TEC (MW) applicable to that Power Station for that Settlement p Period including any STTEC and LDTEC, accounting for any trading of TEC.
The appropriate output (FPN or actual metered) figure is derived from BM Unit data available to The Company and relates to the total TEC of the Power Station.
Once all five Financial Year ALFs have been calculated for the individual Power Station they are compared, and the highest and lowest figures are discarded. The final ALF, to be used for transmission charging purposes, is calculated as the average of the remaining three ALFs.
In the event that only four Financial Years of complete output (FPN or actual metered) data are available for an individual Power Station then the higher three Financial Years ALF would be used in the calculation of the final ALF. In the event that only three Financial Years of complete output (FPN or actual metered) data are available then these three Financial Years would be used.
Due to the aggregation of output (FPN or actual metered) data for dispersed generation (e.g. cascade hydro schemes), where a single generator BMU consists of geographically separated power stations, the ALF would be calculated based on the total output of the BMU and the overall TEC of those Power Stations.
In the event that there are not three full Financial Years of an individual power station’s output available, missing output (FPN or actual metered) data would be replaced by generic data for that generation plant type to ensure three Financial Years of information are available for the Power Station. The derivation of the generic data is described in paragraphs 14.15.111-
Users will receive draft ALFs before 25th December of the Financial Year (t- 1) for the Financial Year (t) and will have a period of 15 Business Days 14.15.109 from date of publishing to notify The Company of any errors. Failure to agree changes relating to errors will be treated as a charging dispute under the CUSC.
The ALFs used in the setting of final tariffs will be published in the annual Statement of Use of System Charges. Changes to ALFs after this publication will not result in changes to published tariffs (e.g. following dispute resolution). Derivation of Generic ALFs
The generic ALF is derived from the average annual output of the ten most recently commissioned GB generation of a particular generation plant type that have at least five Financial Years’ data, using an identical methodology to that used for the Power Station specific calculation described above. Where less than ten GB Generators of a particular generation plant type exist, then data from all existing Generators of that particular generation plant type will be used. Example generation plant type categories are listed below;
| Fuel Type |
|---|
| Biomass |
| Coal |
| Gas |
| Hydro |
| Nuclear (by reactor type) |
| Oil & OCGTs |
| Pumped Storage |
| Onshore Wind |
| Offshore Wind |
| CHP |
The Company will keep these categories under review and update as necessary. Where within a category there is a significant locational difference consideration will be given to zonal generic factors. The factors used will be published in the Statement of Use of System Charges and will be reviewed annually.
If a User can demonstrate that the generation plant type of a Power Station has changed, consideration will be given to the use of relevant generic ALF information in the calculation of their charges until sufficient specific data is available.
For new and emerging generation plant types, where insufficient data is available to allow a generic ALF to be developed, The Company will use the best information available e.g. from manufactuers and data from use of similar technologies outside GB. The factor will be agreed with the relevant Generator. In the event of a disagreement the standard provisions for dispute in the CUSC will apply. TNUoS Embedded Export Tariff
Embedded exports are exports measured on a half-hourly basis by Metering Systems, in accordance with the BSC, that are not subject to generation TNUoS.
The embedded export tariff will be applied to the metered Triad volumes of Embedded Exports for each demand zone as follows: 𝐸𝐸𝑇 = 𝐼𝑇𝑇 +𝐼𝑇𝑇 +𝐸𝑋 𝐷𝑖 𝐷𝑖𝑃𝑆 𝐷𝑖𝑌𝑅 Where ITT DiPS = Peak Security Initial Transport Tariff for the demand zone; ITT DiYR = Year Round Initial Transport Tariff for the demand zone, and EX: First Financial Year following the implementation date of CMP 264/265: = (𝑋𝑃−𝐴𝐺𝐼𝐶)+𝐴𝐺𝐼𝐶 Second Financial Year following the implementation date of CMP 264/265: = (𝑋𝑃−𝐴𝐺𝐼𝐶)+𝐴𝐺𝐼𝐶 Third Financial Year following the implementation date of CMP 264/265 and every subsequent Financial Year: = AGIC Where XP = Value of demand residual in Financial Year prior to implementation AGIC = The Avoided GSP Infrastructure Credit (AGIC) which represents the unit cost of infrastructure reinforcement at GSPs which is avoided as a consequence of embedded generation connected to the distribution networks served by those GSPs. It is calculated from the average annuitised cost of that infrastructure reinforcement divided by the average capacity delivered by a supergrid transformer. The Avoided GSP Infrastructure Credit is calculated at the beginning of each price control period and in the first applicable Financial Year following the implementation date of CMP264/265 using data submitted by onshore TSOs as part of the price control process. The data used is from the most recent [20] schemes submitted under the price control process and indexed each year by the TOPI formula set out in 14.3.6 until the end of the price control. For the avoidance of doubt, this approach does not include the cost of the supergrid transformers or any other connection assets as they are paid for by the relevant DNOs thorough their connection charges. The Value of EET will be floored at zero, so that EET is always zero or positive. Di Di The embedded export tariff applicable where a User directly connected to the National Electricity Transmission System is located at a Grid Supply Point that connects to more than one demand zone, will be derived as follows: ITT = average (ITT ,ITT ITT …) DcPS DaPS DbPS DdPS ITT = average (ITT ,ITT ITT …) DcYR DaYR DbYR DdYR ITT DcPS = average of Peak Security Initial Transport Tariff attributable to each demand zone (ITT DaPS ,ITT DbPS ITT DdPS …); and ITT DcYR = average of Year Round Initial Transport Tariff attributable to each demand zone (ITT ,ITT ITT …). DaYR DbYR DdYR Where C is demand directly connected to the National Electricity Transmission System at a Grid Supply Point that connects to more than one demand zone, and a, b, d… are the relevant GSP Groups. Initial Revenue Recovery
For the Peak Security background the initial tariff for generation is multiplied by the total forecast generation capacity and the PS flag to give the initial revenue recovery: 𝑛 ∑(ITT ×𝐺 ×𝐹 )= 𝐼𝑇𝑅𝑅 𝐺𝑖𝑃𝑆 𝐺𝑖 𝑃𝑆 𝐺𝑃𝑆 𝐺𝑖=1 Where: ITRR = Peak Security Initial Transport Revenue Recovery for GPS generation G = Total forecast Generation for each generation zone (based Gi on analysis of confidential User forecasts) F = Peak Security flag appropriate to that generator type PS n = number of generation zones The initial revenue recovery for gross GSP group demand for the Peak Security background is calculated by multiplying the initial tariff by the total forecast metered triad gross GSP group demand: ∑(𝐼𝑇𝑇 ×𝐷 )= 𝐼𝑇𝑅𝑅 𝐷𝑖𝑃𝑆 𝐷𝑖 𝐷𝑃𝑆 𝐷𝑖=1 Where: ITRR = Peak Security Initial Transport Revenue Recovery for gross DPS GSP group demand D = Total forecast Metered Triad gross GSP group Demand for Di each demand zone (based on analysis of confidential User forecasts)
For the Year Round background, the initial tariff for generation is multiplied by the total forecast generation capacity whilst calculating Initial Recovery for the Not-Shared component from Non Conventional Carbon. For Conventional Carbon the initial tariff for the Not Shared component is multiplied by both, the total forecast generation capacity and the ALF to give the initial revenue recovery. The initial tariff for the Shared component is multiplied by both, the total forecast generation capacity and the ALF to give the initial revenue recovery: 𝑛 ∑(𝐼𝑇𝑇 ×𝐺 )=𝐼𝑇𝑅𝑅 𝐺𝑖𝑌𝑅𝑁𝑆𝑁𝐶𝐶 𝐺𝑖 𝐺𝑌𝑅𝑁𝑆𝑁𝐶𝐶 𝐺𝑖=1 𝑛 ∑(𝐼𝑇𝑇 ×𝐺 ×𝐴𝐿𝐹)=𝐼𝑇𝑅𝑅 𝐺𝑖𝑌𝑅𝑁𝑆𝐶𝐶 𝐺𝑖 𝐺𝑌𝑅𝑁𝑆𝐶𝐶 𝐺𝑖=1 n ( ) ITT G ALF = ITRR GiYRS Gi GYRS Gi=1 𝐼𝑇𝑅𝑅 =𝐼𝑇𝑅𝑅 +𝐼𝑇𝑅𝑅 𝐺𝑌𝑅𝑁𝑆 𝐺𝑌𝑅𝑁𝑆𝑁𝐶𝐶 𝐺𝑌𝑅𝑁𝑆𝐶𝐶 Where: ITRR = Year Round Not-Shared Initial Transport Revenue Recovery for GYRNSNCC Non Conventional Carbon generation ITRR = Year Round Not-Shared Initial Transport Revenue Recovery for GYRNSCC Conventional Carbon generation ITRR = Year Round Not-Shared Initial Transport Revenue Recovery for GYRNS generation ITRR = Year Round Shared Initial Transport Revenue Recovery for GYRS generation ALF = Annual Load Factor appropriate to that generator.
Similar to the Peak Security background, the initial revenue recovery for gross GSP group demand for the Year Round background is calculated by multiplying the initial tariff by the total forecast metered triad gross GSP group demand: (ITT D )= ITRR DiYR Di DYR Di=1 Where: ITRR = Year Round Initial Transport Revenue Recovery for gross GSP DYR group demand
The initial revenue recovery for Embedded Exports is the Embedded Export Tariff multiplied by the total forecast volume of Embedded Export at triad: 𝐼𝑇𝑅𝑅 = ∑(𝐸𝐸𝑇 ×𝐸𝐸𝑉 ) 𝐸𝐸 𝐷𝑖 𝐷𝑖 𝐷𝑖=1 Where ITRR = Initial Revenue impact for Embedded Exports EE EEV = Forecast Embedded Export metered volume at Triad (MW) Di For the avoidance of doubt, the initial revenue recovery for embedded exports can be positive or negative. Deriving the Final Local Tariff (£/kW) Local Circuit Tariff
Generation with a local circuit tariff is calculated by multiplying the Year Round nodal marginal km along the local circuit by the expansion constant and the relevant local security factor (whether onshore or offshore) and summing across local circuits to give the local circuit tariff: NLMkm LECLocalSF Gj k =CLT 1000 Gi k Where k = Local circuit k for generator NLMkm L = Year Round Nodal marginal km along local circuit k using local Gj circuit expansion factor. EC = Expansion Constant LocalSF = Local Security Factor for circuit k k CLT = Circuit Local Tariff (£/kW) Gi Onshore Local Substation Tariff
All chargeable generation is subject to the local substation tariff component. This is determined by assessing the generation substation type for the substation at the connection charging boundary against three cost determining factors:
HV connection voltage – the voltage at the boundary between the User’s connection assets and the transmission system;
Sum of TEC at the generation substation – the combined TEC of all generation at the connecting substation; and
The level of redundancy at the generation substation – single busbar / single switch mesh connections are examples of no redundancy connections, whereas examples of connections with redundancy include double busbar and mesh sub station designs.
Using the above factors, the corresponding £/kW tariffs that are currently applicable, are detailed in the Statement of Use of System Charges.
The process for calculating Local Substation Tariffs will be carried out for the first year of the price control and will subsequently be indexed by TOPI for each subsequent year of the price control period.
The effective Local Tariff (£/kW) is calculated as the sum of the circuit and substation onshore and/or offshore components: E L T = C L T + S L T G i G i G i Where ELT = Effective Local Tariff (£/kW) Gi SLT = Substation Local Tariff (£/kW) Gi
Where tariffs do not change mid way through a Financial Year, final local tariffs will be the same as the effective tariffs: ELT = LT Gi Gi Where LT = Final Local Tariff (£/kW) Gi
Where tariffs are changed part way through the year, the final tariffs will be calculated by scaling the effective tariffs to reflect that the tariffs are only applicable for part of the year and parties may have already incurred TNUoS liability. 21 14 12ELT G −FLL 12ET D −FL Gi Gi Gi Di Di Di LT = Gi=1 FT = Di=1 and Gi 21 Di 14 bG bD Gi Di Gi=1 Di=1 Where: b = number of months the revised tariff is applicable for FLL = Forecast local liability incurred over the period that the original tariff is applicable for
For the purposes of charge setting, the total local charge revenue is calculated by: = j= L C R R L T * G G G i j G i Where LCRR = Local Charge Revenue Recovery G G = Forecast chargeable Generation or Transmission Entry Capacity j in kW (as applicable) for each generator (based on analysis of confidential information received from Users) Offshore substation local tariff
All offshore chargeable generation is subject to an offshore substation tariff. The offshore substation tariff shall be the sum of transformer, switchgear and platform components.
Each tariff component, expressed in £/kW, shall be the ratio of the Offshore Transmission Owner revenue (£) and rating associated with the transformers, switchgear or platform (kW) at each offshore substation. The Offshore Transmission Owner revenue of each tariff component shall include that associated with asset spares. In the case of the platform component, the relevant rating shall be the lower of the transformer or switchgear ratings. As with the offshore circuit expansion factors, the Offshore Transmission Owner revenue associated with each tariff component shall be averaged over the remaining years of the NETSO price control.
Offshore Transmission Owner revenue associated with interest during construction and project development overheads will be attributed to the relevant asset category with which it is associated. If these or any other costs included in the Offshore Transmission Owner revenue are not readily attributable to a given asset category, they will be pro-rated across the various asset categories based on their relative cost.
A discount shall be provided to the offshore substation tariff to reflect the average cost of civil engineering for onshore substations. The currently applicable discount is detailed in the Statement of Use of System Charges. This will be inflated by TOPI each year and reviewed every price control period.
Offshore substation tariffs shall be reviewed at the start of every onshore price control period. For each subsequent year within the price control period, these shall be inflated in the same manner as the associated Offshore Transmission Owner Revenue.
The revenue from the offshore substation local tariff is calculated by: SLTR = SLT Gen k k Alloffshore k substations Where: SLT = the offshore substation tariff for substation k k Gen = the generation connected to offshore substation k k The Residual Tariff
The total revenue to be recovered through TNUoS charges is determined each year with reference to the Transmission Licensees’ Price Control formulas less the costs expected to be recovered through Pre-Vesting connection charges. Hence in any given year t, a target revenue figure for TNUoS charges (TRRt) is set as follows: TRR = R - PVC t t t Where TRR = TNUoS Revenue Recovery target for year . t t R = Forecast Revenue allowed under The Company’s Price Control for year t t (this term includes a number of adjustments, including for over/under recovery from the previous year). For further information, refer to condition F3 of the ESO Licence. PVC = Forecast Revenue from Pre-Vesting connection charges for year t t
In normal circumstances, the revenue forecast to be recovered from the initial transport tariffs will not equate to the total revenue target. This is due to a number of factors. For example, the transport model assumes, for simplicity, smooth incremental transmission investments can be made. In reality, transmission investment can only be made in discrete 'lumps'. The transmission system has been planned and developed over a long period of time. Forecasts and assessments used for planning purposes will not have been borne out precisely by events and therefore some distinction between an optimal system for one year and the actual system can be expected.
As a result of the factors above, in order to ensure adequate recovery of total Transmission Owner revenue, a set of non-locational Transmission Demand Residual Tariffs are calculated, which include infrastructure substation asset costs. These tariffs are billed alongside the initial transport tariffs for demand only so that the total revenue recovery is achieved. The total amount of revenue to be recovered through Transmission Demand Residual Tariffs is defined as the Transmission Demand Residual. 𝑇𝐷𝑅= 𝑇𝑅𝑅− 𝐼𝑇𝑅𝑅 −𝐼𝑇𝑅𝑅 − 𝐼𝑇𝑅𝑅 − 𝐼𝑇𝑅𝑅 − 𝐼𝑇𝑅𝑅 −𝐼𝑇𝑅𝑅 −𝐿𝐶𝑅𝑅 𝐷𝑃𝑆 𝐷𝑌𝑅 𝐸𝐸 𝐺𝑃𝑆 𝐺𝑌𝑅𝑁𝑆 𝐺𝑌𝑅𝑆 𝐺𝐺 −𝐴𝑑𝑗𝑅𝑒𝑣𝑒𝑛𝑢𝑒 Where TDR = Transmission Demand Residual AdjRevenue = Adjustment Revenue as per paragraph 14.14.5 Creation of Charging Bands for use in Transmission Demand Residual Tariff Setting
To produce the Transmission Demand Residual Tariffs a set of Charging Bands are to be created for each of the Residual Charging Groups using the following methodology.
For domestic Final Demand Sites whether connected to the Distribution system or Transmission system there will be one Charging Band and;
For non-domestic Final Demand Sites connected to the Distribution system there will be four Charging Bands for each of the Residual Charging Groups according to the methodology introduced to Schedule 32 of the DCUSA via DCUSA modification DCP358 and entitled ‘RESIDUAL CHARGING BANDS’ with boundaries set at the 40th, 70th and 85th percentiles and;
For Final Demand Sites directly connected to the Transmission system there will be four Charging Bands using the latest 24 months of gross Consumption data (from the Final Reconciliation Settlement Run or Reconciliation Settlement Run) with boundaries set at the 40th, 70th and 93rd percentiles and;
For Unmetered Supplies there will be one Charging Band.
These Charging Bands will be reviewed periodically and be implemented effective from the beginning of each Onshore Transmission Owner price control period. Transmission Demand Residual Tariff Setting
| Domestic Final Demand Sites | |
|---|---|
| LV No Mic | Band 1 (≤40th percentile) |
| Band 2 (>40th percentile – 70th percentile) | |
| Band 3 (>70th percentile – 85th percentile) | |
| Band 4 (>85th percentile) | |
| LV MIC | Band 1 (≤40th percentile) |
| Band 2 (>40th percentile – 70th percentile) | |
| Band 3 (>70th percentile – 85th percentile) | |
| Band 4 (>85th percentile) | |
| HV | Band 1 (≤40th percentile) |
| Band 2 (>40th percentile – 70th percentile) | |
| Band 3 (>70th percentile – 85th percentile) | |
| Band 4 (>85th percentile) | |
| EHV | Band 1 (≤40th percentile) |
| Band 2 (>40th percentile – 70th percentile) | |
| Band 3 (>70th percentile – 85th percentile) | |
| Band 4 (>85th percentile) | |
| Directly Connected Users Final Demand Sites | Band 1 (≤40th percentile) |
| Band 2 (>40th percentile – 70th percentile) | |
| Band 3 (>70th percentile – 93rd percentile) | |
| Band 4 (>93rd percentile) | |
| Unmetered Supplies |
The Transmission Demand Residual Tariffs are derived from the Transmission Demand Residual value calculated in 14.15.137 and the total aggregate annual consumption of all Final Demand Sites and Unmetered Supplies.
To determine the proportion of the Transmission Demand Residual to be recovered from each Charging Band:
Where there are Final Demand Sites in a Charging Band the total annual consumption from Final Demand Sites in the Charging Band in question is divided by the total annual consumption from all Final Demand Sites and Unmetered Supplies creating a percentage value.
Where there are Unmetered Supplies in a Charging Band the total annual consumption from Unmetered Supplies in the Charging Band in question is divided by the total annual consumption from all Final Demand Sites and Unmetered Supplies creating a percentage value. This percentage is multiplied by the Transmission Demand Residual to give the total value to be recovered from the Charging Band.
To set the Transmission Demand Residual Tariff for each Charging Band:
For each Charging Band containing Final Demand Sites the total value to be recovered from the Charging Band as per 14.15.141 is divided by the number of Final Demand Sites in the Charging Band to create a £/site annual charge. This charge is further divided by the number of days in the charging year for which this tariff applies to produce the Transmission Demand Residual Tariff for the Charging Band (£/site/day).
For each Charging Band containing Unmetered Supplies the total value to be recovered from the Charging Band as per 14.15.141 is divided by the total annual consumption from Unmetered Supplies in the Charging Band in question to create a p/kWh charge. This tariff is also defined as the UMS Tariff. Final £/kW Tariff
The effective Transmission Network Use of System tariff (TNUoS) for generation can now be calculated as the sum of the initial transport wider tariffs for Peak Security and Year Round backgrounds and Adjustment Tariff and local tariff (for generation): 𝐼𝑇𝑇 + 𝐼𝑇𝑇 + 𝐼𝐹𝐹 + 𝐴𝑑𝑗𝑇𝑎𝑟𝑖𝑓𝑓 𝐸𝑇 = 𝐺𝑖𝑃𝑆 𝐺𝑖𝑌𝑅𝑁𝑆 𝐺𝑖𝑌𝑅𝑆 𝑖 + 𝐿𝑇 𝐺𝑖 𝐺𝑖 and The effective Transmission Network Use of System tariff (TNUoS) for the HH Demand Locational can now be calculated as the sum of the initial transport wider tariffs for Peak Security and Year Round backgrounds for half-hourly metered demand: 𝐼𝑇𝑇 +𝐼𝑇𝑇 𝐷𝑖𝑃𝑆 𝐷𝑖𝑌𝑅 𝐸𝑇 = 𝐷𝑖 Where ET = Effective Generation TNUoS Tariff expressed in £/kW (ET would only be Gi Gi applicable to a Power Station with a PS flag of 1 and ALF of 1; in all other circumstances ITT , ITT and ITT will be applied using Power GiPS GiYRNS GiYRS Station specific data) AdjTariff = AdjTariff (from 14.14.5) applicable in time period ‘i’. i ET = Effective HH Demand Locational TNUoS Tariff expressed in £/kW Di The effective Transmission Network Use of System tariff (TNUoS) for embedded exports can now be calculated by expressing the embedded export tariff in £/kW values: 𝐸𝐸𝑇 𝐷𝑖 𝐸𝑇 = 𝐸𝐸𝑖 1000 Where ET = Effective Embedded Export TNUoS Tariff expressed in £/kW EEi For the purposes of the annual Statement of Use of System Charges ET will be Gi published as ITT ; ITT , ITT LT and AdjTariff (if required) GiPS GiYRNS GiYRS, Gi i
Where tariffs do not change mid way through a Financial Year, final demand and generation tariffs will be the same as the effective tariffs. F T = E T G i G i F T = E T D i D i 𝐹𝑇 =𝐸𝑇 𝐸𝐸𝐴𝑖 𝐸𝐸𝑖
Where tariffs are changed part way through the year, the final tariffs will be calculated by scaling the effective tariffs to reflect that the tariffs are only applicable for part of the year and parties may have already incurred TNUoS liability.
0 G
2 E T − F L G i G i G i G i= 1 F T = G i
7 G b G i G i= 1 14 12ET D −FL Di Di Di FT = Di=1 and 𝐹𝑇 = 12×(𝐸𝑇𝐸𝐸𝑖×∑1 𝐷 4 𝑖=1𝐸𝐸𝑇𝐷𝑖−𝐹𝐿𝐷𝑖) 𝐸𝐸𝑖 𝑏×∑1 Di 14 𝐸𝐸𝑇𝐷𝑖 𝐷 𝑖=1 bD Di Di=1 Where: b = number of months the revised tariff is applicable for FL = Forecast liability incurred over the period that the original tariff is applicable for Note: The ET element used in the formula above will be based on an individual Power Gi Stations PS flag and ALF for Power Station G , aggregated to ensure overall correct Gi revenue recovery.
If the final HH Demand Locational TNUoS Tariff results in a negative number then this is collared to £0/kW with the resultant revenue to be refunded to tFinal Demand smeared over the remaining demand zones via the Transmission Demand Residual: F T 0 If , then i = 1 to z D i z ( ) FT D Di Di NRRT = i=1 Therefore, D 14 D Di i=z+1 Therefore the revised Final Tariff for the gross demand zones with positive Final tariffs is given by: RFT =0 For i= 1 to z: Di RFT =FT +NRRT For i=z+1 to 14: Di Di D Where NRRT = Non Recovered Revenue Tariff (£/kW) D RFT = Revised Final Tariff (£/kW) Di
The tariffs applicable for any particular year are detailed in the Statement of Use of System Charges. Archived tariff information may also be obtained from the Website.
The zonal maps referenced in the Statement of Use of System Charges contain detailed information for the Financial Year in question of which Grid Supply Points fall into which TNUoS zones.
New Grid Supply Points will be classified into zones on the following basis: • For demand zones, according to the GSP Group to which the Grid Supply Point is allocated for energy market settlement purposes. • For a User directly connected to the National Electricity Transmission System, the following rules will apply to determine its demand zone: o If the Connection Site falls within a GSP Group’s geographic area, the new GSP that connects directly at the site will be assigned to the demand zone corresponding to the GSP Group, unless; o A User is directly connected to the National Electricity Transmission System at a Grid Supply Point that connects to more than one demand zone, in which case, for the purpose of DCLF modelling, the User’s demand will be spread evenly across the relevant GSP Groups to calculate the relevant zonal demand tariffs. • For generation zones, with reference to the geographic proximity to existing zones and, where close to a boundary between existing zones, with reference to the marginal costs arising from transport model studies. The GSP will then be allocated to the zone, which contains the most similar marginal costs.
The Company has available, upon request, the DCLF ICRP transport model, tariff model template and data necessary to run the model, consisting of nodal values of generation and demand connection points to the NETS. The model and data will enable the basic nodal charges to be determined and will also allow sensitivity analysis concerning alternative developments of generation and demand to be undertaken. The model is available from the Charging Team and whilst it is free of charge, it is provided under licence to restrict its distribution and commercial use.
The Company will be pleased to run specific sensitivity studies for Users under a separate study contract in line with the fees set out in the Statement of Use of System Charges. Please contact the Charging Team.
The factors which will affect the level of TNUoS charges from year to year include but are not limited to; • the forecast level of peak demand on the system • the Price Control formula (including the effect of any under/over recovery from the previous year), • the expansion constant, • the locational security factor, • the PS flag • the Year Round Not Shared (YRNS) Flag • the ALF of a generator • changes in the transmission network • HVDC circuit impedance calculation • changes in the pattern of generation capacity and demand. • changes in the pattern of embedded exports • the £/ € exchange rate and expected Generator Output • Number of Final Demand Sites per Charging Band • Volume (in kWh) apportioned to each Charging Band
In accordance with Standard Licence Condition C13, generation directly connected to the NETS 132kV transmission network which would normally be subject to generation TNUoS charges but would not, on the basis of generating capacity, be liable for charges if it were connected to a licensed distribution network qualifies for a reduction in transmission charges by a designated sum, determined by the Authority. Any shortfall in recovery will result in a unit amount increase in gross demand charges to compensate for the deficit. Further information is provided in the Statement of the Use of System Charges. Stability & Predictability of TNUoS tariffs
A number of provisions are included within the methodology to promote the stability and predictability of TNUoS tariffs. These are described in 14.29.
Demand tariffs for Demand Users directly connected to the NETS at GSPs that connect to more than one demand zone, will be derived from averages of the Peak Security and Year Round tariffs respectively attributable to each demand zone, as set out below: Transmission-connected demand user demand C, 200MW 400kV node NODE40 Demand A, 30MW Demand B, 70MW DNO B DNO A As demand C connects at a Connection Site consisting of connections to more than one demand zone, for the purpose of DCLF Transport modelling and calculation of demand zonal tariffs, demand C is spread evenly across the multiple GSP Groups (A and B). Therefore demand C at NODE40 is split into two parts: 100MW at GSP Group A, and 100MW at GSP Group B. The zonal demand at A and B is calculated as below (copying 14.15.41): The zonal Peak Security marginal km for demand zone A and B is calculated as follows. −1NMkm Dem jPS j WNMkm = jPS Dem j jDi j Z M k m = W N M k m D i P S j P S D i Where: Di = Demand zone Dem = Positive Nodal Net Demand from transport model, including 100MW at NODE40 by demand C for demand zone A, and 100MW at NODE40 by demand C for demand zone B. If Nodal Demand from a node is less than 0 (Exporting) the nodal demand will be set to zero and therefore not contribute to the Zonal marginal km Similarly, the zonal Year Round marginal km for demand zones is calculated as follows: −
N M k m D e m jY R j W N M k m = jY R D e m j j D i ZMkm = WNMkm DiYR jYR jDi Once the zonal Peak Security and Year Round tariffs are calculated for demand zones A and B (according to 14.15.97), a set of new demand zonal tariffs will be created for demand C as below – Zonal Peak Security tariff for demand C = average (Zone A Peak Security tariff, Zone B Peak Security tariff) Zonal Year Round tariff for demand C = average (Zone A Year Round tariff, Zone B Year Round tariff) For demand C, 𝑍𝑀𝑘𝑚 = 𝑍𝑀𝑘𝑚 +𝑍𝑀𝑘𝑚 , and 𝐷𝐶𝑃𝑆 𝐷𝐴𝑃𝑆 𝐷𝐵𝑃𝑆 𝑍𝑀𝑘𝑚 = 𝑍𝑀𝑘𝑚 +𝑍𝑀𝑘𝑚 𝐷𝐶𝑌𝑅 𝐷𝐴𝑌𝑅 𝐷𝐵𝑌𝑅 Allocating Final Demand Sites to Charging Bands
Users who own or operate a Distribution System shall maintain a methodology in DCUSA entitled “ALLOCATION OF CUSTOMERS TO CHARGING BANDS BY DNO/IDNO PARTIES” (introduced by DCUSA modification DCP360) to allocate Final Demand Sites and Unmetered Supplies to Charging Bands for their respective Distribution System.
In Charging Bands that are determined in accordance with 14.15.138, Final Demand Sites and Unmetered Supplies will be allocated to Charging Bands as follows;
For Embedded Final Demand Sites and Unmetered Supplies, Users who own or operate a Distribution System shall allocate Embedded Final Demand Sites and Unmetered Supplies to Charging Bands for their respective network as per the methodology described in 14.15.161
For Final Demand Sites connected to the NETS, the following hierarchy will apply, starting at (i) and progressing to (iv) to determine the correct Charging Band as created in 14.15.139; i. Where available, the mean average of the latest 24 months Consumption data for the specific Final Demand Site shall be used. Where this is not available in terms of (ii), (iii) and (iv); ii. The mean average of as much data Consumption data as is available for the specific Final Demand Site, or; iii. The Company making use of any valid information as is available or made available to best estimate the expected Consumption of the Final Demand Site, or; iv. Should no data or information be available for the specific Final Demand Site, a 12 month mean average of all Consumption from all NETS connected Final Demand Sites shall be used. 14.15.157A For all Final Demand Sites allocated under 14.15.157 2. (iii) or (iv), in the September following the completion of a full Financial Year for which the Final Demand Site has recorded actual metered data a review of the Charging Band allocation of the specific Final Demand Site will take place by The Company. 14.15.157B This review, (the “September New Site review”) will use the material change in circumstances as per paragraph 14.15.163 to determine whether the Final Demand Site will be reallocated to a different Charging Band. 14.15.157C The Company shall notify any Final Demand Site and it’s Supplier(s) should they be included in a September New Site review. This notification shall be no issued later than the 15th calendar day in August prior to the September New Site review. 14.15.157D Following the conclusion of the September New Site review, The Company shall notify both the Final Demand Site and it’s Supplier(s) of the outcome within 5 Business Days of the completion of the September New Site review. The Transmission Demand Residual Tariff as per the new Charging Band will apply from 1st October immediately following the September New Site review should any Final Demand Sites be reallocated to a different Charging Band. 14.15.157E The Company shall complete all September New Site reviews by the 15th calendar day of September. 14.15.157F Final Demand Sites will be subject to the September New Site review no more than once during the duration of their Bilateral Connection Agreement.
For the purpose of determining the Transmission Demand Residual Tariff liability for a given Final Demand Site, the Final Demand Site will be allocated to a Charging Band. • Allocation to a Charging Band for NETS connected Final Demand Sites will be in accordance with 14.15.157 2. The Final Demand Site will be allocated into a Charging Band where the Final Demand Site’s gross Consumption value, is less than or equal to the maximum threshold for that Charging Band. • Allocation to a Charging Band for Embedded Final Demand Sites will be in accordance with the methodology described in 14.15.156 and 14.15.157
14.15.158A For Mixed Demand Sites connected to the NETS, the provisions of 14.15.158 shall be applied to the Mixed Demand Site’s gross Consumption except where a valid Declaration is provided by the User. This Declaration shall clearly identify the Metering Systems (or Operational Metering Equipment where a Metering System is not viable) used to isolate and identify gross Final Demand Consumption from any other Consumption at the Mixed Demand Site. A Mixed Demand Site’s gross Final Demand Consumption shall either be measured using meters installed at each Final Demand asset, or alternatively, be calculated as the difference between the Mixed Demand Site’s gross Consumption as metered at the site boundary, and consumption metered at each asset which does not consume Final Demand. Should a valid Declaration be provided, any Consumption not associated with Final Demand will be removed before the provisions of 14.15.158 are applied. Where it is unclear whether the Consumption is Final Demand or not, it will be treated as Final Demand. 14.15.158B For Embedded Mixed Demand Sites, the methodology described in 14.15.156 shall be used.
For the purpose of determining the Transmission Demand Residual Tariff liability for a given Unmetered Supply, the Unmetered Supply will be allocated to the appropriate Residual Charging Group in accordance with 14.15.138.I
Final Demand Sites and Unmetered Supplies will be assigned to a Charging Band for the duration of the Onshore Transmission Owner price control, unless;
The Final Demand Site or and Unmetered Supply is reassigned by an intervention as described in 14.15.161 - 14.15.165, or 2. the Authority directs that the Final Demand Site or Unmetered Supply should be reassigned to a different Charging Band. Once allocated and subject to the intervention process, Final Demand Sites and Unmetered Supplies will be re-allocated to Charging Bands prior to the start of each Onshore Transmission Owner price control in accordance with 14.15.138. Charging Banding Interventions
Users who own or operate a Distribution System shall maintain a methodology in DCUSA entitled “EXCEPTIONAL CIRCUMSTANCES RESULTING IN RE- ALLOCATION TO A DIFFERENT BAND WITHIN A PRICE CONTROL PERIOD” (introduced by DCUSA modification DCP360) to manage interventions and disputes from Embedded Final Demand Sites and Unmetered Supplies connected to their respective Distribution System.
Where a Final Demand Site or Unmetered Supply (or their nominated Supplier(s) or agent) or a User or The Company wishes to challenge the allocation of such a Final Demand Site to a Charging Band, it shall;
For Embedded Final Demand Sites and Unmetered Supplies, Users who own or operate a Distribution System shall follow the methodology described in 14.15.161 for their respective network
For Final Demand Sites directly connected to the NETS, follow the process as defined in CUSC Section 7.3 to demonstrate a material change in circumstances.
For the purposes of 14.15.162 2. a material change in circumstances for NETS connected Final Demand Sites must be demonstrated by;
the voltage of connection of the Final Demand Site changing with an accompanying signed Construction Agreement; or 2. should Consumption data be used as the basis of Directly Connected Final Demand Site Charging Bands, providing 12 months of actual metered gross Consumption data which shows gross Consumption is lower than 50% or greater than 50% of the Consumption data applied to the relevant subheading of 14.15.157. For reductions in Consumption, this shall be accompanied with a signed letter from The Company Director (or equivalent) confirming the rationale for the exceptional and significant changes to consumption (including historical Consumption); or 3. A notice to Disconnect is provided in accordance with CUSC Section 5.7.
Any changes to Transmission Network Use of System Demand Charges as a result of a intervention (as described in 14.15.161) shall be collected or refunded (as appropriate) through the reconciliation process described in 14.25.
The requirements of 14.15.161 - 14.15.163 shall not preclude the Final Demand Site’s or Unmetered Supply’s right to refer the matter directly to the Authority for determination. Declarations
A Declaration is a statement to be submitted by the Registrant of the relevant BM Unit(s) or Single Site, which:
is signed by one of the Storage Facility Operator’s registered Directors that confirms that a Electricity Storage Facility fulfils the criteria set out in the definitions of SVA Storage Facility and CVA Storage Facility as applicable; and either
for SVA Storage Facility only, is submitted in accordance with the BSC and contains other details that are required in accordance with BSC Section S; or
for CVA Storage Facility only, identifies the specific BM Units which only perform activities necessary for Electricity Storage and is submitted to The Company.
is signed by one of the Electricity Generation Facility’s registered Directors that confirms that the Electricity Generation Facility only perform activities necessary for Electricity Generation and is submitted to The Company.
is signed by one of the Eligible Services Facility’s registered Directors that confirms the Eligible Services Facility can only perform activities necessary for Eligible Services and does not consume any Active Power other than for the provision of Eligible Services and is submitted to The Company.
is signed by one of the Mixed Demand Site’s registered Directors that confirms the Mixed Demand Site contains both Final Demand and a Generator or Electricity Storage Plant and is submitted to The Company. The validity of a Declaration for an SVA Storage Facility is determined in accordance with BSC Section S, and of a Declaration for a CVA Storage Facility, Non-Final Demand Site and Eligible Services Facility is determined by The Company.
A Declaration received by The Company will either be accepted or rejected within three Business Days and shall take effect on the effective date and time as notified to the Registrant. Any disagreement between The Company and the Registrant on the validity of a Declaration will be treated as a Charging Dispute.
Any Declarations that are accepted by The Company shall be valid in perpetuity. Should circumstance at the relevant BM Unit(s) or Single Site change in such a way that the Declaration is no longer accurate, it is the responsibility of the User to resubmit a revised Declaration as soon as possible to reflect the change in circumstance. The Company will validate any revised Declarations as per 14.15.167.
The Company shall, at its sole discretion and acting reasonably, have the right to audit and revalidate a previously approved Declaration. The User agrees to support and cooperate with any audit and/or revalidation as required (including access to site if required). An inaccurate Declaration shall immediately be deemed to be invalid and the provisions of this Section 14 applied to the relevant BM Unit(s) or Single Site to:
reflect no Declaration being in effect for the next calendar day; and
retroactively apply Transmission Network Use of System Charges from the date of invalidity to the later of:
a previously valid Declaration; or
the Final Reconciliation Statement as per paragraph 3.13.7.
Anticipatory Investment
Anticipatory Investment (AI) is investment in transmission assets which goes beyond the needs of the immediate offshore development or developments. Where Anticipatory Investment has been identified by the Authority, the generators’ Offshore local tariff will be calculated as per 14.15.121, and 14.15.129 – 14.15.134, but will utilise their individual generation connected and their proportion (AI or non-AI) of the OFTO revenue, Network Export Capacity, and asset ratings rather than those of the total project.
Any generator(s) connected to the Offshore Transmission System at the point of asset transfer to the OFTO, will become liable for Offshore local tariffs for the non-AI portion of the OFTO revenue. Any subsequent generator(s) will become liable for Offshore local tariffs for the AI portion of the OFTO revenue at the point of connection.
During the period between the Offshore Transmission System being transferred to the OFTO and the subsequent generator(s) connecting, the AI portion of the OFTO revenue cannot be recovered from the subsequent generator(s). The difference between what is payable to the OFTO but cannot be recovered from the subsequent generator(s) is referred to as the ‘AI Cost Gap.’
Prior to the subsequent generator(s) connecting, the AI Cost Gap will be recovered from demand customers via the Transmission Demand Residual. The AI Cost Gap will be repaid to demand customers by the subsequent generator(s), once connected to the transmission system, either: • Through the AI Cost Gap Tariff. This tariff will be applied over a period of time equal to the number of days for which the subsequent generator(s) share of the AI Cost Gap was accrued, rounded up to a whole number of years, in addition to the number of days remaining in the charging year in which the subsequent generator(s) connects (if it connects after the first day of a charging year); or • alternatively, if decided by the generator(s), be paid via one payment in the charging year in which the subsequent generator(s) connects.
Calculating the AI Cost Gap: The AI proportion of OFTO revenue associated to the subsequent generator(s), will be identified for each full or partial charging year prior to the subsequent generator(s) connecting. Each year’s value will be inflated in line with the average increase in May – October CPIH as described in 14.15.170.6, to ensure it is in the appropriate price base for the year the AI Cost Gap Tariff becomes applicable. The total of these values will be the AI Cost Gap.
The inflation to be applied to the AI Cost Gap and the AI Cost Gap Tariff will be calculated as follows: (𝑀𝑎𝑦 𝑡𝑜 𝑂𝑐𝑡𝑜𝑏𝑒𝑟 𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝐶𝑃𝐼𝐻) 𝑡−1 𝐼𝑛𝑓𝑙𝑎𝑡𝑖𝑜𝑛 𝑖𝑛 𝑦𝑒𝑎𝑟 𝑡 = (𝑀𝑎𝑦 𝑡𝑜 𝑂𝑐𝑡𝑜𝑏𝑒𝑟 𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝐶𝑃𝐼𝐻) 𝑡−2
Calculating the AI Cost Gap Tariff: The AI Cost Gap Tariff for the subsequent generator (generator 𝑖) which is expressed in £/kW, shall be the ratio of the AI Cost Gap that generator 𝑖 is liable to pay for the relevant year (£) and the Transmission Entry Capacity (kW) of generator 𝑖, i.e: 𝑛×𝐴𝐼 𝐶𝑜𝑠𝑡 𝐺𝑎𝑝 • AI Cost Gap Tariff for Generator 𝑖 = 𝑁×𝑇𝐸𝐶𝑖 • Where: o 𝑇𝐸𝐶= Transmission Entry Capacity of generator 𝑖 in kW 𝑖 o 𝑛 = number of days remaining in the year over which the tariff is to be paid o 𝑁 = total number of days over which the tariff is applicable (calculated as per 14.15.170.4)
The calculation described in 14.15.170.6 shall be used for the initial partial year in which generator 𝑖 connects (if applicable) and the first full charging year. For each subsequent year that the AI Cost Gap Tariff is applicable after the year of calculation, the full year AI Cost Gap Tariff for generator 𝑖 shall be inflated in line with the average increase in May to October CPIH as per 14.15.170.6.
includes an example of adjusting scaling factors to ensure compliance with the floor. The base scaling factors and generation plant types are set out in the Security Standard. These may be reviewed from time to time. The latest version will be used in the calculation of TNUoS tariffs and is published in the Statement of Use of System Charges.
For the purposes of this section, Lead Parties of Balancing Mechanism (BM) Units that are liable for Transmission Network Use of System Demand Charges are termed Suppliers.
Following calculation of the Transmission Network Use of System £/kW HH Demand Locational Tariff (as outlined in Chapter 2: Derivation of the TNUoS Tariff) for each GSP Group a NHH Demand Locational Tariff is calculated as follows: p/kWh Tariff = (NHHD * £/kW Tariff - FL ) *100 F G NHHC G Where: £/kW Tariff = The £/kW Effective HH Demand Locational Tariff (£/kW), as calculated previously, for the GSP Group concerned. NHHD = The Company’s forecast of Suppliers’ non-half-hourly metered Triad F Demand (kW) for the GSP Group concerned. The forecast is based on historical data. FL = Forecast Liability incurred for the GSP Group concerned. G NHHC = The Company’s forecast of GSP Group non-half-hourly metered G total energy consumption (kWh) for the period 16:00 hrs to 19:00hrs inclusive (i.e. Settlement Periods 33 to 38) inclusive over the period the tariff is applicable for the GSP Group concerned. Short Term Transmission Entry Capacity (STTEC) Tariff
The Short Term Transmission Entry Capacity (STTEC) tariff for positive zones is derived from the Effective Tariff (ET ) annual TNUoS £/kW tariffs Gi (14.15.143). If multiple set of tariffs are applicable within a single Financial Year, the Final Tariff used in the STTEC calculation will be prorated in an identical manner to that used when calculating a Generators annual liability. The periods over which the tariff would be prorated would be identical to the periods used when calculating the wider tariff (i.e. over the whole Financial Year, not just the period that the STTEC is applicable for). STTECs will not be reconciled following a mid year charge change. The premium associated with the flexible product is associated with the analysis that 90% of the annual charge is linked to the system peak. The system peak is likely to occur in the period of November to February inclusive (120 days, irrespective of leap years). The calculation for positive generation zones is as follows: F T 0 .9 S T T E C P e r i o d G i = STTEC tariff (£/kW/period)
2 0 Where: FT = Final annual TNUoS Tariff expressed in £/kW Gi = Generation zone STTEC Period = A period applied for in days as defined in the CUSC
For the avoidance of doubt, the charge calculated under 14.16.3 above will represent each single period application for STTEC. Requests for multiple /STTEC periods will result in each STTEC period being calculated and invoiced separately.
The STTEC tariff for Generators with negative final tariffs is set to zero to prevent Users receiving greater than 100% of the annual TNUoS payment that would have been received for that capacity under a firm TEC. Limited Duration Transmission Entry Capacity (LDTEC) Tariffs
The Limited Duration Transmission Entry Capacity (LDTEC) tariff for positive zones is derived from the equivalent zonal STTEC tariff for up to the initial 17 weeks of LDTEC in a given Financial Year (whether consecutive or not). For the remaining weeks of the year, the LDTEC tariff is set to collect the balance of the annual TNUoS liability over the maximum duration of LDTEC that can be granted in a single application. If multiple set of tariffs are applicable within a single Financial Year, the Final Tariff used in the LDTEC calculation will be prorated in an identical manner to that used when calculating a Generators annual liability. The periods over which the tariff would be prorated would be identical to the periods used when calculating the wider tariff (ie over the whole Financial Year, not just the period that the STTEC is applicable for). LDTECs will not be reconciled following a mid year charge change: Initial 17 weeks (high rate): FT 0.97 LDTEC tariff (£/kW/week) = Gi Remaining weeks (low rate): FT 0.10757 LDTEC tariff (£/kW/week) = Gi ( 1+P ) 316−120 where FT is the final annual TNUoS tariff expressed in £/kW; G is the generation TNUoS zone; and i P is the premium in % above the annual equivalent TNUoS charge as determined by The Company, which shall have the value 0.
The LDTEC tariff for Generators with negative final tariffs is set to zero to prevent Users receiving greater than 100% of the annual TNUoS payment that would have been received for that capacity under a firm TEC.
The tariffs applicable for any particular year are detailed in the Statement of Use of System Charges. Historical tariffs are also available on the Website.
Demand Charges Parties Liable for Demand Charges
Demand charges are subdivided into charges for demand locational, Transmission Demand Residual, energy and embedded export. The following parties shall be liable for some or all of the categories of demand charges: • The Lead Party of a Supplier BM Unit; • Power Stations with a Bilateral Connection Agreement; • Parties with a Bilateral Embedded Generation Agreement
Classification of parties for charging purposes, section 14.26, provides an illustration of how a party is classified in the context of Use of System charging and refers to the paragraphs most pertinent to each party. Basis of Demand Locational Charges
Demand Locational charges are based on a de minimis £0/kW charge for Half Hourly and £0/kWh for Non Half Hourly metered demand.
Chargeable Demand Locational Capacity is the value of Half Hourly metered Triad demand (kW). Chargeable Energy Capacity is the energy consumption (kWh). The definition of both these terms is set out below.
If there is a single set of demand locational tariffs within a Financial Year, the Chargeable Demand Locational Capacity is multiplied by the relevant demand locational tariff, for the calculation of demand locational charges.
If there is a single set of energy tariffs within a Financial Year, the Chargeable Energy Capacity is multiplied by the relevant energy consumption tariff for the calculation of energy charges.
If multiple sets of demand locational tariffs are applicable within a single Financial Year, demand locational charges will be calculated by multiplying the Chargeable Demand Locational Capacity by the relevant tariffs pro-rated across the months that they are applicable for, as below, (𝑎×𝑇𝑎𝑟𝑖𝑓𝑓 1)+(𝑏×𝑇𝑎𝑟𝑖𝑓𝑓 2) 𝐴𝑛𝑛𝑢𝑎𝑙 𝐿𝑖𝑎𝑏𝑖𝑙𝑖𝑡𝑦 =𝐶ℎ𝑎𝑟𝑔𝑒𝑎𝑏𝑙𝑒 𝐷𝑒𝑚𝑎𝑛𝑑 𝐿𝑜𝑐𝑎𝑡𝑖𝑜𝑛𝑎𝑙 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦×( ) 𝐷𝑒𝑚𝑎𝑛𝑑 12 Where: Tariff 1 = Original tariff, Tariff 2 = Revised tariff, A = Number of months over which the original tariff is applicable, b = Number of months over which the revised tariff is applicable.
If multiple sets of energy tariffs are applicable within a single Financial Year, energy charges will be calculated by multiplying relevant Tariffs by the Chargeable Energy Capacity over the period that that the tariffs are applicable for and summing over the year. 𝐴𝑛𝑛𝑢𝑎𝑙 𝐿𝑖𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝐸𝑛𝑒𝑟𝑔𝑦 = 𝑇𝑎𝑟𝑖𝑓𝑓 1 𝑇1𝐸 ×∑𝐶ℎ𝑎𝑟𝑔𝑒𝑎𝑏𝑙𝑒 𝐸𝑛𝑒𝑟𝑔𝑦 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑇1𝑆 𝑇2𝐸 +𝑇𝑎𝑟𝑖𝑓𝑓 2×∑𝐶ℎ𝑎𝑟𝑔𝑒𝑎𝑏𝑙𝑒 𝐸𝑛𝑒𝑟𝑔𝑦 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑇2𝑆 Where: T1 = Start date for the period for which the original tariff is S applicable, T1 = End date for the period for which the original tariff is E applicable, T2 = Start date for the period for which the revised tariff is S applicable, T2 = End date for the period for which the revised tariff is E applicable. Basis of Embedded Export Charges
Embedded export charges are based on a £/kW charge for Half Hourly metered embedded export.
Chargeable Embedded Export Capacity is the value of Embedded Export at Triad (kW). The definition of this term is set out below.
If there is a single set of embedded export tariffs within a Financial Year, the Chargeable Embedded Export Capacity is multiplied by the relevant embedded export tariff, for the calculation of embedded export charges.
If multiple sets of embedded export tariffs are applicable within a single Financial Year, embedded export charges will be calculated by multiplying the Chargeable Embedded Export Capacity by the relevant tariffs pro rated across the months that they are applicable for, as below, (𝑎×𝑇𝑎𝑟𝑖𝑓𝑓 1)+(𝑏×𝑇𝑎𝑟𝑖𝑓𝑓 2) 𝐴𝑛𝑛𝑢𝑎𝑙 𝐿𝑖𝑎𝑏𝑖𝑙𝑖𝑡𝑦 =𝐶ℎ𝑎𝑟𝑔𝑒𝑎𝑏𝑙𝑒 𝐸𝑚𝑏𝑒𝑑𝑑𝑒𝑑 𝐸𝑥𝑝𝑜𝑟𝑡 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦×( ) 𝐷𝑒𝑚𝑎𝑛𝑑 12 where: Tariff 1= Original tariff, Tariff 2= Revised tariff, a = Number of months over which the original tariff is applicable, b = Number of months over which the revised tariff is applicable. Supplier BM Unit
A Supplier BM Unit charges will be the sum of its energy, demand locational, Transmission Demand Residual and embedded export liabilities where: • The Chargeable Demand Locational Capacity will be the average of the Supplier BM Unit's half-hourly metered gross demand during the Triad (and the £/kW tariff), and • The Chargeable Embedded Export Capacity will be the average of the Supplier BM Unit's half-hourly metered embedded export during the Triad (and the £/kW tariff), and • The Chargeable Energy Capacity will be the Supplier BM Unit's non half- hourly metered energy consumption over the period 16:00 hrs to 19:00 hrs inclusive every day over the Financial Year (and the p/kWh tariff), and • The Transmission Demand Residual charge for Final Demand Sites will be the sum of the number of sites per Charging Band as served by that Supplier BM Unit multiplied by the number of days the sites were served by that Supplier BM Unit and multiplied by the applicable Transmission Demand Residual Tariff £/site/day as determined in 14.15.142. Where a Connection Site is served by more than one Supplier BM Unit, the charges will be divided by The Company, annually, between the relevant Supplier BM Units in proportion to their annual Consumption from the previous year, and • The Transmission Demand Residual charge for Unmetered Supplies will be the sum of the forecast monthly volume of Unmetered Supplies per Charging Band as served by that Supplier BM Unit multiplied by the applicable UMS Tariff (p/kWh) as determined in 14.15.142. Power Stations with a Bilateral Connection Agreement and Licensable Generation with a Bilateral Embedded Generation Agreement
The Chargeable Demand Locational Capacity for a Power Station with a Bilateral Connection Agreement or Licensable Generation with a Bilateral Embedded Generation Agreement will be based on the average of the net import over each Triad leg of the BM Units associated with the Power Station (in Appendix C of its Bilateral Connection Agreement or Bilateral Embedded Generation Agreement, including metered additional load) during the Triad. Exemptible Generation and Derogated Distribution Interconnectors with a Bilateral Embedded Generation Agreement
The demand charges for Exemptible Generation and Derogated Distribution Interconnector with a Bilateral Embedded Generation Agreement will be the sum of its gross demand and embedded export liabilities where: The Chargeable Demand Locational Capacity for Exemptible Generation and Derogated Distribution Interconnectors with a Bilateral Embedded Generation Agreement will be based on the average of the metered gross demand of each BM Unit specified in Appendix C of the Bilateral Embedded Generation Agreement during the Triad. • The Chargeable Embedded Export Capacity for Exemptible Generation and Derogated Distribution Interconnectors with a Bilateral Embedded Generation Agreement will be based on the average of the metered embedded export of each BM Unit specified in Appendix C of the Bilateral Embedded Generation Agreement during the Triad. Small Generators Tariffs
In accordance with Standard Licence Condition C13, any under recovery from the MAR arising from the small generators discount will result in a unit amount of increase to the Transmission Demand Residual. The Triad
The Triad is used as a short hand way to describe the three Settlement Periods of highest transmission system demand within a Financial Year, namely the half hour Settlement Period of system peak net demand and the two half hour Settlement Periods of next highest net demand, which are separated from the system peak net demand and from each other by at least 10 Clear Days, between November and February of the Financial Year inclusive. Exports on directly connected Interconnectors and Interconnectors capable of exporting more than 100MW to the Total System shall be excluded when determining the system peak net demand. An illustration is shown below. 1999/2000 Triad Season -Peak System Demands )W G ( d 40 n a m e D 30 m e ts y S 20 k a e P
| 20/1 20/01/00 |
|---|
| 08/12/99 |
Nov 99 Date 29 Feb 00 Half-hourly metered Demand Locational charges
For Supplier BMUs and BM Units associated with Exemptible Generation and Derogated Distribution Interconnectors with a Bilateral Embedded Generation Agreement, if the average half-hourly metered gross demand volume over the Triad results in an import, the Chargeable Gross Demand Capacity will be positive resulting in the BMU being charged. If the average half-hourly metered embedded export volume over the Triad results in an export, the Chargeable Embedded Export Capacity will be negative resulting in the BMU being paid the relevant tariff; where the tariff is positive. For the avoidance of doubt, parties with Bilateral Embedded Generation Agreements that are liable for Generation charges will not be eligible for payment of the embedded export tariff. Monthly Charges
Throughout the year Users will submit a Demand Forecast. A Demand Forecast will include: • half-hourly metered gross demand to be supplied during the Triad for each BM Unit • half-hourly metered embedded export to be exported during the Triad for each BM Unit • non-half hourly metered energy to be supplied over the period 16:00 hrs to 19:00 hrs inclusive every day over the Financial Year for each BM Unit
Throughout the year, Users’ monthly demand charges will be based on; a. For HH Charges the User’s Demand Forecast half-hourly metered embedded export to be supplied during the Triad for each BM Unit, multiplied by the relevant zonal £/kW tariff; and where this results in a positive value the User’s Demand Forecast half hourly metered embedded export to be supplied during the Triad for each BM Unit, multiplied by the relevant zonal £/kW tariff. b. For NHH Charges the User’s Demand Forecast non-half hourly metered energy to be supplied over the period 16:00 hrs to 19:00 hrs inclusive every day over the Financial Year for each BM Unit, multiplied by the relevant zonal p/kWh tariff. c. The Final Demand Site Count Forecast for the latest day (that The Company has data available for) multiplied by the relevant £/Site/Day Transmission Demand Residual Tariff for the relevant Charging Band. d. the Unmetered Supply Volume Forecast for the latest day (that The Company has data available for) multiplied by the UMS Tariff. Users’ annual TNUoS demand charges are based on these forecasts with the Demand Forecast split evenly over the 12 months of the year. Users have the opportunity to vary their Demand Forecasts on a quarterly basis over the course of the year, with the Demand Forecast requested in February relating to the next Financial Year. Users will be notified of the timescales and process for each of the quarterly updates. The Company will revise the monthly Transmission Network Use of System Demand Charges by calculating the annual charge based on the above forecasts, subtracting the amount paid to date, and splitting the remainder evenly over the remaining months. For the avoidance of doubt, only positive Demand Forecasts (i.e. representing a net import from the system), positive FDSC Forecast and positive Unmetered Supply Volume Forecast will be used in the calculation of charges. Demand Forecasts for a User will be considered positive where: • The sum of the gross demand forecast and embedded export forecast is positive; and • The non-half hourly metered energy forecast is positive.
Users should submit reasonable demand forecasts of gross demand, embedded export and energy in accordance with the CUSC. The Company shall use the following methodology to derive a forecast to be used in determining whether a User's forecast is reasonable, in accordance with the CUSC, and this will be used as a replacement forecast if the User's total forecast is deemed unreasonable. The Company will, at all times, use the latest available Settlement data. For existing Users: i) The User’s Triad gross demand and embedded export for the preceding Financial Year will be used where User settlement data is available and where The Company calculates its forecast before the Financial Year. Otherwise, the User's average weekday Settlement Period 35 half-hourly metered (HH) gross demand and embedded export in the Financial Year to date is compared to the equivalent average gross demand and embedded export for the corresponding days in the preceding year. The percentage difference is then applied to the User's HH gross demand and embedded export at Triad in the preceding Financial Year to derive a forecast of the User's HH gross demand and embedded export at Triad for this Financial Year. ii) The User's non half-hourly metered (NHH) energy consumption over the period 16:00 hrs to 19:00 hrs every day in the Financial Year to date is compared to the equivalent energy consumption over the corresponding days in the preceding year. The percentage difference is then applied to the User's total NHH energy consumption in the preceding Financial Year to derive a forecast of the User's NHH energy consumption for this Financial Year. For new Users who have completed a Use of System Supply Confirmation Notice in the current Financial Year: iii) The User's average weekday Settlement Period 35 half-hourly metered
gross demand and embedded export over the last complete month for which The Company has settlement data is calculated. Total system average HH gross demand and embedded export for weekday Settlement Period 35 for the corresponding month in the previous year is compared to total system HH gross demand and embedded export at Triad in that year and a percentage difference is calculated. This percentage is then applied to the User's average HH gross demand and embedded export for weekday Settlement Period 35 over the last month to derive a forecast of the User's HH gross demand and embedded export at Triad for this Financial Year. iv) The User's non half-hourly metered (NHH) energy consumption over the period 16:00 hrs to 19:00 hrs every day over the last complete month for which The Company has settlement data is noted. Total system NHH energy consumption over the corresponding month in the previous year is compared to total system NHH energy consumption over the remaining months of that Financial Year and a percentage difference is calculated. This percentage is then applied to the User's NHH energy consumption over the month described above, and all NHH energy consumption in previous months is added, in order to derive a forecast of the User's NHH metered energy consumption for this Financial Year.
Determination of The Company’s Forecast for Demand Charge Purposes illustrates how the demand forecast will be calculated by The Company. Reconciliation of Demand Charges and TNUoS Charges in the event of exceeding the limits to Generator charges in the Limiting Regulation
The reconciliation process is set out in the CUSC. The demand reconciliation process compares the monthly charges paid by Users against actual outturn charges. Due to the Settlements process, reconciliation of demand charges is carried out in two stages; initial reconciliation and final reconciliation.
In the event of annual average transmission charges incurred by Generator Users in the Financial Year not being in compliance with the upper or lower limits in the Limiting Regulation an Ex-Post Reconciliation adjustment will be applied to Generator and Demand Users to bring charges back into compliance. Initial Reconciliation of demand charges
The initial reconciliation process compares Users' demand forecasts, The Company’s FDSC Forecast and Unmetered Supply Volume Forecast and corresponding monthly charges paid over the year against actual outturn data (using latest Settlement data available at the time) and corresponding charges. Initial reconciliation is carried out in three parts; Initial Reconciliation Part 1 deals with the reconciliation of half-hourly metered demand charges, Initial Reconciliation Part 2 deals with the reconciliation of non-half-hourly metered demand charges and Initial Reconciliation Part 3 deals with the reconciliation of Transmission Demand Residual charges. Initial Reconciliation Part 1– Half-hourly metered demand
The Company will identify the periods forming the Triad once it has received Central Volume Allocation data from the Settlement Administration Agent for all days up to and including the last day of February. Once The Company has notified Users of the periods forming the Triad they will not be changed even if disputes are subsequently resolved which would change the periods forming the Triad.
Initial outturn charges for half-hourly metered gross demand will be determined using the latest available data of actual average Triad gross demand (kW) multiplied by the zonal gross demand tariff(s) (£/kW) applicable to the months concerned for each zone for that Financial Year. These actual values are then reconciled against the monthly charges paid in respect of half- hourly gross demand.
Initial outturn charges for half-hourly metered embedded export will be determined using the latest available data of actual average Triad embedded export (kW) multiplied by the zonal embedded export tariff(s) (£/kW) applicable to the months concerned for each zone for that Financial Year. These actual values are then reconciled against the monthly charges paid in respect of half-hourly embedded exports. Initial Reconciliation Part 2 – Non-half-hourly metered demand
Actual payments for non-half-hourly metered demand will be determined using the latest available actual energy consumption data (kWh) for the period 16:00 hrs to 19:00 hrs inclusive (i.e. Settlement Periods 33 to 38) over the year multiplied by the energy consumption tariff(s) (p/kWh) applicable to the months concerned for each zone. These actual values are then reconciled against the monthly charges paid in respect of non-half-hourly energy consumption. Initial Reconciliation Part 3 – FDSC and Unmetered Supply Volume 14.17.29A Actual payments for Transmission Demand Residual charges will be determined using the latest FDSC and Unmetered Supply Volume (provided by the Settlement Administration Agent) multiplied by the relevant Transmission Demand Residual Tariff. These actual values are then reconciled against the charges paid by the User. Final Reconciliation of demand charges
The final reconciliation process compares Users' charges (as calculated during the initial reconciliation process using the latest available data) against final outturn demand charges (based on finalised FDSC and Unmetered Supply Volume, settlement data of half-hourly gross demand, embedded exports and non-half-hourly energy consumption).
Final actual charges will be determined using the Final Demand reconciliation data taken from the Final Reconciliation Settlement Run or the Final Reconciliation Volume Allocation Run. Reconciliation of manifest errors
In the event that a manifest error, or multiple errors in the calculation of TNUoS tariffs results in a material discrepancy in a Users TNUoS tariff, the reconciliation process for all Users qualifying under Section 14.17.34 will be in accordance with Sections 14.17.25 to 14.17.31. The reconciliation process shall be carried out using recalculated TNUoS tariffs. Where such reconciliation is not practicable, a post-year reconciliation will be undertaken in the form of a one-off payment.
A manifest error shall be defined as any of the following: a) an error in the transfer of relevant data between the Transmission Licensees or Distribution Network Operators; b) an error in the population of the Transport Model with relevant data; c) an error in the function of the Transport Model; or d) an error in the inputs or function of the Tariff Model.
A manifest error shall be considered material in the event that such an error or, the net effect of multiple errors, has an impact of the lesser of either:
an error in a User’s TNUoS tariff of at least +/-£0.76/kW; or
an error in a User’s TNUoS tariff which results in an error in the annual TNUoS charge of a User in excess of +/-£377,735 Thresholds are stated in 2020/21 money and will be indexed annually by the Transmission Owner Price Index (TOPI) thereafter, starting from 1st April 2021.
A manifest error shall only be reconciled if it has been identified within the Financial Year for which the error has an effect. Errors identified outside of this period will not be eligible for reconciliation retrospectively. Ex-post Reconciliation of Generator and Demand Charges in the event of exceeding the limits to Generator charges in the Limiting Regulation
The Company shall, following the completion of each Financial Year, produce a statement setting out the annual average transmission charges paid in aggregate by Generators in €/MWh as per paragraph 14.14.5.
In the event that the annual average transmission charges attributable to Generators exceeds the upper limit established in the Limiting Regulation then an Ex-post Reconciliation will be calculated for Generation and Demand Users as per the below and will be invoiced at the time of generation reconciliation and initial demand reconciliation. i) The Ex-post Reconciliation amount for Demand Users will be calculated as : Dadj = GCharge (Actual)-( 𝐺𝑂 ∗(𝐶𝑎𝑝𝐸𝐶∗𝐸𝑅 )) 𝐴 𝐴 Where: Dadj = Revenue to be recovered from Demand GO = Actual generator output in the previous Financial Year A CapEC = The upper limit of the Limiting Regulation 𝐸𝑅 = Actual exchange rate in the previous Financial Year 𝐴 GCharge (Actual) = Actual charges to Generators in the previous Financial Year ii) The rate applied to HH gross Demand, in order to adjust for any TNUoS recovery from generation outside of the range of the Limiting Regulation Dadj 𝐷𝑅𝑎𝑑𝑗 = ( ) 𝐺𝑇𝐷 Where DRadj = Rate applied to AHHD in £/kW GTD = Total actual system metered Gross Triad Demand (kW) iii) The rate applied to NHH energy consumption, in order to adjust for compliance with the Limiting Regulation in the Financial Year is calculated by: 𝐷𝑎𝑑𝑗−(𝐴𝐻𝐻𝐷 × 𝐷𝑅𝑎𝑑𝑗) 𝐸𝑅𝑎𝑑𝑗 = ( )x 100 𝐴𝑁𝐻𝐻𝐶 Where AHHD = The actual gross half-hourly metered Triad Demand (kW) for HH Demand ERadj = Rate applied to energy consumption for the Demand Recovery in p/kWh ANHHC = Total actual annual non-half-hourly metered energy consumption (kWh) for the period 16:00 hrs to 19:00 hrs inclusive (i.e. Settlement Periods 33 to 38) for each day of the preceding Financial Year , iv) The Ex-Post Reconciliation amount for Generation Users will be calculated as: Gadj = 𝐷𝑎𝑑𝑗∗−1 Where: Dadj = Revenue to be recovered from demand Users Gadj = Revenue to be paid to generation Users v) The rate applied to Generator Chargeable Capacity in the preceding Financial Year, in order to adjust for any recovery of TNUoS from generation outside of the range of the Limiting Regulation, is: 𝐺𝑎𝑑𝑗 GRadj = 𝐶ℎ𝑎𝑟𝑔𝑒𝑎𝑏𝑙𝑒𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 Where: GRadj = Adjustment rate to be applied to Generators Chargeable Capacity = As per paragraph 14.18.6
In the event that the annual average transmission charges attributable to Generators is below the lower limit established in the Limiting Regulation then an Ex-post Reconciliation will be calculated for Generator and Demand Users as per the below and will be invoiced at the time of generation reconciliation and initial demand reconciliation. i) Ex-post reconciliation for Demand Users: Dadj = GCharge (Actual)-0 Where: Dadj = Revenue to be credited to Demand GCharge (Actual) = Actual charges to Generators in the previous Financial Year ii) The rate applied to HH gross Demand, in order to adjust for any recovery of TNUoS from generation outside of the range of the Limiting Regulation 𝐷𝑎𝑑𝑗 𝐷𝑅𝑎𝑑𝑗 = ( ) 𝐺𝑇𝐷 Where DRadj = Rate applied to AHHD in £/kW GTD = Total actual system metered gross triad demand (kW) iii) The rate applied to NHH energy consumption, in order to adjust for compliance with the Limiting Regulation in the Financial Year is calculated by: 𝐷𝑎𝑑𝑗 −(𝐴𝐻𝐻𝐷 × 𝐷𝑅𝑎𝑑𝑗) 𝐸𝑅𝑎𝑑𝑗 = ( )x 100 𝐴𝑁𝐻𝐻𝐶 Where AHHD = The actual gross half-hourly metered Triad Demand (kW) for HH Demand ERadj = Rate applied to energy consumption for the Demand Recovery in p/kWh ANHHC = Total actual annual non-half-hourly metered energy consumption (kWh) for the period 16:00 hrs to 19:00 hrs inclusive (i.e. Settlement Periods 33 to 38) for each day of the preceding Financial Year Ex-post reconciliation for Generation Users: The recovery from Generator Users will be Gadj = 𝐷𝑎𝑑𝑗∗−1 Where: Dadj = Revenue to be dispersed to Demand Gadj = Revenue to be recovered from Generation iv) The rate applied to Generator Chargeable Capacity in the preceding Financial Year, in order to adjust for any recovery of TNUoS from generation outside of the range of the Limiting Regulation, is: 𝐺𝑎𝑑𝑗 GRadj = 𝐶ℎ𝑎𝑟𝑔𝑒𝑎𝑏𝑙𝑒𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 Where: GRadj = Adjustment rate to be applied to Generators Chargeable Capacity = As per paragraph 14.18.6
Implementation of P272
BSC modification P272 requires Suppliers to move Profile Classes 5-8 to Measurement Class E - G (i.e. moving from NHH to HH settlement) by April 2016. The majority of these meters are expected to transfer during the preceding Financial Year up until the implementation date of P272 and some meters will have been transferred before the start of 1ST April 2015. A change from NHH to HH within a Financial Year would normally result in Suppliers being liable for TNUoS for part of the year as NHH and also being subject to HH charging. This section describes how The Company will treat this situation in the transition to P272 implementation for the purposes of TNUoS charging; and the forecasts that Suppliers should provide to The Company.
Notwithstanding 14.17.13, for each Financial Year which begins after 31 March 2015 and prior to implementation of BSC Modification P272, all demand associated with meters that are in NHH Profile Classes 5 to 8 at the start of that Financial Year as well as all meters in Measurement Classes E G will be treated as Chargeable Energy Capacity (NHH) for the purposes of TNUoS charging for the full Financial Year.
The Company will calculate the Chargeable Energy Capacity associated with meters that have transferred to HH settlement but are still treated as NHH for the purposes of TNUoS charging from Settlement data provided directly from Elexon i.e. Suppliers need not Supply any additional information if they accept this default position
The forecasts that Suppliers submit to The Company under CUSC 3.10, 3.11 and 3.12 for the purpose of TNUoS monthly billing referred to in 14.17.20 and 14.17.21 for both Chargeable Demand Capacity and Chargeable Energy Capacity should reflect this position i.e. volumes associated those Metering Systems that have transferred from a Profile Class to a Measurement Class in the BSC (NHH to HH settlement) but are to be treated as NHH for the purposes of TNUoS charging should be included in the forecast of Chargeable Energy Capacity and not Chargeable Demand Capacity.
Where a Supplier wishes for Metering Systems that have transferred from Profile Class to Measurement Class in the BSC (NHH to HH settlement) prior to 1st April 2015, to be treated as Chargeable Demand Capacity (HH/ Measurement Class settled) it must inform The Company prior to October 2015. The Company will treat these as Chargeable Demand Capacity (HH / Measurement Class settled) for the purposes of calculating the actual annual liability for the Financial Years up until implementation of P272. For these cases only, the Supplier should notify The Company of the Meter Point Administration Number(s) (MPAN). For these notified meters the Supplier shall provide The Company with verified metered demand data for the hours between 4pm and 7pm of each day of each Financial Year up to implementation of P272 and for each Triad half hour as notified by The Company prior to May of the following Financial Year up until two years after the implementation of P272 to allow reconciliation (e.g. May 2017 and May 2018 for the Financial Year 2016/17). Where the Supplier fails to provide the data or the data is incomplete for a Financial Year TNUoS charges for that MPAN will be reconciled as part of the Supplier’s NHH BMU (Chargeable Energy Capacity). Where a Supplier opts, if eligible, for TNUoS liability to be calculated on Chargeable Demand Capacity it shall submit the forecasts referred to in 14.17.35.4 taking account of this.
The Company will maintain a list of all MPANs that Suppliers have elected to be treated as HH. This list will be updated monthly and will be provided to registered Suppliers upon request.
HH Elective Metering from 1st April 2017. The following section describes how meters migrating to, or already within, Measurement Classes E,F and G will be charged in terms of TNUoS after 31st March 2017.
A change from NHH to HH within a Financial Year would normally result in Suppliers being liable for TNUoS for part of the year as NHH and also being subject to HH charging. This section describes how The Company will treat this situation for Non-Half Hourly (NHH) meters migrating to Measurement Classes E, F & G for the Financial Year which begins after 31 March 2017.
Notwithstanding 14.17.13, for each Financial Year which begins after 31 March 2017 demand associated with Measurement Classes F and G will be treated as Chargeable Energy Capacity (NHH) for the purposes of TNUoS charging. Demand associated with Measurement Class E will continue to be treated as Chargeable Demand Capacity (HH).
The Company will calculate the Chargeable Energy Capacity associated with meters that have transferred to HH settlement but are still treated as NHH for the purposes of TNUoS charging from Settlement data provided directly from ELEXON i.e. Suppliers need not Supply any additional information.
The forecasts that Suppliers submit to The Company under CUSC 3.10, 3.11, 3.12 and 14.17.19 for the purpose of TNUoS monthly billing referred to in 14.17.20 and 14.17.21 for both Chargeable Demand Capacity and Chargeable Energy Capacity should reflect the basis on which demand will be charged for TNUoS.
The following section describes the arrangements that will apply in relation to introduction of half-hourly settlement on a market-wide basis.
Subject to 14.17.40.2, when an MPAN is settled under the MHHS Target Operating Model (as defined in Section C12 of the Balancing and Settlement Code) its associated BM Unit gross demand, embedded export or energy consumption will be charged TNUoS as per 14.17.13, except in the following circumstances:
When an MPAN with a non half-hourly Metering System transitions to a half hourly Metering System with a current transformer at Non- Domestic Premises (as defined in a Supply Licence) and is reported as such from BSCCo (as defined in the Balancing and Settlement Code), to The Company, its associated BM Unit gross demand or embedded export will be treated as Chargeable Demand Locational Capacity or Chargeable Embedded Export Capacity respectively.
When an MPAN with a non half-hourly Metering System transitions to a half-hourly Metering System with whole current metering at Non- Domestic Premises and is reported as such from BSCCo to The Company, its associated BM Unit energy consumption will be treated as Chargeable Energy Capacity.
When an MPAN transitions to a half-hourly Metering System at Domestic Premises (as defined in a Supply Licence) and is reported as such from BSCCo to The Company, its associated BM Unit energy consumption will be treated as Chargeable Energy Capacity Further Information
Paragraph 14.25 (Reconciliation of Demand Related Transmission Network Use of System Charges) of this statement illustrates how the monthly charges are reconciled against the actual values for gross demand, embedded consumption and consumption for half-hourly gross demand, embedded export and non-half-hourly metered demand respectively.
The Statement of Use of System Charges contains the £/kW zonal demand locational tariffs, the £/kW zonal embedded export tariffs, the p/kWh energy consumption tariffs, and the Transmission Demand Residual tariffs for the current charging year.
Transmission Network Use of System Charging Flowcharts of this statement contains flowcharts demonstrating the calculation of these charges for those parties liable.
Generation charges Parties Liable for Generation Charges
The following CUSC parties shall be liable for generation charges: i) Parties of Generators that have a Bilateral Connection Agreement with The Company. ii) Parties of Licensable Generation that have a Bilateral Embedded Generation Agreement with The Company.
14.26 Classification of parties for charging purposes provides an illustration of how a party is classified in the context of Use of System charging and refers to the relevant paragraphs most pertinent to each party. Structure of Generation Charges
Generation Tariffs are comprised of Wider and Local Tariffs. The Wider Tariff is comprised of (i) a Peak Security element, (ii) a Year Round Not-Shared element, (iii) Year Round Shared element and (iv) the Adjustment tariff (if required). The Peak Security element of the Wider Tariff is not applicable for intermittent generators as the PS flag is set to zero. The Year Round Not Shared element is multiplied by the YRNS Flag, which for Non-Conventional Carbon generators results in no change to the tariff, whereas for Conventional Carbon generators the tariff is reduced by ALF
The Local Tariff contains a substation element and may also contain a circuit element. Specifically, all transmission connected generation will be liable to pay a local substation charge, with some of these also being liable to pay a local circuit charge. For the avoidance of doubt, embedded generation has a zero local tariff.
The intention of the charging rules is to charge the same physical entity only once.
The basis of the generation charge for Power Stations is the Chargeable Capacity and the short-term chargeable capacity (as defined below for positive and negative charging zones).
If there is a single set of Wider and Local generation tariffs within a Financial Year, the Chargeable Capacity is multiplied by the relevant generation tariff to calculate the annual liability of a generator. 𝐿𝑜𝑐𝑎𝑙 𝐴𝑛𝑛𝑢𝑎𝑙 𝐿𝑖𝑎𝑏𝑖𝑙𝑖𝑡𝑦 = 𝐶ℎ𝑎𝑟𝑔𝑒𝑎𝑏𝑙𝑒 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦×𝐿𝑜𝑐𝑎𝑙 𝑇𝑎𝑟𝑖𝑓𝑓 The Wider Tariff is broken down into components as described in 14.18.3. The breakdown of the Wider Charge for Conventional and Intermittent Power Stations are given below: Conventional Low Carbon- 𝑊𝑖𝑑𝑒𝑟 𝐴𝑛𝑛𝑢𝑎𝑙 𝐿𝑖𝑎𝑏𝑖𝑙𝑖𝑡𝑦 = 𝐶ℎ𝑎𝑟𝑔𝑒𝑎𝑏𝑙𝑒 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 ×(𝑃𝑆 𝑇𝑎𝑟𝑖𝑓𝑓+ 𝑌𝑅𝑁𝑆 𝑇𝑎𝑟𝑖𝑓𝑓)+(𝑌𝑅𝑆 𝑇𝑎𝑟𝑖𝑓𝑓×𝐴𝐿𝐹)+𝐴𝑑𝑗𝑇𝑎𝑟𝑖𝑓𝑓 Conventional Carbon 𝑊𝑖𝑑𝑒𝑟 𝐴𝑛𝑛𝑢𝑎𝑙 𝐿𝑖𝑎𝑏𝑖𝑙𝑖𝑡𝑦 = 𝐶ℎ𝑎𝑟𝑔𝑒𝑎𝑏𝑙𝑒 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑥 (𝑃𝑆 𝑇𝑎𝑟𝑖𝑓𝑓+ (𝑌𝑅𝑁𝑆 𝑇𝑎𝑟𝑖𝑓𝑓 × 𝐴𝐿𝐹)+(𝑌𝑅𝑆 𝑇𝑎𝑟𝑖𝑓𝑓 × 𝐴𝐿𝐹)+𝐴𝑑𝑗 𝑇𝑎𝑟𝑖𝑓𝑓) Intermittent - 𝑊𝑖𝑑𝑒𝑟 𝐴𝑛𝑛𝑢𝑎𝑙 𝐿𝑖𝑎𝑏𝑖𝑙𝑖𝑡𝑦 = 𝐶ℎ𝑎𝑟𝑔𝑒𝑎𝑏𝑙𝑒 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦×(𝑌𝑅𝑁𝑆 𝑇𝑎𝑟𝑖𝑓𝑓+ (𝑌𝑅𝑆 𝑇𝑎𝑟𝑖𝑓𝑓×𝐴𝐿𝐹)+𝐴𝑑𝑗𝑇𝑎𝑟𝑖𝑓𝑓) Where: PS Tariff = Wider Peak Security Tariff YRNS Tariff = Wider Year Round Not-Shared Tariff YRS Tariff = Wider Year Round Shared Tariff Adj Tariff = Adjustment Tariff
If multiple sets of Wider and Local generation tariffs are applicable within a single Financial Year, the Chargeable Capacity is multiplied by the relevant tariffs pro rated over the entire Financial Year, across the months that they are applicable for. a T a r i f f 1 + b T a r i f f 2 A n n u a l L i a b i l i t y = C h a r g e a b l e C a p a c i t y
2 where: Liability 1 = Original annual liability, Liability 2 = Revised annual liability, a = Number of months over which the original liability is applicable, b = Number of months over which the revised liability is applicable.
For the avoidance of doubt if there are multiple sets of Wider and Local generation tariffs applicable within a single Financial Year and a tariff changes from being positive to negative or vice versa, the Chargeable Capacity for the entire Financial Year will be determined based on the net position of the pro rated tariffs for each affected generator. Basis of Wider Generation Charges Generation with positive wider tariffs
The Chargeable Capacity for Power Stations with positive wider generation tariffs is the highest Transmission Entry Capacity (TEC) applicable to that Power Station for that Financial Year. A Power Station should not exceed its TEC as to do so would be in breach of the CUSC, except where it is entitled to do so under the specific circumstances laid out in the CUSC (e.g. where a User has been granted Short Term Transmission Entry Capacity, STTEC). For the avoidance of doubt, TNUoS Charges will be determined on the TEC held by a User as specified within a relevant bilateral agreement regardless of whether or not it enters into a temporary TEC Exchange (as defined in the CUSC).
The short-term chargeable capacity for Power Stations situated with positive generation tariffs is any approved STTEC or LDTEC applicable to that Power Station during a valid STTEC Period or LDTEC Period, as appropriate.
For Power Stations, the short term chargeable capacity for LDTEC with positive generation tariffs referred to in Paragraph 14.18.11will be the capacity purchased either on a profiled firm1 or indicative2 basis and shall be assessed according to the capacity purchased on a weekly basis. The short- term chargeable capacity for LDTEC in any week may comprise of a number of increments, which shall be determined by considering LDTEC purchased previously in the Financial Year (whether or not in the same LDTEC Period). For example, if in a given week the LDTEC is 200MW but in a previous week the LDTEC had been 150MW, the short-term chargeable capacity in the latter week would comprise of two increments: one of 150MW and a second of 50MW. Further examples are provided in 14.16.6. Generation with negative wider tariffs
The Chargeable Capacity for Power Stations with negative wider generation tariffs is the average of the capped metered volumes during the three Settlement Periods described in 14.18.14 below, for the Power Station (i.e. the sum of the metered volume of each BM Unit associated with Power Station in Appendix C of its Bilateral Agreement). A Power Station should not exceed its TEC as to do so would be in breach of the CUSC, except where it is entitled to do so under the specific circumstances laid out in the CUSC (e.g. where a User has been granted Short Term Transmission Entry Capacity). If TEC is exceeded, the metered volumes would each be capped by the TEC for the Power Station applicable for that Financial Year. For the avoidance of doubt, TNUoS Charges will be determined on the TEC held by a User as specified within a relevant bilateral agreement regardless of whether or not it enters into a temporary TEC Exchange (as defined in the CUSC).
The three Settlement Periods are those of the highest metered volumes for the Power Station and the two half hour Settlement Periods of the next highest metered volumes which are separated from the highest metered volumes and each other by at least 10 Clear Days, between November and February of the relevant Financial Year inclusive. These Settlement Periods do not have to coincide with the Triad. Example 1 where an LDTEC Block Offer has been accepted (Profiled Block LDTEC) and a firm profile of capacity has been purchased.
where an LDTEC Indicative Block Offer has been accepted (Indicative Profiled Block LDTEC) and a right to future additional capacity up to a requested level has been purchased, the availability of which will be notified on a weekly basis in accordance with the CUSC. If the highest TEC for a Power Station were 250MW and the highest metered volumes and resulting capped metered volumes were as follows: Then, the chargeable Capacity for the Power Station would be: 2 4 5 . 5 + 2 5 0 + 2 5 0 = 248.5 MW Note that in the example above, the Generator has exceeded its TEC on 13 December 2007 and 6 February 2008 and would therefore be in breach of the CUSC unless the generator had an approved STTEC or LDTEC value. (The STTEC and LDTEC charge for negative zones is currently set at zero).
| Date | 19/11/08 | 13/12/08 | 06/02/09 |
|---|---|---|---|
| Highest Metered Volume in month (MW) | 245.5 | 250.3 | 251.4 |
| Capped Metered Volume (MW) | 245.5 | 250.0 | 250.0 |
The short-term chargeable capacity for Power Stations with negative generation tariffs is any approved STTEC or LDTEC applicable to that Power Station during a valid STTEC Period or LDTEC Period, as applicable.
For Power Stations with negative generation tariffs, the short-term chargeable capacity for LDTEC referred to in Paragraph 14.18.15 will be the capacity purchased either on a profiled firm or indicative basis and shall be assessed according to the capacity purchased on a weekly basis. The short-term chargeable capacity for LDTEC in any week may comprise of a number of increments, which shall be determined by considering LDTEC purchased previously in the Financial Year (whether or not in the same LDTEC Period). For example, if in a given week the LDTEC is 200MW but in a previous week the LDTEC had been 150MW, the short-term chargeable capacity in the latter week would comprise of two increments: one of 150MW and a second at 50MW.
As noted above, a negative LDTEC tariff in negative generation charging zones is set to zero. Accordingly no payments will be made for use of LDTEC (in any of its forms) in these zones. Basis of Local Generation Charges
The Chargeable Capacity for Power Stations will be the same as that used for wider generation charges, except that each component of the local tariff shall be considered separately as to whether it is a positive or negative tariff component. This means that where a local circuit tariff is negative, the final charging liability for this element will be based on actual metered output as described in Paragraph 14.18.13. Monthly Charges
Initial Transmission Network Use of System Generation Charges for each Financial Year will be based on the Power Station Transmission Entry Capacity (TEC) for each User as set out in their Bilateral Agreement. The charge is calculated as above. This annual TNUoS generation charge is split evenly over the months remaining in the year. For positive final generation tariffs, if TEC increases during the Financial Year, the party will be liable for the additional charge incurred for the full year, which will be recovered uniformly across the remaining chargeable months in the relevant Financial Year (subject to Paragraph 14.18.20 below). An increase in monthly charges reflecting an increase in TEC during the Financial Year will result in interest being charged on the differential sum of the increased and previous TEC charge. The months liable for interest will be those preceding the TEC increase from April in year t. For negative final generation tariff, any increase in TEC during the year will lead to a recalculation of the monthly charges for the remaining chargeable months of the relevant Financial Year. However, as TEC decreases do not become effective until the start of the Financial Year following approval, no recalculation is necessary in these cases. As a result, if TEC increases, monthly payments to the generator will increase accordingly.
The provisions described above for increases in TEC during the Financial Year shall not apply where the LDTEC (in any of its forms) has been approved for use before the TEC is available, which will typically mean the LDTEC has been approved after the TEC increase has been approved. In such instances, the party shall commence payments for TEC during the LDTEC Period for LDTEC purchased up to the future level of TEC and LDTEC Charges will only apply to LDTEC that is incremental to the TEC increase. For the avoidance of doubt, where TEC has been approved after LDTEC in a given year, these provisions shall not apply and the LDTEC shall be considered additional to the TEC and charged accordingly. Ad hoc Charges
For each STTEC period successfully applied for, a charge will be calculated by multiplying the STTEC by the tariff calculated in accordance with Paragraph 14.16.3. The Company will invoice Users for the STTEC charge once the application for STTEC is approved.
For Power Stations utilising LDTEC (in any of its forms) the LDTEC Charge for each LDTEC Period is the sum of the charging liabilities associated with each incremental level of short term chargeable capacity provided by LDTEC within the LDTEC Period (assessed on a weekly basis). The charging liability for a given incremental level of short term chargeable capacity is the sum of: i) the product of the higher tariff rate (calculated in accordance with Paragraph 14.16.6) and capacity purchased at this increment for the first 17 weeks in a Financial Year (whether consecutive or not); and ii) the product of the lower tariff rate (calculated in accordance with Paragraph 14.16.6) and capacity purchased at this increment in any additional weeks within the same Financial Year (whether consecutive or not).
For each LDTEC Period successfully applied for, the LDTEC Charge will be split evenly over the relevant LDTEC Period and charged on a monthly basis. LDTEC charges will apply to both LDTEC (in any of its forms) and Temporary Received TEC held by a User. For the avoidance of doubt, the charging methodology will not differentiate between access rights provided to a generator by LDTEC or through Temporary Received TEC obtained through a Temporary TEC Exchange (as defined in the CUSC). Example The diagrams below show two cases where LDTEC has been purchased: in Case A, two LDTEC Periods have been purchased; and in Case B one LDTEC Period has been purchased. The total capacity purchased in both cases is the same. The top diagrams illustrate the capacity purchased, while lower diagrams illustrate the incremental levels of short term chargeable capacities of LDTEC and the tariff rate that would apply to that capacity. MMM WWW MM WW 22 ww ee ee kk ss 111 333 000 MMM WWW ww ee ee kk ss 111 000 000 MMM WWW MM WW
The ETUoS charges are a component of Use of System charges levied on offshore generators whose offshore transmission connection is embedded in an onshore distribution network. The charge relates to the provision and use of the onshore distribution network.
The main purpose of ETUoS charges is to pass through the charges that are levied by the DNO on the NETSO to the offshore generator(s). This charge, known as the ETUoS charge, reflects the charges levied by the DNO for DNO the costs of any works on and use of the DNO network in accordance with the DNO’s charging statements and will include, but is not limited to, upfront charges and capital contributions in respect of any works as well as the ongoing and annual Use of System charges for generation connected to the distribution network.
In the case of some relevant transitional offshore generation projects, ETUoS will also be used to pass through historic DNO capital contributions forming part of the Offshore Transmission Owner tender revenue stream, this is known as the ETUoS tariff. OFTO i) The ETUoS tariff shall be the ratio of the Offshore Transmission OFTO Owner revenue (£) associated with DNO capital contributions and the Transmission Entry Capacity (TEC) of the generation connected to the offshore substation. ii) In the year of asset transfer to the OFTO, the ETUoS tariff OFTO would be calculated as follows: 𝐷𝑁𝑅𝑒𝑣𝑂𝐹𝑇𝑂1 𝑇𝐸𝐶 Where: 𝐷𝑁𝑅𝑒𝑣𝑂𝐹𝑇𝑂1 = The offshore revenue associated to DN capital contributions, in £, for Year 1 𝑇𝐸𝐶 = the Transmission Entry Capacity of the generation connected to the offshore substation iii) In all subsequent years, the ETUoS tariff would be calculated as OFTO follows: 𝐴𝑣𝐷𝑁𝑅𝑒𝑣𝑂𝐹𝑇𝑂 𝑇𝐸𝐶 Where: 𝐴𝑣𝐷𝑁𝑅𝑒𝑣𝑂𝐹𝑇𝑂 = The annual offshore revenue associated to DN capital contributions averaged over the remaining years of the National Electricity Transmission System Operator (NETSO) price control, in £ 𝑇𝐸𝐶 = the Transmission Entry Capacity of the generation connected to the offshore substation iv) ETUoS tariffs shall be reviewed at the start of every onshore OFTO price control period. For each subsequent year within the price control period, these shall be inflated in the same manner as the associated Offshore Transmission Owner Revenue.
The specific nature of the ETUoS charge and the payment profile for these DNO will depend upon the charging arrangements of the relevant DNO and reference should be made to the relevant DNO’s charging statement. In terms of applicable transitional offshore generation projects the ETUoS OFTO payment profile will be consistent with the recovery of the Offshore Transmission Owner revenue stream, and paragraph 14.18.27.
Where a DNO’s charge relates to more than one offshore generator, the related ETUoS charge will represent a straight pass through of the DNO distribution charge specific to each relevant offshore generator. Where specific information is not available, charges will be pro-rated based on the TEC of the relevant offshore generators connected to that offshore network.
Invoices for ETUoS charges shall be levied by The Company on the DNO offshore generator as soon as reasonably practicable after invoices have been received by The Company for payment such that The Company can meet its payment obligations to the DNO. The initial payments and payment dates will be outlined in a User’s Construction Agreement and/or Bilateral Agreement.
As the ETUoS charges reflect the DNO charges to The Company, such DNO charges will be subject to variation when varied by the DNO. Where the User disputes regarding the ETUoS charge please note that this will result in a DNO dispute between The Company and DNO under the DCUSA. Reconciliation of Generation Charges
The reconciliation process is set out in the CUSC and in line with the principles set out above.
In the event of a manifest error in the calculation of TNUoS charges which results in a material discrepancy in a User’s TNUoS charge as defined in Sections 14.17.33 to 14.17.35, the generation charges of Users qualifying under Section 14.17.34 will be reconciled in line with 14.18.19 and 14.18.20 using the recalculated tariffs. Further Information
The Statement of Use of System Charges contains the £/kW generation zonal tariffs for the current Financial Year.
Data Requirements Data Required for Charge Setting
Users who are Generators or Interconnector Asset Owners provide to The Company a forecast for the following Financial Year of the highest Transmission Entry Capacity (TEC) applicable to each Power Station or Interconnector for that Financial Year. For Financial Year 2008/9 Scottish Generators or Interconnector Asset Owners provide to The Company a forecast of the equivalent highest ‘export’ capacity figure. This data is required by The Company as the basis for setting TNUoS tariffs. The Company may request these forecasts in the November prior to the Financial Year to which they relate, in accordance with the CUSC. Additionally users who are Generators provide to The Company details of their generation plant type.
Users who are owners or operators of a User System (e.g. Distribution companies) provide a forecast for the following Financial Year of the Natural Demand attributable to each Grid Supply Point equal to the forecasts of Natural Demand under both Annual Average Cold Spell (ACS) Conditions and a forecast of the average metered Demand attributable to such Grid Supply Point for the Triad. This data Electricity Ten Year Statement (ETYS) is compiled from week 24 data submitted in accordance with the Grid Code.
The BSCCo will provide data to The Company with respect to Final Demand Site counts and Unmetered Supply volumes to enable the development of the Transmission Demand Residual Tariffs.
For the following Financial Year, The Company shall use these forecasts as the basis of Transmission Network Use of System charges for such Financial Year. A description of how this data is incorporated is included in 14.15 Derivation of the Transmission Network Use of System Tariff.
If no data is received from the User, then The Company will use the best information available for the purposes of calculation of the TNUoS tariffs. This will normally be the forecasts provided for the previous Financial Year. Data Required for Calculating Users’ Charges
In order for The Company to calculate Users' TNUoS charges, Users who are Suppliers shall provide to The Company forecasts of half-hourly and non- half-hourly demand in accordance with paragraph 14.17.19 and 14.17.20 and in accordance with the CUSC.
Application fees are payable in respect of applications for new Use of System agreements; modifications to existing agreements; and applications for short- term access products or services. These are based on the reasonable costs that transmission licensees incur in processing these applications. Applications for short-term access
Application fees for short-term access products or services are fixed and detailed in the Statement of Use of System Charges. These are non- refundable except for the following limited instances: • Where a User (or Users) withdraw their application in accordance with any interactivity provisions that may be contained within the CUSC; or • Where the application fee covers ongoing assessment work that is contingent on the acceptance of the offer.
In either case, the refunded amount will be proportional to the remaining assessment time available.
To ensure that application fees for short-term access are cost reflective, fees may be comprised of a number of components. For instance, the LDTEC Request Fee is comprised of a number of components and the total fee payable is the sum of those components that apply to the type(s) of LDTEC Offer(s) requested. For example: • The LDTEC Request Fee for an LDTEC Block Offer is the basic request fee. • The LDTEC Request Fee for an LDTEC Indicative Block Offer is the sum of the basic request fee and the additional rolling assessment fee. • The LDTEC Request Fee payable for a combined LDTEC Block Offer and LDTEC Indicative Block Offer is the sum of the basic request fee, the additional rolling assessment fee, and the additional combined application fee. Applications for new or modified existing Use of System Agreements
Users can opt to pay a fixed price application fee in respect of their application or pay the actual costs incurred. The fixed price fees for applications are detailed in the Statement of Use of System Charges.
If a User chooses not to pay the fixed fee, the application fee will be based on an advance of transmission licensees’ Engineering and out-of pocket expenses and will vary according to the size of the scheme and the amount of work involved. Once the associated offer has been signed or lapsed, a reconciliation will be undertaken. Where actual expenses exceed the advance, The Company will issue an invoice for the excess. Conversely, where The Company does not use the whole of the advance, the balance will be returned to the User.
The Company will refund the first application fee paid (the fixed fee or the amount post-reconciliation) and consent payments made under the Construction Agreement for new or modified existing agreements. The refund shall be made either on commissioning or against the charges payable in the first three years of the new or modified agreement. The refund will be net of external costs.
The Company will not refund application fees for applications to modify a new agreement or modified existing agreement at the User’s request before any charges become payable. For example, The Company will not refund an application fee to delay the provision of a new connection if this is made prior to charges becoming payable.
Transport Model Example For the purposes of the DCLF Transport algorithm, it has been assumed that the value of circuit impedance is equal to the value of circuit reactance. Consider the following 3-node network, where generation at node A is intermittent and generation at node B is conventional: N o d e k m 2 7 5 k V O H L N o d e G e n = 8 4 5 M WW GD ee nm = 50 00 MM WW A B D e m = 5 0 M = I m p e d a n c e = 2 X 2 k m 4 0 0 k V c a b le I m p e d a n c e = X k m 0 k V O H L 6 k m 4 0 0 k V O H L I m p e d a n c e = X N oC d e T o t a l G e n = 1 4 9 5 M W T o t a l D e m = 1 1 5 0 M W G e n S0 c a lin g F a c t o r = Ge e n = 0 M W . 7 6 9 2 3 0 8 D m = 1 0 0 0 M W Denotes cable For both Peak Security and Year Round generation backgrounds, the nodal generation is scaled according to the relevant Scaling Factors, as per 14.15.7, such that total system generation equals total system demand minus total imports from external systems. Scaling Factor Adjustment to 10% minimum If the SQSS process gives a variable scaling factor less than 10%, then it will be adjusted along with the fixed factors as per the following example. Total Unscaled TEC = 107600 ACS Demand = 49870 Increasing the variable scaling factor to 10% results in an increase of 5190MW to total scaled generation, which is then counteracted by a uniform 10.06% reduction to all fixed scaling factors (N.B some rounding included below). “Scaling Factor after 10% floor applied” column in the table below gives the required scaling factors to ensure total scaled TEC is equal to 49870 (ACS). Total scaled generation for fixed plant types in SQSS = 51600 Reduction required/SQSS fixed generation = 5190/51600 = 10.06% Peak Security background: A fixed scaling factor of 0% is applied to intermittent generation at node A and a variable scaling factor is applied to the conventional generation at node B so that the total generation is equal to the total demand. Node A Generation = 0 * 643MW = 0MW Node B Generation = 1150/ 1500 * 1500MW = 1150MW This gives the following balanced system , where the actual generation after the application of scaling factors is shown: N o d e k m 2 7 5 k V O H L N o d e G e n = 6 5 0 M WW GD ee nm = 00 00 MM WW A B D e m = 5 0 M = Im p e d a n c e = X k m 4 0 0 k V c a b le Im p e d a n c e = X 0 k m 0 k V O H L 6 k m 4 0 k V O H L Im p e d a n c e = X N o d e T o ta l S c a le d G e n = C
| Generator Type | TEC | Type | Year Round Background SQSS Scaling Factor | Scaled Generation (SQSS) | Scaling Factor after 10% floor applied | Scaled Generation after floor applied for variable |
|---|---|---|---|---|---|---|
| Biomass | 2000 | Variable | -5% | -100 | 10.00% | 200 |
| CCGT | 30000 | Variable | -5% | -1500 | 10.00% | 3000 |
| CHP | 2000 | Variable | -5% | -100 | 10.00% | 200 |
| Coal | 0 | Variable | -5% | 0 | 10.00% | 0 |
| Hydro | 600 | Variable | -5% | -30 | 10.00% | 60 |
| Interconnectors | 10000 | Fixed | 100% | 10000 | 89.94% | 8994 |
| Nuclear | 6000 | Fixed | 85% | 5100 | 76.45% | 4587 |
| OCGT | 2000 | Fixed | 0% | 0 | 0% | 0 |
| Pump Storage | 10000 | Fixed | 50% | 5000 | 44.97% | 4497 |
| Tidal | - | Fixed | 70% | 0 | 62.96% | 0 |
| Wave | - | Fixed | 70% | 0 | 62.96% | 0 |
| Wind Offshore | 25000 | Fixed | 70% | 17500 | 62.96% | 15740 |
| Wind Onshore | 20000 | Fixed | 70% | 14000 | 62.96% | 12592 |
1 5 0 M W T o ta l D e m = 1 1 5 0 M W Ge e n = 0 M W D m = 1 0 0 0 M W Assuming Node A is the reference node†,, each 400kV circuit has impedance X, the 275kV circuit has impedance 2X, the 400kV cable circuit expansion factor is 10 and the 275kV overhead line circuit expansion factor is 2, the DCLF transport algorithm calculates the base case power flows for Peak Security background as follows: Node B exports, whilst Nodes A and C import. Hence the DCLF algorithm derives flows to deliver export power from Node B to meet import needs at Nodes A and C. Step 1: Net export from Node B to Node A is 100MW; both routes BA and BC-CA have impedance 2X; hence 50MW would flow down both routes. Gen = 500MW Node 3km 275kV OHL Node Gen = 650MW Dem = 100MW A B Dem = 50MW Impedance =2X 2km 400kV cable Impedance = X 10km 400kV OHL 6km 400kV OHL Impedance = X Node Total Scaled Gen = C 1150MW Total Dem = 1150MW Gen = 0MW Dem = 1000MW Step 2: Net export from Node B to Node C is 1000MW; route BC has impedance X and route BA-AC has impedance 3X; hence 750MW would flow down BC and 250MW along BA- AC † For simplicity, fixed reference node has been used instead of a distributed reference node. Step 3: Using super-position to add the flows derived in Steps 1 and 2 derives the following; Flow AC = -50MW + 250MW = 200MW Flow AB = -50MW – 250MW = -300MW Flow BC = 50MW + 750MW = 800MW Year Round background: A fixed scaling factor of 70% is applied to intermittent generation at node A and a variable scaling factor is applied to the conventional generation at node B so that the total generation is equal to the total demand. Node A Generation = 70% * 643MW = 450MW Node B Generation = (1150-450)/1500 * 1500MW = 700MW This gives the following balanced system, where the actual generation after the application of scaling factors is shown: Gen = 450MW Node 3km 275kV OHL Node Gen = 700MW Dem = 100MW A B Dem = 50MW Impedance = 2X 2km 400kV cable Impedance = X 10km 400kV OHL 6km 400kV OHL Impedance = X Node C Total Scaled Gen = 1150MW Total Dem = 1150MW Gen = 0MW Dem = 1000MW Assuming the same circuit impedances and expansion factors as used above in the Peak Security background, the DCLF transport algorithm calculates the base case power flows for Year Round background as follows: x 2 = k m & I m p =
X N o d e G e n = 7 0 0 M W 50 00 MM WW N oA d e GD ee nm = B D e m = 5 0 M W = 5 M W 2 5 M W 5 7 5 M W 6 + ( 2 x 1 0 ) = 2 6 k m & I m p = X 1I 0m kp m &X = N oC d e p o w e r f lo w s f r o m n o d e B t o n o d e C in v e r s e ly p r o p o r t io n a l t o t h e s u m o f im p e d a n c e s f o r B C a n d B A C . S a m e p r in c ip le is t r u e f o r n o d e A . S u p e r - Ge e n = 0 M W p o s it io n o f t h e s e d e r iv e s f in a l n e t D m = 0 0 0 M W c ir c u it f lo w s f o r A B , A C & B C Nodes A and B export, whilst Node C imports. Hence the DCLF algorithm derives flows to deliver export power from Nodes A and B to meet import needs at Node C. Step 1: Net export from Node A is 350MW; route AC has impedance X and route AB-BC has impedance 3X; hence 262.5MW would flow down AC and 87.5MW along AB-BC Step 2: Net export from Node B is 650MW; route BC has impedance X and route BA-AC has impedance 3X; hence 487.5MW would flow down BC and 162.5MW along BA-AC Step 3: Using super-position to add the flows derived in Steps 1 and 2 derives the following; Flow AC = 262.5MW + 162.5MW = 425MW Flow AB = 87.5MW – 162.5MW = -75MW Flow BC = 87.5MW + 487.5MW = 575MW Then, based on the background giving rise to highest flow, each circuit is tagged as either Peak Security or Year Round.
30 MM WW N oA d e N oB d e G e ne = 1 00 0M M W GD ee nm = D m = W = 0 M W 5 M W M W 0 M W 5 7 5 M W 4 2 5 M W N o d e C Ge e n = 0 M0 WM D m = 1 0 W Therefore, circuits AB and BC are tagged as Peak Security and AC is tagged as Year Round. Total Peak Security cost = (300 X 6) + (800 X 26) = 22,600MWkm (base case) Total Year Round cost = 425 X 10 = 4,250 MWkm (base case) We then ‘inject’ 1MW of generation at each node with a corresponding 1MW offtake (demand) at the reference node and recalculate the total Peak Security MWkm cost and Year Round MWkm cost (noting that each circuit is only in one background). The difference from the base case for Peak Security and Year Round costs is the marginal km or shadow cost for Peak Security and Year Round networks respectively. The size and direction of the incremental MW is shown below along with the resultant when superimposed on the relevant base case flow (i.e. higher of the Peak Security and Year Round) depicted in brackets:. To calculate relevant Peak Security and Year Round the marginal km for node C: Total Peak Security Cost = (300.25 x 6) + (799.75 x 26) =22,595 Total Year Round Cost = 424.25 X 10 = 4,242.5 MWkm Marginal Peak Security cost = Incremental total Peak Security cost – Base case total Peak Security cost = 22595 – 22600 = -5MWkm Marginal Year Round cost = Incremental total Year Round cost – Base case total Year Round cost = 4242.5 – 4250 = -7.5MWkm Thus the overall cost has reduced by .5 for Peak Security (i.e. the marginal km = 5) and by 7.5 for Year Round (i.e the Year Round marginal km = -7.5)
Illustrative Calculation of Boundary Sharing Factors (BSFs) and Shared / Not-Shared incremental km The following illustrative example shows how the boundary sharing factors and shared / not-shared incremental km are calculated for the transmission system described in the table below. The diagram below shows the expanded connectivity of this transmission system. up The above figure illustrates how the Year Round marginal km are split into Shared and Not- Shared.
| Generation Charging Zone | A | B | C | D |
|---|---|---|---|---|
| Zonal MWkm | 450 | 350 | 150 | 100 |
For Boundary AB (where 50MW of the generation is Low Carbon (LC) and 0MW of the generation is Carbon (C) and Year Round boundary marginal km = 100km) - L C = = 1 which is greater than 0.5, therefore the following formula will ( ) L C + C + 0 be used to calculate the Boundary Sharing Factor (BSF) – L C 5 0 ( ) + 2 B S F = − 2 = − 2 + = 0 % L C + C 5 0 + Year Round Shared marginal km = 0.0 * 100km = 0 km Year Round Not-Shared marginal km = (100 – 0)km = 100 km
For Boundary BC (where 130MW of generation is Low Carbon (LC) and 50MW of generation is Carbon (C) and Year Round boundary marginal km = 200km) – ( ) 5 0 + 8 0 L C = = 0 . 7 2 which is greater than 0.5, therefore the ( ) ( ) ( ) L C + C + 8 0 + 0 + 5 following formula will be used to the BSF – L C
3 ( 5 5 .6 % ) + 2 B S F = − 2 = − 2 + = .5 5 L C + C
3 0 + 0 Year Round Shared marginal km = 0.556 * 200km = 111 km Year Round Not-Shared marginal km = (200 – 111)km = 89 km
For Boundary CD (where 250MW of generation is Low Carbon (LC) and 170MW of generation is Carbon (C) and Year Round boundary marginal km = 50km) – ( ) 5 0 + 8 0 + 1
0 L C = = 0 .5 which is greater than 0.5, therefore ( ) ( ) L C + C + 8 0 + 1 2 0 + ( 0 + 5 0 +
2 0 ) the following formula will be used to calculate the BSF – L C
5 0 B S F = − 2 + 2 = − 2 + = . 8 ( 8 1 % ) L C + C 2 5 0 + 1 7 0 Year Round Shared marginal km = 0.81 * 50km = 40.5 km Year Round Not-Shared marginal km = (50 – 40.5)km = 9.5 km
For Boundary D-rest of system (where 330MW of generation is Low Carbon (LC) and 330MW of generation is Carbon (C) and Year Round boundary marginal km = 100km) – ( ) 5 0 + 8 0 + 1 2 0 + 8 0 L C = = 0 .5 therefore it is at the threshold ( ) ( ) ( ) L C + C + 8 0 + 1 2 0 + 8 0 + 0 + 5 0 + 0 + at which maximum sharing occurs between LC and C generation. Therefore 100% of the Year Round zonal marginal km will be shared. (i.e. BSF=1.0); Year Round Shared marginal km = 1.0 * 100 = 100 km Year Round Not-Shared marginal km = (100 – 100)km = 0 km The shared zonal marginal km for each generation charging zone will be the sum of the relevant shared boundary marginal km as shown in the table below (assuming the node below D is the centre of the system i.e. zonal MWkm of 0). These not-shared zonal incremental km are then use to calculate wider £/kW generation tariffs. The not-shared zonal marginal km for each generation charging zone will be the sum of the relevant not-shared boundary marginal km as shown in the table below (assuming the node below D is the centre of the system i.e. zonal MWkm of 0). These not-shared zonal incremental km are then use to calculate wider £/kW generation tariffs.
| Boundary/Zone | A | B | C | D |
|---|---|---|---|---|
| A-B | 0 | |||
| B-C | 111 | 111 | ||
| C-D | 40.5 | 40.5 | 40.5 | |
| D-rest of system | 100 | 100 | 100 | 100 |
| Shared Zonal MWkm | 251.5 | 251.5 | 140.5 | 100 |
| Total Zonal MWkm | 450 | 350 | 150 | 100 |
| Boundary/Zone | A | B | C | D |
|---|---|---|---|---|
| A-B | 100 | |||
| B-C | 89 | 89 | ||
| C-D | 9.5 | 9.5 | 9.5 | |
| D-rest of system | 0 | 0 | 0 | 0 |
| Not-Shared Zonal MWkm | 198.5 | 98.5 | 9.5 | 0 |
| Total Zonal MWkm | 450 | 350 | 150 | 100 |
Example: Calculation of Zonal Generation Tariff Wider Let us consider all nodes in a generation zone in this example. The table below shows a sample output of the transport model comprising the node, the Peak Security wider nodal marginal km and Year Round wider nodal marginal km (observed on non- local assets) of an injection at the node with a consequent withdrawal across distributed reference node, the generation sited at the node, scaled to ensure total national generation equals total national demand, for both Peak Security and Year Round generation backgrounds.. In order to calculate the generation tariff we would carry out the following steps.
| Wider Nodal | Scaled | Wider Nodal | Scaled | ||
|---|---|---|---|---|---|
| Gen | |||||
| Node | Marginal km | Generation | Marginal km | Generation | |
| Zone | |||||
| (Peak Security) | (Peak Security) | (Year Round) | (Year Round) | ||
| 4 | ABNE10 | 5.73 | 0.00 | 459.90 | 0.00 |
| 4 | CLAY1S | 239.67 | 0.00 | 306.47 | 0.00 |
| 4 | CLUN1S | 46.41 | 22.90 | 502.16 | 18.76 |
| 4 | COUA10 | 45.39 | 0.00 | 423.30 | 0.00 |
| 4 | DYCE1Q | 162.70 | 0.00 | 357.81 | 0.00 |
| 4 | ERRO10 | 46.82 | 56.13 | 534.03 | 45.99 |
| 4 | FIDD1B | 91.88 | 0.00 | 220.59 | 0.00 |
| 4 | FINL1Q | 79.69 | 12.35 | 495.63 | 10.12 |
| 4 | GRIF1S | 33.31 | 0.00 | 521.16 | 71.40 |
| 4 | KIIN10 | 79.69 | 0.00 | 495.63 | 0.00 |
| 4 | LOCH10 | 79.69 | 35.18 | 495.63 | 28.82 |
| 4 | MILC10 | 117.69 | 0.00 | 328.86 | 0.00 |
| 4 | PERS20 | 266.00 | 0.00 | 384.05 | 0.00 |
| 4 | TUMB1Q | 46.82 | 0.00 | 536.27 | 0.00 |
| Totals | 126.56 | 175.09 |
calculate the generation weighted wider nodal shadow costs. For this example zone this would be as follows: i.e. 79.69 x 35.18 126.56
| Gen Zone | Gen | Wider Nodal Marginal km (Year Round) | Gen | ||||
|---|---|---|---|---|---|---|---|
| Wider Nodal | Scaled | Weighted | Scaled | Weighted | |||
| Marginal km | Generation | Wider Nodal | Generation | Wider Nodal | |||
| Node | |||||||
| (Peak | (Peak Security) | Marginal km | (Year Round) | Marginal km | |||
| Security) | (MW) | (Peak | (MW) | (Year Round) | |||
| Security) | |||||||
| 4 | CLUN1S | 46.41 | 22.90 | 8.39 | 502.16 | 18.76 | 53.80 |
| 4 | ERRO10 | 46.82 | 56.13 | 20.76 | 534.03 | 45.99 | 140.27 |
| 4 | FINL1Q | 79.69 | 12.35 | 7.77 | 495.63 | 10.12 | 28.65 |
| 4 | GRIF1S | N/A | N/A | N/A | 521.16 | 71.40 | 212.52 |
| 4 | LOCH10 | 79.69 | 35.18 | 22.15 | 495.63 | 28.82 | 81.58 |
| Totals | 126.56 | 175.09 |
sum the generation weighted wider nodal shadow costs to give Peak Security and Year Round zonal figures For this example zone this would be: .Peak Security: (8.39 + 20.76+7.77+22.15) km = 59.07km Year Round: (53.80 + 140.27 + 28.65 + 212.52 + 81.58) = 516.82 km
In this example we have assumed that accounting for sharing in the Year Round background gives: Year Round Shared marginal km = 344.56km Year Round Not-Shared marginal km = 172.26km
calculate the initial Peak Security wider transport tariff, Year Round Shared wider transport tariff and Year Round Not-Shared wider transport tariff by multiplying the figure in (iii) above by the expansion constant (& dividing by 1000 to put into units of £/kW). For zone 4 and assuming an expansion constant of £10.07/MWkm and a locational security factor of 1.8:
Initial Peak Security wider tariff – 59.07 km * £10.07/MWkm * 1.8 = £1.071/kW b) Initial Year Round Shared wider tariff - 344.56 km * £10.07/MWkm * 1.8 = £6.245/kW c) Initial Year Round Not-Shared wider tariff - 172.26 km * £10.07/MWkm * 1.8 = £1.309/kW Local
If we assume (for the sake of this example) that the generator connecting at CLUN1S is a thermal plant with a Peak Security flag of 1 and an Annual Load Factor (ALF) of 60%, which connects via 10km of 132kV 100MVA rated single circuit overhead line from the nearest MITS node, with no redundancy, the substation is rated at less than 1320MW, and there is no other generation or demand connecting to this circuit, then: a) The local substation tariff shall be as published in accordance with paragraph 14.15.122. For this example the local substation tariff will be £0.133/kW; and b) Running the transport model with a local circuit expansion factor of 10.0 applied to the 10km of overhead line connecting CLUN1S to the nearest MITS node and the wider circuit expansion factors applied to all other circuits, gives a local nodal maginal cost of 100MWkm. This is the additional MWkm costs associated with the node’s local assets. Applying the expansion constant of £10.07/MWkm and local security factor of 1.0 and dividing by 1000 gives a local circuit tariff of £1.007/kW. Adjustment Tariff
We now need to calculate the Adjustment Tariff. This is calculated by taking the Adjustment Revenue and dividing this by the Chargable Generation Capacity (as per to 14.14.5 (vii) (h)) create a £/kW figure Assuming annual average transmission charges paid by Generators is due to fall below €0, The Company will add Adjustment Revenue to ensure that compliance with the Limiting Regulation is maintained – in this example let us assume it is £260m and the GB-wide generation Chargable Capacity is 60GW (60,000,000kW). This would mean the non-locational Adjustment Tariff would be calculated as; 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡 𝑅𝑒𝑣𝑒𝑛𝑢𝑒 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡 𝑇𝑎𝑟𝑖𝑓𝑓 (𝐴𝑑𝑗𝑇𝑎𝑟𝑖𝑓𝑓) = 𝐶ℎ𝑎𝑟𝑔𝑎𝑏𝑙𝑒 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 £260𝑚 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡 𝑇𝑎𝑟𝑖𝑓𝑓 (𝐴𝑑𝑗𝑇𝑎𝑟𝑖𝑓𝑓) = 60,000,000𝑘𝑊 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡 𝑇𝑎𝑟𝑖𝑓𝑓 (𝐴𝑑𝑗𝑇𝑎𝑟𝑖𝑓𝑓) = £4.33/𝑘𝑊
Therefore the charges for thermal plant with a TEC of 100MW and an ALF of 60%, connecting at CLUN1S is: = Wider Peak Security Tariff * PS Flag * TEC = 1.071 * 1 * 100,000 = Wider Year Round Shared Tariff * ALF * TEC = 6.245 * 0.6 * 100,000 = Wider Year Round Not-Shared Tariff * TEC = 1.309 * 100, 000 = Local substation Tariff * TEC = 0.133 * 100,000 = Local circuit Tariff * TEC = 1.007 * 100,000 = Adjustment Tariff * TEC = 4.33 * 100,000 (effectively, £11597/kW * 100,000kW = £1,159,700)
Alternatively, if we assume that the generator connecting at CLUN1S is an intermittent wind generation plant (instead of a thermal plant) with a TEC of 100MW, PS Flag of 0 and an ALF of 30%, then the charges payable will be – = Wider Peak Security Tariff * PS Flag * TEC = 1.071 * 0 * 100,000 = Wider Year Round Shared Tariff * ALF * TEC = 6.245 * 0.3 * 100,000 = Wider Year Round Not-Shared Tariff * TEC = 1.309 * 100, 000 = Local substation Tariff * TEC = 0.133 * 100,000 = Local circuit Tariff * TEC = 1.007 * 100,000 = Adjustment Tariff * TEC = 4.33 * 100,000 (effectively, £8.653/kW * 100,000kW = £865,300)
Example: Calculation of Zonal Demand Locational Tariff Let us consider all nodes in the same demand zone in this example The table below shows an example output of the transport model comprising the node, the Peak Security and Year Round nodal marginal km of an injection at the node with a consequent withdrawal at the distributed reference node, the generation sited at the node, scaled to ensure total national generation = total national net demand and the net demand sited at the node. Where the Demand (MW) is negative this indicates that the Demand node is Exporting rather than importing. In order to calculate the gross demand tariff we would carry out the following steps:
| Demand Zone | Node | Peak Security Nodal Marginal km | Year Round Nodal Marginal km | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | A | 110 | 80 | 100 | |||||||
| 1 | B | 140 | 90 | 100 | |||||||
| 1 | C | 120 | 80 | 0 | |||||||
| 1 | D | 100 | 100 | -50 | |||||||
| 1 | E | 100 | 70 | 50 | |||||||
| Totals | 200 |
| Year |
|---|
| Round |
| Nodal |
| Marginal |
| km |
| Peak Security |
| Nodal |
| Marginal km |
| Demand |
| (MW) |
| Peak Security | Year Round | Net | ||
|---|---|---|---|---|
| Demand | ||||
| Node | Nodal Marginal | Nodal Marginal | Demand | |
| Zone | ||||
| km | km | (MW) | ||
| 14 | ABHA4A | -77.25 | -230.25 | 127 |
| 14 | ABHA4B | -77.27 | -230.12 | 127 |
| 14 | ALVE4A | -82.28 | -197.18 | 100 |
| 14 | ALVE4B | -82.28 | -197.15 | 100 |
| 14 | AXMI40_SWEB | -125.58 | -176.19 | 97 |
| 14 | BRWA2A | -46.55 | -182.68 | 96 |
| 14 | BRWA2B | -46.55 | -181.12 | 96 |
| 14 | EXET40 | -87.69 | -164.42 | 340 |
| 14 | HINP20 | -46.55 | -147.14 | 0 |
| 14 | HINP40 | -46.55 | -147.14 | 0 |
| 14 | INDQ40 | -102.02 | -262.50 | 444 |
| 14 | IROA20_SWEB | -109.05 | -141.92 | 462 |
| 14 | LAND40 | -62.54 | -246.16 | 262 |
| 14 | MELK40_SWEB | 18.67 | -140.75 | 83 |
| 14 | SEAB40 | 65.33 | -140.97 | 304 |
| 14 | TAUN4A | -66.65 | -149.11 | 55 |
| 14 | TAUN4B | -66.66 | -149.11 | 55 |
| Totals | 2748 |
Change Negative Demand values to 0 (zero) , which in this example is Node D
| Demand Zone | Node | Peak Security Nodal Marginal km | Year Round Nodal Marginal km | Demand (MW) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | A | 110 | 80 | 100 | ||||||||||
| 1 | B | 140 | 90 | 100 | ||||||||||
| 1 | C | 120 | 80 | 0 | ||||||||||
| 1 | D | 100 | 100 | 0 | ||||||||||
| 1 | E | 100 | 70 | 50 | ||||||||||
| Totals | 250 |
| Peak Security |
|---|
| Nodal Marginal |
| km |
| Year Round |
| Nodal Marginal |
| km |
calculate the demand weighted nodal shadow costs For this example zone this would be as follows:
| Demand Zone | Node | Peak Security Nodal Marginal km | Year Round Nodal Marginal km | Demand (MW) | Peak Security Demand Weighted Nodal Marginal km | Year Round Demand Weighted Nodal Marginal km | |||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | A | 110 | 80 | 100 | |||||||||||||||||
| 1 | B | 140 | 90 | 100 | |||||||||||||||||
| 1 | C | 120 | 80 | 0 | |||||||||||||||||
| 1 | D | 100 | 100 | 0 | |||||||||||||||||
| 1 | E | 100 | 70 | 50 | |||||||||||||||||
| Totals | 250 | 120 | 82 |
| Year |
|---|
| Round |
| Demand |
| Weighted |
| Nodal |
| Marginal |
| km |
| Peak |
| Security |
| Demand |
| Weighted |
| Nodal |
| Marginal km |
| Peak |
| Security |
| Nodal |
| Marginal |
| km |
| Round |
| Nodal |
| Marginal |
| km |
| Demand |
| Zone |
| Demand |
| (MW) |
sum the Peak Security and Year Round demand weighted nodal shadow costs to give zonal figures. For this example zone this is shown in the above table and is 120km for Peak Security background and 82km for Year Round background.
i.) calculate the transport (locational) tariffs by multiplying the figures in (ii) above by -
This changes the original Nodal Marginal Km for injecting (Generation) into Nodal Marginal Km for withdrawing (Demand). Then multiply by the expansion constant, the locational security factor and then divide by 1000 to put into units of £/kW: For this example zone, assuming an expansion constant of £10.07/MWkm and a locational security factor of 1.80: a) Peak Security tariff – - (120km * £10.07/MWkm * 1.8) = -£2.47/kW b) Year Round tariff - - (82* £10.07/MWkm * 1.8) = -£1.49/kW The Locational signal for Demand within this zone is negative for both Peak and Year Round, which indicates withdrawing at this part of the network, reduces total system flows. ii.) A NHH locational demand element is calculated in accordance with the methodology given in 14.16.2.
i.) We now need to calculate the Transmission Demand Residual Tariffs. This is calculated by first taking the total revenue to be recovered from demand less the revenue which would be recovered through the demand locational and energy tariffs and revenue recovery through embedded export tariffs. Assuming the total revenue to be recovered from gross GSP group demand= £779m. Assuming the total recovery from GSP group demand locational and energy tariffs is £140m, total recovery from embedded export tariffs is -£10m the total revenue to be recovered through the Transmission Demand Residual Tariffs will be as follows: £779𝑚−£140𝑚− −£10𝑚 =£649𝑚 ii.) The total revenue to be recovered from the Transmission Demand Residual Tariffs as calculated in (i) above is then apportioned between the Charging Bands as set in 14.15.138 by the sum of the annual energy consumption of the Final Demand Sites or Unmetered Supplies as appropriate allocated to a Charging Band as divided by the total annual energy consumption from all GB Final Demand Sites and Unmetered Supplies. iii.) An example is as follows: The total annual consumption of all GB Final Demand Sites and Unmetered Supplies is 100TWh. The sum of the annual energy consumption of all Final Demand Sites in HV Charging Band 1 is 1TWh Using the example of total revenue to be recovered through the Transmission Demand Residual Tariffs above of £649m, HV Charging Band 1 Final Demand Sites will be liable for 1% of this cost. £6,490,000 The annual cost per site will be where N is the total number of sites in HV Charging 𝑁 Band 1. If, in this example, N = 12,000 the annual charge per Final Demand Site in HV Charging Band 1 will be £540.83. The Transmission Demand Residual Tariff per Final Demand Site in HV Charging Band 1 will be set as a daily charge. The annual charge, in this example £540.83, will be divided by the number of days in the charging year to deliver a Transmission Demand Residual Tariff (£/site/day). £540.83 In this example; or £1.48/site/day. 365 days
The Transmission Demand Residual tariff is subject to further adjustment to allow for the minimum £0/kW gross demand charge.
Reconciliation of Demand Related Transmission Network Use of System Charges This appendix illustrates the methodology used by The Company in the reconciliation of Transmission Network Use of System charges for demand. The example highlights the different stages of the calculations from the monthly invoiced amounts, right through to Final Reconciliation. Monthly Charges - HH and NHH Suppliers provide half-hourly (HH) gross demand and embedded export forecasts and non- half-hourly (NHH) demand forecasts by BM Unit every quarter; The Company provides FDSC Forecasts and Unmetered Supply Volume Forecasts on behalf of Suppliers. An example of such forecasts and the corresponding monthly invoiced amounts, based on tariffs of £10.00/kW for gross demand, £5.00/kW for embedded export and 1.20p/kWh for energy consumption, is as follows: HH and NHH Forecasts As shown, for the first nine months the Supplier provided a 12,000kW HH triad gross demand forecast, and hence paid HH gross demand monthly charges of £10,000 ((12,000kW x £10.00/kW)/12) for that BM Unit. In January the Supplier provided a revised forecast of 7,200kW, implying a forecast annual charge reduced to £72,000 (7,200kW x £10.00/kW). The Supplier had already paid £90,000, so the excess of £18,000 was credited back to the supplier in three £6,000 instalments over the last three months of the year. The Supplier provided an embedded export triad forecast of -600kW and hence was paid an embedded export credit of £250 ((600kW x £5.00/kW)/12) for that BM Unit (For the avoidance of doubt, if the embedded export tariff is negative this will result in a debit). The Supplier also initially provided a 15,000,000kWh NHH energy consumption forecast, and hence paid NHH monthly charges of £15,000 ((15,000,000kWh x 1.2p/kWh)/12) for that BM Unit. In July the Supplier provided a revised forecast of 18,000,000kWh, implying a forecast annual charge increased to £216,000 (18,000,000kWh x 1.2p/kWh). The Supplier had already paid £45,000, so the remaining £171,000 was split into payments of £19,000 for the last nine months of the year. The right hand column shows the net monthly HH and NHH charges for the BM Unit. Monthly Charge – TDR The User shall not be required to submit forecasts of FDSC or Unmetered Supply Volume. The Company shall use the latest daily actual FDSC and Unmetered Supply Volume prior to the forecast as the basis of the forecast. As an example, at the start of the year the supplier has sites in just three of the charging bands, as shown below. The April invoice is calculated as the annual liability divided by 12. Each month The Company recalculates the forecast liability for the full year, based on any revision to the FDSC and Unmetered Supply Volume for the previous months, and the latest forecast for the remainder of the year. The amount the supplier has already paid is deducted from this annual liability, and the balance is divided by the number of months left to bill. Initial Reconciliation (Part 1a – HH Demand) The Supplier’s outturn HH triad gross demand, based on latest settlement data (and therefore subject to change in subsequent settlement runs), was 9,000kW. The HH triad gross demand reconciliation charge is therefore calculated as follows: HHD Reconciliation Charge = (HHD - HHD ) x £/kW Tariff A F = (9,000kW - 7,200kW) x £10.00/kW = 1,800kW x £10.00/kW = £18,000 To calculate monthly interest charges, the outturn HHD charge is split equally over the 12- month period. The monthly reconciliation amount is the monthly outturn HHD charge less the HH gross demand monthly invoiced amount. Interest payments are calculated based on these monthly reconciliation amounts using Barclays Base Rate. Initial Reconciliation (Part 1b – Embedded Export) The Supplier’s outturn HH triad embedded export, based on latest settlement data (and therefore subject to change in subsequent settlement runs), was 500kW. The HH triad embedded export reconciliation charge is therefore calculated as follows: HHEE Reconciliation Charge = (HHEE – HHEE ) x £/kW Tariff A F = (-500kW - -600kW) x £5.00/kW = 100kW x £5.00/kW = £500 To calculate monthly interest charges, the outturn HHEE charge is split equally over the 12- month period. The monthly reconciliation amount is the monthly outturn HHEE charge less the HH embedded generation monthly invoiced amount. Interest payments are calculated based on these monthly reconciliation amounts using Barclays Base Rate. Initial Reconciliation (Part 2 – NHH Demand) The Supplier's outturn NHH energy consumption, based on latest settlement data, was 17,000,000kWh. The NHH energy consumption reconciliation charge is therefore calculated as follows: NHHC Reconciliation Charge = (NHHC - NHHC ) x p/kWh Tariff A F = (17,000,000kWh - 18,000,000kWh) x 1.20p/kWh = -1,000,000kWh x 1.20p/kWh = -£12,000 The monthly reconciliation amount is equal to the outturn energy consumption charge for that month less the NHH monthly invoiced amount. Interest payments are calculated based on these monthly reconciliation amounts using Barclays Base Rate. Initial Reconciliation (Part 3 - TDR) The Supplier’s outturn Transmission Demand Residual charge is calculated for each month using FDSC and Unmetered Supply Volume based on latest settlement data as follows, If the Supplier’s TDR quantity was the same for every month of the year, the total TDR reconciliation charge would be: TDR Reconciliation Charge = [ (230-240) * 1 + (200-180) * 2 + (5000-4800) * 0.012 ] *365 = £11,826 The monthly reconciliation amount is the monthly outturn Transmission Demand Residual Charge less the monthly invoiced amount. Interest payments are calculated based on these monthly reconciliation amounts using Barclays Base Rate. On the above examples, the net initial TNUoS demand reconciliation charge (across HH, EE, NHH and TDR, but excluding interest) is therefore £18,000 + £500 - £12,000 + £11,826 = £18,326. Final Reconciliation Finally, let us now suppose that after all final Settlement data has been received (up to 14 months after the relevant dates) as shown in the below table; This would mean the Final Reconciliation calculations would be. Final HH Gross Demand = (9,500kW - 9,000kW) x £10.00/kW Reconciliation Charge = £5,000 Final HH Embedded Export = (-550kW - -500kW) x £5.00/kW Reconciliation Charge = -£250 Final NHH Reconciliation Charge = (16,700,000kWh – 17,000,000kWh) x 1.20p/kWh = -£3,600 FDSC Charging Band 1 = (235 Sites – 230 Sites) x £1/Site/Day x 365 days = £150 FDSC Charging Band 2 = (195 Sites – 200 Sites) x £2/Site/Day x 365 Days = -£300 UMS Charging Band= (5,100kWh/day – 5,000kWh/day) x 0.012/kWh x 365 Days = -£36 Consequently, the net final TNUoS demand reconciliation charge will be £5,000 -£250 -£3,600 + £150 - £300 +- £36 = £1,036 Monthly reconciliation amounts are calculated in a similar way as for the Initial Reconciliation, being (i) for HH Demand and Embedded Export, the outturn annual charge divided by 12, and for NHH Demand and TDR it is the outturn charge for the month; less (ii) the amount already invoiced for that month (including through the Initial Reconciliation). Interest payments are calculated based on these monthly reconciliation amounts using Barclays Base Rate. Terminology: HHD = The Supplier's outturn half-hourly metered Triad Gross Demand (kW) for the A demand zone concerned. HHD = The Supplier's forecast half-hourly metered Triad Gross Demand (kW) for the F demand zone concerned. HHEE = The Supplier's outturn half-hourly metered Triad Embedded Export (kW) for the A demand zone concerned. HHEE = The Supplier's forecast half-hourly metered Triad Embedded Export (kW) for F the demand zone concerned. NHHC = The Supplier's outturn non-half-hourly metered daily Energy Consumption A (kWh) for the period 16:00 hrs to 19:00 hrs inclusive (i.e. Settlement Periods 33 to 38) from April 1st to March 31st, for the demand zone concerned. NHHC = The Supplier's forecast non-half-hourly metered daily Energy Consumption F (kWh) for the period 16:00 hrs to 19:00 hrs inclusive (i.e. Settlement Periods 33 to 38) from April 1st to March 31st, for the demand zone concerned. £/kW Tariff = The £/kW Gross Demand or Embedded Export Tariff as shown in Schedule 1 of The Statement of Use of System Charges for the demand zone concerned. p/kWh Tariff = The Energy Consumption Tariff shown in Schedule 1 of The Statement of Use of System Charges for the demand zone concerned.
| Forecast HH Triad Gross Demand HHD (kW) F | HH Gross Demand Monthly Invoiced Amount (£) | Forecast HH Triad Embedded Export HHEE (kW) F | HH Embedded Generation Monthly Invoiced Amount (£) | Forecast NHH Energy Consumptio n NHHC (kWh F ) | NHH Monthly Invoiced Amount (£) | Net Monthly Invoiced Amount (£) | |
|---|---|---|---|---|---|---|---|
| Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar | 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 7,200 7,200 7,200 | 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 (6,000) (6,000) (6,000) | -600 -600 -600 -600 -600 -600 -600 -600 -600 -600 -600 -600 | (250) (250) (250) (250) (250) (250) (250) (250) (250) (250) (250) (250) | 15,000,000 15,000,000 15,000,000 18,000,000 18,000,000 18,000,000 18,000,000 18,000,000 18,000,000 18,000,000 18,000,000 18,000,000 | 15,000 15,000 15,000 19,000 19,000 19,000 19,000 19,000 19,000 19,000 19,000 19,000 | 24,750 24,750 24,750 28,750 28,750 28,750 28,750 28,750 28,750 12,750 12,750 12,750 |
| Total | 72,000 | (3,000) | 216,000 | 285,000 |
| Charging Band | TDR Quantity | Tariff | April Invoice |
|---|---|---|---|
| Band 1 | 240 Sites | £1/Site/Day | = 240 x 1 x 365 / 12 = £7,300 |
| Band 2 | 180 Sites | £2/Site/Day | = 180 x 2 x 365 / 12 = £10,950 |
| UMS | 4800kWh/day | £0.012/kWh | = 4800 x 0.012 x 365 / 12 = £1,752 |
| Total | £20,002 |
| Charging Band | Latest TDR Quantity | Tariff | April Charge | Original April Invoice | Initial Demand Reconciliation for April |
|---|---|---|---|---|---|
| Band 1 | 230 Sites | £1/Site/Day | = 230 x 1 x 30 days = £6,900 | £7,300 | -£400 |
| Band 2 | 200 Sites | £2/Site/Day | = 200 x 2 x 30 = £12,000 | £10,950 | £1,050 |
| UMS | 5000kWh/day | £0.012/kWh | = 5000 x 0.012 x 30 = £1,800 | £1,752 | £48 |
| Total | £20,700 | £20,002 | £698 |
| Settlement Data item | Initial Value | Final Value |
|---|---|---|
| HH triad gross demand | 9,000kW | 9,500kW |
| HH triad embedded export | -500kW | -550kW |
| NHH energy consumption | 17,000,000kWh | 16,700,000kWh |
| Band 1 | 230 Sites | 235 Sites |
| Band 2 | 200 Sites | 195 Sites |
| UMS | 5,000kWh/day | 5,100kWh/day |
Classification of parties for charging purposes In the event of any conflict between this Appendix and the main text within this Statement, the main text within the Statement shall take precendence. In the following diagrams, the parties liable for Transmission Network Use of System charges are outlined in red.
| SUPPLIER | |
|---|---|
| Supplier Use of System Agreement Supplier Supplier BMU1 BMUn | |
| Demand Charges See 14.17.13 and 14.17.18. | Generation Charges None. |
| Supplier Use of System Agreement |
|---|
| POWER STATION WITH A BILATERAL CONNECTION AGREEMENT | |
|---|---|
| Bilateral Connection Agreement Appendix C Gen Unit Gen Unit Station Additional BMU1 BMUn Load BMU Load BMU | |
| Demand Charges See 14.17.18. | Generation Charges See 14.18.1 i) and 14.18.3 to 14.18.9 and 14.18.18. For generators in positive zones, see 14.18.10 to 14.18.12. For generators in negative zones, see 14.18.13 to 14.18.17. |
| Bilateral Connection Agreement Appendix C |
|---|
| PARTY WITH A BILATERAL EMBEDDED GENERATION AGREEMENT | |
|---|---|
| Bilateral Embedded Generation Agreement Appendix C Gen Unit Gen Unit Station Additional BMU1 BMUn Load BMU Load BMU | |
| Demand Charges See 14.17.14, 14.17.15 and 14.17.18. | Generation Charges See 14.18.1 ii). For generators in positive zones, see 14.18.3 to 14.18.12 and 14.18.18. For generators in negative zones, see 14.18.3 to 14.18.9 and 14.18.13 to 14.18.18. |
| Bilateral Embedded Generation Agreement Appendix C |
|---|
Transmission Network Use of System Charging Flowcharts The following flowcharts illustrate the parties liable for Demand and Generation TNUoS charges and the calculation of those charges. In the event of any conflict between this Appendix and the main text within this Statement, the main text within the Statement shall take precedence. Demand Charges Demand Charging Start Select appropriate party Power Stations with a Bilateral Connection Exemptable Generation Lead Party of Agreement or Licensable and DDI with a Bilateral Supplier BMU Generation with a Bilateral Embedded Generation Embedded Generation Agreement Agreement Average of each Average metered BMU's HH metered volume of Exempt Average net metered volume during the Export BMU during the import of Power Station Triad (x £/kW tariff) Triad (x £/kW tariff) (including metered additional load) during the Triad (x £/kW tariff) AND NB. If the average HH metered volume of Each BMU's NHH metered the Exempt Export BMU over the Triad energy consumption during results in an import, the BMU will pay the 16.00-19.00 inclusive every amount of the average import x relevant day over the Financial Year £/kW tariff (x p/kWh tariff) If the average HH metered volume of the Exempt Export BMU over the Triad results in an export, the BMU will be paid the amount of the average export x relevant £/kW tariff BMU = BM Unit DDI = Derogated Distribution Interconnector HH = half hourly NHH = Non-half hourly Generation Charges
Example: Determination of The Company’s Forecast for Demand Charge Purposes The Company will use the latest available settlement data for calculation of HH demand and NHH energy consumption forecasts for the Financial Year. The Financial Year runs from 1st April to 31st March inclusive and for the purpose of these examples the year April 2005 to March 2006 is used. Where the preceding year’s settlement data is not available at the time that The Company needs to calculate its forecast, The Company will use settlement data from the corresponding period in Financial Year minus two unless indicated otherwise. All values used with the examples are purely for illustrative purposes only. i) Half-Hourly (HH) Metered Demand Forecast – Existing User At the time of calculation of a HH demand forecast before the relevant Financial Year (approximately 10th March), The Company will be aware at a system level which dates will be used for the determination of Triad. However, The Company may not have settlement data at a User level if the Triad dates were to span a period that includes the latter half of February. When undertaking forecasting before the relevant Financial Year, The Company will use the User’s Triad demand for the previous year for its forecast providing it holds User settlement data for this period, thus: F = T where: F = Forecast of User’s HH demand at Triad for the Financial Year T = User’s HH gross demand and embedded export at Triad in Financial Year minus one Where The Company determines its forecast within a Financial Year: F = T * D/P where: F = Forecast of User’s HH demand at Triad for the Financial Year T = User’s HH gross demand and embedded export at Triad in the preceding Financial Year D = User’s average half hourly metered gross demand and embedded export in Settlement Period 35 in the Financial Year to date P = User’s average half hourly metered gross demand and embedded export in Settlement Period 35 for the period corresponding to D in the preceding Financial Year Where The Company determines its forecast before the relevant Financial Year and User settlement data for the Triad period is not available, The Company shall apply the formula immediately above (within year forecast) but substitute the following definitions for the values T, D, and P: T = User’s HH gross demand and embedded export at Triad in the Financial Year minus two D = User’s average half hourly metered gross demand and embedded export in Settlement Period 35 in the Financial Year minus one, to date P = User’s average half hourly metered gross demand and embedded export in Settlement Period 35 for the period corresponding to D in the Financial Year minus two Example (where User settlement data is not yet available for the Triad period): The Company calculates a HH demand forecast on the above methodology at 10th March 2005 for the period 1st April 2005 to 31st March 2006. Gross demand: F = 10,000 * 13,200 / 12,000 F = 11,000 kW where: T = 10,000 kW (period November 2003 to February 2004) D = 13,200 kW (period 1st April 2004 to 15th February 2005#) P = 12,000 kW (period 1st April 2003 to 15th February 2004) # Latest date for which settlement data is available. Embedded export: F = -280 * -300 / -350 F = -240 kW where: T = -280 kW (period November 2003 to February 2004) D = -300 kW (period 1st April 2004 to 15th February 2005#) P = -350 kW (period 1st April 2003 to 15th February 2004) # Latest date for which settlement data is available. ii) Non Half-Hourly (NHH) Metered Energy Consumption Forecast – Existing User F = E * D/P where: F = Forecast of User’s NHH metered energy consumption for the Financial Year E = User’s summed NHH energy consumption over the hours 16:00 to 19:00 for each day in the preceding Financial Year D = User’s summed NHH energy consumption for the hours 16:00 to 19:00 for each day for the Financial Year to date P = User’s summed NHH energy consumption for the hours 16:00 to 19:00 for each day for the period corresponding to D in the preceding Financial Year Example: The Company calculates a NHH energy consumption forecast on the above methodology at 10th June 2005 for the period 1st April 2005 to 31st March 2006. F = 50,000,000 * 4,400,000 / 4,000,000 F = 55,000,000 kWh where: E = 50,000,000 kWh (period 1st April 2004 to 31st March 2005) D = 4,400,000 kWh (period 1st April 2005 to 15th May 2005#) P = 4,000,000 kWh (period 1st April 2004 to 15th May 2004) # Latest date for which settlement data is available Where forecasting before the relevant Financial Year concerned, The Company would in the above example use values for E and P from Financial Year 2003/04 and D from Financial Year 2004/05. iii) Half-Hourly (HH) Metered Demand Forecast – New User F = M * T/W where: F = Forecast of User’s HH metered gross demand and embedded export at Triad for the Financial Year M = User’s HH average weekday period 35 demand for the last complete month for which settlement data is available T = Total system HH gross demand and embedded export at Triad in the preceding Financial Year W = Total system HH average weekday Settlement Period 35 metered demand for the corresponding period to M for the preceding year Example: The Company calculates a HH demand forecast on the above methodology at 10th September 2005 for a new User registered from 10th June 2005 for the period 10th June 2004 to 31st March 2006. Gross demand: F = 1,000 * 17,000,000 / 18,888,888 F = 900 kW where: M = 1,000 kW (period 1st July 2005 to 31st July 2005) T = 17,000,000 kW (period November 2004 to February 2005) W = 18,888,888 kW (period 1st July 2004 to 31st July 2004) Embedded export: F = -150 * -7,200,000 /- 6,000,000 F = -180 kW where: M = -150 kW (period 1st July 2005 to 31st July 2005) T = -7,200,000 kW (period November 2004 to February 2005) W = -6,000,000 kW (period 1st July 2004 to 31st July 2004) iv) Non Half Hourly (NHH) Metered Energy Consumption Forecast – New User F = J + (M * R/W) where: F = Forecast of User’s NHH metered energy consumption for the Financial Year J = Residual part month summed NHH metered energy consumption for the hours 16:00 to 19:00 for each day where new User registration takes place other than on the first of a month M = User’s summed NHH metered energy consumption for the hours 16:00 to 19:00 for each day for the last complete month for which settlement data is available R = Total system summed NHH metered energy consumption for the hours 16:00 to 19:00 for each day for the period from the start of that defined under M but for the preceding year and until the end of that preceding Financial Year W = Total system summed NHH metered energy consumption for the hours 16:00 to 19:00 for each day for the period identified in M but for the preceding Financial Year Example: The Company calculates a NHH energy consumption forecast on the above methodology at 10th September 2005 for a new User registered from 10th June 2005 for the period 10th June 2005 to 31st March 2006. F = 500 + (1,000 * 20,000,000,000 / 2,000,000,000) F = 10,500 kWh where: J = 500 kWh (period 10th June 2005 to 30th June 2005) M = 1,000 kWh (period 1st July 2005 to 31st July 2005) R = 20,000,000,000 kWh (period 1st July 2004 to 31st March 2005) W = 2,000,000,000 kWh (period 1st July 2004 to 31st July 2004)
Stability & Predictability of TNUoS tariffs Stability of tariffs The Transmission Network Use of System Charging Methodology has a number of elements to enhance the stability of the tariffs, which is an important aspect of facilitating competition in the generation and supply of electricity. This appendix seeks to highlight those elements. Each node of the transmission network is assigned to a zone, these zones are themselves fixed. The result of this is to dampen fluctuations that would otherwise be observed at a given node caused by changes in generation, demand, and network parameters. The criteria used to establish generation zones are part of the methodology and are described in Paragraph 14.15.42. In addition to fixing zones, other key parameters within the methodology are also fixed for the duration of the price control period or annual changes restricted in some way. Specifically: • the expansion constant, which reflects the annuitised value of capital investment required to transport 1MW over 1km by a 400kV over-head line, changes annually according to TOPI. The other elements used to derive the expansion constant are only reviewed at the beginning of a price control period to ensure that it remains cost- reflective. This review will consider those components outlined in Paragraph 14.15.59 to Paragraph 14.15.69. • the expansion factors, which are set on the same basis of the expansion constant and used to reflect the relative investment costs in each TO region of circuits at different transmission voltages and types, are fixed for the duration price control. These factors are reviewed at the beginning of a price control period and will take account of the same factors considered in the review of the expansion constant. • the locational security factor, which reflects the transmission security provided under the NETS Security and Quality of Supply Standard, is fixed for the duration of the price control period and reviewed at the beginning of a price control period. • the Transmission Demand Residual Charging Bands which are used in setting Transmission Demand Residual Tariffs are fixed for the duration of the Onshore Transmission Owner price control period and reviewed at the beginning of a price control period. Predictability of tariffs The Company revises TNUoS tariffs each year to ensure that these remain cost-reflective and take into account changes to allowable income under the price control and TOPI. There are a number of provisions within the ESO Licence and the CUSC designed to promote the predictability of annually varying charges. Specifically, The Company is required to give the Authority 150 days notice of its intention to change use of system charges together with a reasonable assessment of the proposals on those charges; and to give Users 2 months written notice of any revised charges. The Company typically provides an additional months notice of revised charges through the publication of “indicative” tariffs. Shorter notice periods are permitted by the framework but only following consent from the Authority. These features require formal proposals to change the Transmission Use of System Charging Methodology to be initiated in October to provide sufficient time for a formal consultation and the Authority’s veto period before charges are indicated to Users. More fundamentally, The Company also provides Users with the tool used by The Company to calculate tariffs. This allows Users to make their own predictions on how future changes in the generation and supply sectors will influence tariffs. Along with the price control information, the data from the Electricity Ten Year Statement (ETYS), and Users own prediction of market activity, Users are able to make a reasonable estimate of future tariffs and perform sensitivity analysis. To supplement this, The Company also prepares an annual information paper that provides an indication of the future path of the locational element of tariffs over the next five years.1 This analysis is based on data included within the Electricity Ten Year Statement (ETYS). This report typically includes: • an explanation of the events that have caused tariffs to change; • sensitivity analysis to indicate how generation and demand tariffs would change as a result of changes in generation and demand at certain points on the network that are not included within the SYS; • an assessment of the compliance with the zoning criteria throughout the five year period to indicate how generation zones might need to change in the future, with a view to minimising such changes and giving as much notice of the need, or potential need, to change generation zones; and • a complete dataset for the DCLF Transport Model developed for each future year, to allow Users to undertake their own sensitivity analysis for specific scenarios that they may wish to model. The first year of tariffs forecasted in the annual information paper are updated twice throughout the proceeding Financial Year as the various Transport and Tariff model inputs are received or amended. These updates are in addition to the Authority 150 days notice and publication of “indicative” tariffs. The parameters used in the calculation of generation cap (in paragraph 14.15.5) will be published along with the forecast and confirmed values in the Tariff Information Paper which is produced in compliance with Condition 5 (of the NGC’s proposed GB electricity transmission use of system charging methodology - the Authority’s decisions document March 2005 80/5). In addition, The Company will, when revising generation charging zones prior to a new price control period, undertake a zoning consultation that uses data from the latest information paper. The purpose of this consultation will be to ensure tariff zones are robust to contracted changes in generation and supply, which could be expected to reduce the need for re-zoning exercises within a price control period. The calculation, as undertaken by The Company, of the Charges for Physical Assets required for Connection when setting TNUoS Charges for a Charging Year. To aid in the transparency and understanding of the setting of TNUoS Tariffs, at the same time as The Company publishes the draft and final TNUoS Charges for a Charging Year, The Company shall publish the details and components applied in the above calculation, the figures attributed to these and the output of the calculations as provided for in the proforma calculation schedule attached at Schedule 1 to this CUSC Section 14. The output shall be published in the form as set out in Schedule 1 to this CUSC Section 14. Guidance on the Calculation of the Charges for Physical Assets required for Connection when setting TNUoS Charges for a Charging Year.
http://www.nationalgrid.com/uk/Electricity/Charges/gbchargingapprovalconditions/5/ To aid in the transparency and understanding of the setting of TNUoS Tariffs in each Charging Year, and in any event no later than the date The Company publishes the draft TNUoS Charges for the following Charging Year, The Company shall publish guidance on how it will undertake the calculation to set TNUoS tariffs in compliance with the Limiting Regulation for that following Charging Year and when assessing compliance following the conclusion of that Charging Year. Section 2 – The Statement of the Balancing Services Use of System Charging Methodology
The ESO Licence allows The Company to derive revenue through the Balancing Services Use of System (BSUoS) Charges. This statement explains the methodology used in order to calculate the BSUoS Charges.
The Company keeps the electricity system in balance (energy balancing) and maintains the quality and security of supply (system balancing). Users pay for the cost of these through BSUoS Charges.
All Users excluding those Users with valid Declarations, Interconnectors and Virtual Lead Parties are liable for Balancing Services Use of System Charges based on their Final Demand in each Settlement Day.
BSUoS Charges are calculated on a fixed price basis as described in Section 14.31.
BSUoS Charges comprise the following costs:
The Total Costs of the Balancing Mechanism
Total Balancing Services Contract costs
Internal Expenditure (as defined in the ESO Licence)
RAV Returns (as defined in the ESO Licence)
Costs associated with contracting for and developing Balancing Services
Adjustments
Costs invoiced to The Company associated with Manifest Errors and Special Provisions.
All costs under Relevant Contracts awarded through the Onshore Tender Process.
Calculation of the Daily Balancing Services Use of System Charges Calculation of the Daily Balancing Services Use of System Charges
BSUoS Charges are calculated and levied for each Settlement Day based on the Fixed BSUoS Price.
The Fixed BSUoS Price will be the same for all Settlement Days within the same Fixed Price Period, unless a revised Fixed BSUoS Price comes into effect as outlined in Paragraph 14.31.15.
The Fixed BSUoS Price is calculated using forecast average Total BSUoS Costs. Calculation of forecast Total BSUoS Costs
The forecast average Total BSUoS Costs for a Fixed Price Period t (fBSUoSTOTt) are calculated using the following formula: 𝑓𝐵𝑆𝑈𝑜𝑆𝑇𝑂𝑇 = 𝑓𝐵𝑆𝑈𝑜𝑆𝐸𝑋𝑇 + 𝑓𝐵𝑆𝑈𝑜𝑆𝐼𝑁𝑇 + 𝑘𝑏 𝑡 𝑡 𝑡 𝑡 Where: fBSUoSTOT = forecast average Total BSUoS Costs associated with BSUoS t for the Fixed Price Period t fBSUoSEXT = forecast External BSUoS Costs. The terms which make up t External BSUoS Costs are set out as term EXT in part E of condition F1 of t the ESO Licence fBSUoSINT = forecast Internal BSUoS Costs. The terms which make up t Internal BSUoS Costs are set out as term INT in Part D t of condition F1 of the ESO Licence. kb = the amount included in the Fixed BSUoS Price for Fixed Price Period t t, to account for any over or under recovery from previous Fixed Price Periods. For the first Fixed Price Period (t=0) this amount is zero.
The amount included to account for over or under recovery, described in Paragraph 14.31.4, is calculated by subtracting the forecast revenue collected via the Fixed BSUoS Price allocated to Total BSUoS Costs in Fixed Price Periods prior to Fixed Price Period t, from the latest forecast of Total BSUoS Costs, as calculated by applying the latest values to the formula in Paragraph 14.31.4, for those same Fixed Price Periods prior to Fixed Price Period t. This is inclusive of any revenue collected from Final Reconciliation (RF) BSUoS Charges, pursuant to Paragraph 14.32.4.
The process described in Paragraph 14.31.5 does not apply to Final Reconciliation (RF) BSUoS Charges for Settlement Days which occur before the start of the first Fixed Price Period, on 1st April 2023. Calculating the Fixed BSUoS Price
The Fixed BSUoS Price for each Fixed Price Period t is calculated by the following formula: 𝑓𝐵𝑆𝑈𝑜𝑆𝑇𝑂𝑇 𝑡 𝐹𝑖𝑥𝑒𝑑𝐵𝑆𝑈𝑜𝑆𝑃 = 𝑡 𝑓𝑇𝑄𝑀 +𝑓𝑆𝐺𝑄𝑀 𝑡 𝑡 Where: FixedBSUoSP = the Fixed BSUoS Price for the Fixed Price Period t t fBSUoSTOT = forecast average Total BSUoS Costs for the Fixed Price t Period t fTQM = forecast of the total Transmission Connected Site BM Unit Metered t Volume during the Fixed Price Period t fSGQM = forecast of the total Gross Demand BM Unit Volume during the t Fixed Price Period t Notice of Fixed BSUoS Price
Users are given a notice period of at least three months of the Fixed BSUoS Price, for the next Fixed Price Period. Calculation of BSUoS Charges for BM Units
The Total BSUoS Charges for an individual BM Unit are calculated for each Settlement Day, denoted by d, based on the BM Unit’s metered volumes for each Settlement Period, denoted by j, and based on the Fixed BSUoS Price.
Supplier BM Units and Exempt Export BM Units, prefixed by i, have their Total BSUoS Charges calculated by the following formula: 𝐵𝑆𝑈𝑜𝑆𝑇𝑂𝑇 = 𝐹𝑖𝑥𝑒𝑑𝐵𝑆𝑈𝑜𝑆𝑃 𝑥∑ 𝑆𝐺𝑄𝑀 𝑖𝑑 𝑑 𝑖𝑗 𝑗∈𝑑 Where: BSUoSTOT = the Total BSUoS Charges for a Supplier or Exempt Export id BM Unit i, on Settlement Day d FixedBSUoSP = the Fixed BSUoS Price on Settlement Day d. d SGQM = the Gross Demand Supplier or Exempt Export BM Unit Volume ij for a Supplier or Exempt Export BM Unit i for Settlement Period j
All Transmission Connected BM Units, prefixed by m, have their Total BSUoS Charges calculated by the following formula: 𝐵𝑆𝑈𝑜𝑆𝑇𝑂𝑇 = 𝐹𝑖𝑥𝑒𝑑𝐵𝑆𝑈𝑜𝑆𝑃 𝑥∑ 𝑇𝑄𝑀 𝑚𝑑 𝑑 𝑚𝑗 𝑗∈𝑑 Where: BSUoSTOTmd = the Total BSUoS Charges for a Transmission Connected BM Unit m on Settlement Day d FixedBSUoSPd = the Fixed BSUoS Price on Settlement Day d. TQMmj = the total Transmission Connected Site BM Unit Metered Volume for a Transmission Connected BM Unit m for Settlement Period j Calculation of BSUoS Charges for a BSUoS liable customer
The BSUoS Charges for a BSUoS liable customer c on a Settlement Day d will be calculated by the following formula: 𝐵𝑆𝑈𝑜𝑆𝑇𝑂𝑇 = ∑ (𝐵𝑆𝑈𝑜𝑆𝑇𝑂𝑇 +𝐵𝑆𝑈𝑜𝑆𝑇𝑂𝑇 ) 𝑐𝑑 𝑖𝑑 𝑚𝑑 𝑖,𝑚∈𝑐 Where: BSUoSTOT = the Total BSUoS Charges for a BSUoS liable customer c on cd Settlement Day d BSUoSTOT = the Total BSUoS Charges for a Supplier or Exempt Export id BM Unit i on Settlement Day d BSUoSTOT = the Total BSUoS Charges for a Transmission Connected md BM Unit m on Settlement Day d Definition of the BSUoS charging base
BSUoS liability is based on a User’s Final Demand. Interconnector BM Units
BM Unit and Trading Units associated with Interconnectors, including those associated with the Interconnector Error Administrator, are not liable for BSUoS Charges. BM Units, including Secondary BM Units, which are associated with Virtual Lead Parties are not liable for BSUoS Charges. Issuing a revised Fixed BSUoS Price
If before or during a Fixed Price Period, The Company forecasts that it will neither recover sufficient funds through BSUoS Charges nor will it hold sufficient funds in the Industry BSUoS Fund and the BSUoS Working Capital Facility to meet balancing costs during that Fixed Price Period, The Company has the right to set a revised Fixed BSUoS Price for the entirety of or remainder of that Fixed Price Period.
In the case that The Company needs to issue a revised Fixed BSUoS Price, then The Company will use reasonable endeavours to consult on the revised Fixed BSUoS Price prior to its application. The Company will provide a minimum notice of 5 Business Days before the commencement of a revised Fixed BSUoS Price.
The revised Fixed BSUoS Price, described in Paragraph 14.31.15, is determined by the following formula: 𝑓𝐵𝑆𝑈𝑜𝑆𝑇𝑂𝑇 𝑠 𝐹𝑖𝑥𝑒𝑑𝐵𝑆𝑈𝑜𝑆𝑃𝑟𝑒𝑣 = 𝑠 𝑓𝑇𝑄𝑀 +𝑓𝑆𝐺𝑄𝑀 𝑠 𝑠 Where: FixedBSUoSPrev = The revised Fixed BSUoS Price for the number of s Settlement Days s remaining in the Fixed Price Period fBSUoSTOT = forecast of remaining balancing costs for the number of s Settlement Days s remaining in the Fixed Price Period. The Company would use reasonable endeavours to consult on this value, pursuant to Paragraph 14.31.16. fTQM = forecast of the total Transmission Connected Site BM s Unit Metered Volume for the number of Settlement Days s remaining in the Fixed Price Period fSGQM = forecast of the total Gross Demand BM Unit Volume for s the number of Settlement Days s remaining in the Fixed Price Period
Pursuant to Paragraph 14.3 1.17, the revised Fixed BSUoS Price only covers costs for the remainder of the Fixed Price Period. The BSUoS Working Capital Facility would be built back up in subsequent Fixed Price Periods, via the Fixed BSUoS Prices calculated for those Fixed Price Periods.
Settlement of BSUoS Settlement and Reconciliation of BSUoS Charges
There are two stages of the reconciliation of BSUoS Charges described below: • Initial Settlement (SF) • Final Reconciliation (RF) Initial Settlement of BSUoS
The Company will calculate initial settlement (SF) BSUoS Charges in accordance with the methodology set out in section 14.31 above, using the latest available data, including data from the Initial Settlement Run and the Initial Volume Allocation Run. Reconciliation of BSUoS Charges
Final Reconciliation will result in the calculation of a reconciled charge for each Settlement Day in the Financial Year. The Company will calculate Final Reconciliation (RF) BSUoS Charges (with the inclusion of interest as defined in the CUSC) in accordance with the methodology set out in section 14.31 above, using the latest available data, including data from the Final Reconciliation Settlement Run and the Final Reconciliation Volume Allocation Run.
Pursuant to Paragraph 14.31.5, any revenue collected or paid out by The Company as part of Final Reconciliation (RF) BSUoS Charges during a Fixed Price Period t will be considered as part of the revenue associated with that Fixed Price Period t, for the purposes of calculating the over or under recovery factor for subsequent Fixed Price Periods. Unavailability of Data
If any of the elements required to calculate the BSUoS Charges in respect of any Settlement Day have not been notified to The Company in time for it to do the calculations then The Company will use data for the corresponding Settlement Day in the previous week. If no such values for the previous week are available to The Company then The Company will substitute such variables as it shall, at its reasonable discretion, think fit and calculate Balancing Services Use of System Charges on the basis of these values. When the actual data becomes available a reconciliation run will be undertaken. Disputes
If The Company or any customer identifies any error which would affect the total Balancing Services Use of System Charges on a Settlement Day then The Company will recalculate the charges following resolution of the error. Revised invoices and/or credit notes will be issued for the change in charges, plus interest as set out in the CUSC. The charge recalculation and issuing of revised invoices and/or credit notes will not take place for any day where the total change in the Balancing Services Use of System Charges are less than £2000. Relationship between the Statement of the Use of System Charging Methodology and the ESO Licence
BSUoS Charges are made on a daily basis and as such this Statement sets out the details of the calculation of such charges on a daily basis. Customers may, when verifying Balancing Services Use of System Charges refer to the ESO Licence which sets out the maximum allowed revenue that The Company may recover .
The Company has, where possible and appropriate, attempted to ensure that acronyms allocated to variables within the Balancing Services charging software, and associated reporting, match with the acronyms given to those variables used within this statement.
Balancing Services Use of System Acronym Definitions For the avoidance of doubt “as defined in the BSC” relates to the Balancing and Settlement Code as published from time to time. CUSC Section 14 Schedule 1 Calculation of charges that fall within the Connection Exclusion EU Regulation 838/2010 Schedule 1 The proforma of the form and content to be published for the purposes of the calculation in accordance with Paragraph 14.29.
| EXPRESSION | ACRONYM | Unit | Definition |
|---|---|---|---|
| Balancing Mechanism Unit | BM Unit or BMU | As defined in the BSC | |
| System Restoration Costs | SRC d | £ | The total costs associated with the provision of System Restoration (as defined in the Grid Code), including procuring, testing, warming, utilisation, capital contributions and payments for the cost of feasibility studies. This item also includes the costs of any validated claims made for costs of supporting the Electricity System Restoration Standard at Users’ sites, in accordance with CMP398. |
| External Balancing Services Use of System Costs | BSUoSEXT jd | £ | External System Operator (SO) Balancing Services Use of System Costs applicable to Settlement Period j for Settlement Day d |
| Internal Balancing Services Use of System Costs | BSUoSINT d | £ | Internal System Operator (SO) Balancing Services Use of System Costs applicable to Settlement Period j for Settlement Day d |
| Balancing Services Use of System tariff | BSUoStariff j | £/M Wh | Tariff for the Balancing Services Use of System Charge applicable to Settlement Period j |
| Total Balancing Services Use of System Costs | BSUoSTOT | £ | Total Balancing Services Use of System Charges |
| BSUoS Working Capital Facility | BWCF | £ | As defined in Section 11 |
| Fixed BSUoS Price | FixedBSUoSP t | £/M Wh | The Fixed BSUoS Price for the Fixed Price Period t, as defined in Section 11 |
| Revised Fixed BSUoS Price | FixedBSUoSPr ev s | £/M Wh | The revised Fixed BSUoS Price which applies for a number of Settlement Days s within a Fixed Price Period, as described in Paragraph 14.31.15 |
| Over/under recovery factor | kb t | £ | The factor included in the Fixed BSUoS Price for Fixed Price Period t, to account for any over or under recovery from previous Fixed Price Periods. For the first Fixed Price Period (t=0) this factor is zero. |
| BM Unit Metered Volume | QM ij | MWh | As defined in the BSC |
| Gross Final Demand BM Unit Volume | SGQM | MWh | The Import data as at the Transmission System Boundary by Settlement Period for Supplier BM Units in respect to gross Final Demand volume (exclusive of all export volumes and import volumes from BM Units or Single Sites with a valid Declaration), multiplied by the applicable TLM |
| Supplier BM Unit | As defined in the BSC | ||
| Transmission Loss Multiplier | TLM ij | As defined in the BSC | |
| Transmission Connected Final Demand BM Unit Metered Volume | TQM | MWh | The BM Unit Metered Volume for Final Demand with a Bilateral Agreement with The Company, exclusive of export volumes, which is multiplied by the TLM |
| Transmission System Boundary | As defined in the Balancing and Settlement Code | ||
| Total System Energy Imbalance Volume | TQEI j | MWh | As defined in the Balancing and Settlement Code in force immediately prior to 1 April 2001 |
| Final Reconciliation Settlement Run | As defined in the BSC | ||
| Final Reconciliation Volume Allocation Run | As defined in the BSC | ||
| Initial Settlement Run | As defined in the BSC | ||
| Initial Volume Allocation Run | As defined in the BSC | ||
| Lead Party | As defined in the BSC |
| Project Name | Transmission Asset name | PARC/Non PARC | Annual Local Charge for company Transmission Asset | TEC | Tariff |
|---|
SECTION 15: USER COMMITMENT METHODOLOGY
1. Where (a) a Construction Agreement and/or a Bilateral Connection Agreement or Bilateral Embedded Generation Agreement between a User in respect of the categories specified below and The Company is terminated or (b) there is a reduction in Transmission Entry Capacity by or in respect of such User or (c) there is a reduction in Developer Capacity in a Construction Agreement prior to the Charging Date, or (d) there is a reduction in Interconnector User Commitment Capacity by or in respect of such User, such Us
The Cancellation Charge payable shall be calculated in accordance with this Part Two of Section 15.
Value Added Tax will be payable on any Cancellation Charge.
Completion Date and Trigger Date
The Progression Commitment Fee shall become payable in accordance with, and shall be calculated in accordance with, this Part Five. For the avoidance of doubt, the Progression Commitment Fee is only payable (in accordance with this Section 15) from the PCF Activation Date, which shall not be set until the PCF Activation Metric has reached the PCF Activation Threshold.
Activation of the Progression Commitment Fee
2. The Cancellation Charge is payable by Users on termination of agreements with and reductions in Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity in respect of Users in the categories of
a Power Station directly connected to the National Electricity Transmission System in respect of which there is a Bilateral Connection Agreement with The Company;
an Embedded Power Station in respect of which there is a Bilateral Embedded Generation Agreement with The Company;
a Distribution System directly connected to the National Electricity Transmission System in respect of which there is a Construction Agreement associated with Distributed Generation
an Interconnector directly connected to the National Electricity Transmission System in respect of which there is a Bilateral Connection Agreement with The Company and reference to User in this Section 15 shall be interpreted accordingly. For the avoidance of doubt this schedule does not apply to Users other than those described above. CUSC Section 15 v1.14 2 For the avoidance of doubt in respect of Users in the case of category (b) above where The Company has an associated Construction Agreement with a User in the category of (c) above, the Cancellation Charge payable by a User in category (b) above will not include the Attributable Works Cancellation Charge or (from the PCF Activation Date) the Progression Commitment Fee components of the Cancellation Charge. In such case the Attributable Works Cancellation Charge and the Progression Commitment Fee components of the Cancellation Charge will be payable by the associated User in category (c) above. For the avoidance of doubt in the case of:
Users in the case of category (c) above; and
Distributed Generation (other than an Embedded Power Station which is the subject of a Bilateral Embedded Generation Agreement), the Cancellation Charge does not apply for reductions in Developer Capacity on or after the Charging Date or termination on or after the Charging Date. For information, for Users other than Users in the categories to which this Section 15 applies, the liability for and security requirements in respect of Final Sums, which are due on termination of a Construction Agreement are as set out in the Construction Agreement (and in the proforma attached at CUSC Schedule 2, Exhibit 3). From the PCF Activation Date, the Cancellation Charge shall include the Progression Commitment Fee payable in accordance with this Section 15. For the avoidance of doubt, the Progression Commitment Fee is not payable before the PCF Activation Date. For the avoidance of doubt, in addition to the Cancellation Charge, Termination Amounts also apply in respect of Transmission Connection Assets.
In making an Offer to a User The Company will consider the Construction Works and Construction Programme associated with that Offer and taking into account the nature and programming of the Construction Works and the Consents associated with this will identify dates in the Construction Agreement as the Completion Date.
The Trigger Date will be (a) the 1 April which is three Financial Years prior to the start of the Financial Year in which the Charging Date occurs or (b) where the Charging Date is less than three Financial Years from the date of the Construction Agreement, the date of the Construction Agreement (in which case the Financial Year in which such date falls is the relevant Financial Year within the Cancellation Charge Profile working back from the Charging Date).
The Trigger Date is the date from which the Wider Cancellation Charge applies and the date from which, in the case of the Fixed Cancellation Charge, the Fixed Attributable Works Cancellation Charge rather than the Pre Trigger Amount applies. Prior to the Trigger Date, only the Attributable Works Cancellation Charge applies, or in case of the Fixed Cancellation Charge, the Pre Trigger Amount applies.
Changes to Construction Programme or Construction Works or Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity
Where the Construction Programme or the Construction Works or Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity subsequently changes from that in the original Construction Agreement the following principles CUSC Section 15 v1.14 6 will apply in respect of reassessing the Trigger Date and the Cancellation Charge.
Where such change is as a result of The Company’s exercise of its rights under the Construction Agreement then:
Where there is a delay to the Completion Date and the Trigger Date has not passed, the Trigger Date will be revised by reference to the revised Completion Date. The period for which the Pre Trigger Amount applies, will be adjusted to reflect the new Trigger Date;
Where there is a delay to the Completion Date and the Trigger Date has passed, the Trigger Date will be revised by reference to the revised Completion Date and the Cancellation Charge (including the Cancellation Charge Profile) will be adjusted to reflect the revised date.
In the case of a Fixed Cancellation Charge, a change in the Attributable Works will not adjust the Cancellation Charge Profile unless the Completion Date has also changed in which case (ii) above will apply.
Where a change is as a result of the User’s request then, notwithstanding any change in the Completion Date;
Where there is a delay to the Completion Date and the Trigger Date has not passed, the Trigger Date will be revised by reference to the revised Completion Date. The period for which the Pre Trigger Amount applies, will be adjusted to reflect the new Trigger Date;
Where there is a delay to the Completion Date and the Trigger Date has passed, the Trigger Date will not be revised by reference to the revised Completion Date and the Cancellation Charge will not be adjusted downwards but will be held at that level and will increase from that level in line with any new Construction Programme. CUSC Section 15 v1.14 7
Calculation of Cancellation Charge
in the case of a User which meets The Company Credit Rating at the date of the Construction Agreement in accordance with Paragraph 4; and 2.2 in the case of a User which does not meet The Company Credit Rating at the date of the Construction Agreement or thereafter ceases to meet it, in accordance with Paragraph 5.
CALCULATION OF CANCELLATION CHARGE SECURED AMOUNT
Subject to Paragraph 2.2, twice each Financial Year, The Company must use the data it holds to calculate and publish on its web-site the PCF Activation Metric. The Company must publish the PCF Activation Metric:
on or before 1 August (or, where 1 August is not a Business Day, the following Business Day) in each Financial Year for the period from the start of the current PCF Metric Period until the end of the immediately preceding month of June; and 2.1.2. on or before 1 February (or, where 1 February is not a Business Day, the following Business Day) each Financial Year for the period from the start of the current PCF Metric Period until the end of the immediately preceding month of December.
Paragraph 2.1 shall not apply:
for the period from the date the PCF Activation Metric published in accordance with Paragraph 2.1 has reached the PCF Activation Threshold to the end of the PCF Metric Period; or 2.2.2 from the point The Company has set out the PCF Activation Date in a PCF Determination Notice.
Where the PCF Activation Metric calculated and published in accordance with Paragraph 2.1 exceeds the PCF Activation Threshold, The Company must within one month of that publication determine whether or not, in its view, the Progression Commitment Fee should become payable (in accordance with this Section 15), notify the Authority of its determination and publish this determination on its web-site. CUSC Section 15 v1.14 3 7
Within two months of a notification by The Company, having regard to The Company’s determination under Paragraph 2.3, the Authority may determine whether or not, in its view, the Progression Commitment Fee should become payable (in accordance with this Section 15).
Within five Business Days of a determination by the Authority under Paragraph 2.4 or, where there is no such determination, within five Business Days following the end of the period set out in Paragraph 2.4, The Company must publish on its web-site a PCF Determination Notice setting out any determination made.
The Company must include a PCF Activation Date in the PCF Determination Notice where either:
the Authority has determined under Paragraph 2.4 that the Progression Commitment Fee should become payable; or 2.6.2 The Company has determined under Paragraph 2.3 that the Progression Commitment Fee should become payable and the Authority has not, within the period set out in Paragraph 2.4, determined that the Progression Commitment Fee should not become payable.
Other than as provided for in Paragraph 2.6, The Company may not include the PCF Activation Date in a PCF Determination Notice.
For the avoidance of doubt, the Progression Commitment Fee shall not become payable in the remainder of the PCF Metric Period where in the PCF Metric Period either:
the Authority has determined under Paragraph 2.4 that the Progression Commitment Fee should not become payable; or 2.8.2 The Company has determined under Paragraph 2.3 that the Progression Commitment Fee should not become payable and the Authority has not, within the period set out in Paragraph 2.4, determined that the Progression Commitment Fee should become payable.
Where the Progression Commitment Fee has not become payable during a PCF Metric Period, The Company must consider whether or not, in its view, the PCF Activation Threshold is appropriate and publish this view on its web- site, together with any change The Company would recommend, within three months following the end of the PCF Metric Period. (For the avoidance of doubt, CUSC Section 15 v1.14 3 8 The Company giving this view will not itself change the PCF Activation Threshold.)
Information exchange to support calculation of the PCF Activation Metric
3. The Company shall apply and calculate the Cancellation Charge in accordance with Part Two of this Section 15. CUSC Section 15 v1.14 3 The Cancellation Charge is made up of a number of components: the “Pre Trigger Amount”, “Attributable Works Cancellation Charge”, “Wider Cancellation Charge” and (from the PCF Activation Date) the “Progression Commitment Fee” which apply at different stages.
The Cancellation Charge is the charge due to The Company by a User on termination of a Construction Agreement, Disconnection or a reduction in Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity prior to the Charging Date and Disconnection or a reduction in Transmission Entry Capacity or Interconnector User Commitment Capacity on or after the Charging Date.
This calculation of the Cancellation Charge is different:
where the Construction Agreement is terminated or Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity is reduced before the Trigger Date (the “Pre Trigger Amount” or “Actual Attributable Works Cancellation Charge”) (Paragraphs 3.6.1 and 3.7);
where the Construction Agreement is terminated or Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity is reduced on or after the Trigger Date but prior to the Charging Date (the “Fixed Attributable Works Cancellation Charge” or “Actual Attributable Works Cancellation Charge” and the “Wider Cancellation Charge”) (Paragraphs 3.5 to 3.8);
depending whether the Attributable Works Cancellation Charge is a Fixed Cancellation Charge or Actual Attributable Works Cancellation Charge (Paragraphs 3.5 to 3.7);
where the Transmission Entry Capacity or Interconnector User Commitment Capacity is reduced or Disconnection occurs on or after the Charging Date (the “Wider Cancellation Charge”) (Paragraph 3.8);
from the PCF Activation Date, depending on the value of the Progression Commitment Fee calculated in accordance with Part Five of this Section 15. CUSC Section 15 v1.14 8
Where the Construction Agreement is terminated or Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity is reduced before the Trigger Date Where a Construction Agreement is terminated or Transmission Entry Capacity is reduced or Developer Capacity is reduced or Interconnector User Commitment Capacity is reduced before the Trigger Date the Cancellation Charge shall be calculated as follows:
Before the PCF Activation Date or where the PCF Activation Date has not been set: Cancellation Charge = Attributable Works Cancellation Charge
From the PCF Activation Date: Cancellation Charge = Attributable Works Cancellation Charge plus Progression Commitment Fee.
Where the Construction Agreement is terminated or Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity is reduced on or after the Trigger date but prior to the Charging Date Where a Construction Agreement is terminated or Transmission Entry Capacity is reduced or Developer Capacity is reduced or Interconnector User Commitment Capacity is reduced on or after the Trigger date but prior to the Charging Date the Cancellation Charge shall be calculated as follows:
Before the PCF Activation Date or where the PCF Activation Date has not been set: Cancellation Charge = Attributable Works Cancellation Charge plus Wider Cancellation Charge
From the PCF Activation Date: CUSC Section 15 v1.14 9 Cancellation Charge = Attributable Works Cancellation Charge plus Wider Cancellation Charge plus Progression Commitment Fee. The following Paragraphs set out in detail the Attributable Works Cancellation Charge and Wider Cancellation Charge and Paragraph 3.7 sets out the above calculation by formula.
Attributable Works Cancellation Charge The Attributable Works Cancellation Charge can be either the Fixed Cancellation Charge or Actual Attributable Works Cancellation Charge.
Fixed Cancellation Charge The calculation of the Fixed Cancellation Charge is different where the Construction Agreement is terminated or Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity is reduced before (“Pre Trigger Amount”) or on or after the Trigger Date (“Fixed Attributable Works Cancellation Charge”).
Pre Trigger Amount Should a Construction Agreement be terminated, or Transmission Entry Capacity be reduced or Developer Capacity be reduced or Interconnector User Commitment Capacity be reduced before the Trigger Date the Fixed Cancellation Charge is the Pre Trigger Amount calculated as a £/MW figure by reference to the Cancellation Charge Profile and derived in accordance with the formula at Paragraph 3.9 and set out in the Notification of Fixed Cancellation Charge by reference to which an election is made in accordance with Paragraph 7:
Fixed Attributable Works Cancellation Charge Where a Construction Agreement is terminated or Transmission Entry Capacity is reduced or Developer Capacity is reduced or Interconnector User Commitment Capacity is reduced on or after the Trigger Date but prior to the CUSC Section 15 v1.14 1 0 Charging Date the Fixed Cancellation Charge is the Fixed Attributable Works Cancellation Charge calculated as follows: Fixed Attributable Works Cancellation Charge = (Attributable Works Cancellation Amount x MW Reduction in Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity) x Cancellation Charge Profile Where the Attributable Works Cancellation Amount results in a £/MW figure calculated as follows: (Estimated Attributable Works Capital Cost x (1 – Local Asset Reuse Factor) x Strategic Investment Factor x Distance Factor) / Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity Where the Estimated Attributable Works Capital Cost is the fair and reasonable estimate of the Attributable Works Capital Cost for each component within the Attributable Works and which is as set out in the Notification of Fixed Cancellation Charge by reference to which an election is made in accordance with Paragraph 6. Where the Attributable Works are as specified in Appendix MM of the Construction Agreement at the time of the Notification of Fixed Cancellation Charge by reference to which an election is made in accordance with Paragraph 6. Where the Local Asset Reuse Factor is the factor representing the potential for reuse of each component within the Attributable Works as set out in the Notification of Fixed Cancellation Charge by reference to which an election is made in accordance with Paragraph 6. Where the Strategic Investment Factor is a factor calculated for each component within the Attributable Works as a ratio of the Transmission Entry Capacity and/or Developer Capacity and/or Interconnector User Commitment Capacity sharing those Attributable Works against the secured CUSC Section 15 v1.14 1 1 capability of the Transmission assets and set out in the Notification of Fixed Cancellation Charge by reference to which an election is made in accordance with Paragraph 6. Where the Distance Factor is a factor calculated for each component within the Attributable Works as a ratio of distance to the nearest suitable MITS substation and distance to the MITS substation where the Attributable Works connect as set out in the Notification of Fixed Cancellation Charge by reference to which an election is made in accordance with Paragraph 6. This factor is only valid for components where distance is relevant i.e. cables and overhead lines. Where the Cancellation Charge Profile is the profile derived in accordance with the formula at Paragraph 3.10 and set out in the Notification of Fixed Cancellation Charge by reference to which an election is made in accordance with Paragraph 6.
The Pre Trigger Amount and the Attributable Works Cancellation Amount (and the factors used in deriving this) and the Cancellation Charge Profile are fixed at the time an election is made in accordance with Paragraph 7 and the Pre Trigger Amount and Attributable Works Cancellation Amount are not subject to any further specific adjustment, reconciliation or credit should any of the Transmission assets resulting from the Attributable Works be reused or of benefit to other Users.
Actual Attributable Works Cancellation Charge
The Actual Attributable Works Cancellation Charge is the Attributable Works Capital Cost in respect of each component within the Attributable Works at the time at which the Construction Agreement is terminated or Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity is reduced including (a) fees, expenses and costs properly payable by The Company in respect of, or arising from the termination by The Company or any third party of any contract for or relating to the carrying out of any of the Attributable Works provided it is negotiated on an arms length basis (including any such arising under the STC) and (b) a sum equal to the reasonable costs of removing any Transmission Connection Assets and of CUSC Section 15 v1.14 1 2 making good the remaining Plant and Apparatus following such removal and
proper and reasonable expenses incurred and or paid or which The Company is legally bound to incur of pay in seeking Consents for the Attributable Works and (d) interest on any such amounts from the date they were paid by The Company to the date of The Company’s invoice at 2% over Base Rate from time to time and for the time being provided that in each case The Company shall take into account the Local Asset Reuse Factor, the Strategic Investment Factor and the Distance Factor as calculated in paragraph 3.6.2, of the Attributable Works and any of the resulting Transmission assets.
In the case of the Actual Attributable Works Cancellation Charge, on termination of the Construction Agreement or reduction in Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity prior to the Charging Date, The Company shall be entitled to invoice the User for a sum equal to The Company’s fair and reasonable estimate of the Actual Attributable Works Cancellation Charge and so (a) in the case of termination, the User shall pay to The Company on account of the Actual Attributable Works Cancellation Charge a sum equal to the estimate of Actual Attributable Works Cancellation Charge as shown in the Cancellation Charge Statement for the period in which the termination occurs and (b) in the case of a reduction in Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity, a sum by reference to the MW reduction based on the £/MW figure derived from the estimate of Actual Attributable Works Cancellation Charge as shown in the Cancellation Charge Statement for the period in which the termination occurs. These will then be subject to reconciliation in accordance with this Section 15 Part Four.
Wider Cancellation Charge The Wider Cancellation Charge results in a £/MW charge calculated as follows: Zonal Unit Amount x (MW of reduction in Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity) x Cancellation Charge Profile The Zonal Unit Amount is a £/MW figure calculated by reference to the Generation Zone in which the Power Station or Interconnector is to be located CUSC Section 15 v1.14 1 3 as set out in the Cancellation Charge Statement. It is calculated by reference to the Annual Wider Cancellation Charge Statement for the Financial Year in which notice of reduction in Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity is given and/or notice of Disconnection is given or, where in the case of an Event of Default where notice is not given, the Financial Year in which the reduction in Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity or Disconnection occurs. Where the Zonal Unit Amount = Load Related Boundary Capex apportioned to Boundaries by Boundary (LR) Level and Non Load Related Boundary Capex apportioned to Boundaries by Boundary (NLR) Level, summated and multiplied by Boundary Non Compliance Factors and then mapped to Generation Zones and divided by the Wider User Commitment Liability Base, excluding those Power Stations or Interconnectors in respect of which a Construction Agreement has terminated or The Company has been notified of a reduction in the Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity or Disconnection within the period in question. CUSC Section 15 v1.14 1 4 Where Load Related Boundary Capex is the capex required to increase capability in the network as determined by The Company for a given Financial Year, excluding any Attributable Works Capital Cost, reduced by each of the User Risk Factor and the Global Asset Reuse Factor, as set out in the Annual Wider Cancellation Charge Statement. Where Non Load Related Boundary Capex is the capex required to maintain capability in the network as determined by The Company for a given Financial Year, excluding any Attributable Works Capital Cost, reduced by each of the User Risk Factor and the Global Asset Reuse Factor, as set out in the Annual Wider Cancellation Charge Statement. By way of illustration: Load Related Boundary Capex = CAPEX * User Risk Factor * (1 - Global Asset Reuse Factor) and Non Load Related Boundary Capex = CAPEX * User Risk Factor * (1 - Global Asset Reuse Factor) Where CAPEX is the capex required to maintain capability in the network as determined by The Company for a given Financial Year, excluding any Attributable Works Capital Cost Where the User Risk Factor is the share of total risk between generation and consumers, set at 0.5. Where the Global Asset Reuse Factor for a given Financial Year is the percentage of the wider transmission assets which, on average, a Transmission Owner could potentially reuse on another project, as set out in the Annual Wider Cancellation Charge Statement. Where the Boundaries are as detailed in Section 8 of the Electricity Ten Year Statement (ETYS). CUSC Section 15 v1.14 1 5 Where Boundary (LR) Level is the depth of each Boundary as determined by The Company multiplied by the increase in required capability on that Boundary over the forthcoming four year period, as set out in the Electricity Ten Year Statement (ETYS). Where Boundary (NLR) Level is the depth of each Boundary as determined by The Company multiplied by the available capability on that Boundary in the year in question, as set out in the Electricity Ten Year Statement (ETYS). Where Boundary Non Compliance Factors are the ratio between the available capability and required capability on each Boundary as detailed in Section 8 of the Electricity Ten Year Statement (ETYS), capped at 100%. Where Generation Zones are (a) as defined in the Electricity Ten Year Statement (ETYS) for the Financial Year in which the termination or reduction in Transmission Entry Capacity or reduction in Developer Capacity or reduction in Interconnector User Commitment Capacity occurs prior to the Charging Date (or where not so defined as set out in the relevant Cancellation Charge Statement) or (b) as defined in the Electricity Ten Year Statement (ETYS) for the Financial Year in which the notice of Disconnection or reduction in Transmission Entry Capacity occurs on or after the Charging Date. Where the Wider User Commitment Liability Base is the total amount of generation and Interconnector User Commitment Capacity in MW liable for the Wider Cancellation Charge in the year in question and the total amount of generation and Interconnector User Commitment Capacity in MW which will become liable for the Wider Cancellation Charge in the year in question and set out in the Annual Wider Cancellation Charge Statement. Where the Cancellation Charge Profile is the profile derived in accordance with the formula at Paragraph 3.10 or 3.11, as appropriate.
Where the Construction Agreement is terminated or Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity is reduced before the Trigger Date CUSC Section 15 v1.14 1 6 Should a Construction Agreement be terminated, or Transmission Entry Capacity be reduced or Developer Capacity be reduced or Interconnector User Commitment Capacity be reduced before the Trigger Date, before the PCF Activation Date or where the PCF Activation Date has not been set, the Cancellation Charge shall be calculated as follows: Cancellation Charge = Either the Actual Attributable Works Charge or, where on the Fixed Attributable Works Cancellation Charge, a charge calculated as follows: Reduction in Transmission Entry Capacity or Reduction in Developer Capacity or Reduction in Interconnector User Commitment Capacity x Pre Trigger Amount t Where: • Transmission Entry Capacity /Developer Capacity /Interconnector User Commitment Capacity expressed in MW. • Termination of Construction Agreement equates to a reduction in Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity to zero • Pre Trigger Amount which varies according to the number of Financial Years from t the date of the Construction Agreement to the Trigger Date: o up to the end of the first Financial Year (i.e. t =1), the lower of either (a) Pre Trigger Amount = (£1000/MW) or (b) a sum equivalent to the Cancellation t Charge (and if not known an estimate of this) which would apply in the Financial Year which is 3 Financial Years prior to the Financial Year in which the Charging Date occurs. o Where t = 2, the lower of either (a) Pre Trigger Amount = (£2000/MW) or (b) a t sum equivalent to the Cancellation Charge (and if not known an estimate of this) which would apply in the Financial Year which is 3 Financial Years prior to the Financial Year in which the Charging Date occurs. o Where t ≥ 3 up to Trigger Date,the lower of either (a) Pre Trigger Amount = t (£3000/MW) or (b) a sum equivalent to the Cancellation Charge (and if not known an estimate of this) which would apply in the Financial Year which is 3 Financial Years prior to the Financial Year in which the Charging Date occurs. 3.9A From the PCF Activation Date, should a Construction Agreement be terminated, or Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity be reduced before the Trigger Date, the Cancellation Charge shall be the amount calculated using the formula in Paragraph 3.9 plus the Progression Commitment Fee.
Where the Construction Agreement is terminated or Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity is reduced on or after the Trigger Date but prior to the Charging Date CUSC Section 15 v1.14 1 7 Where a Construction Agreement is terminated or Transmission Entry Capacity is reduced or Developer Capacity is reduced or Interconnector User Commitment Capacity is reduced on or after the Trigger Date but prior to the Charging Date, before the PCF Activation Date or where the PCF Activation Date has not been set, a User shall pay the Cancellation Charge calculated as follows: Cancellation Charge = the sum of (a) Fixed Attributable Works Cancellation Charge or Actual Attributable Works Cancellation Charge and (b) Wider Cancellation Charge
Either the Actual Attributable Works Charge or, where on the Fixed Attributable Works Cancellation Charge, a charge calculated as follows: Where: • Termination of Construction Agreement equates to reduction in Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity to zero • Fixed Attributable Works Cancellation Charge = Attributable Works Cancellation Amount x MW reduction in Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity x Cancellation Charge Profile t • Cancellation Charge Profile which varies according to the number of t Financial Years working back from the Charging Date to the Trigger Date: o In the Financial Year in which the Charging Date occurs (t=0), Cancellation Charge Profile = 1.0, o In the Financial Year which is 1 Financial Year prior to the Financial Year in which the Charging Date occurs (t=1), Cancellation Charge Profile = 0.75; o In the Financial Year which is 2 Financial Years prior to the Financial Year in which the Charging Date occurs (t=2), Cancellation Charge Profile = 0.5; and o In the Financial Year which is 3 Financial Years prior to the Financial Year in which the Charging Date occurs (t=3), Cancellation Charge Profile, = 0. 25. AND
Wider Cancellation Charge Where: • Termination of Construction Agreement equates to reduction in Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity to zero • Wider Cancellation Charge = Zonal Unit Amount x reduction in Transmission Entry Capacity or Developer Capacity or CUSC Section 15 v1.14 1 8 Interconnector User Commitment Capacity x Cancellation Charge Profile t • Cancellation Charge Profile which varies according to the number of t Financial Years working back from the Charging Date to the Trigger Date: o In the Financial Year in which the Charging Date occurs (t=0), Cancellation Charge Profile = 1.0, o In the Financial Year which is 1 Financial Year prior to the Financial Year in which the Charging Date occurs (t=1), Cancellation Charge Profile = 0.75; o In the Financial Year which is 2 Financial Years prior to the Financial Year in which the Charging Date occurs (t=2), Cancellation Charge Profile = 0.5; and o In the Financial Year which is 3 Financial Years prior to the Financial Year in which the Charging Date occurs (t=3), Cancellation Charge Profile = 0.25. 3.10A From the PCF Activation Date, where a Construction Agreement is terminated or Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity is reduced on or after the Trigger Date but prior to the Charging Date, the Cancellation Charge shall be the amount calculated using the formula in Paragraph 3.10 plus the Progression Commitment Fee.
Where the Transmission Entry Capacity or Interconnector User Commitment Capacity is reduced or Notice of Disconnection is given on or after the Charging Date The Cancellation Charge payable on notice of Disconnection and/or a reduction in Transmission Entry Capacity or Interconnector User Commitment Capacity on or after the Charging Date is calculated on a £/MW basis as follows by reference to the Zonal Unit Amount for the Financial Year in which the notice is given: Cancellation Charge = Wider Cancellation Charge Where: • Disconnection equates to reduction in Transmission Entry Capacity or Interconnector User Commitment Capacity to zero • Wider Cancellation Charge = Zonal Unit Amount for year in which notice of disconnection or reduction is given x reduction in Transmission Entry Capacity or Interconnector User Commitment Capacity x Cancellation Charge Profile . t CUSC Section 15 v1.14 1 9 • Cancellation Charge Profile which varies according to the number of t Financial Years notice given from the date of notification to Disconnection or reduction in Transmission Entry Capacity or Interconnector User Commitment Capacity: o where notice is given in the Financial Year in which such notice is to take effect (t=0) Cancellation Charge Profile = 1, o except as provided below where notice is given in the Financial Year prior to the Financial Year in which such notice is to take effect (t=1), Cancellation Charge Profile = 0.75, o where notice of reduction of Transmission Entry Capacity is given in the CMP 213 Judicial Review Period which is within a Financial Year prior to the CMP213 Financial Year in which such notice is to take effect (t=1), for the purposes of the Cancellation Charge such notice shall be deemed to have been given in timescales such that the Cancellation Charge Profile = zero where; ▪ the “CMP213 Judicial Review Period” means the period of 20 Business Days (inclusive) from the day on which (having exhausted all appeals) the Judicial Review proceedings against the Authority’s decision to approve Approved CUSC Modification 213 are concluded ▪ The « CMP213 Financial Year » means the Financial Year in which Approved CUSC Modification 213 is directed by the Authority to take effect, o where notice is given in the Financial Year which is two Financial Years prior to the Financial Year in which such notice is to take effect (t=2), Wider Cancellation Charge = zero. CUSC Section 15 v1.14 2 0
Annual Wider Cancellation Charge Statement
Prior to the Trigger Date the Cancellation Charge Secured Amount is the Cancellation Charge as set out in the Cancellation Charge Statement for the relevant Security Period.
Before the PCF Activation Date or where the PCF Activation Date has not been set, on or after the Trigger Date until the Charging Date the Cancellation Charge Secured Amount is that percentage of the figure shown as the Cancellation Charge in the Cancellation Charge Statement for the relevant Security Period determined as follows: CUSC Section 15 v1.14 2 6 3.2A From the PCF Activation Date, on or after the Trigger Date until the Charging Date the Cancellation Charge Secured Amount shall be calculated as: KC% of (Cancellation Charge minus Progression Commitment Fee) plus Progression Commitment Fee where: a) KC% is the % as determined for different categories of User in accordance with Paragraph 3.2, and b) the Cancellation Charge and the Progression Commitment Fee are as set out in the Cancellation Charge Statement for the relevant Security Period.
| For Users in category (a) as per Section 15 Part One Paragraph 2 | |
|---|---|
| Prior to (and including) the Key Consents In Place Date | the % for that Financial Year as set out in the Annual Wider Cancellation Charge Statement. |
| From the Key Consents In Place Date | the % for that Financial Year as set out in the Annual Wider Cancellation Charge Statement. |
| For Users in categories (b) and (c) as per Section 15 Part One Paragraph 2 | |
| Prior to (and including) the Key Consents In Place Date | the % for that Financial Year for Distributed Generation as set out in the Annual Wider Cancellation Charge Statement. |
| From the Key Consents In Place Date | the % for that Financial Year for Distributed Generation as set out in the Annual Wider Cancellation Charge Statement. |
The User shall notify The Company once it considers that it has been granted the Key Consents. The Company shall respond as soon as practicable after such notification confirming that it is satisfied that this is the case or giving reasons why it is not so satisfied.
The Cancellation Charge Secured Amount shall be calculated using the Cancellation Charge inclusive of any applicable Value Added Tax that would be due. CUSC Section 15 v1.14 2 7
PROVISION OF SECURITY WHERE USER MEETS THE COMPANY CREDIT RATING
Subject to Paragraph 3.3, twice each Financial Year each owner/operator of a Distribution System must notify to The Company the cumulative total of Developer Capacity (in MW) where Relevant Construction Agreements between it and The Company:
were terminated as a result of termination (by the owner/operator of the Distribution System) of a related Distribution Connection Agreement due to a failure by the developer to meet Milestone 1; or 3.1.2 had Developer Capacity reduced as a result of termination or reduction of capacity (by the owner/operator of the Distribution System) of a related Distribution Connection Agreement due to a failure by the developer to meet Milestone 1.
The owner/operator of a Distribution System must provide the notification in Paragraph 3.1:
on or before 14 July (or, where 14 July is not a Business Day, the following Business Day) in each Financial Year for the period from the start of the current PCF Metric Period until the end of the immediately preceding month of June; and 3.2.2 on or before 14 January (or, where 14 January is not a Business Day, the following Business Day) each Financial Year for the period from the start of the current PCF Metric Period until the end of the immediately preceding month of December.
Paragraph 3.1 shall cease to apply from the point The Company has set out the PCF Activation Date in a PCF Determination Notice.
Each owner/operator of a Distribution System must provide the information set out in Paragraph 3.1 in such form, and promptly provide such further relevant information, as The Company may reasonably request from time to time. CUSC Section 15 v1.14 3 9
Calculation of the Progression Commitment Fee
4. As provided for at Paragraph 3.5, the Attributable Works Cancellation Charge can be (at the User’s election in accordance with Paragraph 7) on the basis of the Fixed Cancellation Charge (Paragraph 3.6) rather than the Actual Attributable Works Cancellation Charge (Paragraph 3.7).
By not later than 31 January prior to the start of each Financial Year The Company will publish a statement showing:
the Zonal Unit Amount by Generation Zone for that Financial Year;
the Wider User Commitment Liability Base for that Financial Year;
the Total TO Capex for that Financial Year (where the Total TO Capex is the forecast of the Load Related Boundary Capex and Non Load Related Boundary Capex for a given Financial Year, excluding the total Attributable Works Capital Cost);
a forecast of the Total TO Capex for the following three Financial Years;
the Global Asset Reuse Factor for that Financial Year;
the Boundary Non Compliance Factors for that Financial Year;
a forecast of the Zonal Unit Amount by Generation Zone for the following three Financial Years;
the proportion of the Cancellation Charge that is required to be secured prior to (and including) and after the Key Consents in Place Date.
In the event that for any Financial Year it is proposed to change the Global Asset Reuse Factor or the proportion of the Cancellation Charge that is required to be secured prior to (and including) and after the Key Consents in Place Date from that set out in the Annual Wider Cancellation Charge Statement for the previous Financial Year, The Company shall not make such change without first consulting on the change (and its provision in electronic form on the Website and in electronic mails to CUSC Parties and such other persons who have supplied relevant details shall meet this requirement).
Statement of Cancellation Charge
The User shall as soon as possible after entering into a Construction Agreement and/or Bilateral Connection Agreement or Bilateral Embedded Generation Agreement and in any event no later than one (1) month after the date of the same confirm to The Company whether it meets The Company Credit Rating. Thereafter not less than 75 days before the 1 April and 1 October each year until 30 days after the Charging Date the User shall confirm to The Company whether it meets The Company Credit Rating (which in the case of a long term private credit rating shall be confirmed by Standard and Poor’s or Moody’s within a period of 45 days prior to the date of confirmation). The User shall inform The Company in writing forthwith if it becomes aware of no longer meeting The Company Credit Rating or if it is or is likely to be put on credit watch or any similar credit surveillance procedure which may give The Company reasonable cause to believe that the User may not be able to sustain meeting The Company Credit Rating for at least 12 months.
In the event that the User has elected to provide The Company with an indicative credit rating and The Company is of the reasonable opinion that the User has ceased to comply with the requirements of Paragraph 4.1 then The Company may require the User forthwith:
to apply to Standard and Poor’s and/or Moody’s for a further indicative long term private credit rating; or
to confirm to The Company that it shall provide the security referred to in Paragraph 4.4 below.
In the event of the User:
not meeting The Company Credit Rating; or
having a credit rating below The Company Credit Rating; or CUSC Section 15 v1.14 2 8
not having obtained from Standard and Poor’s or Moody’s within 30 days of the written notification under Paragraph 4.2(i) above an indicative long term private credit rating, or if The Company becomes aware that:
the User ceases to meet The Company Credit Rating; or
the User is put on credit watch or other similar credit surveillance procedure as specified above which may give The Company reasonable cause to believe that the User may not be able to maintain The Company Credit Rating for at least 12 months; or
the User has not obtained from Standard and Poor’s within 30 days of the written notification by The Company under Paragraph 4.2(i) above a further indicative long term private credit rating, the User shall (where appropriate on receipt of written notification from The Company) comply with the terms of Paragraph 4.4.
The User shall within 21 days of the giving of a notice under Paragraph 4.3 or within 30 days of the User confirming to The Company under Paragraph 4.2(ii) that it will provide the security specified below (whichever is the earlier), provide The Company with the security specified below to cover the Cancellation Charge Secured Amount for the relevant Security Period as notified by The Company to the User.
The form of security provided shall be of a type set out in Paragraph 6.
If the facts of circumstances giving rise to the obligation of the User to provide the security have ceased, then The Company shall release the security.
PROVISION OF SECURITY WHERE USER DOES NOT MEET OR CEASES TO MEET THE COMPANY CREDIT RATING
The following Paragraphs set out in detail how the Progression Commitment Fee shall be calculated.
The Progression Commitment Fee shall be calculated as follows:
where a Construction Agreement is terminated, the Progression Commitment Fee shall be equal to the Applicable PCF, and 4.2.2 where Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity is reduced: C− RC Progression Commitment Fee = Applicable PCF × , C where: Applicable PCF is calculated in accordance with Paragraphs 4.3 to 4.6; C is the Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity; RC is the reduced capacity being Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity under the Construction Agreement as reduced.
Subject to Paragraphs 4.4 to 4.6, the Applicable PCF shall be calculated as follows for the time periods set out below: CUSC Section 15 v1.14 4 0
| Time Period | Applicable PCF calculation |
|---|---|
| Where the Construction Agreement is entered into before or on the PCF Activation Date, the period from the PCF Activation Date to the end of the PCF Period, OR | £2,500/MW × Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity (in MW) |
| where the Construction Agreement is entered into after the PCF Activation Date, the period from the Construction Agreement being entered into to the end of the PCF Period (in either case being the first PCF Period) | |
| Second PCF Period | £5,000/MW × Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity (in MW) |
| Third PCF Period | £7,500/MW × Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity (in MW) |
| Fourth PCF Period and any subsequent PCF Periods | £10,000/MW × Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity (in MW) |
Notwithstanding Paragraph 4.3 above and subject to paragraphs 4.5 and 4.6, the Progression Commitment Fee shall be £0 in relation to a Construction Agreement:
where the Construction Agreement was entered into on or before the PCF Activation Date and there is six months or less between the PCF Activation Date and the date for Milestone 1 being met; or 4.4.2 where the Construction Agreement is entered into after the PCF Activation Date and there is six months or less remaining until the date for Milestone 1 being met; or 4.4.3 where the Construction Agreement is entered into without Milestone 1 being determined and, once determined, there is six months or less between the date the Construction Agreement was entered into and the date for Milestone 1 being met; or CUSC Section 15 v1.14 4 1 4.4.4 for so long as there is no determined Milestone 1; or 4.4.5 where Milestone 1 has been met.
Where the Construction Agreement is between an owner/operator of a Distribution System and relates to more than one Distribution Connection Agreement, the Progression Commitment Fee shall be £0 only in relation to Developer Capacity where the relevant subparagraph in paragraph 4.4 applies. The reference to Developer Capacity in paragraph 4.3 shall be construed accordingly.
Where there is otherwise more than one Milestone 1 in respect of a Construction Agreement, the Progression Commitment Fee shall be £0 only in relation to the Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity where the relevant subparagraph in paragraph 4.4 applies. The reference to Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity in paragraph 4.3 shall be construed accordingly.
Information exchange to support application of the Progression Commitment Fee
5. This Section 15 also sets out in Part Three the level of, and arrangements for, security required in respect of the Cancellation Charge.
With an Offer The Company shall provide each User with an indicative profile of the estimated spend in respect of the Attributable Works and a Notification of Fixed Cancellation Charge.
Cancellation Charge Statement CUSC Section 15 v1.14 2 1
The Company shall issue a Cancellation Charge Statement to a User showing the amount of the payment required or which may be required to be made by the User to The Company in respect of the Cancellation Charge prior to the Charging Date at the following times and in respect of the following periods:-
Forthwith on and with effect from the signing of the Construction Agreement, in respect of the period from and including the day of signing of the Construction Agreement until the next following 30 September or 31 March, whichever is the earlier; and thereafter
not less than 75 (seventy five) days (or if such day is not a Business Day the next following Business Day) prior to each 30 September and 31 March thereafter in respect of the period of six calendar months commencing on the immediately following 1 October or 1 April (as the case may be), until the earlier of either the termination of the relevant Construction Agreement or the Charging Date.
From the PCF Activation Date, The Company may also issue a Cancellation Charge Statement to a User showing the amount of the payment required or which may be required to be made by the User to The Company in respect of the Cancellation Charge prior to the Charging Date where:
there is a change in the payable Progression Commitment Fee during a Security Period: or
The Company has otherwise received updated information from the owner/operator of a Distribution System in relation to the payable Progression Commitment Fee, and the Cancellation Charge Statement shall be in respect of the period from the Cancellation Charge Statement being issued until the next following 30 September or 31 March, whichever is earlier.
If a User does not elect for the Fixed Cancellation Charge (unless and until a User subsequently elects for a Fixed Cancellation Charge as provided for at Paragraph 7 or advises The Company that it does not wish to receive this) The Company shall provide a Notification of Fixed Cancellation Charge and an estimate of the Actual Attributable Works Cancellation Charge with each Cancellation Charge Statement. CUSC Section 15 v1.14 2 2
The Actual Attributable Works Cancellation Charge shall apply unless and until a User elects for a Fixed Cancellation Charge in accordance with Paragraph 7.
Estimating the Actual Attributable Works Cancellation Charge In the case of the Actual Attributable Works Cancellation Charge, the Cancellation Charge Statement shall set out a fair and reasonable estimate of the Actual Attributable Works Cancellation Charge for the 6 month period and, for the project generally. In addition the 6 month estimate of the Actual Attributable Works Cancellation Charge shall, for the purposes of assessing the Cancellation Charge Secured Amount, be prorated on a MW basis between those Users who share a component within the Attributable Works.
Electing for the Fixed Cancellation Charge
Each User hereby agrees that it shall at the date of the relevant Construction Agreement and/or Bilateral Connection Agreement or Bilateral Embedded CUSC Section 15 v1.14 2 9 Generation Agreement provide to The Company or procure the provision to The Company of, and the User shall until 28 days after the Charging Date maintain or procure that there is maintained in full force and effect (including by renewal or replacement) a security arrangement from time to time and for the time being as set out in Paragraph 6 to provide security for the Cancellation Charge Secured Amount.
If there shall be any dispute between the User and The Company as to:-
the fairness and reasonableness of the estimate of the Attributable Works Capital Charge; or
the calculation of the Cancellation Charge, or
whether there has been an Event of Default as provided in CUSC Section 5; or
the lawfulness or otherwise of any termination or purported termination of the Construction Agreement, such dispute shall not affect the ability of The Company to make demands pursuant to the security arrangement to be provided pursuant to this CUSC Section 15 and to recover the amount or amounts payable thereunder, it being acknowledged by the User that but for such being the case The Company’s security would be illusory by reason of the period of validity of the relevant security being likely to expire or capable of expiring before the final resolution of such dispute. The User accordingly covenants with The Company that it will not take any action, whether by way of proceedings or otherwise, designed or calculated to prevent, restrict or interfere with the payment to The Company of any amount secured under the security arrangement nor seek nor permit nor assist others to do so.
TYPES OF SECURITY
Within one month of a PCF Determination Notice which sets out the PCF Activation Date, each owner/operator of a Distribution System must notify The Company for each Construction Agreement entered into between it and The Company whether or not Paragraph 4.4 applies to the Construction Agreement and, if it applies, the relevant sub-paragraph on which this is based.
From the PCF Activation Date the owner/operator of a Distribution System must, on or before the date it provides The Company with a signed Construction Agreement, notify The Company of whether or not it reasonably expects Paragraph 4.4 to apply to the Construction Agreement once entered into and, if it will apply, the relevant sub-paragraph on which this is based.
Where, in accordance with Paragraph 5.2, the owner/operator of a Distribution System has notified The Company that Paragraph 4.4 is expected to apply to a Construction Agreement once entered into on the basis that Milestone 1 has not been determined, the owner/operator of a Distribution System must, within CUSC Section 15 v1.14 4 2
6. The Company shall apply and calculate the Cancellation Charge Secured Amount in accordance with this Section 15 Part Three.
To elect for a the Fixed Cancellation Charge, a User must notify The Company to this effect by (a) returning a signed copy of the Notification of Fixed Cancellation Charge with its acceptance of the Construction Agreement or
, where a User does not elect at that time, it can elect 45 days (or if such day is not a Business Day the next following Business Day) prior to each 30 September or 31 March thereafter by returning a signed copy of the Notification of Fixed Cancellation Charge as provided with the relevant Cancellation Charge Statement.
Once a User has elected for the Fixed Cancellation Charge, the Pre Trigger Amount, Fixed Attributable Works Cancellation Charge and Cancellation Charge Profile will then be fixed as that set out in the Notification of Fixed Cancellation Charge by reference to which such election was made and a User cannot revert to the Actual Attributable Works Cancellation Charge. For the avoidance of doubt, where the User has elected for the Fixed Attributable Works Cancellation Charge and Construction Works relating to that charge are subsequently designated as Excepted Works an adjustment will be made to the Fixed Attributable Works Cancellation Charge to remove the cost of the Excepted Works from the Fixed Attributable Works Cancellation Charge. CUSC Section 15 v1.14 2 3
If the User becomes aware that the bank or insurance company issuing the Performance Bond or Letter of Credit ceases to be a Qualified Bank or that the company giving the Performance Bond ceases to be a Qualified Company, the User shall so notify The Company in writing as soon as it becomes so aware. If The Company becomes aware that the bank or insurance company issuing the Performance Bond or Letter of Credit ceases to be a Qualified Bank or that the company giving the Performance Bond ceases to be a Qualified Company, The Company may notify the User to that effect in writing. Where the bank, insurance company or the company so ceases to be either a Qualified Bank or a Qualified Company (as the case may be) as a consequence of The Company having reasonable cause to doubt the continued rating of the said bank, insurance company or company, such notice shall be accompanied by a statement setting out The Company’s reasons for having such doubt. The User shall within 21 days of the giving of such notice by The Company or the User whichever is the earlier provide a replacement Performance Bond and/or Letter of Credit from a Qualified Bank or Qualified Company, as the case may be, and/or provide a cash deposit in the required amount in a Bank Account. From the date the replacement Performance Bond or Letter of Credit or Bank Account cash deposit is effectively and unconditionally provided and Valid, The Company will consent in writing to the security which it replaces being released.
Cancellation Charge Secured Amount Statement
The User shall from time to time and for the time being as set out in Paragraph 5 provide security for the Cancellation Charge Secured Amount by any one of the following:-
A Performance Bond or Letter of Credit from a Qualified Bank for Cancellation Charge Secured Amount for a given Security Period, such Performance Bond or Letter of Credit to be Valid for at least that CUSC Section 15 v1.14 3 0 given Security Period and to be renewed periodically where applicable in the manner stated in paragraph 6.2.3; or 6.1.2 A cash deposit in a Bank Account at least for the amount of the Cancellation Charge Secured Amount to be secured for a given Security Period, such cash deposit to be increased or reduced periodically where applicable in the manner stated in paragraph 6.2.4; or 6.1.3 A Performance Bond from a Qualified Company for the amount of the Cancellation Charge Secured Amount to be secured for a given Security Period, such Performance Bond to be Valid for at least that Security Period and to be renewed periodically where applicable in the manner stated in paragraph 6.2.3.
General Provisions regarding Security
Any Notice of Drawing to be delivered to Barclays Bank PLC or any other bank at which the Bank Account shall have been opened or a Qualified Bank or a Qualified Company may be delivered by hand, by post or by other agreed communication method.
If the User becomes aware that the bank issuing the Performance Bond or Letter of Credit ceases to be a Qualified Bank or that the company giving the Performance Bond ceases to be a Qualified Company, the User shall so notify The Company in writing as soon as it becomes so aware. If The Company becomes aware that the bank issuing the Performance Bond or Letter of Credit ceases to be a Qualified Bank or that the company giving the Performance Bond ceases to be a Qualified Company, The Company may notify the User to that effect in writing. Where the bank or the company so ceases to be either a Qualified Bank or a Qualified Company (as the case may be) as a consequence of The Company having reasonable cause to doubt the continued rating of the said bank or company, such notice shall be accompanied by a statement setting out The Company’s reasons for having such doubt. The User shall within 21 days of the giving of such notice by The Company or the User whichever is the earlier provide a replacement Performance Bond and/or Letter of Credit from a CUSC Section 15 v1.14 3 1 Qualified Bank or Qualified Company, as the case may be, and/or provide a cash deposit in the required amount in a Bank Account. From the date the replacement Performance Bond or Letter of Credit or Bank Account cash deposit is effectively and unconditionally provided and Valid, The Company will consent in writing to the security which it replaces being released.
The following provisions shall govern the issuance, renewal and release of the Performance Bond or Letter of Credit:-
The Performance Bond or Letter of Credit shall be Valid initially for the First Security Period. Such Performance Bond or Letter of Credit shall be for an amount not less than the Cancellation Charge Secured Amount for that First Security Period.
On a date which is at least 45 days (or if such day is not a Business Day then on the immediately preceding Business Day) before the start of each following Security Period such Performance Bond or Letter of Credit shall be renewed so as to be Valid for not less than such Security Period and in the case of the last Security Period to be Valid, unless The Company agrees otherwise, for 45 days after the last day of such Security Period. Such renewed Performance Bond or Letter of Credit shall be for an amount not less than the Cancellation Charge Secured Amount to be secured during that Security Period.
The following provisions shall govern the maintenance of cash deposits in the Bank Account:-
The amount of the User’s cash deposit to be maintained in the Bank Account shall be maintained by the User from the date of the Construction Agreement at least to the end of the First Security Period. Such cash deposit shall be in the amount of the Cancellation Charge Secured Amount to be secured during that First Security Period. CUSC Section 15 v1.14 3 2
If the amount of the Cancellation Charge Secured Amount to be secured from the start of each Security Period is an amount greater than the amount then secured, the User’s cash deposit in the Bank Account in respect of the Security Amount shall be increased by the User to such greater amount on the date which is 21 calendar days before the start of the given Security Period. 6.2.4.2a The value of any cash deposit to be provided by the User under 6.2.4.2 shall be notified to The Company in writing on or before 45 calendar days before the start of the given Security Period.
If the Cancellation Charge Secured Amount for a given Security Period is smaller than the amount then secured, the User’s cash deposit in the Bank Account in respect of the Security Amount shall not be reduced to the amount so stated until the expiry of 7 days after the start of that given Security Period (“the Release Date”).
The sum equal to the amount of reduction in the User’s cash deposit in the Bank Account in respect of the Security Amount shall be paid by The Company to the User from the Bank Account on the Release Date.
Any interest accruing in respect of the User’s cash deposit in the Bank Account in respect of the Security Amount shall be for the account of and belong to the User absolutely, and The Company agrees to take any steps required to be taken by it for the release from the Bank Account (or any other bank account in the name of The Company in which such interest is held) and payment to the User of such interest as soon as The Company shall have received notice from the User requesting such payment.
For the avoidance of doubt, the User’s cash deposit in the Bank Account shall remain the sole property and entitlement of the User until such time when (and to such extent as) the Company exercises its right of set off against the User’s cash deposit in accordance with the terms of the CUSC, and the User shall have CUSC Section 15 v1.14 3 3 no right to have the cash deposit returned to it for so long as it is under any prospective or contingent liability to the Company.
Notwithstanding any provision aforesaid:-
The User may provide different securities to The Company at any one time, each securing a different amount, provided that the aggregate amount secured by such securities shall be not less than the amount of the Cancellation Charge Secured Amount required to be secured for that Security Period.
The User may upon the expiry of at least 14 days prior written notice to The Company, substitute one type of security for another provided that unless The Company shall otherwise agree in writing such substituted security must be Valid from the first day of the relevant Security Period and committed at least 45 days before this in the following manner:-
where a Performance Bond or a Letter of Credit is to substitute for other securities, it must be issued or given at least 45 days before the start of the Security Period to which it relates.
where a cash deposit in a Bank Account is to substitute for other securities, it must be deposited into the Bank Account at least 45 days before the start of the Security Period to which it relates.
Upon request by the User to The Company, securities substituted in the aforesaid manner shall, providing the substitute security shall be Valid, be released on the first day of the Security Period which the substitute security is securing. However, where the Cancellation Charge Secured Amount to be secured for any Security Period is less than the amount required to be secured in the preceding Security Period, the substituted security shall not be released until 7 days after the start of the Security Period that that substitute security is securing. CUSC Section 15 v1.14 3 4
Where the User provides securities to The Company in multiple types as per paragraph 6.1, the provisions of paragraph 6.2.3 and 6.2.4 shall apply respectively to each type of security.
From the PCF Activation Date, where Milestone 1 is met in relation to a Construction Agreement, The Company must as soon as reasonably practicable release the security held in respect of any amount of the Progression Commitment Fee which (in accordance with Part Five) has been reduced to £0, provided that the security is not required to be released until any substitute security required under this Section 15 is in place. CUSC Section 15 v1.14 3 5
7. This Section 15 also sets out in Part Four the reconciliation process in respect of the Actual Attributable Works Cancellation Charge. 7A This Section 15 also sets out in Part Five the detail on the activation and administration of the Progression Commitment Fee.
Where a User has to provide security in accordance with Part Three of this Section 15 the Cancellation Charge Statement shall be accompanied by the Cancellation Charge Secured Amount Statement.
The Cancellation Charge Secured Amount shall be based on the highest level of Cancellation Charge due within the period covered by the Cancellation Charge Secured Amount Statement.
Interconnector Transition to Cancellation Charge
8. For reference a number of terms used in this Section 15 are defined within this Section 15.
This provision only applies in respect of Users who are Interconnectors.
The provisions of this Section 15 shall apply in respect of the first Security Period which is not less than 6 months after the Implementation Date for CUSC Modification Proposal 222. In the period prior to that Security Period and as CUSC Section 15 v1.14 2 4 soon as practicable after the Implementation Date for CUSC Modification Proposal 222
The Company shall 8.2.1.1 offer to amend each User’s Construction Agreement such that it will be substantially in the form of that set out Schedule 2, Exhibit 3 Part 1 (as it relates to the Cancellation Charge arrangements);
send to each User in respect of each Construction Agreement a Cancellation Charge Statement for that Security Period 8.2.2 the User shall put Security Arrangements in place in respect of its Construction Agreement in accordance with CUSC Section 15 to be effective from the start of that Security Period to the next following 31 March or 30 September (whichever is the earlier).
If The Company and a User fail to agree changes to the Construction Agreement either such person may refer the matter to the Authority under condition E13.5 of the ESO Licence. CUSC Section 15 v1.14 2 5
9. Distributed Generation Users in the category of (c) above are liable for the Cancellation Charge (or where the Distributed Generation has a Bilateral Embedded Generation Agreement, the Attributable Works Cancellation Charge and (from the PCF Activation Date) the Progression Commitment Fee components of the Cancellation Charge) on a reduction in Developer Capacity (or in the case of Distributed Generation with a Bilateral Embedded Generation Agreement) Transmission Entry Capacity and/or termination of the Co
CALCULATION OF CANCELLATION CHARGE SECURED AMOUNT AND CREDIT REQUIREMENTS
Each User which has a Construction Agreement shall provide security in respect of each of its Construction Agreements for the Cancellation Charge Secured Amount as applied and calculated in accordance with this Part Three of Section 15:
As soon as practicable and in any event within 60 days of the date, as appropriate, of termination of the Construction Agreement or reduction in Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity The Company shall:
furnish the User with a statement showing a revised estimate of the Actual Attributable Works Cancellation Charge and will provide as soon as practicable evidence of such having been incurred; and
furnish the User with justification of and supporting information in respect of its assessment of the actual or potential for reuse and any strategic benefits of the Attributable Works and any of the resulting Transmission assets.
As soon as reasonably practicable after termination of this Construction Agreement or reduction in Transmission Entry Capacity or Developer Capacity or Interconnector User Commitment Capacity and in any event within 12 months of such event The Company shall provide the User with a final statement of the Actual Attributable Works Cancellation Charge. If the Actual Attributable Works Cancellation Charge is greater than the payments made by the User in respect of The Company’s estimate(s) of the Actual Attributable Works Cancellation Charge the User shall within 28 days of the said statement and invoice prepared by The Company pay to The Company the additional payments due by the User together with interest calculated thereon on a daily basis at Base Rate for the time being and from time to time from the date of previous payment(s) to the date of the final statement of the Actual Attributable Works Cancellation Charge and final invoice for the Attributable Works Cancellation Charge. If the Actual Attributable Works Cancellation Charge is less than the payments made by the User in respect of The Company’s estimate(s) of the Actual Attributable Works Cancellation Charge The Company shall forthwith pay to the User the excess paid together with interest on a daily basis at Base Rate for the time being and from time to time from the date of payment of the fair and reasonable estimate of the Actual Attributable Works Cancellation Charge to the date of reimbursement by The Company of the said excess paid. CUSC Section 15 v1.14 3 6
SECTION 16: QUEUE MANAGEMENT PROCESS
The process set out in this Section 16 will be applied by The Company in measuring the progression of a User’s project (excluding any OTSDUW) against the Completion Date, or where the User’s Project is staged, the relevant Completion Date in the Construction Agreement related to that project. The process identifies a set of milestones as set out below against which progress is measured and if not achieved provides for the termination of the Construction Agreement. Although provision for this process is included within Gate 1 Agreements the process and provisions within this Section will only be actively applied in Gate 2 Agreements.
The Queue Management Process will not be applied and included in (i) Construction Agreements with an Embedded Power Station relating to a Bilateral Embedded Generation Agreement or (ii) Construction Agreements with the owner/operator of a Distribution System directly connected to the National Electricity Transmission System where the Construction Agreement is required because of a connection to that Distribution System and the Distribution Queue Management Process applies.
The User Progression Milestones and Evidence The milestone events/timings against which the progress of a User’s project will be measured by The Company are listed in the table below. The table also shows the evidence a User has to provide to The Company to show that a milestone event has been met. A User Progression Milestone must be achieved by the date which represents the end of the milestone period identified for that milestone. Once achieved a Conditional Progression Milestone must also continue to be met on an ongoing basis, that is, the statutory consent and planning permission initiated and secured and the land rights achieved to demonstrate compliance with the Conditional Progression Milestone must remain in place. The Company will provide (in the form of Appendix Q) a Table based on the above with each Construction Agreement. This will specify the dates of the milestone periods for the User’s project derived in accordance with this Section 16 and set out in each Appendix Q. Where a User’s project is being delivered in discrete “stages” of Equipment, or programme for example when the project relates to the installation of different technology types or co-located sites, and they are being progressed discretely a separate Appendix Q will be provided for each “stage” and the Queue Management Process applied to each “stage” separately of the land on which the proposed site is or will be situated; or
| Milestone | Detail | Evidence | Milestone Period |
|---|---|---|---|
| Milestone 1) Initiated Statutory Consents and Planning Permission | Where statutory consents are required for the construction of the User’s project, the User must begin the process of seeking statutory consents, including Planning Permission for the project within the timescales and be able to provide the required evidence. | Submission of planning application to the relevant Statutory Authority or, if the User’s project does not require a statutory consent, a declaration from the User to that effect. | See table (varies with lead time). |
| Milestone 2) Secured Statutory Consents and Planning Permission | Where required for the construction of the User’s project, the User must have secured statutory consents, including Planning Permission for the project within the timescales and be able to provide the required evidence | The planning decision notice confirms planning permission has been granted and that this permission allows the User to meet the terms included in its Construction Agreement. Compliance with this milestone is ongoing. | See table (varies with lead time) |
| Milestone 3) Secure Land Rights | The User must have secured the required land rights to enable the construction of the project. The User may be the owner/occupier of the land or has the necessary agreement from the owner/occupier. | The User shall provide documentation to demonstrate that: (i) The User is an owner or tenant of the land on which the proposed site is or will be situated; or (ii) The User has entered into an agreement to lease (which meets the requirements in the Gate 2 Criteria Methodology) the land from the owner | See table |
The User has an option to purchase or to lease the land from the owner of the land on which the proposed site is or will be situated and this option meets the requirements and parameters set out in the Gate 2 Criteria Methodology; or
For an Offshore Project, which depending on the type of Offshore Projects (and set out in the LoA Guidance) the land rights are provided by reference to the seabed or Onshore Connection Site (a) the User has entered into an agreement for occupation or use of the seabed upon which the User's project (excluding any OTSDUW) is or will be located or (b) the requirements at
and (iii) above apply. Nb the obligation is to secure and evidence the land right for the site of the installation e.g. Power Station or demand site so the evidence does not relate to rights e.g. easements associated with that site or OTSDUW. The date by which a User Progression Milestone has to be achieved is derived from the following Tables working (except in the case of Conditional Progression Milestone M1) backwards from the Completion Date (or where staged, relevant Completion Date) in a Connection Offer to the date on which the Connection Offer is made by The Company to the User. The date by which Conditional Progression Milestone M1 has to be achieved is derived from the following Table based on the earlier of two dates as set out in that Table. The User Progression Milestones are categorised as Conditional Progression Milestones and Construction Progression Milestones. Different rights and obligations on The Company to terminate the User’s Construction Agreement apply for each of these categories. As noted above compliance with the Conditional Progression Milestones is measured on an ongoing basis. Conditional Progression Milestones The standard time period for each planning type to move from M3 to M1 is as follows: Construction Progression Milestones Where durations are referred to as being “bilaterally negotiated” this means that The Company, the Relevant Transmission Licensee and the User will aim to agree the durations for the purposes of Appendix Q during the Offer preparation period. Where not so agreed by the time the Offer is made, Appendix Q will reflect the durations proposed by The Company and Relevant Transmission Licensee and discussions will continue with a view to agreeing these during the Offer acceptance period.
| Compliance with this milestone is ongoing and additionally measured against the requirements regarding the Original Red Line Boundary as set out in Paragraph 16.4.9.3 below. | |||
|---|---|---|---|
| Milestone 4) N/A for Transmission | This milestone does not apply for Transmission | Null | Null |
| Milestone 5) Contestable Design Works Submission | This milestone will apply where a User has gone down the contestable route for connection. | Written confirmation from the Relevant Transmission Licensee that design obligations as bilaterally agreed in a User-Self Build agreement have been received. | See table (varies with lead time) |
| Milestone 6) Agree Construction Plan | The User must have agreed a construction plan for the detailed User’s Works with The Company which demonstrates how they will be progressing the User’s Works to achieve the Completion Date. | The User’s construction plan shall demonstrate how the User will be ready for the Commissioning Programme Commencement Date and Completion Date. This must include a detailed programme for the User’s Works with a fixed start and end date as agreed with the Relevant Transmission Licensee, and be a programme aligned with the Commissioning Programme Commencement | See table (varies with lead time) |
| Written confirmation |
|---|
| from the Relevant |
| Transmission |
| Licensee that design |
| obligations as |
| bilaterally agreed in |
| a User-Self Build |
| agreement have |
| been received. |
| Date and Completion Date. | |||
|---|---|---|---|
| Milestone 7) Project Commitment | This milestone demonstrates that the project has the necessary commitment or backing for it to proceed. | One of the following: • Binding contract issued by the User for main plant equipment; or • Capital contribution payments made to The Company in advance of connection; or • A decision paper from a formal, minuted meeting of the User’s board of directors evidencing Final Investment Decision (FID); or • award of a governmental or regulatory subsidy which provides financial support or incentive to the User’s project. | See table (varies with lead time) |
| Milestone 8) Project Construction | Project construction is the project phase ie the period from when a User begins the site works to carry out construction of its project until completion of the User’s Works | Commence construction according to the construction plan agreed under Milestone 6. Evidence for meeting this milestone will be a letter from the User’s board of directors or equivalent to state construction has commenced. | See table (varies with lead time) |
| Retained Distribution Milestone Names for consistency | From 0 up to | 2 up to 3 | 3 up to 4 | 4 up to 5 | |
| 5 years (1825 | |||||
| 2 years (0 – | years (730 – | years (1095 | years (1460 – | ||
| days) and | |||||
| 729 days) | 1094 days) | to 1459 days) | 1824 days) | ||
| above from | |||||
| from | from | from | from | ||
| contracted | |||||
| contracted | contracted | contracted | contracted | ||
| Completion | |||||
| Completion | Completion | Completion | Completion | ||
| date | |||||
| date | date | date | date | ||
| Milestones: | All durations for milestones other than M1 are calculated back from the | ||||
| contracted Completion Date | |||||
| Durations for M1 (unless M1 has already been met at the time of the Gate | |||||
| 2 Application) will be the earlier of (a) the date calculated forwards from | |||||
| the Gate 2 Offer date (based on an agreed standard time period for each | |||||
| planning type as referred to below) to move from M3 to M1) and (b) the | |||||
| date calculated back from the contracted Completion Date | |||||
| M1 - Initiate | |||||
| Planning | |||||
| Consent | 18 months | 24 months | 36 months | 48 months | |
| Bilaterally | |||||
| M2 - Secure | |||||
| negotiated | |||||
| Consent | |||||
| 12 months | 18 months | 24 months | 30 months | ||
| M3 - Land | |||||
| 21 months | 27 months | 39 months | 51 months | ||
| Rights |
| Retained |
|---|
| Distribution |
| Milestone |
| Names for |
| consistency |
| Planning / Technology Type | Timescale from Gate 2 Offer date to M1 |
|---|---|
| Town and Country Planning (England, Scotland and Wales) | 2 years |
| Section 36 (England/Scotland) | 3 years |
| Development of National Significance (Wales) | 3 years |
| NSIP / DCO (England and Wales) | 3 years |
| Offshore (including Offshore Wind, Interconnectors and OHAs) | 5 years |
| Nuclear | Case by Case |
| Novel technologies | Case by Case |
| Retained Distribution Milestone Names for consistency | From 0 up | 3 up to 4 | 5 years | ||||
| 2 up to 3 years | 4 up to 5 years | ||||||
| to 2 years | years (1095 to | (1825 days) | |||||
| (730 – 1094 | (1460 – 1824 | ||||||
| (0 – 729 | 1459 days) | and above | |||||
| days) from | days) from | ||||||
| days) from | from | from | |||||
| contracted | contracted | ||||||
| contracted | contracted | contracted | |||||
| Completion | Completion | ||||||
| Completion | Completion | Completion | |||||
| date | date | ||||||
| date | date | date | |||||
| Milestones: | All durations referenced back from contracted Completion Date | ||||||
| M5 - | |||||||
| Contestable | |||||||
| 12 months | 15 months | 18 months | 21 months | ||||
| Design Works | |||||||
| Submission | |||||||
| M6 - Agree | |||||||
| Bilaterally | |||||||
| Construction | 9 months | 12 months | 15 months | 18 months | |||
| negotiated | |||||||
| Plan | |||||||
| M7 - Project | |||||||
| 6 months | 9 months | 12 months | 15 months | ||||
| Commitment | |||||||
| M8 - Initiate | |||||||
| 3 months | 6 months | 9 months | 12 months | ||||
| Construction |
| Retained |
|---|
| Distribution |
| Milestone |
| Names for |
| consistency |
Project Milestone Communications
As soon as practicable and in any event by the due date for meeting a User Progression Milestone, the User shall document and provide the evidence in accordance with the table above of progress on a User Progression Milestone to prove to The Company’s reasonable satisfaction that that User Progression Milestone has been met.
The User will notify The Company and the Relevant Transmission Licensee, at the earliest opportunity, as soon as it becomes aware of any issues that could impact on the User’s ability to meet any of the User Progression Milestones and specifically of any that the User believes could fall under 16.5 below. Where the User believes that an issue could fall under 16.5 below evidence supporting this shall be provided to The Company.
The Company will upon receipt of evidence provided in accordance with 16.4.1 above, advise the User within 10 Business Days as to whether it is satisfied that the User Progression Milestone has been met and whether the status of the User’s project is categorised by The Company as “On Track” or “Termination”.
If no evidence is provided in accordance with 16.4.1 above, or the evidence provided is considered insufficient to demonstrate that the milestone has been met, and as a consequence the status of the User’s project is categorised as “Termination” The Company will notify the User that the User’s project is categorised as “Termination” and that the Project Milestone Remedy Period has started.
If during the Project Milestone Remedy Period the User’s project progresses such that it achieves the User Progression Milestone against which it was categorised as “Termination”, the User’s project shall be re-categorised by The Company as being “On Track” by reference to that User Progression Milestone and the User notified accordingly.
Where at the end of the Project Milestone Remedy Period for a Conditional Progression Milestone the status of the User’s project is still categorised as “Termination”, The Company shall terminate the Construction Agreement. Where at the end of the Project Milestone Remedy Period for a Construction Progression Milestone the status of the User’s project is still categorised as “Termination”, The Company may terminate the Construction Agreement.
Whether or not any of the User Progression Milestones have been achieved and/or what constitutes progress towards achieving them is a matter for the sole discretion of The Company.
The Company, the Relevant Transmission Licensee and the User shall constructively engage as required during the Project Milestone Remedy Period to understand whether the relevant User Progression Milestone can or is likely to be met and whether the issues in achieving the User Progression Milestone fall or are likely to fall under 16.5 below.
Ongoing compliance with the Conditional Progression Milestones
Having achieved a Conditional Progression Milestone the User shall notify The Company (or respond to The Company’s request for confirmation on this point) at the earliest opportunity in the event that it no longer meets or has reason to believe it will not continue to meet the requirements set out for that Conditional Progression Milestone.
In the event that the ongoing requirements of a Conditional Progression Milestone are no longer met, The Company will notify the User that the User’s project is categorised as “Termination” and the provisions of 16.4.5 to 16.4.8 shall apply.
Specific Provisions regarding Ongoing Compliance with the Original Red Line Boundary
The User shall be required to confirm at each User Progression Milestone that the User’s project meets the minimum acreage requirements as set out in the LoA Guidance i.e. that the land is equal to or greater than that provided for the technologies included in the Gate 2 Application.
The Original Red Line Boundary can only be changed as provided for in the Queue Management Guidance.
Subject to any changes in the Original Red Line Boundary provided for under the Queue Management Guidance, only 50% of whatever Installed Capacity is built within the Original Red Line Boundary can then be located outside of the Original Red Line Boundary.
A relaxation from the 50% requirement above is possible where this is justified and evidenced by the User in accordance with the Queue Management Guidance.
Exceptional Issues on User Progression Milestones There may be a small number of exceptional issues outwith the User’s control which may lead to User project delay and a User not being able to meet a User Progression Milestone. The Exceptional issues which apply in the context of the Queue Management Process are as follows: • Where the User is delayed in carrying out the User’s Works which entitles the User to fix a later date or dates under Clause 3.2 of the Construction Agreement (Delays and Force Majeure) and that delay is the reason that a User Progression Milestone is not met; • Where the User is not able to meet a User Progression Milestone due to an event of Force Majeure; • • Where a User is not able to meet a User Progression Milestone due to Planning appeals and third-party challenges in relation to the User’s Consents; • Any delay in the achievement of a milestone by the User which is caused by a Relevant Transmission Licensee or The Company • Where a User can demonstrate that a forward looking M1 would have a detrimental impact on developing their User’s project provided that any adjustment cannot be later than the backwards looking M1. Where the User believes an exceptional issue applies it shall provide written evidence to this effect supported by confirmation from the User’s board of directors or equivalent body for The Company’s consideration. Where a User’s project is not able or is considered unlikely to meet a User Progression Milestone, as a result of an exceptional issue under the headings here, and providing the User notifies The Company and the Relevant Transmission Licensee of the delay and reasons for the delay at the earliest opportunity and provides reasonable evidence to justify this and satisfies The Company that the specific delay falls under this Paragraph 16.5, such delay will not result in the User’s project being categorised as “termination” in relation to the relevant User Progression Milestone or User Progression Milestones. In such circumstances The Company will consequently issue a new milestone date for the missed milestone. Whether or not the exceptional issues as listed here apply and the period of any extension, is a matter for the sole discretion of The Company.
| Where delays caused by a party (other than the User, The |
|---|
| Company or a Relevant Transmission Licensee) can be |
| demonstrated to have an impact upon the User meeting a User |
| Progression Milestone and the User could not have avoided these |
| delays or their impact by the exercise of Good Industry Practice |
Implementation
The Queue Management Process will be:
included in any Construction Agreements (other than those which fall within Paragraph 16.2 above) offered as part of any new Connection Offers; and
introduced into any Construction Agreements (other than those which fall within Paragraph 16.2 above) which do not have the Queue Management Process already included within it) when a Modification Offer is made; and
introduced into any Existing CMP376 Construction Agreement which does not have the Queue Management Process already included within it through an Agreement to Vary that Existing CMP376 Construction Agreement in accordance with the process set out in Paragraph 16.6.3 in each case from the CMP376 Implementation Date.
Each User with an Existing CMP376 Construction Agreement shall be notified by The Company within:
ten Business Days of the CMP376 Implementation Date for an Existing Construction Agreement of a type in Paragraph 16.6.6 (c)(i) below; and
ten Business Days of the date of the Construction Agreement for an Existing Construction Agreement of a type in Paragraph 16.6.6 (c)(ii) below; and
in accordance with Paragraph 16.6.4 for an Existing Construction Agreement of a type in Paragraph 16.6.6 (c)(iii) and in each case such notice shall invite the User to make a Modification Application to incorporate the Queue Management Process into its Existing CMP 376 Construction Agreement.
Where a User with an Existing CMP376 Construction Agreement does not make a Modification Application within 6 months of being notified in accordance with Paragraph 16.6.2 or does not accept the Modification Offer made in response to the User’s Modification Application (and acknowledging that such offer may be disputed and referred to the Authority for determination) The Company shall issue the CMP376 Agreement to Vary to the User. The CMP376 Agreement to Vary shall be issued to the User as soon as practicable after the 6 months or failure to accept.
A User with a Construction Agreement (other than those which fall within Paragraph 16.2 above) where the Completion Date is on or before the date which is two years from the CMP376 Implementation Date will not have the Queue Management Process introduced into that Construction Agreement provided that the User’s project is progressing in accordance with and is reasonably aligned to the Construction Programme in that Construction Agreement. If The Company has reason to believe that that is not the case and the User has not been able to demonstrate that it is progressing to The Company’s reasonable satisfaction The Company shall notify the User that the Construction Agreement is to be treated as an Existing CMP376 Construction Agreement and the provisions of Paragraph 16.6.3 shall apply but with the reference to “within 6 months of being notified in accordance with Paragraph 16.6.2” being replaced with “2 months after the issue of such notice”.
In the case of Modification Offers, the Queue Management Process will be applied and Appendix Q created by reference to the Completion Date in the Modification Offer and the date on which the Modification Offer is made by The Company to the User. In the case of the CMP376 Agreement to Vary, the Queue Management Process will be applied and Appendix Q created by reference to the Completion Date in the Existing CMP 376 Construction Agreement and the date on which the CMP 376 Agreement to Vary is offered by The Company to the User.
In this Paragraph 16.6:
the term CMP376 Implementation Date shall mean the Implementation Date for CUSC Modification Proposal 376 (Inclusion of Queue Management Process within the CUSC); and
the term CMP376 Agreement to Vary shall mean the Agreement to Vary issued by The Company to the User in accordance with Paragraph 16.16.3 above introducing the Queue Management Process and Appendix Q into an Existing CMP376 Construction Agreement; and
the term Existing CMP376 Construction Agreement shall mean a Construction Agreement (other than those which fall within Paragraph 16.2 above) where the Works under that Construction Agreement are not completed at the CMP376 Implementation Date and:
the Construction Agreement is dated on or before the CMP376 Implementation Date and the Completion Date is after the date which is two years from the CMP376 Implementation Date; or
the Construction Agreement is the subject of an Offer made on or prior to the CMP376 Implementation Date, is dated after the CMP376 Implementation Date and the Completion Date is after the date which is two years from the CMP376 Implementation Date; or
the Construction Agreement has a Completion Date which is on or before the date which is two years from the CMP376 Implementation Date and where The Company has issued a notice to the User under Paragraph 16.6.4 above.
SECTION 17: GATED APPLICATION AND OFFER PROCESS
This Section explains the processes for making the applications and offers that fall under the Gated Application and Offer Process.
The Gated Application and Offer Process will first apply from the CMP434 Implementation Date and from the CMP434 Implementation Date applications and offers which fall under the Gated Application and Offer Process can only be made in accordance with the Gated Application and Offer Process.
CUSC contains processes for applications and offers and the Gated Application and Offer Process replaces those processes where the Applications are Gated Applications. As a consequence, where the Application is a Gated Application the Offer and Acceptance processes and timelines shall be replaced (as noted in the relevant CUSC Sections) with this Gated Application and Offer Process.
The Gated Application and Offer Process comprises of the following activities: • Gated Application Window • Gated Design Process • Offer The Gated Application and Offer Process will be undertaken in accordance with the Gated Timetable for a Gated Application Window and Offer Run.
Gated Applications After the CMP434 Implementation Date the following types of applications have to follow and offers can only be made in accordance with the Gated Application and Offer Process:
An application for a New Connection Site (including a Grid Supply Point). This includes an application for a New Connection Site where the New Connection Site is triggered by a Transmission Evaluation Application. This does not however include an application for such New Connection Site by an owner/operator of a Distribution System where the application is not triggered by Embedded Power Stations.
An application for a Bilateral Embedded Generation Agreement.
An application for a BELLA.
A Transmission Evaluation Application under CUSC Section 6 Paragraph 6.5.5.
An application (by Modification Application) for a Gate 2 Offer in respect of a Gate 1 Agreement.
A Modification Application (in addition to those referred to in Paragraph 17.5.4 and 17.5.5) to (a) any Gate 2 Agreements or (b) (any Gate 1 Agreements with Reservation (where the Modification Application is not requesting a Gate 2 Offer), which in either case is a Gated Modification Application and so has to follow the Gated Application and Offer Process.
Making a Gated Application
A Gated Application can be made at any time within the Gated Application Window.
In the case of a Transmission Evaluation Application, the application can be made after the closure of the Gate 2 Application Window on the basis that the owner/operator of the Distribution System will (a) within the 5 Business Days Period provide the basic information required to create construction planning assumptions and
within the 15 Business Days Period provide full technical data and the items referred to at Paragraph 17.7.3.2.
Gated Applications for a New Connection Site or applications for a BEGA for a Large Embedded Power Station or BELLA can, at the Applicant’s choice, be made on the basis of a Gate 1 Application or (initially or subsequently) a Gate 2 Application.
The owner/operator of the Distribution System will be notified by The Company as soon as reasonably practicable of the Gate 1 Application or Gate 2 Application for a BEGA or BELLA by Modification Notice.
A Gate 2 Application for a BEGA and BELLA can be made at any time but will not progress as a Gate 2 Application until and within the Gated Application Window in which the Distribution EG Related Application is made.
The owner/operator of the Distribution System will, subject to the requirements of Paragraph 17.6.8 having been met: a) use reasonable endeavours to submit the Distribution EG Related Application to The Company in the current or next available Gated Application Window after the notification to it by The Company of a Gate 2 Application by a Large Embedded Power Station for a BEGA or BELLA; and b) in all other cases, submit the Distribution EG Related Application to The Company by reference to a Gated Application Window in the period specified in Paragraph 17.6.2 where prior to or within that Gated Application Window a Relevant Embedded Power Station has notified the owner/operator of the Distribution System that it wants the owner/operator of the Distribution System to submit a Gate 2 Application and the owner/operator of the Distribution System considers that the Gate 2 Criteria for readiness has been met.
Embedded Power Stations should as soon as reasonably practicable notify the owner/operator of the Distribution System of their intention to make or their having made (in the case of Large Embedded Power Stations) a Gate 1 Application and/or (otherwise) a Gate 2 Application.
Embedded Power Stations should be aware that the owner/operator of the Distribution System will have its own requirements of them (including the Embedded Power Station having entered into an agreement for connection to and use of the Distribution System and paying any relevant fees) prior to the owner/operator of the Distribution System submitting the Distribution EG Related Application.
Other than as expressly noted above, a Gate 1 Application or Gate 2 Application can only be made in the Gated Application Window.
A subsequent Gate 2 Application in respect of Gate 1 Agreements can (except in case of Reservation which will be subject to the Gated Modification Guidance and other relevant guidance) include changes to the project from that as described in the Gate 1 Agreements.
Assessment of the Gated Applications
A Gated Application will need to be Competent. In the case of a Gate 2 Application for a BEGA or BELLA both that Gate 2 Application and the Distribution EG Related Application have to be Competent in the same Gated Application Window.
A Gate 1 Application for a New Connection Site, should also include, as appropriate, a Letter of Authority or a Letter of Acknowledgment.
A Gate 2 Application should also show and evidence readiness to proceed by: 17.7.3.1. in the case of a Gate 2 Application for a New Connection Site, BEGA for a Large Embedded Power Station or BELLA, including the Readiness Declaration and (except where the Gate 2 Criteria Methodology expressly provides otherwise) the Original Red Line Boundary (including the Installed Capacity). As these are provided by the Large Embedded Power Station in the case of a Gate 2 Application by a Large Embedded Power Station these are not required to be included in the Distribution EG Related Application;
in the case of a Gate 2 Application for a Distribution EG Related Application in respect of a (or more than one) Relevant Embedded Power Station (including where they have a BEGA), including the Readiness Declaration and Original Red Line Boundary (including the Installed Capacity) in respect of the (and if more than one each) Relevant Embedded Power Stations being those provided to the owner/operator of the Distribution System by the Relevant Embedded Power Station.
The Company will notify the User whether a Gate 1 Application is Competent and complies with Paragraph 17.7.2 as soon as reasonably practicable after receipt of the Gate 1 Application.
A Gate 2 Application will be checked and assessed by The Company against the Gate 2 Criteria.
The Company will notify the User (and also in the case of a Large Embedded Power Station, the owner/operator of the Distribution System) whether a Gate 2 Application is Competent and complies with (but always subject to Paragraphs 17.8 and 17.10 below) the Gate 2 Criteria such that it can enter the Gated Design Process as soon as reasonably practicable after receipt of the Gate 2 Application and in any event prior to the start of the Gated Design Process.
Any Gate 1 Application not notified accordingly by The Company under Paragraph 17.7.4 above will not receive a Gate 1 Offer. Any Gate 2 Application not notified accordingly by The Company under Paragraph 17.7.6 above will not be able to progress to the Gated Design Process in that Gated Application and Offer Process Run.
Where The Company is considering Reservation in respect of the Gate 1 Offer, The Company will advise the Gated Applicant as soon as reasonably practicable after receipt of the Gate 1 Application and that as a consequence the Gate 1 Offer may be provided later in the Gated Design Process, given the design process involved to confirm the Reservation. Reservation will only be provided for in a Gate 1 Offer where the User has indicated in the Gate 1 Application that it is happy for this to be considered and The Company has notified the Gated Applicant of this.
Installed Capacity The sum of the Installed Capacity provided within a Gate 2 Application and the capacity of any existing User's Equipment or Developer’s equipment at the same site, must be equal to or greater than the total Transmission Entry Capacity or Developer Capacity or directly connected Demand MWs (as applicable) which will outturn at the relevant Connection Site or site of connection of the Embedded Power Station (as applicable) as a consequence of the Gate 2 Application.
Gate 2 Criteria The Gate 2 Application must meet the Gate 2 Criteria. The Gate 2 Criteria, the process of evidencing and confirming that readiness has been met (and what is required for this) from a Gated Applicant is set out in the Gate 2 Criteria Methodology.
Ongoing Compliance with the Original Red Line Boundary There are also particular requirements and consequences for ongoing compliance with the Original Red Line Boundary and these are set out in Paragraph 16.4.9 of the Queue Management Process and the Original Red Line Boundary Reduction Clause.
Checking of the Readiness Declarations
Although a Gate 2 Application may be notified as able to progress to the Gated Design Process under Paragraph 17.7.6, during and as soon as reasonably practicable within the Gated Design Process further detailed checks of the readiness submissions will be undertaken as follows in accordance with the Gate 2 Criteria Methodology:
The Company shall use reasonable endeavours to undertake a more detailed check as set out in the Gate 2 Criteria Methodology on all (unless specified otherwise in the Gate 2 Criteria Methodology) the Readiness Declarations provided (other than where the Readiness Declaration is provided for a Relevant Embedded Power Station by the owner/operator of a Distribution System where it is expected that such owner/operator will use reasonable endeavours to undertake this detailed check).
Within 15 Business Days of the end of the Gated Design Process, The Company will publish on the Website the percentage of detailed checks which have been undertaken under Paragraph 17.10.1.1 as a percentage of the total of Gate 2 Applications which were Competent and met the Gate 2 Criteria for readiness for the purposes of entering that Gated Design Process. To facilitate and enable this, each owner/operator of a Distribution System shall within 10 Business Days of the end of the Gated Design Process provide the percentage of detailed checks it has undertaken for the purposes of Paragraph 17.10.1.1 as a percentage of the total of its Gate 2 Applications that entered the Gated Design Process.
The Company shall check the evidence provided in all the Readiness Declarations for duplications and overlaps. Where duplications and/or overlaps are identified in the Original Red Line Boundaries The Company will contact the relevant parties concerned. In the event that duplications and/or overlaps are identified the process relating to this in the Gate 2 Criteria Methodology will be applied to establish whether in those circumstances any (and if so which) Gate 2 Application has not met the Gate 2 Criteria.
Following the above The Company will notify the User (and in the case of a Large Embedded Power Station, the owner/operator of the Distribution System) whether the Gate 2 Application has fully met the Gate 2 Criteria (and where this is a Transmission Evaluation Application involving more than one Relevant Embedded Power Station whether all, none or which of the Relevant Embedded Power Stations have met the Gate 2 Criteria).
If the Gate 2 Criteria has been met The Company will confirm to the User that a Gate 2 Offer will be made.
If the Gate 2 Criteria has not been met The Company will confirm to the User (providing substantiated reasons why) that the Gate 2 Application has been rejected and that a Gate 2 Offer will not be made.
In the case of a Transmission Evaluation Application involving more than one Relevant Embedded Power Station, the Gate 2 Offer will only be progressed on the basis of the Relevant Embedded Power Stations (and MW) that have met the Gate 2 Criteria and the Gate 2 Application deemed to be amended accordingly.
The notifications under Paragraphs 17.10.2 to 17.10.4 will be given by The Company to the User as soon as reasonably practicable.
Gated Design Process The Gate 2 Applications assessed by The Company as meeting the Gate 2 Criteria will be processed in accordance with the Connections Network Design Methodology and the Project Designation Methodology.
Gate 1 Offer
A Gate 1 Offer shall be provided by The Company as soon as reasonably practicable within the Gated Design Process. Where a Gate 1 Offer includes Reservation that Gate 1 Offer will be provided later in the Gated Design Process, given the design involved, than one which does not include Reservation.
A Gate 1 Offer shall be provided in the CUSC form relevant to the Gated Application but will not have the full details in the Appendices and will include the Gate 1 Conditional Clause, the effect of which is to make all the rights and obligations conditional until a Gate 2 Offer is accepted. A connection location and date will be provided but only on an indicative basis and the connection date and location will only be confirmed (with all the other details) in a Gate 2 Offer following a Gate 2 Application.
There is an exception to Paragraph 17.12.2 where Reservation has been included. In that case, whilst the rights and obligations remain conditional, the connection date and connection location of, as appropriate, the Connection Site or Transmission Interface Site or site of Connection may be provided and identified in the Gate 1 Offer and any Gate 2 Offer will be made on the basis of these subject to a Gate 2 Offer being applied for and accepted by the Applicant in the timescales specified in the Gate 1 Offer.
Gate 2 Offer
Any Gate 2 Offers shall be provided by The Company, in the timescales for this set out in the Gated Timetable for that Gated Application Window and Offer Run.
A Gate 2 Offer shall be made in the CUSC form relevant to the Gated Application and provide a connection date and location and the Construction Works and Construction Programme in respect of this.
If the Gated Applicant has already accepted a Gate 1 Offer, the Gate 2 Offer will be a Modification Offer to, inter alia, remove the effect of the Gate 1 Conditional Clause and on acceptance the rights and obligations (including in respect of Cancellation Charges or Final Sums and the Queue Management Process) will apply.
Any dispute between The Company and the User as to whether the Gated Application is Competent, meets the requirements at Paragraphs 17.7.2 and 17.7.3 and/or conforms to the Gate 2 Criteria shall be treated as an Other Dispute in accordance with CUSC Section 7. End of Section 17
SECTION 18: GATED PROCESS FOR PROJECTS WITH EXISTING AGREEMENTS
This Section introduces and sets out the process by which (reflecting the changes implemented under CUSC CMP434 in respect of certain new types of applications) Existing Agreements for a Project will be given the status of Gate 1 Existing Agreements or Gate 2 Existing Agreements and amended to align the Existing Agreements for a Project with the approach applied to corresponding agreements in the Gated Application and Offer Process.
This Gated Process for Projects with Existing Agreements will apply from the CMP435 Implementation Date. The Gated Process for Projects with Existing Agreements is a one off exercise to address Existing Agreements. Once given the status of Gate 1 Existing Agreements or Gate 2 Existing Agreements and amended accordingly they will be treated as, as appropriate, Gate 1 Agreements or Gate 2 Agreements in terms of the ongoing processes, rights and obligations in CUSC (as modified on the implementation of CMP434).
The elements of the Gated Application and Offer Process will apply during this Gated Process for Projects with Existing Agreements where and to the extent expressly referred to in this Gated Process for Projects with Existing Agreements.
The Gated Process for Projects with Existing Agreements comprises of the following key activities: • An EA Request Window for submitting an EA Request (including reduction in Transmission Entry Capacity or Developer Capacity and request for Advancement) • Existing Agreements for a Project where a Gate 1 Notification is provided or an EA Request is not made within the EA Request Window will be given the status of Gate 1 Existing Agreements and Gate 1 ATVs issued • Assessment of an EA Request (to establish it is Effective) • EA Gated Design Process for those Projects who have submitted an EA Request which is Effective (such process will include checks of Readiness Declarations, assessment against Gate 2 Criteria and whether Advancement is available) • Existing Agreements for a Project given status of Gate 2 Existing Agreements following the EA Gated Design Process and issue of Gate 2 Modification Offers (including Advancement) The EA Timetable shall be published by The Company as soon as practicable and with prior notice of the start date of the EA Request Window.
Existing Agreements Agreements of the following types entered into between The Company and the User prior to EA Cut Off Date where the connection to and/or use of system or right for Embedded Power Stations to be Energised in each case provided for under these has not yet happened are Existing Agreements for the purposes of this Section 18.
A Bilateral Connection Agreement and the associated Construction Agreement for a New Connection Site (including a Grid Supply Point) with a directly connected User. This includes a Bilateral Connection Agreement and the associated Construction Agreement for a New Connection Site by an owner/operator of a Distribution System where the application is triggered by Embedded Power Stations but not where the application is not triggered by Embedded Power Stations.
A Bilateral Embedded Generation Agreement and the associated Construction Agreement regardless of the size of the Embedded Power Station.
A BELLA
A Bilateral Connection Agreement for an already connected/operational Project but where there is a variation to that Bilateral Connection Agreement and a Construction Agreement for a live/ongoing Modification (including in the case of Grid Supply Points any such Modification triggered by Embedded Power Stations).
A Bilateral Embedded Generation Agreement for an already operational Project but where there is a variation to that Bilateral Embedded Generation Agreement and a Construction Agreement for a live/ongoing Modification.
A BELLA for an already operational Project but where there is a variation to that BELLA for a live/ongoing Modification.
For the avoidance of doubt, a Bilateral Connection Agreement (or Modification or variation to it) with an owner/operator of a Distribution System and any associated Construction Agreement are not Existing Agreements where such agreements are not triggered by one or more Embedded Power Stations.
In order for the Existing Agreements that relate to one or more Projects to apply for the status of Gate 2 Existing Agreements in respect of such Projects a User must submit an EA Request in respect of the Existing Agreements for the applicable Project which is Effective within the EA Request Window.
Where an EA Request is not submitted within the EA Request Window, is not Effective, or a User sends a Gate 1 Notification during the EA Request Window, the Existing Agreements will be given the status of Gate 1 Existing Agreements and The Company will notify the User accordingly as soon as reasonably practicable and in any event prior to the start of the EA Gated Design Process and unless the User decides to terminate the Existing Agreements for a Project (in which case the current provisions regarding Cancellation Charge or Final Sums will apply) the Gate 1 ATV process below will be followed.
An EA Request can be submitted by a User in respect of a Project at any time within the EA Request Window. An EA Request can ask for Advancement but other than Advancement and as provided for at Paragraph 18.8.6 no other changes to the Existing Agreements can be requested through the EA Request.
An EA Request (other than one which is seeking Advancement or which is in respect of Transitional Agreements) shall be deemed to be a Modification Application but neither a Modification Application nor a fee for a Modification Application is required. In this case, the Readiness Declaration and Original Red Line Boundary (including the Installed Capacity) will constitute the EA Request.
An EA Request which is seeking Advancement or an EA Request in respect of Transitional Agreements will require both a Modification Application and a fee for the Modification Application. In this case, the Modification Application, the Readiness Declaration and Original Red Line Boundary (including the Installed Capacity) will constitute the EA Request.
To be Effective, an EA Request for Existing Agreements for a Project which has a BEGA and associated Construction Agreement for a Large Power Station or BELLA will also require that the owner/operator of the Distribution System submits an EA Request within the EA Request Window. In such case the corresponding EA Request submitted by a User in the category of the owner/operator of a Distribution System shall take the form of an acknowledgement of the EA Request submitted by the Embedded Power Station (including the request for Advancement and in the case of Advancement will require a Modification Application and fee).
An EA Request for Existing Agreements for a Project for a Relevant Embedded Power Station must be made by the owner/operator of the Distribution System to which the Relevant Embedded Power Station is to be connected. In such case, the EA Request will include the Readiness Declaration and Original Red Line Boundary (including the Installed Capacity) provided to the owner/operator of the Distribution System by the Relevant Embedded Power Station.
An EA Request can include notification of a reduction in Transmission Entry Capacity or Developer Capacity and where it does so such reduction will trigger payment of a Cancellation Charge in accordance with CUSC Section 15 or Final Sums.
Where the Existing Agreements for a Project provide for more than one stage of User’s Works within that overall Project or more than one technology type in the User’s Works within that overall Project or, in the case of new Grid Supply Points or Grid Supply Points which are the subject of a Modification triggered by Embedded Power Stations, the Existing Agreements refer to more than one Relevant Embedded Power Station and/or Embedded Large Power Station Project, the EA Request can be made in part by reference to the specific stage, technology or Embedded Power Station Project and the Existing Agreements amended as required to reflect this.
The Company will confirm whether an EA Request is (but always subject to Paragraphs 18.9 and 18.10 below) Effective for the purposes of entering the EA Gated Design Process as soon as reasonably practicable after receipt of the EA Request and in any event prior to the start of the EA Gated Design Process.
Gate 2 Criteria To be given the status of Gate 2 Existing Agreements the EA Request must meet the requirements of the Gate 2 Criteria. The Gate 2 Criteria, the process of evidencing and confirming that readiness has been met (and what is required of a User) in respect of this is set out in the Gate 2 Criteria Methodology.
Although an EA Request may be confirmed as Effective prior to the start of the EA Gated Design Process, during and as soon as reasonably practicable within the EA Gated Design Process further detailed checks of the readiness submissions will be undertaken as follows:
The Company shall use reasonable endeavours to undertake a more detailed check as set out in the Gate 2 Criteria Methodology on all the Readiness Declarations submitted in respect of Existing Agreements for a Project (other than where the Readiness Declaration is provided for a Relevant Embedded Power Station by the owner/operator of a Distribution System where it is expected that such owner/operator will use reasonable endeavours to undertake this detailed check).
Within 15 Business Days of the end of the EA Gated Design Process, The Company will publish on the Website the percentage of detailed checks which have been undertaken under Paragraph 18.10.1.1 as a percentage of the total of EA Requests which were Effective for the purposes of entering that EA Gated Design Process. To facilitate and enable this, each owner/operator of a Distribution System shall within 10 Business Days of the end of the EA Gated Design Process provide to The Company the percentage of detailed checks it has undertaken for the purposes of Paragraph 18.10.1.1 as a percentage of the total of its EA Requests that entered the EA Gated Design Process.
The Company shall check the evidence provided in all the Readiness Declarations submitted in respect of Existing Agreements for a Project for duplications and overlaps against any other Readiness Declarations submitted in respect of Existing Agreements for a Project. Where duplications or overlaps are identified in the Original Red Line Boundaries, The Company will contact the relevant parties concerned. In the event that duplications and/or overlaps are identified the process relating to this in the Gate 2 Criteria Methodology will be applied to establish whether in those circumstances any (and if so which) Project has not met the Gate 2 Criteria.
The Project will be assessed against the Gate 2 Criteria.
Following the above The Company will notify the User (and in the case where the Project is a Large Power Station, the owner/operator of the Distribution System) whether the EA Request has fully met the Gate 2 Criteria in respect of Existing Agreements for a Project. If the Gate 2 Criteria has been met The Company will confirm to the User that the Existing Agreements for a Project will be given the status of Gate 2 Existing Agreements. If the Gate 2 Criteria has not been met The Company will confirm to the User (providing substantiated reasons why) that the Existing Agreements for a Project will not be given the status of Gate 2 Existing Agreements and will be, as appropriate, given the status of Gate 1 Existing Agreements. Such notifications will be given by The Company to the User as soon as reasonably practicable. Where this is an EA Request by the owner/operator of a Distribution System relating to Existing Agreements relating to more than one Relevant Embedded Power Station the notification will confirm which (if any) of the Relevant Embedded Power Stations in the Existing Agreements have met the Gate 2 Criteria and only those will be given “Gate 2 Status” and the Existing Agreements processed on that basis.
Where a User has submitted an EA Request in respect of Existing Agreements for a Project and the EA Request meets the Gate 2 Criteria the EA Request will be processed in accordance with the Connections Network Design Methodology and the Project Designation Methodology.
A User which has requested Advancement for a Project in their EA Request will be accommodated where practicable and the User notified whether this can be accommodated or not where reasonably practicable prior to the issue of the Gate 2 Modification Offer. The Connections Network Design Methodology sets out the process for the management of requests for Advancement.
The outcome of the Gated Process for Projects with Existing Agreements is that the Existing Agreements for a Project are given the status of Gate 1 Existing Agreements or Gate 2 Existing Agreements as appropriate and amended by a Gate 1 ATV or a Gate 2 Modification Offer to reflect this.
Until given the status of Gate 1 Existing Agreements or Gate 2 Existing Agreements and, as appropriate, the Gate 1 ATV is entered into or Gate 2 Modification Offer is accepted the Existing Agreements for a Project will continue in accordance with their terms provided that any obligations on The Company to progress the Construction Works (including seeking Consents) in any Existing Agreements for (and in respect of) a Project given the status of Gate 1 Existing Agreements are deemed to have been waived by the User with effect from, as appropriate, the Gate 1 Notification or notification by The Company to the User under Paragraphs 18.7 or 18.10.2.
Once the Gate 1 ATV is entered into:
there will be no longer be any liability for payment of a Cancellation Charge or Final Sums under that Existing Agreement for that Project; and 18.12.3.2. any obligation to provide security under that Existing Agreement for that Project will cease, and as a consequence The Company shall as soon as reasonably practicable after and in any event within 6 weeks of the Gate 1 ATV being entered into, release and return any security arrangement held by The Company in respect of the same.
Where an EA Request was not submitted by a User within the EA Request Window or it was not Effective, a Gate 1 ATV for the Existing Agreements for that Project shall be issued by The Company as soon as reasonably practicable after the closure of the EA Request Window and in any event prior to the end of the EA Gated Design Process.
Where a Gate 1 Notification has been provided by a User, a Gate 1 ATV for the Existing Agreements for that Project shall be issued by The Company as soon as reasonably practicable after receipt of the Gate 1 Notification and in any event prior to the end of the EA Gated Design Process.
Where an EA Request was submitted by a User in respect of the Existing Agreements for a Project but the Gate 2 Criteria has not been met, a Gate 1 ATV for the Existing Agreements for that Project shall be issued by The Company as soon as reasonably practicable and in any event prior to the end of the EA Gated Design Process.
Where The Company is considering Reservation in respect of the Existing Agreements for a Project, The Company will advise the User as soon as reasonably practicable and in any event prior to the start of the EA Gated Design Process of this and that as a consequence the Gate 1 ATV may be provided later in the EA Gated Design Process, given the design process involved to confirm the Reservation. If the User is not interested in Reservation being considered it can advise The Company accordingly at this point otherwise the Gate 1 ATV will be progressed on the basis of Reservation. Reservation will only be provided for in a Gate 1 ATV where the User has been notified that The Company is considering Reservation and the User has confirmed it is interested in Reservation.
A Gate 1 ATV shall amend the Existing Agreements for a Project as required to align with the form and content of a CMP434 Gate 1 Agreement under the Gated Application and Offer Process being to (as appropriate) amongst other things:
include the Gate 1 Conditional Clause, the effect of which is to make all the rights and obligations under the Existing Agreements conditional until a Gate 2 Offer is accepted.
delete the content of all Appendices in the Existing Agreements other than to include a new or (where it already exists) a replacement Appendix in the Construction Agreement containing the User Data/Developer Data, and the indicative or Reserved connection date and location.
the connection location and date provided for in the Existing Agreements for a Project will remain as they currently are in the Existing Agreements but are now only provided (unless Reservation is applied) on an indicative basis and the connection date and location will only be confirmed (with all the other details) in any subsequent Gate 2 Offer following a Gate 2 Application under a Gated Application Window and Offer Run.
where Reservation is included, whilst the rights and obligations remain conditional, the connection date and connection location of, as appropriate, the Connection Site or Transmission Interface Site or site of Connection may be provided and identified in the Gate 1 ATV and any Gate 2 Offer will be made on the basis of these subject to a Gate 2 Offer being accepted by the Applicant in the timescales specified in the Gate 1 ATV.
the particular approach for Existing Agreements for a Project with owner/operators of Distribution Systems where triggered by Embedded Power Stations is addressed at Paragraph 18.16 below.
in the case of Existing Agreements for a Project where the User’s Works are staged or the Existing Agreements provide for more than one technology type in the User’s Works, and the EA Request is not submitted in respect of all of these and/or not all stages or technology types meet the Gate 2 Criteria the Existing Agreements for a Project will be adapted to reflect and achieve the intent of the Gate 1 Conditional Clause by reference to those stages/technology types that do not meet the Gate 2 Criteria and to provide the equivalent of a Gate 2 Agreement for those that do.
introduction of Original Red Line Boundary Reduction Clause.
The Variations Clause in the Existing Agreements requires The Company and the User to effect any amendment required to the Existing Agreements by the Authority as a result of a change in the CUSC. The changes proposed in the Gate 1 ATV are to implement the changes to Existing Agreements as a consequence of and to align with the implementation of CMP435.
The Gate 1 ATV should be signed and returned to The Company within the period as notified by The Company being not less than 4 weeks from issue or such later period as may be agreed between The Company and the User and if not signed and returned in this time period The Company will as provided for in the Variations Clause (and having first engaged with the User) sign on the User’s behalf.
Existing Agreements given the status of Gate 1 Existing Agreements do not have to provide a Letter of Authority or Letter of Acknowledgement.
Gate 2 Modification Offer
Where the Existing Agreements for a Project have been given the status of Gate 2 Existing Agreements, a Gate 2 Modification Offer shall be provided by The Company in respect of the Existing Agreements for a Project within the timescales specified for this in the EA Timetable.
A Gate 2 Modification Offer shall amend the Existing Agreements for a Project as required to align with the form and content of a CMP434 Gate 2 Agreement under the Gated Application and Offer Process being to amongst other things:
provide for any changes to the Existing Agreements for a Project to reflect Advancement (including and notwithstanding CUSC Section 16 which does not provide for User Progression Milestone dates to be brought forward, any changes to advance the User Progression Milestone dates to reflect the Advancement);
update Appendix Q (Queue Management Process - User Progression Milestones) to reflect the change in approach to the calculation of the User Progression Milestone date for M1 and add a new Appendix for User Data/Developer Data or update (if it exists) to include the Installed Capacity data;
provide for any changes to the Existing Agreements for a Project including Connection Site or Site of Connection, Construction Programme and Construction Works and changes as a consequence of this to reflect the outcome of the EA Gated Design Process.
A Gate 2 Modification Offer shall remain open for acceptance in accordance with CUSC Paragraph 6.9.
If a Gate 2 Modification Offer is not accepted by a User The Company will notify the User that the status given to the Existing Agreements for that Project has been changed to Gate 1 Existing Agreements and that a Gate 1 ATV will be issued by The Company to the User as soon as reasonably practicable and the provisions of Paragraph 18.13 above will apply.
Any dispute between The Company and the User as to whether the EA Request is Effective and/or the Gate 2 Criteria has been met shall be treated as an Other Dispute in accordance with CUSC Section 7.
This section is intended to clarify the position on what is to happen with the Existing Agreements for a Project with the owner/operator of a Distribution System which are triggered by Embedded Power Stations and the Existing Agreements for a Project with the Embedded Power Stations:
for Relevant Embedded Power Stations (where there is no BEGA) the Existing Agreements for a Project are only with the owner/operator of the Distribution System and the Existing Agreements can provide for one or more Relevant Embedded Power Stations;
for Embedded Power Stations (where there is a BEGA or BELLA) there are two sets of Existing Agreements for a Project, one set with the owner/operator of the Distribution System and one set with the owner/operator of the Embedded Power Station so the effect of this Gated Process for Projects with Existing Agreements on both sets of Existing Agreements has to be determined. The effect on the Existing Agreements for a Project in the circumstances where: a Gate 1 Notification is submitted within the EA Request Window by a Large Embedded Power Station, an EA Request is not submitted within the EA Request Window, the EA Request is not Effective or the Gate 2 Criteria is not met (and in the case where the Existing Agreements provide for more than one Embedded Power Station) is not the same for all the Embedded Power Stations.
As a consequence in the circumstances referred to in Paragraph 18.16.1:
in the case of Existing Agreements for a Project of the type at Paragraph 18.16.1.1 and save for Existing Agreements as provided for in Paragraph 18.16.2.3, the Existing Agreements for that Project will be treated, as agreed between The Company and the User as having either been terminated by the User or changed to be the equivalent of a Gate 1 Agreement. The termination or change to being the equivalent of a Gate 1 Agreement will be effective on, as appropriate, the day after (a) the closure of the EA Request Window or (b) notification that the Gate 2 Criteria has not been met under Paragraph 18.10.2. Such termination of or change in the Existing Agreements will not trigger payment of a Cancellation Charge in accordance with CUSC Section 15;
in the case of Existing Agreements for a Project of the type at Paragraph 18.16.1.2 but where the Relevant Embedded Power Station has a BEGA, the BEGA will also be treated, as agreed between The Company and the User, as having either been terminated by the User or changed to be the equivalent of a Gate 1 Agreement in the same circumstances and on the same basis as at Paragraph 18.16.2.1 above;
in the case of Existing Agreements for a Project of the type at Paragraph 18.16.1.1 where the Existing Agreements for a Project provide for more than one Relevant Embedded Power Station and/or Embedded Large Power Station but not all meet the Gate 2 Criteria, the Existing Agreements for a Project will be amended as required through the Gate 2 Modification Offer so as to remove any reference to any Relevant Embedded Power Station and/or Embedded Large Power Station for which an EA Request has not been made, an EA Request is not Effective or which do not meet the Gate 2 Criteria. Such amendment will not trigger payment of a Cancellation Charge in accordance with CUSC Section 15;
in the case of Existing Agreements for a Project of the type at Paragraph 18.16.1.2 (where the BEGA is with a Large Embedded Power Station) (a) the BEGA or BELLA will be offered a Gate 1 ATV and (b) the Existing Agreements with the owner/operator of the Distribution System will be treated, as agreed between The Company and the User, as having either been terminated by the User or changed to be the equivalent of a Gate 1 Agreement in the same circumstances and on the same basis as at Paragraph 18.16.2.1.
In the case of Existing Agreements for a Project of the type at Paragraph 18.16.1.2 in order to receive a Gate 2 Modification Offer and be given the status of Gate 2 Existing Agreements:
where the BEGA is with a Relevant Embedded Power Station, both the User with the BEGA and the owner/operator of the Distribution System will be offered and must accept the respective Gate 2 Modification Offer. Unless both Gate 2 Modification Offers are accepted, Paragraph 18.16.2.1 and 18.16.2 will apply;
where the BEGA is with a Large Embedded Power Station or there is a BELLA, (a) an EA Request must be made by both the party with the BEGA or BELLA and the owner/operator of the Distribution System (b) both these EA Requests must be Effective and the Project must meet the Gate 2 Criteria and (c) both the User with the BEGA or BELLA and the owner/operator of the Distribution System must accept the respective Gate 2 Modification Offer. Unless both Gate 2 Modification Offers are accepted, Paragraph 18.16.2.4 will apply.
A Large Embedded Power Station with a BEGA or BELLA should notify the owner/of the Distribution System as soon as reasonably practicable of its intention to make an EA Request and whether it is seeking Advancement.
Schedule 1
| Account Name | Trade Register Number | Account Registered Address | Category of use | CUSC Accession date |
|---|---|---|---|---|
| 24 POWER LTD | 12598609 | Victoria Court, 9 1 Huddersfield Road, Holmfirth , United Kingdom, HD9 3JA | Directly Connected Power Station | 17/05/2022 |
| 3R ENERGY SOLUTIONS LIMITED | SC354680 | 19 BUCCLEUCH STREET, LANARK , UNITED KINGDOM, TD9 0HL | Dormant CUSC Party; Embedded Power Station | 13/05/2015 |
| 548 UK INVESTMENT HOLDINGS LIMITED | 14400118 | 50 Broadway, London , United Kingdom, SW1H 0RG | Directly Connected Power Station | 05/05/2023 |
| A'CHRUACH WIND FARM LIMITED | 06572505 | CONNECT HOUSE, LONDON , UNITED KINGDOM, SW19 7JY | Directly Connected Power Station | 30/09/2014 |
| Aarhus Energy A/S | 44422778 | Søren Frichs Vej 38K, st. tv., Åbyhøj, Åbyhøj, Denmark, 8230 | Interconnector User | 09/05/2024 |
| ABBEY PROPERTIES CAMBRIDGESHIRE LIMITED | 03138929 | Nene Lodge, Funthams Lane, Whittlesey, Peterborough, Cambridgeshire, United Kingdom, PE7 2PB | Directly Connected Power Station | 05/12/2022 |
| ABBOTSHAUGH ENERGY STORAGE LIMITED | 13587232 | Unit 25.7 Coda Studios 1 89 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 23/03/2022 |
| ABEI ENERGY LIMITED | 11974488 | Orgin Workspace, B erkeley Square, Bristol , United Kingdom, BS8 1HP | Directly Connected Power Station | 01/04/2025 |
| ABERARDER WIND FARM LLP | OC398487 | No.1 Forbury Place, 43 Forbury Road,, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 15/05/2015 |
| ABERDEEN OFFSHORE WIND FARM LIMITED | SC278869 | 4 Jackson's Entry, Holyrood Road, Edinburgh , United Kingdom, EH8 8PJ | Directly Connected Power Station | 04/02/2016 |
| ABEREDW ENERGY PARK LIMITED | 12904601 | HODGE HOUSE, GUILDHALL PLACE, CARDIFF , UNITED KINGDOM, CF10 1DY | Embedded Power Station | 03/06/2021 |
| ABERGELLI POWER LIMITED | 08190497 | DRAX POWER STATION, SELBY , United Kingdom, YO8 8PH | Directly Connected Power Station | 21/09/2017 |
| ABERTHAW ENERGY LIMITED | 13334556 | THE ESTATES OFFICE, NEWPORT , United Kingdom, NP20 4PG | Directly Connected Power Station | 03/12/2021 |
| Aberthaw Green Limited | 12725483 | 17th Floor Hylo, 103-105 Bunhill Row, London , United Kingdom, EC1Y 8LZ | Directly Connected Power Station | 27/06/2024 |
| ACDC INFRASTRUCTURE LIMITED | 13672389 | 1 Bartholomew Lane, London , United Kingdom, EC2N 2AX | Non-Embedded Customer Site | 17/11/2022 |
| ACHLACHAN WIND FARM LLP | OC393612 | 1st Floor Midland House, 77 Huddersfield Road, Mirfield, West Yorkshire, United Kingdom, WF14 8BL | Embedded Exemptable Large Power Station | 18/12/2017 |
| ACKRON WIND FARM LTD | SC474066 | 1ST FLOOR, 1 WEST REGENT STREET, GLASGOW , United Kingdom, G2 1RW | Embedded Power Station | 29/04/2021 |
| ADELA ENERGY LTD | 11621670 | Strelley Hall M ain Street S trelley, Nottingham, Nottinghamshire, United Kingdom, NG8 6PE | Virtual Lead Party | 01/09/2020 |
| ADV 004 LIMITED | 12317010 | 70 Jermyn Street, London , United Kingdom, SW1Y 6NY | Embedded Power Station | 15/05/2023 |
| ADVANCED ELECTRICITY NETWORKS LIMITED | 14657793 | Nexus Park Avenue East, Skyline 120, Braintree, Essex, United Kingdom, CM77 7AL | Independent Distribution N/W Operator | 13/03/2024 |
| Advance Grid Solutions Limited | SC744757 | 4 Linnet Way, S trathclyde Business Park, Bellshill , United Kingdom, ML4 3RA | Directly Connected Power Station | 20/02/2024 |
| A Energi Vannkraft AS | NO882973972 | Kjøita 18, Kristiansand , Norway, 4630 | Interconnector User | 17/04/2025 |
| AEUK BATTERY PROJECT III LTD | 14431299 | Origin Workspace, 40 Berkeley Square, Bristol , United Kingdom, BS8 1HP | Directly Connected Power Station | 20/02/2025 |
| AEUK BATTERY PROJECT II LTD | 14421795 | Origin Workspace, 40 Berkeley Square, Bristol , United Kingdom, BS8 1HP | Directly Connected Power Station | 03/01/2025 |
| AEUK WIND PROJECT II LTD | 14990905 | Origin Workspace, 40 Berkeley Square, Bristol , United Kingdom, BS8 1HP | Directly Connected Power Station | 20/12/2024 |
| AFTON WIND FARM LIMITED | 10332231 | 60 MILTON GATE CHISWELL STREET, LONDON , United Kingdom, EC1Y 4AG | Directly Connected Power Station | 07/06/2017 |
| AGILE ENERGY RECOVERY (INVERURIE) LIMITED | SC487774 | 1 Marischal Square, Broad Street, Aberdeen , United Kingdom, AB10 1BL | Embedded Power Station | 31/03/2021 |
| Agratas Limited | 15069959 | 18 Grosvenor Place, London , United Kingdom, SW1X 7HS | Non-Embedded Customer Site | 19/10/2023 |
| AGR RENEWABLES LIMITED | 07647332 | 4th Floor Burlington Building, 19 Heddon Street, London , United Kingdom, W1B 4BG | Directly Connected Power Station | 26/10/2023 |
| AGR SOLAR 2 LIMITED | 12294992 | WHITE HART HOUSE HIGH STREET, OXTED , United Kingdom, RH8 0DT | Directly Connected Power Station | 06/01/2021 |
| AGR SOLAR 3 LIMITED | 12295197 | WHITE HART HOUSE HIGH STREET, OXTED , United Kingdom, RH8 0DT | Directly Connected Power Station | 06/01/2021 |
| AGR SOLAR 4 LIMITED | 12295056 | WHITE HART HOUSE HIGH STREET, OXTED , United Kingdom, RH8 0DT | Directly Connected Power Station | 06/01/2021 |
| AIK2A SUSTAINABLE ENERGY LTD | SC488512 | 13 Queen's Road, Aberdeen , United Kingdom, AB15 4YL | Directly Connected Power Station | 20/08/2019 |
| AIKENGALL COMMUNITY WIND COMPANY LIMITED | SC313596 | CALEDONIAN EXCHANGE, EDINBURGH , United Kingdom, EH3 8HE | Embedded Exemptable Large Power Station | 30/11/2007 |
| AIKENGALL II COMMUNITY WIND COMPANY LIMITED | SC457920 | CALEDONIAN EXCHANGE, Edinburgh , United Kingdom, EH3 8HE | Directly Connected Power Station | 20/08/2019 |
| AIRIES WINDFARM LIMITED | SC407954 | 13 QUEEN'S ROAD, ABERDEEN , United Kingdom, AB15 4YL | Directly Connected Power Station | 06/08/2014 |
| Akku Tealing Limited | SC758389 | Bowling Green Road, Cupar , United Kingdom, KY15 4HD | Directly Connected Power Station | 03/06/2024 |
| AL BOUM PHOTO LTD | 13057703 | 88 GRAYS INN ROAD, LONDON , United Kingdom, WC1X 8AA | Directly Connected Power Station | 19/01/2022 |
| ALBUSIA LTD | 15594668 | 2 Upperton Gardens, Eastbourne , United Kingdom, BN21 2AH | Directly Connected Power Station | 23/07/2024 |
| ALCEMI STORAGE DEVELOPMENTS 1 LIMITED | 12376951 | FIRST FLOOR WINSTON HOUSE, LONDON , United Kingdom, N3 1DH | Directly Connected Power Station | 23/05/2022 |
| Alcemi Storage Developments 23 Ltd | 14615636 | First Floor, Winston House, 349 Regents Park Road,, London , United Kingdom, N3 1DH | Directly Connected Power Station | 23/01/2024 |
| ALCEMI STORAGE DEVELOPMENTS 2 LIMITED | 12376960 | FIRST FLOOR WINSTON HOUSE, LONDON , United Kingdom, N3 1DH | Directly Connected Power Station | 11/08/2022 |
| ALCEMI STORAGE DEVELOPMENTS 3 LIMITED | 12376962 | FIRST FLOOR WINSTON HOUSE, LONDON , United Kingdom, N3 1DH | Directly Connected Power Station | 19/04/2021 |
| ALCEMI STORAGE DEVELOPMENTS 4 LIMITED | 12376965 | FIRST FLOOR WINSTON HOUSE, LONDON , United Kingdom, N3 1DH | Directly Connected Power Station | 15/03/2021 |
| ALCEMI STORAGE DEVELOPMENTS 5 LIMITED | 12376959 | FIRST FLOOR WINSTON HOUSE, LONDON , United Kingdom, N3 1DH | Directly Connected Power Station | 08/09/2021 |
| ALCEMI STORAGE DEVELOPMENTS 6 LIMITED | 13848257 | First Floor, Winston House, 349 Regents Park Road, London , United Kingdom, N3 1DH | Directly Connected Power Station | 17/06/2022 |
| ALCEMI STORAGE DEVELOPMENTS 8 LTD | 13848254 | First Floor, Winston House, 3 49 Regents Park Road, London , United Kingdom, N3 1DH | Directly Connected Power Station | 18/07/2023 |
| ALLIANDER N.V. | 34108286 | UTRECHTSEWEG 68, ARNHEM , Netherlands, 6812 AH | Interconnector User | 13/03/2008 |
| ALLT AN TUIR RENEWABLE ENERGY PARK LIMITED | SC705418 | c/o Womble Bond Dickinson (Uk) Llp, 2 Semple Street, Edinburgh , United Kingdom, EH3 8BL | Embedded Power Station | 08/06/2022 |
| Alpha Energy ApS | 42985449 | Hermodsvej 5B, Aabyhoj , Denmark, 8230 | Interconnector User | 22/08/2022 |
| ALPHATARAXIA EUROPIUM B.V. | 72270853 | JOOP GEESINKWEG 701, AMSTERDAM-DUIVENDRECHT , Netherlands, 1114 AB | Interconnector User | 03/06/2021 |
| ALPIQ SUISSE SA | CH550-0076169-3 | CHEMIN DE MORNEX 10, LAUSANNE , Switzerland, 1003 | Interconnector User | 14/07/2006 |
| Alverdiscott 10 Renewables Ltd | 14605063 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 30/11/2023 |
| AMAZON DATA SERVICES UK LIMITED | 09959151 | 1 PRINCIPAL PLACE, LONDON , UNITED KINGDOM, EC2A 2FA | Non-Embedded Customer Site | 31/07/2019 |
| Amersham 10 Renewables Limited | 15122671 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 22/11/2023 |
| AMINTH ENERGY LTD | 11049753 | Amp Technology Centre Advanced Manufacturing Park, Brunel Way, Rotherham , United Kingdom, S60 5WG | Interconnector Owner | 20/11/2018 |
| Ancleggan Limited | 12951231 | Biddlesgate Farm, Cranborne, Wimborne, Dorset, United Kingdom, BH21 5RS | Embedded Power Station | 25/09/2023 |
| ANDERSHAW WIND POWER LIMITED | 07886325 | 5th Floor, 20 Fenchurch Street, London , United Kingdom, EC3M 3BY | Embedded Power Station | 16/10/2013 |
| ANESCO LIMITED | 07443091 | The Green Easter Park Benyon Road, Reading, Bershire, UK, RG7 2PQ | Directly Connected Power Station | 07/03/2022 |
| ANGLO AMERICAN WOODSMITH LIMITED | 07251600 | 17 CHARTERHOUSE STREET, LONDON , United Kingdom, EC1N 6RA | Non-Embedded Customer Site | 17/09/2021 |
| ANGLO ENERGY STORAGE LTD | 13237697 | Unit 4, S hieling Court, Corby , United Kingdom, NN18 9QD | Directly Connected Power Station | 22/12/2022 |
| AN SUIDHE WIND FARM LIMITED | 05469552 | Windmill Hill Business Park, Whitehill Way, Swindon , United Kingdom, SN5 6PB | Directly Connected Power Station | 29/07/2005 |
| Apatura Battery Ltd | 13884355 | 3rd Floor 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Directly Connected Power Station | 03/07/2023 |
| Appin Wind Farm Limited | 12672772 | 19th Floor, 22 Bishopsgate, London , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 12/02/2024 |
| APPLEFORD 2 RENEWABLES LTD | 14915058 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 31/08/2023 |
| Appleford 7 Renewables Limited | 01491437 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 31/08/2023 |
| AQUIND LIMITED | 06681477 | 5 STRATFORD PLACE, LONDON , United Kingdom, W1C 1AX | Interconnector Owner | 01/06/2016 |
| ARBROATH LIMITED | 12142520 | C/O Gresham House Asset Management Limited5 New Street Square, London , EC4A 3TW | Embedded Power Station | 30/07/2020 |
| ARDAGH GLASS LIMITED | 00567801 | Headlands Lane, Knottingley, West Yorkshire, United Kingdom, WF11 0HP | Non-Embedded Customer Site | 05/12/2024 |
| Ardonald Renewables Limited | 15511410 | Willowpit Lane, Hilton, Derby, United Kingdom, DE65 5FN | Directly Connected Power Station | 27/06/2024 |
| ARENKO CLEANTECH LIMITED | 08831289 | Harmsworth House13-15 Bouverie Street, London, Greater London, United Kingdom, EC4Y 8DP | Directly Connected Power Station; Dormant CUSC Party | 13/02/2020 |
| ARISE AB | 556274-6726 | P.O. BOX: 808, HALMSTAD , Sweden, 301 18 | Directly Connected Power Station | 20/04/2022 |
| Arise Renewable Energy UK Limited | 13569939 | 78 York Street, London , United Kingdom, W1H 1DP | Directly Connected Power Station | 24/05/2023 |
| ARJO WIGGINS FINE PAPERS LIMITED | 00961440 | 2ND FLOOR 110 CANNON STREET, LONDON , United Kingdom, EC4N 6EU | Embedded Power Station | 02/03/2005 |
| Arkaig Hydrogen Plant Limited | SC759981 | 39 George Street, Edinburgh , United Kingdom, EH2 2HN | Non-Embedded Customer Site | 20/12/2023 |
| ARK ESTATES 1 LIMITED | 12104497 | Spring Park, Westwells Road, Corsham, Wiltshire, United Kingdom, SN13 9GB | Non-Embedded Customer Site | 16/04/2021 |
| ARK ESTATES 2 LIMITED | 12113969 | SPRING PARK, WESTWELLS ROAD, CORSHAM , United Kingdom, SN13 9GB | Directly Connected Power Station | 03/09/2019 |
| ARK ESTATES 3 LIMITED | 12777470 | SPRING PARK, WESTWELLS ROAD, CORSHAM , United Kingdom, SN13 9GB | Non-Embedded Customer Site | 12/05/2021 |
| ARLINGTON (GROUP SERVICES) LIMITED | 11545785 | 4 Kingdom Street, London , United Kingdom, W2 6BD | Directly Connected Power Station | 22/05/2023 |
| ARLINGTON ENERGY (DEVELOPMENT) LIMITED | 11867454 | 70 Jermyn Street, London , United Kingdom, SW1Y 6NY | Directly Connected Power Station | 25/04/2023 |
| ARL O09 LIMITED | 11113979 | 4TH FLOOR ABBEY HOUSE, B OOTH STREET, MANCHESTER , United Kingdom, M2 4AB | Embedded Power Station | 29/11/2019 |
| ARM Cedar Limited | 15507927 | 338 Euston Road, London , United Kingdom, NW1 3BG | Directly Connected Power Station | 24/12/2024 |
| Aros Commodities A/S | 43398288 | Skt. Clemens Torv 11, 1. sal. Arhaus C,, Arhaus , Denmark, DK8000 | Interconnector User | 25/03/2024 |
| Arosource ApS | 44372487 | Hack Kampmanns Plads 3, st. th, Aarhus C,, Aarhus, Aarhus, Denmark, 8000 | Interconnector User | 16/05/2024 |
| Arran View Storage Limited | 12479235 | Manor Court Yard, S tretton on the Fosse, Radstock , United Kingdom, BA3 4QF | Embedded Exemptable Large Power Station | 26/10/2023 |
| ARRESGILL ENERGY LIMITED | SC734816 | Muirhall Farm, Auchengray, Carnwath, Lanark, South Lanarkshire, United Kingdom, ML11 8LL | Directly Connected Power Station | 08/02/2023 |
| Arresgill Energy Storage 1 Limited | SC760928 | Muirhall Farm, Auchengray, Carnwath, Lanark, South Lanarkshire, United Kingdom, ML11 8LL | Directly Connected Power Station | 09/11/2023 |
| ARTFIELD FOREST WIND FARM LTD | 11756439 | 19th Floor 22 Bishopsgate, London , United Kingdom, EC2N 4BQ | Embedded Exemptable Large Power Station | 15/10/2019 |
| ARVEN OFFSHORE WIND FARM LIMITED | 14406699 | Shepherd And Wedderburn Llp Octagon Point5 Cheapside, London , United Kingdom, EC2V 6AA | Directly Connected Power Station | 25/10/2023 |
| ARVEN SOUTH LIMITED | 14306369 | c/o Shepherd And Wedderburn Llp, O ctagon Point, 5 Cheapside, London , United Kingdom, EC2V 6AA | Directly Connected Power Station | 29/07/2024 |
| ASHGREEN ENERGY FARM LIMITED | 10487668 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton Le Spring, Sunderland, United Kingdom, DH4 5RA | Directly Connected Power Station | 31/01/2020 |
| ASSEL VALLEY WIND ENERGY LIMITED | SC464714 | Beauly House, D ochfour Business Centre, Dochgarroch, Inverness , United Kingdom, IV3 8GY | Directly Connected Power Station | 01/07/2015 |
| ASTWOOD GREEN ENERGY LTD | 14496383 | The Goods Shed, Jubilee Way, Faversham, Kent, United Kingdom, ME13 8GD | Directly Connected Power Station | 30/01/2023 |
| ATLANTIC SUPERCONNECTION LLP | OC371296 | Purnells, Suite 4 Portfolio House, 3 Princes Street, Dorchester, Dorset, United Kingdom, DT1 1TP | Interconnector Owner | 29/03/2019 |
| Atlas Energy Designated Activity Company | 754439 | 32 Molesworth Street, Dublin, Dublin, Ireland, D02 Y512 | Interconnector User | 10/12/2024 |
| Auchnasavil Battery Storage Ltd | SC712813 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Directly Connected Power Station | 07/09/2022 |
| AUCHROBERT WIND ENERGY LIMITED | SC478613 | Beauly House, D ochfour Business Centre, Dochgarroch, Inverness , United Kingdom, IV3 8GY | Directly Connected Power Station | 13/07/2016 |
| Aukera Energy Limited | 13732955 | 1st Floor Sackville House, 143-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 07/02/2024 |
| AURORA FLOATING OFFSHORE WIND LIMITED | 12887867 | Chi An Lorell Sector 2, Aerohub Business Park, St. Mawgan, Newquay, United Kingdom, TR8 4RZ | Directly Connected Power Station | 27/01/2022 |
| Aurora Utilities Limited | 14668032 | 5th Floor, 25 Old Broad Street, London , United Kingdom, EC2N 1HN | Independent Distribution N/W Operator | 27/11/2024 |
| AW1 ENERGY STORAGE LIMITED | 12763409 | Uskmouth Power Station, W est Nash Road, Nash, Newport, United Kingdom, NP18 2BZ | Directly Connected Power Station | 22/03/2021 |
| AWEL Y MOR OFFSHORE WIND FARM LIMITED | 12270928 | Windmill Hill Business Park, Whitehill Way, Swindon , United Kingdom, SN5 6PB | Directly Connected Power Station | 03/09/2020 |
| AXLE ENERGY LIMITED | 14633671 | 113–115 Fonthill Road Finsbury Park, London, Greater London, United Kingdom, N4 3HH | Interconnector User | 23/05/2024 |
| Axpo Solutions AG | CHE-105.779.348 | Lerzenstrasse 10, Dietikon , Switzerland, 8953 | Interconnector User | 11/02/2015 |
| AXPO UK LIMITED | 06600942 | 155 FENCHURCH STREET, LONDON , United Kingdom, EC3M 6AL | Supplier | 12/11/2013 |
| AYRE OFFSHORE WIND FARM LIMITED | 13847599 | Ibex House, Baker Street, Weybridge, Surrey, United Kingdom, KT13 8AH | Directly Connected Power Station | 20/09/2022 |
| BAGLAN GENERATING LIMITED | 03689741 | 10 FLEET PLACE, LONDON , United Kingdom, EC4M 7QS | Directly Connected Power Station | 18/09/2001 |
| BAGLAN OPERATIONS LIMITED | 03882153 | 10 FLEET PLACE, LONDON , United Kingdom, EC4M 7QS | Directly Connected Power Station | 18/09/2001 |
| BAILLIE WINDFARM LIMITED | SC256692 | c/o Eversheds LLP, 3 -5 Melville Street, Edinburgh , United Kingdom, EH3 7PE | Embedded Power Station | 26/10/2005 |
| Balance Power Ltd | 09285621 | 27-28 Eastcastle Street, London , United Kingdom, W1W 8DH | Directly Connected Power Station | 20/03/2023 |
| Balance Power Projects Limited | 10564553 | 107 Mere Grange Business Park, St. Helens, Merseyside, United Kingdom, WA9 5GG | Directly Connected Power Station | 06/11/2023 |
| Balbougie Energy Centre II Limited | 13484500 | 141-145 Curtain Road, London , United Kingdom, EC2A 3BX | Embedded Power Station | 24/11/2022 |
| BALMEANACH WIND FARM LIMITED | SC671620 | 1st Floor, 50 Lothian Road, Edinburgh , United Kingdom, EH3 9BY | Embedded Exemptable Large Power Station | 22/04/2021 |
| BALNACRAIG BATTERY STORAGE LIMITED | SC725328 | Office 202 One Lochrin Square, 92-94 Fountainbridge, Edinburgh , United Kingdom, EH3 9QA | Embedded Exemptable Large Power Station | 04/01/2023 |
| BALWEN LIMITED | 12896619 | 19TH FLOOR 22 BISHOPSGATE, LONDON , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 15/06/2021 |
| BANC DU ENERGY PARK LIMITED | 12576992 | HODGE HOUSE, GUILDHALL PLACE, CARDIFF , United Kingdom, CF10 1DY | Embedded Power Station | 03/09/2021 |
| Banks Renewables (Bodinglee Wind Farm) Limited | 12857095 | Inkerman House, St. Johns Road,M eadowfield, Durham , United Kingdom, DH7 8XL | Directly Connected Power Station | 11/07/2022 |
| Banks Renewables (Lethans East Wind Farm) Limited | 08332209 | Inkerman House, S t. Johns Road, M eadowfield Industrial Estate, Durham , United Kingdom, DH7 8XL | Directly Connected Power Station | 19/04/2023 |
| BANKS RENEWABLES (LETHANS WIND FARM) LIMITED | 08217768 | Inkerman House, S t John's Road, M eadowfield, Durham , United Kingdom, DH7 8XL | Directly Connected Power Station | 16/10/2014 |
| BANKS RENEWABLES (MILL RIG WIND FARM) LIMITED | 08773091 | Inkerman House, S t John's Road, M eadowfield, Durham , United Kingdom, DH7 8XL | Dormant CUSC Party; Embedded Exemptable Large Power Station | 07/01/2020 |
| BARCLAYS BANK PLC | 01026167 | 1 CHURCHILL PLACE, LONDON, LONDON, United Kingdom, E14 5HP | Interconnector User | |
| BARKING POWER LIMITED | 02354681 | GUILDHALL, PO BOX 270, LONDON, LONDON, United Kingdom, EC2P 2EJ | Directly Connected Power Station; Dormant CUSC Party | 18/09/2001 |
| BARROW OFFSHORE WIND LIMITED | 04145993 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 12/05/2010 |
| BASINGSTOKE EAST 2 RENEWABLES LTD | 14914367 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 31/08/2023 |
| Basingstoke East 7 Renewables Ltd | 14914353 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 31/08/2023 |
| BayWa r.e. Energy Trading GmbH | HRB 238502 | Katharinenstraße 6, Leipzig , Germany, 04109 | Interconnector User | 31/07/2024 |
| BAYWA R.E. ENERGY TRADING UK LIMITED | 15405596 | 22 Chancery Lane, London , United Kingdom, WC2A 1LS | Interconnector User | 31/07/2024 |
| BAYWA R.E. UK LIMITED | 07538870 | 22 CHANCERY LANE, LONDON, LONDON, United Kingdom, WC2A 1LS | Directly Connected Power Station | 29/07/2020 |
| BB2 WIND FARM LIMITED | 12280775 | 19TH FLOOR 22 BISHOPSGATE, LONDON , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 25/08/2021 |
| BCM ENERGY | 813273554 | BOULEVARD JULES FAVRE, LYON 06 , France, 69006 | Interconnector User | 08/07/2021 |
| BD Energy A/S | DK43343122 | Mejlgade 47, 2, Aarhus C, Aarhus C, Denmark, 8000 | Interconnector User | 29/12/2023 |
| BEACON FEN ENERGY PARK LIMITED | 13347752 | Stirling Square, 5-7 Carlton Gardens, London , United Kingdom, SW1Y 5AD | Directly Connected Power Station | 17/07/2023 |
| Beacon Solar Limited | 15705695 | 12 Cathedral Road, Cardiff , United Kingdom, CF11 9LJ | Directly Connected Power Station | 28/03/2025 |
| BEARSDEN BESS LTD | 13912752 | Overross House, Ross Park, Ross-On-Wye , United Kingdom, HR9 7US | Directly Connected Power Station | 03/11/2023 |
| BEATRICE OFFSHORE WINDFARM LIMITED | SC350248 | Inveralmond House, 200 Dunkeld Road, Perth , United Kingdom, PH1 3AQ | Directly Connected Power Station | 14/02/2011 |
| BEAUFORT WIND LIMITED | 04712922 | Connect House, 133-137 Alexandra Road, W imbledon, London , United Kingdom, SW19 7JY | Embedded Power Station | 31/03/2005 |
| BEAW FIELD SHETLAND LIMITED | 07551084 | 19th Floor, 22 Bishopsgate, London , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 25/06/2016 |
| BEECHGREEN ENERGYFARM LIMITED | 11860483 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton Le Spring, Sunderland, United Kingdom, DH4 5RA | Directly Connected Power Station | 21/10/2019 |
| BEFERLEAH ENERGY PARK LIMITED | 15040447 | 1st Floor Sackville House, 143-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 22/09/2023 |
| BEINNEUN WIND FARM LTD | 07661372 | 33 HOLBORN, LONDON , United Kingdom, EC1N 2HT | Embedded Power Station | 29/01/2013 |
| BEN AKETIL WIND ENERGY LIMITED | SC254421 | Beauly House, D ochfour Business Centre, Dochgarroch, Inverness , United Kingdom, IV3 8GY | Embedded Exemptable Large Power Station | 29/06/2005 |
| Benbrack Wind Farm Limited | 12971043 | c/o Cms Cameron Mckenna Nabarro Olswang Llp, Cannon Place, 7 8 Cannon Street, London , United Kingdom, EC4N 6AF | Directly Connected Power Station | 16/02/2021 |
| BEN SCA WIND FARM LIMITED | SC587934 | c/o Ocean Winds UK Limited, 5th Floor, Atria 1, 144 Morrison Street, Edinburgh , United Kingdom, EH3 8EX | Embedded Exemptable Large Power Station | 13/05/2020 |
| Benthead Solar Limited | SC708803 | c/o Locogen Limited, 4 West Silvermills Lane, Edinburgh , United Kingdom, EH3 5BD | Embedded Power Station | 14/06/2022 |
| BERKSWELL ENERGY PARK LIMITED | 14376601 | 1st Floor Sackville House, 143-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 19/06/2023 |
| BERRY BURN WIND FARM LIMITED | 04511914 | 19TH FLOOR 22 BISHOPSGATE, LONDON , United Kingdom, EC2N 4BQ | Embedded Power Station | 30/06/2005 |
| BERRYHILL SOLAR FARM LIMITED | SC677678 | Wind 2 Office, 2 Walker Street, Edinburgh , United Kingdom, EH3 7LB | Embedded Exemptable Large Power Station | 21/09/2022 |
| BERWICK BANK A LIMITED | 07294493 | No.1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 06/02/2020 |
| Berwick Bank B Limited | 13884182 | No.1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 29/03/2023 |
| BERWICK BANK C LIMITED | 07294599 | No.1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 06/07/2020 |
| BERWICK RENEWABLES TX LIMITED | 15508573 | Badgers Farm, Willowpit Lane, H ilton, Derby , United Kingdom, DE65 5FN | Directly Connected Power Station | 02/05/2024 |
| BES COMMERCIAL ELECTRICITY LTD | 06882734 | PARKSIDE STAND, FLEETWOOD , United Kingdom, FY7 6TX | Supplier | |
| BESS HOLDCO 2 LIMITED | 10671242 | Burdett House15-16 Buckingham Street, London , WC2N 6DU | Virtual Lead Party | 11/11/2021 |
| BEXLEY GREEN ENERGY CENTRE LTD | 15346083 | Flat 81 Blake Tower, 2 Fann Street, London , United Kingdom, EC2Y 8AF | Directly Connected Power Station | 03/01/2025 |
| BGI TRADING LIMITED | 10971802 | 245 HAMMERSMITH ROAD, LONDON , United Kingdom, W6 8PW | Supplier | 14/01/2021 |
| BHP BILLITON MARKETING AG | CH-170.3.014.047-1 | JOECHLERWEG 2, BAAR, BAAR, Switzerland, 6340 | Interconnector User | 28/07/2003 |
| BIG BATTERY (FLATTERTON FARM) LIMITED | SC733684 | Third Floor, Suite 2, Ink Building, 24 Douglas Street, Glasgow , United Kingdom, G2 7NQ | Embedded Exemptable Large Power Station | 17/07/2024 |
| BIG BATTERY (LETHAM FARM) LIMITED | SC728715 | Third Floor, Suite 2, Ink Building, 24, Douglas Street, Glasgow , United Kingdom, G2 7NQ | Embedded Power Station | 01/01/2024 |
| BIG BATTERY (SHERIFF FAULDS FARM 1) LIMITED | SC722086 | Third Floor, Suite 2, Ink Building, 24, Douglas Street, Glasgow , United Kingdom, G2 7NQ | Embedded Exemptable Large Power Station | 15/01/2024 |
| Biggleswade 10 Renewables Limited | 15128288 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 22/11/2023 |
| BKW AG | CH-035.3.000.316-4 | VIKTORIAPLATZ 2, BERN , Switzerland, 3000 | Interconnector User | 07/01/2004 |
| BLACKCRAIG WIND FARM (SCOTLAND) LIMITED | SC493311 | Morton Fraser Quartermile Two, 5th Floor, 2 Lister Square, Edinburgh , United Kingdom, EH3 9GL | Directly Connected Power Station | 29/04/2015 |
| BLACKHILLOCK FLEXPOWER LTD | SC698712 | 272 BATH STREET, GLASGOW , United Kingdom, G2 4JR | Directly Connected Power Station | 21/12/2021 |
| Black Knowe Energy Limited | SC734817 | Muirhall Farm, Carnwath Auchengray, Lanark , United Kingdom, ML11 8LL | Directly Connected Power Station | 26/06/2023 |
| BLACKPARK ENERGY STORAGE LIMITED | SC595139 | c/o Foresight Group LLP, Clarence House, 1 33 George Street, Edinburgh , United Kingdom, EH2 4JS | Directly Connected Power Station | 19/04/2021 |
| BLAENCOTHI ENERGY PARK LIMITED | 13687872 | HODGE HOUSE GUILDHALL PLACE, CARDIFF , United Kingdom, CF10 1DY | Embedded Power Station | 19/10/2022 |
| BLAIRGOWRIE BESS LTD | 14761727 | The Factory, Whitchurch,, Ross-On-Wye, Herefordshire, United Kingdom, HR9 6D | Directly Connected Power Station | 29/09/2023 |
| BLARGHOUR WIND FARM LIMITED | 09171723 | 22-24 King Street, Maidenhead, Berkshire, United Kingdom, SL6 1EF | Directly Connected Power Station | 18/08/2020 |
| BLARY HILL ENERGY LIMITED | 09507308 | Beaufort Court, Egg Farm Lane, Kings Langley, Hertfordshire, United Kingdom, WD4 8LR | Directly Connected Power Station | 14/03/2019 |
| BLOXWICH ENERGY STORAGE LIMITED | 10884765 | c/o Gresham House Asset Management Limited, 5 New Street Square, London , United Kingdom, EC4A 3TW | Embedded Power Station | 12/09/2018 |
| BLUEBELL WIND FARM LIMITED | 11120093 | 16 West Borough, Wimborne, Dorset, United Kingdom, BH21 1NG | Directly Connected Power Station | 15/01/2019 |
| BLUEFIELD RENEWABLE DEVELOPMENTS LIMITED | 12642196 | 1st Floor 25 King Street, Bristol , United Kingdom, BS1 4PB | Directly Connected Power Station | 16/02/2024 |
| BLUEFLOAT ENERGY UK HOLDINGS LIMITED | 12955781 | ONE GLASS WHARF, BRISTOL , United Kingdom, BS2 0ZX | Directly Connected Power Station | 22/04/2021 |
| Blue Gem Wind Limited | 11116383 | Bridge Innovation Centre, Pembrokeshire Science & Technology Park, Pembroke Dock, , United Kingdom, SA72 6UN | Directly Connected Power Station | 18/03/2020 |
| BLUEGRIDPOWER LTD | 10512978 | Suite 1 3rd Floor, 11-12, St James’s Square, London , United Kingdom, SW1Y 4LB | Non-Embedded Customer Site | 21/08/2020 |
| BLUE PLANET SOLAR LIMITED | 12326987 | 2 Crossways Business Centre, Bicester Road, Kingswood, Aylesbury, United Kingdom, HP18 0RA | Directly Connected Power Station | 22/10/2021 |
| Bluestone Energy Ltd | 11673645 | 35th Floor (Leaf B) Tower 42, 25 Old Broad Street, London , United Kingdom, EC2N 1HQ | Embedded Power Station | 19/04/2023 |
| BNP PARIBAS | FC013447 | 10 Harewood Avenue, London , United Kingdom, NW1 6AA | Interconnector User | 29/11/2023 |
| BNP PARIBAS DEPOSITARY SERVICES LIMITED | 14168 | IFC 1 THE ESPLANADE, SAINT HELIER , Jersey (United Kingdom), JE1 4BP | Non-Embedded Customer Site | 24/10/2023 |
| BNRG ALBION LIMITED | 12634537 | 3rd Floor, Norvin House, 45-55 Commercial Street, London , United Kingdom, E1 6BD | Directly Connected Power Station | 07/06/2023 |
| BNRG LANGMEAD LIMITED | 09355380 | Ham Farm;Main Road, Bosham , PO18 8EH | Directly Connected Power Station | 24/01/2024 |
| BOAT OF GARTEN BESS LIMITED | 13564582 | 1st Floor Midland House, 77 Huddersfield Road, Mirfield, West Yorkshire, United Kingdom, WF14 8BL | Embedded Exemptable Large Power Station | 28/10/2021 |
| BOC LIMITED | 00337663 | Forge, 43 Church Street West, Woking, Surrey, United Kingdom, GU21 6HT | Non-Embedded Customer Site | 18/09/2001 |
| Bodelwyddan Solar & Energy Storage Limited | 13307064 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 21/12/2021 |
| BOOM DEVELOPMENTS LTD | 12488646 | Unit 5e Park Farm, Chichester Road, Arundel, West Sussex, United Kingdom, BN18 0AG | Embedded Power Station | 12/04/2022 |
| BOOM POWER LTD | 12254340 | Unit 5e Park Farm, Chichester Road, Arundel, West Sussex, United Kingdom, BN18 0AG | Directly Connected Power Station | 12/11/2021 |
| BORALEX LIMITED | 04732465 | 16 WEST BOROUGH, WIMBORNE , United Kingdom, BH21 1NG | Directly Connected Power Station | 23/03/2006 |
| BORD GAIS ENERGY LIMITED | 463078 | 1 WARRINGTON PLACE, DUBLIN, DUBLIN, IRELAND, 2 | Interconnector User | 31/05/2014 |
| BORELAND ENERGY LTD | SC743486 | Boreland, Glen Lochay, Killin, Perthshire, United Kingdom, FK21 8TT | Directly Connected Power Station | 05/09/2024 |
| BOTLEY GREEN ENERGY CENTRE LTD | 14437740 | Flat 81 Blake Tower, 2 Fann Street, London , United Kingdom, EC2Y 8AF | Directly Connected Power Station | 04/12/2024 |
| BOULFRUICH WIND FARM LIMITED | SC171876 | Boulfruich, Houstry, Dunbeath, Caithness, United Kingdom, KW6 6EN | Embedded Power Station | 23/05/2005 |
| BOWDUN OFFSHORE WIND FARM LIMITED | 13847868 | Ibex House, Baker Street,, Weybridge, Surrey, United Kingdom, KT13 8AH | Directly Connected Power Station | 16/09/2022 |
| BOYNDIE WIND ENERGY LIMITED | SC242760 | Beauly House, Dochfour Business Centre, Dochgarroch, Inverness, United Kingdom, IV3 8GY | Embedded Power Station | 01/07/2005 |
| BP ALTERNATIVE ENERGY INVESTMENTS LIMITED | 05998019 | Chertsey Road, Sunbury On Thames, Middlesex, United Kingdom, TW16 7BP | Directly Connected Power Station | 06/05/2021 |
| BP GAS MARKETING LIMITED | 00908982 | Chertsey Road, Sunbury On Thames, Middlesex, UK, TW16 7BP | Interconnector User; Supplier | 17/04/2019 |
| BP NORTH EAST OFFSHORE WIND LIMITED | 14789320 | Chertsey Road, Sunbury-on-Thames , United Kingdom, TW16 7BP | Embedded Power Station | 12/12/2024 |
| BPUWL 29 LIMITED | 14917678 | Second Floor Hanover House, 47 Corn Street, Bristol , United Kingdom, BS1 1HT | Embedded Power Station | 25/09/2024 |
| BRACO ENERGY STORAGE LIMITED | 12614452 | c/o Foresight Group Llp, T he Shard, 32 London Bridge Street, London , United Kingdom, SE1 9SG | Embedded Power Station | 15/09/2020 |
| Braco West BESS Limited | 13706145 | 1st Floor Midland House, 77 Huddersfield Road, Mirfield, West Yorkshire, United Kingdom, WF14 8BL | Embedded Exemptable Large Power Station | 19/11/2021 |
| BRADWELL POWER GENERATION COMPANY LIMITED | 09941394 | 5th Floor Rex House, 4-12 Lower Regent Street, London , United Kingdom, SW1Y 4PE | Directly Connected Power Station; Dormant CUSC Party | 30/01/2017 |
| BRAEMORE WOOD WINDFARM LIMITED | 04599450 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton Le Spring, Sunderland, United Kingdom, DH4 5RA | Dormant CUSC Party; Embedded Exemptable Large Power Station | 04/06/2015 |
| BRAES OF DOUNE WIND FARM (SCOTLAND) LIMITED | SC255020 | Dla Piper Scotland Llp, Collins House, Rutland Square, Edinburgh , United Kingdom, EH1 2AA | Embedded Power Station | 08/12/2005 |
| BRAIDFIELD BATTERY STORAGE LIMITED | SC717244 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Directly Connected Power Station | 27/03/2023 |
| Braintree 10 Renewables Limited | 15125518 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 22/11/2023 |
| BRAMFORD 2 GREEN ENERGY CENTRE LTD | 14437476 | 81 Blake Tower, 2 Fann Street, London , United Kingdom, EC2Y 8AF | Directly Connected Power Station | 09/12/2024 |
| BRAMFORD GREEN ENERGY CENTRE LTD | 14433788 | Flat 81 Blake Tower, 2 Fann Street, London , United Kingdom, EC2Y 8AF | Directly Connected Power Station | 04/12/2024 |
| BRAMFORD GREEN LIMITED | 12516896 | Ropemaker Place, 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 24/07/2020 |
| BRAMLEY 2 RENEWABLES LTD | 14915202 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 31/08/2023 |
| BRAMLEY 7 RENEWABLES LTD | 14915277 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 31/08/2023 |
| BRAMLEY BESS LIMITED | 12295046 | WHITE HART HOUSE HIGH STREET, OXTED , United Kingdom, RH8 0DT | Directly Connected Power Station | 06/01/2021 |
| BRAXBESS LTD | 14573446 | 7 Furze Hill House, Furze Hill, Hove , United Kingdom, BN3 1PU | Directly Connected Power Station | 20/01/2023 |
| BREESEA LIMITED | 07883217 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 19/06/2015 |
| BRIDGWATER GREEN LIMITED | 12516809 | Ropemaker Place, 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 24/07/2020 |
| BRITISH GAS TRADING LIMITED | 03078711 | Millstream, Maidenhead Road, Windsor, Berkshire, United Kingdom, SL4 5GD | Supplier | 18/09/2001 |
| BRITNED DEVELOPMENT LIMITED | 04251409 | 1-3 STRAND, LONDON , United Kingdom, WC2N 5EH | Interconnector Owner | 16/02/2002 |
| BRIXTON (HEATHROW ESTATE) LIMITED | 04523673 | 1 NEW BURLINGTON PLACE, LONDON , United Kingdom, W1S 2HR | Non-Embedded Customer Site | 24/10/2022 |
| Broadclyst Energy Storage Limited | 13307080 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 06/01/2022 |
| BROADHAVEN DISTRIBUTION LIMITED | 11239800 | 27-28 EASTCASTLE STREET, LONDON , United Kingdom, W1W 8DH | Embedded Exemptable Large Power Station | 14/09/2016 |
| BROCKLOCH RIG WINDFARM LIMITED | SC149100 | c/o Harper Macleod Llp, T he Cadoro, 45 Gordon Street, Glasgow , United Kingdom, G1 3PE | Directly Connected Power Station | 11/04/2006 |
| BROCKWELL ENERGY LIMITED | SC560225 | The Eagle Building-Third Floor, 19 Rose Street, Edinburgh , United Kingdom, EH2 2PR | Directly Connected Power Station | 01/09/2020 |
| BROCKWELL STORAGE & SOLAR LIMITED | 09819652 | 16 Stratford Place, London , United Kingdom, W1C 1BF | Directly Connected Power Station | 14/04/2021 |
| BROKEN CROSS WIND FARM LIMITED | SC579904 | Ground Floor West Suite Prospect House, 5 Thistle Street, Edinburgh , United Kingdom, EH2 1DF | Directly Connected Power Station | 25/10/2018 |
| BROOK GREEN TRADING LIMITED | 09523064 | 80 HAMMERSMITH ROAD, LONDON , United Kingdom, W14 8UD | Supplier | 09/09/2016 |
| BROWNIELEYS RENEWABLES LLP | SO303878 | MUIRDEN FARM MUIRDEN, TURRIFF , United Kingdom, AB53 4NH | Directly Connected Power Station | 04/05/2016 |
| BRUTON ONE BESS LIMITED | 13935958 | 31 City Business Centre, Hyde Street, Winchester, Hampshire, United Kingdom, SO23 7TA | Directly Connected Power Station | 24/01/2024 |
| BRYN GILWERN ENERGY PARK LIMITED | 13052399 | HODGE HOUSE, GUILDHALL PLACE, CARDIFF , United Kingdom, CF10 1DY | Embedded Power Station | 03/06/2021 |
| Bryn Glas Energy Park Limited | 13686094 | Hodge House, Guildhall Place, Cardiff , United Kingdom, CF10 1DY | Embedded Power Station | 19/10/2022 |
| BRYNGWYN ENERGY PARK LIMITED | 13688038 | HODGE HOUSE, GUILDHALL PLACE, CARDIFF , United Kingdom, CF10 1DY | Embedded Power Station | 19/10/2022 |
| BRYT ENERGY LIMITED | 10167351 | 1 Victoria Squarenull, Birmingham , B1 1BD | Supplier | 21/12/2016 |
| BSR APPLICATIONS LIMITED | 08264822 | 35 And 35a The Maltings, Lower Charlton Trading Estate, Shepton Mallet, Somerset, United Kingdom, BA4 5QE | Directly Connected Power Station; Embedded Exemptable Large Power Station | 19/11/2024 |
| BUCCLEUCH ESTATES, LTD. (THE) | SC012615 | BUCCLEUCH WEATHERHOUSE, BOWHILL, SELKIRK, UNITED KINGDOM, TD7 5ES | Directly Connected Power Station | 03/06/2024 |
| BUCHAN OFFSHORE WIND LIMITED | SC719636 | Suite 3b, 58 Waterloo Street, Glasgow , United Kingdom, G2 7DA | Directly Connected Power Station | 18/09/2023 |
| BUK23 Limited | SC758698 | Ground Floor West Suite, Prospect House, 5 Thistle Street, Edinburgh , United Kingdom, EH2 1DF | Directly Connected Power Station | 20/12/2023 |
| BUNTINGTON GREEN ENERGY CENTRE LTD | 14438293 | 81 Blake Tower, 2 Fann Street, London , United Kingdom, EC27 8AF | Directly Connected Power Station | 21/09/2023 |
| BURBO EXTENSION LTD | 07307131 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 10/03/2011 |
| Burwell 11 Solar Limited | 11884312 | 6th Floor, 33 Holborn, London, London, United Kingdom, EC1N 2HT | Directly Connected Power Station | 07/11/2019 |
| Bushbury 10 Renewables Limited | 15125508 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 22/11/2023 |
| BUSINESS POWER AND GAS LIMITED | 09523024 | Jubilee House, E ast Beach, Lytham St. Annes, , United Kingdom, FY8 5FT | Supplier | 07/04/2016 |
| Bute Hydrogen Project 1 Limited | 15078056 | The Broadgate Tower, Third Floor, 2 0 Primrose Street, London , United Kingdom, EC2A 2RS | Directly Connected Power Station | 11/01/2024 |
| Bute Hydrogen Project 2 Limited | 15077939 | The Broadgate Tower. Third Floor, 2 0 Primrose Street, London , United Kingdom, EC2A 2RS | Directly Connected Power Station | 11/01/2024 |
| BUTE HYDROGEN PROJECT 3 LIMITED | 15078022 | The Broadgate Tower, Third Floor, 2 0 Primrose Street, London , United Kingdom, EC2A 2RS | Directly Connected Power Station | 11/01/2024 |
| BUTE HYDROGEN PROJECT 4 LIMITED | 15078071 | The Broadgate Tower, Third Floor, 2 0 Primrose Street, London , United Kingdom, EC2A 2RS | Directly Connected Power Station | 11/01/2024 |
| BUTE HYDROGEN PROJECT 5 LIMITED | 15078097 | The Broadgate Tower, Third Floor, 2 0 Primrose Street, London , United Kingdom, EC2A 2RS | Directly Connected Power Station | 11/01/2024 |
| Bute Hydrogen Project 6 Limited | 15078180 | The Broadgate Tower. Third Floor, 2 0 Primrose Street, London , United Kingdom, EC2A 2RS | Directly Connected Power Station | 11/01/2024 |
| Bute Hydrogen Project 7 Limited | 15078238 | The Broadgate Tower Third Floor, 20 Primrose Street, London , United Kingdom, EC2A 2RS | Directly Connected Power Station | 11/01/2024 |
| BW ESS DEVELOPMENT UK LIMITED | 11122632 | Office 10, Wingate Business Exchange, Wingate Square, London , United Kingdom, SW4 0AF | Directly Connected Power Station | 15/02/2022 |
| C.GEN KILLINGHOLME LIMITED | 06422434 | 130 Shaftesbury Avenue, 2nd Floor, London , United Kingdom, W1D 5EU | Directly Connected Power Station | 30/04/2013 |
| C & S ENERGY LIMITED | 13272189 | 73 Maygrove Road, London , United Kingdom, NW6 2EG | Directly Connected Power Station | 21/09/2021 |
| C A COMMODITIES A/S | 41338741 | KANNIKEGADE 16 A, 02, AARHUS C , Denmark, 8000 | Interconnector User | 22/03/2022 |
| CALDERDALE WIND FARM LTD | 13200694 | C/O Enshore Subsea Limited Port Of Blyth;South Harbour, Blyth , NE24 3PB | Directly Connected Power Station | 17/09/2024 |
| CALDER WATER COMMUNITY WIND CO LTD | SC412643 | Caledonian Exchange, 19a Canning Street, Edinburgh , United Kingdom, EH3 8HE | Embedded Exemptable Large Power Station | 07/11/2013 |
| CALEDONIA OFFSHORE WIND FARM LIMITED | 13844888 | Shepherd And Wedderburn Llp Octagon Point, 5 Cheapside, London , United Kingdom, EC2V 6AA | Directly Connected Power Station | 12/06/2023 |
| CAMBRIDGE POWER LIMITED | 12481022 | Salisbury House, S tation Road, Cambridge , United Kingdom, CB1 2LA | Directly Connected Power Station | 05/07/2022 |
| CAM CAPITAL LIMITED | 07612329 | 64 NEW CAVENDISH STREET, LONDON , United Kingdom, W1G 8TB | Directly Connected Power Station | 19/08/2020 |
| Canterbury North 10 Renewables Limited | 15125499 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 22/11/2023 |
| CAPBAL LIMITED | SC519076 | 29 RUTLAND SQUARE, EDINBURGH , United Kingdom, EH1 2BW | Dormant CUSC Party; Embedded Power Station | 04/12/2018 |
| CAPELLA BESS LTD | 13115768 | Beaufort Court Egg Farm LaneOff Station Road, Kings Langley, Hertfordshire , WD4 8LR | Directly Connected Power Station | 07/03/2025 |
| CAPTURED CARBON LIMITED | 497694 | 3rd Floor, 1-3 The Green, Malahide, Co.Dublin, Ireland, K36 KC44 | Interconnector User | 03/08/2015 |
| CARBON FREE 2030 ENERGY LIMITED | 14057298 | 2 Crossways Business Centre, Bicester Road, Kingswood, Aylesbury, United Kingdom, HP18 0RA | Directly Connected Power Station | 31/01/2023 |
| CAR DUIBH WIND FARM LIMITED | 12820057 | 19th Floor, 22 Bishopsgate, London , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 20/02/2025 |
| CARE POWER (BARNSLEY) LIMITED | 10042216 | Prennau House, C opse Walk, Pontprennau, Cardiff, United Kingdom, CF23 8XH | Embedded Power Station | 13/06/2022 |
| CARE POWER (BROOK FARM) LIMITED | 10780034 | Prennau House, C opse Walk, Pontprennau, Cardiff , CF23 8XH | Embedded Power Station | 21/11/2022 |
| CARE POWER (BURWELL 1) LIMITED | 11110483 | Prennau House, C opse Walk, Pontprennau, Cardiff, United Kingdom, CF23 8XH | Embedded Power Station | 31/08/2021 |
| CARE POWER (NEWTONWOOD) LIMITED | 11257609 | Prennau House, C opse Walk, Pontprennau, Cardiff, United Kingdom, CF23 8XH | Embedded Power Station | 18/12/2023 |
| CARGILL PLC | 01387437 | Velocity V1, Brooklands Drive, Weybridge, Surrey, United Kingdom, KT13 0SL | Interconnector User | 06/09/2004 |
| CARLTON POWER LIMITED | 08833435 | 26 Ellerbeck Court, Stokesley, Middlesbrough, United Kingdom, TS9 5PT | Directly Connected Power Station | 30/10/2022 |
| CARMARTHEN BESS LIMITED | 15206371 | Hodge House, Guildhall Place, Cardiff , United Kingdom, CF10 1DY | Directly Connected Power Station | 09/01/2024 |
| Carnegie (BES) Ltd | 12864991 | Princes House Suite 2a 3 8 Jermyn Street, London , United Kingdom, SW1Y 6DN | Directly Connected Power Station | 10/11/2022 |
| CARRAVINDOON LIMITED | 12710427 | Biddlesgate Farm, Cranborne, Wimborne, United Kingdom, BH21 5RS | Embedded Power Station | 08/07/2022 |
| CARRINGTON POWER LIMITED | 04706728 | 132 Manchester Road, Carrington, Manchester, United Kingdom, M31 4AY | Directly Connected Power Station | 25/04/2008 |
| Carrington Storage Limited | 06711448 | 4th Floor, 80 Victoria Street, London , United Kingdom, SW1E 5JL | Directly Connected Power Station | 18/05/2009 |
| Carrog Storage Facility Limited | 14197726 | Unit 5e,Park Farm, Chichester Road, Arundel , United Kingdom, BN18 0AG | Directly Connected Power Station | 09/08/2023 |
| CATHKIN ENERGY STORAGE LIMITED | 13341612 | Rooms 481 - 499, Second Floor Salisbury House,, London Wall, London, United Kingdom, EC2M 5SQ | Embedded Exemptable Large Power Station | 05/05/2022 |
| CAUSEYMIRE WINDFARM LIMITED | SC149105 | 50 Lothian Road, Festival Square, Edinburgh , United Kingdom, EH3 9WJ | Embedded Power Station | 31/03/2005 |
| CBB SPV LIMITED | 15747963 | 2 Crossways Business Centre, Bicester Road Kingswood, Aylesbury, Buckinghamshire, United Kingdom,, Aylesbury, Buckinghamshire, United Kingdom, HP18 0RA | Directly Connected Power Station | 21/08/2024 |
| CBS ENERGY STORAGE ASSETS UK LIMITED | 02352390 | MillstreamMaidenhead Road, Windsor, Berkshire, UK, SL4 5GD | Embedded Power Station | 18/09/2001 |
| CELSA MANUFACTURING (UK) LIMITED | 04577881 | Building 58, East Moors Road, Cardiff , United Kingdom, CF24 5NN | Non-Embedded Customer Site | 27/06/2003 |
| CELTIC SEA OFFSHORE WIND FARM LIMITED | 13469943 | Shepherd And Wedderburn Llp, Octagon Point, 5 Cheapside, London , United Kingdom, EC2V 6AA | Directly Connected Power Station | 24/01/2022 |
| Celtic Sea Wind Electric Limited | 14044542 | Calcutt Court, Calcutt, Swindon , United Kingdom, SN6 6JR | Directly Connected Power Station | 20/09/2023 |
| CELTPOWER LIMITED | 02656561 | 3 PRENTON WAY, PRENTON , United Kingdom, CH43 3ET | Directly Connected Power Station; Dormant CUSC Party | 10/11/2003 |
| CENERGISE LIMITED | 535935 | 125 BAGGOT STREET LOWER, DUBLIN , Ireland, D02 EW74 | Interconnector User | 11/02/2014 |
| Central Bedfordshire Council | N/A | Priory House, Monks Walk, Chicksands, Shefford, Bedfordshire, United Kingdom, SG17 5TQ | Directly Connected Power Station | 27/10/2022 |
| CENTRICA BUSINESS SOLUTIONS UK OPTIMISATION LIMITED | 08355344 | MillstreamMaidenhead Road, Windsor, Berkshire, UK, SL4 5GD | Virtual Lead Party | 29/07/2020 |
| CENTRICA ENERGY LIMITED | 02877398 | Millstream, Maidenhead Road, Windsor, Berkshire, United Kingdom, SL4 5GD | Interconnector User | 18/09/2001 |
| CENTRICA ENERGY TRADING A/S | 20293195 | SKELAGERVEJ 1, AALBORG , Denmark, 9000 | Interconnector User | 08/09/2010 |
| CERULEA LIMITED | 08584174 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 19/06/2015 |
| CERULEAN WINDS LIMITED | 12626805 | 1 HIGH STREET, GUILDFORD , UNITED KINGDOM, GU2 4HP | Directly Connected Power Station | 12/06/2024 |
| CESA (KIRKCALDY) LIMITED | 14517581 | 33 Cavendish Square, London , United Kingdom, W1G 0PW | Directly Connected Power Station | 07/08/2023 |
| CEZ A.S. | 45274649 | 2/1444, DUHOVA, PRAHA , Czech Republic, 140 53 | Interconnector User | 15/01/2020 |
| CF Flex Power GmbH | HRB174868 | Budapester St. 47, Hamburg, Hamburg, GERMANY, 20359 | Interconnector User | 13/05/2024 |
| CFP Commodities Limited | 670121 | 118 Lower Baggott Street, Dublin, DUBLIN, Ireland, D02 AW89 | Interconnector User | 15/10/2024 |
| CHICKERELL SOLAR LIMITED | 11505358 | 4th Floor, 80 Victoria Street, London , United Kingdom, SW1E 5JL | Directly Connected Power Station | 04/04/2022 |
| CHILTERN RENEWABLES LIMITED | 12459542 | Unit 3 Cotswold Business Park, Millfield Lane, C addington, Luton, Bedfordshire, United Kingdom, LU1 4AJ | Directly Connected Power Station | 19/10/2022 |
| Chiltern Renewables Millfield Limited | 14475395 | Unit 3 Cotswold Business Park, Millfield Lane, C addington, Luton, Bedfordshire, United Kingdom, LU1 4AJ | Directly Connected Power Station | 15/06/2023 |
| CHINT SOLAR UK MANAGEMENT LTD | 14721949 | 25 Farringdon Street, London , EC4A 4AB | Directly Connected Power Station | 17/02/2025 |
| CHIRMORIE WIND FARM LIMITED | 09171934 | 22-24 King Street, Maidenhead, Berkshire, United Kingdom, SL6 1EF | Directly Connected Power Station | 01/03/2016 |
| CHRISTOPHER MORAN ENERGY LIMITED | 07395884 | CHELSEA CLOISTERS, S LOANE AVENUE, LONDON , United Kingdom, SW3 3DW | Directly Connected Power Station | 11/02/2019 |
| CHRYSAOR PETROLEUM COMPANY U.K. LIMITED | 00792712 | 23 Lower Belgrave Street, London , United Kingdom, SW1W 0NR | Non-Embedded Customer Site | 16/09/2022 |
| Cilfynydd BESS Limited | 14469856 | Hodge House, Guildhall Place, Cardiff , United Kingdom, CF10 1DY | Directly Connected Power Station | 15/06/2023 |
| CILFYNYDD GREEN ENERGY LIMITED | 13298796 | 3rd Floor, Norfolk House, 106 Saxon Gate West, Milton Keynes , United Kingdom, MK9 2DN | Directly Connected Power Station | 18/11/2021 |
| CILFYNYDD GRID SERVICES LIMITED | 13396965 | 3rd Floor, 24 Savile Row, London , United Kingdom, W1S 2ES | Directly Connected Power Station | 30/03/2023 |
| CINERGY GLOBAL POWER (UK) LIMITED | 03504828 | c/o Pricewaterhousecoopers Llp, 2 Humber Quays, Wellington Street West, Hull , United Kingdom, HU1 2BN | Directly Connected Power Station | 18/09/2001 |
| CITIGEN (LONDON) LIMITED | 02427823 | Westwood Way, Westwood Business Park, Coventry , United Kingdom, CV4 8LG | Embedded Power Station | 18/09/2001 |
| CLASHINDARROCH WINDFARM EXTENSION LIMITED | 12435260 | Chelsea Cloisters, Sloane Avenue, London , United Kingdom,, SW3 3DW | Directly Connected Power Station | 17/12/2024 |
| CLASHINDARROCH WIND FARM LIMITED | 05358030 | 5th Floor 70 St Mary Axe, London , United Kingdom, EC3A 8BE | Embedded Power Station | 10/09/2014 |
| CLAVERHOUSE GENERATION LIMITED | SC604760 | Clyde View (Suite F3) Riverside Business Park, 22 Pottery Street, Greenock , United Kingdom, PA15 2UZ | Directly Connected Power Station | 21/03/2019 |
| Clayfords Energy Storage Ltd | SC595136 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Embedded Exemptable Large Power Station | 21/04/2022 |
| CLEAN AIR RENEWABLES LIMITED | 13695350 | 2 Crossways Business Centre, Bicester Road, Kingswood, Aylesbury, United Kingdom, HP18 0RA | Directly Connected Power Station | 08/09/2022 |
| Clean Earth Energy Limited | 07225190 | Unit 2a/2b Bees Park Road, Wadebridge , United Kingdom, PL27 6HB | Embedded Power Station | 22/09/2023 |
| Clean Planet Solar Farm Limited | 13189132 | Unit 2 Crossways, Bicester Road, Kingswood, Aylesbury, United Kingdom, HP18 0RA | Directly Connected Power Station | 11/04/2023 |
| CLEARSTONE SERVICES LIMITED | 10487840 | 8 DEVONSHIRE SQUARE, LONDON , United Kingdom, EC2M 4PL | Directly Connected Power Station | 22/08/2018 |
| CLEVE HILL SOLAR PARK LIMITED | 08904850 | 3rd Floor 24 Savile Row, London, London, United Kingdom, W1S 2ES | Directly Connected Power Station | 05/11/2018 |
| Cloud Hill Windfarm Limited | 13180855 | 22 Chancery Lane, London , United Kingdom, WC2A 1LS | Directly Connected Power Station | 15/06/2022 |
| CLOUDHQ DIDCOT POWER LP | OE023539 | 3RD FLOOR 37 ESPLANADE, SAINT HELIER , Jersey (United Kingdom, JE1 1AD | Non-Embedded Customer Site | 29/04/2020 |
| CLOUDHQ UK LIMITED | 10150306 | c/o Buzzacott Llp, 130 Wood Street, London , United Kingdom, EC2V 6DL | Non-Embedded Customer Site | 18/12/2018 |
| CLUMP FARM SOLAR LIMITED | 12368142 | 22 CHANCERY LANE, LONDON , United Kingdom, WC2A 1LS | Directly Connected Power Station | 01/12/2020 |
| CLYDE WINDFARM (SCOTLAND) LIMITED | SC281105 | Inveralmond House, 200 Dunkeld Road, Perth , United Kingdom, PH1 3AQ | Directly Connected Power Station | 01/08/2005 |
| CNOC BUIDHE WIND ENERGY HUB LIMITED | 13325515 | 10 Victoria Street, Bristol , United Kingdom, BS1 6BN | Directly Connected Power Station | 03/12/2021 |
| CNOOC PETROLEUM EUROPE LIMITED | 01051137 | Prospect House, 9 7 Oxford Road, Uxbridge , United Kingdom, UB8 1LU | Non-Embedded Customer Site | 31/05/2024 |
| COALBURN ENERGY LIMITED | 15700870 | Level 8 Lily House 13 Hanover Square, Mayfair, London , United Kingdom, W1S 1HN | Directly Connected Power Station | 23/01/2025 |
| COBBLESTONE ENERGY DMCC | DMCC179669 | Unit No: 1701, SABA 1, P lot No: JLT-PH1-E3A, Jumeirah Lakes Towers, Dubai, Dubai, United Arab Emirates, JLT-PH1-E3A, | Interconnector User | 10/12/2021 |
| COBBLESTONE ENERGY LTD | 10468940 | Unit 28 City Business Centre, Lower Road, London , United Kingdom, SE16 2XB | Interconnector User | 11/12/2018 |
| COCKENZIE STORAGE B LTD | 15592524 | 2 Upperton Gardens, Eastbourne , United Kingdom, BN21 2AH | Directly Connected Power Station | 20/02/2025 |
| COCKENZIE STORAGE LIMITED | 11007306 | 5 New Street Square, London , United Kingdom, EC4A 3TW | Directly Connected Power Station | 18/11/2022 |
| CODDINGTON 10 RENEWABLES LTD | 14914945 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 31/08/2023 |
| CODLING WIND PARK III LIMITED | 531195 | c/o Cooney Carey Consulting Limited, T he Courtyard, C armanhall Road, Sandyford, Dublin 18, Ireland, D18 YD27 | Directly Connected Power Station | 22/12/2020 |
| CODLING WIND PARK LIMITED | 358470 | c/o Cooney Carey Consulting Limited, T he Courtyard, C armanhall Road, Sandyford, Dublin 18, Ireland, D18 YD27 | Directly Connected Power Station | 12/12/2012 |
| COGLE MOSS RENEWABLES LLP | SO304944 | Muirden Farm, Turriff, Aberdeenshire, United Kingdom, AB53 4NH | Embedded Power Station | 21/09/2020 |
| COIRE GLAS HYDRO PUMPED STORAGE LIMITED | SC561128 | Inveralmond House, 200 Dunkeld Road, Perth , United Kingdom, PH1 3AQ | Directly Connected Power Station | 08/06/2018 |
| COIRE NA CLOICHE WINDFARM LLP | SO304435 | 5 ATHOLL CRESCENT, EDINBURGH , United Kingdom, EH3 8EJ | Embedded Power Station | 23/12/2015 |
| COLT DATA CENTRE SERVICES UK LIMITED | 07306352 | Colt House, 20 Great Eastern Street, London , United Kingdom, EC2A 3EH | Directly Connected Power Station; Dormant CUSC Party | 06/10/2021 |
| COMCOM TRADING d.o.o. | 8633118000 | Lapajnetova ulica 29, Idrija, Idrija, Slovenia, 5280 | Interconnector User | 16/02/2024 |
| COMPAGNIE NATIONALE DU RHONE | B957520901 | 2 RUE ANDRE BONIN, LYON , France, 69004 | Interconnector User | 08/10/2010 |
| CONNECTID 1 LIMITED | 14714608 | The Surrey Technology Centre, The Surrey Research Park, Guildford , United Kingdom, GU2 7YG | Directly Connected Power Station | 15/12/2023 |
| CONNECTID 2 LIMITED | 14714921 | The Surrey Technology Centre, The Surrey Research Park, Guildford , United Kingdom, GU2 7YG | Directly Connected Power Station | 14/12/2023 |
| CONNECTID 3 LIMITED | 14714607 | The Surrey Technology Centre, The Surrey Research Park, Guildford , United Kingdom, GU2 7YG | Directly Connected Power Station | 15/12/2023 |
| Connectid 9 Limited | 14713671 | The Surrey Technology Centre, The Surrey Research Park, Guildford , United Kingdom, GU2 7YG | Directly Connected Power Station | 15/12/2023 |
| CONRAD (BASINGSTOKE) LIMITED | 12500002 | Suites D&E, W indrush Court, B lacklands Way, Abingdon , United Kingdom, OX14 1SY | Embedded Power Station | 13/06/2024 |
| CONRAD (BISPHAM) LIMITED | 10487882 | Suites D&E Windrush Court, Blacklands Way, Abingdon , United Kingdom, OX14 1SY | Embedded Power Station | 22/06/2020 |
| Conrad (Blackpool) Limited | 12611339 | Suites D&E, W indrush CourtB lacklands Way, Abingdon, Abingdon, United Kingdom, OX14 1SY | Embedded Power Station | 03/08/2023 |
| CONRAD (CHATTERLEY) LIMITED | 10322690 | Suites D&E Windrush Court, Blacklands Way, Abingdon , United Kingdom, OX14 1SY | Embedded Power Station | 20/04/2020 |
| CONRAD (EYE) LIMITED | 14405221 | Suites D&E Windrush Court, Blacklands Way, Abingdon , United Kingdom, OX14 1SY | Directly Connected Power Station | 24/05/2023 |
| CONRAD (MIDDLEWICH) LIMITED | 11596046 | Suites D&E Windrush Court, Blacklands Way, Abingdon , United Kingdom, OX14 1SY | Embedded Power Station | 20/04/2020 |
| CONRAD (REDSCAR) LIMITED | 11596310 | Suites D&E Windrush Court, Blacklands Way, Abingdon , United Kingdom, OX14 1SY | Directly Connected Power Station | 20/01/2020 |
| CONRAD (SWINDON) LIMITED | 10923676 | Suites D&E, W indrush Court, B lacklands Way, Abingdon, Abingdon, United Kingdom, OX14 1SY | Embedded Power Station | 13/06/2024 |
| CONRAD (TORQUAY) LIMITED | 13207993 | Suites D&E, Windrush Court, B lacklands Way, Abingdon, Abingdon, United Kingdom, OX14 1SY | Embedded Power Station | 13/06/2024 |
| Conrad (Walpole) Limited | 14405214 | Suites D&E Windrush Court, Blacklands Way, Abingdon , United Kingdom, OX14 1SY | Directly Connected Power Station | 31/05/2023 |
| CONRAD (WINCHESTER) LIMITED | 10923638 | Suites D&E Windrush Court, Blacklands Way, Abingdon , United Kingdom, OX14 1SY | Embedded Power Station | 26/07/2024 |
| Conrad Energy (Developments) II Limited | 12886485 | Suites D&E, W indrush Court, Blacklands Way, Abingdon , United Kingdom, OX14 1SY | Embedded Exemptable Large Power Station | 12/02/2024 |
| CONRAD ENERGY (TRADING) LIMITED | 10969329 | Suites D & E, Windrush CourtBlacklands Way, Abingdon, Abingdon, UK, OX14 1SY | Supplier | 10/01/2020 |
| CONSTELLATION GENERATION LIMITED | 09198137 | Suite 1, 7th Floor, 50 Broadway, London, LONDON, United Kingdom, SW1H 0BL | Interconnector User; Supplier | 07/06/2018 |
| Contullich Energy Storage Limited | 14074698 | Beaufort Court, Egg Farm Lane, Kings Langley , United Kingdom, WD4 8LR | Directly Connected Power Station | 19/07/2024 |
| CONVEX ENERGY GMBH | HRB196620 | EUREF-CAMPUS 6 - 9, BERLIN , GERMANY, 10829 | Interconnector User | 02/12/2020 |
| CO-OPERATIVE ENERGY LIMITED | 06993470 | Co-Operative House, Warwick Technology Park, Gallows Hill, Warwick , United Kingdom, CV34 6DA | Supplier | 28/08/2012 |
| COPENHAGEN ENERGY TRADING A/S | 42526991 | BAG ELEFANTERNE 1, ST TH, KOBENHAVN V , DENMARK, 1799 | Interconnector User | 13/01/2022 |
| Copper Nose Energy Ltd | 14150596 | 68 Dalling Road, London , United Kingdom, W6 0JA | Directly Connected Power Station | 24/11/2022 |
| CORBY POWER LIMITED | 92329494 | Mitchell Road, Phoenix Parkway, Corby, Northamptonshire, United Kingdom, NN17 5QT | Embedded Power Station | 18/09/2001 |
| Corio Generation Limited | 13715492 | Ropemaker Place, 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 03/08/2023 |
| CORONA ENERGY RETAIL 4 LIMITED | 02798334 | Building 2 Level 2, Croxley Park, Watford , United Kingdom, WD18 8YA | Supplier | 24/06/2019 |
| CORONATION POWER LIMITED | 04971270 | Crown House, 108 Aldersgate Street, London , United Kingdom, EC1A 2JQ | Dormant CUSC Party; Embedded Power Station | 15/05/2019 |
| CORRIEGARTH 2 WIND FARM LIMITED | 12207006 | 22 CHANCERY LANE, LONDON , United Kingdom, WC2A 1LS | Directly Connected Power Station | 04/05/2020 |
| CORRIEGARTH WIND ENERGY LIMITED | SC486712 | Dla Piper Scotland Llp. C ollins House, Rutland Square, Edinburgh , United Kingdom, EH1 2AA | Directly Connected Power Station | 07/08/2015 |
| CORRIEMOILLIE WINDFARM LIMITED | 09377951 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton Le Spring, Sunderland, United Kingdom, DH4 5RA | Directly Connected Power Station | 02/04/2015 |
| CORRIMONY ENERGY LIMITED | SC358976 | 10 ARDROSS STREET, INVERNESS , United Kingdom, IV3 5NS | Embedded Exemptable Large Power Station | 26/01/2017 |
| Corshellach Energy Storage Limited | 14074757 | Beaufort Court, Egg Farm Lane, Kings Langley , United Kingdom, WD4 8LR | Directly Connected Power Station | 19/07/2024 |
| Coryton 10 Renewables Limited | 15125478 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 22/11/2023 |
| CORYTON ENERGY COMPANY, LTD. | FC020597 | Maples And Calder, Ugland House, P O BOX 309, George Town, Grand Cayman, Cayman Islands, PO BOX 309 | Directly Connected Power Station | 18/09/2001 |
| COSTA HEAD WIND FARM LIMITED | SC385352 | c/o Hoolan Energy Limited, 16 Young Street, Edinburgh , United Kingdom, EH2 4JB | Directly Connected Power Station | 02/06/2016 |
| COTTAM SOLAR PROJECT LIMITED | 12711231 | Unit 20.2 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 29/01/2021 |
| COULOMB ENERGY SUPPLY LIMITED | 07488842 | Px HouseWestpoint Road, Stockton-On-Tees , TS17 6BF | Supplier | 30/08/2012 |
| COUPAR LIMITED | 11966683 | c/o Gresham House Asset Management Limited, 5 New Street Square, London , United Kingdom, EC4A 3TW | Embedded Power Station | 27/01/2021 |
| COUPAR TWO LIMITED | 13465261 | 6TH FLOOR 2 LONDON WALL PLACE, LONDON , United Kingdom, EC2Y 5AU | Embedded Power Station | 05/04/2022 |
| COUR WIND FARM (SCOTLAND ) LIMITED | SC493307 | 4th Floor Saltire Court, 20 Castle Terrace, Edinburgh , United Kingdom, EH1 2EN | Directly Connected Power Station | 29/04/2015 |
| COWLEY 2 RENEWABLES LTD | 14914340 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 31/08/2023 |
| COWLEY 7 RENEWABLES LTD | 14914334 | Century House 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 31/08/2023 |
| COWLEY BALDON GREEN LIMITED | 12517381 | Ropemaker Place, 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 24/07/2020 |
| COYLTON ENERGY LIMITED | 14096780 | 19th Floor 22 Bishopsgate, London , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 28/11/2022 |
| Cragside Energy Limited | 13093560 | 15 Golden Square, 4th Floor, London , United Kingdom, W1F 9JG | Directly Connected Power Station | 13/06/2023 |
| Craig Watch Wind Farm Limited | 12792263 | 19th Floor 22 Bishopsgate, London , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 11/03/2022 |
| CRAIG WIND FARM LIMITED | 05539653 | c/o Temporis Capital Limited, 7th Floor, Wellington House, 125 -130 Strand, London , United Kingdom, WC2R 0AP | Directly Connected Power Station | 18/04/2016 |
| CRAKAIG WIND ENERGY HUB LIMITED | 14751820 | 10 Victoria Street, Bristol , United Kingdom, BS1 6BN | Embedded Power Station | 15/01/2025 |
| CREAG RIABHACH WIND FARM LTD | SC424471 | 2 Castle Terrace, 4 th Floor, Edinburgh , United Kingdom, EH1 2EL | Directly Connected Power Station | 12/12/2014 |
| CREYKE BECK BATTERY 2 LIMITED | 14359695 | Mills & Reeve Llp Botanic House1 00 Hills Road, Cambridge , CB2 1PH | Directly Connected Power Station | 07/08/2023 |
| CRONOS ENERGY LTD | 10768224 | Amp Technology Centre Advanced Manufacturing Park, Brunel Way, Rotherham , United Kingdom, S60 5WG | Interconnector Owner | 20/11/2018 |
| CROOKEDSTANE WINDFARM LIMITED | SC415902 | Ground Floor West Suite, Prospect House, 5 Thistle Street, Edinburgh , United Kingdom, EH2 1DF | Directly Connected Power Station; Dormant CUSC Party | 22/09/2015 |
| CROSSDYKES WF LIMITED | SC424921 | c/o Brodies Llp, Capital Square, 5 8 Morrison Street, Edinburgh, Edinburgh, United Kingdom, EH3 8BP | Directly Connected Power Station | 21/07/2015 |
| CROSSRAIL LIMITED | 04212657 | 5 Endeavour Square, Stratford, London, United Kingdom, E20 1JN | Non-Embedded Customer Site | 09/04/2010 |
| CROWN GAS AND POWER 2 LIMITED | 11357910 | The Oil Centre, B ury New Road, Heap Bridge, Bury , United Kingdom, BL9 7HY | Supplier | 27/07/2021 |
| CRYOBATTERY ONE LIMITED | 12041852 | SUITE A 6 HONDURAS STREET, LONDON , United Kingdom, EC1Y 0TH | Directly Connected Power Station | 27/11/2020 |
| CRYSTAL RIG III LIMITED | SC353920 | c/o Harper Macleod Llp, T he Cadoro, 45 Gordon Street, Glasgow, London, United Kingdom, G1 3PE | Directly Connected Power Station | 13/04/2016 |
| CRYSTAL RIG II LIMITED | SC257737 | c/o Harper Macleod Llp, T he Cadoro, 45 Gordon Street, Glasgow, London, United Kingdom, G1 3PE | Directly Connected Power Station | 02/10/2006 |
| CRYSTAL RIG IV LIMITED | SC167068 | c/o Harper Macleod Llp, T he Cadoro, 45 Gordon Street, Glasgow , United Kingdom, G1 3PE | Directly Connected Power Station | 01/06/2020 |
| CRYSTAL RIG WINDFARM LIMITED | 04364525 | 2ND FLOOR, 36 BROADWAY, LONDON , United Kingdom, SW1H 0BH | Embedded Exemptable Large Power Station | 31/03/2005 |
| CSE22 LIMITED | 10824187 | 8 DEVONSHIRE SQUARE, LONDON , United Kingdom, EC2M 4PL | Directly Connected Power Station | 01/05/2020 |
| CSE23 LIMITED | 10824252 | 8 DEVONSHIRE SQUARE, LONDON , United Kingdom, EC2M 4PL | Directly Connected Power Station | 27/05/2020 |
| CSE25 LIMITED | 11354620 | 8 DEVONSHIRE SQUARE, LONDON , United Kingdom, EC2M 4PL | Directly Connected Power Station | 12/01/2022 |
| CSE26 LIMITED | 11354627 | 8 DEVONSHIRE SQUARE, LONDON , United Kingdom, EC2M 4PL | Directly Connected Power Station | 07/06/2022 |
| CSE27 LIMITED | 11354710 | 8 DEVONSHIRE SQUARE, LONDON , United Kingdom, EC2M 4PL | Directly Connected Power Station | 03/08/2023 |
| CSE28 LIMITED | 11354731 | 8 DEVONSHIRE SQUARE, LONDON , UNITED KINGDOM, EC2M 4PL | Directly Connected Power Station | 11/07/2023 |
| CSE29 LIMITED | 11354705 | 8 Devonshire Square, London , United Kingdom, EC2M 4PL | Directly Connected Power Station | 23/06/2023 |
| CSE30 LIMITED | 11354785 | 8 DEVONSHIRE SQUARE, LONDON , United Kingdom, EC2M 4PL | Directly Connected Power Station | 03/08/2023 |
| CSE33 LIMITED | 11354830 | 8 DEVONSHIRE SQUARE, LONDON , United Kingdom, EC2M 4PL | Directly Connected Power Station | 08/02/2023 |
| CSE34 LIMITED | 11354838 | 8 DEVONSHIRE SQUARE, LONDON , United Kingdom, EC2M 4PL | Directly Connected Power Station | 11/07/2023 |
| CSE37 Limited | 13891981 | 8 Devonshire Square, London , United Kingdom, EC2M 4PL | Directly Connected Power Station | 19/09/2023 |
| CSE38 LIMITED | 13892270 | 8 Devonshire Square, London , United Kingdom, EC2M 4PL | Directly Connected Power Station | 19/11/2024 |
| CSE39 LIMITED | 13892303 | 8 Devonshire Square, London , United Kingdom, EC2M 4PL | Directly Connected Power Station | 19/09/2023 |
| CSE41 LIMITED | 13892074 | 8 Devonshire Square, London , United Kingdom, EC2M 4PL | Directly Connected Power Station | 15/05/2023 |
| CSE42 LIMITED | 13892056 | 8 Devonshire Square, London , United Kingdom, EC2M 4PL | Directly Connected Power Station | 15/06/2023 |
| CSE43 LIMITED | 13891979 | 8 Devonshire Square, London , United Kingdom, EC2M 4PL | Directly Connected Power Station | 11/07/2023 |
| CSE45 LIMITED | 14450117 | 8 Devonshire Square, London , United Kingdom, EC2M 4PL | Directly Connected Power Station | 03/08/2023 |
| CS UK HOLDINGS III LIMITED | 10909660 | 111 Park Street, Mayfair, London, United Kingdom, W1K 7JF | Directly Connected Power Station | 16/03/2020 |
| CUBICO UK DEVELOPMENT LIMITED | 13308909 | 70 St Mary Axe, London , United Kingdom, EC3A 8BE | Directly Connected Power Station | 16/02/2024 |
| CULHAM STORAGE LIMITED | 14305030 | 4th Floor, 80 Victoria Street, London , United Kingdom, SW1E 5JL | Directly Connected Power Station | 01/02/2023 |
| CUMBERHEAD WEST WIND FARM LTD. | SC535501 | 320 ST. VINCENT STREET, GLASGOW , United Kingdom, G2 5AD | Directly Connected Power Station | 21/11/2019 |
| CUMBERHEAD WIND ENERGY LIMITED | 08926189 | 33 HOLBORN, LONDON , United Kingdom, EC1N 2HT | Directly Connected Power Station | 23/02/2015 |
| Current Commodities A/S | 38617990 | Niels W. Gades Vej 1, Aarhus C, AARHUS, Denmark, 8000 | Interconnector User | 02/09/2024 |
| Cuxton Energy Storage Limited | 13048364 | c/o Low Carbon Limited, Stirling Square, 5 -7 Carlton Gardens, London , United Kingdom, SW1Y 5AD | Embedded Power Station | 13/09/2022 |
| CWE Lochend Ltd | 13465111 | First Floor River Court T he Old Mill Office Park M ill Lane, Goldalming, Surrey , GU7 1EZ | Embedded Exemptable Large Power Station | 18/03/2025 |
| CWP Energy Limited | SC803977 | Caledonian Exchange, 19a Canning Street, Edinburgh , United Kingdom, EH3 8HE | Embedded Exemptable Large Power Station | 11/04/2006 |
| CYP SOLAR LIMITED | 12357995 | 111 Park Street, Mayfair, London, United Kingdom, W1K 7JF | Directly Connected Power Station | 09/02/2022 |
| DAINES ENERGY PARK LIMITED | 14446646 | 1st Floor Sackville House 1 43-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 21/04/2023 |
| DALIA HOLDINGS LTD | 11762101 | First Floor, Winston House, 3 49 Regents Park Road, London , United Kingdom, N3 1DH | Directly Connected Power Station | 15/06/2023 |
| DALMARNOCK BESS LTD | 13090868 | The Factory, Whitchurch, Ross On Wye, Herefordshire, United Kingdom, HR9 6DF | Embedded Power Station | 16/11/2021 |
| DALMARNOCK STORAGE LTD | 15025787 | 19 Friar Road, Brighton , United Kingdom, BN1 6NG | Directly Connected Power Station | 08/01/2024 |
| DALQUHANDY WIND FARM LIMITED | SC579907 | Ground Floor West Suite, Prospect House, 5 Thistle Street, Edinburgh , United Kingdom, EH2 1DF | Directly Connected Power Station; Non-Embedded Customer Site | 19/07/2018 |
| DALRIADA RENEWABLES LIMITED | 13732818 | 1st Floor Sackville House, 143-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 15/03/2024 |
| DALSWINTON WINDFARM (SCOTLAND) LIMITED | SC279014 | 50 Lothian Road, Festival Square, Edinburgh , United Kingdom, EH3 9WJ | Embedded Power Station | 13/10/2006 |
| DAMSONGREEN ENERGYFARM LIMITED | 15426313 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton Le Spring, Sunderland, United Kingdom, DH4 5RA | Directly Connected Power Station | 07/02/2025 |
| Danske Commodities A/S | 28113951 | Vaerkmestergade 38000, Aarhus, Denmark, Denmark, 8000 | Interconnector User; Virtual Lead Party | 22/02/2008 |
| DARE POWER LTD | 13381297 | 43-45 Dorset Street, London , United Kingdom, W1U 7NA | Interconnector User | 01/04/2022 |
| Darlington Solar 1 Limited | 13370167 | 111 Park Street, Mayfair, London , United Kingdom, W1K 7JF | Directly Connected Power Station | 11/07/2023 |
| DC01 UK Limited | 14262393 | Unit 3 Cotswold Business Park, M illfield Lane, Caddington, Luton, United Kingdom, LU1 4AJ | Directly Connected Power Station | 14/12/2022 |
| DC ENERGY TRADING V.O.F. | 86227289 | Stationsplein 21, Goes , Netherlands, 4461 HP | Interconnector User | 09/08/2023 |
| DE 001 LIMITED | 15312543 | Old Pump House, 1 9 Hooper Street, London , United Kingdom, E1 8BU | Directly Connected Power Station | 06/12/2024 |
| DEALANACH LIMITED | SC658650 | Muirhall Farm, Auchengray, Carnwath, Lanark, South Lanarkshire, United Kingdom, ML11 8LL | Directly Connected Power Station | 26/01/2022 |
| Decerna Limited | 08183909 | Decerna House, 3 2-33, Apex Business Village, Annitsford, Cramlington, Northumberland, United Kingdom, NE23 7BF | Directly Connected Power Station | 16/01/2024 |
| DEESIDE POWER (UK) LIMITED | 08887001 | Saltend Power Station, S altend Chemicals Park, H edon Road, Hull, East Riding Of Yorkshire, United Kingdom, HU12 8GA | Directly Connected Power Station | 03/06/2014 |
| DELL WIND FARM LIMITED | 08974131 | 22-24 King Street, Maidenhead, Berkshire, United Kingdom, SL6 1EF | Directly Connected Power Station | 02/03/2020 |
| DELTA GAS AND POWER LIMITED | 09933244 | 344-354 GRAY'S INN ROAD, LONDON , United Kingdom, WC1X 8BP | Supplier | 12/09/2017 |
| D-ENERGI TRADING LIMITED | 10769307 | Unit D, Madison Place, C entral Park, N orthampton Road, Manchester , United Kingdom, M40 5AG | Supplier | 22/12/2020 |
| DENGIE MARSHES WIND FARM LIMITED | 16027722 | Cornelius Barton & Co Alliance House 29-30 H igh Holborn, London , United Kingdom, WC1V 6AZ | Embedded Power Station | 20/03/2025 |
| DEUTSCHE BANK AG LONDON | BR000005 | Winchester House, 1 Great Winchester Street, London, LONDON, UK, EC2N 2DB | Interconnector User | 04/11/2008 |
| DIAMOND WIND LIMITED | SC415420 | HUMBIE MILL, HUMBIE , United Kingdom, EH36 5PB | Directly Connected Power Station | 14/04/2014 |
| DIDCOT BATTERY LIMITED | 11577622 | c/o Buzzacott Llp 130 Wood Street, London , United Kingdom, EC2V 6DL | Directly Connected Power Station | 05/08/2021 |
| DIGITAL POWER ENERGY SUPPLY UK LIMITED | 11042157 | The Barns Offices, Little Grimsby, Louth , United Kingdom, LN11 0TZ | Supplier | 01/02/2022 |
| DISTRIBUTED ENERGY CUSTOMER SOLUTIONS LIMITED | 04942184 | Millstream, Maidenhead Road, Windsor, Berkshire, United Kingdom, SL4 5GD | Directly Connected Power Station; Dormant CUSC Party | 27/10/2005 |
| DODO ENERGY LIMITED | 11042718 | 274 HATFIELD ROAD, ST ALBANS , United Kingdom, AL1 4UN | Supplier | 27/02/2019 |
| DOGGERBANK OFFSHORE WIND FARM PROJECT 1 HOLDCO LIMITED | 10930991 | No.1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station; Dormant CUSC Party | |
| DOGGERBANK OFFSHORE WIND FARM PROJECT 1 PROJCO LIMITED | 07791991 | No.1 Forbury Place, 43 Forbury Road, Reading, BERKSHIRE, United Kingdom, RG1 3JH | Directly Connected Power Station | 12/06/2017 |
| DOGGERBANK OFFSHORE WIND FARM PROJECT 2 HOLDCO LIMITED | 10931831 | No.1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station; Dormant CUSC Party | |
| DOGGERBANK OFFSHORE WIND FARM PROJECT 2 PROJCO LIMITED | 07914510 | No.1 Forbury Place, 4 3 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 12/06/2017 |
| DOGGERBANK OFFSHORE WIND FARM PROJECT 3 HOLDCO LIMITED | 10931009 | No.1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station; Dormant CUSC Party | |
| Dollymans Storage Limited | 10915634 | 4th Floor 80 Victoria Street, London , United Kingdom, SW1E 5JL | Embedded Power Station | 28/11/2022 |
| Don Cossack Ltd | 13057675 | 88 Grays Inn Road, London , United Kingdom, WC1X 8AA | Directly Connected Power Station | 18/04/2023 |
| DORENELL WINDFARM EXTENSION LIMITED | 12900205 | Chelsea Cloisters, Sloane Avenue,, London , United Kingdom, SW3 3DW | Directly Connected Power Station | 31/03/2023 |
| DORENELL WINDFARM LIMITED | 05628395 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton Le Spring, Sunderland, United Kingdom, DH4 5RA | Directly Connected Power Station | 09/11/2015 |
| DOUGLAS WEST EXTENSION LTD | SC587662 | 320 ST VINCENT STREET, GLASGOW , UNITED KINGDOM, G2 5AD | Directly Connected Power Station | 08/08/2019 |
| DOUGLAS WEST WIND FARM LTD | SC524434 | Dla Piper Scotland Llp, Collins House, Rutland Square, Edinburgh , United Kingdom, EH1 2AA | Directly Connected Power Station | 31/03/2017 |
| DOWNIEBRAE BESS LTD | 14657677 | Overross House, Ross Park, Ross-on-Wye, Herefordshire, United Kingdom, HR9 7US | Directly Connected Power Station | 15/09/2023 |
| Downing Renewable Developments LLP | OC439748 | 6TH FLOOR ST MAGNUS HOUSE, LONDON , UNITED KINGDOM, EC3R 6HD | Directly Connected Power Station | 12/06/2023 |
| Dragon Green 2 Renewables Ltd | 14914407 | Century House 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 31/08/2023 |
| DRAGON GREEN 7 RENEWABLES LTD | 14913700 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 31/08/2023 |
| DRAKELOW GREEN ENERGY LIMITED | 13358336 | 3rd Floor, Norfolk House, 106 Saxon Gate West, Milton Keynes , United Kingdom, MK9 2DN | Directly Connected Power Station | 06/12/2021 |
| Drax Cruachan Expansion Limited | 06657393 | Drax Power Station, Drax, Selby, North Yorkshire, United Kingdom, YO8 8PH | Directly Connected Power Station | 05/04/2022 |
| Drax Energy Solutions Limited | 05893966 | Drax Power StationDrax, Selby, North Yorkshire, UK, YO8 8PH | Supplier | 11/01/2007 |
| Drax Power Limited | 04883589 | Drax Power Station, Drax, Selby, North Yorkshire, United Kingdom, YO8 8PH | Directly Connected Power Station | 16/12/2003 |
| DRAX PUMPED STORAGE LIMITED | 06657336 | Drax Power StationDrax, Selby, North Yorkshire, UK, YO8 8PH | Directly Connected Power Station | 01/07/2021 |
| Drax River Hydro Limited | 05956747 | Drax Power Station, Drax, Selby, North Yorkshire, United Kingdom, YO8 8PH | Embedded Exemptable Large Power Station | 01/07/2021 |
| Drongan Battery Storage Ltd | SC730119 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Directly Connected Power Station | 27/03/2023 |
| DRUIM LEATHANN WINDFARM LIMITED | SC414109 | Ground Floor West Suite, Prospect House, 5 Thistle Street, Edinburgh , United Kingdom, EH2 1DF | Directly Connected Power Station | 03/01/2013 |
| Drummarnock Wind Farm Limited | SC671213 | Office 202 One Lochrin Square, 92-94 Fountainbridge, Edinburgh , EH3 9QA | Directly Connected Power Station | 14/06/2022 |
| DUDGEON OFFSHORE WIND LIMITED | 04418909 | ONE KINGDOM STREET, LONDON , United Kingdom, W2 6BD | Directly Connected Power Station | 02/07/2010 |
| Duferco Energia SpA | 03544070174 | Via Paolo Imperiale 4, Genoa, Genoa, Italy, 16126 | Interconnector User | 14/09/2023 |
| DUMMUIES WINDFARM HUNTLY LIMITED | 05624537 | 100 AVEBURY BOULEVARD, MILTON KEYNES , United Kingdom, MK9 1FH | Embedded Power Station | 16/03/2006 |
| DUNMAGLASS WIND FARM LIMITED | SC607482 | Inveralmond House, 200 Dunkeld Road, Perth , United Kingdom, PH1 3AQ | Directly Connected Power Station | 01/02/2019 |
| Dvalin ApS | 40420347 | 10 Niels Jernes Vej, Aalborg, Aalborg, Denmark, 9220 | Interconnector User | 11/05/2022 |
| Dyce Battery Storage Limited | SC705681 | The Shires, 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Embedded Exemptable Large Power Station | 06/12/2022 |
| DYCE ENERGY LIMITED | 09995796 | B3 Patrick Tobin Business Park, Bolton Road, Wath-Upon-Dearne, Rotherham, United Kingdom, S63 7LL | Supplier | 12/04/2021 |
| E.E.W. ECO ENERGY WORLD DEVELOPMENT HOLDING LIMITED | 11794857 | 13 Hanover Square, London , United Kingdom, W1S 1HN | Directly Connected Power Station | 22/09/2022 |
| E.ON ENERGY SOLUTIONS LIMITED | 03407430 | Westwood Way, Westwood Business Park, Coventry , United Kingdom, CV4 8LG | Supplier | |
| E.ON NEXT ENERGY LIMITED | 03782443 | Westwood WayWestwood Business Park, Coventry, KENT, UK, CV4 8LG | Supplier | 18/09/2001 |
| E.ON UK PLC | 02366970 | Westwood Way, Westwood Business Park, Coventry , United Kingdom, CV4 8LG | Directly Connected Power Station; Supplier | 31/03/2005 |
| E.ON UK STEVEN'S CROFT LIMITED | 10253456 | Westwood Way, Westwood Business Park, Coventry , United Kingdom, CV4 8LG | Directly Connected Power Station | 20/12/2018 |
| E (GAS AND ELECTRICITY) LIMITED | 08520118 | Bowcliffe Hall, B ramham, Wetherby, West Yorkshire, United Kingdom, LS23 6LP | Supplier | 16/05/2014 |
| EARBA LIMITED | 14386618 | Canal Head North, Kendal , LA9 7BZ | Directly Connected Power Station | 19/09/2023 |
| EARLSBURN WIND ENERGY LIMITED | SC254429 | Beauly House, Dochfour Business Centre, Dochgarroch, Inverness, United Kingdom, IV3 8GY | Embedded Exemptable Large Power Station | 02/08/2005 |
| EARL SHILTON ENERGY PARK LIMITED | 14376476 | 1st Floor Sackville House, 143-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 19/06/2023 |
| EAST ANGLIA ONE LIMITED | 07366753 | 3rd Floor, 1 Tudor Street, London , United Kingdom, EC4Y 0AH | Directly Connected Power Station | 03/10/2014 |
| EAST ANGLIA ONE NORTH LIMITED | 11121800 | 3rd Floor, 1 Tudor Street, London , United Kingdom, EC4Y OAH | Directly Connected Power Station | 03/03/2021 |
| EAST ANGLIA THREE LIMITED | 08141208 | 3rd Floor, 1 Tudor Street, London , United Kingdom, EC4Y 0AH | Directly Connected Power Station | 11/02/2016 |
| EAST ANGLIA TWO LIMITED | 11121842 | 3rd Floor, 1 Tudor Street, London , United Kingdom, EC4Y OAH | Directly Connected Power Station | 29/04/2021 |
| EastCoastGridServices Ltd | 13518282 | 67 Westow Street, London , United Kingdom, SE19 3RW | Directly Connected Power Station | 07/09/2022 |
| EASTERN POWER NETWORKS PLC | 02366906 | Newington House, 237 Southwark Bridge Road, London , United Kingdom, SE1 6NP | Directly Connected Distribution System | 18/09/2001 |
| Eccles Energy Centre Limited | SC766863 | 13 Queen's Road, Aberdeen , United Kingdom, AB15 4YL | Directly Connected Power Station | 03/04/2025 |
| Eccles Grid Stability Limited | 11323302 | 3rd Floor 1 Dover Street, London , United Kingdom, W1S 4LD | Directly Connected Power Station | 19/12/2023 |
| Eclipse Power Networks Limited | 09633506 | 25 Osier Way, Olney , United Kingdom, MK46 5FP | Independent Distribution N/W Operator | 21/12/2017 |
| ECOCEL ENERGY (STORAGE) LTD | SC745066 | 44 Milton Road, East Kilbride, Glasgow, United Kingdom, G74 5BU | Directly Connected Power Station; Embedded Exemptable Large Power Station | 27/08/2024 |
| ECODEV (ALYTH) LTD | 13774236 | Overross House, Ross Park, Ross-on-Wye, Herefordshire, United Kingdom, HR9 7US | Directly Connected Power Station | 04/11/2022 |
| ECODEV GROUP LTD | 10276309 | Overross House, Ross Park, Ross-on-Wye, Herefordshire, United Kingdom, HR9 7US | Embedded Power Station | 31/08/2021 |
| ECODEV PROJECTS LTD | 13910272 | The Factory, Whitchurch,, Ross On Wye, Herefordshire, United Kingdom, HR9 6DF | Directly Connected Power Station | 23/05/2023 |
| ECO GREEN MANAGEMENT LIMITED | 06957198 | 4305 Park Approach, Leeds , United Kingdom, LS15 8GB | Supplier | 23/09/2016 |
| Econergy International Limited | 12669318 | 1st Floor, 76-80 Old Broad Street, London , United Kingdom, EC2M 1QP | Directly Connected Power Station | 07/12/2022 |
| ECOTRICITY GENERATION LIMITED | 03117225 | Lion House, R owcroft, Stroud , United Kingdom, GL5 3BY | Directly Connected Power Station | 19/07/2022 |
| ECOTRICITY LIMITED | 03043412 | Lion House, R owcroft, Stroud, Stroud, United Kingdom, GL5 3BY | Supplier | 28/08/1997 |
| Edelweiss Energia S.P.A. | IT03258290166 | VIA VITTORIO VENETO 42, SARNICO, SARNICO, Italy, 24067 | Interconnector User | 25/04/2014 |
| EDF DEVELOPMENT COMPANY LIMITED | 06222043 | Nova North, 11 Bressenden Place, London , United Kingdom, SW1E 5BY | Directly Connected Power Station; Dormant CUSC Party | 03/10/2008 |
| EDF ENERGY (THERMAL GENERATION) LIMITED | 04267569 | Nova North, 11 Bressenden Place, London , United Kingdom, SW1E 5BY | Directly Connected Power Station | 01/12/2016 |
| EDF ENERGY (TSO) LIMITED | 03432165 | 90 WHITFIELD STREET, LONDON , United Kingdom, W1T 4EZ | Directly Connected Power Station | 18/09/2001 |
| EDF ENERGY CUSTOMERS LIMITED | 02228297 | Nova North, 11 Bressenden Place, London, LONDON, United Kingdom, SW1E 5BY | Supplier | 18/09/2001 |
| EDF ENERGY LIMITED | 02366852 | Nova North, 11 Bressenden Place, London, LONDON, United Kingdom, SW1E 5BY | Directly Connected Power Station | 18/09/2001 |
| EDF ENERGY NUCLEAR GENERATION LIMITED | 03076445 | Javelin House, Building 1420, Charlton Court, Gloucester Business Park, Gloucester , United Kingdom, GL3 4AE | Directly Connected Power Station | 18/09/2001 |
| EDF ENERGY RENEWABLES LIMITED | 06456689 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton Le Spring, Sunderland, United Kingdom, DH4 5RA | Directly Connected Power Station | 30/01/2015 |
| EDF Service National | 552 081 317 | 2, rue Louis Murat, Paris , France, 75008 Paris | Interconnector User | |
| EDF TRADING LIMITED | 03750288 | 80 Victoria Street, Cardinal Place 3rd Floor, London , United Kingdom, SW1E 5JL | Interconnector User | 18/09/2001 |
| EDGWARE ENERGY LIMITED | 09256462 | Windmill Hill Business Park, Whitehill Way, Swindon, Swindon, United Kingdom, SN5 6PB | Supplier; Virtual Lead Party | 12/11/2018 |
| EDINTORE WIND FARM LIMITED | SC432839 | c/o Robb Ferguson Regent Court, 70 West Regent Street, Glasgow , United Kingdom, G2 2QZ | Embedded Exemptable Large Power Station | 23/02/2015 |
| EDP RENEWABLES UK LIMITED | SC297087 | 1st Floor, 50 Lothian Roadnull, Edinburgh , EH3 9BY | Embedded Exemptable Large Power Station | 16/05/2014 |
| EEB15 LIMITED | 10789285 | THE OLD RECTORY CHURCH STREET, WEYBRIDGE , United Kingdom, KT13 8DE | Embedded Power Station | 28/11/2018 |
| EEB 19 LIMITED | 10978393 | THE OLD RECTORY, C HURCH STREET, WEYBRIDGE , UNITED KINGDOM, KT13 8DE | Embedded Power Station | 11/06/2019 |
| EEB57 Limited | 12559995 | The Old Rectory, Church Street, Weybridge, Surrey, United Kingdom, KT13 8DE | Directly Connected Power Station | 15/11/2023 |
| EEB68 LIMITED | 13207804 | THE OLD RECTORY CHURCH STREET, WEYBRIDGE , United Kingdom, KT13 8DE | Directly Connected Power Station | 31/01/2023 |
| EEB74 LIMITED | 13463938 | The Old Rectory, C hurch Street, Weybridge, Surrey, United Kingdom, KT13 8DE | Directly Connected Power Station | 20/02/2024 |
| EFW NESS LIMITED | SC627853 | 37 ALBYN PLACE, ABERDEEN , United Kingdom, AB10 1YN | Directly Connected Power Station | 20/08/2019 |
| EGGBOROUGH POWER LIMITED | 03782700 | Part Ground Floor, Paradigm Building 3175 Century Way, Thorpe Park, Leeds, LEEDS, United Kingdom, LS15 8ZB | Directly Connected Power Station | 18/09/2001 |
| EGNEDOL PEMBROKE ECO-POWER LIMITED | 09295745 | THE WHITE HOUSE WATERSTON ROAD, MILFORD HAVEN , United Kingdom, SA73 1DR | Directly Connected Power Station | 24/05/2017 |
| Eio Energy ApS | 43423320 | P.O. Pedersens Vej 2, Aarhus N, AARHUS, Denmark, 8200 | Interconnector User | 14/02/2024 |
| EIRGRID INTERCONNECTOR DESIGNATED ACTIVITY COMPANY | 473045 | The Oval, 160 Shelbourne Road, Ballsbridge, Dublin, Ireland, 4 | Interconnector Owner | 30/07/2010 |
| EKU ENERGY FAUNE PROJECTS (UK) LIMITED | 13361703 | The Corner Building, 91-93 Farringdon Road, London , United Kingdom, EC1M 3LN | Embedded Power Station | 23/02/2023 |
| EL (WEST WEYBRIDGE) LIMITED | 13327847 | 101 New Cavendish Street, 1st Floor South, London , United Kingdom, W1W 6XH | Directly Connected Power Station | 12/09/2023 |
| ELBESS LTD | 14484708 | Suite 7 7 Furze Hill House, Furze Hill, Hove, United Kingdom, BN3 1PU | Directly Connected Power Station | 03/02/2023 |
| ELCHIES WIND LIMITED | 06801474 | 2ND FLOOR, 36 BROADWAY, LONDON , UNITED KINGDOM, SW1H 0BH | Directly Connected Power Station | 03/08/2016 |
| ELECLINK LIMITED | 07595420 | 4 KINGDOM STREET, LONDON , United Kingdom, W2 6BD | Interconnector Owner | 07/12/2012 |
| ELECTRABEL | 0403.170.701 | Boulevard Simon Bolivar 36, Brussels , Belgium, 1000 | Interconnector User | |
| ELECTRICITY NORTH WEST LIMITED | 02366949 | Electricity North WestBorron Street, Stockport, Stockport, UK, SK1 2JD | Directly Connected Distribution System | 18/09/2001 |
| ELECTRICITY PLUS SUPPLY LIMITED | 05199936 | Network Hq 508 Edgware Road, The Hyde, London , United Kingdom, NW9 5AB | Supplier | 15/11/2004 |
| ELECTROROUTE ENERGY LIMITED | 10364177 | MID CITY PLACE, 71 HIGH HOLBORN, LONDON , UNITED KINGDOM, WC1V 6BA | Supplier | 08/11/2017 |
| ELECTROROUTE ENERGY TRADING LIMITED | 497188 | MARKET HOUSE, LETTERKENNY, DUBLIN 2, IRELAND, F92 C92T | Interconnector User | 13/12/2011 |
| ELEMENTS GREEN DEVELOPMENT LTD | 14167850 | 8 Queen Street, London , United Kingdom, W1J 5PD | Directly Connected Power Station | 13/06/2023 |
| ELEMENTS GREEN LIMITED | 13665201 | 8 QUEEN STREET, LONDON , United Kingdom, W1J 5PD | Directly Connected Power Station | 17/11/2022 |
| ELEMENTS GREEN TRENT LTD | 13665771 | 8 Queen Street, London , United Kingdom, W1J 5PD | Directly Connected Power Station | 15/12/2021 |
| ELGIN ENERGY ES CO LIMITED | 07176403 | Twp Accounting Llp, The Old Rectory, Church Street, Weybridge, Surrey, United Kingdom, KT13 8DE | Directly Connected Power Station | 22/12/2022 |
| ELMYA ENERGY UK 13 LIMITED | 14142768 | 6th Floor, 9 Appold Street, London , United Kingdom, EC2A 2AP | Directly Connected Power Station | 29/01/2025 |
| ELMYA ENERGY UK 17 LIMITED | 14535687 | 6th Floor, 9 Appold Street, London , United Kingdom, EC2A 2AP | Directly Connected Power Station | 02/12/2023 |
| ELMYA ENERGY UK 1 LIMITED | 14059656 | 6th Floor, 9 Appold Street, London , United Kingdom, EC2A 2AP | Directly Connected Power Station | 22/10/2024 |
| ELMYA RPC UK BRAYBROOKE LIMITED | 14142763 | 6th Floor, 9 Appold Street, London , United Kingdom, EC2A 2AP | Directly Connected Power Station | 11/04/2023 |
| ELMYA RPC UK GRANGE ROAD LIMITED | 14059907 | 6th Floor, 9 Appold Street, London , United Kingdom, EC2A 2AP | Directly Connected Power Station | 29/03/2023 |
| ELMYA RPC UK HUNTERSTON LIMITED | 14059815 | 6th Floor, 9 Appold Street, London , United Kingdom, EC2A 2AP | Directly Connected Power Station | 06/12/2022 |
| ELMYA RPC UK MELBOURNE LIMITED | 14059928 | 6th Floor, 9 Appold Street, London , United Kingdom, EC2A 2AP | Directly Connected Power Station | 28/03/2023 |
| ELMYA RPC UK MORNINGSIDE LIMITED | 14535749 | Princes House, S uite 2a, 38 Jermyn Street, London , United Kingdom, SW1Y 6DN | Directly Connected Power Station | 22/10/2024 |
| ELMYA RPC UK REDNAL LIMITED | 14142767 | 6th Floor, 9 Appold Street, London , EC2A 2AP | Directly Connected Power Station | 22/09/2023 |
| ELSTREE GREEN LIMITED | 12517332 | Ropemaker Place, 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 24/07/2020 |
| ELVANFOOT ENERGY STORAGE LIMITED | SC679842 | Muirhall Farm, Auchengray, Carnwath, Lanark, South Lanarkshire, United Kingdom, ML11 8LL | Directly Connected Power Station | 23/09/2021 |
| EnBW Energie Baden-Württemberg AG | HRB 107956 | Durlacher Allee 93, Karlsruhe, Karlsruhe, Germany, 76131 | Interconnector User | 03/10/2024 |
| ENDESA GENERACION SA | A82434697 | AVENIDA LA BORBOLLA, 5, SEVILLA , Spain, 41004 | Interconnector User | 25/10/2012 |
| ENECO BURN OF WHILK LIMITED | 08767037 | c/o Pinsent Masons Llp, 1 Park Row, Leeds , United Kingdom, LS1 5AB | Embedded Exemptable Large Power Station | 16/01/2015 |
| ENECO ENERGY TRADE B.V. | 30167836 | MARTEN MEESWEG 5, ROTTERDAM , Netherlands, 3068 AV | Interconnector User; Supplier | 28/09/2009 |
| ENECO MOY LIMITED | 07145797 | c/o Pinsent Masons, 1 Park Row, Leeds , United Kingdom, LS1 5AB | Embedded Power Station | 03/06/2015 |
| ENECO UK LIMITED | 06616497 | c/o Pinsent Masons, 1 Park Row, Leeds , United Kingdom, LS1 5AB | Directly Connected Power Station | 26/09/2011 |
| ENEL GLOBAL TRADING S.P.A. | IT05918271007 | VLE REGINA MARGHERITA 125, ROMA , Italy, 198 | Interconnector User | 21/10/2014 |
| ENEL X UK LIMITED | 06937931 | Epworth House 25 City Road, London, LONDON, UK, EC1Y 1AA | Virtual Lead Party | 18/08/2020 |
| Energetech Europe BV | 82542953 | Teleport Boulevard 124, 124-130, Office Unit 1.05, Amsterdam, Amsterdam, The Netherlands, 1043EJ | Interconnector User | 20/09/2023 |
| ENERGETECH TRADING DMCC | DMCC183541 | Cluster V, Dubai, Dubai, United Arab Emirates, N/A | Interconnector User | 10/06/2022 |
| ENERGETICK APS | 42643785 | Orientkaj 4, 1., Nordhavn , Denmark, 2150 | Interconnector User | 15/07/2022 |
| ENERGIA CUSTOMER SOLUTIONS NI LIMITED | NI35800 | Greenwood House, 64 Newforge Lane, Belfast , United Kingdom, BT9 5NF | Interconnector User | 04/03/2005 |
| ENERGI DANMARK A/S | 17225898 | TANGEN 29, AARHUS N, Danmark, Denmark, 8200 | Interconnector User | 04/04/2011 |
| ENERGIEKONTOR UK LTD | 03830819 | 114 St Martin's Lane, Covent Garden, London , United Kingdom, WC2N 4BE | Directly Connected Power Station | 02/12/2019 |
| Energi Generation 14 Ltd | 10702376 | 14 Beechwood Close, Lytham , United Kingdom, FY8 4BF | Directly Connected Power Station | 12/06/2023 |
| Energi Generation 6 Ltd | 10701876 | 14 Beechwood Close, Lytham , United Kingdom, FY8 4BF | Directly Connected Power Station | 20/11/2023 |
| ENERGY ASSETS NETWORKS LIMITED | 10068882 | SHIP CANAL HOUSE 98 KING STREET, MANCHESTER , United Kingdom, M2 4WU | Independent Distribution N/W Operator | 04/06/2019 |
| ENERGYA VM GESTION DE ENERGIA SLU | ES-B83393066 | CALLE FEDERICO MOMPOU, 5 ED 1 PLTA 4, MADRID, MADRID, Spain, 28050 | Interconnector User | 20/01/2014 |
| ENERGYFARM DIVOT HILL LTD | 15417775 | 4330 Park Approach, T horpe Park, Leeds , United Kingdom, LS15 8GB | Directly Connected Power Station | 21/11/2024 |
| ENERGYFARM ROWAN LLP | OC446822 | 4330 Park Approach, Thorpe Park, Leeds, United Kingdom, LS15 8GB | Directly Connected Power Station | 17/01/2024 |
| ENERGYFARM STRATH OYKEL LLP | OC446819 | 114 St Martin's Lane, London , United Kingdom, WC2N 4BE | Directly Connected Power Station | 14/01/2025 |
| ENERGYFARM UK ACHEILIDH LTD | 15087195 | 4330 Park Approach, Leeds , England, LS15 8GB | Directly Connected Power Station | 15/04/2025 |
| ENERGYFARM UK CORNHARROW LLP | OC428014 | 4330 PARK APPROACH, THORPE PARK, LEEDS , United Kingdom, LS15 8GB | Directly Connected Power Station | 20/03/2023 |
| ENERGYFARM UK CRAIGINMODDIE LLP | OC436174 | 4330 Park Approach, Thorpe Park, Leeds, United Kingdom, LS15 8GB | Directly Connected Power Station | 26/02/2024 |
| ENERGYFARM UK FELL LLP | OC429449 | 4330 PARK APPROACH, THORPE PARK, LEEDS , United Kingdom, LS15 8GB | Directly Connected Power Station | 15/02/2022 |
| ENERGYFARM UK GARBET LLP | OC429448 | 4330 PARK APPROACH, THORPE PARK, LEEDS , United Kingdom, LS15 8GB | Embedded Power Station | 14/10/2022 |
| ENERGYFARM UK GLENSHIMMEROCH LLP | OC428013 | 4330 PARK APPROACH, THORPE PARK, LEEDS , United Kingdom, LS15 8GB | Directly Connected Power Station | 22/06/2020 |
| ENERGYFARM UK HARE CRAIG LLP | OC429444 | 4330 PARK APPROACH, THORPE PARK, LEEDS , United Kingdom, LS15 8GB | Directly Connected Power Station | 26/11/2021 |
| ENERGYFARM UK LAIRG LLP | OC428012 | 4330 PARK APPROACH, THORPE PARK, LEEDS , United Kingdom, LS15 8GB | Directly Connected Power Station | 01/04/2021 |
| ENERGYFARM UK MANQUHILL LTD | 15408800 | 4330 Park Approach, Thorpe Park, Leeds , United Kingdom, LS15 8GB | Directly Connected Power Station | 21/11/2024 |
| ENERGYFARM UK MARGREE LLP | OC436123 | 4330 Park Approach, Thorpe Park, Leeds , United Kingdom, LS15 8GB | Directly Connected Power Station | 14/01/2022 |
| ENERGYFARM UK NARACHAN LLP | OC429447 | 4330 PARK APPROACH, THORPE PARK, LEEDS , United Kingdom, LS15 8GB | Embedded Power Station | 31/10/2022 |
| ENERGYFARM UK OVERHILL LLP | OC428015 | 4330 PARK APPROACH, THORPE PARK, LEEDS , United Kingdom, LS15 8GB | Directly Connected Power Station | 22/06/2020 |
| ENERGYGRIDPOWER2 LTD | 13292361 | Suite 1, 3rd Floor, 11-12 St. James's Square, London , United Kingdom, SW1Y 4LB | Directly Connected Power Station | 14/10/2021 |
| ENERGYGRIDPOWER3 LTD | 13291849 | Suite 1, 7th Floor, 50 Broadway, 11 - 12 St. James's Square, London , United Kingdom, SW1H OBL | Directly Connected Power Station | 14/10/2021 |
| ENERGYGRIDPOWER LTD | 13291845 | Suite 1, 3rd Floor, 11 - 12 St. James's Square, LONDON , United Kingdom, SW1Y 4LB | Directly Connected Power Station | 09/11/2021 |
| ENERGYHUBDEVELOPMENTS LIMITED | 13028274 | 19 Friar Road, Brighton , United Kingdom, BN1 6NG | Directly Connected Power Station | 03/02/2023 |
| ENERGY ISLES SHETLAND LIMITED | 12044893 | 19TH FLOOR 22 BISHOPSGATE, LONDON , UNITED KINGDOM, EC2N 4BQ | Directly Connected Power Station | 06/02/2020 |
| ENERGY POWER RESOURCES LIMITED | 03302734 | 6th Floor, 33 Holborn, London , United Kingdom, EC1N 2HT | Embedded Power Station | 18/09/2001 |
| Energy UK Fell LLP | OC429449 | 4330 Park Approach, Thorpe Park, Leeds , United Kingdom, LS15 8GB | Directly Connected Power Station | 15/02/2024 |
| ENEUS ENERGY LIMITED | SC739030 | Suite 2, Ground Floor, Orchard Brae House, 30 Queensferry Road, Edinburgh , United Kingdom, EH4 2HS | Directly Connected Power Station | 26/03/2025 |
| ENGELHART CTP (SWITZERLAND) SA | CHE-275.115.728 | ROUTE DE PRE-BOIS 29, WORLD TRADE CENTER II, COINTRIN , Switzerland, 1216 | Interconnector User | 16/12/2015 |
| ENGIE ENERGY MANAGEMENT | 831958211 | BOULEVARD SIMON BOLIVAR 34, BRUXELLES, BRUXELLES, Belgium, 1000 | Interconnector User | 20/01/2017 |
| ENGIE GLOBAL MARKETS | B437982937 | 1 PL SAMUEL DE CHAMPLAIN, COURBEVOIE , France, 92400 | Interconnector User | 09/09/2002 |
| Engie Power Limited | 04236804 | No. 1 Leeds, 26 Whitehall Road, Leeds , United Kingdom, LS12 1BE | Supplier | 25/03/2005 |
| Enki Trading s.r.o | 28664779 | Hybernská 1034/5, Prague, Prague, Czech Republic, 110 00 | Interconnector User | 04/01/2023 |
| ENRAY POWER LTD | 13052159 | Magma House, 1 6 Davy Court, Castle Mound Way, Rugby , United Kingdom, CV23 0UZ | Directly Connected Power Station | 24/01/2024 |
| ENSCO ENERGY SERVICES COMPANY AG | CHE-485.204.837 | RIGISTRASSE 3, ZUG , Switzerland, 6300 | Interconnector User | 29/09/2021 |
| ENSO GREEN HOLDINGS A LIMITED | 12759332 | Ropemaker Place, 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 23/10/2020 |
| ENSO GREEN HOLDINGS B LIMITED | 12763872 | Ropemaker Place, 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 04/12/2020 |
| ENSO GREEN HOLDINGS C LIMITED | 12761273 | Ropemaker Place, 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 07/12/2020 |
| ENSO GREEN HOLDINGS D LIMITED | 12762856 | Ropemaker Place, 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 02/12/2020 |
| ENSO GREEN HOLDINGS F LIMITED | 12764449 | Ropemaker Place, 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 05/11/2020 |
| ENSO GREEN HOLDINGS G LIMITED | 12768166 | Ropemaker Place, 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 22/03/2021 |
| ENSO GREEN HOLDINGS H LIMITED | 12767586 | 17th Floor Hylo, 103-105 Bunhill Row, London , United Kingdom, EC1Y 8LZ | Directly Connected Power Station | 19/09/2024 |
| ENSO GREEN HOLDINGS I LIMITED | 12758956 | 17th Floor Hylo, 103-105 Bunhill Row, London , United Kingdom, EC1Y 8LZ | Directly Connected Power Station | |
| ENSO GREEN HOLDINGS K LIMITED | 12763391 | 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 15/10/2019 |
| ENSO GREEN HOLDINGS LIMITED | 12153574 | Ropemaker Place, 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 15/10/2019 |
| ENSO GREEN HOLDINGS N LIMITED | 12767316 | 17th Floor Hylo, 103-105 Bunhill Row, London , Unted Kingdom, EC1Y 8LZ | Directly Connected Power Station | 17/12/2024 |
| ENSO GREEN HOLDINGS Q LIMITED | 13327737 | 17th Floor Hylo, 103-105 Bunhill Row, London , United Kingdom, EC1Y 8LZ | Directly Connected Power Station | 01/07/2024 |
| ENSO GREEN HOLDINGS R LIMITED | 13328511 | Ropemaker Place, 28 Ropemaker Street,, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 14/04/2022 |
| ENSO GREEN HOLDINGS V LIMITED | 13328563 | 17th Floor Hylo, 103-105 Bunhill Row, London , United Kingdom, EC1Y 8LZ | Directly Connected Power Station | 01/07/2024 |
| ENSO GREEN HOLDINGS W LIMITED | 13328645 | 17th Floor Hylo 103-105 Bunhill Row, London , United Kingdom, EC1Y 8LZ | Directly Connected Power Station | 18/03/2025 |
| ENSO GREEN HOLDINGS X LIMITED | 13328111 | ROPEMAKER PLACE, LONDON , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 03/11/2021 |
| ENSO GREEN HOLDINGS Z LIMITED | 13328913 | ROPEMAKER PLACE, LONDON , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 19/12/2024 |
| Enviromena Project Management UK Limited | 12079566 | 15 Diddenham Court, Lambwood Hill, Grazeley, Berkshire, United Kingdom, RG7 1JQ | Directly Connected Power Station | 11/12/2023 |
| ENZEE Commodities A/S | 42676330 | Aboulevarden 3,1 sal, Aarhus C , Denmark, 8000 | Interconnector User | 08/11/2023 |
| EOLFI SAS | 477 951 644 | 10 Place de Catalogne, Paris , France, 75014 | Directly Connected Power Station | 11/10/2021 |
| EP COMMODITIES, A.S. | 3437680 | KLIMENTSKA 1216/46, PRAHA 1 , Czech Republic, 11000 | Interconnector User | 15/07/2021 |
| EPG ENERGY LIMITED | 06616147 | Hurst House, 131-133 New London Road, Chelmsford, Essex, United Kingdom, CM2 0QT | Supplier | |
| EP LANGAGE LIMITED | 03462783 | Byron House, 7 - 9 St. James's Street, London , United Kingdom, SW1A 1EE | Directly Connected Power Station | 18/09/2001 |
| EPL NEWCO5 LIMITED | 14062571 | 2nd Floor, R egis House, 4 5 King William Street, London , United Kingdom, EC4R 9AN | Directly Connected Power Station | 11/07/2023 |
| EPL NEWCO6 LIMITED | 14062645 | 2nd Floor, R egis House, 4 5 King William Street, London , United Kingdom, EC4R 9AN | Directly Connected Power Station | 11/07/2023 |
| EPL NEWCO7 LIMITED | 14115311 | 2nd Floor Regis House, 45 King William Street, London , EC4R 9AN | Directly Connected Power Station | 25/09/2024 |
| EPL NEWCO8 LIMITED | 14117875 | 2nd Floor, Regis House, 4 5 King William Street, London , United Kingdom, EC4R 9AN | Directly Connected Power Station | 09/11/2023 |
| EPL NEWCO9 LIMITED | 14117944 | 2nd Floor, Regis House, 4 5 King William Street, London , United Kingdom, EC4R 9AN | Directly Connected Power Station | 09/11/2023 |
| E Power Limited | 04625938 | 6th Floor 17a Curzon Street, London , United Kingdom, W1J 5HS | Directly Connected Power Station | 25/08/2022 |
| EPPING ENERGY PARK LIMITED | 14370231 | 1st Floor Sackville House, 143-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 26/05/2023 |
| EPR EYE LIMITED | 02234141 | 6th Floor, 33 Holborn, London , United Kingdom, EC1N 2HT | Embedded Power Station | |
| EPR GLANFORD LIMITED | 02547498 | 6th Floor, 33 Holborn, London , United Kingdom, EC1N 2HT | Embedded Power Station | 18/09/2001 |
| EPR THETFORD LIMITED | 03057688 | 6th Floor, 33 Holborn, London , United Kingdom, EC1N 2HT | Embedded Power Station | 18/09/2001 |
| EP SHB LIMITED | 02571241 | Byron House, 7 - 9 St. James's Street, London , United Kingdom, SW1A 1EE | Directly Connected Power Station | 18/09/2001 |
| Epsilon Generation Limited | 11118545 | THE OLD RECTORY CHURCH STREET, WEYBRIDGE , United Kingdom, KT13 8DE | Embedded Power Station | 10/11/2022 |
| EP UK POWER DEVELOPMENT LTD | 10808313 | Byron House, 7 - 9 St. James's Street, London , United Kingdom, SW1A 1EE | Directly Connected Power Station | 03/08/2017 |
| EQUINICITY LTD | 11374646 | The Quadrangle Imperial Square, Cheltenham, Cheltenham, United Kingdom, GL50 1PZ | Supplier | 29/10/2019 |
| Equinix (LD-A) Limited | OE005938 | 44 Esplanade, Saint Helier , Jersey, JE4 9WU | Non-Embedded Customer Site | 22/08/2024 |
| EQUINOR NEW ENERGY LIMITED | 06824625 | 1 Kingdom Streetnull, London , W2 6BD | Directly Connected Power Station | 02/05/2019 |
| EROVA ENERGY LIMITED | 557068 | Molesworth House, 1 -2 South Frederick Street, Dublin , Ireland, D02 N820 | Interconnector User; Virtual Lead Party | 25/04/2017 |
| ER PROJECT DEVELOPMENT CO LIMITED | 14420107 | The Barn, F ord Farm, Aldbourne, Marlborough, United Kingdom, SN8 2DP | Directly Connected Power Station | 31/05/2023 |
| ESB ASSET DEVELOPMENT UK LIMITED | 06925667 | Tricor Suite 4th Floor, 50 Mark Lane, London , United Kingdom, EC3R 7QR | Directly Connected Power Station | 14/09/2018 |
| ESBI CONTRACTING LIMITED | 200660 | 27 FITZWILLIAM STREET LOWER, DUBLIN 2 , IRELAND, D02 KT92 | Directly Connected Power Station; Dormant CUSC Party | 21/07/2008 |
| ESB INDEPENDENT ENERGY (NI) LIMITED | 252609 | 27 FITZWILLIAM STREET LOWER, DUBLIN 2 , IRELAND, D02 KT92 | Interconnector User | 04/03/2005 |
| ESB INDEPENDENT GENERATION TRADING LIMITED | 466142 | 27 FITZWILLIAM STREET LOWER, DUBLIN 2 , IRELAND, D02 KT92 | Embedded Power Station | 08/06/2017 |
| ESGAIR GALED ENERGY PARK LIMITED | 13153937 | Hodge House, Guildhall Place, Cardiff , United Kingdom, CF10 1DY | Embedded Power Station | 03/09/2021 |
| ESP ELECTRICITY LIMITED | 04718806 | 1st Floor, Bluebird House, M ole Business Park, Leatherhead, Surrey, United Kingdom, KT22 7BA | Independent Distribution N/W Operator | 19/07/2018 |
| ESSO PETROLEUM COMPANY,LIMITED | 00026538 | Ermyn House, Ermyn Way, Leatherhead, Surrey, United Kingdom, KT22 8UX | Embedded Power Station | 26/02/2010 |
| ETP UK 1 LTD | 14548137 | 17 Grosvenor Street, Mayfair, London , United Kingdom, W1K 4QG | Directly Connected Power Station | 15/06/2023 |
| ETP UK 2 LTD | 14545198 | 17 Grosvenor Street, Mayfair, London, United Kingdom, W1K 4QG | Directly Connected Power Station | 04/09/2023 |
| EUROPEAN COMMODITY CLEARING AG | HRB 22362 | AUGUSTUSPLATZ 9, LEIPZIG , Germany, DE-04109 | Interconnector User | 25/07/2013 |
| EVOLUTION POWER LIMITED | 13544817 | 2nd Floor, R egis House, 4 5 King William Street, London , United Kingdom, EC4R 9AN | Directly Connected Power Station | 06/03/2023 |
| EWII Energi A/S | DK20810440 | Kokbjerg 30, Kolding, KOLDING, Denmark, 6000 | Interconnector User | 02/04/2024 |
| Exagen Development Limited | 11698003 | 71 - 75 Shelton Street, London , United Kingdom, WC2H 9JQ | Directly Connected Power Station | 01/08/2022 |
| EXAGEN GROUP LIMITED | 12783713 | 71-75 Shelton Street Covent Garden, London , WC2H 9JQ | Directly Connected Power Station | 16/12/2024 |
| EXERGY SOLUTIONS LIMITED | 13532972 | 2.18 Trafford House Chester RoadOld Trafford, Stretford, Greater Manchester, UK, M32 0RS | Virtual Lead Party | 15/11/2023 |
| EXETER MAIN BATTERY LIMITED | 12368146 | 22 CHANCERY LANE, LONDON , United Kingdom, WC2A 1LS | Directly Connected Power Station | 04/12/2020 |
| Exeter Storage Limited | 13869756 | 4th Floor 80 Victoria Street, London , United Kingdom, SW1E 5JL | Directly Connected Power Station | 14/07/2022 |
| EXPRESS DISTRIBUTION PARK LTD | 13410141 | 4 King Square, Bridgwater , TA6 3YF | Directly Connected Power Station | 04/11/2024 |
| EXXONMOBIL CHEMICAL LIMITED | 00867162 | Ermyn House, Ermyn Way, Leatherhead , United Kingdom, KT22 8UX | Non-Embedded Customer Site | 31/03/2005 |
| EXXONMOBIL GAS MARKETING EUROPE LIMITED | 02517230 | Ermyn House, Ermyn Way, Leatherhead, Surrey, UK, KT22 8UX | Interconnector User | 08/05/2024 |
| Ezpada AG | CHE-110.624.390 | Baarerstrasse 139, Zug, ZUG, Switzerland, 6300 | Interconnector User | 03/10/2024 |
| F & S ENERGY LIMITED | 07524841 | 87-91 Springfield Roadnull, Chelmsford, CHELMSFORD , CM2 6JL | Supplier | 01/02/2013 |
| FAB LINK LIMITED | 54637 | c/o Collas Crill Trust Limited, G lategny Court, G lategny Esplanade, St Peter Port , Guernsey (United Kingdom), GY1 1WR | Interconnector Owner | 27/01/2014 |
| Fairways Battery Storage Ltd | SC716348 | The Shires, 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Embedded Exemptable Large Power Station | 04/01/2023 |
| FALKIRK POWER LTD | 13321637 | The Factory, Whitchurch, Ross-on-Wye, Herefordshire, United Kingdom, HR9 6DF | Embedded Power Station | 06/10/2022 |
| FALLAGO RIG WINDFARM LIMITED | SC226523 | Atria One, Level 7, 144 Morrison Street, Edinburgh , United Kingdom, EH3 8EX | Directly Connected Power Station | 21/10/2010 |
| FARMOOR ENERGY LIMITED | 07111074 | Drax Power Station, Drax, Selby, North Yorkshire, United Kingdom, YO8 8PH | Supplier | 11/04/2013 |
| FARRINGDON ENERGY LIMITED | 09256369 | Endeavour House 3rd Floor, Coopers End Road, Stansted , United Kingdom, CM24 1SJ | Supplier | 16/03/2020 |
| FARR WINDFARM LIMITED | SC166005 | 50 Lothian Road, Festival Square, Edinburgh , United Kingdom, EH3 9WJ | Directly Connected Power Station | 02/08/2005 |
| FASNAKYLE BATTERY STORAGE LIMITED | SC725349 | 33 BOTHWELL ROAD, HAMILTON , United Kingdom, ML3 0AS | Embedded Power Station | 20/01/2023 |
| FEARNA PSH LIMITED | 14819538 | No.1 Forbury Place, 4 3 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 24/04/2024 |
| FENWICK SOLAR PROJECT LIMITED | 13705886 | 5e Park Farm, Chichester Road, Arundel , United Kingdom, BN18 0AG | Directly Connected Power Station | 03/10/2023 |
| FERRYMUIR ENERGY STORAGE LIMITED | 11194667 | 8th Floor, 100 Bishopsgate, London , United Kingdom, EC2N 4AG | Embedded Exemptable Large Power Station | 30/09/2020 |
| FETTERESSO WIND LIMITED | 06801490 | 2ND FLOOR, 36 BROADWAY, LONDON , United Kingdom, SW1H 0BH | Embedded Exemptable Large Power Station | 10/10/2014 |
| FIDDLERS FERRY LTD | 14385301 | The Factory, Whitchurch, Ross-on-Wye, Herefordshire, United Kingdom, HR9 6DF | Directly Connected Power Station | 27/03/2023 |
| FIELD AUCHTERAW LTD. | SC621663 | 9th Floor, 41 West Campbell Street, Glasgow , United Kingdom, G2 6SE | Embedded Exemptable Large Power Station | 01/10/2021 |
| FIELD CORRIEMOILLIE LTD | 15258085 | Montacute Yards, 1 85-186 Shoreditch High Street, London , United Kingdom, E1 6HU | Directly Connected Power Station | 23/01/2025 |
| FIELD DEVCO LTD | 14347177 | Fora Montacute Yards, Shoreditch High St, London , United Kingdom, E1 6HU | Directly Connected Power Station | 08/08/2023 |
| Field Devco Ltd | 14347177 | Fora Montacute YardsShoreditch High St, London , E1 6HU | Directly Connected Power Station | 17/03/2025 |
| Field Drum Farm Ltd | SC721836 | 9th Floor, 41 West Campbell Street, West Campbell Street, Glasgow , United Kingdom, G2 6SE | Embedded Power Station | 31/10/2023 |
| FIELD HARTMOOR LTD | 13995703 | Fora Montacute Yards, Shoreditch High Street, London , United Kingdom, E1 6HU | Directly Connected Power Station | 18/03/2023 |
| FIELD KNOCKNAGAEL LTD | 15249773 | Montacute Yards, 1 85-186 Shoreditch High Street, London , United Kingdom, E1 6HU | Directly Connected Power Station | 10/05/2023 |
| Fig Power Limited | 13879348 | Finzels Reach, Counterslip, Bristol, United Kingdom, BS1 6BX | Embedded Power Station | 03/07/2024 |
| Firma Vogt Solar Ltd | 13979492 | 14A High Cross, Truro, Cornwall, United Kingdom, TR1 2AJ | Directly Connected Power Station | 13/02/2024 |
| First Hydro Company | 02444277 | Dinorwig Power StationLlanberis, Gwynedd, Gwynedd, UK, LL55 4TY | Directly Connected Power Station | 18/09/2001 |
| FIRSTWAY SOLAR LTD | 14056763 | 67 Westow Street, London , United Kingdom, SE19 3RW | Directly Connected Power Station | 12/08/2024 |
| Fishcross Generation Limited | SC604768 | Clyde View (Suite F3), Riverside Business Park, 22 Pottery Street, Greenock , United Kingdom, PA15 2UZ | Directly Connected Power Station | 30/07/2024 |
| FIVE ESTUARIES OFFSHORE WIND FARM LIMITED | 12292474 | Windmill Hill Business Park, Whitehill Way, Swindon , United Kingdom, SN5 6PB | Directly Connected Power Station | 08/09/2020 |
| FLAVUSIA LTD | 15594838 | 2 Upperton Gardens, Eastbourne , United Kingdom, BN21 2AH | Directly Connected Power Station | 23/07/2024 |
| Fleet Green Limited | 12725583 | Ropemaker Place, 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 01/07/2024 |
| FLEET SOLAR LIMITED | 12368193 | 22 CHANCERY LANE, LONDON , UNITED KINGDOM, WC2A 1LS | Directly Connected Power Station | 04/12/2020 |
| Flemyland Battery Storage Ltd | SC729992 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Directly Connected Power Station | 02/03/2023 |
| FLEXIBLE GENERATION 1 LTD | 14247769 | 4th Floor 80 Victoria Street, London , United Kingdom, SW1E 5JL | Directly Connected Power Station | 15/05/2023 |
| FLEXIBLEGRIDPOWER2 LTD | 10683876 | Suite 1 3rd Floor, 11-12 St James’s Square, London , United Kingdom, SW1Y 4LB | Directly Connected Power Station | 21/07/2020 |
| FLEXIBLEGRIDPOWER LTD | 10683796 | Suite 1 3rd Floor, 11-12 St James’s Square, London , United Kingdom, SW1Y 4LB | Non-Embedded Customer Site | 12/03/2021 |
| FLEXION ENERGY SPV 2 LTD | 14073230 | 27 Old Gloucester Street, London , United Kingdom, WC1N 3AX | Embedded Power Station | 21/08/2023 |
| FLEXION ENERGY UK STORAGE LTD | 13492210 | 27 Old Gloucester Street, London , United Kingdom, WC1N 3AX | Embedded Exemptable Large Power Station | 06/03/2023 |
| FLEXITRICITY LIMITED | SC263298 | Mainpoint, 1 02 West Port, Edinburgh, Edinburgh, United Kingdom, EH3 9DN | Supplier; Virtual Lead Party | 24/09/2018 |
| Flooring Porter Ltd | 13342788 | 88 Grays Inn Road, London , United Kingdom, WC1X 8AA | Directly Connected Power Station | 18/04/2023 |
| FLOTATION ENERGY LIMITED | SC597702 | 12 Alva Street, Edinburgh , United Kingdom, EH2 4QG | Directly Connected Power Station | 16/08/2021 |
| FOEL FACH WIND FARM LIMITED | 14144097 | 22-24 King Street, Maidenhead, Berkshire, United Kingdom, SL6 1EF | Directly Connected Power Station | 27/11/2024 |
| FOREPOWER LINCOLN (250) LIMITED | 13932692 | Medforth House, C atfoss Lane, Brandesburton, Driffield, United Kingdom, YO25 8ES | Directly Connected Power Station | 06/12/2024 |
| Forestry Finance Ltd | 13597923 | 7 Queen Annes Grove, London , United Kingdom, W4 1HW | Directly Connected Power Station | 21/12/2022 |
| FORSA ENERGY GAS HOLDINGS LIMITED | 10913384 | Masters House107 Hammersmith Road, London, LONDON, UK, W14 0QH | Directly Connected Power Station | 30/10/2024 |
| FORTUM GLASGOW LIMITED | 10359853 | 4th Floor, Phoenix House, 1 Station Hill, Reading, Berkshire, United Kingdom, RG1 1NB | Embedded Exemptable Large Power Station | 04/07/2018 |
| FOSSE GREEN ENERGY LIMITED | 13438725 | S10 Blyth Workspace Commissioners Quay, Quay Road, Blyth , United Kingdom, NE24 3AF | Directly Connected Power Station | 24/11/2022 |
| FOUNDDIGITAL DS LIMITED | 10767987 | 63/66 Hatton Garden, Fifth Floor, Suite 23, London , United Kingdom, EC1N 8LE | Dormant CUSC Party; Non-Embedded Customer Site | 16/04/2021 |
| Found Digital DS Ltd | 10767987 | 63/66 Hatton Garden, Fifth Floor, Suite 23,, London , United Kingdom, EC1N 8LE | Non-Embedded Customer Site | 16/04/2021 |
| FOXGLOVE ENERGY SUPPLY LTD | 09689035 | 16 North Mills, Frog Island, Leicester , United Kingdom, LE3 5DL | Supplier | |
| FPC ELECTRIC LAND LIMITED | 09542958 | 101 New Cavendish Street1st Floor South, London , W1W 6XH | Directly Connected Power Station | 10/01/2023 |
| FRASERBURGH ENERGY LTD | 13453110 | Temporis Capital, Wellingon House, 125-130 Strand,, London, London , WC2R OAP | Dormant CUSC Party | 21/03/2022 |
| FREASDAIL ENERGY LIMITED | 09605716 | Beaufort Court, Egg Farm Lane, Kings Langley, Hertfordshire, United Kingdom, WD4 8LR | Directly Connected Power Station | 09/03/2016 |
| FRED. OLSEN RENEWABLES LIMITED | 13633932 | 64-65 VINCENT SQUARE, LONDON , United Kingdom, SW1P 2NU | Directly Connected Power Station | 05/01/2023 |
| FRED OLSEN SEAWIND LIMITED | 02672436 | 2ND FLOOR, 36 BROADWAY, LONDON , United Kingdom, SW1H 0BH | Directly Connected Power Station | 17/11/2021 |
| FREEPOINT COMMODITIES EUROPE LLP | OC367926 | 62 BUCKINGHAM GATE, LONDON, LONDON, United Kingdom, SW1E 6AJ | Interconnector User | 06/02/2013 |
| Frodsham Devco Limited | 15999224 | First Floor, 5 Fleet Place, London , United Kingdom, EC4M 7RD | 04/03/2025 | |
| Frodsham Solar Limited | 14432433 | 70 St Mary Axe, London , United Kingdom, EC3A 8BE | Embedded Power Station | 09/04/2024 |
| FRONTIER POWER INTERNATIONAL LIMITED | 10917493 | The American Barns, Banbury Road, L ighthorne, Warwick , United Kingdom, CV35 0AE | Interconnector Owner | 21/08/2020 |
| FRV TH Powertek Limited | 14161993 | Parkes & Swan Limited The Officers' Mess, Coldstream Road,, Caterham , CR3 5QX | Directly Connected Power Station | 19/12/2023 |
| FRV Tyler Hill BESS 1 Ltd | 13869939 | C/O Parkes & Swan Limited, The Officers Mess, , CR3 5QX, Caterham | Directly Connected Power Station | 19/09/2024 |
| FS WEST GOURDIE LIMITED | 12356268 | The Long Barn, Manor Courtyard, Stratton-On-The-Fosse, Radstock, United Kingdom, BA3 4QF | Embedded Exemptable Large Power Station | 23/12/2020 |
| FUSE ENERGY SUPPLY LIMITED | 08469701 | Fuse Energy, Level39 One Canada SquareCanary Wharf, London, London , E14 5AB | Supplier | 16/05/2022 |
| FUTURE ENERGY LLANWERN LIMITED | 11578319 | Hailstone House, Hailstone Hill, Nr Cricklade, Wiltshire, United Kingdom, SN6 6JP | Directly Connected Power Station | 15/05/2019 |
| FUTURE POWER ENTERPRISES LTD | 14884426 | Temporis Capital, Wellington House, 125-130 Strand, London , United Kingdom, WC2R 0AP | Directly Connected Power Station | 04/12/2024 |
| GALAWHISTLE WIND FARM LIMITED | 07715284 | Connect House, 133-137 Alexandra Road, Wimbledon, London, United Kingdom, SW19 7JY | Directly Connected Power Station | 01/12/2011 |
| GALILEO 01 LIMITED | SC738436 | 7-9 North St. David Street, Edinburgh , United Kingdom, EH2 1AW | Directly Connected Power Station | 05/09/2023 |
| GALILEO 02 LIMITED | SC738437 | 7-9 North St. David Street, Edinburgh , United Kingdom, EH2 1AW | Directly Connected Power Station | 04/06/2024 |
| GALILEO 04 LIMITED | SC761010 | 7-9 North St. David Street, Edinburgh , United Kingdom, EH2 1AW | Directly Connected Power Station | 13/09/2023 |
| GALILEO 05 LIMITED | SC761068 | 7-9 North St. David Street, Edinburgh , United Kingdom, EH2 1AW | Directly Connected Power Station | 14/11/2024 |
| GALILEO 07 LIMITED | SC761089 | 7-9 North St. David Street, Edinburgh , United Kingdom, EH2 1AW | Directly Connected Power Station | 02/04/2025 |
| GALILEO 09 LIMITED | 14710288 | C12 Cathedral Road, Cardiff , United Kingdom, CF11 9LJ | Directly Connected Power Station | 27/01/2025 |
| GALILEO 10 LIMITED | SC761091 | 7-9 North St. David Street, Edinburgh , United Kingdom, EH2 1AW | Directly Connected Power Station | 08/05/2024 |
| GALILEO 12 LIMITED | SC783153 | 7-9, North St. David Street, Edinburgh , United Kingdom, EH2 1AW | Directly Connected Power Station | 02/12/2024 |
| GALILEO 13 LIMITED | SC783292 | 7-9 North St. David Street, Edinburgh , United Kingdom, EH2 1AW | Directly Connected Power Station | 05/04/2024 |
| GALILEO 15 LIMITED | 15358916 | C12 Cathedral Road, Cardiff , United Kingdom, CF11 9LJ | Directly Connected Power Station | 05/03/2025 |
| GALILEO 16 LIMITED | SC792765 | 7-9 North St. David Street, Edinburgh , United Kingdom, EH2 1AW | Directly Connected Power Station | 27/03/2025 |
| Galileo Empower UK Limited | SC683992 | 7-9 North St. David Street, Edinburgh , United Kingdom, EH4 1AW | Directly Connected Power Station | 28/02/2024 |
| GALLOPER WIND FARM LIMITED | 07320597 | Windmill Hill Business Park, Whitehill Way, Swindon , United Kingdom, SN5 6PB | Directly Connected Power Station | |
| GARREG FAWR ENERGY PARK LIMITED | 13052403 | HODGE HOUSE GUILDHALL PLACE, CARDIFF , United Kingdom, CF10 1DY | Embedded Power Station | 03/06/2021 |
| GARSCADDEN PARK LIMITED | SC665314 | 200 St. Vincent Street, Glasgow , United Kingdom, G2 5SG | Directly Connected Power Station | 04/10/2024 |
| GARVARY WIND FARM LTD | 09749336 | 22-24 King Street, Maidenhead, Berkshire, United Kingdom, SL6 1EF | Directly Connected Power Station | 04/05/2022 |
| GATE BURTON ENERGY PARK LIMITED | 12660764 | Stirling Square, 5-7 Carlton Gardens, London , United Kingdom, SW1Y 5AD | Directly Connected Power Station | 03/06/2021 |
| GATEWAY ENERGY CENTRE LIMITED | 07146501 | 30 Crown Place, Earl Street, London , United Kingdom, EC2A 4ES | Directly Connected Power Station | 04/09/2014 |
| GATROBEN OFFSHORE DEVELOPMENTS 2 LIMITED | 13587611 | No.1 Forbury Place, 4 3 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 06/10/2021 |
| GAZPROM MARKETING & TRADING LIMITED | 03768267 | 20 TRITON STREET, LONDON, London, United Kingdom, NW1 3BF | Interconnector User; Virtual Lead Party | 20/12/2007 |
| GEN-I, trgovanje in prodaja električne energije, d.o.o. | 1587714000 | Vrbina 17, Krsko, Krsko, Slovenia, 8270 | Interconnector User | 13/02/2025 |
| Geocore (Newarthill) Ltd | SC772814 | 21 Melville Street, Edinburgh , United Kingdom, EH3 7PE | Directly Connected Power Station | 23/02/2024 |
| Geocore Ltd | SC711786 | 21 Melville Street, Edinburgh , United Kingdom, EH3 7PE | Directly Connected Power Station | 07/12/2022 |
| GETLINK PROJECTS 2 LIMITED | 15001715 | Uk Terminal;Ashford Road, Folkestone , CT18 8XX | Interconnector Owner | 12/09/2024 |
| GF Norwich Energy Ltd | 14824334 | 20-22 Wenlock Road, London , United Kingdom, N1 7GU | Directly Connected Power Station | 07/02/2024 |
| GF Sellindge Energy Ltd | 14824340 | 20-22 Wenlock Road, London , N1 7GU | Directly Connected Power Station | 04/10/2024 |
| GF THORNTON ENERGY LTD | 14754797 | 20-22 Wenlock Road, London , United Kingdom, N1 7GU | Directly Connected Power Station | 23/10/2023 |
| GIGABOX DEVELOPMENTS LIMITED | 11731923 | 1st Floor Midland House, 7 7 Huddersfield Road, Mirfield, West Yorkshire, United Kingdom, WF14 8BL | Embedded Exemptable Large Power Station | 29/10/2019 |
| GIGABOX NO 5 LIMITED | 13614175 | 1st Floor Midland House, 77 Huddersfield Road, Mirfield, West Yorkshire, United Kingdom, WF14 8BL | Embedded Exemptable Large Power Station | 20/05/2022 |
| GILKES ENERGY LIMITED | 03203285 | Canal Head North, Kendal, Cumbria, United Kingdom, LA9 7BZ | Directly Connected Power Station | 07/11/2022 |
| GLAXO OPERATIONS LTD | 00711851 | 980 Great West Road, Brentford , United Kingdom, TW8 9GS | Embedded Exemptable Large Power Station | 25/07/2023 |
| GLENCHAMBER WIND ENERGY LIMITED | 08986190 | Beaufort Court, Egg Farm Lane, Kings Langley, Hertfordshire, United Kingdom, WD4 8LR | Directly Connected Power Station | 03/12/2014 |
| GLENCORE ENERGY UK LTD. | 04542769 | 18 HANOVER SQUARE, LONDON , United Kingdom, W1S 1JY | Interconnector User | 12/07/2022 |
| GLENDEVON ENERGY STORAGE LIMITED | 13146302 | c/o Foresight Group Llp, T he Shard, 32 London Bridge Street, London , United Kingdom, SE1 9SG | Embedded Exemptable Large Power Station | 16/06/2021 |
| GLENDOE STORAGE LIMITED | 13869958 | 4th Floor 80 Victoria Street, London , United Kingdom, SW1E 5JL | Directly Connected Power Station | 03/03/2022 |
| GLENDYE WIND FARM LIMITED | 09171944 | 22-24 King Street, Maidenhead, Berkshire, United Kingdom, SL6 1EF | Directly Connected Power Station | 05/05/2022 |
| GLEN EARRACH ENERGY LIMITED | SC777268 | 50 Lothian Road;Festival Square, Edinburgh , EH3 9WJ | Directly Connected Power Station | 06/02/2025 |
| GLEN KYLLACHY WIND FARM LIMITED | 11914689 | 27-28 EASTCASTLE STREET, LONDON , United Kingdom, W1W 8DH | Directly Connected Power Station | 16/05/2019 |
| Glen Lednock Wind Farm Limited | 15296141 | Stirling Square, 5 -7 Carlton Gardens, London , United Kingdom, SW1Y 5AD | Directly Connected Power Station | 14/08/2024 |
| GLENMUCKLOCH PUMPED STORAGE HYDRO LIMITED | SC522520 | c/o Foresight Group, Clarence House,1 31-135 George Street, Edinburgh , United Kingdom, EH2 4JS | Directly Connected Power Station | 01/04/2016 |
| GLENMUCKLOCH RENEWABLE ENERGY LIMITED | SC474474 | c/o Foresight Group, Clarence House, 1 31-135 George Street, Edinburgh , United Kingdom, EH2 4JS | Directly Connected Power Station | 11/06/2015 |
| GLENROTHES BESS LTD | 13641024 | The Factory, Whitchurch, Ross On Wye, Herefordshire, United Kingdom, HR9 6DF | Embedded Power Station | 26/01/2023 |
| GLENS OF FOUDLAND WIND FARM LIMITED | 04493791 | c/o RES Limited, Beaufort Court, Egg Farm Lane, Kings Langley, Hertfordshire, United Kingdom, WD4 8LR | Embedded Power Station | 31/03/2005 |
| GLENTAGGART WIND LIMITED | SC580101 | c/o Brockwell Energy Limited, The Eagle Building-Third Floor, 1 9 Rose Street, Edinburgh , United Kingdom, EH2 2PR | Directly Connected Power Station | 25/08/2021 |
| GLEN ULLINISH WF 2 LTD | SC666970 | Muirhall Farm, Auchengray, Carnwath, Lanark, South Lanarkshire, United Kingdom, ML11 8LL | Directly Connected Power Station | 30/11/2020 |
| GLEN ULLINISH WF LIMITED | SC380407 | Muirhall Farm, Auchengray, Carnwath, Lanark, South Lanarkshire, United Kingdom, ML11 8LL | Directly Connected Power Station | 16/11/2012 |
| GLOBAL INFRASTRUCTURE UK LIMITED | 10031299 | 5 NEW STREET SQUARE, LONDON , UNITED KINGDOM, EC4A 3TW | Non-Embedded Customer Site | 02/05/2023 |
| Global Risk Management A/S | DK79332216 | 7 Strandvejen, Middelfart , Denmark, 5500 | Interconnector User | 11/08/2020 |
| GLOUCESTER ENERGY PARK LIMITED | 14220265 | 1st Floor Sackville House, 143-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 17/02/2023 |
| Gnera Energia y Tecnologia SL | 84196997 | Planta 7, Edificio Abedul Serrano Galvache 56, Madrid, MADRID, Spain, 28033 | Interconnector User | 15/11/2023 |
| GOOD ENERGY DEVELOPMENT (NO.7) LIMITED | 08719457 | GOOD ENERGY, MONKTON PARK OFFICE, CHIPPENHAM , United Kingdom, SN15 1GH | Directly Connected Power Station; Dormant CUSC Party | 17/07/2015 |
| GOOD ENERGY LIMITED | 03899612 | GOOD ENERGY, MONKTON PARK OFFICE, CHIPPENHAM , United Kingdom, SN15 1GH | Supplier | |
| GOODMAN UK LIMITED | 03625138 | Cornwall House, Blythe Valley Park,, Solihull, West Midlands, United Kingdom, B90 8AF | Non-Embedded Customer Site | 21/07/2023 |
| GORDONSTOWN HILL WIND FARM LIMITED | 06772099 | Third Floor, 10 Lower Grosvenor Place, London , United Kingdom, SW1W 0EN | Embedded Exemptable Large Power Station | |
| GPC 013 LTD | 14605861 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Embedded Power Station | 28/03/2024 |
| GPC 016 Ltd | 14605888 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Embedded Power Station | 21/03/2024 |
| GPC 1039 Ltd | 14247712 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Directly Connected Power Station | 20/12/2022 |
| GPC 1119 Ltd | 14428809 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Directly Connected Power Station | 03/05/2023 |
| GPC 1127 Ltd | 14757688 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Embedded Power Station | 03/01/2024 |
| GPC 1134 Ltd | 14527803 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Directly Connected Power Station | 09/08/2023 |
| GPC 1137 Ltd | 14735508 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Embedded Power Station | 11/12/2023 |
| GPC 1154 Ltd | 14342160 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Directly Connected Power Station | 25/09/2023 |
| GPC 1169 Ltd | 14757640 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Embedded Power Station | 02/04/2024 |
| GPC 1184 LTD | 14736773 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Embedded Exemptable Large Power Station | 31/03/2025 |
| GPC 1210 Ltd | 14431015 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Directly Connected Power Station | 24/01/2024 |
| GPC 1211 Ltd | 14443829 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Directly Connected Power Station | 23/10/2023 |
| GPC 2008 Ltd | 14736935 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Embedded Power Station | 31/01/2024 |
| GPC 612 Ltd | 14574747 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Embedded Power Station | 18/09/2023 |
| GPC 680 Ltd | 14574720 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Embedded Power Station | 30/01/2024 |
| GPC 700 Ltd | 14403812 | 3rd Floor, 1 Ashley Road, Altrincham, Cheshire, United Kingdom, WA14 2DT | Directly Connected Power Station | 03/05/2023 |
| GRAIN NORTH POWER LIMITED | 12164360 | 4th Floor, 80 Victoria Street, London , United Kingdom, SW1E 5JL | Directly Connected Power Station | 14/09/2021 |
| Grain South Power Limited | 12164408 | First Floor, 145 Kensington Church Street, London , United Kingdom, W8 7LP | Directly Connected Power Station | 29/09/2021 |
| GRANGEMOUTH CHP LIMITED | SC178243 | Inchyra Road, Grangemouth, Stirlingshire, United Kingdom, FK3 9XB | Embedded Power Station | 01/09/2004 |
| GRAVEN HILL PURCHASER LTD | 13128906 | One, Fleet Place, London , United Kingdom, EC4M 7WS | Directly Connected Power Station | 16/10/2024 |
| GREAT CASTERTON ENERGY PARK LIMITED | 15040612 | 1st Floor Sackville House, 143-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 29/09/2023 |
| GREATER GABBARD OFFSHORE WINDS LIMITED | 04985731 | No.1 Forbury Place, 4 3 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 31/01/2005 |
| Greenchoice B.V. | 24302685 | Kruisplein 15, Rotterdam, ROTTERDAM, Netherlands, 3014DB | Interconnector User | 15/01/2025 |
| GREEN ENERGY (UK) LIMITED | 04194006 | Black Swan House, 2 3 Baldock Street, Ware , United Kingdom, SG12 9DH | Supplier | 09/02/2015 |
| GREEN ENERGY INTERNATIONAL LIMITED | 10086572 | TRINITY HOUSE NEWBY ROAD, STOCKPORT , United Kingdom, SK7 5DA | Directly Connected Power Station | 28/04/2022 |
| GREEN ENERGY MAB LTD | 14169451 | c/o Srs Direct, Corporation House,C orporation Road, Swansea , United Kingdom, SA4 6SD | Directly Connected Power Station | 03/02/2025 |
| GREENFIELDS (T) LIMITED | 09145738 | 5th Floor, North Side, 7 /10 Chandos Street, Cavendish Square, London , United Kingdom, W1G 9DQ | Directly Connected Power Station | 09/10/2018 |
| GREENGAIRS EAST WIND FARM LIMITED | 07383770 | Springfield, Ackenthwaite, Milnthorpe, United Kingdom, LA7 7DQ | Embedded Power Station | 12/11/2019 |
| GREEN GENERATION ENERGY NETWORKS CYMRU LIMITED | 13060815 | HODGE HOUSE, GUILDHALL PLACE, CARDIFF , United Kingdom, CF10 1DY | Directly Connected Distribution System | 27/05/2021 |
| GreenGridPower1 Ltd | 12831353 | 67 Westow Street, London , United Kingdom, SE19 3RW | Embedded Exemptable Large Power Station | 05/07/2022 |
| GREEN HYDROGEN SOLAR FARM LIMITED | 14389052 | 2 Crossways Business Centre, Bicester Road, Kingswood, Aylesbury, United Kingdom, HP18 0RA | Directly Connected Power Station | 15/05/2023 |
| GREEN INVESTMENT GROUP LIMITED | SC574147 | ATRIA ONE 144 MORRISON STREET, EDINBURGH , UNITED KINGDOM, EH3 8EX | Directly Connected Power Station | 18/09/2020 |
| Greenland Wind Farm Limited | SC723561 | c/o Locogen Limited, 4 West Silvermills Lane, Edinburgh, Midlothian, United Kingdom, EH3 5BD | Directly Connected Power Station | 13/01/2023 |
| GREENLINK INTERCONNECTOR LIMITED | 536954 | Unit 3, 4 075 Kingswood Road, C itywest Business Campus, Saggart, Co. Dublin, Ireland, D24 KF85 | Interconnector Owner | 11/11/2014 |
| GREENPOWER (CARRAIG GHEAL) LIMITED | SC245115 | The E-Centre, Cooperage Way, Alloa, Clackmannanshire, United Kingdom, FK10 3LP | Directly Connected Power Station | 02/11/2005 |
| GREENPOWER (INTERNATIONAL) LTD. | SC203660 | THE E CENTRE, ALLOA , United Kingdom, FK10 3LP | Embedded Exemptable Large Power Station | 03/12/2024 |
| GREENTECH PROJECTS HOLDING UK LIMITED | 12676147 | Challenge House, Sherwood Drive,, Milton Keynes , United Kingdom, MK3 6DP | Embedded Exemptable Large Power Station | 23/08/2022 |
| GREENWIRE TRANSMISSION PENTIR LIMITED | 536955 | Building 3400, Avenue 3000, C ork Airport Business Park, Cork , Ireland, T12 D23C | Directly Connected Power Station; Dormant CUSC Party | 11/12/2014 |
| GREENWIRE TRANSMISSION SOUTH WALES LIMITED | 568810 | Building 3400, Avenue 3000, C ork Airport Business Park, Cork , Ireland | Directly Connected Power Station; Dormant CUSC Party | 14/12/2017 |
| Grenergy Renewables UK Limited | 12875804 | 6th Floor, 25 Farringdon Street, London , United Kingdom, EC4A 4AB | Directly Connected Power Station | 20/02/2025 |
| Gresham House Asset Management Limited | 09447087 | 5 New Street Square, London , United Kingdom, EC4A 3TW | Directly Connected Power Station | 19/04/2023 |
| Gresham House Devco Pipeline Limited | 11007494 | 5 New Street Square, London , United Kingdom, EC4A 3TW | Directly Connected Power Station | 05/05/2023 |
| Greta IV Limited | 14548630 | 2 Crossways Business Centre, Bicester Road, Kingswood, Aylesbury, United Kingdom, HP18 0RA | Directly Connected Power Station | 17/08/2023 |
| GRETNA GRID SERVICES LIMITED | 12394809 | 1030 CENTRE PARK, SLUTCHERS LANE, WARRINGTON , UNITED KINGDOM, WA1 1QL | Non-Embedded Customer Site | 29/01/2021 |
| GRIDBEYOND LIMITED | 08211691 | Office 7.08, Gridiron Building 1 Pancras SquareKing's Cross, London, Greater London, UK, N1C 4AG | Virtual Lead Party | 24/09/2018 |
| GRIDLINK INTERCONNECTOR LIMITED | 10181689 | c/o D&M Financial Services, Anumerate Office 2.05 Clockwise, O ld Town Hall, 3 0 Tweedy Road, Bromley , United Kingdom, BR1 3FE | Interconnector Owner | 27/10/2016 |
| GRIDMOVE LTD | 11749475 | 20-22 Wenlock Road, London , United Kingdom, N1 7GU | Directly Connected Power Station | 24/11/2021 |
| GRIFFIN WIND FARM LIMITED | SC245113 | Inveralmond House, 200 Dunkeld Road, Perth , United Kingdom, PH1 3AQ | Directly Connected Power Station | 07/11/2005 |
| GROVEHURST ENERGY LIMITED | 02197516 | 350 EUSTON ROAD, LONDON , United Kingdom, NW1 3AX | Embedded Power Station | 18/09/2001 |
| Grupotec Renewables Limited | 07543880 | Parkshot House, 5 Kew Road, Richmond , United Kingdom, TW9 2PR | Embedded Power Station | 19/04/2023 |
| GRUPOTEC SOLAR UK 5 LIMITED | 14888176 | 5 Kew Road, Richmond, London, United Kingdom, TW9 2PR | Embedded Power Station | 01/05/2024 |
| GT R4 LIMITED | 13281221 | c/o Johnston Carmichael LLP, B irchin Court, 2 0 Birchin Lane, London , United Kingdom, EC3V 9DU | Directly Connected Power Station | 24/08/2021 |
| GTR London 2 S.À R.L | B 284 296 | 2 Rue Edward Steichen, Luxembourg , Grand-Duchy de Luxembourg, 2540 | Non-Embedded Customer Site | 29/04/2024 |
| GUNFLEET SANDS II LIMITED | 06114226 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 03/12/2007 |
| Gunfleet Sands II Ltd | 06114226 | 5 Howick Place, London , United Kingdom, SW1P 1WG | Directly Connected Power Station | 17/02/2011 |
| GUNFLEET SANDS LIMITED | 04019207 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 17/02/2011 |
| GWYDDELWERN BESS LIMITED | 15206459 | Hodge House, Guildhall Place, Cardiff , United Kingdom, CF10 1DY | Directly Connected Power Station | 09/01/2024 |
| GWYNT GLAS OFFSHORE WIND FARM LIMITED | 13499295 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park,, Houghton Le Spring, Sunderland, United Kingdom, DH4 5RA | Directly Connected Power Station | 26/05/2022 |
| GWYNT Y MOR OFFSHORE WIND FARM LIMITED | 03697015 | Windmill Hill Business Park, Whitehill Way, Swindon , United Kingdom, SN5 6PB | Directly Connected Power Station | 10/08/2007 |
| HABITAT ENERGY LIMITED | 10923911 | 3rd Floor 24 Savile Rownull, London, LONDON, United Kingdom, W1S 2ES | Virtual Lead Party | 15/04/2020 |
| HAGSHAW HILL REPOWERING LTD | SC603085 | 320 ST. VINCENT STREET, GLASGOW, GLASGOW, United Kingdom, G2 5AD | Directly Connected Power Station | 28/05/2019 |
| HAGSHAW REPOWERING 2 LTD | SC732631 | J R W, 1 9 Buccleuch Street, Hawick, Roxburghshire, United Kingdom, TD9 0HL | Directly Connected Power Station | 06/12/2022 |
| HAMS HALL GREEN ENERGY LIMITED | 13483632 | The Goods Shed, Jubilee Way, Faversham, Kent, United Kingdom, ME13 8GD | Directly Connected Power Station | 16/02/2022 |
| HARESHAW RIG WF LIMITED | SC651792 | Muirhall Farm, Auchengray, Carnwath, Lanark, South Lanarkshire, United Kingdom, ML11 8LL | Directly Connected Power Station | 15/09/2020 |
| HARKER ENERGY PARK LIMITED | 14487367 | 1st Floor Sackville House, 143-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 12/07/2023 |
| Harmony BD Ltd | 10683446 | Conyngham Hall, Bond End, Knaresborough , United Kingdom, HG5 9AY | Embedded Power Station | 28/11/2022 |
| Harmony BF Ltd | 10772215 | Conyngham Hall, Bond End, Knaresborough, United Kingdom, HG5 9AY | Embedded Power Station | 11/07/2023 |
| HARMONY BW LTD | 15609692 | 10 St James Business Park, Grimbald Crag Court, Knaresborough , United Kingdom, HG5 8QB | Directly Connected Power Station | 03/04/2025 |
| HARMONY CBR LTD | 15605529 | 10 St James Business Park, Grimbald Crag Court, Knaresborough , United Kingdom, HG5 8QB | Directly Connected Power Station | 08/04/2025 |
| Harmony CTF 2 Limited | 11558612 | Conyngham Hall, Bond End, Knaresborough , United Kingdom, HG5 9AY | Embedded Power Station | 20/09/2022 |
| HARMONY CTF LIMITED | 10683553 | Conyngham Hall, Bond End, Knaresborough , United Kingdom, HG5 9AY | Embedded Power Station | 13/09/2022 |
| HARMONY DL LTD | 14233742 | 10 St James Business Park, Grimbald Crag Court, Knaresborough , HG5 8QB | Directly Connected Power Station | 03/04/2025 |
| HARMONY ENERGY 3 LIMITED | 12345037 | Conyngham Hall, Bond End, Knaresborough , United Kingdom, HG5 9AY | Non-Embedded Customer Site | 27/03/2025 |
| HARMONY ENERGY LIMITED | 10141078 | 10 St James Business Park, Grimbald Cragg Court, Knaresborough, North Yorkshire, United Kingdom, HG5 8QB | Directly Connected Power Station | 21/06/2022 |
| Harmony FM Limited | 10944636 | Conyngham Hall, Bond End, Knaresborough , United Kingdom, HG5 9AY | Embedded Power Station | 25/01/2023 |
| HARMONY HB LIMITED | 10683540 | Conyngham Hall, Bond End,, Knaresborough , United Kingdom, HG5 9AY | Embedded Power Station | 02/04/2020 |
| HARMONY JF LIMITED | 10959382 | Conyngham Hall, Bond End, Knaresborough , United Kingdom, HG5 9AY | Embedded Power Station | 15/08/2018 |
| HARMONY MF LIMITED | 13596721 | 10 St James Business Park, Grimbald Crag Court, Knaresborough , United Kingdom, HG5 8QB | Directly Connected Power Station | 03/04/2025 |
| Harmony MS Limited | 15754938 | 10 St James Business Park, Grimbald Crag Court, Knaresborough , United Kingdom, HG5 8QB | Directly Connected Power Station | 03/04/2025 |
| Harmony SH Limited | 15611259 | 10 St James Business Park, Grimbald Crag Court, Knaresborough , United Kingdom, HG5 8QB | Directly Connected Power Station | 04/04/2025 |
| Hartree Partners Power & Gas Company (UK) Limited | 04308186 | 2nd Floor Cardinal Place, 1 00 Victoria Street, London , United Kingdom, SW1E 5JL | Interconnector User | 17/01/2023 |
| HARTREE PARTNERS SUPPLY (UK) LIMITED | 09283816 | 2nd Floor, Cardinal Place, 100 Victoria Street, London , United Kingdom, SW1E 5JL | Supplier | 14/09/2016 |
| Hatchworks Investments Ltd | 11324088 | St Georges House 6 th Floor1 5 Hanover Square, London , United Kingdom, W1S 1HS | Directly Connected Power Station | 31/05/2023 |
| HAVBREDEY LIMITED | SC717714 | Regus Building, 1st Floor, 93 George Street, Edinburgh , United Kingdom, EH2 3ES | Directly Connected Power Station | 05/02/2025 |
| HAWKERS HILL ENERGY PARK LIMITED | 10010531 | Beaufort Court, Egg Farm Lane, Kings Langley, Hertfordshire, United Kingdom, WD4 8LR | Embedded Power Station | 01/02/2022 |
| HB197END Limited | 12147583 | 8th Floor, 100 Bishopsgate, London , United Kingdom, EC2N 4AG | Directly Connected Power Station | 07/09/2020 |
| HB222BRI LTD | 12119824 | BASEMENT 68 GLOUCESTER STREET, LONDON , United Kingdom, SW1V 4EF | Directly Connected Power Station | 14/09/2021 |
| HB333MIL LTD | 12023569 | BASEMENT 68 GLOUCESTER STREET, LONDON , United Kingdom, SW1V 4EF | Directly Connected Power Station | 13/09/2021 |
| HB411MIN Limited | 12119919 | Basement 68 Gloucester Street, London , United Kingdom, SW1V 4EF | Directly Connected Power Station | 07/09/2020 |
| HB825AXM LTD | 11824601 | BASEMENT 68 GLOUCESTER STREET, LONDON , United Kingdom, SW1V 4EF | Directly Connected Power Station | 07/01/2020 |
| HD000ACT LTD | 12023670 | BASEMENT 68 GLOUCESTER STREET, LONDON , United Kingdom, SW1V 4EF | Directly Connected Power Station | 18/03/2020 |
| HD001KIR LTD | 11776395 | 68 GLOUCESTER STREET, LONDON , United Kingdom, SW1V 4EF | Directly Connected Power Station | 11/09/2019 |
| HD143OCK LTD | 12023540 | BASEMENT 68 GLOUCESTER STREET, LONDON, LONDON, United Kingdom, SW1V 4EF | Directly Connected Power Station | 18/03/2020 |
| HD144WHI LTD | 12023571 | BASEMENT 68 GLOUCESTER STREET, LONDON, LONDON, United Kingdom, SW1V 4EF | Directly Connected Power Station | 20/03/2020 |
| HD381GRE Limited | 12023580 | Basement 68 Gloucester Street, London , United Kingdom, SW1V 4EF | Directly Connected Power Station | 14/09/2021 |
| HD639LEG LIMITED | 11824675 | BASEMENT 68 GLOUCESTER STREET, LONDON, LONDON, United Kingdom, SW1V 4EF | Directly Connected Power Station | 27/02/2020 |
| HD777FRY LTD | 12023701 | BASEMENT 68 GLOUCESTER STREET, LONDON, LONDON, United Kingdom, SW1V 4EF | Directly Connected Power Station | 18/03/2020 |
| HD888CAP LIMITED | 11802123 | BASEMENT 68 GLOUCESTER STREET, LONDON, LONDON, United Kingdom, SW1V 4EF | Directly Connected Power Station | 11/09/2019 |
| HDCI HAYES LONDON LIMITED | 13085639 | Colt House, 20 Great Eastern Street, London , United Kingdom, EC2A 3EH | Non-Embedded Customer Site | 30/03/2022 |
| HEADWIND DEVELOPMENT SERVICES LIMITED | 06964875 | Connect House, 133-137 Alexandra Road, Wimbledon, London, United Kingdom, SW19 7JY | Embedded Power Station | 02/10/2024 |
| HEATHROW AIRPORT LIMITED | 01991017 | The Compass Centre, N elson Road, Hounslow , United Kingdom, TW6 2GW | Directly Connected Power Station | 02/05/2025 |
| HEIT LR LIMITED | 08527265 | 10 St James Business Park, Grimbald Crag Court, Knaresborough , United Kingdom, HG5 8QB | Embedded Power Station | 09/04/2018 |
| HEIT PW2 LIMITED | 11558969 | Conyngham Hall, B ond End, Knaresborough , United Kingdom, HG5 9AY | Embedded Power Station | 10/05/2022 |
| HEIT PW LIMITED | 10776494 | Conyngham Hall, B ond End, Knaresborough , United Kingdom, HG5 9AY | Embedded Power Station | 10/05/2022 |
| Helios Power Trading A/S | 41622296 | 13 Hasselager Centervej, Viby J , Denmark, 8260 | Interconnector User | 27/07/2021 |
| HESTA HEAD WIND FARM LIMITED | SC385374 | Suites 303 And 312 Floor 3, 2 West Regent Street, Glasgow , United Kingdom, G2 1RW | Directly Connected Power Station | 02/06/2016 |
| HFD RENEWABLES LIMITED | SC699755 | 177 Bothwell Street, Glasgow , United Kingdom, G2 7ER | Directly Connected Power Station | 28/01/2025 |
| High Brenfield Wind Farm Limited | 15292500 | Stirling Square, 5 -7 Carlton Gardens, London , SW1Y 5AD | Embedded Power Station | 10/02/2025 |
| HIGH CONSTELLATION WINDFARM LIMITED | 11800500 | 22 CHANCERY LANE, LONDON , United Kingdom, WC2A 1LS | Directly Connected Power Station | 03/04/2020 |
| HIGHLAND WIND FARM LIMITED | 13299694 | 14B, Tower 42, 25 Old Broad St, London , United Kingdom, EC2N 1HN | Directly Connected Power Station | 12/05/2022 |
| HIGHLAND WIND LIMITED | SC675148 | 4TH FLOOR 115 GEORGE STREET, EDINBURGH , United Kingdom, EH2 4JN | Directly Connected Power Station | 17/06/2021 |
| HIGH SPEED TWO (HS2) LIMITED | 06791686 | Two Snowhill, Snow Hill Queensway, Birmingham , United Kingdom, B4 6GA | Non-Embedded Customer Site | 22/12/2015 |
| HILL OF GLASCHYLE RENEWABLES LLP | SO303879 | MUIRDEN FARM, TURRIFF, Aberdeenshire, United Kingdom, AB53 4NH | Directly Connected Power Station | 28/10/2015 |
| HILL OF TOWIE LIMITED | 06952881 | Beaufort Court, Egg Farm Lane, Kings Langley, Hertfordshire, United Kingdom, WD4 8LR | Directly Connected Power Station | 28/10/2009 |
| HILL STREET SHELFCO 1 LIMITED | 14842959 | 31 Hill Street, London , United Kingdom, W1J 5LS | Directly Connected Power Station | 22/11/2023 |
| HIRWAUN POWER LIMITED | 08190283 | DRAX POWER STATION, SELBY, LONDON, United Kingdom, YO8 8PH | Directly Connected Power Station | 18/07/2014 |
| HM GB (WIND) LTD | 12421411 | 16 Kier Park, Ascot , SL5 7DS | Embedded Power Station | 01/04/2025 |
| HOCKLIFFE GREEN ENERGY CENTRE LTD | 14435128 | Flat 81 Blake Tower, 2 Fann Street, London , United Kingdom, EC2Y 8AF | Directly Connected Power Station | 09/12/2024 |
| HOLLYGREEN ENERGYFARM LIMITED | 15776139 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton Le Spring, Sunderland, United Kingdom, DH4 5RA | Directly Connected Power Station | 03/12/2024 |
| HOME ENERGY TRADING LTD | 10364306 | GRANVILLE HALL GRANVILLE ROAD, LEICESTER , United Kingdom, LE1 7RU | Supplier | 09/08/2018 |
| HOPSRIG WIND FARM LIMITED | SC501771 | Muirhall Farm, Auchengray, Carnwath, Lanark, South Lanarkshire, United Kingdom, ML11 8LL | Directly Connected Power Station | 28/09/2015 |
| HORIZON NUCLEAR POWER OLDBURY LIMITED | 06811995 | Sefton Park, Bells Hill, Stoke Poges,, Buckinghamshire, United Kingdom, SL2 4HD | Directly Connected Power Station | 11/04/2012 |
| HORIZON NUCLEAR POWER WYLFA LIMITED | 06811987 | Sefton Park, Bells Hill, Stoke Poges, Buckinghamshire, United Kingdom, SL2 4HD | Directly Connected Power Station | 07/07/2009 |
| HORNSEA 1 LIMITED | 07640868 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 22/09/2010 |
| HOUSEHILL BESS LIMITED | 14168554 | 1st Floor Midland House, 7 7 Huddersfield Road, Mirfield, West Yorkshire, United Kingdom, WF14 8BL | Embedded Exemptable Large Power Station | 17/01/2023 |
| HUMBER TECH PARK LIMITED | 15528913 | c/o Dragon Argent Limited, 63 Bermondsey Street, London , United Kingdom, SE1 3XF | Directly Connected Power Station | 25/10/2024 |
| Huntly Development Trust Limited | SC358964 | Brander Building, T he Square, Huntly, Aberdeenshire, United Kingdom, AB54 8BR | Embedded Exemptable Large Power Station | 23/04/2024 |
| HVS GRIDCO LTD | 12633642 | SUITE A 6 HONDURAS STREET, LONDON , United Kingdom, EC1Y 0TH | Directly Connected Power Station | 04/11/2020 |
| HVS SITECO LTD | 12616131 | First Floor, Hobhouse Court, Suffolk Street, London , United Kingdom, SW1Y 4HH | Directly Connected Power Station | 23/01/2025 |
| HYDROCK CONSULTANTS LIMITED | 03118932 | Over Court Barns Over Lane, Almondsbury, Bristol, Avon, United Kingdom, BS32 4DF | Embedded Power Station | 06/11/2023 |
| HYWIND (SCOTLAND) LIMITED | 08709450 | ONE KINGDOM STREET, LONDON , United Kingdom, W2 6BD | Directly Connected Power Station | 26/12/2014 |
| IBERDROLA ENERGIA ESPANA S.A.U. | A95758371 | PLAZA EUSKADI, 5, BILBAO, BILBAO, Spain, 48009 | Interconnector User | 01/10/2014 |
| IB VOGT UK LTD | 06451452 | 127 Cheapside, London , United Kingdom, EC2V 6BT | Directly Connected Power Station | 30/11/2023 |
| IDAHO ENERGY LIMITED | 11751953 | 2 LONDON WALL PLACE, LONDON , United Kingdom, EC2Y 5AU | Supplier | 02/06/2021 |
| IGP ENERGY STORAGE 2 LIMITED | 14731208 | Unit 25.7, Coda Studios 1 89 Munster Rd, London , United Kingddom, SW6 6AW | Directly Connected Power Station | 11/10/2024 |
| IGP ENERGY STORAGE 3 LIMITED | 14817010 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 04/06/2024 |
| IGP ENERGY STORAGE 4 LIMITED | 14817026 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 18/07/2024 |
| IGP ENERGY STORAGE 5 LIMITED | 14832885 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 13/11/2023 |
| IGP ENERGY STORAGE 6 LIMITED | 14832860 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 13/11/2023 |
| IGP INTERNATIONAL PROSPECTING LIMITED | 11838529 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 01/12/2022 |
| IGP SOLAR 14 LIMITED | 13211481 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 22/12/2021 |
| IGP SOLAR 16 LIMITED | 13211590 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 01/12/2021 |
| IGP SOLAR 17 LIMITED | 13266705 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 03/12/2021 |
| IGP SOLAR 19 LIMITED | 13290216 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 22/12/2021 |
| IGP SOLAR 22 LIMITED | 13307072 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 07/09/2023 |
| IG RENEWABLES SPV 1 LTD | 14971486 | 3 Queen Street, London , United Kingdom, W1J 5PA | Directly Connected Power Station | 09/01/2024 |
| ILI (Borders PSH) Ltd | SC581726 | The Shires, 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Directly Connected Power Station | 20/12/2022 |
| ILI (Trossachs PSH) Ltd | SC581741 | The Shires, 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Directly Connected Power Station | 20/03/2023 |
| ILI Aurelius Ltd | SC825293 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Non-Embedded Customer Site | 17/04/2025 |
| ILI Rufus Ltd | SC825440 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Non-Embedded Customer Site | 01/05/2025 |
| INCH CAPE OFFSHORE LIMITED | SC373173 | 5th Floor, 40 Princes Street, Edinburgh , United Kingdom, EH2 2BY | Directly Connected Power Station | 04/01/2012 |
| IN COMMODITIES A/S | 38381954 | TANGEN 6, AARHUS N , Denmark, 8200 | Interconnector User | 15/08/2017 |
| Independent Distribution Connection Specialists Limited | 13901266 | 55 Baker Street, London , United Kingdom, W1U 7EU | Independent Distribution N/W Operator | 15/02/2024 |
| INDEPENDENT POWER NETWORKS LIMITED | 04935008 | SYNERGY HOUSE WINDMILL AVENUE, BURY ST EDMUNDS , United Kingdom, IP30 9UP | Independent Distribution N/W Operator | 07/02/2006 |
| INDIAN QUEENS POWER LIMITED | 02928100 | Saltend Power Station, S altend Chemicals Park, Hedon Road, Hull, East Riding Of Yorkshire, United Kingdom, HU12 8GA | Directly Connected Power Station | 18/09/2001 |
| INDIGO POWER LIMITED | 12159646 | 200 Brook Drive, Green Park, Reading, United Kingdom, RG2 6UB | Independent Distribution N/W Operator | 15/07/2020 |
| Inductive Energy A/S | 42192287 | Abogade 15, Aarhus N, AARHUS, Denmark, 8200 | Interconnector User | 15/05/2024 |
| Ineos Infrastructure (Grangemouth) Limited | 06981874 | The Adelphi 1-11, John Adam Street, London , United Kingdom, WC2N 6HT | Non-Embedded Customer Site | 30/09/2011 |
| INNOVA RENEWABLES LIMITED | 12092691 | 3rd Floor, St George's House, 1 3-14 Ambrose Street, Cheltenham , United Kingdom, GL50 3LG | Directly Connected Power Station | 13/12/2021 |
| INOVYN ENERGY LIMITED | 02076043 | Bankes Lane Office, B ankes Lane, Runcorn, Cheshire, United Kingdom, WA7 4EL | Non-Embedded Customer Site | 18/09/2001 |
| Invenergy Development UK Ltd | SC726480 | 50 Lothian Road, Festival Square, Edinburgh , United Kingdom, EH3 9WJ | Directly Connected Power Station | 16/04/2024 |
| INVENERGY SERVICES UK LIMITED | SC501024 | 50 Lothian Road, Festival Square, Edinburgh , United Kingdom, EH3 9WJ | Directly Connected Power Station | 31/01/2022 |
| IPC GRID CONNECTION LIMITED | 14903216 | 49 Wood Vale, London , United Kingdom, SE23 3DT | Directly Connected Power Station | 10/11/2023 |
| IPC GRID CONNECTION TWO LIMITED | 15291356 | 49 Wood Vale, London , United Kingdom,, SE23 3DT | Directly Connected Power Station | 25/09/2024 |
| IQ ENERGY CENTRE LIMITED | 11678461 | Millhouse, 32-38 East Street, Rochford, Essex, United Kingdom, SS4 1DB | Directly Connected Power Station | 07/06/2019 |
| Irena BESS LIMITED | 13984476 | 30 Queen Square, Bristol , United Kingdom, BS1 4ND | Directly Connected Power Station | 30/11/2022 |
| IRON ACTON GREEN LIMITED | 12517505 | Ropemaker Place, 28 Ropemaker Street,, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 24/07/2020 |
| Isenau Energy Storage Resources Eight Limited | 14497014 | 147a Northcote Road, London , United Kingdom, SW11 6QB | Directly Connected Power Station | 16/08/2023 |
| Isenau Energy Storage Resources Five Limited | 14369829 | 147a Northcote Road, London , United Kingdom, SW11 6QB | Directly Connected Power Station | 18/08/2023 |
| Isenau Energy Storage Resources Four Limited | 14369816 | 147a Northcote Road, London , United Kingdom, SW11 6QB | Directly Connected Power Station | 15/04/2024 |
| Isenau Energy Storage Resources Two Limited | 14245764 | 147a Northcote Road, London , United Kingdom, SW11 6QB | Directly Connected Power Station | 06/02/2024 |
| ISLAND GREEN POWER UK LIMITED | 08615657 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 01/06/2021 |
| ISLAY TIDAL POWER LIMITED | SC521051 | 26 DUBLIN STREET, EDINBURGH , United Kingdom, EH3 6NN | Directly Connected Power Station | 20/04/2016 |
| J.P. Morgan Ventures Energy Corporation | 13-3804817 | 270 Park Avenue, New York , USA, NY 10017 | Interconnector User | 30/06/2006 |
| J Aron & Company | 13-3092284 | 200 WEST STREET, NEW YORK , United States of America, 10282 | Interconnector User | 17/02/2004 |
| JBM SOLAR PROJECTS 12 LTD | 12140230 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 10/07/2020 |
| JBM SOLAR PROJECTS 13 LIMITED | 12140364 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 08/07/2020 |
| JBM SOLAR PROJECTS 14 LTD | 12140396 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 10/07/2020 |
| JBM SOLAR PROJECTS 2 LTD | 11761556 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Embedded Power Station | 01/08/2024 |
| JBM SOLAR PROJECTS 33 LIMITED | 13237568 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 24/01/2023 |
| JEPIPHANY LIMITED | 15091275 | 3rd Floor St George’s House, 13-14 Ambrose Street, Cheltenham , United Kingdom, GL50 3LG | Directly Connected Power Station | 05/02/2024 |
| JG PEARS GRID CONNECTION LIMITED | 10146372 | Bella Vista Farm, H artcliffe Road, Penistone, Sheffield, United Kingdom, S36 9FN | Directly Connected Power Station | 05/12/2016 |
| JP MORGAN MARKETS LIMITED | 01592029 | 25 Bank Street, Canary Wharf, London , United Kingdom, E14 5JP | Interconnector User | 15/01/2008 |
| JP MORGAN SECURITIES PLC | 02711006 | 25 Bank Street, Canary Wharf, London , United Kingdom, E14 5JP | Interconnector User | 01/06/2007 |
| Juniper Energy Limited | 15825395 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton Le Spring, Sunderland, United Kingdom, DH4 5RA | Directly Connected Power Station | 26/11/2024 |
| JWM Energia sp. z o.o. | 0000451843 | JWM Energia sp. z o.o., Kolejowa 57, Katowice, Poland, 40-602 | Interconnector User | 06/03/2025 |
| KARI ENERGY LIMITED | 12603435 | c/o Tmf Group, 13th Floor 1 Angel Court, London , United Kingdom, EC2R 7HJ | Directly Connected Power Station | 25/10/2021 |
| KEADBY GENERATION LIMITED | 02729513 | KEADBY POWER STATION, SCUNTHORPE , UNITED KINGDOM, DN17 3EF | Directly Connected Power Station | 18/09/2001 |
| KEGWORTH 10 RENEWABLES LTD | 14914243 | Century House 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 31/08/2023 |
| KEITH RENEWABLE LIMITED | 13124496 | Crown House, 1 08 Aldersgate Street, London , United Kingdom, EC1A 4JQ | Embedded Power Station | 26/04/2022 |
| KEITH SOLAR PV LIMITED | 14180200 | 14B, Tower 42, 25 Old Broad St, London , United Kingdom, EC2N 1HN | Directly Connected Power Station | 01/07/2022 |
| KEITH STORAGE SOLUTIONS LIMITED | 11248767 | 19TH FLOOR 22 BISHOPSGATE, LONDON , UNITED KINGDOM, EC2N 4BQ | Non-Embedded Customer Site | 30/06/2020 |
| KENNOXHEAD WIND FARM LIMITED | 12602263 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 16/10/2020 |
| KILBRAUR WIND ENERGY LIMITED | SC254430 | Beauly House, D ochfour Business Centre, Dochgarroch, Inverness , United Kingdom, IV3 8GY | Directly Connected Power Station | 30/06/2005 |
| KILDRUMMY WIND FARM LIMITED | 07400002 | 5th Floor, 20 Fenchurch Street, London , United Kingdom, EC3M 3BY | Embedded Exemptable Large Power Station | 31/07/2012 |
| Kilmarnock Energy Centre Limited | SC766862 | 13 Queen's Road, Aberdeen , United Kingdom, AB15 4YL | Directly Connected Power Station | 03/04/2025 |
| KILMARNOCK FLEXPOWER LTD | SC692127 | 272 BATH STREET, GLASGOW , United Kingdom, G2 4JR | Directly Connected Power Station | 21/03/2022 |
| KINCARDINE OFFSHORE WINDFARM LIMITED | SC475345 | c/o Cms Cameron McKenna Nabarro Olswang Llp, 4 th Floor Saltire Court, 20 Castle Terrace, Edinburgh , United Kingdom, EH1 2EN | Embedded Power Station | 29/04/2016 |
| KINCORTH ENERGY STORAGE SYSTEM LTD | SC783932 | 6 Castle Street,, Edinburgh, Midlothian , EH2 3AT | Embedded Exemptable Large Power Station | 30/01/2025 |
| Kincraig Energy Centre Limited | 13459551 | Millhouse, 32-38 East Street, Rochford , United Kingdom, SS4 1DB | Embedded Power Station | 07/03/2022 |
| KINGSTON SPACE PROPERTY LIMITED | 12663171 | 73 CORNHILL, LONDON , United Kingdom, EC3V 3QQ | Non-Embedded Customer Site | 24/12/2021 |
| KINLOCHLEVEN POWER LTD | SC552928 | 1st Floor Cef Building, I nveralmond Road, Inveralmond Industrial Estate, Perth , United Kingdom, PH1 3TW | Directly Connected Power Station | 20/03/2018 |
| KINMUCK ENERGY STORAGE LIMITED | 13384297 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 20/09/2021 |
| KIRK HILL WIND FARM LIMITED | 09172034 | 1 PHIPP STREET, LONDON , United Kingdom, EC2A 4PS | Embedded Power Station | 12/04/2016 |
| Kirkton Wind Farm Ltd | SC662410 | Wind 2 Office, 2 Walker Street, Edinburgh , United Kingdom, EH3 7LB | Directly Connected Power Station | 21/03/2022 |
| KIWI POWER LTD | 07104653 | 35 Ballards Lane, London , United Kingdom, N3 1XW | Virtual Lead Party | 21/04/2020 |
| Knockcronal Wind Farm Limited | 11964184 | 19th Floor 22 Bishopsgate, London , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 05/04/2022 |
| KOCH SUPPLY & TRADING SARL | CH-112-980-714 | CHEMIN DE BLANDONNET 8, VERNIER, VERNIER, Switzerland, 1214 | Interconnector Owner | 21/12/2015 |
| Koehler Renewable Energy UK Limited | SC710079 | c/o Robb Ferguson, R egent Court, 70 West Regent Street, Glasgow , United Kingdom, G2 2QZ | Directly Connected Power Station | 20/02/2025 |
| KONA ASSET 3 LIMITED | 14521622 | Orchard Works, Carterton Industrial Estate, Carterton , United Kingdom, OX18 3EZ | Directly Connected Power Station | 12/12/2024 |
| KONA ASSET 4 LIMITED | 14523258 | Orchard Works, Carterton Industrial Estate, Carterton , United Kingdom, OX18 3EZ | Directly Connected Power Station | 18/12/2023 |
| Kona Energy Limited | 13184249 | 15-19 Bloomsbury Way, London , United Kingdom, WC1A 2TH | Directly Connected Power Station | 11/03/2025 |
| KSP (GRENDON) 1 LIMITED | 16278391 | 73 Cornhill, London , United Kingdom, EC3V 3QQ | Non-Embedded Customer Site | 24/04/2025 |
| KSP (IRONBRIDGE) 1 LIMITED | 16256066 | 73 Cornhill, London , United Kingdom, EC3V 3QQ | Non-Embedded Customer Site | 24/04/2025 |
| KSP (L) LIMITED | 16264169 | 73 Cornhill, London , United Kingdom, EC3V 3QQ | Non-Embedded Customer Site | 24/04/2025 |
| KSP (RUGELEY) 1 LIMITED | 16256065 | 73 Cornhill, London , United Kingdom, EC3V 3QQ | Non-Embedded Customer Site | 24/04/2025 |
| KS SPV 75 LIMITED | 13808213 | Office 17, Cleveland House, 3 9 Old Station Road, Newmarket , United Kingdom, CB8 8QE | Directly Connected Power Station | 23/01/2024 |
| KULIZUMBOO LIMITED | 09874701 | 189-193 EARLS COURT ROAD, LONDON , United Kingdom, SW5 9AN | Interconnector Owner | 02/04/2019 |
| KXP ALPHA III LIMITED | 14177817 | 30 Orange Street, London , United Kingdom, WC2H 7HH | Directly Connected Power Station | 26/10/2022 |
| KXP ALPHA II LIMITED | 14177716 | 30 Orange Street, London , United Kingdom, WC2H 7HH | Directly Connected Power Station | 26/10/2022 |
| KXP ALPHA I LIMITED | 14169073 | 30 Orange Street, London , United Kingdom, WC2H 7HH | Directly Connected Power Station | 24/11/2022 |
| KYPE EXTENSION WIND FARM LIMITED | 08791006 | Inkerman House, S t John's Road, M eadowfield, Durham , United Kingdom, DH7 8XL | Directly Connected Power Station | 01/05/2015 |
| LAGRAE BATTERY STORAGE LIMITED | SC762496 | Buccleuch Weatherhouse, Bowhill, Selkirk , United Kingdom, TD7 5ES | Directly Connected Power Station | 02/07/2024 |
| LAIRDMANNOCH ENERGY PARK LIMITED | SC714903 | Wind 2 Office, 2 Walker Street, Edinburgh, Midlothian, United Kingdom, EH3 7LA | Directly Connected Power Station | 24/02/2025 |
| LAKESIDE ENERGY STORAGE LIMITED | 10942509 | Carlton House, High Street, Higham Ferrers, Rushden , United Kingdom, NN10 8BW | Directly Connected Power Station | 26/10/2021 |
| LAN FAWR ENERGY PARK LIMITED | 13060780 | HODGE HOUSE GUILDHALL PLACE, CARDIFF , United Kingdom, CF10 1DY | Embedded Power Station | 03/06/2021 |
| Langage 10 Renewables Limited | 14605013 | Century House 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 14/12/2023 |
| LANGAGE ENERGY PARK LIMITED | 03886291 | 26 Ellerbeck Court, Stokesley, Middlesbrough, United Kingdom, TS9 5PT | Directly Connected Power Station | 19/07/2022 |
| LAUGHTON SOLAR PARK LIMITED | 12007066 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 18/11/2019 |
| LAWMOOR DEVELOPMENTS ENERGY STORAGE LIMITED | SC799659 | 64 Strathclyde Street, Glasgow , UK, G40 4JR | Embedded Exemptable Large Power Station | 15/11/2024 |
| LDV HARBURNHEAD LIMITED | SC420122 | 13 QUEEN'S ROAD, ABERDEEN , United Kingdom, AB15 4YL | Embedded Power Station | 17/06/2015 |
| Learielaw Energy Storage Ltd | SC639604 | 33 BOTHWELL ROAD, HAMILTON , United Kingdom, ML3 0AS | Directly Connected Power Station | 18/05/2023 |
| LEEP ELECTRICITY NETWORKS LIMITED | 06684589 | LEVEL 2, METRO 33 TRAFFORD ROAD, SALFORD , United Kingdom, M5 3NN | Independent Distribution N/W Operator | 22/12/2015 |
| LEGACY GREEN ENERGY LIMITED | 13299031 | The Goods Shed, J ubilee Way, Faversham, Kent, United Kingdom, ME13 8GD | Directly Connected Power Station | 25/01/2022 |
| Leighton Buzzard 10 Renewables Limited | 15128338 | Century House 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 22/11/2023 |
| LEITHENWATER WIND ENERGY HUB LIMITED | 13325593 | 10 Victoria Street, Bristol , United Kingdom, BS1 6BN | Embedded Exemptable Large Power Station | 08/07/2022 |
| LEL BILBO SOLAR LIMITED | 11296012 | 33 CAVENDISH SQUARE, LONDON , United Kingdom, W1G 0PG | Embedded Power Station | 24/05/2019 |
| LEVELISE LIMITED | 10653159 | Synergy House, W oolpit Business Park, Woolpit, Bury St. Edmunds, United Kingdom, IP30 9UP | Virtual Lead Party | 09/11/2021 |
| LG-B-300 | SC765613 | Lovat Estates Office, Station Road, Beauly , United Kingdom, IV4 7DA | Directly Connected Power Station | 29/01/2025 |
| LG-B-50a Limited | SC765614 | Lovat Estates Office, Station Road, Beauly , United Kingdom, IV4 7DA | Embedded Power Station | 08/05/2024 |
| LH NGET GRID SERVICES LIMITED | 14649836 | c/o Lightrock Power Limited, E lectric Works, 3 Concoure Way, Sheffield , United Kingdom, S1 2BJ | Directly Connected Power Station | 02/02/2024 |
| LIBERTY STEEL DALZELL LTD | 10071517 | 40 GROSVENOR PLACE, LONDON , United Kingdom, SW1X 7GG | Non-Embedded Customer Site | 17/06/2016 |
| Lightsource Renewable UK Development Limited | 08945965 | 7th Floor, 33 Holborn, London , United Kingdom, EC1N 2HU | Directly Connected Power Station | 15/06/2020 |
| LIGHTSOURCE SPV 191 LIMITED | 08938960 | 7TH FLOOR, 3 3 HOLBORN, LONDON , United Kingdom, EC1N 2HT | Directly Connected Power Station | 21/07/2022 |
| LIGHTSOURCE SPV 192 LIMITED | 08938959 | 7TH FLOOR, 3 3 HOLBORN, LONDON , United Kingdom, EC1N 2HT | Directly Connected Power Station | 13/06/2023 |
| LIGHTSOURCE SPV 204 LIMITED | 08943830 | 7TH FLOOR, 3 3 HOLBORN, LONDON , United Kingdom, EC1N 2HT | Directly Connected Power Station | 21/07/2022 |
| LIGHTSOURCE SPV 214 LIMITED | 08946243 | 7th Floor, 33 Holborn, London , United Kingdom, EC1N 2HT | Directly Connected Power Station | 09/04/2022 |
| Light Valley Solar Limited | 13290180 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 03/12/2021 |
| LIME DOWN SOLAR PARK LIMITED | 13211532 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 05/07/2021 |
| LIMEJUMP ENERGY LIMITED | 08246300 | Shell CentreYork Road, London, London , SE1 7NA | Supplier | 19/03/2018 |
| Limekiln Extension Limited | 10988722 | 16 West Borough, Wimborne, Dorset, United Kingdom, BH21 1NG | Directly Connected Power Station | 28/09/2023 |
| LIMEKILN GRID LIMITED | 12615099 | 16 West Borough, Wimborne, Dorset, United Kingdom, BH21 1NG | Directly Connected Power Station | 02/09/2020 |
| LIMEKILN WIND LIMITED | 08074755 | Infinergy Limited, 1 6 West Borough, Wimborne, Dorset, United Kingdom, BH21 1NG | Directly Connected Power Station | 07/04/2020 |
| LINCS WIND FARM LIMITED | SC213646 | 13 QUEENS ROAD, ABERDEEN , United Kingdom, AB15 4YL | Directly Connected Power Station | 27/10/2005 |
| LINK PARK HEATHROW LLP | OC404614 | MAGMA HOUSE CASTLE MOUND WAY, RUGBY , United Kingdom, CV23 0UZ | Non-Embedded Customer Site | 19/01/2021 |
| LISTER BATTERY LTD | 12473807 | c/o Gresham House Asset Management Limited, 5 New Street Square, London , United Kingdom, EC4A 3TW | Directly Connected Power Station | 11/03/2020 |
| LISTER DRIVE SOLUTIONS LIMITED | 12781976 | 19TH FLOOR 22 BISHOPSGATE, LONDON , United Kingdom, EC2N 4BQ | Non-Embedded Customer Site | 17/08/2021 |
| LITTLEBROOK GREEN ENERGY CENTRE LTD | 14440750 | 81 Blake Tower, 2 Fann Street, London , United Kingdom, EC2Y 8AF | Directly Connected Power Station | 20/02/2025 |
| Little Harrowden 10 Renewables Limited | 15128323 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 22/11/2023 |
| Llyn Lort Energy Park Limited | 13153924 | Hodge House, Guildhall Place, Cardiff , United Kingdom, CF10 1DY | Embedded Power Station | 03/09/2021 |
| Llyn Lort II Energy Park Limited | 14273760 | Hodge House, G uildhall Place, Cardiff , United Kingdom, CF10 1DY | Embedded Power Station | 02/10/2023 |
| Llŷr Floating Wind Limited | SC608546 | The Boathouse, Hawkcraig Road, Aberdour , United Kingdom, KY3 0TZ | Directly Connected Power Station | 06/09/2022 |
| LOCH KEMP STORAGE LIMITED | 10813231 | 4th Floor, 80 Victoria Street, London , United Kingdom, SW1E 5JL | Directly Connected Power Station | 03/03/2022 |
| LOCH LIATH WIND FARM LIMITED | 12836747 | 19TH FLOOR 22 BISHOPSGATE, LONDON , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 19/11/2024 |
| Lochluichart Battery Storage Limited | SC696025 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Embedded Exemptable Large Power Station | 02/02/2023 |
| LOCHORE BESS LTD | 14725777 | The Factory, Whitchurch, Ross-On-Wye , United Kingdom, HR9 6DF | Directly Connected Power Station | 06/11/2023 |
| LOGANHEAD WF LIMITED | SC453136 | Muirhall Farm, Auchengray, Carnwath, Lanark South, South Lanarkshire, United Kingdom, ML11 8LL | Directly Connected Power Station | 28/06/2017 |
| LONDON ARRAY LIMITED | 04344423 | NUMBER 22 MOUNT EPHRAIM, TUNBRIDGE WELLS , United Kingdom, TN4 8AS | Directly Connected Power Station | 06/03/2008 |
| LONDON POWER NETWORKS PLC | 03929195 | Newington House , London, United Kingdom, SE1 6NP | Directly Connected Distribution System | 18/09/2001 |
| LONDORF CAPITAL LIMITED | 08393551 | 2 LANSDOWNE ROW, LONDON , UNITED KINGDOM, W1J 6HL | Directly Connected Power Station | 14/12/2021 |
| LONGBURN WIND FARM LIMITED | 07735135 | c/o Tmf Group, 13th Floor, One Angel Court, London , United Kingdom, EC4A 4AB | Directly Connected Power Station; Dormant CUSC Party | 17/02/2014 |
| LONGFIELD SOLAR ENERGY FARM LIMITED | 11618210 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton Le Spring, Sunderland, United Kingdom, DH4 5RA | Directly Connected Power Station | 03/10/2019 |
| LONGHILL WIND FARM LLP | OC428018 | 114 St. Martin's Lane, Covent Garden, London, United Kingdom, WC2N 4BE | Embedded Exemptable Large Power Station | 12/10/2020 |
| LONGPARK WINDFARM LIMITED | 06708766 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton Le Spring, Sunderland, United Kingdom, DH4 5RA | Directly Connected Power Station | 24/03/2010 |
| LONG STRATTON ENERGY PARK LIMITED | 15040380 | 1st Floor Sackville House, 143-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 29/09/2023 |
| Lovat Estates Limited | SC179037 | Lovat Estate Office, Beauly , United Kingdom, IV4 7DA | Directly Connected Power Station | 14/06/2023 |
| LOVEDEAN GREEN LIMITED | 12517014 | Ropemaker Place, 28 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 24/07/2020 |
| LOW CARBON SOLAR PARK 18 LIMITED | 13347611 | Stirling Square, 5-7 Carlton Gardens, London , United Kingdom, SW1Y 5AD | Embedded Power Station | 28/03/2023 |
| LOW CARBON SOLAR PARK 28 LIMITED | 14219218 | Stirling Square, 5-7 Carlton Gardens, London , United Kingdom, SW1Y 5AD | Directly Connected Power Station | 22/01/2024 |
| LOW CARBON SOLAR PARK 34 LIMITED | 14224113 | Stirling Square, 5-7 Carlton Gardens, London , United Kingdom, SW1Y 5AD | Directly Connected Power Station | 19/09/2023 |
| LOW CARBON SOLAR PARK 35 LIMITED | 14228854 | Stirling Square, 5-7 Carlton Gardens, London , United Kingdom, SW1Y 5AD | Directly Connected Power Station | 19/09/2023 |
| LOW CARBON SOLAR PARK 39 LIMITED | 14443655 | Stirling Square, 5-7 Carlton Gardens, London , United Kingdom, SW1Y 5AD | Interconnector Owner | 23/01/2024 |
| Low Carbon Solar Park 40 Limited | 14443694 | Stirling Square, 5-7 Carlton Gardens, London , United Kingdom, SW1Y 5AD | Directly Connected Power Station | 22/01/2024 |
| LOW CARBON SOLAR PARK 43 LIMITED | 14443807 | Stirling Square, 5-7 Carlton Gardens, London , United Kingdom, SW1Y 5AD | Directly Connected Power Station | 22/01/2024 |
| Lower 48 Energy BESS Limited | 14373103 | 33 Bedford Place, London , United Kingdom, WC1B 5JU | Directly Connected Power Station | 23/06/2023 |
| LOWER FRANKTON BESS LIMITED | 15206408 | Hodge House, Guildhall Place, Cardiff , United Kingdom, CF10 1DY | Directly Connected Power Station | 09/01/2024 |
| LUMINOUS ENERGY GROUP LIMITED | 08416646 | Hartham Park, Hartham Lane, Corsham , United Kingdom, SN13 0RP | Directly Connected Power Station | 12/12/2023 |
| LUMINUS | 471811661 | KONING ALBERT II-LAAN 7, BRUSSEL , Belgium, 1210 | Interconnector User | 01/02/2022 |
| LUNANHEAD ENERGY STORAGE LIMITED | 12848218 | c/o Foresight Group Llp, T he Shard, 32 London Bridge Street, London , United Kingdom, SE1 9SG | Embedded Exemptable Large Power Station | 01/04/2021 |
| LYNEMOUTH POWER LIMITED | 07866585 | Lynemouth Power Station, Ashington, Northumberland, United Kingdom, NE63 9NW | Embedded Power Station | 03/10/2013 |
| LYSE PRODUKSJON AS | 980335216 | Breiflåtveien 18, Stavanger, Stavanger, Norway, 4017 | Interconnector User | 01/03/2024 |
| LZN LIMITED | 04846309 | c/o Pinsent Masons Llp, 1 Park Row, Leeds , United Kingdom, LS1 5AB | Directly Connected Power Station | 05/08/2005 |
| M2 Energy Storage Limited | SC748399 | 201 West George Street, Glasgow , United Kingdom, G2 2LW | Directly Connected Power Station | 20/02/2025 |
| MABLETHORPE GREEN ENERGY CENTRE LIMITED | 13230498 | 3rd Floor, Norfolk House, 106 Saxon Gate West, Milton Keynes , United Kingdom, MK9 2DN | Directly Connected Power Station | 24/01/2023 |
| Macduff Battery Storage Ltd | SC723975 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Embedded Exemptable Large Power Station | 31/10/2022 |
| MACQUARIE BANK LTD | 46 008 583 542 | Level 6, 50 Martin Place, Sydney , Australia, NSW 2000 | Interconnector User | 31/07/2014 |
| MA ENERGY LIMITED | 06541758 | Pearl Assurance House, 319 Ballards Lane, London , United Kingdom, N12 8LY | Interconnector User | |
| Maesnant Energy Park Limited | 13685890 | The Broadgate Tower Third Floor, 20 Primrose Street, London , United Kingdom, EC2A 2RS | Embedded Power Station | 19/10/2022 |
| MAGNORA OFFSHORE WIND AS | 927 136 546 | 9. ETASJE KARENSLYST ALLE 2, OSLO , NORWAY, 278 | Directly Connected Power Station | 22/02/2022 |
| MALLARD PASS SOLAR FARM LIMITED | 12575861 | 111 Park Street, Mayfair, London, United Kingdom, W1K 7JF | Directly Connected Power Station | 08/10/2021 |
| MANNINGTON ENERGY CENTRE LIMITED | 11433331 | 70 St Mary Axe, London , United Kingdom, EC3A 8BE | Directly Connected Power Station | 02/03/2020 |
| MANX UTILITIES | N/A | PO BOX 177, DOUGLAS , Isle Of Man (United Kingdom), IM99 1PS | Distribution Interconnector Owner | 18/09/2001 |
| MARBLE POWER LIMITED | 08474535 | Office 7, Kestral Court, Waterwells Drive, Quedgeley, Gloucester, United Kingdom, GL2 2AT | Supplier | 19/05/2015 |
| MARCHWOOD POWER LIMITED | 04229146 | Oceanic Way, M archwood Industrial Park, Marchwood, Southampton, United Kingdom, SO40 4BD | Directly Connected Power Station | |
| Maresconnect Limited | 605488 | The Victorians, 15-18 Earlsfort Terrace, Dublin 2 , Ireland, D02 YX28 | Interconnector Owner | 01/10/2018 |
| MARKET HARBOROUGH GREEN ENERGY CENTRE LTD | 14438087 | 81 Blake Tower, 2 Fann Street, London , United Kingdom, EC2Y 8AF | Directly Connected Power Station | 20/02/2025 |
| MAS 002 LIMITED | 14690765 | 70 Jermyn Street, London , United Kingdom, SW1Y 6NY | Directly Connected Power Station | 12/11/2024 |
| MAS 005 Limited | 14689808 | 70 Jermyn Street, London , United Kingdom, SW1Y 6NY | Embedded Exemptable Large Power Station | 10/02/2025 |
| MAXEN POWER SUPPLY LIMITED | 10298693 | Olympic House, 2 8-42 Clements Road, Ilford, Essex, United Kingdom, IG1 1BA | Supplier | 09/07/2018 |
| MEDWAY POWER LIMITED | 02537903 | No.1 Forbury Place, 4 3 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 18/09/2001 |
| MELKSHAM CALNE GREEN LIMITED | 12517251 | 18 Navigation Way, Ashton-On-Ribble, Preston, United Kingdom, PR2 2YP | Directly Connected Power Station | 24/07/2020 |
| MELKSHAM ENERGY CENTRE ONE LTD | 09047132 | Millhouse, 32-38 East Street, Rochford, Essex, United Kingdom, SS4 1DB | Directly Connected Power Station; Dormant CUSC Party | 15/06/2020 |
| MELKSHAM ENERGY CENTRE TWO LTD | 11869745 | Millhouse, 32-38 East Street, Rochford, Essex, United Kingdom, SS4 1DB | Directly Connected Power Station; Dormant CUSC Party | 15/06/2020 |
| Melvich Wind Energy Hub Limited | 13035564 | 10 Victoria Street, Bristol , United Kingdom, BS1 6BN | Directly Connected Power Station | 09/12/2021 |
| Menter Môn Morlais Limited | 10747114 | Neuadd Y Dref B ulkeley Square, Llangefni , United Kingdom, LL77 7LR | Directly Connected Power Station | 16/09/2020 |
| MERCIA POWER RESPONSE LIMITED | 09688709 | STRELLEY HALL, NOTTINGHAM , UNITED KINGDOM, NG8 6PE | Directly Connected Power Station | 01/12/2023 |
| MERCURIA ENERGY TRADING SA | CH-660-1372004-2 | RUE DU RHONE 50, GENEVE , Switzerland, 1204 | Interconnector User | 24/07/2013 |
| MERSEY REACTIVE POWER LIMITED | 12650628 | St Magnus House, 6th Floor, 3 Lower Thames Street, London , United Kingdom, EC3R 6HD | Non-Embedded Customer Site | 10/12/2020 |
| METROPOLITAN WASTE MANAGEMENT (ORSETT) LIMITED | 06401632 | c/o Street Fuel Ltd, Berth 6, Basin 3, Chatham Dockyards, Gillingham , United Kingdom, ME4 4SR | Directly Connected Power Station | 20/12/2024 |
| MEYGEN PLC | SC347501 | 26 DUBLIN STREET, EDINBURGH , United Kingdom, EH3 6NN | Directly Connected Power Station | 08/12/2010 |
| Meygrid Limited | SC786510 | 26 Dublin Street, Edinburgh , United Kingdom, EH3 6NN | Directly Connected Power Station | 08/05/2024 |
| MFT ENERGY A/S | 38175130 | MARGRETHEPLADSEN 4 03, AARHUS C , Denmark, 8000 | Interconnector User | 13/06/2018 |
| MGT TEESSIDE LIMITED | 06574235 | 8 White Oak Square, L ondon Road, Swanley , United Kingdom, BR8 7AG | Directly Connected Power Station | 12/02/2009 |
| Mid Craigie BESS Limited | 14905884 | 1st Floor Midland House, 7 7 Huddersfield Road, Mirfield, West Yorkshire, United Kingdom, WF14 8BL | Embedded Exemptable Large Power Station | 06/06/2023 |
| Middleton Energy Storage Limited | 13524329 | 8th Floor, 100 Bishopsgate, London , United Kingdom, EC2N 4AG | Directly Connected Power Station | 08/07/2022 |
| MID HILL WIND LIMITED | SC257734 | c/o Harper Macleod Llp, T he Cadoro, 45 Gordon Street, Glasgow , United Kingdom, G1 3PE | Embedded Exemptable Large Power Station | 22/07/2005 |
| MILLBROOK POWER LIMITED | 08920458 | DRAX POWER STATION, SELBY, SELBY, United Kingdom, YO8 8PH | Directly Connected Power Station | 24/02/2015 |
| Millennium Commodities I Designated Activity Company | 761010 | 32 Molesworth Street, Dublin 2 , Ireland | Interconnector User | 25/10/2024 |
| MILLENNIUM WIND ENERGY LIMITED | SC254420 | Beauly House, D ochfour Business Centre, Dochgarroch, Inverness , United Kingdom, IV3 8GY | Directly Connected Power Station | 30/06/2005 |
| Milligansbush Battery Storage Ltd | SC760555 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Directly Connected Power Station | 30/01/2025 |
| Mill Rig Wind Farm LLP | OC431615 | Inkerman House St. Johns Road, M eadowfield Industrial Estate, Durham , United Kingdom, DH7 8XL | Directly Connected Power Station | 25/11/2021 |
| MILLTOWN AIRFIELD SOLAR PV LIMITED | 08838324 | 4TH FLOOR 1 TUDOR STREET, LONDON , UNITED KINGDOM, EC4Y 0AH | Embedded Power Station | 28/11/2018 |
| MILTON FARM ENERGY PARK LIMITED | SC723912 | 10 Newton Place, Glasgow , United Kingdom, G3 7PR | Embedded Exemptable Large Power Station | 09/05/2024 |
| MINNYGAP ENERGY LIMITED | 09644754 | ST HELEN'S 1 UNDERSHAFT, LONDON , United Kingdom, EC3P 3DQ | Directly Connected Power Station | 18/10/2016 |
| MINSCA WINDFARM (SCOTLAND) LIMITED | SC279051 | Fourth Floor, 12 Blenheim Place, Edinburgh , United Kingdom, EH7 5JH | Embedded Power Station | 29/09/2006 |
| MITCHELL ENERGY LTD | Sc455085 | JRW 19 BUCCLEUCH STREET, LANARK , United Kingdom, TD9 0HL | Directly Connected Power Station | 28/03/2025 |
| MOEL CHWA ENERGY PARK LIMITED | 13036635 | HODGE HOUSE GUILDHALL PLACE, CARDIFF , United Kingdom, CF10 1DY | Directly Connected Power Station | 22/06/2021 |
| MOELFRE ENERGY PARK LIMITED | 13011082 | HODGE HOUSE, GUILDHALL PLACE, CARDIFF , UNITED KINGDOM, CF10 1DY | Directly Connected Power Station | 24/06/2021 |
| Mona Offshore Wind Limited | 13497266 | Chertsey Road, Sunbury On Thames, Middlesex, United Kingdom, TW16 7BP | Directly Connected Power Station | 25/09/2023 |
| MONETS GARDEN BATTERY LTD | 12472854 | c/o Gresham House Asset Management Limited, 5 New Street Square, London , United Kingdom, EC4A 3TW | Directly Connected Power Station | 11/03/2020 |
| MONK FRYSTON 1 LIMITED | 16286977 | 73 Cornhill, London , United Kingdom, EC3V 3QQ | Non-Embedded Customer Site | 01/05/2025 |
| Monolith Capital AG | CHE-143.474.602 | Grabenstrasse 2, Baar, Zug, Switzerland, CH-6340 | Interconnector User | 05/03/2024 |
| Montreathmont Energy Centre Limited | 12988209 | Millhouse, 32-38 East Street, Rochford , United Kingdom, SS4 1DB | Embedded Power Station | 17/02/2022 |
| Mooir Vannin Offshore Wind Farm Limited | 013051V | 33-37 Athol Street, Douglas , Isle of Man, IM1 1LB | Directly Connected Power Station | 26/05/2023 |
| Morar Hydrogen Plant Limited | SC759983 | 39 George Street, Edinburgh , United Kingdom, EH2 2HN | Non-Embedded Customer Site | 20/12/2023 |
| MORAY OFFSHORE RENEWABLE POWER LIMITED | 10303640 | Shepherd And Wedderburn Llp, Octagon Point, 5 Cheapside, London , United Kingdom, EC2V 6AA | Directly Connected Power Station | 02/06/2021 |
| MORAY OFFSHORE WINDFARM (EAST) LIMITED | 07101438 | Shepherd And Wedderburn Llp, Octagon Point, 5 Cheapside, London, London, United Kingdom, EC2V 6AA | Directly Connected Power Station | 09/08/2010 |
| MORAY OFFSHORE WINDFARM (WEST) LIMITED | 10515140 | Shepherd And Wedderburn Llp, Octagon Point, 5 Cheapside, London, LONDON, United Kingdom, EC2V 6AA | Directly Connected Power Station | 23/08/2017 |
| MORECAMBE WIND LIMITED | 05294242 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 22/10/2013 |
| Morgan Offshore Wind Limited | 13497271 | Chertsey Road, Sunbury-on-Thames, Middlesex, United Kingdom, TW16 7BP | Directly Connected Power Station | 25/09/2023 |
| Morven Offshore Wind Limited | 13792251 | Chertsey Road, Sunbury On Thames,, Middlesex, United Kingdom, TW16 7BP | Directly Connected Power Station | 23/04/2024 |
| Morwind Ltd | 13015099 | Harbour Lights, B usvannah, Penryn , United Kingdom, TR10 9LQ | Directly Connected Power Station | 31/01/2022 |
| MOSEDALE ENERGY LIMITED | 13645113 | 189-193 EARLS COURT ROAD, LONDON , United Kingdom, SW5 9AN | Directly Connected Power Station | 23/06/2023 |
| MOSSMORRAN STORAGE LTD | 15025798 | 19 Friar Road, Brighton , United Kingdom, BN1 6NG | Directly Connected Power Station | 08/01/2024 |
| MOSSY HILL SHETLAND LIMITED | 07075398 | 19th Floor, 22 Bishopsgate, London , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 04/06/2019 |
| MOSTYN SEAPOWER LIMITED | 11992210 | THE PORT OF MOSTYN COAST ROAD, HOLYWELL, Flintshire, United Kingdom, CH8 9HE | Directly Connected Power Station | 26/09/2019 |
| MOYLE INTERCONNECTOR LIMITED | NI36562 | First Floor, The Arena Building, 85 Ormeau Road, Belfast , United Kingdom, BT7 1SH | Interconnector Owner | 16/03/2005 |
| MSFT MCIO LIMITED | 09616816 | 1 Blossom Yard, F ourth Floor, London , United Kingdom, E1 6RS | Non-Embedded Customer Site | 25/01/2021 |
| MUA ELECTRICITY LIMITED | 10622250 | HIVIEW HOUSE, HIGHGATE ROAD, LONDON , UNITED KINGDOM, NW5 1TN | Directly Connected Power Station | 31/05/2023 |
| MUIRDEN ENERGY LLP | SO302777 | Muirden Farm, Turriff,, Aberdeenshire, United Kingdom, AB53 4NH | Dormant CUSC Party; Embedded Power Station | 27/11/2014 |
| MUIR MHÒR OFFSHORE WIND FARM LIMITED | SC717262 | 4 Jackson's Entry, Holyrood Road, Edinburgh , United Kingdom, EH8 8PJ | Directly Connected Power Station | 28/08/2023 |
| MVV ENVIRONMENT BALDOVIE LIMITED | SC148254 | FORTIES ROAD, DUNDEE , United Kingdom, DD4 0NS | Embedded Exemptable Large Power Station | |
| MVV ENVIRONMENT SERVICES LIMITED | 08500792 | 40 CREEK ROAD, PLYMOUTH , United Kingdom, PL5 1FL | Supplier | 07/11/2014 |
| NADARA LIMITED | SC546368 | Fourth Floor, 12 Blenheim Place, Edinburgh , United Kingdom, EH7 5JH | Dormant CUSC Party; Embedded Power Station | 29/09/2006 |
| NANT AMAN ENERGY PARK LIMITED | 13248724 | Hodge House. G uildhall Place, Cardiff , United Kingdom, CF10 1DY | Directly Connected Power Station | 25/11/2021 |
| NANT CEIMENT ENERGY PARK LIMITED | 13229301 | Hodge House, G uildhall Place, Cardiff , United Kingdom, CF10 1DY | Embedded Power Station | 03/06/2021 |
| NANT MITHIL ENERGY PARK LIMITED | 13052400 | HODGE HOUSE GUILDHALL PLACE, CARDIFF , United Kingdom, CF10 1DY | Embedded Power Station | 03/06/2021 |
| NASDAQ OMX STOCKHOLM AB | 52-1165937 | TULLVAKTSVAGEN 15, STOCKHOLM , SWEDEN, 105 78 | Interconnector User | 22/10/2013 |
| NATIONAL GAS TRANSMISSION PLC | 02006000 | National Grid House, W arwick Technology Park, G allows Hill, Warwick , United Kingdom, CV34 6DA | Non-Embedded Customer Site | 14/02/2006 |
| National Grid Electricity Distribution (East Midlands) plc | 02366923 | Avonbank, F eeder Road, Bristol , United Kingdom, BS2 0TB | Directly Connected Distribution System | 18/09/2001 |
| NATIONAL GRID ELECTRICITY DISTRIBUTION (SOUTH WALES) PLC | 02366985 | Avonbank, F eeder Road, Bristol , United Kingdom, BS2 0TB | Directly Connected Distribution System | 18/09/2001 |
| NATIONAL GRID ELECTRICITY DISTRIBUTION (SOUTH WEST) PLC | 02366894 | Avonbank, F eeder Road, Bristol , United Kingdom, BS2 0TB | Directly Connected Distribution System | 18/09/2001 |
| National Grid Electricity Distribution (West Midlands) Plc | 03600574 | Avonbank, F eeder Road, Bristol , United Kingdom, BS2 0TB | Directly Connected Distribution System | 12/11/2001 |
| National Grid Grain LNG Limited | 04463679 | 1-3 Strand, London , United Kingdom, WC2N 5EH | Non-Embedded Customer Site | 31/10/2006 |
| NATIONAL GRID IFA 2 LIMITED | 09129992 | 1-3 Strand, London , United Kingdom, WC2N 5EH | Interconnector Owner | 16/02/2017 |
| NATIONAL GRID INTERCONNECTOR HOLDINGS LIMITED | 08169384 | 1-3 Strand, London , United Kingdom, WC2N 5EH | Interconnector Owner | 26/09/2014 |
| NATIONAL GRID INTERCONNECTORS LIMITED | 03385525 | 1-3 Strand, London , United Kingdom, WC2N 5EH | Interconnector Owner | 14/08/2006 |
| NATIONAL GRID INTERNATIONAL LIMITED | 02537092 | 1-3 Strand, London , United Kingdom, WC2N 5EH | Interconnector Owner | 29/12/2004 |
| NATIONAL GRID NORTH SEA LINK LIMITED | 08082344 | 1-3 Strand, London , United Kingdom, WC2N 5EH | Interconnector Owner | 26/03/2015 |
| NATIONAL GRID VIKING LINK LIMITED | 09075537 | 1-3 Strand, London , United Kingdom, WC2N 5EH | Interconnector Owner | 10/04/2015 |
| NATIVE RIVER LTD | 12997344 | C/O Watson Farley & Williams Llp15 Appold Street, London , EC2A 2HB | Directly Connected Power Station | 26/07/2021 |
| NATPOWER MARINE LIMITED | 15009953 | Lilly House, 1 3 Hanover Square, London , United Kingdom, W1S 1HN | Directly Connected Power Station | 14/12/2023 |
| NATPOWER MARINE UK LIMITED | 15361289 | Level 8 Lily House, 13 Hanover Square, London , United Kingdom, W1S 1HN | Directly Connected Power Station | 12/09/2024 |
| Naturalis Energy Developments Ltd | 12222848 | Third Floor, 10 Lower Grosvenor Place, London , United Kingdom, SW1W 0EN | Embedded Power Station | 18/03/2022 |
| NATURGY LIMITED | 376223 | 24 - 28 TARA STREET, DUBLIN 2 , IRELAND, D07 YX67 | Interconnector User | 25/04/2014 |
| NAVENBY ENERGY LIMITED | 15700663 | Level 8 Lily House, 1 3 Hanover Square,M ayfair, London , United Kingdom, W1S 1HN | Directly Connected Power Station | 16/12/2024 |
| NAVENBY GREEN ENERGY CENTRE LTD | 14437953 | 81 Blake Tower, 2 Fann Street, London , United Kingdom, EC2Y 8AF | Directly Connected Power Station | 04/12/2024 |
| NEART NA GAOITHE OFFSHORE WIND LIMITED | SC356223 | ATRIA ONE 144 MORRISON STREET, EDINBURGH, EDINBURGH, UNITED KINGDOM, EH3 8EX | Directly Connected Power Station | 17/02/2010 |
| NEAS ENERGY LIMITED | 06993636 | Millstream, Maidenhead Road, Windsor, Berkshire, United Kingdom, SL4 5GD | Supplier | 11/04/2013 |
| NECTON GREEN ENERGY CENTRE LTD | 14469002 | Flat 81 Blake Tower, 2 Fann Street, London , United Kingdom, EC2Y 8AF | Directly Connected Power Station | 11/11/2024 |
| Necton Grid Solutions Limited | 14655633 | 19th Floor, 22 Bishopsgate, London , EC2N 4BQ | Directly Connected Power Station | 18/09/2024 |
| NEILSTON GRID SERVICES LIMITED | 12648776 | FOURTH FLOOR, 2 KINGSWAY, CARDIFF , United Kingdom, CF10 3FD | Non-Embedded Customer Site | 25/11/2020 |
| Nembus BESS Limited | 14401674 | 30 Queen Square, Penthouse Office, Bristol , United Kingdom, BS1 4ND | Directly Connected Power Station | 09/10/2023 |
| NEMO LINK LIMITED | 08169409 | GRAND BUILDINGS, LONDON , United Kingdom, WC2N 5EH | Interconnector Owner | 27/02/2015 |
| NETWORK RAIL INFRASTRUCTURE LIMITED | 02904587 | 1 EVERSHOLT STREET, LONDON, LONDON, UNITED KINGDOM, NW1 2DN | Non-Embedded Customer Site | 18/09/2001 |
| NET ZERO MARINE SERVICES LIMITED | 13351530 | 9-10 Copper Row, London , United Kingdom, SE1 2LH | Directly Connected Power Station | 27/10/2023 |
| Net Zero One Limited | 13505202 | The Long Barn Manor Courtyard, Stratton-On-The-Fosse, Radstock , United Kingdom, BA3 4QF | Directly Connected Power Station | 09/06/2022 |
| NET ZERO TEESSIDE POWER LIMITED | 12473751 | CHERTSEY ROAD, SUNBURY-ON-THAMES , United Kingdom, TW16 7BP | Directly Connected Power Station | 03/06/2021 |
| Neuconnect Britain Ltd | 11138769 | c/o FULCRUM, 1 05 PICCADILLY, LONDON , UNITED KINGDOM, W1J 7NJ | Interconnector Owner | 28/02/2019 |
| Newatt Srl | 03591360049 | Piazza Cecilia Arione Morando 6B, Magliano Alfieri, Cuneo, Italy, 12050 | Interconnector User | 14/09/2023 |
| NEW CUMNOCK BESS LTD | 14725803 | The Factory, Whitchurch, Ross-On-Wye, Herefordshire, United Kingdom, HR9 6DF | Directly Connected Power Station | 17/12/2024 |
| NEW DEER ENERGY CENTRE LIMITED | SC766864 | 13 Queen's Road, Aberdeen , United Kingdom, AB15 4YL | Directly Connected Power Station | 03/04/2025 |
| NEW ENERGY PARTNERSHIP LIMITED | 13895454 | Building 7 Floor 4, Vantage Point Business Village, Mitcheldean , United Kingdom, GL17 0DD | Directly Connected Power Station | 19/04/2023 |
| NEWHOUSE ENERGY STORAGE LIMITED | SC592721 | 33 BOTHWELL ROAD, HAMILTON , United Kingdom, ML3 0AS | Embedded Exemptable Large Power Station | 25/04/2022 |
| NEWLANDS HILL WIND ENERGY HUB LIMITED | 13327241 | 10 Victoria Street, Bristol , United Kingdom, BS1 6BN | Directly Connected Power Station | 07/07/2022 |
| NEW MARTON GREEN ENERGY CENTRE LIMITED | 15365178 | Flat 81 Blake Tower, 2 Fann Street, London , EC2Y 8AF | Directly Connected Power Station | 22/01/2025 |
| Newton Energi Limited | 10199022 | Meadow House, L ong Bennington Business Park, Long Bennington, Newark, United Kingdom, NG23 5JR | Directly Connected Power Station | 16/11/2023 |
| NEXTPOWER EELPOWER CAMILLA LIMITED | SC614202 | 5 SOUTH CHARLOTTE STREET, EDINBURGH , United Kingdom, EH2 4AN | Embedded Exemptable Large Power Station | 08/10/2019 |
| Ninfield 10 Renewables Limited | 15125441 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 22/11/2023 |
| NINFIELD GREEN ENERGY CENTRE LIMITED | 14003910 | 3rd Floor, Norfolk House, 106 Saxon Gate West, Milton Keynes , United Kingdom, MK9 2DN | Directly Connected Power Station | 15/02/2023 |
| NISTHILL WIND FARM LIMITED | 13944407 | 16 West Boroughnull , Dorset , BH21 1NG | Embedded Exemptable Large Power Station | 27/11/2024 |
| Nitor Energy AS | 38680781 | Klosterport, Aarhus , Denmark, 8000 | Interconnector User | 27/07/2021 |
| NLEI LTD | SC511747 | Ground Floor West Suite, Prospect House,5 Thistle Street, Edinburgh , United Kingdom, EH2 1DF | Directly Connected Power Station | 16/02/2016 |
| NNB GENERATION COMPANY (HPC) LIMITED | 06937084 | 90 WHITFIELD STREET, LONDON , UNITED KINGDOM, W1T 4EZ | Directly Connected Power Station | 26/09/2013 |
| Nordic Energy House ApS | 39533685 | 27 Østergade, Aarhus , Denmark, 8000 | Interconnector User | 08/12/2020 |
| NORD POOL EUROPEAN MARKET COUPLING OPERATOR AS | 984058098 | LILLEAKERVEIEN 2A, OSLO , Norway, 283 | Interconnector User | 23/05/2014 |
| NORFOLK BOREAS LIMITED | 03722058 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 11/09/2006 |
| Norfolk Vanguard East Ltd | 12476373 | First Floor, 1 Tudor Street, London EC4Y 0AH | Directly Connected Power Station | 10/03/2021 |
| NORFOLK VANGUARD WEST LIMITED | 08141115 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 11/02/2016 |
| NORIKER POWER LTD | 09675162 | Fourth Floor The Quadrangle, Imperial Square, Cheltenham, Hereford, United Kingdom, GL50 1PZ | Directly Connected Power Station | 02/10/2023 |
| NORLYS ENERGY TRADING A/S | 41419849 | OVERBAEKKEN 6, AALBORG , Denmark, 9000 | Interconnector User | 16/05/2022 |
| NORTHAMPTON ENERGY PARK LIMITED | 15040505 | 1st Floor Sackville House, 143-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 29/09/2023 |
| NORTHCONNECT LIMITED | SC633953 | 37 Albyn Place, Aberdeen , United Kingdom, AB10 1YN | Interconnector Owner | 03/02/2020 |
| NORTHERN POWERGRID (NORTHEAST) PLC | 02906593 | Lloyds Court, 78 Grey Street, Newcastle Upon Tyne , United Kingdom, NE1 6AF | Directly Connected Distribution System | 18/09/2001 |
| NORTHERN POWERGRID (YORKSHIRE) PLC | 04112320 | Lloyds Court, 78 Grey Street, Newcastle Upon Tyne , United Kingdom, NE1 6AF | Directly Connected Distribution System | 21/03/2025 |
| NORTH FALLS OFFSHORE WIND FARM LIMITED | 12435947 | Windmill Hill Business Park, Whitehill Way, Swindon , United Kingdom, SN5 6PB | Directly Connected Power Station | 23/11/2020 |
| Northfleet Devco Limited | 15941657 | 5 Fleet Place, London , United Kingdom, EC4M 7RD | Directly Connected Power Station | 19/11/2024 |
| NORTH KYLE WIND FARM LIMITED | SC572042 | c/o Brockwell Energy Limited, The Eagle Building-Third Floor, 1 9 Rose Street, Edinburgh, Edinburgh, United Kingdom, EH2 2PR | Directly Connected Power Station | 15/05/2019 |
| Northland Power UK Limited | 11587463 | 21 Holborn Viaduct, London , United Kingdom, EC1A 2DY | Directly Connected Power Station | 05/10/2021 |
| North Lanrigg Battery Storage Ltd | SC737400 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Directly Connected Power Station | 20/07/2023 |
| NORTHPOOL B.V. | 56443838 | 3E BINNENVESTGRACHT 23 N, LEIDEN, The Netherlands, Netherlands, 2312 NR | Interconnector User | 02/08/2018 |
| Northumberland Estates Limited | 05941545 | Quayside House , 1 10 Quayside,, Newcastle Upon Tyne , United Kingdom, NE1 3DX | Embedded Power Station | 05/06/2023 |
| NORWICH GREEN ENERGY LIMITED | 13476169 | The Goods Shed, J ubilee Way, Faversham, Kent, United Kingdom, ME13 8GD | Directly Connected Power Station | 16/02/2022 |
| NOVENTUM POWER SOLAR 11 LIMITED | 15371784 | 19 Eastbourne Terrace, London , United Kingdom, W2 6LG | Directly Connected Power Station | 28/10/2024 |
| NOVENTUM POWER SOLAR 12 LIMITED | 15370475 | 19 Eastbourne Terrace, London , United Kingdom, W2 6LG | Directly Connected Power Station | 24/09/2024 |
| NOVENTUM POWER SOLAR 13 LIMITED | 15370498 | 6th Floor 2 London Wall Place,, London , United Kingdom, EC2Y 5AU | Directly Connected Power Station | 28/10/2024 |
| NOVENTUM POWER SOLAR 14 LIMITED | 15370476 | 19 Eastbourne Terrace, London , United Kingdom, W2 6LG | Directly Connected Power Station | 17/09/2024 |
| NOVENTUM POWER SOLAR 15 LIMITED | 15370540 | 19 Eastbourne Terrace, London , United Kingdom, W2 6LG | Directly Connected Power Station | 16/10/2024 |
| NOVENTUM POWER SOLAR 1 LIMITED | 14742996 | 19 Eastbourne Terrace, London , United Kingdom, W2 6LG | Directly Connected Power Station | 15/01/2024 |
| NOVENTUM POWER SOLAR 2 LIMITED | 14743068 | 19 Eastbourne Terrace, London , United Kingdom, W2 6LG | Directly Connected Power Station | 30/09/2023 |
| NOVENTUM POWER SOLAR 3 LIMITED | 14743154 | 19 Eastbourne Terrace, London , United Kingdom, W2 6LG | Directly Connected Power Station | 30/09/2023 |
| NOVENTUM POWER SOLAR 4 LIMITED | 14743131 | 19 Eastbourne Terrace, London , United Kingdom, W2 6LG | Directly Connected Power Station | 15/01/2024 |
| NOVENTUM POWER SOLAR 5 LIMITED | 14743200 | 19 Eastbourne Terrace, London , United Kingdom, W2 6LG | Directly Connected Power Station | 15/01/2024 |
| NOVENTUM POWER SOLAR 6 LIMITED | 15094892 | 19 Eastbourne Terrace, London , United Kingdom, W2 6LG | Directly Connected Power Station | 20/06/2024 |
| NOVENTUM POWER SOLAR 7 LIMITED | 15093621 | 6th Floor 2 London Wall Place, London , United Kingdom, EC2Y 5AU | Directly Connected Power Station | 15/01/2024 |
| Noventum Power Solar 8 Limited | 15251228 | 19 Eastbourne Terrace, London , United Kingdom, W2 6LG | Directly Connected Power Station | 20/08/2024 |
| Noventum Power Solar 9 Limited | 15251143 | 19 Eastbourne Terrace, London , United Kingdom, W2 6LG | Directly Connected Power Station | 20/08/2024 |
| NOVERGY LTD | 11676519 | Hartham Park, Hartham Lane, Corsham , United Kingdom, SN13 0RP | Directly Connected Power Station | 05/02/2020 |
| NPOWER COMMERCIAL GAS LIMITED | 03768856 | Westwood Way, W estwood Business Park, Coventry , United Kingdom, CV4 8LG | Supplier | 25/05/2021 |
| NPOWER LIMITED | 03653277 | Westwood Way, W estwood Business Park, Coventry , UNITED KINGDOM, CV4 8LG | Supplier | 18/09/2001 |
| NP SPV 21 LIMITED | 14673199 | Lilly House, 13 Hanover Square, London , United Kingdom, W1S 1HN | Directly Connected Power Station | 08/12/2023 |
| NP SPV 22 LIMITED | 14858948 | Lilly House, 13 Hanover Square, London , United Kingdom, W1S 1HN | Directly Connected Power Station | 08/12/2023 |
| NP SPV23 LIMITED | 14858360 | Level 8 Lily House, 1 3 Hanover Square, Mayfair, London, United Kingdom, W1S 1HN | Directly Connected Power Station | 08/12/2023 |
| NP SPV24 LIMITED | 14858485 | 12 Bridewell Place, London , United Kingdom, EC4V 6AP | Directly Connected Power Station | 03/12/2024 |
| NP SPV 29 LIMITED | 15006705 | Level 8 Lily House, 1 3 Hanover Square,, Mayfair, London, United Kingdom, W1S 1HN | Directly Connected Power Station | 04/10/2024 |
| NP SPV30 LIMITED | 15006757 | Level 8, Lily House, 13 Hanover Square, London , United Kingdom, W1S 1HN | Directly Connected Power Station | 16/12/2024 |
| NP SPV31 Limited | 14673340 | 12 Bridewell Place, Third Floor East,, London , EC4V 6AP | Directly Connected Power Station | 10/10/2024 |
| NP SPV32 LIMITED | 14858425 | 12 Bridewell Place,, London , EC4V 6AP | Directly Connected Power Station | 04/10/2024 |
| NP SPV33 LIMITED | 14859626 | 12 Bridewell Place,, London , EC4V 6AP | Directly Connected Power Station | 28/11/2024 |
| NP SPV34 LIMITED | 14858567 | Level 8 Lily House 13 Hanover Square, Mayfair, London, , W1S 1HN | Directly Connected Power Station | 23/12/2024 |
| NP SPV35 LIMITED | 14858518 | 12 Bridewell Place, London , EC4V 6AP | Directly Connected Power Station | 18/11/2024 |
| NP SPV 39 LIMITED | 15006461 | Lilly House, 13 Hanover Square, London , United Kingdom, W1S 1HN | Directly Connected Power Station | 18/01/2024 |
| NP SPV 41 LIMITED | 15592880 | Level 8 Lily House, 1 3 Hanover Square, Mayfair, London, United Kingdom, W1S 1HN | Directly Connected Power Station | 05/12/2024 |
| NP SPV 43 Limited | 15850610 | Level 8 Lily House, 13 Hanover Square, Mayfair, London, United Kingdom, W1S 1HN | Directly Connected Power Station | 24/01/2025 |
| NS SOLAR KINNON PARK LIMITED | 14541632 | 13-17 Margett StreetCottenham , CB24 8QY | Embedded Exemptable Large Power Station | 27/03/2025 |
| NTT Global Data Centers LON2-A Ltd | 16122721 | 1 King William Street, London , United Kingdom, EC4N 7BJ | Non-Embedded Customer Site | 25/03/2025 |
| NUCLEAR DECOMMISSIONING AUTHORITY | N/A | Herdus House, Westlakes Science & Technology Park, Moor Row, Cumbria, United Kingdom, CA24 3HU | Non CUSC Party | |
| NUCLEAR RESTORATION SERVICES LIMITED | 02264251 | Hinton House, B irchwood Park Avenue, Risley, Warrington, Cheshire, United Kingdom, WA3 6GR | Embedded Power Station | 18/09/2001 |
| NURSLING ENERGY TWO LIMITED | 11020721 | 6th Floor, St Magnus House, 3 Lower Thames Street, London , United Kingdom, EC3R 6HD | Directly Connected Power Station | 09/07/2019 |
| Nvalue AG | CHE 113 939 430 | Shileggstrasse 23, Wollerau , Switzerland, 8832 | Interconnector User | 07/04/2021 |
| O&G Solar (SPV 19) Limited | 13892141 | 315, 37 Cremer Street, London , United Kingdom, E2 8HD | Directly Connected Power Station | 08/03/2023 |
| O&G Solar (SPV 20) Limited | 14028889 | 315, 37 Cremer Street, London , United Kingdom, E2 8HD | Directly Connected Power Station | 06/02/2024 |
| O&G Solar (SPV 30) Limited | 14214882 | 315, 37 Cremer Street, London , United Kingdom, E2 8HD | Directly Connected Power Station | 06/12/2022 |
| O&G Solar (SPV 31) Limited | 14135842 | 315, 37 Cremer Street, London , United Kingdom, E2 8HD | Directly Connected Power Station | 06/12/2022 |
| O&G Solar (SPV 36) Limited | 14368457 | 315, 37 Cremer Street, London , United Kingdom, E2 8HD | Directly Connected Power Station | 26/05/2023 |
| O&G Solar (SPV 38) Limited | 14370357 | 315, 37 Cremer Street, London , United Kingdom, E2 8HD | Directly Connected Power Station | 13/06/2023 |
| O&G Solar (SPV 39) Limited | 14373796 | 315, 37 Cremer Street, London , United Kingdom, E2 8HD | Directly Connected Power Station | 19/06/2023 |
| O&G Solar (SPV 40) Limited | 14376431 | 315, 37 Cremer Street, London , United Kingdom, E2 8HD | Directly Connected Power Station | 26/05/2023 |
| O&G Solar (SPV 47) Limited | 14444176 | 315, 37 Cremer Street, London , United Kingdom, E2 8HD | Directly Connected Power Station | 20/02/2025 |
| O&G Solar (SPV 49) Limited | 14448556 | 315, 37 Cremer Street, London , United Kingdom, E2 8HD | Directly Connected Power Station | 25/07/2023 |
| O&G Solar (SPV 57) Limited | 15040467 | 315, 37 Cremer Street, London , United Kingdom, E2 8HD | Directly Connected Power Station | 14/05/2024 |
| OAKLANDS FARM SOLAR LIMITED. | 12915335 | 22 Chancery Lane, London , United Kingdom, WC2A 1LS | Directly Connected Power Station | 12/06/2023 |
| Octopus Energy Limited | 09263424 | UK House, 5th Floor, 164-182 Oxford Street, London, London, United Kingdom, W1D 1NN | Supplier | 06/11/2015 |
| OCTOPUS ENERGY TRADING LIMITED | 09263368 | Uk House, 5th Floor, 164-182 Oxford Street, London , United Kingdom, W1D 1NN | Supplier | 19/11/2015 |
| OFFSHORE WIND LIMITED | 12125532 | ONE ST PETER'S SQUARE, MANCHESTER , United Kingdom, M2 3DE | Directly Connected Power Station | 09/02/2021 |
| OFFSHORE WIND POWER LIMITED | SC605260 | Clava House, Cradlehall Business Park, Inverness , United Kingdom, IV2 5GH | Directly Connected Power Station | 01/05/2020 |
| OKU Power Limited | 659293 | Paramount Court, Corrig Road, Sandyford Industrial Estate, Dublin, DUBLIN, Ireland, 18 | Interconnector User | 09/03/2023 |
| Oliver Forest Wind Farm Limited | 14293534 | 19th Floor 22 Bishopsgate, London , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 09/10/2023 |
| Ompex AG | CHE-112.711.924 | 20 Mühlebachstrasse, Zürich , Switzerland, 8008 | Interconnector User | 04/03/2021 |
| ONE EARTH SOLAR FARM LIMITED | 13078087 | UNIT 2 CROSSWAYS BICESTER ROAD, AYLESBURY , United Kingdom, HP18 0RA | Directly Connected Power Station | 05/05/2021 |
| ONE PLANET DEVELOPMENTS LIMITED | 12261202 | Biddlesgate Farm, C ranborne, Wimborne , United Kingdom, BH21 5RS | Directly Connected Power Station | 24/01/2024 |
| ONE PLANET SOLAR FARM LIMITED | 12327233 | 2 Crossways Business Centre, Bicester Road, Kingswood, Aylesbury, United Kingdom, HP18 0RA | Directly Connected Power Station | 22/10/2021 |
| Onpath Energy Limited | 02387216 | Chase House, 4 Mandarin Road, Houghton-Le-Spring , United Kingdom, DH4 5RA | Directly Connected Power Station | 04/12/2023 |
| Onpath Energy Limited (KYPE MUIR WIND FARM) LIMITED | 06917667 | Inkerman House, S t John's Road, M eadowfield, Durham , United Kingdom, DH7 8XL | Directly Connected Power Station | 15/10/2013 |
| OnPath Energy Limited (MIDDLE MUIR WIND FARM) LIMITED | 07376956 | Inkerman House, S t John's Road, M eadowfield, Durham , United Kingdom, DH7 8XL | Directly Connected Power Station | 28/01/2014 |
| OPDE UK LIMITED | 08848489 | 12 Hammersmith Grove, London , United Kingdom, W6 7AP | Directly Connected Power Station | 29/03/2023 |
| OPTIMAL POWER NETWORKS LIMITED | 11024024 | No.1 Forbury Place, 4 3 Forbury Road, Reading , United Kingdom, RG1 3JH | Independent Distribution N/W Operator | 30/11/2020 |
| Optimax Energy Gmbh | HRB 29307 | Kathe-Kollwitz-Str.1, Leipzig , Germany, 4109 | Interconnector User | 30/08/2018 |
| OPTIMUS WIND LIMITED | 07883284 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 19/06/2015 |
| OPUS ENERGY (CORPORATE) LIMITED | 05199937 | DRAX POWER STATION, SELBY , United Kingdom, YO8 8PH | Supplier | 15/11/2004 |
| OPUS ENERGY LIMITED | 04382246 | DRAX POWER STATION, SELBY , United Kingdom, YO8 8PH | Supplier | 02/09/2002 |
| OPUS ENERGY RENEWABLES LIMITED | 07126582 | DRAX POWER STATION, SELBY , United Kingdom, YO8 8PH | Supplier | 01/06/2012 |
| Orddu Energy Park Limited | 14877649 | Hodge House, Guildhall Place, Cardiff , United Kingdom, CF10 1DY | Directly Connected Power Station | 09/01/2024 |
| Orkney Islands Council | N/A | School Place, Kirkwall, Orkney, United Kingdom, KW15 1NY | Directly Connected Power Station | 19/02/2024 |
| ORMONDE ENERGY LIMITED | 04874027 | 5th Floor, 70 St Mary Axe, London , United Kingdom, EC3A 8BE | Embedded Power Station | 11/09/2006 |
| ORRÖN ENERGY DEVELOPMENT LIMITED | 14737332 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HB | Directly Connected Power Station | 16/08/2023 |
| ORSTED BURBO (UK) LIMITED | 04129545 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Embedded Power Station; Interconnector User | 09/05/2007 |
| ORSTED ESS MERSEY LIMITED | 11206846 | 5 Howick Placenull, London, LONDON , SW1P 1WG | Embedded Power Station | |
| ORSTED HORNSEA PROJECT FOUR LIMITED | 08584182 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 01/03/2016 |
| ORSTED HORNSEA PROJECT THREE (UK) LIMITED | 08584210 | 5 HOWICK PLACE, LONDON , UNITED KINGDOM, SW1P 1WG | Directly Connected Power Station | 19/06/2015 |
| ORSTED ONSHORE UK LIMITED | 06636519 | 5 HOWICK PLACE, LONDON , UNITED KINGDOM, SW1P 1WG | Embedded Power Station | 17/10/2013 |
| ORSTED POWER (UK) LIMITED | 04984787 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 16/01/2023 |
| ORTHIOS DISTRIBUTION (ANGLESEY) LIMITED | 09540941 | c/o Begbies Traynor, 29th Floor, 40 Bank Street, London , United Kingdom, E14 5NR | Independent Distribution N/W Operator | 05/04/2016 |
| ORTHIOS POWER (ANGLESEY) LIMITED | 06983862 | c/o Begbies Traynor, 31st Floor, 40 Bank Street, London , United Kingdom, E14 5NR | Embedded Power Station | 16/08/2016 |
| OSSPV001 LIMITED | 10933403 | 8th Floor 100 Bishopsgatenull, London, LONDON, UK, EC2N 4AG | Embedded Power Station | 29/07/2021 |
| OURACK WIND FARM LLP | SO305106 | 3rd Floor, The Tun Building, 4 Jackson's Entry, Holyrood Road, Edinburgh , United Kingdom, EH8 8PJ | Directly Connected Power Station | 11/10/2022 |
| Ouse Energy Limited | 13270213 | 189-193 Earls Court Road, London , United Kingdom, SW5 9AN | Directly Connected Power Station | 05/04/2022 |
| OUTLOOK ENERGY LTD | 12061886 | ASTON HOUSE CORNWALL AVENUE, LONDON , United Kingdom, N3 1LF | Interconnector User | 08/03/2022 |
| OUTOKUMPU STAINLESS LIMITED | 02794127 | Distribution Offices, E uropa Link, Sheffield , United Kingdom, S9 1TZ | Non CUSC Party | 11/10/2022 |
| OVO ELECTRICITY LTD | 06858121 | 1 Rivergate, Temple Quay, Bristol , United Kingdom, BS1 6ED | Supplier | |
| P3P ENERGY SUPPLY LIMITED | 10872509 | FIRST FLOOR 5 FLEET PLACE, LONDON, LONDON, United Kingdom, EC4M 7RD | Supplier | 25/02/2020 |
| P3P PARTNERS LLP | OC365083 | First Floor, 5 Fleet Place, London , United Kingdom, EC4M 7RD | Directly Connected Power Station | 04/05/2023 |
| PATRIZIA PIM LIMITED | 01878842 | 24 Endell Street, London , United Kingdom, WC2H 9HQ | Non-Embedded Customer Site | 25/08/2021 |
| PAUL'S HILL II LIMITED | SC353922 | c/o Harper Macleod Llp, T he Cadoro, 45 Gordon Street, Glasgow , United Kingdom, G1 3PE | Embedded Exemptable Large Power Station | 09/12/2014 |
| PAUL'S HILL WIND LIMITED | 04364516 | 2ND FLOOR, 36 BROADWAY, LONDON , United Kingdom, SW1H 0BH | Embedded Exemptable Large Power Station | 22/07/2005 |
| PD300RON Ltd | 13277482 | Basement 68 Gloucester Street, London , United Kingdom, SW1V 4EF | Directly Connected Power Station | 24/06/2022 |
| PD503HAN LTD | 13247820 | BASEMENT 68 GLOUCESTER STREET, LONDON , United Kingdom, SW1V 4EF | Directly Connected Power Station | 14/09/2021 |
| PD688IRO LTD | 13255644 | BASEMENT 68 GLOUCESTER STREET, LONDON , United Kingdom, SW1V 4EF | Directly Connected Power Station | 14/09/2021 |
| PD813ETY LTD | 13247847 | BASEMENT 68 GLOUCESTER STREET, LONDON , United Kingdom, SW1V 4EF | Directly Connected Power Station | 14/09/2021 |
| PEAK GEN POWER 2 LIMITED | 08179576 | Gables Lodge, 62 Kenilworth Road, Leamington Spa, Warwickshire, United Kingdom, CV32 6JX | Embedded Power Station | 10/05/2018 |
| PEAK GEN TOP CO LIMITED | 08544585 | Gables Lodge62, Kenilworth Road, Leamington Spa, Warwickshire , CV32 6JX | Interconnector User | 25/09/2024 |
| PEEL NRE DEVELOPMENTS LIMITED | 06335364 | Venus Building, 1 Old Park Lane, Traffordcity, Manchester, United Kingdom, M41 7HA | Embedded Power Station | 26/10/2022 |
| PELHAM ENERGY PARK LIMITED | 14376564 | 1st Floor Sackville House, 143-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 08/08/2023 |
| PELHAM GREEN ENERGY CENTRE LTD | 14437509 | Flat 81 Blake Tower, 2 Fann Street, London , United Kingdom, EC2Y 8AF | Directly Connected Power Station | 21/11/2024 |
| PENCLOE WIND ENERGY LIMITED | SC398688 | 50 Lothian Road, Festival Square, Edinburgh , United Kingdom, EH3 9WJ | Embedded Power Station | 28/04/2014 |
| PENMANSHIEL ENERGY LIMITED | 08263863 | CUBICO SUSTAINABLE INVESTMENTS, LONDON , United Kingdom, EC3A 8BE | Directly Connected Power Station; Dormant CUSC Party; Embedded Power Station | 03/10/2014 |
| PENTLAND ROAD WINDFARM LIMITED | 06661827 | Harpford Farm, Payton, Wellington, Somerset, United Kingdom, TA21 0EE | Embedded Exemptable Large Power Station | 13/11/2008 |
| Penwortham (BES) Ltd | 13789677 | Unit 1, Junction Lane, Newton-le-Willows , United Kingdom, WA12 8DN | Directly Connected Power Station | 10/11/2022 |
| PENWORTHAM GREEN ENERGY LIMITED | 13358478 | The Goods Shed, J ubilee Way, Faversham, Kent, United Kingdom, ME13 8GD | Directly Connected Power Station | 18/11/2021 |
| PEN Y CYMOEDD WIND FARM LIMITED | 03494498 | 5th Floor, 70 St Mary Axe, London , United Kingdom, EC3A 8BE | Directly Connected Power Station | 20/12/2006 |
| PEPPERHILL SOLAR FARM LIMITED | 13354040 | Stirling Square, 5-7 Carlton Gardens, London , United Kingdom, SW1Y 5AD | Directly Connected Power Station | 31/05/2022 |
| Perry Barr Limited | 11307128 | 25 Great Pulteney Street, London , W1F 9LF | Directly Connected Power Station | 17/12/2024 |
| PETERHEAD FLEXPOWER LTD | SC692128 | 272 BATH STREET, GLASGOW , United Kingdom, G2 4JR | Directly Connected Power Station | 21/12/2021 |
| PetroChina International (London) CO., Limited | 04410974 | The Adelphi 1-11, John Adam Street, London, LONDON, United Kingdom, WC2N 6HT | Interconnector User | 25/07/2024 |
| PETROINEOS TRADING LIMITED | 107836 | 44 Esplanade, St Helier, St Helier, Jersey (United Kingdom, JE4 9WG | Interconnector User | 16/04/2014 |
| P-FREQUENCY LTD | 14034023 | 3 Dove Tree Apartments;95 Grove Park, London , NW9 0FP | Directly Connected Power Station | 24/03/2025 |
| PINES BURN WIND FARM LLP | OC428008 | Sovereign House, 212-224 Shaftesbury Avenue, London , United Kingdom, WC2H 8HQ | Directly Connected Power Station | 26/08/2020 |
| PITKEVY BATTERY STORAGE LIMITED | SC668224 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Embedded Exemptable Large Power Station | 06/03/2022 |
| Pittlesheugh Farm BESS Limited | SC749339 | Pittlesheugh Farm, Greenlaw, Duns, United Kiongdom, TD10 6UL | Directly Connected Power Station | 20/02/2025 |
| PIVOTED POWER LLP | OC420973 | Alexander House 1 Mandarin RoadRainton Bridge Business Park, Houghton Le Spring, Sunderland, uk, DH4 5RA | Directly Connected Power Station | 06/09/2018 |
| PLANET 9 ENERGY LIMITED | 10167383 | Eastcastle House, 27/28 Eastcastle Street, London , United Kingdom, W1W 8DH | Supplier | 02/11/2016 |
| POGBIE WIND FARM (GRID) LIMITED | SC575533 | Loganwood House, H igh Mathernock Farm,A uchentiber Road, Kilmacolm, Renfrewshire, United Kingdom, PA13 4SP | Directly Connected Power Station | 10/11/2017 |
| Point and Sandwick Power Limited | SC369199 | 26 Lewis Street, Stornoway, Isle Of Lewis, United Kingdom, HS1 2JF | Embedded Power Station | 03/03/2023 |
| POLLIE HILL WIND FARM LIMITED | 14139559 | 22-24 King Street, Maidenhead, Berkshire, United Kingdom, SL6 1EF | Directly Connected Power Station | 27/02/2024 |
| Pond Flexible Energy Park Limited | 14486869 | Inkerman House, S t. Johns Road, Meadowfield, County Durham, United Kingdom, DH7 8XL | Directly Connected Power Station | 21/09/2023 |
| POTENCIA ENERGY LIMITED | SC758168 | 216 West George Street, Glasgow , United Kingdom, G2 2PQ | Directly Connected Power Station | 13/03/2023 |
| POWER BY BRITISHVOLT LIMITED | 12381543 | 1 More London Place, London , United Kingdom, SE1 2AF | Non-Embedded Customer Site | 10/08/2021 |
| POWERMART APS | 36201770 | ABOULEVARDEN 17 A, 03, AARHUS C , Denmark, 8000 | Interconnector User | 18/10/2017 |
| POWER NI ENERGY LIMITED | NI27394 | GREENWOOD HOUSE, BELFAST , United Kingdom, BT9 5NW | Interconnector User | 29/06/2012 |
| Power On Technologies Ltd t/a Joulen | NI643146 | 19 Bedford Street, Belfast , United Kingdom, BT2 7EJ | Virtual Lead Party | 17/04/2025 |
| POWERSITE LTD | 08076202 | MULBERRY HOUSE, ANDOVER , United Kingdom, SP11 6EF | Directly Connected Power Station | 13/09/2017 |
| POZITIVE ENERGY LTD | 09523048 | THE OCTAGON 27 MIDDLEBOROUGH, COLCHESTER , United Kingdom, CO1 1TG | Supplier | 26/09/2016 |
| PRIESTGILL WIND FARM LIMITED | 07640919 | Springfield, Ackenthwaite,, Milnthorpe, United Kingdom, LA7 7DQ | Directly Connected Power Station | 10/09/2019 |
| PRIVATE ENERGY PARTNERS (UK) LTD | 12673927 | 3rd Floor, 24 Savile Row, London , United Kingdom, W1S 2ES | Directly Connected Power Station | 17/03/2025 |
| PROGRESS POWER LIMITED | 08421833 | DRAX POWER STATION, SELBY, YORKSHIRE, United Kingdom, YO8 8PH | Directly Connected Power Station | 12/11/2013 |
| PROLOGIS UK CCCXXXVIII S.À R.L | OE021391 | 34 Avenue de la Liberté, Luxembourg , Luxembourg, 1930 | Directly Connected Power Station | 13/07/2023 |
| Pulse Clean Energy Limited | 07056616 | 2 New Bailey, 6 Stanley Street, Salford, Manchester , UNITED KINGDOM, M3 5GS | Directly Connected Power Station | 06/12/2023 |
| PULSE CLEAN ENERGY SPV FRANKLIN LIMITED | 13726084 | 197 Kensington High Street, London , United Kingdom, W8 6BA | Directly Connected Power Station | 12/04/2023 |
| QAIR RENEWABLES UK LIMITED | 09800258 | 5th Floor, Exchange Station, T ithebarn Street, Liverpool , United Kingdom, L2 2QP | Directly Connected Power Station | 23/01/2023 |
| QAIR SCOTLAND LIMITED | SC705805 | 1 Johns Place;Leith, Edinburgh , EH6 7EL | Directly Connected Power Station | 17/03/2025 |
| Q-Energy Sustainable Investments Ltd | 13821241 | 58 Marylebone High Street, London , United Kingdom, W1U 5HT | Directly Connected Power Station | 07/12/2023 |
| QUARK ENERGY TRADING LIMITED | 13051162 | Oxford Centre For Innovation, New Road, Oxford, OXFORD, United Kingdom,, OX1 1BY | Interconnector User | 12/04/2023 |
| Queequeg Renewables Ltd | 11780524 | 2nd Floor, The Works, 14 Turnham Green Terrace Mews, London , United Kingdom, W4 1QU | Directly Connected Power Station | 21/09/2023 |
| QUENT ApS | 39711303 | Svanemøllevej 41, Hellerup, Hellerup, Denmark, 2900 | Interconnector User | 06/02/2023 |
| QUESTPIT LIMITED | 09533916 | 7th Floor, Aldgate High Street, London , United Kingdom, EC3N 1AG | Non-Embedded Customer Site | 25/07/2024 |
| QUIXWOOD MOOR LIMITED | 07455293 | Suite 5, 7th Floor, 50 Broadway, London , United Kingdom, SW1H 0DB | Dormant CUSC Party; Embedded Power Station | 07/10/2014 |
| Rabbit Marketing Ltd | 13341181 | 2 Upperton Gardens, Eastbourne , United Kingdom, BN21 2AH | Directly Connected Power Station | 08/12/2023 |
| RACE BANK WIND FARM LIMITED | 05017828 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 27/10/2005 |
| RAD CHP LIMITED | 14200920 | 5 Seaforth Place, London , United Kingdom, SW1E 6AB | Non-Embedded Customer Site | 09/11/2023 |
| RADIANT ENERGY HOLDINGS LIMITED | 14423102 | St Georges House 6th Floor, 1 5 Hanover Square, London , United Kingdom, W1S 1HS | Dormant CUSC Party | 02/06/2023 |
| RADIUS ENERGY LIMITED | 11211289 | Eurocard Centre Herald Park, Herald Drive, Crewe , United Kingdom, CW1 6EG | Supplier | 28/07/2021 |
| RAMPION EXTENSION DEVELOPMENT LIMITED | 12091939 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 05/10/2021 |
| RAMPION OFFSHORE WIND LIMITED | 07199847 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 20/12/2001 |
| RAYLEIGH GREEN LIMITED | 12517501 | Ropemaker Place 2 8 Ropemaker Street, London , United Kingdom, EC2Y 9HD | Directly Connected Power Station | 24/07/2020 |
| RDRL LIMITED | SC457854 | 295 Fenwick Road;Giffnock, Glasgow , G46 6UH | Non-Embedded Customer Site | 07/04/2025 |
| REBEL ENERGY SUPPLY LIMITED | 10767623 | First Floor, 10 Queen Street Place, London , United Kingdom, EC4R 1BE | Supplier | 02/02/2021 |
| Recell Energy Bloom Developments Limited | 14160610 | 5 Sidings Court, White Rose Way, Doncaster, Yorkshire, United Kingdom, DN4 5NU | Embedded Power Station | 16/10/2022 |
| RECHARGE PRODUCTION UK LIMITED | 14631941 | 27 Old Gloucester Street, London , United Kingdom, WC1N 3AX | Directly Connected Power Station | 06/04/2023 |
| Regen Properties LLP | OC433666 | 167 Broadhurst Gardens, London , United Kingdom, NW6 3AU | Non-Embedded Customer Site | 21/07/2022 |
| REGENT POWER LIMITED | 09875997 | c/o Regent Gas Ltd, R egent House, Kendal Avenue, London , United Kingdom, W3 0XA | Supplier | 15/11/2021 |
| REG GREENBURN LIMITED | SC508240 | c/o Gillespie Macandrew Llp, 5 Atholl Crescent, Edinburgh , United Kingdom, EH3 8EJ | Directly Connected Power Station | 21/12/2018 |
| REG KNOCKODHAR LIMITED | SC566750 | 2 SEMPLE STREET, EDINBURGH , United Kingdom, EH3 8BL | Directly Connected Power Station | 08/05/2019 |
| REG Power Developments Limited | 13535415 | Unit 3b Damery Works, Damery Lane W oodford, Berkeley, Gloucestershire, United Kingdom, GL13 9JR | Directly Connected Power Station | 12/10/2023 |
| RELAY BALBEGGIE LIMITED | 13084817 | 1 Vine Street, London , United Kingdom, W1J 0AH | Embedded Exemptable Large Power Station | 14/03/2023 |
| RELAY HOLDCO LIMITED | 13084817 | 1 Vine Street, London , United Kingdom, W1J 0AH | Directly Connected Power Station | 02/01/2025 |
| RELAY SUTTIESIDE LIMITED | 13084884 | 1 VINE STREET, LONDON , United Kingdom, W1J 0AH | Directly Connected Power Station | 19/10/2021 |
| Renantis Energy Trading Srl. UK Branch | BR022176 | 10 Lower Grosvenor Place, London , United Kingdom, SW1W 0EN | Supplier | 04/07/2024 |
| Renantis UK Limited | 04501104 | Third Floor, 1 0 Lower Grosvenor Place, London , United Kingdom, SW1W 0EN | Directly Connected Power Station | 29/09/2023 |
| Renesola Hercules Energy 1 Limited | 13057891 | 9 St. Clare Street, London , United Kingdom, EC3 1LQ | Directly Connected Power Station | 17/11/2022 |
| Renewable Connections Developments Limited | 12351905 | Level 4 Ldn:W, 3 Noble Street, London , United Kingdom, EC2V 7EE | Embedded Exemptable Large Power Station | 28/03/2025 |
| Renewable Energy Systems Limited | 01589961 | Beaufort Court, Egg Farm Lane, Kings Langley, Hertfordshire, United Kingdom, WD4 8LR | Directly Connected Power Station | 05/08/2005 |
| RENEWABLES NORTH WEST LTD | 13987235 | 264 Manchester Road, Warrington, Cheshire, United Kingdom, WA1 3RB | Embedded Power Station | 06/02/2024 |
| RENEWCO POWER LIMITED | SC708511 | 10 Newton Place, Glasgow , United Kingdom, G3 7PR | Directly Connected Power Station | 25/01/2023 |
| RE Projects Development Limited | 08805101 | 565 High Road, Leytonstone, London, United Kingdom, E11 4PB | Directly Connected Power Station | 04/12/2022 |
| RESPECT ENERGY S.A. | 0000759658 | Ludwika Rydygiera 8, Warsaw , Poland, 01-793 | Interconnector User | 04/01/2023 |
| RES UK & IRELAND LIMITED | 04913493 | Beaufort Court Egg Farm LaneOff Station Road, Kings Langley , WD4 8LR | Directly Connected Power Station; Embedded Exemptable Large Power Station | 27/02/2006 |
| REVOLUTION ENERGY (SCOTLAND) LIMITED | SC582024 | 16 Muir Street, Hamilton , ML3 6EP | Directly Connected Power Station | 20/02/2024 |
| REWE 11 Limited | 15054172 | 111 Park Street, Mayfair, London, United Kingdom, W1K 7JF | Directly Connected Power Station | 13/12/2023 |
| REWE 1 LIMITED | 13710920 | 111 Park Street, Mayfair, London, United Kingdom, W1K 7JF | Directly Connected Power Station | 24/05/2023 |
| REWE 2 LIMITED | 13714757 | 111 Park Street, Mayfair, London, United Kingdom, W1K 7JF | Directly Connected Power Station | 28/11/2022 |
| REWE 3 LIMITED | 13714767 | 111 Park Street, Mayfair, London, United Kingdom, W1K 7JF | Directly Connected Power Station | 21/03/2023 |
| REWE 4 LIMITED | 13714782 | 111 Park Street, Mayfair, London, United Kingdom, W1K 7JF | Directly Connected Power Station | 21/11/2022 |
| REWE 5 LIMITED | 13714747 | Palladium House, 1-4 Argyll Street, London , United Kingdom, W1F 7LD | Directly Connected Power Station | 21/03/2023 |
| REWE 6 LIMITED | 13714752 | 111 Park Street, Mayfair, London, United Kingdom, W1K 7JF | Directly Connected Power Station | 24/05/2023 |
| REWE 7 LIMITED | 14475805 | 111 Park Street, Mayfair, London , United Kingdom, W1K 7JF | Directly Connected Power Station | 11/07/2023 |
| REWE 8 LIMITED | 14479318 | 111 Park Street, Mayfair, London, United Kingdom, W1K 7JF | Directly Connected Power Station | 11/08/2023 |
| REWE 9 LIMITED | 14879799 | 111 Park Street, Mayfair, London, United Kingdom, W1K 7JF | Directly Connected Power Station | 26/10/2023 |
| RHIGOS BESS LIMITED | 15206496 | Hodge House, Guildhall Place, Cardiff , United Kingdom, CF10 1DY | Directly Connected Power Station | 09/01/2024 |
| RHIWLAS ENERGY PARK LIMITED | 12580599 | Hodge House, Guildhall Place, Cardiff , United Kingdom, CF10 1DY | Embedded Power Station | 03/09/2021 |
| RICHBOROUGH ENERGY PARK LIMITED | 10158720 | 4 ALBEMARLE STREET, LONDON , UNITED KINGDOM, W1S 4GA | Directly Connected Power Station | 30/06/2020 |
| RIGGHILL WIND FARM LIMITED | 06850808 | Seebeck House, 1 Seebeck Place, Knowlhill, Milton Keynes, Buckinghamshire, United Kingdom, MK5 8FR | Embedded Power Station | 06/11/2020 |
| RISQ ENERGY LIMITED | 12705570 | 3rd Floor, 80 Cannon Street, London, LONDON, United Kingdom, EC4N 6HL | Interconnector User | 16/06/2023 |
| RIVER NENE POWER LIMITED | 04262250 | FIRST FLOOR, TEMPLEBACK, BRISTOL , United Kingdom, BS1 6FL | Embedded Power Station | 18/09/2001 |
| RIVOX WIND ENERGY HUB LIMITED | 13547705 | 10 Victoria Street, BRISTOL , United Kingdom, BS1 6BN | Directly Connected Power Station | 23/05/2022 |
| ROARING HILL ENERGY STORAGE LTD | 10272710 | Beaufort Court, Egg Farm Lane, Kings Langley, Hertfordshire, United Kingdom, WD4 8LR | Directly Connected Power Station | 30/11/2021 |
| Rochdale (BES) Ltd | 13789732 | Unit 1, Junction Lane, Newton-le-Willows , United Kingdom, WA12 8DN | Directly Connected Power Station | 10/11/2022 |
| ROCKSAVAGE POWER COMPANY, LTD. | FC018868 | Maples And Calder, Ugland House, P O BOX 309, George Town, Grand Cayman, Cayman Islands | Directly Connected Power Station | 18/09/2001 |
| Rosefield Energyfarm Limited | 11618221 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton Le Spring, Sunderland, United Kingdom, DH4 5RA | Directly Connected Power Station | 05/06/2020 |
| Rosside Energy Limited | 11033624 | 565 High Road, Leytonstone, London, United Kingdom, E11 4PB | Directly Connected Power Station | 13/10/2023 |
| ROTHES III LIMITED | SC307540 | c/o Harper Macleod Llp, T he Cadoro, 45 Gordon Street, Glasgow , United Kingdom, G1 3PE | Embedded Exemptable Large Power Station | 09/12/2014 |
| ROTHES II LIMITED | 04916606 | 2ND FLOOR, 36 BROADWAY, LONDON , United Kingdom, SW1H 0BH | Embedded Exemptable Large Power Station | 05/05/2006 |
| ROTHES WIND LIMITED | 04364513 | 2ND FLOOR, 36 BROADWAY, LONDON , United Kingdom, SW1H 0BH | Embedded Exemptable Large Power Station | 31/03/2005 |
| Rothienorman Flexpower A Ltd | SC745788 | 272 Bath Street, Glasgow , United Kingdom, G2 4JR | Directly Connected Power Station | 05/08/2022 |
| ROTHIENORMAN FLEXPOWER LTD | SC691670 | 272 BATH STREET, GLASGOW , UNITED KINGDOM, G2 4JR | Directly Connected Power Station | 21/12/2021 |
| ROTHIENORMAN GRID SERVICES LIMITED | 12648462 | FOURTH FLOOR, 2 KINGSWAY, CARDIFF , United Kingdom, CF10 3FD | Non-Embedded Customer Site | 03/03/2021 |
| ROWAN ONSHORE WINDFARMS LIMITED | 06708797 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton le Spring, Sunderland, United Kingdom, DH4 5RA | Directly Connected Power Station | 10/04/2024 |
| ROWNALL FARM SOLAR LIMITED | 12368199 | 22 CHANCERY LANE, LONDON , United Kingdom, WC2A 1LS | Directly Connected Power Station | 08/09/2020 |
| RPC ELMYA CARNATION DEVCO LIMITED | 15303566 | Princes House, Suite 2a, 38 Jermyn Street, London , United Kingdom, SW1Y 6DN | Directly Connected Power Station | 18/09/2024 |
| RPC ELMYA CARNATION FOXDALE LIMITED | 16013631 | Princes House, S uite 2a, 38 Jermyn Street, London , United Kingdom,, SW1Y 6DN | Directly Connected Power Station | 27/02/2025 |
| RPC ELMYA CARNATION GISSING LIMITED | 16014880 | Princes House, S uite 2a, 38 Jermyn Street, London , United Kingdom,, SW1Y 6DN | Directly Connected Power Station | 27/02/2025 |
| RPC ELMYA CARNATION KILWORTH LIMITED | 16014937 | Princes House, S uite 2a, 38 Jermyn Street, London , United Kingdom, SW1Y 6DN | Directly Connected Power Station | 27/02/2025 |
| RPC ELMYA CARNATION TOWCASTER LIMITED | 16014941 | Princes House, S uite 2a, 38 Jermyn Street, London , United Kingdom, SW1Y 6DN | Directly Connected Power Station | 27/02/2025 |
| RUFUSIA LTD | 15594981 | 2 Upperton Gardens, Eastbourne , United Kingdom, BN21 2AH | Directly Connected Power Station | 20/02/2025 |
| RUGELEY POWER GENERATION LIMITED | 03300792 | Rooms 481-499, Second Floor, Salisbury House, London Wall, London, United Kingdom, EC2M 5SQ | Directly Connected Power Station | 29/09/2017 |
| RUGELEY POWER LIMITED | 04212554 | Rooms 481-499 Second Floor, Salisbury House,, London Wall, London, United Kingdom, EC2M 5SQ | Directly Connected Power Station; Dormant CUSC Party | 18/09/2001 |
| RWE COGEN UK (HYTHE) LIMITED | 04445217 | Bishop Fleming Llp, 16 Queen Square, Bristol, BRISTOL, United Kingdom, BS1 4NT | Embedded Power Station | 09/03/2004 |
| RWE GENERATION UK PLC | 03892782 | Windmill Hill Business Park, Whitehill Way, Swindon , United Kingdom, SN5 6PB | Directly Connected Power Station | 18/09/2001 |
| RWE MARKINCH LIMITED | 06574689 | Windmill Hill Business Park, Whitehill Way, Swindon , United Kingdom, SN5 6PB | Directly Connected Power Station | 22/12/2009 |
| RWE Renewables UK Dogger Bank South (East) Limited | 13656240 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 05/12/2024 |
| RWE RENEWABLES UK DOGGER BANK SOUTH (WEST) LIMITED | 13656525 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 05/12/2024 |
| RWE RENEWABLES UK HUMBER WIND LIMITED | 04899318 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 14/09/2007 |
| RWE RENEWABLES UK LIMITED | 03758404 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 24/02/2022 |
| RWE RENEWABLES UK ONSHORE WIND LIMITED | 03758407 | Windmill Hill Business Park, Whitehill Way, Swindon , United Kingdom, SN5 6PB | Directly Connected Power Station; Embedded Power Station | 22/09/2006 |
| RWE RENEWABLES UK OPERATIONS LIMITED | 02692529 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Embedded Power Station | 29/12/2005 |
| RWE RENEWABLES UK ROBIN RIGG EAST LIMITED | 03568724 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 22/01/2010 |
| RWE RENEWABLES UK ROBIN RIGG WEST LIMITED | 04150735 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 22/01/2010 |
| RWE RENEWABLES UK SOLAR AND STORAGE LIMITED | 14539260 | Windmill Hill Business ParkWhitehill Way, Swindon , SN5 6PB | Directly Connected Power Station | 21/08/2023 |
| RWE RENEWABLES UK SWINDON LIMITED | 02550622 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | 09/05/2008 |
| RWE RENEWABLES UK ZONE SIX LIMITED | 07054842 | Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, United Kingdom, SN5 6PB | Directly Connected Power Station | |
| RWE STALLINGBOROUGH LIMITED | 6269884 | WINDMILL HILL BUSINESS PARK, SWINDON , United Kingdom, SN5 6PB | Embedded Power Station; No longer a CUSC Party | 25/07/2007 |
| RWE SUPPLY & TRADING GMBH | HRB 14327 | RWE PLATZ 6, ESSEN , Germany, 45141 | Interconnector User | 04/03/2011 |
| RYE HOUSE 10 RENEWABLES LIMITED | 15125422 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 22/11/2023 |
| S4N SPITTAL LTD | 14439316 | 51 Hollingbourne Road, London , United Kingdom, SE24 9NB | Directly Connected Power Station | 30/08/2023 |
| SAGE NORTH SEA LIMITED | FC033971 | Paget-Brown Trust Company Ltd Century Yard Cricket Square PO BOX 1111, George Town, Grand Cayman, Cayman Islands, Ky1-1102 | Non-Embedded Customer Site | 15/02/2018 |
| SALAMANDER WIND PROJECT COMPANY LIMITED | SC662940 | 2nd Floor, 2 Lochrin Square, 9 6 Fountainbridge, Edinburgh , United Kingdom, EH3 9QA | Directly Connected Power Station | 27/01/2022 |
| SALTEND CHEMICALS PARK LIMITED | 10542068 | Px House, Westpoint Road, Stockton-On-Tees , United Kingdom, TS17 6BF | Directly Connected Power Station | 20/12/2023 |
| Saltend Cogeneration Company Limited | 03274929 | Saltend Power Station, S altend Chemicals Park, Hedon Road, Hull, East Riding Of Yorkshire, United Kingdom, HU12 8GA | Directly Connected Power Station | 18/09/2001 |
| SAMBAR POWER LIMITED | SC380227 | Second Floor, 112 George Street, Edinburgh , United Kingdom, EH2 4LH | Directly Connected Power Station | 18/11/2022 |
| SANDY KNOWE WIND FARM LIMITED | 06850950 | c/o Tmf Group, 13th Floor, One Angel Court, London, London, United Kingdom, EC2R 7HJ | Directly Connected Power Station | 22/07/2014 |
| SANQUHAR COMMUNITY WIND COMPANY LIMITED | SC459230 | Caledonian Exchange, 19a Canning Street, Edinburgh , United Kingdom, EH3 8HE | Directly Connected Power Station | 18/07/2014 |
| SANQUHAR II COMMUNITY WIND CO LTD | SC449688 | Caledonian Exchange, 19a Canning Street, Edinburgh , United Kingdom, EH3 8HE | Directly Connected Power Station | 22/08/2016 |
| SAVE OUR PLANET ENERGY LIMITED | 14057269 | 2 Crossways Business Centre, Bicester Road, Kingswood, Aylesbury, United Kingdom, HP18 0RA | Directly Connected Power Station | 05/02/2025 |
| SCIRA OFFSHORE ENERGY LIMITED | 05119310 | 1 KINGDOM STREET, LONDON , United Kingdom, W2 6BD | Embedded Power Station | 09/01/2007 |
| SCORPIA ENERGY SUPPLY LTD | 12665145 | Connect House, 133-137 Alexandra Road, Wimbledon, London, United Kingdom, SW19 7JY | Supplier | 02/09/2024 |
| SCOT ELEC 1 LIMITED | 14893585 | 4th Floor, 80 Victoria Street, London , United Kingdom, SW1E 5JL | Non-Embedded Customer Site | 21/06/2024 |
| SCOT ELEC 2 LIMITED | 14888343 | 4th Floor, 80 Victoria Street, London , United Kingdom, SW1E 5JL | Directly Connected Power Station | 31/03/2025 |
| SCOT ELEC 3 LIMITED | 15074773 | 4th Floor, 80 Victoria Street, London , United Kingdom, SW1E 5JL | Non-Embedded Customer Site | 04/04/2024 |
| SCOT ELEC 4 LIMITED | 15075463 | 4th Floor, 80 Victoria Street, London , United Kingdom, SW1E 5JL | Non-Embedded Customer Site | 30/05/2024 |
| Scot Stability Limited | SC668729 | 272 Bath Street, Glasgow , United Kingdom, G2 4JR | Directly Connected Power Station | 07/04/2025 |
| Scottish Hydro Electric Power Distribution Plc | SC213460 | Inveralmond House, 200 Dunkeld Road, Perth , United Kingdom, PH1 3AQ | Directly Connected Distribution System | 01/01/1999 |
| ScottishPower Energy Retail Limited | SC190287 | 320 St. Vincent Street, Glasgow , United Kingdom, G2 5AD | Supplier | 18/09/2001 |
| SCOTTISHPOWER RENEWABLES (UK) LIMITED | NI028425 | The Soloist, 1 Lanyon Place, Belfast, Ireland, United Kingdom, BT1 3LP | Directly Connected Power Station | 31/03/2005 |
| SEABANK POWER LIMITED | 02591188 | Severn Road, Hallen, Bristol, United Kingdom, BS10 7SP | Directly Connected Power Station | 18/09/2001 |
| SEAGREEN 1A LIMITED | 12575047 | No.1 Forbury Place, 4 3 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 01/06/2020 |
| SEAGREEN ALPHA WIND ENERGY LIMITED | 07185533 | No.1 Forbury Place, 4 3 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station; Dormant CUSC Party | 18/02/2015 |
| SEAGREEN BRAVO WIND ENERGY LIMITED | 07185543 | No.1 Forbury Place, 4 3 Forbury Road,, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station; Dormant CUSC Party | 18/02/2015 |
| Seagreen Wind Energy Limited | 06873902 | No.1 Forbury Place, 43 Forbury Road, Reading, BERKSHIRE, United Kingdom, RG1 3JH | Directly Connected Power Station | 17/08/2010 |
| SEAGULL PROPERTIES LIMITED | 06885531 | Corner Oak, 1 Homer Road, Solihull, West Midlands, United Kingdom, B91 3QG | Directly Connected Power Station | 05/03/2025 |
| SEAHILLS PROPERTIES LIMITED | SC695795 | Unit 1a Halbeath Interchange Business Park, Kingseat Road,, Dunfermline, , Fife, KY11 8RY | Embedded Exemptable Large Power Station | 23/12/2024 |
| SECTION 31 SOLUTIONS LTD | 13135012 | 2 Hopkins Mead, Chelmsford , United Kingdom, CM2 6SS | Directly Connected Power Station | 21/12/2023 |
| SEFE Energy Limited | 03904624 | 20 TRITON STREET, LONDON , UNITED KINGDOM, NW1 3BF | Supplier | |
| SEGRO PROPERTIES LIMITED | 00448911 | 1 New Burlington Place, London , United Kingdom, W1S 2HR | Directly Connected Power Station | 28/02/2025 |
| SELLAFIELD LIMITED | 01002607 | HINTON HOUSE, WARRINGTON , United Kingdom, WA3 6GR | Dormant CUSC Party; Embedded Power Station | 18/09/2001 |
| SELLINDGE GRID SERVICES LIMITED | 12395277 | Fourth Floor, 2 Kingsway, Cardiff , United Kingdom, CF10 3FA | Directly Connected Power Station | 08/04/2022 |
| Sellindge West 10 Renewables Limited | 15125694 | Century House 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 22/11/2023 |
| SEMBCORP (WILTON BESS) LTD | 15151480 | Sembcorp UK Headquarters, Wilton International, Middlesbrough, Cleveland, UK, TS90 8WS | Directly Connected Power Station | 08/02/2024 |
| SEMBCORP UTILITIES (UK) LIMITED | 04636301 | Sembcorp UK Headquarters, Wilton International,, Middlesbrough, Cleveland, United Kingdom, TS90 8WS | Directly Connected Power Station | 20/03/2003 |
| SE RIGIFA BESS LTD | 14044436 | Calcutt Court, Calcutt, Swindon, United Kingdom, SN6 6JR | Embedded Exemptable Large Power Station | 08/05/2024 |
| SETT WIND DEVELOPMENT LIMITED | 10988810 | 16 West Borough, Wimborne, Dorset, United Kingdom, BH21 1NG | Directly Connected Power Station | 20/08/2019 |
| SEVERN POWER LIMITED | 05392552 | Severn Power Station, W est Nash Road, Nash, Newport, United Kingdom, NP18 2BZ | Directly Connected Power Station; Embedded Exemptable Large Power Station | 04/11/2005 |
| Shama BESS Limited | 14522918 | Penthouse Office 30 Queen Square, Bristol , United Kingdom, BS1 4ND | Directly Connected Power Station | 31/08/2023 |
| SHAW-ENERGI LTD | 03949279 | Unit 1, Junction Lane, Sankey Valley Industrial Estate, Newton Le Willows, Warrington, United Kingdom, WA12 8DN | Directly Connected Power Station | 19/05/2020 |
| SHEAF ENERGY LIMITED | 13270168 | 168 Church Roadnull, Hove , BN3 2DL | Directly Connected Power Station | 27/09/2022 |
| Sheilhill Battery Storage Limited | SC726914 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Directly Connected Power Station | 07/09/2022 |
| SHELL ENERGY EUROPE LIMITED | 04162523 | Shell Centre, LONDON, LONDON, UK, SE1 7NA | Interconnector User | 25/08/2014 |
| SHELL ENERGY UK LIMITED | 07489042 | Shell Centre, Y ork Road, London , United Kingdom, SE1 7NA | Supplier | 25/02/2013 |
| Shell New Energies UK Ltd | 04153040 | Shell Centre, London , United Kingdom, SE1 7NA | Directly Connected Power Station | 20/02/2025 |
| SHELL UK LIMITED | 00140141 | SHELL CENTRE, LONDON , UNITED KINGDOM, SE1 7NA | Non-Embedded Customer Site | 31/03/2005 |
| Shetland Offshore Wind Limited | 14306989 | Tricor Suite, 4th Floor, 50 Mark Lane, London , United Kingdom, EC3R 7QR | Directly Connected Power Station | 30/05/2023 |
| Shiel Hydrogen Plant Limited | SC759982 | 39 George Street, 4th Floor, Edinburgh , United Kingdom, EH2 2HN | Non-Embedded Customer Site | 20/12/2023 |
| Shotwick Land Limited | 10380450 | 45-51 Wychtree Street, Swansea , United Kingdom, SA6 8EX | Directly Connected Power Station | 21/03/2024 |
| SIMEC LOCHABER HYDROPOWER 2 LIMITED | 00750143 | c/o Marble Power Ltd, 1 st Floor, 3 More London Place, London , United Kingdom, SE1 2RE | Directly Connected Power Station; Embedded Power Station | 08/12/2014 |
| SIMEC USKMOUTH POWER LIMITED | 05104786 | Uskmouth Power Station, W est Nash Road, Nash, Newport, United Kingdom, NP18 2BZ | Directly Connected Power Station; No longer a CUSC Party | 25/08/2004 |
| SIMEC WIND ONE LTD | 10060100 | BIRDPORT CORPORATION ROAD, NEWPORT , United Kingdom, NP19 4RE | Directly Connected Power Station; Dormant CUSC Party | 22/01/2018 |
| SINCLAIR OFFSHORE WIND FARM LIMITED | SC750268 | First Floor, 2 Lochrin Square, 96 Fountainbridge, Edinburgh , United Kingdom, EH3 9QA | Directly Connected Power Station | 26/01/2024 |
| SINQ POWER LIMITED | 09284085 | NO. 1 DOVECOTE OLD HALL ROAD, SALE , United Kingdom, M33 2GS | Supplier | 02/02/2016 |
| SIRIUS ECODEV (BROXBURN) LTD | 12129867 | THE FACTORY, WHITCHURCH, ROSS-ON-WYE , United Kingdom, HR9 6DF | Embedded Power Station | 21/04/2022 |
| SIRIUSECODEV (GASTARD) LTD | 14807829 | Russell House, L ittleburn Industrial Estate, Langley Moor, Durham, United Kingdom, DH7 8HJ | Directly Connected Power Station | 12/12/2023 |
| SIRIUS ECODEV (KEITHICK) LTD | 13170877 | Overross House, Ross Park, Ross-on-Wye , United Kingdom, HR9 7US | Embedded Power Station | 27/10/2021 |
| SIRIUS ECODEV (STIRLING) LTD | 13459817 | The Factory,W hitchurch, Ross-on-Wye , United Kingdom, HR9 6DF | Embedded Power Station | 24/03/2022 |
| SIRIUS RENEWABLE ENERGY LTD | 10925888 | Russel House, M ill Road, Langley Moor, County Durham, United Kingdom, DH7 8HJ | Embedded Power Station | 18/11/2021 |
| Sizewell C Limited | 09284825 | 25 Copthall Avenue, London , United Kingdom, EC2R 7BP | Directly Connected Power Station | 26/06/2015 |
| SIZING JOHN LIMITED | 12997545 | C/O Watson Farley & Williams Llp15 Appold Street, London , EC2A 2HB | Directly Connected Power Station | 17/08/2021 |
| Skelmersdale Energy Storage Limited | 11347214 | 3 More London Riverside, London , United Kingdom,, SE1 2AQ | Embedded Power Station | 15/11/2022 |
| SKY UK DEVELOPMENT LIMITED | 13630960 | UK House, 5th Floor, 164-182 Oxford Street, London , United Kingdom, W1D 1NN | Directly Connected Power Station | 06/03/2025 |
| Slickly Wind Farm Limited | 11248508 | 19th Floor, 22 Bishopsgate, London , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 07/07/2021 |
| SLOUGH HEAT & POWER LIMITED | 00174142 | No.1 Forbury Place, 4 3 Forbury Road, Reading , United Kingdom, RG1 3JH | Non-Embedded Customer Site | 08/09/2021 |
| SMARTESTENERGY BUSINESS LIMITED | 06468946 | Ridgeworth House, L iverpool Gardens, Worthing, West Sussex, United Kingdom, BN11 1RY | Supplier | |
| SMARTESTENERGY LIMITED | 03994598 | The Columbus Building7 Westferry Circus, London, LONDON, UK, E14 4HD | Supplier | 18/01/2001 |
| SMS ENERGY SERVICES LIMITED | 03197379 | Prennau House, C opse Walk, C ardiff Gate Business Park, Pontprennau, Cardiff, United Kingdom, CF23 8XH | Directly Connected Power Station | 04/03/2024 |
| SNEDDON LAW COMMUNITY WIND COMPANY LTD | SC443267 | Caledonian Exchange, 19a Canning Street,, Edinburgh , United Kingdom, EH3 8HE | Embedded Power Station | 22/08/2016 |
| SO ENERGY TRADING LIMITED | 09263295 | Studio 2 Power Road Studios 114 Power RoadChiswick, London , W4 5PY | Supplier | 07/10/2015 |
| SOFIA OFFSHORE WIND FARM LIMITED | 07791964 | Windmill Hill Business Park, Whitehill Way, Swindon , United Kingdom, SN5 6PB | Directly Connected Power Station | 27/03/2017 |
| SOLAR 2 LIMITED | 11913504 | Linden House, W rexham Road, Mold Business Park, Mold , United Kingdom, CH7 1XP | Embedded Power Station | 23/09/2024 |
| SOLAR 2 PROJECT J LIMITED | SC709552 | WIND 2 OFFICE, 2 WALKER STREET, EDINBURGH , United Kingdom, EH3 7LA | Directly Connected Power Station | 20/10/2022 |
| SOLAR CENTURY HOLDINGS LIMITED | 03570325 | 19TH FLOOR, 22 BISHOPSGATE, LONDON , UNITED KINGDOM, EC2N 4BQ | Directly Connected Power Station | 21/02/2020 |
| SOLARFIVE LTD | 12602740 | 2 West Street, Henley-On-Thames, Oxfordshire, United Kingdom, RG9 2DU | Directly Connected Power Station | 20/09/2021 |
| SolarFour Ltd | 12602174 | 2 West Street, Henley-On-Thames, Oxfordshire, United Kingdom, RG9 2DU | Directly Connected Power Station | 21/12/2023 |
| SolarNine Ltd | 15010349 | 16 Great Queen Street, Covent, London, United Kingdom, WC2B 5AH | Directly Connected Power Station | 03/04/2025 |
| SOLAR SECURITIES LIMITED | 07074035 | 6 Hatfield Close, West Byfleet , United Kingdom, KT14 6PG | Directly Connected Power Station | 02/05/2024 |
| SolarSeven Ltd | 12603936 | 16 Great Queen Street, Covent Garden, London, United Kingdom, WC2B 5AH | Directly Connected Power Station | 26/03/2025 |
| SolarTen Ltd | 15136171 | 16 Great Queen Street, Covent Garden, London, United Kingdom, WC2B 5AH | Directly Connected Power Station | 31/03/2025 |
| SolarThree Ltd | 12602707 | 2 West Street, Henley-On-Thames, Oxfordshire, United Kingdom, RG9 2DU | Directly Connected Power Station | 01/02/2023 |
| SOLWAYBANK ENERGY LIMITED | 09275294 | Beaufort Court, Egg Farm Lane, Kings Langley, Hertfordshire, United Kingdom, WD4 8LR | Directly Connected Power Station | 15/11/2017 |
| SONI LIMITED | NI38715 | Castlereagh House, 1 2 Manse Road, Belfast , United Kingdom, BT6 9RT | Interconnector Error Administrator | 04/03/2005 |
| Sonnedix Weston Limited | 13987895 | 90 Union Street, London , United Kingdom, SE1 0NW | Embedded Exemptable Large Power Station | 19/04/2023 |
| SONNINGMAY WIND LIMITED | 10722635 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 26/10/2018 |
| SOUNDMARK WIND LIMITED | 10721881 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 26/10/2018 |
| SOURCE ENERGIE LIMITED | 12655787 | CALCUTT COURT CALCUTT, SWINDON , United Kingdom, SN6 6JR | Directly Connected Power Station | 21/11/2022 |
| Source GalileoL imited | 13475747 | Calcutt Court, Calcutt, Swindon , United Kingdom, SN6 6JR | Directly Connected Power Station | 06/03/2024 |
| SOUTH EASTERN POWER NETWORKS PLC | 03043097 | Newington House, 237 Southwark Bridge Road, London , United Kingdom, SE1 6NP | Directly Connected Distribution System | 18/09/2001 |
| Southern Electric Power Distribution Plc | 04094290 | No.1 Forbury Place, 4 3 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Distribution System | 18/09/2001 |
| SOUTH GRANTHAM ENERGY CENTRE LIMITED | 15670595 | Level 4 Ldn:W, 3 Noble Street, London , United Kingdom, EC2V 7EE | Directly Connected Power Station | 06/02/2025 |
| SOUTH KENT ENERGY PARK LIMITED | 13353151 | Stirling Square, 5-7 Carlton Gardens, London , United Kingdom, SW1Y 5AD | Directly Connected Power Station | 31/05/2022 |
| SOUTH KILBRAUR WIND FARM LIMITED | SC583096 | WIND 2 OFFICE 2, W ALKER STREET, EDINBURGH , UNITED KINGDOM, EH3 7LB | Embedded Exemptable Large Power Station | 03/10/2018 |
| SOUTH KYLE WIND FARM LIMITED | SC617500 | Dla Piper Scotland Llp, Collins House, R utland Square, Edinburgh , United Kingdom, EH1 2AA | Directly Connected Power Station | 13/03/2020 |
| South Street BESS Limited | 15278086 | 3rd Floor, St Georges House, 1 3-14 Ambrose Street, Cheltenham, Gloucestershire, United Kingdom, GL50 3LG | Directly Connected Power Station | 03/02/2025 |
| SOUTH TEES SITE COMPANY LIMITED | 10424065 | Teesside Airport Business Suite, T eesside International Airport, Darlington , United Kingdom, DL2 1NJ | Non-Embedded Customer Site | 05/10/2021 |
| South West Wind Holdco Limited | 13981274 | Amp Technology Centre Advanced Manufacturing Park, Brunel Way, Rotherham , United Kingdom, S60 5WG | Directly Connected Power Station | 23/01/2023 |
| SPALDING ENERGY COMPANY LTD | FC019668 | c/o Maples And Calder, A ttorneys-At-Law, U gland House,, George Town, B.W.Indies, Cayman Islands, PO Box 309 | Directly Connected Power Station | 18/09/2001 |
| SPALDING ENERGY EXPANSION LIMITED | 06790895 | 30 Crown Place, Earl Street, London , United Kingdom, EC2A 4ES | Directly Connected Power Station | 04/09/2014 |
| SP Distribution plc | SC189125 | 320 St. Vincent Street, Glasgow , United Kingdom, G2 5AD | Directly Connected Distribution System | 01/09/2004 |
| SPECIALITY STEEL UK LIMITED | 10491177 | 7 Fox Valley Way, Stocksbridge, Sheffield, United Kingdom, S36 2JA | Dormant CUSC Party; Non-Embedded Customer Site | 07/06/2017 |
| SPECTRUMRESERVE LTD | 10726304 | Suite 1, 7th Floor, 50 Broadway, London , United Kingdom, SW1H 0BL | Directly Connected Power Station | 20/08/2020 |
| SPEYSIDE RENEWABLE ENERGY PARTNERSHIP LIMITED | SC403396 | 13 QUEENS ROAD, ABERDEEN, London, United Kingdom, AB15 4YL | Embedded Exemptable Large Power Station | 13/06/2016 |
| SPEYSLAW SOLAR LIMITED | 09370270 | 4TH FLOOR 1 TUDOR STREET, LONDON , UNITED KINGDOM, EC4Y 0AH | Embedded Power Station | 28/11/2018 |
| SPIORAD NA MARA LIMITED | SC717716 | Regus Building, 1st Floor, 93 George Street, Edinburgh , United Kingdom, EH2 3ES | Directly Connected Power Station | 29/11/2023 |
| Spirebush Ltd | SC697238 | J R W, 19 Buccleuch Street, Hawick, Roxburgh, United Kingdom, TD9 0HL | Directly Connected Power Station | 11/11/2021 |
| SP MANWEB PLC | 02366937 | 3 PRENTON WAY, PRENTON , UNITED KINGDOM, CH43 3ET | Directly Connected Distribution System | 18/09/2001 |
| SPRINGWELL ENERGYFARM LIMITED | 13484004 | Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton le Spring, Sunderland, United Kingdom, DH4 5RA | Directly Connected Power Station | 20/04/2022 |
| SQUARE1 ENERGY LIMITED | 11042192 | 71 Graham Road, Malvern, Worcestershire, United Kingdom, WR14 2JS | Supplier | 27/02/2019 |
| SQUEAKY CLEAN ENERGY LIMITED | 09812682 | 151-153 WARDOUR STREET, LONDON , United Kingdom, W1F 8WE | Supplier | 19/08/2016 |
| SSE BATTERY MONK FRYSTON LIMITED | 13212047 | No.1 Forbury Place, 4 3 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 05/08/2021 |
| SSE COTTERED SOLAR LIMITED | 15346645 | No. 1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 22/10/2024 |
| SSE DAINES BESS LIMITED | 15344013 | No. 1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 22/10/2024 |
| SSE DE SOLAR HOLDCO LIMITED | 14189570 | No. 1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 11/04/2023 |
| SSE EGGBOROUGH LIMITED | 14939853 | No.1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 01/07/2024 |
| SSE ENERGY SUPPLY LIMITED | 03757502 | No.1 Forbury Place43 Forbury Road, Reading, BERKSHIRE, UK, RG1 3JH | Interconnector User; Supplier | 18/09/2001 |
| SSE Enterprise Energy Solutions | 08462158 | Ocean Court, Caspian Road, Atlantic Street, Altrincham , United Kingdom, WA14 5HH | Virtual Lead Party | 31/03/2021 |
| SSE ENTERPRISE LIMITED | 10060563 | No.1 Forbury Place, 4 3 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 20/12/2023 |
| SSE EWERBY SOLAR LIMITED | 14959032 | No. 1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 01/07/2024 |
| SSE FERRYBRIDGE BATTERY LIMITED | 14411214 | No. 1 Forbury Place, 43 Forbury Road, Reading, BERKSHIRE, United Kingdom, RG1 3JH | Directly Connected Power Station | 02/07/2024 |
| SSE FIDDLERS FERRY BATTERY LIMITED | 14418916 | No. 1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 01/07/2024 |
| SSE Generation Limited | 02310571 | No.1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station; Embedded Power Station | 18/09/2001 |
| SSE HYDROGEN DEVELOPMENTS LIMITED | 15238086 | No.1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Non-Embedded Customer Site | 19/08/2024 |
| SSE IMPERIAL PARK PN LIMITED | 02631510 | No. 1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 20/12/2023 |
| SSE Plc | SC117119 | Inveralmond House200 Dunkeld Road, Perth , PH1 3AQ | Directly Connected Power Station; Dormant CUSC Party | 18/09/2011 |
| SSE RENEWABLES HOLDINGS LIMITED | 314061 | Red Oak South, South County Business Park, Leopardstown, Dublin, Ireland, D18 W688 | Directly Connected Power Station | 08/07/2010 |
| SSE RENEWABLES OFFSHORE WINDFARM HOLDINGS LIMITED | SC436251 | Inveralmond House, 2 00 Dunkeld Road, Perth , United Kingdom, PH1 3AQ | Directly Connected Power Station | 25/05/2021 |
| SSE RENEWABLES SERVICES (UK) LIMITED | NI043294 | Millennium House, 2 5 Great Victoria Street, Belfast , United Kingdom, BT2 7AQ | Directly Connected Power Station; Embedded Power Station | 20/02/2006 |
| SSE RENEWABLES SOLAR & BATTERY HOLDINGS LIMITED | 13561962 | No. 1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 11/07/2023 |
| SSE RENEWABLES WIND FARMS (UK) LIMITED | SC654502 | Inveralmond House, 2 00 Dunkeld Road, Perth , United Kingdom, PH1 3AQ | Directly Connected Power Station | 02/08/2021 |
| SSE SOUTHERY SOLAR LIMITED | 14953142 | No. 1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 01/07/2024 |
| SSE STAYTHORPE POWER LIMITED | 14043534 | No.1 Forbury Place, 43 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 14/10/2022 |
| SSE THERMAL GENERATION (SCOTLAND) LIMITED | SC664055 | Inveralmond House, 2 00 Dunkeld Road, Perth , United Kingdom, PH1 3AQ | Directly Connected Power Station | 01/06/2021 |
| SSE TODDLEBURN LIMITED | SC259104 | Inveralmond House, 2 00 Dunkeld Road, Perth , United Kingdom, PH1 3AQ | Directly Connected Power Station | 28/11/2005 |
| SSE UTILITY SOLUTIONS LIMITED | 06894120 | No.1 Forbury Place, 4 3 Forbury Road, Reading , United Kingdom, RG1 3JH | Directly Connected Power Station | 28/02/2022 |
| STANDARD LIFE ASSURANCE LTD | SC286833 | Standard Life House, 30 Lothian Road, Edinburgh , United Kingdom, EH1 2DH | Non-Embedded Customer Site | 14/12/2021 |
| STARK ENERGY LIMITED | 11857289 | 306 The Plaza, 100 Old Hall Street, Liverpool , United Kindom, L3 9QJ | Directly Connected Power Station | 12/12/2022 |
| STARLIGHT ENERGY UK LIMITED | 13505799 | 5th Floor North Side, 7/10 Chandos Street, Cavendish Square, London , United Kingdom, W1G 9DQ | Directly Connected Power Station | 15/05/2023 |
| STATERA ENERGY LIMITED | 09840486 | 4th Floor 80 Victoria Streetnull, London , SW1E 5JL | Directly Connected Power Station | 11/01/2018 |
| STATKRAFT ENERGY LTD. | 06544123 | 19th Floor 22 Bishopsgatenull, London , EC2N 4BQ | Embedded Power Station | 15/12/2008 |
| STATKRAFT HIGHLANDS PSH LIMITED | SC581757 | The Garment Factory, 1 0 Montrose Street, Glasgow , United Kingdom, G1 1RE | Directly Connected Power Station | 19/01/2021 |
| STATKRAFT HYDROGEN UK HOLDING LIMITED | 14509580 | 19th Floor, 22 Bishopsgate, London , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 08/05/2024 |
| STATKRAFT IRELAND LIMITED | 487313 | Building 3400, Cork Airport Business Park, Cork , Ireland, T12AE76 | Directly Connected Power Station | 20/08/2019 |
| STATKRAFT MARKETS GMBH | HRB 37885 | Derendorfer Allee 2a, Düsseldorf, Düsseldorf, Germany, 40476 | Interconnector User; Supplier | 19/11/2003 |
| STATKRAFT UK LTD | 05742795 | 19th Floor 22 Bishopsgatenull, London , EC2N 4BQ | Directly Connected Power Station | 15/12/2009 |
| Statkraft Windco 1 Limited | 13558599 | 19th Floor 22 Bishopsgate, London , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 14/03/2023 |
| STG Switzerland GmbH | CHE-463.317.717 | Baarerstrasse 55, Zug, ZUG, Switzerland, 6300 | Interconnector User | 23/10/2023 |
| St James Group Limited | 03190056 | Berkeley House, 19 Portsmouth Road, Cobham, Surrey, UK, KT11 1JG | Directly Connected Power Station | 04/04/2025 |
| Stoke Bardolph 10 Renewables Limited | 15128170 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 22/11/2023 |
| STORNOWAY WIND FARM LIMITED | SC225262 | c/o Edf Renewables, Atria One, 144 Morrison Street, Edinburgh , United Kingdom, EH3 8EX | Embedded Power Station | 12/12/2013 |
| STORY FUTURE ENERGY LIMITED | 14086033 | Burgh Road Industrial Estate, Carlisle , United Kingdom, CA2 7NA | Directly Connected Power Station | 26/11/2024 |
| Stranoch Windfarm Limited | 02825049 | Alexander House, 1 Mandarin Road, Houghton le Spring , United Kingdom, DH4 5RA | Directly Connected Power Station | 10/07/2024 |
| Strath Tirry Wind Energy 2021 Ltd | 13659419 | Third Floor, 10 Lower Grosvenor Place, London , United Kingdom, SW1W 0EN | Embedded Power Station | 21/03/2022 |
| STRATH TIRRY WIND ENERGY LIMITED | 12534303 | Unit 3b, Damery Works, Damery Lane, Woodford, Berkeley, Gloucestershire, United Kingdom, GL13 9JR | Embedded Power Station | 23/02/2021 |
| STRATHY WIND FARM LIMITED | SC663103 | Inveralmond House, 2 00 Dunkeld Road, Perth, Perth, United Kingdom, PH1 3AQ | Directly Connected Power Station | 01/03/2021 |
| Stromar Offshore Wind Farm Limited | SC716924 | 2nd Floor, 2 Lochrin Square, 9 6 Fountainbridge, Edinburgh , United Kingdom, EH3 9QA | Directly Connected Power Station | 18/02/2025 |
| STRONELAIRG WIND FARM LIMITED | SC607491 | INVERALMOND HOUSE, PERTH, 200 Dunkeld Road, United Kingdom, PH1 3AQ | Directly Connected Power Station | 01/02/2019 |
| STROUPSTER CAITHNESS WIND FARM LIMITED | 08254673 | 5TH FLOOR, 20 FENCHURCH STREET, LONDON , United Kingdom, EC3M 3BY | Embedded Exemptable Large Power Station | 19/12/2012 |
| Sun4net Ltd | 08797521 | 51 Hollingbourne Road, London , United Kingdom, SE24 9NB | Directly Connected Power Station | 06/12/2022 |
| SUNDON BATTERY STORAGE LIMITED | 10824109 | c/o Foresight Group Llp, T he Shard, 3 2 London Bridge Street, London , United Kingdom, SE1 9SG | Directly Connected Power Station | 21/10/2019 |
| SUNDON GREEN LIMITED | 12726010 | 18 Riversway Business VillageNavigation Way, Ashton-On-Ribble, Preston, UK, PR2 2YP | Directly Connected Power Station | 25/08/2022 |
| SUNNICA LIMITED | 08826077 | 2 Crossways Business Centre, Bicester Road, Kingswood, Aylesbury, United Kingdom, HP18 0RA | Directly Connected Power Station | 13/02/2019 |
| SUNSHINE PROJECT 01 LIMITED | 13117802 | Denbridge Road, Bromley , United Kingdom, BR1 2AG | Embedded Power Station | 01/05/2024 |
| Sunshine Project 03 Limited | 13117246 | 20 Denbridge Road, Bromley , United Kingdom, BR1 2AG | Directly Connected Power Station | 03/12/2024 |
| SUSI EELPOWER DUNSINANE LIMITED | 12356110 | 124 CITY ROAD, LONDON , United Kingdom, EC1V 2NX | Embedded Exemptable Large Power Station | 24/09/2020 |
| SUSI EELPOWER FORDTOWN LIMITED | SC595142 | 6 QUEENS ROAD, ABERDEEN , United Kingdom, AB15 4ZT | Embedded Exemptable Large Power Station | 15/10/2021 |
| SUTTON BRIDGE POWER GENERATION | 02586357 | Severn Power Station, W est Nash Road, Nash, Newport, United Kingdom, NP18 2BZ | Directly Connected Power Station | 18/09/2001 |
| Swansea Grid Solutions Limited | 12371459 | 19th Floor, 22 Bishopsgate, London , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 11/10/2023 |
| SWEET BRIAR 2 ENERGY PARK LIMITED | 16218290 | 25 King Street, Bristol , United Kingdom, BS1 4PB | Directly Connected Power Station | 15/04/2025 |
| SWITCH BUSINESS GAS AND POWER LTD | 09310083 | GRANTA LODGE, MALVERN , United Kingdom, WR14 2JS | Supplier | 25/05/2016 |
| SYLVAMO UK LIMITED | SC004787 | Commerce House, S outh Street, Elgin, Moray, United Kingdom, IV30 1JE | Embedded Power Station | 15/03/2005 |
| TAGENERGY DEVELOPMENT UK LIMITED | 13370962 | Carlton House, High Street, Higham Ferrers, Northamptonshire, United Kingdom, NN10 8BW | Embedded Power Station | 06/11/2023 |
| TARCHON ENERGY LIMITED | 11040231 | Amp Technology Centre Advanced Manufacturing Park, Brunel Way, Rotherham , United Kingdom, S60 5WG | Interconnector Owner | 22/01/2019 |
| TARENNI ENERGY PARK LIMITED | 13248705 | Hodge House, Guildhall Place, Cardiff , United Kingdom, CF10 1DY | Directly Connected Power Station | 25/11/2021 |
| Tarland Limited | 11966492 | Crown House1 08 Aldersgate Street, London , United Kingdom, EC1A 4JQ | Embedded Power Station | 24/02/2021 |
| TATA STEEL UK LIMITED | 02280000 | 18 GROSVENOR PLACE, LONDON, LONDON, UNITED KINGDOM, SW1X 7HS | Non-Embedded Customer Site | 05/05/2022 |
| TBC 001 Limited | 14486279 | 4c Princes House38 Jermyn Street , SW1Y 6DN | Directly Connected Power Station | 14/12/2023 |
| TBC 002 LIMITED | 14486288 | 4c Princes House, 38 Jermyn Street, London , United Kingdom, SW1Y 6DN | Directly Connected Power Station | 25/03/2023 |
| TBC 003 LIMITED | 14486514 | 4c Princes House, 38 Jermyn Street, London , United Kingdom, SW1Y 6DN | Directly Connected Power Station | 31/07/2023 |
| TBC PARTNERS LIMITED | 14468409 | 4c Princes House, 38 Jermyn Street, London , United Kingdom, SW1Y 6DN | Directly Connected Power Station | 26/11/2023 |
| TEINDLAND WIND FARM LIMITED | SC689060 | Floor 1/1, 39 St. Vincent Place, Glasgow , United Kingdom, G1 2ER | Directly Connected Power Station | 06/04/2022 |
| TELIS ENERGY UK LIMITED | 14259671 | Suite 1, 7th Floor, 50 Broadway, London , United Kingdom, SW1H 0BL | Directly Connected Power Station | 15/05/2023 |
| Templemurry Limited | 13302073 | Biddlesgate Farm, C ranborne, Wimborne , United Kingdom, BH21 5RS | Embedded Power Station | 24/06/2022 |
| TEVIOT WF LIMITED | SC653266 | Muirhall Farm, Auchengray, Carnwath, Lanark, South Lanarkshire, United Kingdom, ML11 8LL | Directly Connected Power Station | 06/04/2021 |
| THANET OFFSHORE WIND LIMITED | 04512200 | 5th Floor, St Mary Axe, London , United Kingdom, EC3A 8BE | Embedded Power Station | 04/10/2007 |
| THE ABBEY GROUP CAMBRIDGESHIRE LIMITED | 02197844 | Nene Lodge, Funthams Lane, Whittlesey, Peterborough, Cambridgeshire, United Kingdom, PE7 2PB | Embedded Exemptable Large Power Station | 28/08/2023 |
| THE CLEAN FUTURE RENEWABLES LIMITED | 13815181 | 2 Crossways Business Centre, Bicester Road, Kingswood, Aylesbury, United Kingdom, HP18 0RA | Directly Connected Power Station | 25/08/2022 |
| The Crown State | N/A | 1 ST JAMES'S MARKET, LONDON , UNITED KINGDOM, SW1Y 4AH | Non CUSC Party | |
| THEDDLETHORPE FLEXIBLE GENERATION LIMITED | 14304859 | 4th Floor, 80 Victoria Street, London , United Kingdom, SW1E 5JL | Directly Connected Power Station | 01/02/2022 |
| THE ELECTRICITY NETWORK COMPANY LIMITED | 05581824 | Synergy House, W indmill Avenue, Woolpit, Bury St. Edmunds, United Kingdom, IP30 9UP | Independent Distribution N/W Operator | 24/05/2006 |
| THE EUROPEAN MARINE ENERGY CENTRE LIMITED | SC249331 | The Charles Clouston Building O.R.I.C., Back Road, Stromness, Orkney, United Kingdom, KW16 3AW | Embedded Power Station | 31/03/2005 |
| The Farm Energy Company Limited | 10048543 | 2 Jubilee Way, Faversham , United Kingdom, ME13 8GD | Directly Connected Power Station | 10/05/2024 |
| THORNEY LANE LLP | OC338779 | Thorney Business Park, Thorney Lane North, Iver, Buckinghamshire, United Kingdom, SL0 9HF | Non-Embedded Customer Site | 16/04/2021 |
| Thorpe Marsh Green Energy Hub Limited | 14403918 | 20 St. James’s Street, 7th Floor, London , United Kingdom, SW1A 1ES | Directly Connected Power Station | 21/08/2023 |
| THURROCK FLEXIBLE GENERATION LIMITED | 10917470 | 4th Floor 80 Victoria Street, London, LONDON, United Kingdom, SW1E 5JL | Directly Connected Power Station | 28/08/2018 |
| THURSO GRID SERVICES LIMITED | 12393509 | 1030 CENTRE PARK, SLUTCHERS LANE, WARRINGTON , UNITED KINGDOM, WA1 1QL | Non-Embedded Customer Site | 03/03/2021 |
| TIDAL LAGOON (SWANSEA BAY) PLC | 08141301 | 8TH FLOOR, ONE CENTRAL SQUARE, CARDIFF , United Kingdom, CF10 1FS | Directly Connected Power Station; Dormant CUSC Party | 03/02/2014 |
| TILBURY GREEN POWER LIMITED | 06453656 | Equitix Management Services, Unit G1 Ash Tree Court, Nottingham Business Park, Nottingham , United Kingdom, NG8 6PY | Embedded Power Station | 17/11/2022 |
| TI LIRIC Limited | 12300898 | 17th Floor, 88 Wood Street, London , United Kingdom, EC2V 7DA | Interconnector Owner | 16/12/2022 |
| TILLBRIDGE SOLAR LIMITED | 12887594 | 111 Park Street, Mayfair, London, United Kingdom, W1K 7JF | Directly Connected Power Station | 13/11/2020 |
| TINZ PROGRAMME 1 PROJECTCO 1 LIMITED | 13078692 | GABLES LODGE, LEAMINGTON SPA , United Kingdom, CV32 6JX | Non-Embedded Customer Site | 06/09/2021 |
| TINZ PROGRAMME 1 PROJECTCO 2 LIMITED | 13078723 | GABLES LODGE, LEAMINGTON SPA , United Kingdom, CV32 6JX | Directly Connected Power Station | 19/11/2021 |
| TINZ PROGRAMME 1 PROJECTCO 3 LIMITED | 13078880 | GABLES LODGE, LEAMINGTON SPA, LEAMINGTON SPA, United Kingdom, CV32 6JX | Directly Connected Power Station | 09/12/2021 |
| TINZ PROGRAMME 2 PROJECTCO 1 LIMITED | 13692059 | Gables Lodge,6 2 Kenilworth Road, Leamington Spa , United Kingdom, CV32 6JX | Non-Embedded Customer Site | 24/01/2022 |
| TINZ PROGRAMME 3 HOLDCO LIMITED | 13721318 | Gables Lodge,6 2 Kenilworth Road, Leamington Spa , United Kingdom, CV32 6JX | Directly Connected Power Station | 31/05/2022 |
| TINZ PROGRAMME 3 PROJECTCO 1 LIMITED | 13757518 | GABLES LODGE, LEAMINGTON SPA, Warwickshire, United Kingdom, CV32 6JX | Directly Connected Power Station | 26/03/2023 |
| TINZ PROGRAMME 3 PROJECTCO 4 LIMITED | 13757901 | Gables Lodge, 62 Kenilworth Road, Leamington Spa , United Kingdom, CV32 6JX | Directly Connected Power Station | 26/06/2023 |
| TI PROJECTCO 1 LIMITED | 14410303 | 17th Floor, 88 Wood Street, London , United Kingdom, EC2V 7DA | Directly Connected Power Station | 05/06/2023 |
| TI PROJECTCO 2 LIMITED | 14410318 | 17th Floor, 88 Wood Street, London , United Kingdom, EC2V 7DA | Directly Connected Power Station | 05/06/2023 |
| TI PROJECTCO 3 LIMITED | 14410404 | 17th Floor, 88 Wood Street, London , United Kingdom, EC2V 7DA | Directly Connected Power Station | 05/06/2023 |
| TOFTINGALL WIND LIMITED | 13695678 | 16 West Borough, Wimborne, Dorset, United Kingdom, BH21 1NG | Embedded Exemptable Large Power Station | 24/05/2024 |
| Tolkien Solar Farm Limited | 14347966 | Trinity House, Newby Road, Hazel Grove, Stockport, United Kingdom, SK7 5DA | Directly Connected Power Station | 03/02/2023 |
| Tollgate Energy Storage Limited | 13048014 | c/o Low Carbon Limited, Stirling Square, 5 -7 Carlton Gardens, London , United Kingdom, SW1Y 5AD | Embedded Power Station | 13/09/2022 |
| TOMATO ENERGY LIMITED | 09735768 | Devonshire Business Centre, A viary Court, W ade Road, Basingstoke , United Kingdom, RG24 8PE | Supplier | 09/08/2017 |
| TORMYWHEEL WIND FARM LIMITED | SC272942 | 2 SEMPLE STREET, EDINBURGH , United Kingdom, EH3 8BL | Embedded Exemptable Large Power Station | 24/01/2017 |
| TOTALENERGIES E&P UK LIMITED | 00811900 | 18th Floor, 10 Upper Bank Street, Canary Wharf, London, United Kingdom, E14 5BF | Non-Embedded Customer Site | 16/09/2022 |
| TOTALENERGIES GAS & POWER LIMITED | 02172239 | Bridge Gate, 55 - 57 High Street, Redhill, Surrey, United Kingdom, RH1 1RX | Supplier | 18/09/2001 |
| TOUCAN ENERGY LIMITED | 09688876 | 1 LONG LANE, LONDON , United Kingdom, SE1 4PG | Supplier | 31/08/2018 |
| Tradergy S.L. | B67694125 | Alberto Alcocer Avenue 24, 7th Floor, Madrid, Madrid, Spain, 28036 | Interconnector User | 10/12/2024 |
| TRAFIGURA DENMARK APS | 43431579 | c/o Accura Advokatpartnerselskab, A lexandriagade 8, Nordhavn, Nordhavn, Denmark, DK-2150 | Interconnector User | 15/09/2023 |
| TRAILSTONE GMBH | HB154548 | KURFUERSTENDAMM 194, BERLIN , Germany, 10707 | Interconnector User | 23/05/2014 |
| TRAILSTONE RENEWABLES GMBH | HRB 206999 | KURFUERSTENDAMM 194, BERLIN , Germany, 10707 | Interconnector User | 27/04/2020 |
| TRALORG WIND FARM LIMITED | 09916617 | 100 LIVERPOOL STREET, LONDON , United Kingdom, EC2M 2AT | Directly Connected Power Station | 25/01/2016 |
| TRANQUILITY ENERGY LIMITED | 12267627 | 2 Crossways Business Centre, Bicester Road, Kingswood, Aylesbury, United Kingdom, HP18 0RA | Directly Connected Power Station | 05/01/2022 |
| TRANSPORT FOR WALES | 09476013 | 3 LLYS CADWYN, PONTYPRIDD , United Kingdom, CF37 4TH | Non-Embedded Customer Site | 07/01/2020 |
| Trasteel Nordic ApS | DK43565729 | Beierholm, Voergårdvej 2, Aalborg, Aalborg, Denmark, 9200 | Interconnector User | 31/07/2024 |
| Trent BESS III LIMITED | 13552338 | 2 Crossways Business Centre, Bicester Road, Kingswood, Aylesbury, United Kingdom, HP18 0RA | Directly Connected Power Station | 05/04/2022 |
| Trent BESS II Limited | 14548773 | 2 Crossways Business Centre, Bicester Road, Kingswood, Aylesbury, Buckinghamshire, United Kingdom, HP18 0RA | Directly Connected Power Station | 26/11/2024 |
| Trent BESS I Limited | 15567018 | 2 Crossways Business Centre, Bicester Road, Kingswood, Aylesbury, Buckinghamshire, United Kingdom, HP18 0RA | Directly Connected Power Station | 26/11/2024 |
| TRIBUS CLEAN ENERGY LIMITED | 11494471 | 2 Crossways Business Centre, Bicester Road, Kingswood, Aylesbury, United Kingdom, HP18 0RA | Directly Connected Power Station | 15/02/2024 |
| TRIO POWER LIMITED | 15032495 | UK House, 5th Floor, 164-182 Oxford Street, London, Gloucestershire, United Kingdom, W1D 1NN | Directly Connected Power Station | 24/01/2025 |
| TRITAX ACQUISITION 52 LIMITED | 16247180 | 72 Broadwick Street, London , United Kingdom, W1F 9QZ | Non-Embedded Customer Site | 15/04/2025 |
| TRITON KNOLL OFFSHORE WIND FARM LIMITED | 03696654 | Windmill Hill Business Park, Whitehill Way, Swindon, Swindon, United Kingdom, SN5 6PB | Directly Connected Power Station | 28/07/2009 |
| TROSTON WINDFARM LIMITED | 15052348 | 1st Floor, Sackville House, 143-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 11/01/2024 |
| TRU ENERGY LIMITED | 09735909 | Gable House, 239 Regents Park Road, London , United Kingdom, N3 3LF | Supplier | 14/06/2017 |
| TULLO WIND FARM LIMITED | 04580320 | 1 PARK ROW, LEEDS , United Kingdom, LS1 5AB | Embedded Exemptable Large Power Station | 02/08/2005 |
| TULLYMURDOCH LIMITED | 08101703 | 7th Floor, Wellington House, 125-130 Strand, London , United Kingdom, WC2R 0AP | Embedded Power Station | 15/08/2014 |
| TURBINE MARKETING SPV LIMITED | 11393385 | Wader Lodge, Cusworth, Doncaster, United Kingdom, DN5 7TR | Directly Connected Power Station | 27/06/2019 |
| TWENTYSHILLING LIMITED | 07990781 | 27-28 EASTCASTLE STREET, LONDON, London, United Kingdom, W1W 8DH | Directly Connected Power Station | 30/10/2014 |
| TWINSHIELS WIND FARM LTD | SC390355 | c/o Eneco Ness House, D ochfour Business Centre, Dochgarroch, Inverness, United Kingdom, IV3 8GY | Embedded Power Station | 18/12/2015 |
| Twyn Hywel Energy Park Ltd | 12576991 | Hodge House, Guildhall Place, Cardiff , United Kingdom, CF10 1DY | Directly Connected Power Station | 24/06/2021 |
| TYLER HILL RENEWABLES LIMITED | 08731028 | Venture X, 1 Ariel Way, London , United Kingdom, W12 7SL | Directly Connected Power Station | 29/07/2024 |
| UC ENERGY LTD | 10972017 | 30 Old Bailey, London , United Kingdom, EC4M 7AU | Supplier | 26/07/2024 |
| UISENIS POWER LIMITED | SC389045 | c/o Anderson Strathern, 58 Morrison Street, Edinburgh , United Kingdom, EH3 8BP | Directly Connected Power Station | 18/04/2012 |
| UKAEA LTD | 14458243 | Culham Science Centre, Abingdon, Oxfordshire, United Kingdom, OX14 3DB | Non CUSC Party; Non-Embedded Customer Site | 01/02/2004 |
| UK ATOMIC ENERGY AUTHORITY | N/A | CULHAM CAMPUS, ABINGDON, OXFORDSHIRE, UNITED KINGDOM, OX14 3DB | Non CUSC Party | |
| UK MAINSTREAM RENEWABLE POWER LIMITED | 06538309 | 10 ORANGE STREET, HAYMARKET, LONDON, UNITED KINGDOM, WC2H 7DQ | Directly Connected Power Station | 28/01/2021 |
| UK POWER DISTRIBUTION LIMITED | 06339585 | Eleanor House Queenswood Office Park, Newport Pagnell Road, Northampton, Northamptonshire, United Kingdom, NN4 7JJ | Directly Connected Distribution System | 07/02/2022 |
| UK POWER NETWORKS (IDNO) LIMITED | 06489447 | Newington House, 2 37 Southwark Bridge Road, London , United Kingdom, SE1 6NP | Independent Distribution N/W Operator | 28/07/2009 |
| UK POWER NETWORKS SERVICES (CONTRACTING) LIMITED | 02228168 | Newington House, 2 37 Southwark Bridge Road, London , United Kingdom, SE1 6NP | Non-Embedded Customer Site | 18/09/2001 |
| UK POWER RESERVE LIMITED | 07385282 | 6th Floor, Radcliffe House, Blenheim Court, Solihull , United Kingdom, B91 2AA | Embedded Power Station; Supplier | 10/06/2016 |
| UK RENFREWSHIRE 1 LTD | 14225523 | Lilly House, 1 3 Hanover Square, London , United Kingdom, W1S 1HN | Directly Connected Power Station | 08/11/2023 |
| UK UTILITY RESERVE LIMITED | 11008814 | 6th Floor, Radcliffe House, Blenheim Court, Solihull , United Kingdom, B91 2AA | Embedded Power Station | |
| ULZIESIDE WIND ENERGY LIMITED | SC386880 | Caledonian Exchange, 19a Canning Street, Edinburgh , United Kingdom, EH3 8HE | Directly Connected Power Station; Dormant CUSC Party | 28/04/2014 |
| UNIFY ENERGY LIMITED | 09523118 | UNION ALBERT SQUARE, MANCHESTER , United Kingdom, M2 6LW | Supplier | 30/09/2016 |
| Union Fenosa Generacion SA | Registro Mercantil | Avenida San Luis, 77, Madrid, MADRID, Spain, 28033 | Interconnector User | 11/11/2002 |
| UNIPER GLOBAL COMMODITIES SE | HRB 61123 | HOLZSTR. 6, DUESSELDORF , Germany, 40221 | Interconnector User | 24/07/2008 |
| UNIPER HYDROGEN UK LIMITED | 09513014 | Compton House, 2 300 The Crescent, B irmingham Business Park, Birmingham , United Kingdom, B37 7YE | Directly Connected Power Station | 28/01/2025 |
| UNIPER UK LIMITED | 02796628 | Compton House 2300 The CrescentB irmingham Business Park, Birmingham, West Midlands, UK, B37 7YE | Directly Connected Power Station | 13/08/2015 |
| UNITED GAS & POWER TRADING LTD | 09995683 | 16 Otley Road, Guiseley, Leeds, United Kingdom, LS20 8AH | Supplier | 15/01/2018 |
| UPM-KYMMENE (UK) LIMITED | SC102969 | 1 Meadowhead Road, Irvine, Ayrshire, United Kingdom, KA11 5AT | Non-Embedded Customer Site | 15/03/2005 |
| URUK BESS LIMITED | 14578390 | 30 Queen Square, Penthouse Office, Bristol, Somerset, United Kingdom, BS1 4ND | Embedded Power Station | 21/03/2025 |
| USKMOUTH ENERGY STORAGE LIMITED | 13989624 | 128 CITY ROAD, LONDON , UNITED KINGDOM, EC1V 2NX | Directly Connected Power Station | 02/08/2022 |
| UTILITA ENERGY LIMITED | 04849181 | Hutwood Court Bournemouth Road, Chandler's Ford, Eastleigh, Hampshire, United Kingdom, SO53 3QB | Supplier | 19/12/2003 |
| VALDA ENERGY LIMITED | 11212563 | Unit 11, Talisman Business Centre, T alisman Road, Bicester , United Kingdom, OX26 6HR | Supplier | 10/07/2019 |
| VANTAGE DATA CENTERS UK LIMITED | 06132144 | 2 Old Bath Road, Newbury, Berkshire, United Kingdom, RG14 1QL | Non-Embedded Customer Site | 18/01/2022 |
| VANTAGE DATA CENTERS UNITED KINGDOM (OPCO) LIMITED | 14236061 | 1 Bartholomew Lane, London , United Kingdom, EC2N 2AX | Non-Embedded Customer Site | 27/10/2023 |
| VATTENFALL AB | 556036-2138 | EVENEMANGSGATAN 13, SOLNA, SOLNA, SWEDEN, 169 79 | Interconnector User | 29/08/2003 |
| VATTENFALL ENERGY TRADING GMBH | HRB 80335 | DAMMTORSTR. 29 - 32, HAMBURG, HAMBURG, Germany, 20354 | Interconnector User; Supplier | 13/03/2008 |
| VATTENFALL ENERGY TRADING NETHERLANDS N.V. | 9096519 | Hoekenrode 8, Amsterdam , Netherlands, 1102 BR | Interconnector User | |
| VATTENFALL NETWORKS LTD | 02731769 | 5th Floor 70St Mary Axe, London , EC3A 8BE | Independent Distribution N/W Operator | 05/04/2018 |
| VATTENFALL WIND POWER LTD | 06205750 | 5th Floor 70 St Mary Axe, London, LONDON, UK, EC3A 8BE | Directly Connected Power Station; Embedded Power Station | 11/08/2008 |
| VDC CWL SERVICES LIMITED | OE032481 | 44 Esplanade, Saint Helier , Jersey, JE4 9WU | Non-Embedded Customer Site | 09/09/2024 |
| VDC UK MANAGEMENT COMPANY LIMITED | 12361880 | 1 Bartholomew Lane, London , United Kingdom, EC2N 2AX | Non-Embedded Customer Site | 26/08/2020 |
| VIKING ENERGY WIND FARM LLP | SO305400 | Inveralmond House, 2 00 Dunkeld Road, Perth, Perth, United Kingdom, PH1 3AQ | Directly Connected Power Station | 06/02/2020 |
| VIRIDIS 178 LIMITED | 09464998 | 110 CANNON STREET, LONDON , United Kingdom, EC4N 6EU | Embedded Power Station | 11/08/2015 |
| VIRIDISIA LTD | 15594522 | 2 Upperton Gardens, Eastbourne , United Kingdom, BN21 2AH | Directly Connected Power Station | 20/02/2025 |
| VIRIDOR ENVIROSCOT LIMITED | SC182926 | c/o Shepherd & Wedderburn Llp, 9 Haymarket Square, Edinburgh , United Kingdom, EH3 8FY | Embedded Exemptable Large Power Station | 15/12/2015 |
| Virmati Energy Ltd | 13095982 | Montacute Yards183 Shoreditch High Street, London, LONDON, UK, E1 6HU | Directly Connected Power Station | 17/03/2023 |
| Virtus Data Centres Limited | 06762600 | 4th Floor,2 0 Balderton Street, London , United Kingdom, W1K 6TL | Non-Embedded Customer Site | 26/04/2022 |
| Virtus Holdco Limited | 07670473 | 4th Floor,2 0 Balderton Street, London , United Kingdom, W1K 6TL | Non-Embedded Customer Site | 07/07/2022 |
| Virtus Saunderton | 13618549 | 64 New Cavendish Street, London , United Kingdom, W1G 8TB | Directly Connected Power Station | 28/09/2022 |
| Vital Energi Solutions Limited | 07828647 | Century House, R oman Road, Blackburn, Lancashire, United Kingdom, BB1 2LD | Embedded Power Station | 02/10/2023 |
| Vitol S.A | CHE-107.746.845 | Pl. des Bergues 3, 1201 Geneva PO Box 2056, 1211 Geneva 1, Geneva, Geneva, Switzerland, 1211 | Interconnector User | 22/02/2008 |
| VOLTA ENERGY DESIGNATED ACTIVITY COMPANY | 746154 | CUSTOM HOUSE PLAZA BLOCK 6, INTERNATIONAL FINANCIAL SERVICES CENTRE, DUBLIN, DUBLIN, IRELAND, D01 X9Y5 | Interconnector User | 13/02/2024 |
| VOLTALIA UK LTD | 07489990 | The Wheelhouse, Bond's Mill Estate, Stonehouse, Gloucestershire, United Kingdom, GL10 3RF | Embedded Exemptable Large Power Station | 26/01/2023 |
| VOLTIS PEOPLE LIMITED | 13774196 | 315, 37 Cremer Street, London , United Kingdom, E2 8HD | Embedded Power Station | 17/04/2023 |
| VOLTWISE POWER HOLDINGS LIMITED | 14687074 | 125 Old Broad Street, London , United Kingdom, EC2N 1AR | Embedded Power Station | 12/08/2024 |
| VOLUE MARKET SERVICES AS | 863 769 132 | LANGBRYGGEN 9, ARENDAL , NORWAY, 4841 | Interconnector User | 14/01/2011 |
| Vox Charlie Ltd | 13099852 | 30 Orange Street, London , United Kingdom, WC2H 7HH | Embedded Power Station | 25/05/2023 |
| VPI IMMINGHAM B LIMITED | 10630563 | 4th Floor, Nova South, 160 Victoria Street, London , United Kingdom, SW1E 5LB | Directly Connected Power Station | 08/09/2020 |
| VPI IMMINGHAM LLP | OC300980 | 4th Floor, Nova South, 160 Victoria Street, London , United Kingdom, SW1E 5LB | Directly Connected Power Station | 18/09/2001 |
| VPI POWER LIMITED | SC189124 | Building 1, 9 Haymarket Square, Edinburgh , United Kingdom, EH3 8RY | Directly Connected Power Station | 18/09/2001 |
| W4B RENEWABLE ENERGY LIMITED | 06479668 | Gables Lodge, 62 Kenilworth Road, Leamington Spa , United Kingdom, CV32 6JX | Embedded Power Station | 28/02/2023 |
| WALNEY (UK) OFFSHORE WINDFARMS LIMITED | 05246622 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 14/03/2006 |
| WALNEY EXTENSION LIMITED | 07306956 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 22/09/2011 |
| WALPOLE GREEN LIMITED | 12517507 | 18 Riversway Business Village, Navigation Way, Ashton-On-Ribble, Preston, United Kingdom, PR2 2YP | Directly Connected Power Station | 24/07/2020 |
| Walsoken Limited | 13748823 | Crown House, 1 08 Aldersgate Street, London , United Kingdom, EC1A 4JQ | Embedded Power Station | 20/11/2023 |
| Waltham Cross 2 Renewables Limited | 14914290 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 12/12/2023 |
| Waltham Cross 7 Renewables Limited | 14914262 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 12/12/2023 |
| WARLEY BATTERY STORAGE | 10824037 | 8 DEVONSHIRE SQUARE, LONDON , United Kingdom, EC2M 4PL | Directly Connected Power Station | 08/02/2023 |
| WARLEY GREEN LIMITED | 12725706 | 18 Riversway Business Village, Navigation Way, Ashton-On-Ribble, Preston, United Kingdom, PR2 2YP | Directly Connected Power Station | 01/08/2022 |
| WATHEGAR 2 LIMITED | 10276414 | 5 NEW STREET SQUARE, LONDON , United Kingdom, EC4A 3TW | Directly Connected Power Station | 02/05/2017 |
| Waun Hesgog Energy Park Limited | 13152996 | The Broadgate Tower Third Floor, 2 0 Primrose Street, London , United Kingdom, EC2A 2RS | Embedded Power Station | 03/09/2021 |
| WEAVER POWER LIMITED | SC233043 | 13 Queen's Road, Aberdeen , United Kingdom, AB15 4YL | Non-Embedded Customer Site | 24/02/2021 |
| WELBAR ENERGY STORAGE LIMITED | 10326869 | HARTHAM PARK HARTHAM PARK, CORSHAM , United Kingdom, SN13 0RP | Directly Connected Power Station | 10/11/2021 |
| Welsh Government | N/A | CROWN BUILDING, CARDIFF , UNITED KINGDOM, CF10 3NQ | Non-Embedded Customer Site | 22/05/2022 |
| WELSH POWER GROUP LIMITED | 5766467 | FOURTH FLOOR 2 KINGSWAY, CARDIFF , United Kingdom, CF10 3FD | Virtual Lead Party | 18/01/2022 |
| WEST ANDERSHAW WIND FARM LIMITED | 13212185 | 19th Floor, 22 Bishopsgate, London , United Kingdom, EC2N 4BQ | Directly Connected Power Station | 05/12/2023 |
| WEST BURTON B LIMITED | 13027787 | West Burton B CCGT, S turton Road, Retford, Nottinghamshire, United Kingdom, DN22 9BL | Directly Connected Power Station | 17/05/2021 |
| WEST BURTON SOLAR PROJECT LIMITED | 13049324 | Unit 25.7 Coda Studios, 189 Munster Road, London , United Kingdom, SW6 6AW | Directly Connected Power Station | 20/01/2022 |
| WESTERMOST ROUGH LIMITED | 06232914 | 5 HOWICK PLACE, LONDON , United Kingdom, SW1P 1WG | Directly Connected Power Station | 27/01/2009 |
| WESTFIELD ENERGY RECOVERY LIMITED | SC579887 | c/o Equitix Management Services Limited, S uite 1l-10, Avondale House, S trathclyde Business Park, Bellshill , United Kingdom, ML4 3NJ | Dormant CUSC Party; Embedded Power Station | 31/01/2019 |
| West Haddon 10 Renewables Limited | 15123046 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 22/11/2023 |
| West Weybridge 10 Renewables Limited | 15122977 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 22/11/2023 |
| WHIRLWIND ENERGY STORAGE LIMITED | 12314124 | 1st Floor Midland House, 77 Huddersfield Road, Mirfield, West Yorkshire, United Kingdom, WF14 8BL | Embedded Exemptable Large Power Station | 14/06/2023 |
| Whitehill Battery Storage Ltd | SC696005 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Directly Connected Power Station | 07/09/2022 |
| WHITELAW BRAE WINDFARM LIMITED | SC456527 | Ground Floor, West Suite, Prospect House,5 Thistle Street,, Edinburgh , United Kingdom, EH2 1DF | Directly Connected Power Station | 03/06/2015 |
| WHITESIDE HILL WINDFARM (SCOTLAND) LIMITED | SC312729 | 13 QUEENS ROAD, ABERDEEN , United Kingdom, AB15 4YL | Directly Connected Power Station | 29/04/2015 |
| WHITETOWER ENERGY LIMITED | 03479694 | First Floor Templeback, 10 Temple Back, Bristol, BRISTOL, United Kingdom, BS1 6FL | Embedded Power Station | 02/07/2019 |
| WILLINGTON ENERGY PARK LIMITED | 14376802 | 1st Floor Sackville House 1 43-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 20/02/2025 |
| WILLINGTON GREEN ENERGY LIMITED | 13539334 | The Goods Shed, Jubilee Way, Faversham, Kent, United Kingdom, ME13 8GD | Directly Connected Power Station | 08/04/2022 |
| WILSON RENEWABLES III LLP | SO307605 | Carbiestone House, Ayr, Ayrshire, United Kingdom, KA6 5JU | Directly Connected Power Station | 13/03/2023 |
| WILSON RENEWABLES IV LLP | SO307604 | Carbieston House, Ayr, Ayrshire, United Kingdom, KA6 5JU | Directly Connected Power Station | 23/03/2023 |
| WILTON ENERGY LIMITED | 04557531 | Sembcorp UK Headquarters, Wilton International, Middlesbrough, Cleveland, United Kingdom, TS90 8WS | Directly Connected Power Station; Supplier | 20/03/2003 |
| WIND 2 LIMITED | 10276420 | LINDEN HOUSE WREXHAM ROAD, MOLD , United Kingdom, CH7 1XP | Directly Connected Power Station | 23/08/2021 |
| Wind 2 Project 2 Limited | 13697273 | Linden House, M old Business Park, W rexham Road, Mold , United Kingdom, CH7 1XP | Directly Connected Power Station | 20/06/2023 |
| Wind 2 Project 3 Limited | 13740904 | Linden House, W rexham Road, M old Business Park, Mold , United Kingdom, CH7 1XP | Directly Connected Power Station | 16/04/2025 |
| Wind 2 Project 6 Limited | SC714904 | Wind 2 Office 2 Walker Street, Edinburgh , United Kingdom, EH3 7LA | Directly Connected Power Station | 22/05/2024 |
| WIND DEVELOPMENT HOLDINGS LIMITED | 12902171 | LEVEL 25, ONE CANADA SQUARE, LONDON , UNITED KINGDOM, E14 5AA | Directly Connected Power Station | 08/06/2021 |
| WINDEL GRID 1 LIMITED | 13438781 | S10 Blyth Workspace Commissioners Quay, Quay Road, Blyth , United Kingdom, NE24 3AF | Directly Connected Power Station | 13/11/2023 |
| Wind Harvest Limited | SC370464 | Corrary Farm, Glenelg, Kyle , United Kingdom, IV40 8JX | Embedded Exemptable Large Power Station | 11/06/2021 |
| WINDY RIG WIND FARM LIMITED | 09802052 | 27-28 EASTCASTLE STREET, LONDON, London, United Kingdom, W1W 8DH | Directly Connected Power Station | 06/08/2019 |
| Windy Standard III Ltd | SC295868 | c/o Harper Macleod Llp, The Cadoro, 45 Gordon Street, Glasgow , United Kingdom, G1 3PE | Directly Connected Power Station | 16/02/2016 |
| WKN SALLACHY LIMITED | SC384979 | 12-16 HOPE STREET, EDINBURGH , United Kingdom, EH2 4DB | Directly Connected Power Station | 09/08/2011 |
| Woodcock Faulds Battery Storage Limited | SC752620 | 33 Bothwell Road, Hamilton , United Kingdom, ML3 0AS | Directly Connected Power Station | 14/05/2024 |
| Worcestershire Solar 1 Limited | 12335286 | 5 New Street Square, London , United Kingdom, EC4A 3TW | Directly Connected Power Station | 09/11/2022 |
| WP GRID SERVICES 13 LIMITED | 13394560 | Fourth Floor, 2 Kingsway, Cardiff , United Kingdom, CF10 3FD | Directly Connected Power Station | 12/12/2023 |
| WP GRID SERVICES 14 LIMITED | 13394871 | Fourth Floor, 2 Kingsway, Cardiff , United Kingdom, CF10 3FD | Directly Connected Power Station | 31/03/2025 |
| WP Grid Services 16 Limited | 13396670 | Fourth Floor, 2 Kingsway,, Cardiff , United Kingdom, CF10 3FD | Directly Connected Power Station | 20/02/2024 |
| WP Grid Storage 3 Limited | 14049799 | Fourth Floor, 2 Kingsway, Cardiff , United Kingdom, CF10 3FD | Directly Connected Power Station | 08/12/2023 |
| WP Voltage Services 1 Limited | 13394399 | Fourth Floor, 2 Kingsway, Cardiff , United Kingdom, CF10 3FD | Non-Embedded Customer Site | 15/04/2025 |
| WP VOLTAGE SERVICES 4 LIMITED | 13394737 | FOURTH FLOOR, 2 KINGSWAY, CARDIFF , UNITED KINGDOM, CF10 3FD | Non-Embedded Customer Site | 21/01/2022 |
| WYLFA GREEN LIMITED | 12726341 | 17th Floor Hylo, 103-105 Bunhill Row, London , United Kingdom, EC1Y 8LZ | Directly Connected Power Station | 01/07/2024 |
| Wymondley 10 Renewables Ltd | 14605051 | Century House, 1 The Lakes, Northampton , United Kingdom, NN4 7HD | Directly Connected Power Station | 30/11/2023 |
| WYMONDLEY GREEN ENERGY CENTRE LTD | 14438314 | 81 Blake Tower, 2 Fann Street, London , United Kingdom, EC2Y 8AF | Directly Connected Power Station | 04/12/2024 |
| WYSEBYHILL ENERGY FARM LIMITED | 12013703 | Trinity House, Newby Road, Hazel Grove, Stockport, United Kingdom, SK7 5DA | Directly Connected Power Station | 20/12/2022 |
| XENON CAPITAL MARKETS LIMITED | 11033458 | 1 Canada Square 37th Floor, Canary Wharf, London, United Kingdom, E14 5AA | Interconnector User | 30/04/2019 |
| XLCC Limited | 13057883 | Kingfisher House, R adford Way, Billericay, Essex, United Kingdom, CM12 0EQ | Non-Embedded Customer Site | 14/06/2023 |
| XLINKS 1 LTD | 13481017 | Kingfisher House, W oodbrook Crescent, Billericay, Essex, United Kingdom, CM12 0EQ | Directly Connected Power Station | 08/09/2023 |
| XLINKS LIMITED | 11891505 | Kingfisher House, R adford Way, Billericay, Essex, United Kingdom, CM12 0EQ | Directly Connected Power Station | 14/12/2020 |
| Xrenewable Ltd | 11955142 | 20-22 Wenlock Road, London , United Kingdom, N1 7GU | Embedded Exemptable Large Power Station | 13/09/2022 |
| YAXLEY ENERGY LIMITED | 15010102 | Lilly House, 13 Hanover Square,, London , United Kingdom, W1S 1HN | Directly Connected Power Station | 07/10/2024 |
| YAXLEY GREEN ENERGY CENTRE LTD | 14437282 | Flat 81 Blake Tower, 2 Fann Street,, London , United Kingdom, EC2Y 8AF | Directly Connected Power Station | 12/12/2024 |
| Y BRYN WIND FARM LIMITED | 12194519 | 22-24 King Street, Maidenhead, Berkshire, United Kingdom, SL6 1EF | Directly Connected Power Station | 20/09/2022 |
| YORK ENERGY PARK LIMITED | 14444117 | 1st Floor, Sackville House, 143-149 Fenchurch Street, London , United Kingdom, EC3M 6BL | Directly Connected Power Station | 30/05/2023 |
| YU ENERGY RETAIL LIMITED | 08246810 | Cpk House, 2 Horizon Place, N ottingham Business Park, Mellors Way, Nottingham , United Kingdom, NG8 6PY | Supplier | 08/01/2016 |
| ZENOBE BLACKHILLOCK LIMITED | 12246552 | Burdett House15-16 Buckingham Street, London, LONDON, UK, WC2N 6DU | Directly Connected Power Station | 06/08/2021 |
| ZENOBE CAPENHURST LIMITED | 12246481 | 4TH FLOOR 13 CHARLES II STREET, LONDON , United Kingdom, SW1Y 4QU | Directly Connected Power Station | 28/04/2021 |
| Zenobe Coalburn Limited | 13413000 | Burdett House, 1 5-16 Buckingham Street, London , United Kingdom, WC2N 6DU | Directly Connected Power Station | 04/10/2023 |
| Zenobe Eccles Limited | 12249742 | Burdett House, 1 5-16 Buckingham Street, London , United Kingdom, WC2N 6DU | Directly Connected Power Station | 30/01/2025 |
| Zenobe Energy Limited | 10436249 | Burdett House, 1 5-16 Buckingham Street, London, London, United Kingdom, WC2N 6DU | Directly Connected Power Station | 11/09/2020 |
| ZENOBE STALYBRIDGE LIMITED | 14299411 | Burdett House, 15-16 Buckingham Street, London , United Kingdom, WC2N 6DU | Directly Connected Power Station | 16/09/2022 |
| ZENOBE WISHAW LIMITED | 10726477 | Burdett House, 1 5-16 Buckingham Street,, London , United Kingdom, WC2N 6DU | Directly Connected Power Station | 01/04/2021 |
| ZURICH ASSURANCE LTD | 02456671 | Unity Place, 1 Carfax Close, Swindon, Wiltshire, United Kingdom, SN1 1AP | Non-Embedded Customer Site | 17/03/2021 |
Schedule 2 Exhibit 1
1. The Company registered in England with number 11014226 (“The Company”,, which expression shall include its successors and/or permitted assigns); and
2. [] a company registered in [] with number [] whose registered office is at [] (“User”, which expression shall include its successors and/or permitted assigns) WHEREAS
Pursuant to the ESO Licence, The Company is required to prepare a Connection and Use of System Code (CUSC) setting out the terms of the arrangements for connection to and use of the National Electricity Transmission System and the provision of certain Balancing Services.
The User has applied for [Connection to] [and use of] [Modification of its existing Connection to [and use of]] the National Electricity Transmission System and pursuant to the ESO Licence The Company is required to offer terms in this respect.
The User has applied for connection [and use] in the capacity of a [ ] as set out in Paragraph 1.2.4 of the CUSC.
The Company and the User are parties to the CUSC Framework Agreement (being an agreement by which the CUSC is made contractually binding between CUSC Parties).
This Bilateral Connection Agreement is entered into pursuant to the CUSC and shall be read as being governed by it. [(F) The parties are also on even date herewith entering into a Construction Agreement.] [(G) This Bilateral Connection Agreement is entered into on the basis of the Connect and Manage Arrangements. [Directly Connected power Station and Distribution System where associated with Connect and Manage Power Station.] ] [(H) This is a [Gate 1 Agreement][Gate 2 Agreement].] NOW IT IS HEREBY AGREED as follows:
DEFINITIONS, INTERPRETATION AND CONSTRUCTION Unless the subject matter or context otherwise requires or is inconsistent therewith, terms and expressions defined in Section 11 of the CUSC [and the Construction Agreement] have the same meanings, interpretations or constructions in this Bilateral Connection Agreement [and the following terms and expressions shall have the meaning set out below:- “Construction Agreement" the agreement made between the parties of even date herewith for the carrying out of construction works; "Charging Date" as defined in the Construction Agreement; [“Circuit [ ]” [insert detailed description of circuit(s) affected by the Design Variation] (power station with Design Variation and/or Offshore Standard Design and\or Non Standard Boundary only);] [“ET Conditions” any reduction in the Maximum Export Capacity and/or Maximum Import Capacity or disconnection or deenergisation of the Offshore Transmission System at the ET Interface Point;] (power station connected via ET Offshore Transmission System only)] [“ET Condition Period” the period of time during which the ET Conditions apply;] (power station connected via ET Offshore Transmission System only) [“ET Interface Point” means [insert details];] (power station connected via ET Offshore Transmission System only) “GIS Assets” the assets between the electrical boundary and the point within the Gas Insulated Switchgear where the busbar connects to the Transmission circuit which connects the User to the National Electricity Transmission System; [where the boundary is in accordance with CUSC Paragraph 2.12.1(f) (i) only] “GIS Asset Outage” the unavailability of the GIS Assets as a result of:
a planned or unplanned incident occurring directly on the GIS Assets or
the GIS Assets requiring to be Deenergised for health and safety reasons to allow for the planned or unplanned availability of a circuit in the immediate vicinity of the GIS Assets; [where the boundary is in accordance with CUSC Paragraph 2.12.1(f) (i) only] “GIS Asset Outage Period” the period of time during which the GIS Asset Outage applies; [where the boundary is in accordance with CUSC Paragraph 2.12.1(f) (i) only] [“Maximum Export Capacity” the figure specified as such in Appendix C Part 4;] (power station connected via ET Offshore Transmission System only); [“Maximum Import Capacity” the figure specified as such in Appendix C Part 4;] (power station connected via ET Offshore Transmission System only) [“Outage Conditions [ ]” the unavailability of Circuit [ ] as a result of
a [planned]/[unplanned]/[planned or unplanned] incident occurring directly on Circuit [ ]; or
Circuit [ ] requiring to be Deenergised for health and safety reasons to allow for the planned or unplanned availability of a circuit in the immediate vicinity of Circuit [ ]; (power station with Design Variation and\or Offshore Standard Design and\or Non Standard Boundary only)] [“Outage Period” the period of time during which the Outage Conditions and/or reduced circuit capability apply; (power station with Design Variation and\or Offshore Standard Design and\or Non Standard Boundary only)] [“Notification of Circuit Restrictions” means the notification issued by The Company to the User in accordance with Clause [10.8] of this Bilateral Connection Agreement; (power station with Design Variation and\or Offshore Standard Design and\or Non Standard Boundary only)] “Notification of GIS Asset Outage” means the notification issued by The Company to the User in accordance with Clause [14.2] of this Bilateral Connection Agreement; [where the boundary is in accordance with CUSC Paragraph 2.12.1(f) (i) only] [“Notification of Outage Conditions” means the notification issued by The Company to the User in accordance with Clause [10.4] of this Bilateral Connection Agreement; (power station with Design Variation and\or Offshore Standard Design and\or Non Standard Boundary only)] [“Notification of Restrictions on Availability” means a Notification of Outage Conditions and\or a Notification of Circuit Restrictions as applicable; (power station with Design Variation and\or Offshore Standard Design and\or Non Standard Boundary only)] [“Notification of ET Restrictions on Availability” means the notification issued by The Company to the User in accordance with Clause [10.11] of this Bilateral Connection Agreement advising of the ET Conditions;] (power station via an ET Offshore Transmission System only) [“Relevant Circuits” means [Circuit [ ]]; (power station with Design Variation and\or Offshore Standard Design and\or Non Standard Boundary only)] [“Transmission Related Agreement” means the agreement of even date entered into between the parties for the provision of and payment for Balancing Services in respect of Bid-Offer Acceptances; (power station with Design Variation and\or Offshore Standard Design and\or Non Standard Boundary and\or via an ET Offshore Transmission System only)] [1.2 Gate 1 Conditional Clause [and Reservation] – Gate 1 Agreements only
As provided for at Clause 1.2 of the Construction Agreement and this Clause 1.2 the parties agree that until the [Gate 2 Date] the rights and obligations of each party pursuant to this Bilateral Connection Agreement other than this Clause 1.2 shall be suspended.
[The parties further agree and acknowledge that the information provided for the purposes of the Gate 1 Agreement and set out in the Appendix [O][P] to the Construction Agreement is indicative only prior to the [Gate 2 Date] and shall not be binding on the parties or confer any commitment to these by The Company and any reliance on them for any purpose prior to the Gate 2 Date is at the User’s risk – no Reservation.] [The parties further agree that the Connection Site and Completion Date and Transmission Entry Capacity [add other capacity refs reflecting import and export] for Interconnector/MPI as set out in Appendix [O][P] to the Construction Agreement have been Reserved for the purposes of this connection and/or use of system and any Gate 2 Offer will reflect this provided that the Gate 2 Application is made prior to the Reservation Expiry Date and the Gate 2 Offer is accepted – where Reservation].
With effect from the [Gate 2 Date] the provisions of this Bilateral Connection Agreement, as amended by the [Gate 2 Offer] by agreement of the parties shall be in full force and effect.]
2 COMMENCEMENT This Bilateral Connection Agreement shall commence on [].
3 THE CONNECTION SITE AND TRANSMISSION CONNECTION ASSETS The Connection Site and Transmission Connection Assets to which this Bilateral Connection Agreement relates is more particularly described in Appendix A.
4 CONNECTION CHARGES The Connection Charges payable by the User in accordance with the CUSC in respect of the Transmission Connection Assets set out in Appendix A [(including the One-Off Charge)] are set out in Appendix B. These Connection Charges shall be payable by the User from the [CUSC Implementation Date] [or] [Charging Date].
5 [USE OF SYSTEM (power station only) The right to use the National Electricity Transmission System shall commence on and Use of System Charges shall be payable by the User from the [CUSC Implementation Date] [or] [Charging Date].]
6 CREDIT REQUIREMENTS The amount to be secured by the User from [date] is set out in the Secured Amount Statement issued from time to time and as varied from time to time in accordance with Section 2 of the CUSC.
7 CONNECTION ENTRY CAPACITY AND TRANSMISSION ENTRY CAPACITY
The Connection Entry Capacity in relation to the Generating Units and the Connection Site and the Transmission Entry Capacity in relation to the Connection Site, are specified in Appendix C.
Appendix C Part 3 will set out the BM Unit Identifiers of the BM Units registered at the Connection Site under the Balancing and Settlement Code. The User will provide The Company with the information needed to complete details of these BM Unit Identifiers as soon as practicable after the date hereof and thereafter in association with any request to modify the Transmission Entry Capacity and The Company shall prepare and issue a revised Appendix C incorporating this information. The User shall notify The Company prior to any alteration in the BM Unit Identifiers and The Company shall prepared and issue a revised Appendix C incorporating this information.
The Company shall monitor the Users compliance with its obligation relating to Transmission Entry Capacity against the sum of metered volumes of the BM Units set out in Part 3 of Appendix C submitted by the User for each Settlement Period.
8 COMPLIANCE WITH SITE SPECIFIC TECHNICAL CONDITIONS The site specific technical conditions applying to the Connection Site are set out in Appendices F1 to F5 to this Bilateral Connection Agreement as modified from time to time in accordance with Paragraph 6.9 of the CUSC.
9 [ELECTRICAL BOUNDARY (Non Standard Boundary only) The division of ownership of Plant and Apparatus at the Connection Site shall be at [define ownership boundary]. For the avoidance of doubt, nothing in this Clause 9 shall effect any transfer of ownership in any Plant or Apparatus.]
10 [RESTRICTIONS ON AVAILABILITY (power station with Design Variation and\or Offshore Standard Design and\or Non Standard Boundary only) [AND ET RESTRICTIONS ON AVAILABILITY - ET Offshore Transmission System only]
[The division of ownership of Plant and Apparatus in Clause 9 above is contrary to the principles of ownership set out in CUSC Paragraph 2.12.]
[In addition the] [The] User acknowledges that the connection design which provides for connection to the National Electricity Transmission System is [a variation to the connection design as provided for in Chapter 2 or Chapter 4 (as appropriate) of the NETS SQSS] [of an Offshore Standard Design – User connected at Offshore Transmission System only [and the User further acknowledges that the User is connected at an ET Offshore Transmission System and that as such its rights under CUSC Paragraph 2.3 (Export of Power from Connection Site) and Paragraph 2.4 (Import of Power to Connection Site) are subject to the availability of the Maximum Export Capacity and Maximum Import Capacity and to the ET Offshore Transmission System not being disconnected from or deenergised at the ET Interface Point- ET Offshore Transmission System only] and the following provisions shall apply. [10.3 It is a condition of the NETS SQSS that any Design Variation satisfies the criteria set out inparagraphs 2.15 to 2.18 (inclusive) for an Onshore Connection or 7.21 to 7.24 (inclusive) for an Offshore Connection of the NETS SQSS and on that basis [and in light of the non standard principles of ownership] the following provisions will apply. power station with Design Variation and\or Non Standard Boundary only ]
The Company shall issue to the User a notice that advises the User of the occurrence of the Outage Conditions and where practicable the expected Outage Period. Such notice shall be issued:
In the event that the Notification of Circuit Outage relates to a Planned Outage on the National Electricity Transmission System, where practicable, be in accordance with Grid Code OC2 requirements; or 10.4.2 In the event that the Notification of Circuit Outage relates to something other than a Planned Outage on the National Electricity Transmission System or relates to a Planned Outage on the National Electricity Transmission System but it is not practicable for such notice to be in accordance with Grid Code OC2 requirements, as soon as reasonably practicable and The Company and the User shall agree as soon as practicable after the date hereof the method of such notification.
The Company shall promptly notify the User when the Outage Period will or has ceased.
The Company shall be entitled to revise the Notification of Circuit Outage given under Clause 10.4 above at any time.
The User will acknowledge receipt of such Notification of Circuit Outage and where practicable shall revise its Output Useable forecast for the affected BM Unit accordingly.
Following such Notification of Circuit Outage in accordance with Clause 10.4:
[(i) In respect of the Outage Conditions [ ], the User shall (i) ensure that the Maximum Export Limit and Maximum Import Limit for the BM Units relating to the Power Station reflects the outage of the Relevant Circuits and (ii) operate its Power Station to reflect the outage of the Relevant Circuits for all Settlement Periods or parts thereof falling within the Outage Period.]
In the event that the User does not comply with Clauses [ ] above, The Company shall issue Bid-Offer Acceptances to the User to reduce the export from and/or import to the affected BM Unit so that the effect is as if the User had complied with the relevant Clause, and the provisions of the Transmission Related Agreement shall apply.
The Company shall issue to the User a notice that advises the User of the occurrence of an event leading to a reduced circuit capability of Circuit [ ] and where practicable the expected Outage Period. Such notice (including any revision) shall be issued:
In the event that the Notification of Circuit Restriction relates to a Planned Outage on the National Electricity Transmission System, where practicable, be in accordance with Grid Code OC2 requirements; or 10.8.2 In the event that the Notification of Circuit Restriction relates to something other than a Planned Outage on the National Electricity Transmission System or relates to a Planned Outage on the National Electricity Transmission System but it is not practicable for such notice to be in accordance with Grid Code OC2 requirements, such notice shall be given as soon as reasonably practicable and The Company and the User shall agree as soon as practicable after the date hereof the means of such notification.
The Company shall promptly notify the User when the period of reduced circuit capability will or has ceased.
The Company shall be entitled to revise the Notification of Circuit Restriction given under Clause 10.8 above at any time.
Following such Notification of Circuit Restriction in accordance with Clause 10.8:
[(i) In respect of the reduction in capability of Circuit [ ], the User shall (i) ensure that the Maximum Export Limit and Maximum Import Limit for the BM Units relating to the Power Station reflects the reduction in capability of the Relevant Circuits and (ii) operate its Power Station to reflect the reduction in capability of the Relevant Circuits for all Settlement Periods or parts thereof falling within the Outage Period.]
In the event that the User does not comply with Clauses [ ] above, The Company shall issue Bid-Offer Acceptances to the User to reduce the export from and/or import to the affected BM Unit so that the effect is as if the User had complied with the relevant Clause, and the provisions of the Transmission Related Agreement shall apply.
The Company shall issue to the User a notice that advises the User of the occurrence of the ET Conditions and where practicable the expected ET Condition Period. Such notice shall be issued as soon as reasonably practicable and The Company and the User shall agree as soon as practicable after the date hereof the method of such notification.
The Company shall promptly notify the User when the ET Condition Period will or has ceased.
The Company shall be entitled to revise the Notification of ET Restrictions on Availability given under Clause 10.11 above at any time.
The User will acknowledge receipt of such Notification of ET Restrictions on Availability and where practicable shall revise its Output Useable forecast for the affected BM Unit to reflect the reduction in capability specified in the Notification of Restrictions on Availability.
Following such Notification of ET Restrictions on Availability in accordance with Clause 10.11:
the User shall (i) ensure that the Maximum Export Limit and Maximum Import Limit for the BM Units relating to the Power Station reflect the reduction in capability specified in the Notification of ET Restrictions on Availability and (ii) operate its Power Station to reflect the reduction in capability specified in the Notification of ET Restrictions on Availability for all Settlement Periods or parts thereof falling within the ET Condition Period.]
In the event that the User does not comply with Clause 10.15.1 above, The Company shall issue Bid-Offer Acceptances to the User to reduce the export from and/or import to the affected BM Unit so that the effect is as if the User had complied with the Clause, and the provisions of the Transmission Related Agreement shall apply.
Where the User becomes aware or is notified by The Company of any breach of Clauses 14.6 above the User shall forthwith take all reasonable steps to comply with the provisions of that Clause.
Where the User becomes aware or is notified by The Company of any breach of Clauses 10.7 or 10.10 [or 10.15] above the User shall forthwith take all reasonable steps to comply with the provisions of that Clause.
Where the User breaches in whole or in part the provisions of Clause 10.7 or Clause 10.10 [or 10.15] above, the User shall at The Company’s request explain to The Company’s satisfaction (acting reasonably) the reason for the breach and demonstrate to The Company’s satisfaction that appropriate steps have been taken to ensure that such breach will not reoccur. In the event that the User does not do this The Company may give notice to the User reducing the Transmission Entry Capacity of the Connection Site and Appendix C of this Bilateral Connection Agreement shall be varied accordingly. This Transmission Entry Capacity shall apply until such time as the User has explained to The Company’s reasonable satisfaction the reason for the breach and has demonstrated that appropriate steps have been taken to ensure that such breach will not reoccur and Appendix C shall be automatically amended thereafter to reflect the reinstatement of the Transmission Entry Capacity. 10.19] If within 3 months of a breach of Clause 10.7 or Clause 10.10 [or 10.15] above which entitled The Company to take action under Clause 10.12\18 above, the User has still failed to provide the explanation and\or demonstration required by The Company under Clause 10.12\18 then The Company may treat such breach as an Event of Default for the purposes of Section 5 of the CUSC and following such breach may give notice of termination to the User whereupon this Bilateral Connection Agreement shall terminate and the provisions of CUSC Paragraph 5.4.7 shall apply.
For the avoidance of doubt any Deenergisation resulting from the Outage Conditions as set out in the relevant Notification of Restrictions on Availability [or ET Conditions as set out in the relevant Notification of ET Restrictions on Availability] constitutes an Allowed Interruption.
The Company and the User shall act in accordance with Good Industry Practice to minimise so far as reasonably practicable the occurrence and duration of (i) the Outage Conditions and
an Event leading to reduced circuit capability of the Relevant Circuits. The Company and the User will, recognising the effect of the Outage Conditions and the reduced circuit capability on the User’s operations, coordinate the Outage Conditions and the reduced circuit capability on the National Electricity Transmission System (where they occur as a result of a Planned Outage) and the User’s Plant and Apparatus in accordance with Good Industry Practice and to the extent practicable. The Company and the User acknowledge however that even where Planned Outages are coordinated and agreed that The Company and\or the User may need to cancel or change such Planned Outage.
The Company and the User hereby acknowledge and agree that, where reasonably practicable, alternative operating arrangements shall be implemented to minimise the effect of Outage Conditions and reduced circuit capability [, including, but not limited to [describe potential arrangements]]. In the event that The Company and the User implement alternative operating arrangements in respect of an Outage Condition and reduced circuit capability, the provisions of Clauses 10.7 and 10.10 shall not apply to the extent that the alternative operating arrangements mitigate the restrictions (whether in whole or in part) that would otherwise apply to the User under this Clause 10 for all Settlement Periods or parts thereof falling within the Outage Period or period of reduced circuit capability. [10.22 In the event that the National Electricity Transmission System conditions subsequently change such that the conditions required for a design variation under the NETS SQSS are no longer met then The Company shall be entitled to revise Clause 1, this Clause 10 and the Outage Conditions as necessary to ensure that such NETS SQSS conditions continue to be met. power station with Design Variation only ]
11 TERM Subject to the provisions for earlier termination set out in the CUSC this Bilateral Connection Agreement shall continue until the User's Equipment is Disconnected from the National Electricity Transmission System at the Connection Site (or in the case of OTSDUW Build, the OTSUA is Disconnected from the National Electricity Transmission System at the Transmission Interface Site prior to the OTSUA Transfer Time) in accordance with Section 5 of the CUSC.
12 VARIATIONS
Subject to Clause 12.2, 12.3, 12.4 [and 12.5 Offshore only] [and 12.6 Gated Agreements only] below, no variation to this Bilateral Connection Agreement shall be effective unless made in writing and signed by or on behalf of both The Company and the User.
The Company and the User shall effect any amendment required to be made to this Bilateral Connection Agreement by the Authority as a result of a change in the CUSC, the ESO Licence or the Transmission Licence, an order or direction made pursuant to the Act or a Licence, or as a result of settling any of the terms hereof. The User hereby authorises and instructs The Company to make any such amendment on its behalf and undertakes not to withdraw, qualify or revoke such authority or instruction at any time.
The Company has the right to vary Appendices A and B in accordance with this Bilateral Connection Agreement and the CUSC including any variation necessary to enable The Company to charge in accordance with the Charging Statements, or upon any change to the Charging Statements.
Appendices A and B shall be varied automatically to reflect any change to the Construction Works or Transmission Connection Assets as provided for in the Construction Agreement. [12.5 The Company has the right to vary this Bilateral Connection Agreement as necessary as provided for in Clause 1.2.3 of the Construction Agreement. Offshore only]. [12.6 The Company has the right to vary the Transmission Entry Capacity [other capacity as appropriate] as provided for in Clause [7.4/7.5] of the Construction Agreement. Gated Agreements only]
13 GENERAL PROVISIONS Paragraph 6.10 and Paragraphs 6.12 to 6.26 of the CUSC are incorporated into this Bilateral Connection Agreement mutatis mutandis.
14 [OUTAGE OF GIS ASSETS (power station/Non-Embedded Customer/DNO with boundary in accordance with CUSC Paragraph 2.12.1(f) (i) only)
The division of ownership of Plant and Apparatus in Clause [9] above is in accordance with the principles of ownership set out in CUSC Paragraph 2.12.1 (f)(i) and as such the following provisions shall apply.
The Company shall issue to the User a notice that advises the User of the occurrence of the GIS Asset Outage and where practicable the expected GIS Asset Outage Period. Such notice shall be issued:
In the event that the Notification of GIS Asset Outage relates to a Planned Outage on the National Electricity Transmission System, where practicable, be in accordance with Grid Code OC2 requirements; or 14.2.2 In the event that the Notification of GIS Asset Outage relates to something other than a Planned Outage on the National Electricity Transmission System or relates to a Planned Outage on the National Electricity Transmission System but it is not practicable for such notice to be in accordance with Grid Code OC2 requirements, as soon as reasonably practicable and The Company and the User shall agree as soon as practicable after the date hereof the method of such notification.
The Company shall promptly notify the User when the GIS Asset Outage Period will or has ceased.
The Company shall be entitled to revise the Notification of GIS Asset Outage given under Clause 14.2 above at any time.
The User will acknowledge receipt of such Notification of GIS Asset Outage and in the case of a User in the category of a Power Station shall, where practicable, revise its Output Useable forecast for the affected BM Unit accordingly.
Following such Notification of GIS Asset Outage in accordance with Clause 14.2 a User in the category of a Power Station shall:
(i) ensure that the Maximum Export Limit and Maximum Import Limit for the BM Units relating to the Power Station reflects the outage of the GIS Assets and (ii) operate its Power Station to reflect the GIS Asset Outage for all Settlement Periods or parts thereof falling within the GIS Asset Outage Period.
In the event that the User does not comply with Clause 14.5 and Clause 14.6.1 above, The Company shall issue Bid-Offer Acceptances to the User to reduce the export from and/or import to the affected BM Unit to zero so that the effect is as if the User had complied with the Clauses and the provisions of the Transmission Related Agreement shall apply.
For the avoidance of doubt any Deenergisation resulting from the GIS Asset Outage as set out in the relevant Notification of GIS Asset Outage constitutes an Allowed Interruption in the case of a User in the category of a Power Station and shall relieve The Company from its obligations under CUSC Section 2 Paragraphs 2.2.1 and 2.4 in the case of a User in the category of a Non-Embedded Customer or a Distribution System directly connected to the National Electricity Transmission System.
15 OTSDUW Build
Where the Transmission Interface Site is to be Operational prior to the OTSUA Transfer Time, during such period the following provisions shall apply and the other provisions of this Bilateral Connection Agreement shall be construed accordingly.
The OTSUA will be connected to the National Electricity Transmission System at the Transmission Interface Point and:
until the OTSUA Transfer Time the provisions of CUSC Paragraphs 2.2, 2.3 and 2.4 shall apply by reference to the Transmission Interface Site rather than the Connection Site;
until the OTSUA Transfer Time the obligation at CUSC Paragraph 2.5 shall apply by reference to the Transmission Plant and Transmission Apparatus at the Transmission Interface Site;
until the OTSUA Transfer Time, in addition to its obligations at Clause 8 of this Bilateral Connection Agreement, the User shall operate the OTSUA in accordance with Appendices OF3 and OF4 to the Construction Agreement;
until the OTSUA Transfer Time the User shall comply with the site specific technical conditions set out in Appendix OF5 to the Construction Agreement and CUSC Paragraph 2.9.3 shall also apply by reference to Appendices OF1, OF3, OF4 and OF5 as attached to the Construction Agreement;
the division of ownership of Plant and Apparatus at the Transmission Interface Site shall be at [describe electrical or other boundary] and where there are GIS Assets at the Transmission substation at the Transmission Interface Site the GIS Outage Restrictions will apply depending on such boundary;
until the OTSUA Transfer Time the Connection Charges and Use of System Charges shall not take account of any OTSUA that will, at the OTSUA Transfer Time, become Transmission Connection Assets;
at and after the OTSUA Transfer Time the Connection Charges and Use of System Charges shall take account of the OTSUA (including any OTSUA that will become Transmission Connection Assets);
until the OTSUA Transfer Time the Offshore Restrictions on Availability shall not apply;
at the OTSUA Transfer Time the Offshore Restrictions on Availability shall apply. IN WITNESS WHEREOF the hands of the duly authorised representatives of the parties hereto at the date first above written
1. Connection Charges The Connection Charges set out below may be revised in accordance with the terms of this Bilateral Connection Agreement and/or the Construction Agreement and/or the CUSC and/or the Charging Statements Part 1 - Pre-Vesting Assets The Connection Charge for those assets extant at 31st March 1990 and specified in Appendix A Part 1 will be at an annual rate for the period [] to [] of £[] where Rate of Return = []% Transmission Costs Part A Site specific maintenance element = £[] Part B Ot
2. Payment The Connection Charges for Parts 1 to 6 shall be payable in equal monthly instalments as specified in Paragraph 6.6 of the CUSC Appendix Reference: [] APPENDIX C (Power Stations) CONNECTION ENTRY CAPACITY AND TRANSMISSION ENTRY CAPACITY [AND MAXIMUM EXPORT CAPACITY AND MAXIMUM IMPORT CAPACITY - ET Offshore Transmission System only] Company: Grid Supply Point/Connection Site: Part 1 Connection Entry Capacity Connection Entry Capacity (CEC) expressed as an instantaneous MW figure CEC(MW) Power Statio
Schedule 2 Exhibit 1A & Appendix G
1. The Company registered in England with number 11014226 (“The Company”),, which expression shall include its successors and/or permitted assigns); and
2. [] PLC a company registered in [] with number [] whose registered office is at [] (“User”, which expression shall include its successors and/or permitted assigns). WHEREAS
Pursuant to the ESO Licence, The Company has prepared a Connection and Use of System Code ("CUSC") setting out the terms of the arrangements for connection to and use of the National Electricity Transmission System and the provision of certain Balancing Services.
The Company and the User are parties to the CUSC Framework Agreement being an agreement by which the CUSC is made contractually binding between parties.
In accordance with the CUSC The Company and the User entered into a Bilateral Connection Agreement (the "Bilateral Connection Agreement”) reference no [ ] brought into effect on the [ ] in respect of its connection to the National Electricity Transmission System.
in accordance with CUSC Paragraph 6.5.1 (Evaluation of Transmission Impact) the User has notified The Company of the Relevant Embedded Power Stations (as defined below) which are intending to connect to its Distribution System.
Recognising the volume and volatility of requests for connection to the Distribution System and the resulting need for The Company to consider the effect of this on the National Electricity Transmission System, The Company and the User have agreed a process to better manage this as between themselves (the “Transmission Impact Assessment Process”).
This Transmission Impact Assessment Process is used by The Company to identify the Relevant Embedded Power Stations where the effect on the National Electricity Transmission System of the Energisation of such Relevant Embedded Power Stations to the Distribution System can be (a) accommodated subject to Site Specific Requirements and/or (b) accommodated with Construction Works on the National Electricity Transmission System but which can be Energised prior to completion of such works in accordance with the general principles of a Design Variation or (c) cannot be accommodated until the completion of works on the National Electricity Transmission System.
The Company and the User have now agreed to enter into this Agreement in order to amend the terms of the Bilateral Connection Agreement to reflect the Transmission Impact Assessment Process and provide for the Energisation of the Relevant Embedded Power Stations. NOW IT IS HEREBY AGREED as follows:-
1. Unless the subject matter or context requires or is inconsistent therewith terms and expressions defined in Section 11 of the CUSC and in the Bilateral Connection Agreement have the same meanings, interpretations or constructions in this Agreement.
2. The Bilateral Connection Agreement shall be varied with effect from the date hereof as follows:-
Appendix G (Developers and Relevant Embedded Power Stations) attached to this Agreement shall be annexed to the Bilateral Connection Agreement and the Contents Page amended accordingly.
The following definitions shall be added at Clause 1 of the Bilateral Connection Agreement. Developer Capacity in the context of this Bilateral Connection Agreement shall mean the MW figure for each Relevant Embedded Power Station as identified in Appendix G Schedule 1. Developers in the context of this Bilateral Connection Agreement shall mean the developers of the Relevant Embedded Power Stations as identified in Appendix G Schedule 1. Relevant Embedded Power in the context of this Bilateral Connection Stations Agreement shall mean those Relevant Embedded Power Stations identified as such in Appendix G Schedule 1. Technical Limitations any technical limitations at the Connection Site as specified in Appendix G Schedule 1 Part 2. Total MWs means the figure specified as such in Appendix G Schedule 1 Part 2.
The following shall be added as Clause [ ] of the Bilateral Connection Agreement and the Contents Page amended accordingly [ ] Transmission Impact Assessment Process [ ].1 The Company and the User have agreed a process utilising Transmission Impact Assessment (as detailed in Appendix G to this Bilateral Connection Agreement) to manage the Relevant Embedded Power Stations which require an Evaluation of Transmission Impact assessment by The Company under CUSC Paragraph 6.5.1. [ ].3 The intent and structure of Appendix G Schedule 1, which identifies the Relevant Embedded Power Stations which have contracts with the User to connect to the Distribution System and the specific terms that apply to such Relevant Embedded Power Stations (including whether it is the subject of a Construction Agreement), is explained in Appendix G Schedule 2. [ ].4 The provisions in Appendix G Schedule 2 set out the process through which the User can add Relevant Embedded Power Stations to Appendix G Schedule 1. [ ].5 The Transmission Impact Assessment Process envisages and is designed such that Appendix G Schedule 1 is revised and updated and this Bilateral Connection Agreement shall be read and construed by reference to the relevant revision of Schedule 1. [ ].6 The User will provide The Company with regular updates (as agreed by both parties but no fewer than one every 6 months) to the Relevant Embedded Power Stations set out in Schedule 1 of Appendix G in accordance with the requirements set out in Schedule 2 of Appendix G. [ ].7 The Company shall review the updates provided by the User under paragraph [ ].6 in accordance with the requirements of Schedule 2 of Appendix G and notify The User within [5] business days of receipt of the outcome of the review. Should this notification from The Company confirm acceptance or not be provided, the update from the User will be deemed approved and form part of the Bilateral Connection Agreement. Should the update from the User not meet the requirements of Schedule 2 of Appendix G, The Company shall confirm this via the notification to The User. [ ]. 8 Should The Company provide a notification to the User under paragraph [ ].7 that the requirements of Schedule 2 of Appendix G have not being met, The Company and the User shall meet within [5] Business Days to discuss resolution. Should no resolution be agreed between The Company and the User (both acting reasonably), the update will not be incorporated into the Bilateral Connection Agreement until an agreement is reached or the Dispute Resolution Procedure is concluded. [ ].9 The Company shall be entitled to revise Appendix G Schedule 1 as provided for in the Transmission Impact Assessment Process
At Clause 8 (Compliance with Site Specific Technical Conditions) of the Bilateral Connection Agreement the following shall be introduced as Clause 8.2 and the previous Clause renumbered as Clause 8.1.
The following shall be added as Clause 8.3 of the Bilateral Connection Agreement.
In the context of connection of Generation to the Distribution System, unless otherwise agreed with The Company (and recognising that this may require a Modification at the Connection Site), the User shall not exceed the Technical Limitations at the Connection Site.
In respect of each Relevant Embedded Power Station and in each case prior to Energising the connection of that Relevant Embedded Power Station to the Distribution System the User shall ensure that the Site Specific Requirements set out in Appendix F5 (Part 11) identified as applicable to that Relevant Embedded Power are in place.
CONTRACTS (RIGHTS OF THIRD PARTIES) ACT 1999 The parties hereto hereby acknowledge and agree for the purposes of the Contracts (Rights of Third Parties) Act 1999 that no rights, powers or benefits are or shall be conferred on any person pursuant to this Agreement except for such rights, powers or benefits as are expressly conferred on the parties hereto in accordance with, and subject to, its terms. IN WITNESS WHEREOF the hands of the duly authorised representatives of the parties hereto at the date first above written
1. Connection Charges The Connection Charges set out below may be revised in accordance with the terms of this Bilateral Connection Agreement and/or the Construction Agreement and/or the CUSC and/or the Charging Statements Part 1 - Pre-Vesting Assets The Connection Charge for those assets extant at 31st March 1990 and specified in Appendix A Part 1 will be at an annual rate for the period [] to [] of £[] where Rate of Return = []% Transmission Costs Part A Site specific maintenance element = £[] Part B Ot
2. Payment The Connection Charges for Parts 1 to 6 shall be payable in equal monthly instalments as specified in Paragraph 6.6 of the CUSC Appendix Reference: []
| Relevant Embedded Power Station | Developer Capacity in MW | Date of Connection | Technology | Site Specific Conditions # | Interim Restrictions on Availability ^ | Access ahead of completion of all Construction Works Schedule Y/N | Construction Works Schedule * | User Commitment Trigger Date | Consented |
|---|---|---|---|---|---|---|---|---|---|
| Example 1 | 10 | [Date 1] | Wind | 1 only | None | N | A | [Date 2] | Yes |
| Example 2 | 17 | [Date 3] | Solar | 1, 2 | 1A | Y | B | [Date 4] | No |
| Capacity Limit Summary | ||
|---|---|---|
| Total MWs Table 1 | [ ]MW | Additional new generation can be added and will be subject to the applicable works schedule, interim restrictions of availability and site specific conditions as detailed in the final row of table in part 1. Generation should be added in queue order. |
| Total Developer Capacity | [ ]MW | Subject to Cancellation Charge in accordance with CUSC Section 15 User Commitment Methodology |
| Technical Condition Summary | ||
| Connection Asset Reverse Power Limits (Usually the SGT at the site, where that SGT is classified as connection) | [ ] MVA | Where facilities exist, such as an ANM scheme, or other suitable control scheme to curtail generation in the event of a SGT circuit fault this limit can be raised. Detail of the raised limit and associated requirements are contained in technical appendix F3. |
| Fault Level headroom | [ ] kA | [Fault level notes] |
| Voltage | See Note | Voltages conditions in BCA / Appendix F apply to new generation projects. |
| Generator Technology | See Note | There is/is not (delete as appropriate) limit on technology change within this GSP. |
| Comments/Constraints or Additional Restrictions: | ||
| Transferable Capacity (see note below) | [ ] MW | GSP’s: [ ] |
| Date of Base BCA agreement | ||||
|---|---|---|---|---|
| Date Change | Name & Position | Changes/Comments: | Approved Date | The Company Approved By |
| Submitted |
Appendix G Schedule 1 Part 1 – Contains legacy Relevant Embedded Power Stations and all new Relevant Embedded Power Stations. Legacy Relevant Embedded Power Stations should be listed at the top of Part 1 and, unless otherwise specified in the Bilateral Connection Agreement, only pre-existing Site Specific Technical Conditions or restrictions shall apply. No new legacy Relevant Embedded Power Stations can be retrospectively added to Schedule 1.
New Relevant Embedded Power Stations should be added to Part 1 in contractual order.
Part 1 specifies the Site Specific Requirements, any Interim Restrictions on Availability as set out in the Bilateral Connection Agreement and any associated Construction Works against each individual Relevant Embedded Power Station listed.
For the avoidance of doubt The Company will provide details of the Site Specific Requirements, Interim Restrictions on Availability and applicable Construction Works that the User must apply to any future Relevant Embedded Power Station applications and this will be set out at the bottom of Part 1.
Where a Relevant Embedded Power Station is subsequently connected the User will confirm this by replacing the expected connection date with ‘connected’ when providing the next Appendix G update. The User will provide the expected connection dates for each Relevant Embedded Power Station and provide any updates ahead of connection, confirming either the revised date of connection or confirmation that they are now ‘connected’. Therefore, all dates populated in this section must be recorded as either a date in the future (in the format DD/MM/YYYY) or as ‘connected’.
Where a Relevant Embedded Power Station triggers Construction Works they will be unable to connect until these Construction Works have been completed unless indicated in Appendix G Schedule 1 Part 1 in which case any Interim Restrictions on Availability will apply. Any such Interim Restrictions on Availability will be specified in Appendix [ ] to the Bilateral Connection Agreement in which case such Interim Restrictions on Availability will be indicated in Appendix G Schedule 1 Part 1.
Relevant Embedded Power Stations that disconnect from the Distribution System should be removed from Schedule 1 Part 1 by strike through.
Where contracted Relevant Embedded Power Stations terminate their agreement or reduce Developer Capacity before connection the User should notify The Company within the timescale ([ ] business days) set out in Clause [ ] of the Construction Agreement and removed from Appendix G Schedule 1 Part 1 by striking through. For the avoidance of doubt any such termination will attract a Cancellation Charge in accordance with CUSC Section 15.
9 Appendix G Schedule 1 Part 2 - Provides the User with Technical Limitations that must be applied to all Relevant Embedded Power Stations. Connection Asset Reverse Power Limit Where it is possible for the Total MWs Table 1 in Appendix G Schedule 1 minus the minimum GSP demand (as provided by the User to The Company in accordance with the Data Registration Code) to exceed the Connection Asset Reverse Power Limit the User will ensure operational facilities are in place to prevent the Connection Asset Reverse P
10 Administration of Appendix G Schedule 1
All fields for new Relevant Embedded Power Stations in Part 1 of Schedule 1 must be populated. The column for Consent is required in accordance with CUSC Section 15 User Commitment Methodology.
In accordance with Clause [] of this Bilateral Connection Agreement the User will provide The Company with regular updates to Appendix G Schedule 1, including confirmation if there are no changes. The Company requires such updates to be provided on a monthly basis, noting certain changes require notification sooner than 1 month* or on a regular basis as agreed between The Company and the User (but no fewer than one per half calendar year in May and November). Updates must include details of any Relevant Embedded Power Stations that; a) have disconnected from the Distribution System since the last update and b) *that have terminated their Connection Agreement with the User, the CUSC requirement for terminations is 5 business days. c) the User believes the current connection date is expected to be delayed. Advanced notification of the revised connection date is required imperative. d) other recorded information has changed or any that have subsequently energised. Where the Relevant Embedded Power Station has energised the connection date will be updated to ‘connected’. e) new Relevant Embedded Power Station added since the last update.
The submission of each update to Appendix G Schedule 1 from the User must clearly identify any changes.
Each update from the User should be submitted by email to The Company at the following address transmissionconnections@nationalgrideso.com
The Company will review the changes to Appendix G Schedule 1, in accordance with the requirements set out in this Schedule 2 and notify The User within [5] business days of receipt of the outcome of the review. In accordance with Clause [10.8] of this Bilateral Connection Agreement where no notification is provided by The Company or the notification confirms acceptance, the updated Appendix G Schedule 1 will form part of the Bilateral Connection Agreement. Where the notification states there are outstanding concerns, The Company and the User will meet within [5] business days to discuss further and a revised Appendix G Schedule 1 shall not be incorporated in to the Bilateral Connection Agreement until both the User and The Company agree on the required changes For the avoidance of doubt The Company will only not accept changes to Appendix G Schedule 1 if the changes do not comply with the requirements as set out in this Schedule 2 and may charge the User a cost-reflective re-work fee as per The Company’s Statement of Use of System Charges. Monthly changes to Appendix G will be recorded in the register of embedded generation.
[not used]
The Bilateral Connection Agreement will be deemed to be updated with the latest version of the Appendix G Schedule 1 once The Company and User agree to an updated Appendix G Schedule 1 in accordance with paragraph 6. The sole criteria used by The Company for successful or unsuccessful review will be following the requirements of this Schedule 2. For the avoidance of doubt, the requirement for an Evaluation of Transmission Impact (as per CUSC paragraph 6.5.1(c)) shall not be deemed as met until Appendix G Schedule 1 is updated.
Periodically, The Company will reconcile the Appendix G against the changes indicated in Schedule 1 and any changes in the transmission background. If any Interim Restrictions on Availability or Construction Works are deemed no longer applicable these will be removed and any update to the Securities, together with the invoice for any Cancellation Charge in accordance with CUSC Section 15 will be provided to the User.
Where the User breaches in whole or in part the provisions of this Appendix G Schedule 2, the User shall, if requested by The Company, explain to The Company’s satisfaction (acting reasonably) the reason for the breach and demonstrate to The Company’s satisfaction that appropriate steps have been taken (or will be taken) to ensure that such breach will not reoccur. If the User does not provide such explanation, or if The Company is not satisfied with the explanation provided, The Company may give written notice to the User reducing the Total MWs of the Connection Site to zero and update Appendix G Schedule 1 accordingly if there is;
A single breach occurs which risks operation of the National Electricity Transmission System or creates a risk to life or property or,
Three (3) consecutive material breaches, or 3. Eight (8) breaches within a twelve (12) month period. This shall apply until such time as the User has explained to The Company’s reasonable satisfaction the reason for the breach and has demonstrated that appropriate steps have been taken to ensure that such breach will not reoccur, at which point Appendix G Schedule 1 shall be unilaterally amended thereafter by The Company to reflect the reinstatement of the Total MWs.
If within 3 months of a written notice from The Company (reducing the Total MWs of the Connection Site to zero) under paragraph 10.10 above, the User has still failed to provide the explanation and\or demonstration required by The Company under paragraph 10 then The Company may treat such breach as an Event of Default for the purposes of Section 5 of the CUSC and following such breach may give notice of termination to the User whereupon this Bilateral Connection Agreement shall terminate and the provisions of CUSC Paragraph 5.4.7 shall apply.
Schedule 2 Exhibit 2
1. The company registered in England with number 11014226 (“The Company”),”, which expression shall include its successors and/or permitted assigns); and
2. [] a company registered in [] with number [] whose registered office is at [] (“User”, which expression shall include its successors and/or permitted assigns). WHEREAS
Pursuant to the ESO Licence, The Company is required to prepare a Connection and Use of System Code (CUSC) setting out the terms of the arrangements for connection to and use of the National Electricity Transmission System and the provision of certain Balancing Services.
The User has applied for use of the National Electricity Transmission System and pursuant to the ESO Licence The Company is required to offer terms for use of system.
The User has applied for use of the National Electricity Transmission System in the capacity of [ ] as set out in Paragraph 1.2.4 of the CUSC.
As at the date hereof, The Company and the User are parties to the CUSC Framework Agreement (being an agreement by which the CUSC is made contractually binding between the parties). This Bilateral Embedded Generation Agreement is entered into pursuant to the CUSC and shall be read as being governed by it.
This is a [Gate 1 Agreement – large only] [Gate 2 Agreement]. NOW IT IS HEREBY AGREED as follows:
1. DEFINITIONS, INTERPRETATION AND CONSTRUCTION Unless the subject matter or context otherwise requires or is inconsistent therewith, terms and expressions defined in Section 11 of the CUSC [and the Construction Agreement] have the same meanings, interpretations or constructions in this Bilateral Embedded Generation Agreement. [and the following terms and expressions shall have the meaning set out below:- [“Circuit []” [insert detailed description of circuit(s) affected by the design variation] (power station
a [planned]/ [unplanned]/ [planned or unplanned] incident occurring directly on Circuit [ ]; or
Circuit [ ] requiring to be Deenergised for health and safety reasons to allow for the planned or unplanned availability of a circuit in the immediate vicinity of Circuit [ ] (power station with Design Variation only);] [“Outage Period” the period of time during which the Outage Conditions and/or reduced circuit capability apply (power station with Design Variation only).]] [“Notification of Circuit Restrictions” means the notification issued by The Company to the User in accordance with Clause [9.2] of this Bilateral Embedded Generation Agreement; (power station with Design Variation only)] [“Notification of Outage Conditions” means the notification issued by The Company to the User in accordance with Clause [9.4] of this Bilateral Embedded Generation Agreement; (power station with Design Variation only)] [“Notification of Restrictions on Availability” means a Notification of Outage Conditions and\or a Notification of Circuit Restrictions as applicable; (power station with Design Variation only)] [“Relevant Circuits” means [Circuit [ ]]; (power station with Design Variation only)] [“Transmission Related Agreement” means the agreement of even date entered into between the parties for the provision of and payment for Balancing Services in respect of Bid-Offer Acceptances; (power station with Design Variation only)]
[Gate 1 Conditional Clause [and Reservation] – Gate 1 Agreements only
As provided for at Clause 1.2 of the Construction Agreement and this Clause 1.2 the parties agree that until the [Gate 2 Date] the rights and obligations of each party pursuant to this Bilateral Embedded Generation Agreement other than this Clause 1.2 shall be suspended.
[The parties further agree and acknowledge that the information provided for the purposes of the Gate 1 Agreement and set out in the Appendix [O][P] to the Construction Agreement is indicative only prior to the [Gate 2 Date] and shall not be binding on the parties or confer any commitment to these by The Company and any reliance on them for any S2E2-4 purpose prior to the Gate 2 Date is at the User’s risk – no Reservation] [The parties further agree that the Connection Site and Completion Date and Transmission Entry Capacity as set out in Appendix [O][P] to the Construction Agreement have been Reserved for the purposes of this connection and/or use of system and any Gate 2 Offer will reflect this provided that the Gate 2 Application is made prior to the Reservation Expiry Date and the Gate 2 Offer is accepted – where Reservation].
With effect from the [Gate 2 Date] the provisions of this Bilateral Embedded Generation Agreement, as amended by the [Gate 2 Offer] by agreement of the parties shall be in full force and effect.
2. COMMENCEMENT This Bilateral Embedded Generation Agreement shall commence on [].
3. THE SITE OF CONNECTION TO THE DISTRIBUTION SYSTEM The site of Connection of the Embedded Power Station [Distribution Interconnector] to the Distribution System to which this Bilateral Embedded Generation Agreement relates is more particularly described in Appendix A. [The sites of Connection of the Embedded Power Stations [Distribution Interconnector] to the relevant Distribution Systems to which this Bilateral Embedded Generation Agreement relates are more particularly described in Appendix A.]
4. CHARGING DATE The date from which Use of System Charges shall be payable by the User (including One-Off Charges where applicable) shall be [].
5. USE OF SYSTEM The right to use the National Electricity Transmission System shall commence on and Use of System Charges shall be payable by the User from the date hereof.
6. CREDIT REQUIREMENTS [The amount to be secured by the User from [date] is set out in the Secured Amount Statement issued from time to time and as varied from time to time in accordance with Section 3 of the CUSC.] S2E2-5
7. TRANSMISSION ENTRY CAPACITY
The Transmission Entry Capacity of [each of the] site[s] of Connection is [are] and the[ir] value[s] for the purposes of Paragraph 3.2 of the CUSC are specified in Appendix C.
Appendix C Part 3 will set out the BM Unit Identifiers of the BM Units registered at the Connection Site under the Balancing and Settlement Code. The User will provide The Company with the information needed to complete details of these BM Unit Identifiers as soon as practicable after the date hereof and thereafter in association with any request to modify the Transmission Entry Capacity and The Company shall prepare and issue a revised Appendix C incorporating this information. The User shall notify The Company prior to any alteration in the BM Unit Identifiers and The Company shall prepare and issue a revised Appendix C incorporating this information.
The Company shall monitor the Users compliance with its obligation relating to Transmission Entry Capacity against the sum of metered volumes of the BM Units set out in Part 3 of Appendix C and submitted by the User for each Settlement Period.
8. COMPLIANCE WITH SITE SPECIFIC TECHNICAL CONDITIONS The site specific technical conditions applying to [each of] the site[s] of Connection are set out in Appendices F1 to F5 to this Bilateral Embedded Generation Agreement as modified from time to time in accordance with Paragraph 6.9 of the CUSC.
9. [RESTRICTIONS ON AVAILABILITY (power stations with Design Variation only)
The design of the connection of the Distribution System (to which the User is to connect) to the National Electricity Transmission System is when studied under Chapter 2 of the NETS SQSS a variation to the connection design as provided for in that chapter. It is a condition of the NETS SQSS that any variation to the connection design satisfies the criteria set out in paragraphs 2.15 to 2.18 (inclusive) of the NETS SQSS and on that basis the following provisions shall apply.
The Company shall issue to the User a notice that advises the User of the occurrence of the Outage Conditions and where practicable the expected Outage Period. Such notice shall be issued:
In the event that the Notification of Circuit Outage relates to a Planned Outage on the National Electricity Transmission System, where practicable, in accordance with Grid Code OC2 requirements; or 9.2.2 In the event that the Notification of Circuit Outage relates to something other than a Planned Outage on the National Electricity Transmission S2E2-6 System or it relates to a Planned Outage on the National Electricity Transmission System but it is not practicable for such notice to be in accordance with Grid Code 0C2 requirements, as soon as reasonably practicable and The Company and the User shall agree as soon as practicable after the date hereof the method of such notification.
The Company shall promptly notify the User when the Outage Period will or has ceased.
The Company shall be entitled to revise the Notification of Circuit Outage given under Clause 9.2 above at any time.
The User will acknowledge receipt of such Notification of Circuit Outage and where practicable shall revise its Output Useable forecast for the affected BM Unit accordingly.
Following such Notification of Circuit Outage in accordance with Clause 9.2:
[(i) In respect of the Outage Conditions [ ], the User shall (i) ensure that the Maximum Export Limit and Maximum Import Limit for the BM Units relating to the Power Station reflects the outage of the Relevant Circuits and (ii) operate its Power Station to reflect the outage of the Relevant Circuits for all Settlement Periods or parts thereof falling within the Outage Period.]
In the event that the User does not comply with Clauses [ ] above, The Company shall issue Bid-Offer Acceptances to the User to reduce the export from and/or import to the affected BM Unit so that the effect is as if the User had complied with the relevant Clause, and the provisions of the Transmission Related Agreement shall apply.
The Company shall issue to the User a notice that advises the User of the occurrence of an event leading to a reduced circuit capability of Circuit [ ] and where practicable the expected Outage Period. Such notice (including any revision) shall be issued:
In the event that the Notification of Circuit Restriction relates to a Planned Outage on the National Electricity Transmission System, where practicable, in accordance with Grid Code OC2 requirements; or 9.6.2 In the event that the Notification of Circuit Restriction relates to something other than a Planned Outage on the National Electricity Transmission System or relates to a Planned Outage on the National Electricity Transmission System but it is not practicable for such notice to be in accordance with Grid Code OC2 requirements, as soon as reasonably practicable and The Company and the User shall agree as soon as practicable after the date hereof the means of such notification.
The Company shall promptly notify the User when the period of reduced circuit capability will or has ceased. S2E2-7
The Company shall be entitled to revise the Notification of Circuit Restriction given under Clause 9.6 above at any time.
Following such Notification of Circuit Restriction in accordance with Clause 9.6:
[(i) In respect of the reduction in capability of Circuit [ ], the User shall (i) ensure that the Maximum Export Limit and Maximum Import Limit for the BM Units relating to the Power Station reflects the reduction in capability of the Relevant Circuits and (ii) operate its Power Station to reflect the reduction in capability of the Relevant Circuits for all Settlement Periods or parts thereof falling within the Outage Period.]
In the event that the User does not comply with Clauses [ ] above, The Company shall issue Bid-Offer Acceptances to the User to reduce the export from and/or import to the affected BM Unit so that the effect is as if the User had complied with the relevant Clause, and the provisions of the Transmission Related Agreement shall apply.
Where the User becomes aware or is notified by The Company of any breach of Clause 9.5 or Clause 9.8 above the User shall forthwith take all reasonable steps to comply with the provisions of that Clause.
Where the User breaches in whole or in part the provisions of Clause 9.5 or Clause 9.8 above, the User shall at The Company’s request explain to The Company’s satisfaction (acting reasonably) the reason for the breach and demonstrate to The Company’s satisfaction that appropriate steps have been taken to ensure that such breach will not reoccur. In the event that the User does not do this The Company may give notice to the User reducing the Transmission Entry Capacity of the Connection Site and Appendix C of this Bilateral Embedded Generation Agreement shall be varied accordingly. This Transmission Entry Capacity shall apply until such time as the User has explained to The Company’s reasonable satisfaction the reason for the breach and has demonstrated that appropriate steps have been taken to ensure that such breach will not reoccur and Appendix C shall be automatically amended thereafter to reflect the reinstatement of the Transmission Entry Capacity.
If within 3 months of a breach of Clause 9.5 or Clause 9.8 above which entitled The Company to take action under Clause 9.10 above, the User has still failed to provide the explanation and\or demonstration required by The Company under Clause 9.10 then The Company may treat such breach as an Event of Default for the purposes of Section 5 of the CUSC and following such breach may give notice of termination to the User whereupon this Bilateral Embedded Generation Agreement shall terminate and the provisions of CUSC Paragraph 5.4.7 shall apply. S2E2-8
For the avoidance of doubt any Deenergisation resulting from the Outage Conditions as set out in the relevant Notification of Restrictions on Availability constitutes an Allowed Interruption.
The Company and the User shall act in accordance with Good Industry Practice to minimise so far as reasonably practicable the occurrence and duration of (i) the Outage Conditions and (ii) an Event leading to reduced circuit capability of the relevant circuits. The Company and the User will, recognising the effect of the Outage Conditions and the reduced circuit capability on the User’s operations, coordinate the Outage Conditions and the reduced circuit capability on the National Electricity Transmission System (where they occur as a result of a Planned Outage) and the User’s Plant and Apparatus in accordance with Good Industry Practice and to the extent practicable. Company and the User acknowledge however that even where Planned Outages are coordinated and agreed that The Company and\or the User may need to cancel or change such Planned Outage.
The Company and the User hereby acknowledge and agree that, where practicable, alternative operating arrangements shall be implemented to minimise the effect of Outage Conditions [, including, but not limited to [describe potential arrangements]]. In the event that The Company and the User implement alternative operating arrangements in respect of an Outage Condition, the provisions of Clause 9.5 and Clause 9.8 shall not apply to the extent that the alternative operating arrangements mitigate the restrictions (whether in whole or in part) that would otherwise apply to the User under this Clause 9 for all Settlement Periods or parts thereof falling within the Outage Period.
In the event that the National Electricity Transmission System conditions subsequently change such that the conditions required for a design variation under the NETS SQSS are no longer met then The Company shall be entitled to revise Clause 1, this Clause 9 and the Outage Conditions as necessary to ensure that such NETS SQSS conditions continue to be met.]
10. TERM Subject to the provisions for earlier termination set out in the CUSC, this Bilateral Embedded Generation Agreement shall continue until all of the User's equipment [or Equipment for which the User is responsible (as defined in Section K of the Balancing and Settlement Code] is Disconnected from the relevant Distribution System at the site[s] of Connection as provided in Section 5 of the CUSC.
11. VARIATIONS
Subject to 11.2 and 11.3, no variation to this Bilateral Embedded Generation Agreement shall be effective unless made in writing and signed by or on behalf of both The Company and the User. S2E2-9
The Company and the User shall effect any amendment required to be made to this Bilateral Embedded Generation Agreement by the Authority as a result of a change in the CUSC, the ESO Licence or the Transmission Licence, an order or direction made pursuant to the Act or a Licence, or as a result of settling any of the terms hereof. The User hereby authorises and instructs The Company to make any such amendment on its behalf and undertakes not to withdraw, qualify or revoke such authority or instruction at any time.
The Company has the right to vary Appendix B in accordance with this Bilateral Embedded Generation Agreement and the CUSC including any variation necessary to enable The Company to charge in accordance with the Charging Statements or upon any change to the Charging Statements.
12. GENERAL PROVISIONS Paragraph 6.10 and Paragraphs 6.12 to 6.26 of the CUSC are incorporated into this Bilateral Embedded Generation Agreement mutatis mutandis. IN WITNESS WHEREOF the hands of the duly authorised representatives of the parties hereto at the date first above written
SITE[s] OF CONNECTION Company: Site[s] of Connection: Owner[s] / Operator[s] of Distribution System: S2E2-11 APPENDIX B
PART 1: ONE-OFF CHARGES
PART 2: MISCELLANEOUS CHARGE(S) S2E2-12 APPENDIX C
Schedule 2 Exhibit 3
Construction Agreements with an Embedded Power Station relating to a Bilateral Embedded Generation Agreement or (ii) in Construction Agreements with the owner/operator of a Distribution System directly connected to the National Electricity Transmission System where the Construction Agreement is required because of a connection to that Distribution System and the Distribution Queue Management Process applies. INDICATIVE DATED [ ] 20[17]
1. The company registered in England with number 11014226 (“The Company” (“The Company”, which expression shall include its successors and/or permitted assigns); and
2. [] a company registered in [] with number [] whose registered office is at [] (“User”, which expression shall include its successors and/or permitted assigns) WHEREAS
Pursuant to the ESO Licence, The Company has prepared a Connection and Use of System Code (CUSC) setting out the terms of the arrangements for connection to and use of the National Electricity Transmission System and the provision of certain Balancing Services.
The User has applied for [connection to] [and use of] [modification to its connection to] [or use of] the National Electricity Transmission System and pursuant to condition E12 of the ESO Licence, The Company is required to offer terms in accordance with the CUSC in this respect or [specific recital to reflect that the Construction Agreement is an amendment of an existing signed offer pursuant to the CUSC amending documents]
The Company and the User are parties to the CUSC Framework Agreement (being an agreement by which the CUSC is made contractually binding between the parties).
Certain works are required as part of this offer as set out in this Construction Agreement.
This Construction Agreement is entered into pursuant to the terms of the CUSC.
This Construction Agreement has been prepared under the Connect and Manage Arrangements [and is subject to the Queue Management Process].
This Construction Agreement is a [Gate 1 Agreement][Gate 2 Agreement]. NOW IT IS HEREBY AGREED as follows:
DEFINITIONS, INTERPRETATION AND CONSTRUCTION Unless the subject matter or context otherwise requires or is inconsistent therewith, terms and expressions defined in Section 11 of the CUSC and in the Bilateral Connection Agreement have the same meanings, interpretations or constructions in this Construction Agreement. “Attributable Works” those Construction Works identified as such in accordance with the User Commitment Methodology and which are set out in Appendix MM Part 1. "Authority" as defined in the CUSC. “Bilateral Connection Agreement” the Bilateral Connection Agreement entered into between the parties on even date herewith. "Bilateral Embedded Generation the Bilateral Embedded Generation Agreement" Agreement entered into between the parties on even date herewith. “Cancellation Charge” as calculated in accordance with the User Commitment Methodology. "Charging Date" the date upon which the Construction Works are first Commissioned and available for use by the User or if the Independent Engineer before, on or after the Commissioning Programme Commencement Date shall have certified in writing that the Transmission Connection Assets, are completed to a stage where The Company could commence commissioning and by such date the User’s Works shall not have been so certified then the date falling [ ] days after the date of such certification, provided that the Transmission Reinforcement Works are Commissioned and Network Options Assessment Works are completed as at that date. In the event that the Transmission Reinforcement Works are not so Commissioned and/or the Network Options Assessment Works are not so completed the Charging Date shall be the date on which they are Commissioned and/or completed as appropriate. [Exclude Network Options Assessment Works from this definition if they are not also Enabling Works]. “Commissioning Programme the date specified in the Construction Commencement Date” Programme for the commencement of the Commissioning Programme or any substituted date fixed under the terms of this Construction Agreement “Commissioning Programme” the sequence of operations/tests necessary to connect the User’s Works and the Transmission Connection Asset Works to the National Electricity Transmission System for the purpose of making the User's Works available for operation to be determined pursuant to Clause 2.10 of this Construction Agreement. “Completion Date” [ ] or such other date as may be agreed in terms of this Construction Agreement for completion of the Construction Works. “Connect and Manage the temporary derogation from the NETS Derogation” SQSS available to The Company under condition E7 of the ESO Licence and/or the Relevant Transmission Licensee under Standard Condition D3 of its transmission licence; “Connected Planning Data” data required pursuant to the Planning Code which replaces data containing estimated values assumed for planning purposes by validated actual values and updated estimates for the future and by updated forecasts for forecast data items. “Consents” in relation to any Works:-
all such planning and other statutory consents; and
all wayleaves, easements, rights over or interests in land or any other consent; or
permission of any kind as shall be necessary for the construction of the Works and for commencement and carrying on of any activity proposed to be undertaken at or from such Works when completed. “Construction Programme” the agreed programme for the Works to be carried out by or on behalf of The Company and the User set out in detail in Appendix [J] to this Construction Agreement or as amended from time to time pursuant to Clauses 2.3 and 3.2 of this Construction Agreement. "Construction Site" the site where the Transmission Connection Asset Works are being undertaken by or on behalf of The Company; “Construction Works” the Transmission Connection Asset Works, Enabling Works, Network Options Assessment Works and One Off Works and such additional works as are required in order to comply with any relevant Consents relating to any such works but excluding for the avoidance of doubt any Third Party Works. "Dispute Resolution Procedure” the procedure for referral to arbitration set out in Paragraph 7.4 of the CUSC. “Enabling Works” those Transmission Reinforcement Works which are specified in Appendix H Part 1 to this Construction Agreement. “Event of Default” any of the events set out in Clause 10 of this Construction Agreement as constituting an event of default. “Gate 2 Date” means the date on which the last of the conditions at Clause 1.2 of this Construction Agreement are satisfied - [include only in Gate 1 Agreements with Reservation] “Independent Engineer” the engineer specified in Appendix L to this Construction Agreement. Provided that:-
where the parties fail to agree on a suitable engineer within 120 days of the date of this Construction Agreement; or
where any Independent Engineer appointed from time to time shall fail, refuse or cease to act in the capacity set out herein and no substitute engineer of suitable standing and qualification can be agreed by the parties within 30 days; then such engineer as the President of the Institution of Electrical Engineers shall, on the application of either party, nominate shall be the Independent Engineer. “Installed Capacity” the installed capacity provided in the Original Red Line Boundary and set out in Appendix [O][P]. “Key Consents” those Consents required in respect of the [User’s/Developer’s] Power Station which The Company has identified as such and which are set out in Appendix MM Part 2. “Liquidated Damages” the sums specified in or calculated pursuant to Appendix K to this Construction Agreement. “Network Options Assessment the works set out in the Networks Works” Options Assessment report prepared by The Company pursuant to C13 of the ESO Licence and issued by The Company in [ ] which in The Company’s reasonable opinion are required to be completed before the Completion Date to ensure that the National Electricity Transmission System complies with the requirements of condition E7 of the ESO Licence and Standard Condition D3 of any Relevant Transmission Licensee’s transmission licence prior to the Connection of the User’s Equipment in terms of Clause 7.1 [or 7.2] of this Construction Agreement. “One Off Works” the works described in Appendix B1 to this Construction Agreement. “Reservation Expiry Date” [ ] being the date as bilaterally negotiated between The Company and the User [and which may be extended by agreement between the parties] on which the Reservation expires.[include only in Gate 1 Agreements with Reservation] “Term” the term of this Construction Agreement commencing on the date hereof and ending in accordance with Clause 12. “Third Party Works” the works to be undertaken on assets belonging to a party other than a Relevant Transmission Licensee and the User to enable The Company to provide or as a consequence of the connection to and\or use of the National Electricity Transmission System by the User as specified in Appendix N; "Transmission Connection the assets specified in Appendix A to the Assets" Bilateral Connection Agreement. “Transmission Connection Asset the works necessary for construction and Works” installation of the Transmission Connection Assets at the Connection Site specified in Appendix G to this Construction Agreement. “Transmission Reinforcement those works other than the Transmission Works” Connection Asset Works Network Options Assessment Works and One Off Works, which in the reasonable opinion of The Company (and in the absence of the Connect and Manage Derogation) are all necessary to extend or reinforce the National Electricity Transmission System to ensure that the National Electricity Transmission System complies with the requirements of condition E7 of the ESO Licence and Standard Condition D3 of any Relevant Transmission Licensee’s transmission system and which are specified in Appendix H to this Construction Agreement, where Part 1 is the Enabling Works and Part 2 is the Wider Transmission Reinforcement Works. “Trigger Date” [date] as identified in accordance with the User Commitment methodology. “User Progression Milestones” the milestones (applied in accordance with CUSC Section 16) for the User’s project as set out in Appendix Q of this Construction Agreement. “User’s Works” those works necessary for installation of the User’s Equipment which are specified in Appendix I to this Construction Agreement. “Wider Transmission those Transmission Reinforcement Reinforcement Works” Works which are specified in Appendix H Part 2 to this Construction Agreement where Part 2.1 is works required for the User and Part 2.2 is works required for wider system reasons. “Works” the Construction Works and the User’s Works. Users in the capacity of a Directly Connected Power Station or Embedded Power Station (other than those who are a BELLA) insert the following [Notice of Intent the notice issued by The Company pursuant to Clause 7.4.4. Notice of Reduction the notice issued by The Company pursuant to Clause 7.4.7 including a revised Appendix C specifying the revised Transmission Entry Capacity. Preliminary Request the request issued by The Company pursuant to Clause 7.4.1. Reduction Fee the fee payable by the User to The Company in respect of the agreement to vary issued pursuant to Clause 7.4.9 such fee being calculated on the same basis as that set out in the Charging Statements as payable on a payment of actual costs basis in respect of a Modification Application.. Users in the capacity of a Directly Connected Distribution System where works are required in respect of a BELLA or a Relevant Embedded Power Station insert the following (and where the Construction Agreement relates to more than one, for each of the Developers) [Developer Capacity the MW figure [for export] specified in the Developer’s Data. Developer Insert name address and registered number who is party to a BELLA with The Company or the subject of the Transmission Evaluation Application. Developer’s Data the information provided by the [Developer-BELLA] [User in respect of the Developer in the Transmission Evaluation Application-relevant embedded power station] and set out in Appendix [P]. Developer’s Project the connection of a [xMW wind farm\power station to the User’s Distribution System at [ ]] Notice of Intent the notice issued by The Company pursuant to Clause 7.4.4. Notice of Reduction the notice issued by The Company pursuant to Clause 7.4.7 revising the Developer’s Capacity for this Construction Agreement and Appendix A to the BELLA. Preliminary Request the request issued by The Company pursuant to Clause 7.4.1. Reduction Fee the fee payable by the User to The Company in respect of the agreement to vary issued pursuant to Clause 7.4.9 such fee being calculated on the same basis as that set out in the Charging Statements as payable on a payment of actual costs basis in respect of a Modification Application. [A Gate 1 Agreement with/without Reservation only]
GATED APPLICATION AND OFFER PROCESS – GATE 1 CONDITIONAL CLAUSE [AND RESERVATION]
The rights and obligations of the User and The Company under this Construction Agreement [and the [Bilateral Connection Agreement] [Bilateral Embedded Generation Agreement]] are conditional on:
the User making a Gate 2 Application;
the Gate 2 Application meeting the Gate 2 Criteria; and 1.2.1.3 the User accepting the terms of the [Gate 2 Offer]; [and in the case of a BEGA, 1.2.1.4 the owner/operator of the Distribution System accepting the related Gate 2 Offer.]
The parties agree and acknowledge that until the Gate 2 Date, the rights and obligations of each party pursuant to this Construction Agreement (other than this Clause 1.2 and Clause 13 – edit to include any other provisions agreed between the parties as useful to include) and the [Bilateral Connection Agreement] [Bilateral Embedded Generation Agreement] shall be suspended.
[The parties further agree that the information provided for the purposes of this Gate 1 Agreement and set out in the Appendix [O][P] to this Construction Agreement being a proposed [Connection Site] [Site of Connection], Completion Date and requested [Transmission Entry Capacity – edit for other capacity types] are indicative only prior to the Gate 2 Date and shall not be binding on the parties or confer any commitment by The Company to the [Connection Site][Site of Connection], Completion Date or requested [Transmission Entry Capacity – add other relevant capacity refs as appropriate] and any reliance on them for any purpose prior to the Gate 2 Date is at the User’s risk- no reservation]. [The parties further agree that the [Connection Site] [Site of Connection] and Completion Date and [Transmission Entry Capacity-add other relevant capacity refs as appropriate] as set out in Appendix [O][P] to this Construction Agreement have been Reserved for the purposes of this connection/use of system and any Gate 2 Offer will reflect this position and the requested [Transmission Entry Capacity- add other relevant capacity refs as appropriate] provided that the Gate 2 Application is made prior to the Reservation Expiry Date and the Gate 2 Offer is accepted- Reservation only].
At any time prior to the Gate 2 Date, the User shall have the right to terminate this Connection Agreement by written notice to The Company without any liability for any Cancellation Charge. This right to terminate shall expire with effect from the Gate 2 Date.
With effect from the Gate 2 Date the provisions of this Construction Agreement, as amended by the Gate 2 Offer by agreement of the parties, shall be in full force and effect.
2 Carrying out of the Works
Forthwith following the date of this Construction Agreement the User shall agree with the Relevant Transmission Licensee the Safety Rules and Local Safety Instructions to apply during the Construction Programme and Commissioning Programme. Failing agreement within three months of the date of this Construction Agreement the matter shall be referred to the Independent Engineer for determination in accordance with Clause 6 of the Construction Agreement.
Subject to Clauses 2.3 and 2.4 of this Construction Agreement forthwith following the date of this Construction Agreement The Company shall use its best endeavours to obtain in relation to the Construction Works, and the User shall use its best endeavours to obtain in relation to the User's Works, all Consents. Each shall give advice and assistance to the other to the extent reasonably required by the other in the furtherance of these obligations. Further, each party shall, so far as it is legally able to do so, grant to the other or the Relevant Transmission Licensee, all such wayleaves, easements, servitude rights, rights over or interests (but not estates as regards land in England and Wales and not heritable or leasehold interests as regards land in Scotland) in land or any other consents reasonably required by the other or the Relevant Transmission Licensee in order to enable the Works to be expeditiously completed and to enable that other to carry out its obligations to the other under this Construction Agreement and in all cases subject to such terms and conditions as are reasonable.
The following additional provisions shall apply in respect of the Consents and Construction Works:-
All dates specified in this Construction Agreement are subject to The Company obtaining Consents for the Construction Works in a form acceptable to it within the time required to carry out the Construction Works in accordance with the Construction Programme.
In the event of:-
the Consents not being obtained by the required date; or
the Consents being subject to conditions which affect the dates; or
The Company wishing to amend the Construction Works to facilitate the granting of the Consents, The Company shall be entitled to revise the Construction Works (and as a consequence Appendix A to the Bilateral Connection Agreement) and all dates specified in this Construction Agreement and the charges specified in Appendix B to the Bilateral Connection Agreement. For the avoidance of doubt such revisions shall be at The Company 's absolute discretion and the consent of the User is not required.
The User shall be regularly updated by The Company in writing or by such other means as the parties may agree as to progress made by The Company from time to time in the obtaining of relevant Consents pursuant to its obligations under Clause 2.2 or 2.3 of this Construction Agreement.
Paragraphs 11.2.3 to 11.2.5 of the CUSC relating to Consents shall apply to the Construction Agreement as if set out here in full.
The User shall be liable to pay to The Company as part of Final Sums:-
all The Company 's Engineering Charges accrued; and
proper and reasonable out-of-pocket expenses incurred and/or paid or which The Company is legally bound to incur or pay in seeking and obtaining the Consents the subject of Clause 2.2 of this Construction excluding any costs associated with the Network Options Assessment Works and the works specified in Part 2 of Appendix H. The User acknowledges these out of pocket ancillary expenses may include planning inquiries or appeals and the capital costs together with reasonable legal and surveyors costs of landowners or occupiers in acquiring permanent easements or other rights in respect of any electric line or underground cable forming part of the Transmission Connection Asset Works. This sum shall not include any capital costs incurred by The Company, in the acquisition by it of the freehold of any land in England and Wales or the feuhold of any land in Scotland in relation to Connection Sites. The Company shall keep the User informed of the level of such charges and expenses being incurred. The User shall pay such sums within 28 (twenty eight) days of the date of The Company 's invoice therefor.
Paragraphs 11.2.3 to 11.2.5 of the CUSC relating to Consents shall apply to the Construction Agreement as if set out here in full.
Prior to the commencement of the Transmission Connection Asset Works the User shall have the right to terminate this Construction Agreement upon giving not less than 7 (seven) days notice in writing to The Company. In the event of the User terminating this Construction Agreement in terms of this Clause 2.5 the provisions of Clause 11 shall apply].
If the User fails to obtain all Consents for the User's Works having complied with the obligations in Clause 2.2 of this Construction Agreement the obligation on the User to complete the User's Works shall cease and the User may by written notice to The Company terminate this Construction Agreement and the provisions of Clause 11 shall apply
Both parties shall be entitled to contract or sub-contract for the carrying out of their respective parts of the Works (which in the case of The Company shall include work carried out by a Relevant Transmission Licensee or its contractors or sub-contractors). The User or any contractor on its behalf shall be responsible for commencing and for carrying out the User's Works to such stage of completion as shall render them capable of being Commissioned in accordance with the Construction Programme and The Company or any contractor on its behalf shall be responsible for commencing and carrying out the Construction Works to such stage of completion as shall render them capable of being Commissioned in accordance with the Construction Programme.
The parties shall continuously liaise throughout the Construction Programme and Commissioning Programme and each shall provide to the other all information relating to in the case of the User the User’s Works and in the case of The Company the Construction Works reasonably necessary to assist the other in performance of that other’s part of the Works, and shall use all reasonable endeavours to coordinate and integrate their respective part of the Works. There shall be on-site meetings between representatives of the parties at intervals to be agreed between the parties. Each party shall deliver to the other party a written report of progress during each calendar quarter within 7 days of the end of that quarter. Users in the capacity of a Directly Connected Distribution System where works are required in respect of a BELLA or a Relevant Embedded Power Station insert the following [“2.8 The parties shall continuously liaise throughout the Construction Programme and Commissioning Programme and each shall provide to the other all information relating to its own Works reasonably necessary to assist the other in performance of that other’s part of the Works, and shall use all reasonable endeavours to coordinate and integrate their respective part of the Works. There shall be on-site meetings between representatives of the parties at intervals to be agreed between the parties. The User shall also provide to The Company such information as The Company shall reasonably request and which the User is entitled to disclose in respect of the Developer’s Project. Each party shall deliver to the other party where requested a written report of progress during each calendar quarter (including in the case of the User progress on the Developer’s Project to the extent that the User has such information and is entitled to disclose it) within 7 days of the end of that quarter.”]
During the period of and at the times and otherwise as provided in the Construction Programme and the Commissioning Programme The Company shall allow the User, its employees, agents, suppliers, contractors and sub-contractors necessary access to the Construction Site and the User shall allow the Relevant Transmission Licensee and in either case their employees, agents, suppliers, contractors and sub-contractors necessary access to its site to enable each to carry out the Transmission Connection Asset Works and One Off Works or User's Works but not so as to disrupt or delay the construction and completion of the other’s Works on the said sites or the operation of the other’s Plant and Apparatus located thereon, such access to be in accordance with any reasonable regulations relating thereto made by the site owner or occupier.
Not later than six months prior to the Commissioning Programme Commencement Date The Company shall provide the User with a draft Commissioning Programme for the Commissioning of the Transmission Connection Assets, and the User's Equipment. The User shall, as quickly as practicable and in any event within three months of receipt thereof, determine whether or not to approve the proposed Commissioning Programme (which approval shall not be unreasonably withheld or delayed) and shall within such three month period either notify The Company of its approval or, in the event that the User reasonably withholds its approval, notify The Company of any changes or variations to the proposed commissioning programme recommended by the User. If The Company does not accept such changes or variations submitted by the User any dispute shall be referred to the Independent Engineer for determination. The Commissioning Programme agreed between the parties or determined by the Independent Engineer as the case may be shall be implemented by the parties and their sub-contractors in accordance with its terms.
If at any time prior to the Completion Date it is necessary for The Company or The Company in its reasonable discretion wishes to make any addition to or omission from or amendment to the Transmission Connection Asset Works and/or Transmission Reinforcement Works and/or the One Off Works and/or the Third Party Works The Company shall notify the User in writing of such addition, omission or amendment and Appendices [B1 (One Off Works), G (Transmission Connection Asset Works) H (Transmission Reinforcement Works), MM (Attributable Works) and N (Third Party Works)] to this Construction Agreement and consequently Appendices [A (Transmission Connection Assets) and B (Connection Charges and One Off Charges)] to the associated Bilateral Connection Agreement shall be automatically amended to reflect the change. Provided that where a User has elected for the Actual Attrubutable Works Cancellation Charge to be based on the Fixed Attributable Works Cancellation Charge the Attributable Works can only be changed after the Trigger Date as provided for in CUSC Section 15.
[The User shall apply to the Secretary of State for Trade and Industry as part of its application under Section 36 of the Act for its generating station, for deemed planning permission in relation to the substation forming part of the Transmission Connection Asset Works. The User shall use its best endeavours to procure that the said deemed planning permission is so obtained. The Company's obligations under Clause 2.2 of this Construction Agreement shall not require it to obtain planning consent for the said substation unless and until the relevant Secretary of State shall for whatever reason refuse to deem the grant of planning permission in respect of the same. The User shall liaise with The Company as to its construction and operational requirements and shall ensure that the said application meets The Company's requirements. The Company shall provide the User with all information reasonably required by it in relation to the application and the User shall ensure that all requirements of The Company are incorporated in the application for deemed planning consent.]
[The Enabling Works are conditional on British Energy Generation Limited and/or Magnox Electric plc (as the case may be)granting approval to the carrying out of the Construction Works in terms of the Nuclear Site Licence Provisions Agreement being an agreement dated 30 March 1990 between The Company and Nuclear Electric plc (now called Magnox Electric plc) and an agreement dated 31 March 1996 between The Company and British Energy Generation Limited (and described as such). In the event of British Energy Generation Limited and/or Magnox Electric plc (as the case may be) not granting approval The Company shall be entitled to change the Construction Works, the Construction Programme and all dates specified in this Construction Agreement.]
[It is hereby agreed and declared for the purposes of the Construction (Design and Management) Regulations 1994 that the User is the only client in respect of the User's Works and The Company is the only client in respect of the Construction Works and Wider Transmission Reinforcement Works and each of the User and The Company shall accordingly discharge all the duties of clients under the said Regulations.]
[The Company and the User hereby agree and acknowledge that this Construction Agreement is not to be treated as a construction contract within the meaning of section 104 of the Housing Grants, Construction and Re- generation Act 1996 and sections 104 to 113 of the said Act shall have no application either to the Construction Works or the User's Works and the parties’ rights and obligations with regard to matters of dispute resolution and payment procedures are as expressly set out herein.
Third Party Works
The User shall be responsible for carrying out or procuring that the Third Party Works are carried out and shall carry them out or procure that they are carried out in accordance with the timescales specified in the Construction Programme. The User shall confirm to The Company or, where requested to do so by The Company, provide confirmation from the third party that the Third Party Works have been completed.
Given the nature of these works it may not be possible to fully identify the works required or the third parties they relate to at the date hereof. Where this is the case The Company shall, subject to 2.16.3 below, advise the User as soon as practicable and in any event by [ ] of the Third Party Works and shall be entitled to revise Appendix N and as a consequence the Construction Programme as necessary to reflect this.
Where Third Party Works are likely to be Modifications required to be made by another user(s) (“the “First User(s)”) as a consequence of Modifications to the National Electricity Transmission System to be undertaken by The Company under this Construction Agreement The Company shall as soon as practicable after the date hereof issue the notification to such First User’s in accordance with CUSC Paragraph 6.9.3.1. The User should note its obligations under CUSC Paragraph 6.10.3 in respect of the costs of any Modifications required by the First User(s).
In the event that the Third Party Works have not been completed by the date specified in the Construction Programme or, in The Company’s reasonable opinion are unlikely to be completed by such date, The Company shall be entitled to revise the Construction Programme as necessary to reflect such delay and also, where The Company considers it necessary to do so, shall be entitled to revise the Construction Works (and as a consequence Appendices A and B to the Bilateral Connection Agreement). For the avoidance of doubt such revisions shall be at The Company's absolute discretion and the consent of the User is not required. Further, in the event that the Third Party Works have not been completed by [ ] The Company shall have the right to terminate this Construction Agreement upon giving notice in writing to the User and in this event the provisions of Clause 11 of this Construction Agreement shall apply.
Wider Transmission Reinforcement Works The Company shall keep the User advised as to progress on the Wider Transmission Reinforcement Works and shall include information on these in the reports produced pursuant to Clause 2.8.
Forthwith following the date of this Construction Agreement the User shall agree with the Relevant Transmission Licensee the Safety Rules and Local Safety Instructions to apply during the Construction Programme and Commissioning Programme. Failing agreement within three months of the date of this Construction Agreement the matter shall be referred to the Independent Engineer for determination in accordance with Clause 6 of the Construction Agreement.
Subject to Clauses 2.3 and 2.4 of this Construction Agreement forthwith following the date of this Construction Agreement The Company shall use its best endeavours to obtain in relation to the Construction Works, and the User shall use its best endeavours to obtain in relation to the User's Works, all Consents. Each shall give advice and assistance to the other to the extent reasonably required by the other in the furtherance of these obligations. Further, each party shall, so far as it is legally able to do so, grant to the other, or the Relevant Transmission Licensee, all such wayleaves, easements, servitude rights, rights over or interests (but not estates as regards land in England and Wales and not heritable or leasehold interests as regards land in Scotland) in land or any other consents reasonably required by the other or the Relevant Transmission Licensee in order to enable the Works to be expeditiously completed and to enable that other to carry out its obligations to the other under this Construction Agreement and in all cases subject to such terms and conditions as are reasonable.
The following additional provisions shall apply in respect of the Consents and Construction Works:-
All dates specified in this Construction Agreement are subject to The Company obtaining Consents for the Construction Works in a form acceptable to it within the time required to carry out the Construction Works in accordance with the Construction Programme.
In the event of:-
the Consents not being obtained by the required date; or
the Consents being subject to conditions which affect the dates; or
The Company wishing to amend the Construction Works to facilitate the granting of the Consents, The Company shall be entitled to revise the Construction Works (and as a consequence Appendix A to the Bilateral Connection Agreement) and all dates specified in this Construction Agreement and the charges specified in Appendix B to the Bilateral Connection Agreement. For the avoidance of doubt such revisions shall be at The Company 's absolute discretion and the consent of the User is not required.
The User shall be regularly updated by The Company in writing or by such other means as the parties may agree as to progress made by The Company from time to time in the obtaining of relevant Consents pursuant to its obligations under Clause 2.2 or 2.3 of this Construction Agreement.
Prior to the commencement of the Transmission Connection Asset Works the User shall have the right to terminate this Construction Agreement upon giving not less than 7 (seven) days notice in writing to The Company. In the event of the User terminating this Construction Agreement in terms of this Clause 2.5 the User shall in addition to the payments for which it is liable under Clause 2.4 hereof be liable to pay to The Company a sum equal to The Company 's estimate or if applicable revised estimate of Final Sums. The User shall pay such sums within 14 (fourteen) days of the date of The Company's invoice(s) therefore and (where applicable) on termination where applicable The Company shall disconnect the User's Equipment at the Connection Site and:
the User shall remove any of the User's Equipment on the Relevant Transmission Licensee's land within 6 months of the date of termination or such longer period as may be agreed between the Relevant Transmission Licensee and the User; and
The Company shall procure that the Relevant Transmission Licensee removes, any of the Transmission Connection Assets on the User’s land within 6 months of the date of termination or such longer period as may be agreed between the Relevant Transmission Licensee and the User.
If the User fails to obtain all Consents for the User's Works having complied with the obligations in Clause 2.2 of this Construction Agreement the obligation on the User to complete the User's Works shall cease and the User may by written notice to The Company terminate this Construction Agreement whereupon the User shall in addition to the sums for which it is liable under Clause 2.4 hereof be liable to pay to The Company a sum equal to The Company 's estimate or if applicable revised estimate of Final Sums. The User shall pay such sums within 14 (fourteen) days of the date of The Company 's invoice(s) therefore and (where applicable) on termination The Company shall disconnect the User's Equipment at the Connection Site and;
the User shall remove any of the User's Equipment on the Relevant Transmission Licensee's land within 6 months of the date of termination or such longer period as may be agreed between the Relevant Transmission Licensee and the User; and
The Company shall procure that the Relevant Transmission Licensee removes, any of the Transmission Connection Assets on the User’s land within 6 months of the date of termination or such longer period as may be agreed between the Relevant Transmission Licensee and the User.
Both parties shall be entitled to contract or sub-contract for the carrying out of their respective parts of the Works (which in the case of The Company shall include work carried out by a Relevant Transmission Licensee or its contractors or sub-contractors). The User or any contractor on its behalf shall be responsible for commencing and for carrying out the User's Works to such stage of completion as shall render them capable of being Commissioned in accordance with the Construction Programme and The Company or any contractor on its behalf shall be responsible for commencing and carrying out the Construction Works to such stage of completion as shall render them capable of being Commissioned in accordance with the Construction Programme.
The parties shall continuously liaise throughout the Construction Programme and Commissioning Programme and each shall provide to the other all information relating to its own Works reasonably necessary to assist the other in performance of that other’s part of the Works, and shall use all reasonable endeavours to coordinate and integrate their respective part of the Works. There shall be on-site meetings between representatives of the parties at intervals to be agreed between the parties. Each party shall deliver to the other party a written report of progress during each calendar quarter within 7 days of the end of that quarter.
During the period of and at the times and otherwise as provided in the Construction Programme and the Commissioning Programme The Company shall allow the User, its employees, agents, suppliers, contractors and sub-contractors necessary access to the Construction Site and the User shall allow the Relevant Transmission Licensee and in either case their employees, agents, suppliers, contractors and sub-contractors necessary access to its site to enable each to carry out the Transmission Connection Asset Works and One Off Works or User's Works but not so as to disrupt or delay the construction and completion of the other’s Works on the said sites or the operation of the other’s Plant and Apparatus located thereon, such access to be in accordance with any reasonable regulations relating thereto made by the site owner or occupier.
Not later than six months prior to the Commissioning Programme Commencement Date The Company shall provide the User with a draft Commissioning Programme for the Commissioning of the Transmission Connection Assets, and the User's Equipment. The User shall, as quickly as practicable and in any event within three months of receipt thereof, determine whether or not to approve the proposed Commissioning Programme (which approval shall not be unreasonably withheld or delayed) and shall within such three month period either notify The Company of its approval or, in the event that the User reasonably withholds its approval, notify The Company of any changes or variations to the proposed commissioning programme recommended by the User. If The Company does not accept such changes or variations submitted by the User any dispute shall be referred to the Independent Engineer for determination. The Commissioning Programme agreed between the parties or determined by the Independent Engineer as the case may be shall be implemented by the parties and their sub-contractors in accordance with its terms.
If at any time prior to the Completion Date it is necessary for The Company or The Company in its reasonable discretion wishes to make any addition to or omission from or amendment to the Transmission Connection Asset Works and/or Transmission Reinforcement Works and/or the One Off Works and/or the Third Party Works The Company shall notify the User in writing of such addition, omission or amendment and Appendices [B1 (One Off Works), G (Transmission Connection Asset Works) H (Transmission Reinforcement Works) and N (Third Party Works)] to this Construction Agreement and consequently Appendices [A (Transmission Connection Assets) and B (Connection Charges and One Off Charges)] to the associated Bilateral Connection Agreement shall be automatically amended to reflect the change.
[The User shall apply to the Secretary of State for Trade and Industry as part of its application under Section 36 of the Act for its generating station, for deemed planning permission in relation to the substation forming part of the Transmission Connection Asset Works. The User shall use its best endeavours to procure that the said deemed planning permission is so obtained. The Company's obligations under Clause 2.2 of this Construction Agreement shall not require it to obtain planning consent for the said substation unless and until the relevant Secretary of State shall for whatever reason refuse to deem the grant of planning permission in respect of the same. The User shall liaise with The Company as to its construction and operational requirements and shall ensure that the said application meets The Company's requirements. The Company shall provide the User with all information reasonably required by it in relation to the application and the User shall ensure that all requirements of The Company are incorporated in the application for deemed planning consent.]
[The Transmission Reinforcement Works are conditional on British Energy Generation Limited and/or Magnox Electric plc (as the case may be)granting approval to the carrying out of the Construction Works in terms of the Nuclear Site Licence Provisions Agreement being an agreement dated 30 March 1990 between The Company and Nuclear Electric plc (now called Magnox Electric plc) and an agreement dated 31 March 1996 between The Company and British Energy Generation Limited (and described as such). In the event of British Energy Generation Limited and/or Magnox Electric plc (as the case may be) not granting approval The Company shall be entitled to change the Construction Works, the Construction Programme and all dates specified in this Construction Agreement.]
[It is hereby agreed and declared for the purposes of the Construction (Design and Management) Regulations 1994 that the User is the only client in respect of the User's Works and The Company is the only client in respect of the Construction Works and each of the User and The Company shall accordingly discharge all the duties of clients under the said Regulations.]
[The Company and the User hereby agree and acknowledge that this Construction Agreement is not to be treated as a construction contract within the meaning of section 104 of the Housing Grants, Construction and Re- generation Act 1996 and sections 104 to 113 of the said Act shall have no application either to the Construction Works or the User's Works and the parties’ rights and obligations with regard to matters of dispute resolution and payment procedures are as expressly set out herein.
Third Party Works
The User shall be responsible for carrying out or procuring that the Third Party Works are carried out and shall carry them out or procure that they are carried out in accordance with the timescales specified in the Construction Programme. The User shall confirm to The Company or, where requested to do so by The Company, provide confirmation from the third party that the Third Party Works have been completed.
Given the nature of these works it may not be possible to fully identify the works required or the third parties they relate to at the date hereof. Where this is the case The Company shall, subject to 2.x.3 below, advise the User as soon as practicable and in any event by [ ] of the Third Party Works and shall be entitled to revise Appendix N and as a consequence the Construction Programme as necessary to reflect this.
Where Third Party Works are likely to be Modifications required to be made by another user(s) (“the “First User(s)”) as a consequence of Modifications to the National Electricity Transmission System to be undertaken by The Company under this Construction Agreement The Company shall as soon as practicable after the date hereof issue the notification to such First User’s in accordance with CUSC Paragraph 6.9.3.1. The User should note its obligations under CUSC Paragraph 6.10.3 in respect of the costs of any Modifications required by the First User(s).
In the event that the Third Party Works have not been completed by the date specified in the Construction Programme or, in The Company’s reasonable opinion are unlikely to be completed by such date, The Company shall be entitled to revise the Construction Programme as necessary to reflect such delay and also, where The Company considers it necessary to do so, shall be entitled to revise the Construction Works (and as a consequence Appendices A and B to the Bilateral Connection Agreement). For the avoidance of doubt such revisions shall be at The Company's absolute discretion and the consent of the User is not required. Further, in the event that the Third Party Works have not been completed by [ ] The Company shall have the right to terminate this Construction Agreement upon giving notice in writing to the User and in this event the provisions of Clause 11 of this Construction Agreement shall apply.
A Performance Bond or Letter of Credit from a Qualified Bank for the amount stated in the Secured Amount Statement as the estimated amount of the User’s Obligation to be secured, such Performance Bond or Letter of Credit to be Valid for at least the period stated in such Secured Amount Statement and to be renewed periodically where applicable in the manner stated in paragraph 3.3 of this Appendix M; or 2.2 A cash deposit in a Bank Account at least for the amount stated in the Secured Amount Statement as the estimated amount of the User’s Obligation to be secured, such cash deposit to be increased or reduced periodically where applicable in the manner stated in paragraph 3.4 of this Appendix M; or 2.3 A Performance Bond from a Qualified Company for the amount stated in the Secured Amount Statement as the estimated amount of the User’s Obligation to be secured, such Performance Bond to be Valid for at least the period stated in such Secured Amount Statement and to be renewed periodically where applicable in the manner stated in paragraph 3.3 of this Appendix M.
3 Delays
If either party shall have reason to believe that it is being delayed or will be delayed in carrying out that party’s Works for any reason (whether it is one entitling it to the fixing of a new date under Clause 3.2 of this Construction Agreement or not) it shall forthwith notify the other party in writing of the circumstances giving rise to the delay and of the extent of the actual and/or anticipated delay.
If prior to the Completion Date a party (in this Clause 3.2 “the Affected Party”) shall be delayed in carrying out any of the Affected Party’s Works (including their commissioning) by reason of any act, default or omission on the part of the other Party (in this Clause the “Defaulting Party”) or the Defaulting Party’s employees, agents, contractors or sub-contractors or by reason of an event of Force Majeure, the Affected Party shall be entitled to have such later date or dates fixed as the Commissioning Programme Commencement Date and/or (as the case may be) the Completion Date as may be fair and reasonable in the circumstances provided that it shall have notified the Defaulting Party in writing of such act, default or omission or event of Force Majeure within 28 days of it becoming aware of the occurrence giving rise to the delay together with an estimate of the proposed delay which it will cause the Affected Party. In the event of a dispute between the parties over what is or are any fair and reasonable new date or dates to be fixed in the cir- cumstances this shall be promptly referred to and determined by the Independent Engineer. Once the new date or dates are fixed the Construction Programme and/or Commissioning Programme shall be deemed automatically amended as appropriate.
If either party shall have reason to believe that it is being delayed or will be delayed in carrying out that party’s Works for any reason (whether it is one entitling it to the fixing of a new date under Clause 3.2 of this Construction Agreement or not) it shall forthwith notify the other party in writing of the circumstances giving rise to the delay and of the extent of the actual and/or anticipated delay.
If prior to the Completion Date a party (in this Clause 3.2 “the Affected Party”) shall be delayed in carrying out any of the Affected Party’s Works (including their commissioning) by reason of any act, default or omission on the part of the other Party (in this Clause the “Defaulting Party”) or the Defaulting Party’s employees, agents, contractors or sub-contractors or by reason of an event of Force Majeure, the Affected Party shall be entitled to have such later date or dates fixed as the Commissioning Programme Commencement Date and/or (as the case may be) the Completion Date as may be fair and reasonable in the circumstances provided that it shall have notified the Defaulting Party in writing of such act, default or omission or event of Force Majeure within 28 days of it becoming aware of the occurrence giving rise to the delay together with an estimate of the proposed delay which it will cause the Affected Party. In the event of a dispute between the parties over what is or are any fair and reasonable new date or dates to be fixed in the cir- cumstances this shall be promptly referred to and determined by the Independent Engineer. Once the new date or dates are fixed the Construction Programme and/or Commissioning Programme shall be deemed automatically amended as appropriate.
Any Notice of Drawing to be delivered to Barclays Bank PLC or any other bank at which the Bank Account shall have been opened or a Qualified Bank or a Qualified Company may be delivered by hand, by post or by other agreed communication method.
If the User becomes aware that the bank issuing the Performance Bond or Letter of Credit ceases to be a Qualified Bank or that the company giving the Performance Bond ceases to be a Qualified Company, the User shall so notify The Company in writing as soon as it becomes so aware. If The Company becomes aware that the bank issuing the Performance Bond or Letter of Credit ceases to be a Qualified Bank or that the company giving the Performance Bond ceases to be a Qualified Company, The Company may notify the User to that effect in writing. Where the bank or the company so ceases to be either a Qualified Bank or a Qualified Company (as the case may be) as a consequence of The Company having reasonable cause to doubt the continued rating of the said bank or company, such notice shall be accompanied by a statement setting out The Company’s reasons for having such doubt. The User shall within 21 days of the giving of such notice by The Company or the User whichever is the earlier provide a replacement Performance Bond and/or Letter of Credit from a Qualified Bank or Qualified Company, as the case may be, and/or provide a cash deposit in the required amount in a Bank Account. From the date the replacement Performance Bond or Letter of Credit or Bank Account cash deposit is effectively and unconditionally provided and Valid, The Company will consent in writing to the security which it replaces being released.
The following provisions shall govern the issuance, renewal and release of the Performance Bond or Letter of Credit:-
The Performance Bond or Letter of Credit shall be Valid initially from the signing of this Construction Agreement at least to and including the following 31st March or 30th September whichever is the earlier date. Such Performance Bond or Letter of Credit shall be for an amount not less than that stated in the Secured Amount Statement as the amount of the User’s Obligation to be secured during the period specified in the Secured Amount Statement.
On a date which is at least 45 days (or if such day is not a Business Day then on the immediately preceding Business Day) before the next following 31st March or 30th September whichever is the earlier date such Performance Bond or Letter of Credit shall be renewed so as to be Valid for not less than 6 months commencing from the immediately following 1st April or 1st October (as the case may be). Such renewed Performance Bond or Letter of Credit shall be for an amount not less than the amount of the User’s Obligation stated in the Secured Amount Statement as the amount to be secured during the period that such renewed Performance Bond or Letter of Credit shall be Valid.
Thereafter, the renewed Performance Bond or Letter of Credit shall be further renewed in like manner every 6 months.
The following provisions shall govern the maintenance of cash deposits in the Bank Account:-
The amount of the cash deposit to be maintained in the Bank Account shall be maintained from the date of this Construction Agreement at least to and including the following 31st March or 30th September, whichever is the earlier date. Such cash deposit shall be in an amount as stated in the Secured Amount Statement as the amount of the User’s Obligation to be secured during the period stated in the Secured Amount Statement.
If the amount stated in the Secured Amount Statement as the amount of the User’s Obligation to be secured from the following 1st April to 30th September or from the following 1st October to 31st March (as the case may be) is an amount greater than the amount then secured, the cash deposit in the Bank Account shall be increased to such greater amount on a date which is 45 days before the following 31st March or 30th September (as the case may be) which immediately precedes the commencement of the relevant above mentioned period.
If such amount stated in the Secured Amount Statement is smaller than the amount then secured, the cash deposit in the Bank Account shall not be reduced to the amount so stated until the expiry of 7 days after the next following 31st March or 30th September (as the case may be) (“the Release Date”).
The sum equal to the amount of reduction in the cash deposit in the Bank Account shall be paid by The Company to the User from the Bank Account on the Release Date.
Any interest accruing to the Bank Account shall be for the account of and belong to the User absolutely, and The Company agrees to take any steps required to be taken by it for the release from the Bank Account and payment to the User of such interest as soon as the same shall have been credited to the Bank Account and The Company shall have received notice of such credit.
Notwithstanding any provision aforesaid:-
The User may provide different securities to The Company at any one time, each securing a different amount, provided that the aggregate amount secured by such securities shall be not less than the aggregate amount required to be secured pursuant to the Secured Amount Statement for any period specified therein.
The User may upon the expiry of at least 14 days prior written notice to The Company, substitute one type of security for another provided that unless The Company shall otherwise agree in writing such substituted security must be Valid from 1st April or 1st October (as the case may be) and committed at least 45 days before the immediately preceding 31st March or 30th September (as the case may be) in the following manner:-
where a Performance Bond or a Letter of Credit is to substitute for other securities, it must be issued or given at least 45 days before such immediately preceding 31st March or 30th September (as the case may be).
where a cash deposit in a Bank Account is to substitute for other securities, it must be deposited into the Bank Account at least 45 days before such immediately preceding 31st March or 30th September (as the case may be).
Upon request by the User to The Company, securities substituted in the aforesaid manner shall, providing the substitute security shall be Valid, be released on the following 1st April or 1st October (as the case may be). However, where the amount required by the Secured Amount Statement to be secured for any period is less than the amount required to be secured in the preceding period, the substituted security shall not be released until 7 days after the then following 31st March or 30th September (as the case may be). PART 2
4 Commissioning Programme and Liquidated Damages
Each party shall give written notice to the other declaring its readiness to commence the Commissioning Programme when this is the case.
The Commissioning Programme shall commence forthwith once both parties have given written notice to the other under Clause 4.1.
The Works shall be deemed to have been Commissioned on the date that the Independent Engineer certifies in writing to that effect.
In the event that the actual date of commencement of the Commissioning Programme is later than the Commissioning Programme Commencement Date The Company (if and to the extent that it is responsible for delayed commissioning beyond the Commissioning Programme Commencement Date, such responsibility and/or its extent to be determined by the Independent Engineer failing agreement between the parties) shall be liable to pay to the User Liquidated Damages for each day that the actual date of commencement of the Commissioning Programme is later than the Commissioning Programme Commencement Date. It is declared and agreed that such Liquidated Damages shall cease to be payable in respect of any period after the date of actual commencement of the Commissioning Programme.
In the event that the actual date on which the Construction Works are Commissioned is later than the Completion Date The Company (if and to the extent that it is responsible for delayed completion beyond the Completion Date, such responsibility and/or its extent to be determined by the Independent Engineer failing agreement between the parties) shall be liable to pay to the User Liquidated Damages for each day that the actual date on which the Construction Works are Commissioned is later than the Completion Date. It is hereby agreed and declared that such Liquidated Damages shall cease to be payable in respect of any period after completion of the Construction Works.
Liquidated Damages payable under Clauses 4.4 and 4.5 of this Construction Agreement shall accumulate on a daily basis but shall be payable calendar monthly. On or before the 15th day of each month the party entitled to receive the payment of Liquidated Damages shall send to the other party a statement of the Liquidated Damages which have accrued due in the previous calendar month. The party receiving such statement shall in the absence of manifest error pay the Liquidated Damages shown on the statement within 28 days of the date upon which the statement is received.
Without prejudice to and in addition to the obligation of the User pursuant to Clause 2.4 of this Construction Agreement, the payment or allowance of Liquidated Damages pursuant to this Clause 4 shall be in full satisfaction of The Company's liability for failure to perform its obligations by the Commissioning Programme Commencement Date and/or the Completion Date as appropriate.
In the event that the User shall have failed, in circumstances not entitling it to the fixing of a new date as the Commissioning Programme Commencement Date pursuant to Clause 3.2, to complete the User's Works by [ ] to a stage where the User is ready to commence the Commissioning Programme, The Company shall have the right to terminate this Construction Agreement upon giving notice in writing to the User and the provisions of Clause 11 shall apply.
Each party shall give written notice to the other declaring its readiness to commence the Commissioning Programme when this is the case.
The Commissioning Programme shall commence forthwith once both parties have given written notice to the other under Clause 4.1.
The Works shall be deemed to have been Commissioned on the date that the Independent Engineer certifies in writing to that effect.
In the event that the actual date of commencement of the Commissioning Programme is later than the Commissioning Programme Commencement Date The Company (if and to the extent that it is responsible for delayed commissioning beyond the Commissioning Programme Commencement Date, such responsibility and/or its extent to be determined by the Independent Engineer failing agreement between the parties) shall be liable to pay to the User Liquidated Damages for each day that the actual date of commencement of the Commissioning Programme is later than the Commissioning Programme Commencement Date. It is declared and agreed that such Liquidated Damages shall cease to be payable in respect of any period after the date of actual commencement of the Commissioning Programme.
In the event that the actual date on which the Construction Works are Commissioned is later than the Completion Date The Company (if and to the extent that it is responsible for delayed completion beyond the Completion Date, such responsibility and/or its extent to be determined by the Independent Engineer failing agreement between the parties) shall be liable to pay to the User Liquidated Damages for each day that the actual date on which the Construction Works are Commissioned is later than the Completion Date. It is hereby agreed and declared that such Liquidated Damages shall cease to be payable in respect of any period after completion of the Construction Works.
Liquidated Damages payable under Clauses 4.4 and 4.5 of this Construction Agreement shall accumulate on a daily basis but shall be payable calendar monthly. On or before the 15th day of each month the party entitled to receive the payment of Liquidated Damages shall send to the other party a statement of the Liquidated Damages which have accrued due in the previous calendar month. The party receiving such statement shall in the absence of manifest error pay the Liquidated Damages shown on the statement within 28 days of the date upon which the statement is received.
Without prejudice to and in addition to the obligation of the User pursuant to Clause 2.4 of this Construction Agreement, the payment or allowance of Liquidated Damages pursuant to this Clause 4 shall be in full satisfaction of The Company's liability for failure to perform its obligations by the Commissioning Programme Commencement Date and/or the Completion Date as appropriate.
In the event that the User shall have failed, in circumstances not entitling it to the fixing of a new date as the Commissioning Programme Commencement Date pursuant to Clause 3.2, to complete the User's Works by [ ] to a stage where the User is ready to commence the Commissioning Programme, The Company shall have the right to terminate this Construction Agreement upon giving notice in writing to the User. In the event of such termination the User shall in addition to the amounts for which it is liable under Clause 2.4 to this Construction Agreement be liable to The Company to pay to The Company a sum equal to The Company's estimate or revised estimate of Final Sums. The User shall pay such sums within 14 (fourteen) days of the date of The Company 's invoice(s) therefor and on termination (where applicable) The Company shall disconnect the User's Equipment at the Connection Site and:
the User shall remove any of the User's Equipment on the Relevant Transmission Licensee's land within 6 months of the date of termination or such longer period as may be agreed between the Relevant Transmission Licensee and the User; and
The Company shall procure that the Relevant Transmission Licensee removes, any Transmission Connection Assets on the User’s land within 6 months of the date of termination or such longer period as may be agreed between the Relevant Transmission Licensee and the User.
5 Approval to Connect/Energise/Become Operational
Not later than 4 months prior to the expected Commissioning Programme Commencement Date or by such other time as may be agreed between the parties the parties shall prepare and submit the Operation Diagrams required to be prepared and submitted by each of them respectively under CC 7.4.7 and 7.4.10 and likewise the Site Common Drawings required under CC 7.5.2 and 7.5.4 and, if necessary, Gas Zone Diagrams referred to in CC 7.4.9 and 7.4.12.
Not later than 3 months prior to the expected Commissioning Programme Commencement Date or by such other time as may be agreed between the parties the parties shall prepare and submit the Operation Diagrams required to be prepared and submitted by each of them respectively under CC 7.4.8 and 7.4.11 and likewise the Site Common Drawings required under CC 7.5.3 and 7.5.5.
Not later than 3 months prior to the expected Commissioning Programme Commencement Date or by such other time as may be agreed between the parties:- 5.3.1 each party shall submit to the other data within its possession needed to enable the completion of Appendices F3 and F4 to the Bilateral Connection Agreement; and 5.3.2 the User shall submit to The Company evidence satisfactory to The Company that the User's Equipment complies or will on completion of the User's Works comply with Clause 8 of this Construction Agreement and Paragraphs [1.3.3(b), 2.9 and 6.7] of the CUSC.
Not later than 8 weeks prior to the expected Commissioning Programme Commencement Date or by such other time as may be agreed between the parties each party shall submit to the other:
for the Connection Site information to enable preparation of Site Responsibility Schedules complying with the provisions of Appendix 1 to the Connection Conditions together with a list of managers who have been duly authorised by the User to sign such Site Responsibility Schedules on the User's behalf;
written confirmation as required under CC.5.2(g) that the list of Safety Co-ordinators are authorised and competent [and a list of persons appointed pursuant to Grid Code CC5.2(m)];
a list of the telephone numbers for the facsimile machines referred to in CC6.5.9.
Confirmation of access to the Electronic Communications Platform referred to in CC6.5.9 upon access being provided by The Company.
If directly connected to the National Electricity Transmission System not later than 3 months prior to the expected Commissioning Programme Commencement Date each party shall submit to the other a statement of readiness to complete the Commissioning Programme in respect of the Works and the statement submitted by the User shall in addition contain relevant Connected Planning Data and a report certifying to The Company that, to the best of the information, knowledge and belief of the User, all relevant Connection Conditions applicable to the User have been considered and complied with. If The Company considers that it is necessary, it will require this latter report to be prepared by the Independent Engineer. The report shall incorporate if requested by The Company type test reports and test certificates produced by the manufacturer showing that the User's Equipment meets the criteria specified in CC6.
If embedded not later than 3 months prior to the Charging Date or by such other time as may be agreed between the Parties the User shall submit to The Company a statement of readiness to use the National Electricity Transmission System together with Connected Planning Data and a report certifying to The Company that, to the best of the information, knowledge and belief of the User:-
all relevant Connection Conditions applicable to the User have been considered;
CC 6 insofar as it is applicable to the User has been complied with; and
the site-specific conditions set out in Appendices [F1, F3, F4] and [F5] to the Bilateral Embedded Generation Agreement have been complied with. If The Company considers that it is necessary, it will require this report to be prepared by the Independent Engineer. The report shall incorporate if requested by The Company type test reports and test certificates produced by the manufacturer showing that the User's Equipment meets the criteria.
Not later than 4 months prior to the expected Commissioning Programme Commencement Date or by such other time as may be agreed between the parties the parties shall prepare and submit the Operation Diagrams required to be prepared and submitted by each of them respectively under CC 7.4.7 and 7.4.10 and likewise the Site Common Drawings required under CC 7.5.2 and 7.5.4 and, if necessary, Gas Zone Diagrams referred to in CC 7.4.9 and 7.4.12.
Not later than 3 months prior to the expected Commissioning Programme Commencement Date or by such other time as may be agreed between the parties the parties shall prepare and submit the Operation Diagrams required to be prepared and submitted by each of them respectively under CC 7.4.8 and 7.4.11 and likewise the Site Common Drawings required under CC 7.5.3 and 7.5.5.
Not later than 3 months prior to the expected Commissioning Programme Commencement Date or by such other time as may be agreed between the parties:- 5.3.1 each party shall submit to the other data within its possession needed to enable the completion of Appendices F3 and F4 to the Bilateral Connection Agreement; and 5.3.2 the User shall submit to The Company evidence satisfactory to The Company that the User's Equipment complies or will on completion of the User's Works comply with Clause 8 of this Construction Agreement and Paragraphs [2.9 and 6.7] of the CUSC.
Not later than 8 weeks prior to the expected Commissioning Programme Commencement Date or by such other time as may be agreed between the parties each party shall submit to the other:
for the Connection Site information to enable preparation of Site Responsibility Schedules complying with the provisions of Appendix 1 to the Connection Conditions together with a list of managers who have been duly authorised by the User to sign such Site Responsibility Schedules on the User's behalf;
written confirmation as required under CC.5.2(g) that the list of Safety Co-ordinators are authorised and competent [and a list of persons appointed pursuant to Grid Code CC5.2(m)];
a list of the telephone numbers for the facsimile machines referred to in CC6.5.9.
Confirmation of access to the Electronic Communications Platform referred to in CC6.5.9 upon access being provided by The Company.
Not later than 3 months prior to the expected Commissioning Programme Commencement Date each party shall submit to the other a statement of readiness to complete the Commissioning Programme in respect of the Works and the statement submitted by the User shall in addition contain relevant Connected Planning Data and a report certifying to The Company that, to the best of the information, knowledge and belief of the User, all relevant Connection Conditions applicable to the User have been considered and complied with. If The Company considers that it is necessary, it will require this latter report to be prepared by the Independent Engineer. The report shall incorporate if requested by The Company type test reports and test certificates produced by the manufacturer showing that the User's Equipment meets the criteria specified in CC6.
INDEPENDENT ENGINEER The parties agree and shall procure that the Independent Engineer shall act as an expert and not as an arbitrator and shall decide those matters referred or reserved to them under this Construction Agreement by reference to Good Industry Practice using their skill, experience and knowledge and with regard to such other matters as the Independent Engineer in their sole discretion considers appropriate. All references to the Independent Engineer shall be made in writing by either party with notice to the other being given contemporaneously as soon as reasonably practicable and in any event within 14 days of the occurrence of the dispute to be referred to the Independent Engineer. The parties shall promptly supply the Independent Engineer with such documents and information as they may request when considering such question. The Independent Engineer shall use their best endeavours to give their decision upon the question before them as soon as possible following its referral to them. The parties shall share equally the fees and expenses of the Independent Engineer. The parties expressly acknowledge that submission of disputes for resolution by the Independent Engineer does not preclude subsequent submission of disputes for resolution by arbitration as provided for in the Dispute Resolution Procedure. Pending any such submission the parties shall treat the Independent Engineer’s decision as final and binding.
6 INDEPENDENT ENGINEER The parties agree and shall procure that the Independent Engineer shall act as an expert and not as an arbitrator and shall decide those matters referred or reserved to them under this Construction Agreement by reference to Good Industry Practice using their skill, experience and knowledge and with regard to such other matters as the Independent Engineer in their sole discretion considers appropriate. All references to the Independent Engineer shall be made in writing by either party wi
(Confidentiality), 6.18 (Intellectual Property), 6.19 (Force Majeure), 6.20 (Waiver), 6.21 (Notices), 6.22 (Third party Rights), 6.23 (Jurisdiction), 6.24 (Counterparts), 6.25 (Governing Law), 6.26 (Severance of Terms), 6.27 (Language), 6.38 (Directions related to national security) inclusive of the CUSC shall apply mutatis mutandis to this Construction Agreement as if set out in this Construction Agreement.
(Confidentiality), 6.18 (Intellectual Property), 6.19 (Force Majeure), 6.20 (Waiver), 6.21 (Notices), 6.22 (Third party Rights), 6.23 (Jurisdiction), 6.24 (Counterparts), 6.25 (Governing Law), 6.26 (Severance of Terms), 6.27 (Language) inclusive of the CUSC shall apply mutatis mutandis to this Construction Agreement as if set out in this Construction Agreement.
DISPUTES Except as specifically provided for in this Construction Agreement any dispute arising under the terms of this Construction Agreement shall be referred to arbitration in accordance with the Dispute Resolution Procedure.
7 BECOMING OPERATIONAL [7.1 If directly connected to the National Electricity Transmission System The Company shall connect and Energise the User's Equipment at the Connection Site during the course of and in accordance with the Commissioning Programme and thereafter upon compliance by the User with the provisions of Clause 5 and provided (1) the Construction Works excluding the Network Options Assessment Works [delete Network Options Assessment Works under the Connect and Manage Arrangements if these are not
If, on completion of the User's Works in accordance with the terms of this Construction Agreement the Registered Capacity of the User's Equipment is less than [ ]MW, The Company shall automatically have the right to amend Clause 7 and Appendix C to the Bilateral Connection Agreement to reflect the actual Registered Capacity of the User's Equipment. Users in the capacity of a Directly Connected Power Station or Embedded Power Station (other than those who are a BELLA) insert the following [7.4 Transmission Entry Capacity Reduction
If, at any time prior to the Completion Date The Company reasonably believes from data provided by the User to The Company, the reports provided by the User pursuant to Clause 2.8 and Clause 5 of this Construction Agreement, the commissioning process under the Construction Agreement or otherwise that the User’s Equipment will be such that it will not be capable of exporting power onto the National Electricity Transmission System at the level of the Transmission Entry Capacity The Company shall advise the User accordingly in writing setting out its reasons for this belief, the source of the information giving rise to the concern and seeking clarification from the User.
The User shall respond to The Company within 15 Business Days of the date of the Preliminary Request providing such information or data as is necessary to satisfy The Company’s concerns set out in the Preliminary Request and making any amendments necessary to the report provided by the User pursuant to Clause 2.8 and / or data provided by the User to The Company to reflect this.
In the event that The Company is satisfied from the information provided in accordance with Clause 7.4.2 by the User that the User’s Equipment will be such that it will be capable of exporting power onto the National Electricity Transmission System at the level of the Transmission Entry Capacity The Company shall notify the User accordingly.
In the event that the User does not respond to the Preliminary Request or, notwithstanding the User’s response, The Company remains of the view that the User’s Equipment will be such that it will not reasonably be capable of exporting power onto the National Electricity Transmission System at the level of the Transmission Entry Capacity The Company shall inform the User in writing that it intends to amend Clause 7 and Appendix C to the [Bilateral Connection Agreement] [Bilateral Embedded Generation Agreement] to reflect the Transmission Entry Capacity that it reasonably believes to be the level of power that the User's Equipment will be capable of exporting .
The User shall respond to the Notice of Intent within 15 Business Days of the date of the Notice of Intent explaining why it still reasonably believes that its User's Equipment will be capable of exporting power onto the National Electricity Transmission System at the level of the Transmission Entry Capacity or at more than the MW figure proposed by The Company in the Notice of Intent or providing a reasonable explanation as to why this is not the case.
In the event that The Company is satisfied from the information provided in accordance with Clause 7.4.5 by the User that the User’s Equipment will be such that it will be capable of exporting power onto the National Electricity Transmission System at the level of the Transmission Entry Capacity The Company shall notify the User accordingly.
Where notwithstanding the User’s response to the Notice of Intent The Company remains of the view that the User’s Equipment will be such that it will not reasonably be capable of exporting power onto the National Electricity Transmission System at the level of the Transmission Entry Capacity or at more than the MW figure proposed by The Company in the Notice of Intent or the User does not provide a response that is satisfactory to The Company within the timescale specified in 7.4.5 above The Company will issue the Notice of Reduction to the User and will send a copy of the same to the Authority.
Unless during such period the matter has been referred by the User to the Authority for determination by the Authority under the provisions of condition E13.5 of the ESO Licence, the Notice of Reduction shall take effect on the day 15 Business Days after the date of the Notice of Reduction and Appendix C of the [Bilateral Connection Agreement] [Bilateral Embedded Generation Agreement] shall be amended on that date in the manner set out in the Notice of Reduction. Where the matter has been referred the amendments to Appendix C of the [Bilateral Connection Agreement] [Bilateral Embedded Generation Agreement] and the date they take effect shall be as set out in the Authority’s determination.
After a Notice of Reduction has taken effect The Company shall be entitled to make such amendments to this Construction Agreement as it requires as a result of the reduction in Transmission Entry Capacity effected by the Notice of Reduction and as a consequence to the [Bilateral Connection Agreement] [Bilateral Embedded Generation Agreement]. The Company shall advise the User as soon as practicable and in any event within 3 months of the date of the Notice of Reduction (or if the matter has been referred by the User to the Authority for determination, the date of determination) of such amendments by way of offer of an agreement to vary the Construction Agreement and [Bilateral Connection Agreement] [Bilateral Embedded Generation Agreement]. This agreement to vary will also provide for payment by the User of the Reduction Fee where applicable. The parties acknowledge that any dispute regarding this variation shall be referable to and determined by the Authority under the provisions of condition E13.5 of the ESO Licence. [7.5 Compliance with Original Red Line Boundary -add only where it’s a Gated Agreement for a direct connection If a User is not compliant at a User Progression Milestone with the Original Red Line Boundary (other than as it may be changed under the Queue Management Guidance) for one or more technologies, The Company shall be entitled to amend the Construction Agreement and as a consequence the Bilateral Connection Agreement to:
reduce the Installed Capacity (of each technology that is non- compliant).
remove that technology if the Installed Capacity of a technology is reduced to 0 MW.
reduce the [Transmission Entry Capacity] [other relevant capacity] if the sum of the Installed Capacity of all technologies is reduced such that it is less than the [Transmission Entry Capacity] [other relevant capacity] and such that the [Transmission Entry Capacity] [other relevant capacity] is no higher than the sum of the Installed Capacity of all technologies.] [7.6 Where there is a reduction in Transmission Entry Capacity under Clause 7.4 [or Clause 7.5] prior to the Charging Date, on such reduction in Transmission Entry Capacity taking effect the User the User shall pay to The Company the Cancellation Charge such payment to be made within 14 days of the date of The Company’s invoice in respect thereof.] Users in the capacity of a Directly Connected Distribution System where works are required in respect of a BELLA or a Relevant Embedded Power Station insert the following (and where the Construction Agreement relates to more than one, for each of the Developers) [7.4 Developer Capacity Reduction
If, at any time prior to the Completion Date The Company reasonably believes from the reports provided by the User pursuant to Clause 2.8 and Clause 5 of this Construction Agreement [in the case of relevant embedded power stations – and\or CUSC Paragraphs 6.5.8 or 6.5.5.11], the commissioning process generally or otherwise that the Developer’s Equipment will be such that it will not be capable of generating at the Developer Capacity, The Company shall advise the User accordingly in writing setting out its reasons and seeking clarification of the position from the User.
The User shall respond to The Company within 15 Business Days of the date of the Preliminary Request providing such information or data as is necessary to satisfy The Company’s concerns set out in the Preliminary Request and making any amendments necessary to the report provided by the User pursuant to Clause 2.8 and /or data provided by the User to The Company to reflect this.
In the event that The Company is satisfied from the information provided in accordance with Clause 7.4.2 by the User that the Developer’s Equipment will be such that it will be capable of generating at the Developer Capacity The Company shall notify the User accordingly.
In the event that the User does not respond to the Preliminary Request or, notwithstanding the User’s response, The Company remains of the view that the Developer’s Equipment will be such that it will not reasonably be capable of generating at the Developer Capacity , The Company shall inform the User and the Developer in writing that it intends to amend the Developer Capacity in this Construction Agreement [and the associated BELLA] to reflect the whole MW figure that it reasonably believes the Developer's Equipment will be capable of generating at.
The User shall respond to the Notice of Intent within 15 Business Days of the date of the Notice of Intent explaining why it still reasonably believes that the Developer's Equipment will be capable of generating at the Developer Capacity or at more than the MW figure proposed by The Company in the Notice of Intent or providing a reasonable explanation as to why this is not the case.
In the event that The Company is satisfied from the information provided in accordance with Clause 7.4.5 by the User that the Developer’s Equipment will be such that it will be capable of generating at the Developer Capacity The Company shall notify the User accordingly.
Where notwithstanding the User’s response The Company remains of the view that the Developer’s Equipment will be such that it will not be capable of generating at the Developer Capacity or at or at more than the MW figure proposed by The Company in the Notice of Intent or the User does not provide a response that is satisfactory to The Company within the timescale specified in Clause 7.4.5 above The Company will issue the Notice of Reduction to the User and the Developer and will send a copy of the same to the Authority.
Unless during such period the matter has been referred by the User to the Authority for determination by the Authority under the provisions of condition E13.5 of the ESO Licence, the Notice of Reduction shall take effect on the day 15 Business Days after the date of the Notice of Reduction and the Developer Capacity in this Construction Agreement [and Appendix A of the associated BELLA] shall be amended on that date in the manner set out in the Notice of Reduction. Where the matter has been referred the amendments to Appendix A of the associated BELLA and the date they take effect shall be as set out in the Authority’s determination.
After a Notice of Reduction has taken effect The Company shall be entitled to make such amendments to this Construction Agreement as it requires as a result of the reduction in the Developer Capacity effected by the Notice of Reduction and as a consequence to the [Bilateral Connection Agreement or Agreement to Vary] [and BELLA]. The Company shall advise the User as soon as practicable and in any event within 3 months of the date of the Notice of Reduction (or if the matter has been referred by the User [and BELLA] to the Authority, the date of determination) of such amendments by way of agreement(s) to vary. The agreement to vary will also provide for payment by the User of the Reduction Fee and on such reduction in Developer Capacity taking effect the User shall pay the Cancellation Charge in respect of the reduction such payment to be made within 14 days of the date of The Company’s invoice in respect thereof. The parties acknowledge that any dispute regarding this variation shall be referable to and determined by the Authority under the provisions of condition E13.5 of the ESO Licence.”]
Where as a result of the reduction in the Developer Capacity effected by the Notice of Reduction the Developer is no longer an Embedded Exemptable Large Power Station and as a result the BELLA is to be terminated as provided for in the BELLA then the following provisions shall apply:
The agreement to vary referred to in Clause 7.4.9 above shall also provide for such amendments as are necessary to the Construction Agreement and [Bilateral Connection Agreement or Agreement to Vary] to reflect the fact that the Developer is no longer to be party to a BELLA but is a Relevant Embedded Power Station.
Where The Company determines that the reduction in the Developer Capacity effected by the Notice of Reduction is such that if a Transmission Evaluation Application had been made by the User on the basis of that reduced Developer Capacity on the same date as, but instead of, the Developer’s application for the BELLA then no works would have been required on the National Electricity Transmission System then The Company shall be entitled to terminate this Construction Agreement and the provisions of Clause 11 shall apply. In such case The Company shall be entitled to make such amendments as are necessary to the [Bilateral Connection Agreement or Agreement to Vary] to reflect the fact that the Developer is no longer party to a BELLA but is a Relevant Embedded Power Station.
The Company and the User shall treat the Developer as if it had been a Relevant Embedded Power Station at the time of its application for a BELLA and for the purposes of CUSC Paragraph 6.5 as if a) the Developer’s application for the BELLA had been a Transmission Evaluation Application under CUSC 6.5.5, b) this Construction Agreement had been entered into as a result of the Modification Application referred to in CUSC Paragraph 6.5.5.5, c) the Notice of Reduction is a revised Transmission Evaluation Application from the User under CUSC Paragraph 6.5.5.8 by reference to the reduction in the Developer Capacity effected by the Notice of Reduction and d) the agreement to vary referred to in Clause 7.4.10.1 or 7.4.10.2 as The Company’s response to the User’s revised Transmission Evaluation Application and the provisions of CUSC Paragraph 6.5 shall apply on that basis.
Where there is a reduction in Developer Capacity under Clause 7.4 prior to the Charging Date, on such reduction in Developer Capacity taking effect the User shall pay to The Company the Cancellation Charge such payment to be made within 14 days of the date of The Company’s invoice in respect thereof.
The Company shall connect and Energise the User's Equipment at the Connection Site during the course of and in accordance with the Commissioning Programme and thereafter upon compliance by the User with the provisions of Clause 5 and provided (1) the Construction Works excluding the Network Options Assessment Works shall be Commissioned and (2) [the Network Options Assessment Works and Third Party Works shall be completed The Company shall forthwith notify the User in writing that the Connection Site shall become Operational.
[Compliance with Original Red Line Boundary - add only where it’s a Gated Agreement for a direct connection If a User is not compliant at a User Progression Milestone with the Original Red Line Boundary (other than as it may be changed under the Gate 2 Criteria) for one or more technologies, The Company shall be entitled to amend the Construction Agreement and as a consequence the Bilateral Connection Agreement to:
reduce the Installed Capacity (of each technology that is non- compliant).
remove that technology if the Installed Capacity of a technology is reduced to 0 MW.
reduce the [relevant capacity] if the sum of the Installed Capacity of all technologies is reduced such that it is less than the [capacity] and such that the [capacity] is no higher than the sum of the Installed Capacity of all technologies.]
COMPLIANCE WITH SITE SPECIFIC TECHNICAL CONDITIONS The User shall ensure that on the Completion Date the User's Equipment complies with the site specific technical conditions set out in Appendix F 1-5 to the Bilateral Connection Agreement .
CREDIT REQUIREMENTS Alternate provisions apply depending whether or not the User does (9A) or does not (9B) meet The Company's required credit rating on signing the Construction Agreement. Details of the credit requirements are set out in the CUSC. 9A1 PROVISION OF SECURITY 9A.1.1 The User shall as soon as possible after execution of this Construction Agreement and in any event no later than one (1) month after the date of such execution confirm to The Company whether it meets The Company Credit Rating. Thereafter not less than 75 days before 1 April and 1 October in each year until (subject to Clause 9A.4) 28 days after the Charging Date the User shall confirm its The Company Credit Rating to The Company (which in the case of a long term private credit rating shall be confirmed by Standard and Poor’s or Moody’s within a period of 45 days prior to the date of confirmation). The User shall inform The Company in writing forthwith if it becomes aware of losing its The Company Credit Rating or if it is or is likely to be put on credit watch or any similar credit surveillance procedure which may give The Company reasonable cause to believe that the User may not be able to sustain its The Company Credit Rating for at least 6 months. 9A.1.2In the event that the User has elected to provide The Company with an indicative credit rating and The Company is of the reasonable opinion that the User has ceased to comply with the requirements of Clause 9A.1.1 then The Company may require the User forthwith:-
to apply to Standard and Poor’s and/or Moody’s for a further indicative long term private credit rating; or
to confirm to The Company that it shall provide the security referred to in Clause 9A.1.4 hereof. 9A.1.3 In the event of the User:-
not having an The Company Credit Rating; or
having a credit rating below The Company Credit Rating; or
not having obtained from Standard and Poor’s or Moody’s within 30 days of the written notification under Clause 9A.1.2 above an indicative long term private credit rating, or if The Company becomes aware that:
the User ceases to have an The Company Credit Rating; or
the User is put on credit watch or other similar credit surveillance procedure as specified above which may give The Company reasonable cause to believe that the User may not be able to maintain an The Company Credit Rating for at least 6 months; or
the User has not obtained from Standard and Poor’s within 30 days of the written notification by The Company under Clause 9A.1.2(i) above a further indicative long term private credit rating, the User shall (where appropriate on receipt of written notification from The Company) comply with the terms of Clause 9A.1.4. 9A.1.4 The User shall within 21 days of the giving of a notice under Clause 9A.1.3 or within 30 days of the User confirming to The Company under Clause 9A.1.2(ii) that it will provide the security specified below (whichever is the earlier), provide The Company with the security specified below to cover the User’s payment obligations to The Company arising in the event of, or which have arisen prior to, termination of this Construction Agreement. The security to be provided shall be in an amount not greater than such sums payable on termination (inclusive of any applicable Value Added Tax that would be due) and specified in writing by The Company to the User from time to time as appropriate. Such security shall be provided by way of:-
an irrevocable on demand standby Letter of Credit or guarantee; or
cash held in escrow [Escrow Account/ Bank Account]; or
any other form included in The Company’s then current policy and procedure such letter of credit or guarantee or security to be in a form agreed in writing by The Company and to be given by a Qualifying Bank, or Qualifying Company. Cash deposited in [escrow] shall be deposited with a Qualifying Bank. The choice of such security shall be at the discretion of the User. 9A.1.5 The User shall in addition to providing the requisite security enter into an agreement with The Company, which shall be supplemental to this Construction Agreement (the “Amending Agreement”). The Amending Agreement shall be in such form as The Company shall reasonably require and shall contain such provisions in relation to the User’s obligations to provide and maintain security as shall be consequential upon the requirement for security having arisen, in line with The Company’s then current provisions to the like effect in its agreements with other parties. The Amending Agreement shall relate to the procedures required in obtaining and maintaining the security and shall not alter or amend the amount of security required in terms of this Construction Agreement. 9A.1.6 In the event of The Company’s credit requirements being reviewed at any time The Company shall advise the User in writing of the new credit requirements and the User shall within 30 days of such notification confirm in writing to The Company whether it wishes to enter into an Amending Agreement to reflect the new credit requirements. Thereafter if the User has confirmed it wishes to accept the new credit requirements The Company and the User shall within 30 days of such notification enter into an Amending Agreement. 9A.1.7 In the event that the facts or circumstances giving rise to the obligations of the User to provide the security have ceased, then The Company shall release the security and provisions to that effect shall be included in the Amending Agreement. Final Sums 9A.2 Within 60 days of the date of termination of this Construction Agreement The Company shall:
furnish the User with a further statement showing a revised estimate of Final Sums and will provide as soon as practicable evidence of such costs having been incurred; and
by written notice to the User inform the User of all capital items which cost The Company in excess of £10,000 and in relation to which an amount on account of Final Sums shall have been paid and whether The Company (1) wishes to retain the said capital items or (2) dispose of them. 9A.3.1 In respect of all capital items which The Company wishes to retain (other than those which have been, or are proposed to be installed as a replacement for Transmission Plant and Transmission Apparatus) The Company shall forthwith reimburse to the User the amount paid by the User on account of Final Sums in respect of the said capital items (including without limitation the amount paid on account of the design, purchase, installation and testing of the said capital item and also associated construction works and interest charges) together with interest calculated thereon on a daily basis from the date of termination of this Construction Agreement to the date of payment at Base Rate for the time being and from time to time provided that in the event that The Company wishes to retain any capital item which has been installed but wishes to remove it to storage or to another site then it shall only reimburse to the User the cost of the capital item and not the costs of such installation and shall deduct from any reimbursement due to the User the costs of removal and/or storage. 9A.3.2 In respect of all capital items which The Company wishes to dispose (other than those which have been, or are proposed to be installed as a replacement for Transmission Plant and Transmission Apparatus) it shall forthwith (and subject to The Company obtaining the consent of the Authority under condition F4 of the ESO Licence if required and\or subject to any Relevant Transmission Licensee obtaining the consent of the Authority under Standard Condition B3 of its transmission licence) sell or procure the sale of the said capital item on an arms-length basis as soon as reasonably practicable. Forthwith upon receipt of the sale proceeds The Company shall pay to the User the proceeds received from any such sale together with interest thereon calculated on a daily basis from the date of termination to the date of payment at Base Rate for the time being and from time to time less any reasonable costs associated with the sale including the costs and expenses reasonably incurred and/or paid and/or which The Company is legally bound to pay on removing the capital item, any storage charges and any costs reasonably incurred by The Company in respect of reinstatement associated with removal of the capital item. The Company shall provide the User with reasonably sufficient evidence of all such costs and expenses having been incurred. If the Authority does not agree to the disposal of the capital item the capital item shall be retained by The Company and The Company shall reimburse the User the notional current market value in situ of the said capital item as between a willing buyer and a willing seller as agreed between the parties and failing agreement as determined by reference to arbitration in accordance with the Dispute Resolution Procedure together with interest thereon calculated on a daily basis from the date of termination of this Construction Agreement to the date of payment at Base Rate for the time being and from time to time. 9A.3.3 As soon as reasonably practicable after termination of this Construction Agreement The Company shall provide the User with a statement of and invoice for Final Sums together with evidence of such costs having been incurred and/or paid and/or having been committed to be incurred. If the Final Sums are greater than the payments made by the User in respect of The Company’s estimate(s) of Final Sums the User shall within 28 days of the said statement and invoice prepared by The Company pay to The Company the additional payments due by the User together with interest calculated thereon on a daily basis at Base Rate for the time being and from time to time from the date of previous payment(s) sums equal to The Company’s estimate of Final Sums to the date of the statement of and invoice for Final Sums. If the Final Sums is less than the payments made by the User in respect of The Company’s estimate of Final Sums paid by the User following termination of this Construction Agreement The Company shall forthwith pay to the User the excess paid together with interest on a daily basis at Base Rate for the time being and from time to time from the date of payment of the fair and reasonable estimate of Final Sums to the date of reimbursement by The Company of the said excess paid. 9A.4 The obligations to provide security under this Clause 9A shall continue until either all sums due under this Construction Agreement have been paid in full or security arrangements have been put in place by the User under the Bilateral Connection Agreement in accordance with Section 2 Part III of the CUSC. Until such time as the security arrangements are put in place in accordance with Section 2 Part III of the CUSC The Company shall be entitled to call upon the security put in place under the terms of this Construction Agreement for payment of Termination Amounts when due under the provisions of the CUSC. Or 9B.1 Provision of Security 9B.1.1 The User hereby agrees that it shall forthwith upon the signing of this Construction Agreement provide to The Company or procure the provision to The Company of, and the User shall until (subject to Clause 9B.8) 28 days after the Charging Date (unless and until this Construction Agreement shall be terminated and all sums due or which will or might fall due in respect of which security is to be provided shall have been paid) maintain or procure that there is maintained in full force and effect (including by renewal or replacement), a security arrangement from time to time and for the time being as set out in Appendix M hereto to provide security for the User’s obligation to pay The Company any and all sums specified by The Company in accordance with Clause 9B.2 of this Construction Agreement as requiring to be secured in respect of:-
the User’s liability to pay The Company amounts from time to time due under Clause 2.4 of this Construction Agreement; and
Final Sums. 9B.2 Provision of Bi-annual Estimate and Secured Amount Statement 9B.2.1 The Company shall provide to the User an estimate (“the Bi-annual Estimate”) in substantially the form set out in Part 2 of Appendix M to this Construction Agreement and showing the amounts of all payments required or which may be required to be made by the User to The Company in respect of Final Sums and The Company Engineering Charges and other expenses in relation to seeking Consents referred to in Clause 2.4 of this Construction Agreement (inclusive of any Value Added Tax that would be due) at the fol- lowing times and in respect of the following periods:-
forthwith on and with effect from the signing of this Construction Agreement, in respect of the period from and including the day of signing of this Construction Agreement until the next following 31st March or 30th September (whichever shall first occur); and
not less than 75 (seventy five) days (or if such day is not a Business Day the next following Business Day) prior to each 31st March and 30th September thereafter in respect of the period of six calendar months commencing on the immediately following 1st April or 1st October (as the case may be), until this Construction Agreement shall be terminated and all sums due or which will or might fall due in respect of which security is to be provided shall have been paid. 9B.2.2 Such Bi-annual Estimate shall be accompanied by a statement (in the form of the Secured Amount Statement set out in Part 3 of Appendix M to this Construction Agreement) (“Secured Amount Statement”) specifying the aggregate amount to be secured at the beginning of and throughout each such period. 9B.2.3 If The Company shall not provide any subsequent Bi-annual Estimate and Secured Amount Statement by the requisite date, then the User shall at the date it is next required to have in full force and effect security and whether by renewal or replacement or otherwise in respect of the following six calendar month period nonetheless provide security in accordance with the provisions of this Construction Agreement in the same amount as the amount then in force in respect of the then current six calendar month period. Notwithstanding the foregoing, if The Company shall provide the User with any Bi-annual Estimate and Secured Amount Statement later than the date specified in Clause 9B.2.1 of this Construction Agreement, then the following shall apply. The User shall within 30 (thirty) days of receipt of the said Secured Amount Statement procure that to the extent that the amount in respect of which security has been or is to be provided pursuant to this Clause 9B.2.3 in respect of the relevant period (“the Secured Amount”) falls short of the amount stated in the Secured Amount Statement (“the Required Amount”) the Secured Amount shall be adjusted to the Required Amount. 9B.3 Entitlement to Estimate If The Company is (for whatever reason) unable on any relevant date to calculate precisely any sum due or which has accrued due or in respect of which the User has a liability to The Company for payment under any of the provisions of this Construction Agreement, The Company shall be entitled to invoice the User for a sum equal to The Company’s fair and reasonable estimate of the sums due or which may become due or in respect of which the User has a liability to The Company for payment. The Company shall also be entitled to send the User further invoices for such sums not covered in previous invoices. The User shall pay The Company all sums so invoiced by The Company. 9B.4 Demands not Affected by Disputes It is hereby agreed between The Company and the User that if there shall be any dispute between the User and The Company as to:- 9B.4.1 any amount certified by The Company in any Secured Amount Statement as requiring at any time and from time to time to be secured; or 9B.4.2 the fairness and reasonableness of The Company’s estimate; or 9B.4.3 whether there has been an Event of Default (under the Construction Agreement or the CUSC), or 9B.4.4 the lawfulness or otherwise of any termination or purported termination of this Construction Agreement such dispute shall not affect the ability of The Company to make demands pursuant to the security arrangement to be provided pursuant to Clause 9B.1 of and Appendix M to this Construction Agreement and to recover the amount or amounts payable thereunder, it being acknowledged by the User that but for such being the case The Company’s security would be illusory by reason of the period of validity of the relevant security being likely to expire or capable of expiring before the final resolution of such dispute. The User accordingly covenants with The Company that it will not take any action, whether by way of proceedings or otherwise, designed or calculated to prevent, restrict or interfere with the payment to The Company of any amount secured under the security arrangement nor seek nor permit nor assist others to do so. 9B.5 If there shall be any dispute as mentioned in Clause 9B.4 of this Construction Agreement the same shall, whether The Company shall have terminated this Construction Agreement and recovered or sought to recover payment under the security arrangement or not, and without prejudice to The Company’s right to recover or seek to recover such payment, be referred in the case of Clauses 9B.4.1 and 9B.4.2 to the Independent Engineer (and, for the avoidance of doubt the provisions of this Construction Agreement relating to the Independent Engineer for the purposes of this Clause 9B.5 shall survive termination) and, in the case of Clauses 9B.4.3 and 9B.4.4 be dealt with by referral to arbitration in accordance with the Dispute Resolution Procedure. Final Sums 9B.6 Within 60 days of the date of termination of this Construction Agreement The Company shall:
furnish the User with a further statement showing a revised estimate of Final Sums and will provide as soon as practicable evidence of such costs having been incurred; and
by written notice to the User inform the User of all capital items which cost The Company in excess of £10,000 and in relation to which an amount on account of Final Sums shall have been paid and whether The Company (1) wishes to retain the said capital items or (2) dispose of them. 9B.7.1 In respect of all capital items which The Company wishes to retain (other than those which have been, or are proposed to be installed as a replacement for Transmission Plant and Transmission Apparatus) The Company shall forthwith reimburse to the User the amount paid by the User on account of Final Sums in respect of the said capital items (including without limitation the amount paid on account of the design, purchase, installation and testing of the said capital item and also associated construction works and interest charges) together with interest calculated thereon on a daily basis from the date of termination of this Construction Agreement to the date of payment at Base Rate for the time being and from time to time provided that in the event that The Company wishes to retain any capital item which has been installed but wishes to remove it to storage or to another site then it shall only reimburse to the User the cost of the capital item and not the costs of such installation and shall deduct from any reimbursement due to the User the costs of removal and/or storage. 9B.7.2 In respect of all capital items which The Company wishes to dispose (other than those which have been, or are proposed to be installed as a replacement for Transmission Plant and Transmission Apparatus) it shall forthwith (and subject to The Company obtaining the consent of the Authority under Standard Condition B3 of the Transmission Licence if required and\or subject to any Relevant Transmission Licensee obtaining the consent of the Authority under condition F4 of the ESO Licence) sell or procure the sale of the said capital item on an arms-length basis as soon as reasonably practicable. Forthwith upon receipt of the sale proceeds The Company shall pay to the User the proceeds received from any such sale together with interest thereon calculated on a daily basis from the date of termination to the date of payment at Base Rate for the time being and from time to time less any reasonable costs associated with the sale including the costs and expenses reasonably incurred and/or paid and/or which The Company is legally bound to pay on removing the capital item, any storage charges and any costs reasonably incurred by The Company in respect of reinstatement associated with removal of the capital item. The Company shall provide the User with reasonably sufficient evidence of all such costs and expenses having been incurred. If the Authority does not agree to the disposal of the capital item the capital item shall be retained by The Company and The Company shall reimburse the User the notional current market value in situ of the said capital item as between a willing buyer and a willing seller as agreed between the parties and failing agreement as determined by reference to arbitration in accordance with the Dispute Resolution Procedure together with interest thereon calculated on a daily basis from the date of termination of this Construction Agreement to the date of payment at Base Rate for the time being and from time to time. 9B.7.3 As soon as reasonably practicable after termination of this Construction Agreement The Company shall provide the User with a statement of and invoice for Final Sums together with evidence of such costs having been incurred and/or paid and/or having been committed to be incurred. If the Final Sums are greater than the payments made by the User in respect of The Company’s estimate(s) of Final Sums the User shall within 28 days of the said statement and invoice prepared by The Company pay to The Company the additional payments due by the User together with interest calculated thereon on a daily basis at Base Rate for the time being and from time to time from the date of previous payment(s) sums equal to The Company’s estimate of Final Sums to the date of the statement of and invoice for Final Sums. If the Final Sums is less than the payments made by the User in respect of The Company’s estimate of Final Sums paid by the User following termination of this Construction Agreement The Company shall forthwith pay to the User the excess paid together with interest on a daily basis at Base Rate for the time being and from time to time from the date of payment of the fair and reasonable estimate of Final Sums to the date of reimbursement by The Company of the said excess paid. 9B.8 The obligations to provide security under this Clause 9 B shall continue until either all sums due under this Construction Agreement have been paid in full or security arrangements have been put in place by the User under the Bilateral Connection Agreement in accordance with Section 2 Part III of the CUSC. Until such time as the security arrangements are put in place in accordance with Section 2 Part III of the CUSC The Company shall be entitled to call upon the security put in place under the terms of this Construction Agreement for payment of Termination Amounts where due under the provisions of the CUSC.
EVENT OF DEFAULT As before alternate provisions apply depending whether or not the User does (10A) or does not (10B) meet The Company's required credit rating on signing this Construction Agreement 10A. Event of Default Any of the following events shall constitute an Event of Default:- 10A.1 If the User fails to provide or procure that there is provided to The Company within the requisite time any relevant security satisfactory to The Company, or to enter into the Amending Agreement pursuant to Clauses 9A.1 or 10A.3 of this Construction Agreement. 10A.2 If having entered into the Amending Agreement and having provided security satisfactory to The Company pursuant to Clauses 9A.1 and 10A.3 of this Construction Agreement.
The User thereafter fails to provide or procure that there is provided to The Company or at any time fails to maintain or procure that there is maintained in full force and effect the relevant security arrangement required by this Construction Agreement as varied by the Amending Agreement or to revise or renew such security with the required replacement security or to maintain or procure that there is maintained in full force and effect any such renewed, revised or substituted security as so required, or if the User shall otherwise be in breach of any of its obligations in respect of security under this Construction Agreement as varied by the Amending Agreement;
The User or any shareholder (whether direct or indirect) of the User or any other party who may at any time be providing security to The Company pursuant to the requirements of this Construction Agreement as varied by the Amending Agreement takes any action whether by way of proceedings or otherwise designed or calculated to prevent, restrict or interfere with the payment to The Company of any amount so secured whether or not there shall be a dispute between the parties;
Any party who may at any time be providing security to The Company pursuant to the provisions of this Construction Agreement as varied by the Amending Agreement fails to pay to The Company any sum demanded pursuant thereto. 10A.3 If
There is a material adverse change in the financial condition of the User such as to give The Company reasonable grounds for concluding that there is a substantial probability that the User will default in the payment of any sums due or to become due to The Company within the next following period of twelve (12) months in terms of or on termination of this Construction Agreement; or
an event of default has occurred under any banking arrangements (as such may be more particularly described in the Bilateral Connection Agreement) (an event of default being any event described as such in the banking arrangements)] put in place by the User in connection with a project for which security under this Clause 10A is required by The Company and as a result the banks who are party to such banking arrangement have taken steps to declare the principle of the advances under such arrangement immediately due and payable; or
any other indebtedness of the User for the repayment of borrowed money (in a principal outstanding amount of not less than £1,000,000 pounds sterling or such greater amount specified in the Bilateral Connection Agreement) has become due and payable prior to the stated date of maturity thereof by reason of any default or breach on the part of the User and the amount in question has not been paid by the User or refinanced within a period of 28 days following the date upon which it was so declared due and payable and in (i) or (ii) or (iii) the User fails, within a period of 7 (seven) days following the date on which The Company gives the User notice in writing of one or other of the above events occurring to provide The Company with such security as The Company shall require to cover the User’s payment obligations to The Company arising in the event of or which have arisen prior to termination of this Construction Agreement and which arise under this Construction Agreement. The security to be provided shall be in a form satisfactory to The Company in accordance with its then current policy and procedures and in such amount as The Company shall specify to the User in the aforesaid notice. The User shall if required by The Company, in addition to providing the requisite security, within a period of 30 days following the date on which The Company gives the User such notice enter into an Amending Agreement. Such Amending Agreement shall contain such provisions in relation to the User’s obligations to provide and maintain security as shall be consequential upon the requirement for security having arisen and shall be in such form as The Company shall reasonably require in line with The Company’s then current provisions to the like effect in its connection agreements with other parties. Provided that (in relation to paragraphs (i) or (ii) or (iii) above) if at anytime after the putting in place of security under Clause 10A.3 the User shall produce to The Company evidence to The Company’s reasonable satisfaction that there is not a substantial probability of the User not being able to make payment to The Company of such sums within the next following period of twelve (12) months, The Company shall not require the User to provide the aforesaid security and shall release any such security then in place. This waiver is without prejudice to The Company’s right to require security at any time thereafter in the event of any of the circumstances set out in paragraph (i) and/or (ii), and/or
subsequently occurring. 10A.4 Any of the Events of Default in Paragraph 5.3.1 of the CUSC have occurred and are occurring. Or 10B Event of Default Any of the following events shall constitute an Event of Default:- 10B.1 If
an event of default has occurred under any banking arrangements (as such may be more particularly described in the Bilateral Connection Agreement) (an event of default being any event described as such in the banking arrangements) put in place by the User in connection with a project for which security under this Clause 10B is required by The Company and as a result the banks who are party to such banking arrangement have taken steps to declare the principle of the advances under such arrangement immediately due and payable; or
there is a material adverse change in the financial condition of the User such as to give The Company reasonable grounds for concluding that there is a substantial probability that the User will default in the payment of any unsecured sum due or to become due to The Company within the next following period of 12 (twelve) months in terms of or on termination of this Construction Agreement;
any other indebtedness of the User for the repayment of borrowed money (in a principal amount of not less than £1,000,000 pounds sterling or such greater amount specified in the Bilateral Connection Agreement) has become due and payable prior to the stated date of maturity thereof by reason of any default or breach on the part of the User and the amount in question has not been paid by the User or refinanced within a period of 28 days following the date upon which it was so declared due and payable and in either (i) or (ii) or (iii) the User fails:-
1. within a period of 14 (fourteen) days following the date on which The Company gives notice of such circumstances to provide to The Company a cash deposit in a Bank Account, a Performance Bond or Letter of Credit (as defined in Appendix M) in favour of The Company and Valid (as defined in Appendix M) at least up to the last day of the Financial Year in which the event occurs for such amount representing The Company’s reasonable estimate of all unsecured sums to become due to The Company in the period up to t
2. to subsequently provide such cash deposit or renew such Performance Bond or Letter of Credit (or such renewed Performance Bond or Letter of Credit provided under this paragraph) not less than 45 days prior to its stated expiry date for such amount representing The Company’s reasonable estimate of the unsecured sums to become due to The Company in the next following Financial Year valid at least up to the last day of the next following Financial Year and to continue the provision of cash deposit a Performanc
in this Clause 10B.1 subsequently occurring. 10B.2 If the User fails to provide or procure that there is provided to The Company or at any time fails to maintain or procure that there is maintained in full force and effect the relevant security arrangement required under Clauses 9B.1 or 10B.1 of and Appendix M to this Construction Agreement or to renew or revise such security or to substitute any security with the required replacement security or to maintain or procure that there is maintained in full force and effect any such renewed, revised or substituted security as so required or if the User is otherwise in breach of any of its obligations under Appendix M to this Construction Agreement. 10B.3 If the User or any shareholder (whether direct of indirect) of the User takes any action whether by way of proceedings or otherwise designed or calculated to prevent restrict or interfere with the payment to The Company of any amount so secured or seeks or permits or assists others to do so, whether or not there shall be a dispute between the parties. 10B.4 If any party who may at any time be providing or holding security in favour of The Company pursuant to Clauses 9B.1 or 10B.1 of and Appendix M to this Construction Agreement fails to pay The Company any sum demanded in any Notice of Drawing (as defined in Appendix M) pursuant thereto. 10B.5 Any of the Events of Default in Paragraph 5.3.1 of the CUSC have occurred and are occurring.
8 COMPLIANCE WITH SITE SPECIFIC TECHNICAL CONDITIONS The User shall ensure that on the Completion Date the User's Equipment complies with the site specific technical conditions set out in Appendices F1-5 to the Bilateral Connection Agreement.
9 PROVISION OF SECURITY Where required to do so under CUSC Section 15, the User shall provide The Company with security arrangements in accordance with CUSC Section 15 Part Three in respect of the User’s obligations to pay the Cancellation Charge to The Company on termination of this Construction Agreement or a reduction in [Transmission Entry Capacity] [Developer Capacity] prior to the Charging Date.
10 EVENT OF DEFAULT Once any of the Events of Default in Paragraph 5.3.1 and/or Paragraph 5.4.6.2 and/or Paragraph 5.4.6.3 of the CUSC has occurred and is continuing The Company may give notice of termination to the User whereupon this Construction Agreement shall forthwith terminate and the provisions of Clause 11 shall apply.
11 Termination
On termination of this Construction Agreement The Company shall disconnect all the User’s Equipment at the Connection Site and:
the User shall remove any of the User’s Equipment on the Relevant Transmission Licensee's land within 6 months of the date of termination or such longer period as may be agreed between the Relevant Transmission Licensee and the User; and
The Company shall procure that the Relevant Transmission Licensee removes, any Transmission Connection Assets on the User’s land within 6 months of the date of termination or such longer period as may be agreed between the Relevant Transmission Licensee and the User.
The User shall where this Construction Agreement terminates prior to the Charging Date be liable forthwith on the date this Construction Agreement so terminates to pay to The Company the Cancellation Charge such payment to be made within 14 days of the date of The Company’s invoice in respect thereof.
Once an Event of Default pursuant to Clause 10 has occurred and is continuing The Company may give notice of termination to the User whereupon this Construction Agreement shall forthwith terminate and The Company shall disconnect all the User’s Equipment at the Connection Site and:
the User shall remove any of the User’s Equipment on the Relevant Transmission Licensee's land within 6 months of the date of termination or such longer period as may be agreed between the Relevant Transmission Licensee and the User; and
The Company shall procure that the Relevant Transmission Licensee removes, any Transmission Connection Assets on the User’s land within 6 months of the date of termination or such longer period as may be agreed between the Relevant Transmission Licensee and the User.
The User shall (notwithstanding any longer time for payment which but for such termination the User may have for payment pursuant to this Construction Agreement) within 14 days from the date of termination pay to The Company all amounts already due and owing on the date this Construction Agreement so terminates and if this Construction Agreement terminates prior to the Charging Date the User shall be liable forthwith on the date this Construction Agreement so terminates to pay to The Company:-
1. a sum equal to all liabilities arising under Clause 2.4 of this Construction Agreement which have not yet been invoiced by The Company to the User; and
2. a sum equal to The Company’s fair and reasonable estimate of Final Sums, such payments in each case to be made within 14 days of the date of The Company’s invoice(s) in respect thereof subject to adjustment in respect of The Company’s estimate of Final Sums in accordance with Clause 9 A.3.3. or 9B.7.3.
12 Term
Subject to the provisions for earlier termination set out in the CUSC this Construction Agreement shall continue until terminated in accordance with Clause 2.5, 2.6, 4.8, 11 or 17 hereof.
In addition this Construction Agreement shall terminate upon termination of the associated Bilateral Connection Agreement and in the event that this is prior to the Charging Date the User the provisions of Clause 11 shall apply.
The associated [Bilateral Connection Agreements or Agreement to Vary the Bilateral Connection Agreement] will automatically terminate upon termination of this Construction Agreement prior to the Charging Date.
Any provisions for payment shall survive termination of this Construction Agreement.
Subject to the provisions for earlier termination set out in the CUSC this Construction Agreement shall continue until terminated in accordance with Clause 2.5, 2.6, 4.8, 11 or 16 hereof.
In addition this Construction Agreement shall terminate upon termination of the associated Bilateral Connection Agreement and in the event that this is prior to the Charging Date the User shall in addition to the amounts for which it is liable under Clause 2.4 hereof be liable to pay to The Company Final Sums and the provisions of Clause 11 shall apply.
The associated [Bilateral Connection Agreements or Agreement to Vary the Bilateral Connection Agreement] will automatically terminate upon termination of this Construction Agreement prior to the Charging Date.
Any provisions for payment shall survive termination of this Construction Agreement.
CUSC The provisions of Sections 6.6 (Payment), 6.14 (Transfer and Subcontracting),
13 CUSC The provisions of Sections 6.6 (Payment), 6.14 (Transfer and Subcontracting),
14 Disputes
Except as specifically provided for in this Construction Agreement any dispute arising under the terms of this Construction Agreement shall be referred to arbitration in accordance with the Dispute Resolution Procedure.
15 Variations
Subject to Clause 15.2 and 15.3 below, no variation to this Construction Agreement shall be effective unless made in writing and signed by or on behalf of both The Company and the User.
The Company and the User shall effect any amendment required to be made to this Construction Agreement by the Authority as a result of a change in the CUSC, the ESO Licence or the Transmission Licence, an order or direction made pursuant to the Act or a Licence, or as a result of settling any of the terms hereof. The User hereby authorises and instructs The Company to make any such amendment on its behalf and undertakes not to withdraw, qualify or revoke such authority or instruction at any time.
The Company has the right to vary Appendices in accordance with Clauses 2.3, 2.11 and 7.4 and 7.5 and 17 and Paragraph 6.9 of the CUSC. [Users in the capacity of a Directly Connected Distribution System insert the following:
Subject to Clause 15.2 and 15.3 below, no variation to this Construction Agreement shall be effective unless made in writing and signed by or on behalf of both The Company and the User.
The Company and the User shall effect any amendment required to be made to this Construction Agreement by the Authority as a result of a change in the CUSC, the ESO Licence or the Transmission Licence, an order or direction made pursuant to the Act or a Licence, or as a result of settling any of the terms hereof. The User hereby authorises and instructs The Company to make any such amendment on its behalf and undertakes not to withdraw, qualify or revoke such authority or instruction at any time.
The Company has the right to vary Appendices in accordance with Clauses 2.3, 2.11 and 7.4 and 16 and Paragraph 6.9 of the CUSC.
QUEUE MANAGEMENT PROCESS
16 Distributed Generation
In consideration of and recognising the provisions at Clause 16.4 of this Construction Agreement and notwithstanding that the liability for the Cancellation Charge rests with the User, the User will within 5 Business Days of receipt of the same provide the Developer with a copy of the Cancellation Charge Secured Amount Statement.
Where this Construction Agreement is entered into by reference to and provides for the Construction Works required as a consequence of more than one Developer a Cancellation Charge, Cancellation Charge Statement and Cancellation Charge Secured Amount will be prepared by reference to each Developer and the reference to “Cancellation Charge” “Developer” and “Developer Capacity” in this Construction Agreement and CUSC Section 15 shall be construed accordingly.
In the event that the/a Developer reduces its Developer Capacity and/or terminates its agreement for connection to the Distribution System the User shall notify The Company in writing within 5 Business Days of that event.
In the event of a Cancellation Charge Shortfall:
On application by the User in writing (which cannot be made prior to the Shortfall Application Date and without the conditions at Clause 16.5 having been met), The Company shall pay the Cancellation Charge Shortfall to the User together with interest calculated thereon on a daily basis at Base Rate from the date of the payment of the Cancellation Charge to The Company by the User to the date of the payment of the Cancellation Charge Shortfall by The Company to the User.
The User shall keep The Company advised as to any ongoing process to recover the Cancellation Charge Shortfall and any associated interest charges from the Developer and notify The Company when it has reasonable grounds to believe that it is not practicable to take any further action) to recover the Cancellation Charge Shortfall from the Developer.
If at any time the User subsequently successfully recovers the Cancellation Charge Shortfall in full or part from the Developer, the User shall forthwith notify The Company and pay the amount received to The Company together with interest calculated thereon on a daily basis at Base Rate from the date of the payment of the Cancellation Charge Secured Amount to The Company by the User to the date of the payment of the Cancellation Charge Shortfall by the User to The Company.
In order for the User to make an application for payment of a Cancellation Charge Shortfall the following conditions must have been met and evidence of this provided to The Company by the User with the application. i) that the User asked the Developer whether or not it wishes the User to elect for the Fixed Cancellation Charge and elected accordingly; and ii) (in respect of its liability for the Cancellation Charge as it relates to this Contruction Agreement) for each Security Period the User only sought security from the Developer for the amount as set out in the Cancellation Charge Secured Amount Statement for that Security Period]
The Queue Management Process shall be incorporated into this Construction Agreement and apply between The Company and the User and Appendix Q to this Construction Agreement has been prepared in accordance with the principles set out in CUSC Section 16.
Where, in accordance with the Queue Management Process,:
in the case of any of the Conditional Progression Milestones, the status of the User’s project at the end of the Project Milestone Remedy Period is categorised as “Termination”, The Company will terminate this Construction Agreement by notice in writing (such notice being not less than 10 Business Days); and 16.2.2 in the case of any of the Construction Progression Milestones, the status of the User’s project at the end of the Project Milestone Remedy Period is categorised as “Termination” The Company may terminate this Construction Agreement by notice in writing (such notice being not less than 10 Business Days); and 16.2.3 on such termination the User shall in addition to the sums for which it is liable under Clause 2.4 hereof be liable to pay to The Company a sum equal to The Company 's estimate or if applicable revised estimate of Final Sums. The User shall pay such sums within 14 (fourteen) days of the date of The Company 's invoice(s) therefore and (where applicable) on termination The Company shall disconnect the User's Equipment at the Connection Site and;
the User shall remove any of the User's Equipment on the Relevant Transmission Licensee's land within 6 months of the date of termination or such longer period as may be agreed between the Relevant Transmission Licensee and the User; and
The Company shall procure that the Relevant Transmission Licensee removes, any of the Transmission Connection Assets on the User’s land within 6 months of the date of termination or such longer period as may be agreed between the Relevant Transmission Licensee and the User.
Where in accordance with the Queue Management Process there is a variation to the date by which a User Progression Milestone has to be met The Company shall revise Appendix Q to this Construction Agreement as required to reflect such change.
Any dispute or difference between The Company and the User on the Queue Management Process in respect of this Construction Agreement shall be resolved as an Other Dispute under the Dispute Resolution Procedure. [17 Distribution Queue Management3 The User will keep The Company advised as to the categorisation of the Developer’s Project in the Distribution Queue Management Process and notify The Company as soon as practicable if the categorisation of the Developer’s Project is changed to “Termination” and if and when, in accordance with that process, the Distribution Connection Agreements are terminated.] IN WITNESS WHEREOF the hands of the duly authorised representatives of the parties hereto at the date first above written
17 QUEUE MANAGEMENT PROCESS
The Queue Management Process shall be incorporated into this Construction Agreement and apply between The Company and the User and Appendix Q to this Construction Agreement has been prepared in accordance with the principles set out in CUSC Section 16.
Where, in accordance with the Queue Management Process:
in the case of any of the Conditional Progression Milestones, the status of the User’s project at the end of the Project Milestone Remedy Period is categorised as “Termination”, The Company will terminate this Construction Agreement by notice in writing (such notice being not less than 10 Business Days); and 17.2.2 in the case of any of the Construction Progression Milestones, the status of the User’s project at the end of the Project Milestone Remedy Period is categorised as “Termination”, The Company may terminate this Construction Agreement by notice in writing (such notice being not less than 10 Business Days) and on such termination the provisions of Clause 11 of this Construction Agreement shall apply.
Where in accordance with the Queue Management Process there is a variation to the date by which a User Progression Milestone has to be met The Company shall revise Appendix Q to this Construction Agreement as required to reflect such change.
Any dispute or difference between The Company and the User on the Queue Management Process in respect of this Construction Agreement shall be resolved as an Other Dispute under the Dispute Resolution Procedure. [18 Distribution Queue Management 1 The User will keep The Company advised as to the categorisation of the [User’s project/Developer’s Project] in the Distribution Queue Management Process and notify The Company as soon as practicable if the categorisation of the [User’s project/Developer’s Project] is changed to “Termination” and if and when, in accordance with that process, the Distribution Connection Agreements are terminated.] IN WITNESS WHEREOF the hands of the duly authorised representatives of the parties hereto at the date first above written
Only include where Construction Agreement is for a Power Station with a BEGA or for a DNO and associated with Distributed Generation APPENDIX [B]
| Milestone | Date due |
|---|---|
| M1 – Initiate Planning Consent | |
| M2 – Secure Consent | |
| M3 – Land Rights | |
| M5 – Contestable Design Works Submission | |
| M6 – Agree Construction Plan | |
| M7 – Project Commitment | |
| M8 – Initiate Construction |
1. The company registered in England with number 11014226 (“The Company”, which expression shall include its successors and/or permitted assigns); and
2. [] a company registered in [] with number [] whose registered office is at [] (“User”, which expression shall include its successors and/or permitted assigns) WHEREAS
Pursuant to the ESO Licence, The Company has prepared a Connection and Use of System Code (CUSC) setting out the terms of the arrangements for connection to and use of the National Electricity Transmission System and the provision of certain Balancing Services.
The User has applied for [connection to] [and use of] [modification to its connection to] [or use of] the National Electricity Transmission System and pursuant to condition E12 of the ESO Licence, The Company is required to offer terms in accordance with the CUSC in this respect or [specific recital to reflect that the Construction Agreement is an amendment of an existing signed offer pursuant to the CUSC amending documents]
The Company and the User are parties to the CUSC Framework Agreement (being an agreement by which the CUSC is made contractually binding between the parties).
Certain works are required as part of this offer as set out in this Construction Agreement.
This Construction Agreement is entered into pursuant to the terms of the CUSC.
[This Construction Agreement is subject to the Queue Management Process].
This Construction Agrement is a [Gate 1 Agreement] [Gate 2 Agreement]. NOW IT IS HEREBY AGREED as follows:
DEFINITIONS, INTERPRETATION AND CONSTRUCTION Unless the subject matter or context otherwise requires or is inconsistent therewith, terms and expressions defined in Section 11 of the CUSC and in the Bilateral Connection Agreement have the same meanings, interpretations or constructions in this Construction Agreement. "Authority" as defined in the CUSC. “Bilateral Connection Agreement” the Bilateral Connection Agreement entered into between the parties on even date herewith. "Charging Date" the date upon which the Construction Works are first Commissioned and available for use by the User or if the Independent Engineer before, on or after the Commissioning Programme Commencement Date shall have certified in writing that the Transmission Connection Assets, are completed to a stage where The Company could commence commissioning and by such date the User’s Works shall not have been so certified then the date falling [ ] days after the date of such certification, provided that the Transmission Reinforcement Works are Commissioned and Network Options Assessment Works are completed as at that date. In the event that the Transmission Reinforcement Works are not so Commissioned and/or the Network Options Assessment Works are not so completed the Charging Date shall be the date on which they are Commissioned and/or completed as appropriate. “Commissioning Programme the date specified in the Construction Commencement Date” Programme for the commencement of the Commissioning Programme or any substituted date fixed under the terms of this Construction Agreement “Commissioning Programme” the sequence of operations/tests necessary to connect the User’s Works and the Transmission Connection Asset Works to the National Electricity Transmission System for the purpose of making the User's Works available for operation to be determined pursuant to Clause 2.10 of this Construction Agreement. “Completion Date” [ ] or such other date as may be agreed in terms of this Construction Agreement for completion of the Construction Works. “Connected Planning Data” data required pursuant to the Planning Code which replaces data containing estimated values assumed for planning purposes by validated actual values and updated estimates for the future and by updated forecasts for forecast data items. “Consents” in relation to any Works:-
all such planning and other statutory consents; and
all wayleaves, easements, rights over or interests in land or any other consent; or
permission of any kind as shall be necessary for the construction of the Works and for commencement and carrying on of any activity proposed to be undertaken at or from such Works when completed. “Construction Programme” the agreed programme for the Works to be carried out by The Company and the User set out in detail in Appendix [J] to this Construction Agreement or as amended from time to time pursuant to Clauses 2.3 and 3.2 of this Construction Agreement. "Construction Site" the site where the Transmission Connection Asset Works are being undertaken by or on behalf of The Company; “Developer”2 [insert name address and registered number] who is party to the Distribution Connection Agreements with the User “Developer’s Project” the connection of a [ ] to the User's Distribution System “Event of Default” any of the events set out in Clause 10 of this Construction Agreement as constituting an event of default. “Final Sums” the amount payable by the User on termination of this Construction Agreement being the aggregate from time to time and for the time being of:-
1. all The Company Engineering Charges arisen prior to the date of termination;
2. fees, expenses and costs (excluding costs on account of interest charges incurred by The Company) of whatever nature reasonably and properly incurred or due by The Company in respect of any part of the Construction Works carried out prior to the date of termination of this Construction Agreement;
3. fees, expenses and costs properly payable by The Company in respect of, or arising from the termination by it or any third party of any contract for or relating to the carrying out of any Construction Works provided it is negotiated on 2 add where Construction Agreement is with owner/operator of a Distribution System and the Construction Agreement is required because of a developers connection to the Distribution System an arms length basis (including any such arising under the STC);
4. a sum equal to the reasonable costs of removing any Transmission Connection Assets and of making good the remaining Plant and Apparatus following such removal; and
5. interest on any such amounts from the date they were paid by The Company to the date of The Company’s invoice at 2% over Base Rate from time to time and for the time being. Provided that no sum shall be due in respect of Final Sums in respect of fees, expenses and costs associated with (a) the Network Options Assessment Works and/or (b) Transmission Reinforcement Works and specified in Part 2 of Appendix H. Any dispute as to the amount of Final Sums shall be referred to arbitration in accordance with the Di
where the parties fail to agree on a suitable engineer within 120 days of the date of this Construction Agreement; or
where any Independent Engineer appointed from time to time shall fail, refuse or cease to act in the capacity set out herein and no substitute engineer of suitable standing and qualification can be agreed by the parties within 30 days; then such engineer as the President of the Institution of Electrical Engineers shall, on the application of either party, nominate shall be the Independent Engineer. “Installed Capacity” the installed capacity provided in the Original Red Line Boundary and set out in Appendix [O][P]. “Liquidated Damages” the sums specified in or calculated pursuant to Appendix K to this Construction Agreement. “One Off Works” the works described in Appendix B1 to this Construction Agreement. the works set out in the Networks Options Assessment report prepared by The Company pursuant to C13 of the ESO Licence and issued by The Company in [ ] which in The Company’s reasonable opinion are required to be completed before the Completion Date to ensure that the National Electricity Transmission System complies with the requirements of condition E7 of the ESO Licence and Standard Condition D3 of any Relevant Transmission Licensee’s transmission licence prior to the Connection of the User’s Equipment in terms of Clause 7.1 [or 7.2] of this “Network Options Assessment Construction Agreement. Works” [“Reservation Expiry Date” [ ] being the date as bilaterally negotiated between The Company and the User [and which may be extended by agreement between the parties] on which the Reservation expires.- include only in Gate 1 Agreements with Reservation] “Term” the term of this Construction Agreement commencing on the date hereof and ending in accordance with Clause 12. “Third Party Works” the works to be undertaken on assets belonging to a party other than a Revelvant Transmission Licensee and the User to enable The Company to provide or as a consequence of the connection to and\or use of the National Electricity Transmission System by the User as specified in Appendix N; "Transmission Connection the assets specified in Appendix A to the Assets" Bilateral Connection Agreement. “Transmission Connection Asset the works necessary for construction and Works” installation of the Transmission Connection Assets at the Connection Site specified in Appendix G to this Construction Agreement. “Transmission Reinforcement those works other than the Transmission Works” Connection Asset Works, ) Network Options Assessment Works and One Off Works, which in the reasonable opinion of The Company are all necessary to extend or reinforce the National Electricity Transmission System to ensure that the National Electricity Transmission System complies with the requirements of condition E7 of the ESO Licence and Standard Condition D3 of any Relevant Transmission Licensee’s transmission system in relation to and prior to the connection of the User’s Equipment at the Connection Site and which are specified in Appendix H to this Construction Agreement, where Part 1 is works required for the User and Part 2 is works required for wider system reasons. “User Progression Milestones” the milestones (applied in accordance with CUSC Section 16) for the User’s project as set out in Appendix Q of this Construction Agreement. “User’s Works” those works necessary for installation of the User’s Equipment which are specified in Appendix I to this Construction Agreement. “Works” the Construction Works and the User’s Works. [A Gate 1 Agreement with/without Reservation only]
GATED APPLICATION AND OFFER PROCESS – GATE 1 CONDITIONAL CLAUSE [AND RESERVATION]
The rights and obligations of the User and The Company under this Construction Agreement [and the [Bilateral Connection Agreement] are conditional on:
the User making a Gate 2 Application;
the Gate 2 Application meeting the Gate 2 Criteria; and 1.2.1.3 the User accepting the terms of the Gate 2 Offer
The parties agree that until the Gate 2 Date, the rights and obligations of each party pursuant to this Construction Agreement (other than this Clause 1.2 and Clause 13 – and any other provisions that the parties agree are appropriate) and the [Bilateral Connection Agreement] shall be suspended.
[The parties further agree that the information provided for the purposes of this Gate 1 Agreement and set out in the Appendix [O] to this Construction Agreement being a proposed Connection Site, Completion Date and requested [capacity] are indicative only prior to the Gate 2 Date and shall not be binding on the parties or confer any commitment by The Company to the Connection Site, Completion Date or requested [capacity] and any reliance on them for any purpose prior to the Gate 2 Date is at the User’s risk – no reservation] [The parties further agree that the Connection Site and Completion Date and [capacity] as set out in Appendix [O][P] to this Construction Agreement have been Reserved for the purposes of this connection/use of system and any Gate 2 Offer will reflect this position and the requested [capacity] provided that the Gate 2 Application is made prior to the Reservation Expiry Date and the Gate 2 Offer is accepted- reservation only].
At any time prior to the Gate 2 Date, the User shall have the right to terminate this Connection Agreement by written notice to The Company without any liability for any Final Sums. This right to terminate shall expire with effect from the Gate 2 Date.
With effect from the [Gate 2 Date] the provisions of this Construction Agreement, as amended by the [Gate 2 Offer] by agreement of the parties, shall be in full force and effect.
With effect from the [Gate 2 Date] the provisions of this Construction Agreement, as amended by the [Gate 2 Offer] by agreement of the parties, shall be in full force and effect.
DEFINITIONS In this Appendix M, the following terms have the meanings set out next to them:- “Bi-annual Estimate” means an estimate pursuant to Clause [9B.2.1] of this Construction Agreement of all payments to be made or which may be required to be made by the User in any relevant period, such estimate to be substantially in the form set out in Part 2 of this Appendix M; “Bank Account” means a separately designated bank account in the name of The Company at such branch of Barclays Bank PLC, or such branch of any other bank, in the City of London as is notified by The Company to the User, bearing interest from (and including) the date of deposit of principal sums to (but excluding) the date of withdrawal of principal sums from such account, mandated for withdrawal of principal solely by The Company against delivery of a Notice of Drawing for the amount demanded therein and mandated for the transfer of any interest accrued to the Bank Account to such bank account as the User may specify; “Letter of Credit" means an irrevocable standby letter of credit in a form reasonably satisfactory to The Company but in any case expressed to be governed by the Uniform Customs and Practice for Documentary Credits 1993 Revision ICC Publication No. 500 or such other form as may be reasonably satisfactory to The Company and allowing for partial drawings and providing for the payment to The Company on demand forthwith on and against The Company’s delivery to the issuer thereof of a Notice of Drawing of the amount demanded therein; “Notice of Drawing” means a notice of drawing signed by or on behalf of The Company substantially in the form set out in Part 4 of this Appendix M; “Performance Bond” means an on first demand without proof or conditions irrevocable performance bond or performance guarantee executed as a deed in a form reasonably satisfactory to The Company but in any case allowing for partial drawings and providing for the payment to The Company on demand forthwith on and against The Company’s delivery to the issuer thereof of a Notice of Drawing of the amount demanded therein; “Qualified Bank” means a City of London branch of a bank, its successors and assigns, which has throughout the validity period of the Performance Bond or Letter of Credit it issues in favour of The Company, a rating of at least A- in Standard and Poor’s long term debt rating or A3 in Moody’s long term debt rating provided that such bank is not during such validity period put on any credit watch or any similar credit surveillance which gives The Company reasonable cause to doubt that such bank may not be able to maintain the aforesaid rating throughout the validity period and no other event has occurred which gives The Company reasonable cause to have such doubt; “Qualified Company” a company which is a public company or a private company within the meaning of section 1(3) of the Companies Act 1985 and which is either :
a shareholder of the User or any holding company of such shareholder or
any subsidiary of any such holding company, but only where the subsidiary
demonstrates to The Company’s satisfaction that it has power under its constitution to give a Performance Bond other than in respect of its subsidiary;
provides an extract of the minutes of a meeting of its directors recording that the directors have duly concluded that the giving of the Performance Bond is likely to promote the success of that subsidiary for the benefit of its members;
provides certified copies of the authorisation by every holding company of the subsidiary up to and including the holding company of the User, of the giving of the Performance Bond, (the expressions “holding company” and “subsidiary” having the respective meanings assigned thereto by section 736, Companies Act 1985 as supplemented by section 144(3), Companies Act 1989) and which has throughout the validity period of the Performance Bond it gives in favour of The Company, a rating of at least A- in Standard and Poor’s long term debt rating or A3 in Moody’s long term debt rating or such lesser rating which The Company may in its absolute discretion allow by prior written notice given pursuant to a resolution of its board of directors for such period and on such terms as such resolution may specify provided that such company is not during such validity period put on any credit watch or any similar credit surveillance procedure which gives The Company reasonable cause to doubt that such company may not be able to maintain the aforesaid rating throughout the validity period of the Performance Bond and no other event has occurred which gives The Company reasonable cause to have such doubt; “Secured Amount means a statement accompanying the Bi-annual Statement” Estimate setting out the amount of the User’s Obligation based on figures contained in the Bi- annual Estimate being the amount for which security shall be provided to The Company pursuant to Clause 9B of this Construction Agreement; “User’s Obligation” means the User’s obligation to pay under this Construction Agreement:-
all amounts in respect of which the User has a liability to pay to The Company pursuant to Clause 2.4 of this Construction Agreement Agreement;
Final Sum “Valid" means valid for payment to be made thereunder against delivery of a Notice of Drawing given within the period stated therein.
SECURITY REQUIREMENT The User’s Obligation shall be secured by any one of the following:-
The Company Engineering Charges & expenses for obtaining Consents pursuant to to Clause 2.4
Final Sums [3. One Off Charge] PART 3
| Milestone | Date due |
|---|---|
| M1 – Initiate Planning Consent | |
| M2 – Secure Consent | |
| M3 – Land Rights | |
| M5 – Contestable Design Works Submission | |
| M6 – Agree Construction Plan | |
| M7 – Project Commitment | |
| M8 – Initiate Construction |
Schedule 2 Exhibit 3A
1. The company registered in England with number 11014226 (“The Company”, which expression shall include its successors and/or permitted assigns); and
2. [] a company registered in [] with number [] whose registered office is at [] (“User”, which expression shall include its successors and/or permitted assigns) WHEREAS
Pursuant to the ESO Licence, The Company has prepared a Connection and Use of System Code (CUSC) setting out the terms of the arrangements for connection to and use of the National Electricity Transmission System and the provision of certain Balancing Services.
The User has applied for [connection to and use of] [modification to its connection to] the National Electricity Transmission System and pursuant to condition E12 of the ESO Licence, The Company is required to offer terms in accordance with the CUSC in this respect.
The Company and the User are parties to the CUSC Framework Agreement (being an agreement by which the CUSC is made contractually binding between the parties).
Certain works are required as part of this offer as set out in this Construction Agreement.
This Construction Agreement sets out the Offshore Works Assumptions used to identify the initial Onshore Construction Works and Construction Programme and the process whereby this Construction Agreement [will be amended to provide for the Offshore Construction Works] [may be varied in case of changes to such assumptions].
This Construction Agreement is entered into pursuant to the terms of the CUSC.
The Queue Management Process applies to this Construction Agreement.
This is a [Gate 1 Agreement] [Gate 2 Agreement]. NOW IT IS HEREBY AGREED as follows:
DEFINITIONS, INTERPRETATION AND CONSTRUCTION Unless the subject matter or context otherwise requires or is inconsistent therewith, terms and expressions defined in Section 11 of the CUSC and in the Bilateral Connection Agreement have the same meanings, interpretations or constructions in this Construction Agreement. "Authority" as defined in the CUSC. “Assumed Offshore Tender insert date of Offshore Tender Process it Process Start Date” is assumed User will enter. “Attributable Works” those Construction Works identified as such in accordance with the User Commitment Methodology and which are set out in Appendix MM Part 1. “Bilateral Connection the Bilateral Connection Agreement Agreement” entered into between the parties on even date herewith. “Cancellation Charge” as calculated in accordance with the User Commitment Methodology. "Charging Date" the date upon which the Construction Works (excluding the Wider Transmission Reinforcement Works are first Commissioned and available for use by the User or if the Independent Engineer before, on or after the Commissioning Programme Commencement Date shall have certified in writing that the [Transmission Connection Assets] [Transmission Plant and Transmission Apparatus at the Transmission Interface Point1] are completed to a stage where The Company could commence commissioning and by such date the User’s Works shall not have been so certified then the date falling [ ] days after the date of such certification, provided that the Offshore
Use where OTSDUW build Transmission Reinforcement Works and2] the Enabling Works are Commissioned and Network Options Assessment Works are completed as at that date. In the event that the Offshore Transmission Reinforcement Works and3 the Enabling Works are not so Commissioned and/or the Network Options Assessment Works are not so completed the Charging Date shall be the date on which they are Commissioned and/or completed as appropriate. “Commissioning Programme the date specified in the Construction Commencement Date” Programme for the commencement of the Commissioning Programme or any substituted date fixed under the terms of this Construction Agreement “Commissioning Programme” the sequence of operations/tests necessary to connect the User’s Works and the [Transmission Connection Asset Works] [Transmission Plant and Transmission Apparatus at the Transmission Interface Point4] to the National Electricity Transmission System for the purpose of making the User's Works available for operation to be determined pursuant to Clause 2.10 of this Construction Agreement. “Completion Date” [ ] or such other date as may be agreed in terms of this Construction Agreement. “Connect and Manage the temporary derogation from the NETS Derogation” SQSS available to The Company under condition E7 of the ESO Licence and/or the Relevant Transmission Licensee under Standard Condition D3 of its transmission licence; “Connected Planning Data” data required pursuant to the Planning Code which replaces data containing estimated values assumed for planning
2 Delete where OTSDUW Build
Forthwith following the date of [the Offshore Agreement to Vary] [this Construction Agreement] the User shall agree with the [Relevant Transmission Licensee] [Onshore Transmission Licensee] the Safety Rules and Local Safety Instructions to apply at the [Connection Site] [Transmission Interface Site] during the Construction Programme and Commissioning Programme [and until the OTSUA Transfer Time]. Failing agreement within three months of such date the matter shall be referred to the Independent Engineer for determination in accordance with Clause 6 of the Construction Agreement.
Subject to Clauses 2.3 and 2.4 of this Construction Agreement forthwith following the date of [the Offshore Agreement to Vary] [this Construction Agreement] The Company shall use its best endeavours to obtain in relation to the Construction Works, excluding the Wider Transmission Reinforcement Works and the User shall use its best endeavours to obtain in relation to the User's Works, all Consents. Each shall give advice and assistance to the other to the extent reasonably required by the other in the furtherance of these obligations. Further, the User and the [Relevant Transmission Licensee] [Onshore Transmission Licensee] shall, so far as it is legally able to do so, grant to, the other in respect of the [Connection Site] [Transmission Interface Site] all such wayleaves, easements, servitude rights, rights over or interests in land or any other consents reasonably required by the User or [Relevant Transmission Licensee] [Onshore Transmission Licensee] in order to enable the Works excluding the Wider Transmission Reinforcement Works to be expeditiously completed and to enable that other to carry out its obligations to the other under this Construction Agreement and in all cases subject to such terms and conditions as are reasonable.
The following additional provisions shall apply in respect of the Consents and Construction Works [and OTSDUW] excluding the Wider Transmission Reinforcement Works:-
All dates specified in this Construction Agreement are subject to The Company obtaining Consents for the Construction Works in a form acceptable to it within the time required to carry out the Construction Works excluding the Wider Transmission Reinforcement Works [and the User obtaining Consents for the OTSDUW]in accordance with the Construction Programme.
In the event of:-
the Consents not being obtained by the required date; or
the Consents being subject to conditions which affect the dates; or
The Company wishing to amend the Construction Works excluding the Wider Transmission Reinforcement Works [or the User wishing to amend OTSDUW] to facilitate the granting of the Consents, then, in the case of Construction Works and Consents therefor, The Company shall be entitled to revise the Construction Works (and as a consequence Appendix A to the Bilateral Connection Agreement) and all dates specified in this Construction Agreement in relation to those Construction Works and the charges specified in Appendix B to the Bilateral Connection Agreement. For the avoidance of doubt such revisions shall be at The Company's absolute discretion and the consent of the User is not required. [In the case of OTSDUW and Consents therefore, the User shall be entitled to revise the OTSDUW (including any changes to the Offshore Works Assumptions) and the dates specified in this Construction Agreement in relation to OTSDUW, in which case the User shall propose such revisions to The Company and the parties shall (without prejudice to paragraph 6.9.2) agree such amendments to this Construction Agreement as are necessary to reflect such revisions. The parties acknowledge that any dispute regarding such amendments shall be referable to and determined by the Authority under the provisions of condition E13.5 of the ESO Licence, and where such application is made, the parties shall take into account any determination or other direction from the Authority.]
The User shall be regularly updated by The Company in writing or by such other means as the parties may agree as to progress made by The Company from time to time in the obtaining of relevant Consents pursuant to its obligations under Clause 2.2 or 2.3 of this Construction Agreement.
[The Company shall be regularly updated by the User in writing or by such other means as the parties may agree as to progress made by the User from time to time in the obtaining of relevant Consents for the OTSDUW pursuant to its obligations under Clause 2.2 or 2.3 of this Construction Agreement.]
Paragraphs 11.2.3 to 11.2.5 of the CUSC relating to Consents shall apply to the Construction Agreement as if set out here in full.
Prior to the commencement of the Transmission Connection Asset Works [Onshore Transmission Reinforcement Works or any One Off Works] the User shall have the right to terminate this Construction Agreement upon giving not less than 7 (seven) days notice in writing to The Company. In the event of the User terminating this Construction Agreement in terms of this Clause 2.5 the provisions of Clause 11 shall apply.
If the User fails to obtain all Consents for the User's Works having complied with the obligations in Clause 2.2 of this Construction Agreement the obligation on the User to complete the User's Works shall cease and the User may by written notice to The Company terminate this Construction Agreement. In the event of the User terminating this Construction Agreement in terms of this Clause 2.6 the provisions of Clause 11 shall apply
Both parties shall be entitled to contract or sub-contract for the carrying out of their respective parts of the Works excluding the Wider Transmission Reinforcement Works (which in the case of The Company shall include work carried out by a Relevant Transmission Licensee or its contractors or sub- contractors). The User or any contractor on its behalf shall be responsible for commencing and for carrying out the User's Works to such stage of completion as shall render them capable of being Commissioned in accordance with the Construction Programme and The Company or any contractor on its behalf shall be responsible for commencing and carrying out the Construction Works excluding the Wider Transmission Reinforcement Works to such stage of completion as shall render them capable of being Commissioned in accordance with the Construction Programme.
The parties shall continuously liaise throughout the Construction Programme and Commissioning Programme and each shall provide to the other all information relating to its own Works reasonably necessary to assist the other in performance of that other’s part of the Works, [and where the User is undertaking OTSDUW such additional information as The Company shall require in order to perform its obligations under the STC provided that The Company shall not request information greater in scope than that which The Company would be entitled to receive from a Relevant Transmission Licensee were it undertaking the OTSDUW,] and shall use all reasonable endeavours to coordinate and integrate their respective part of the Works. There shall be meetings between representatives of the parties at intervals to be agreed between the parties. Each party shall deliver to the other party a written report of progress during each calendar quarter within 7 days of the end of that quarter.
During the period of and at the times and otherwise as provided in the Construction Programme and the Commissioning Programme The Company shall allow the User, its employees, agents, suppliers, contractors and sub-contractors necessary access to the [Construction Site] [Transmission Interface Site] and the User shall allow the Relevant Transmission Licensee and in either case their employees, agents, suppliers, contractors and sub-contractors necessary access to its site to enable each to carry out the [Transmission Connection Asset Works [Onshore Transmission Reinforcement Works or any One Off Works] or User's Works but not so as to disrupt or delay the construction and completion of the other’s Works on the said sites or the operation of the other’s Plant and Apparatus located thereon, such access to be in accordance with any reasonable regulations relating thereto made by the site owner or occupier.
Not later than six months prior to the Commissioning Programme Commencement Date The Company shall provide the User with a draft Commissioning Programme for the Commissioning of the [Transmission Connection Assets] [OTSUA], and the User's Equipment. The User shall, as quickly as practicable and in any event within three months of receipt thereof, determine whether or not to approve the proposed Commissioning Programme (which approval shall not be unreasonably withheld or delayed) and shall within such three month period either notify The Company of its approval or, in the event that the User reasonably withholds its approval, notify The Company of any changes or variations to the proposed commissioning programme recommended by the User. If The Company does not accept such changes or variations submitted by the User any dispute shall be referred to the Independent Engineer for determination. The Commissioning Programme agreed between the parties or determined by the Independent Engineer as the case may be shall be implemented by the parties and their sub-contractors in accordance with its terms.
If at any time prior to the Completion Date it is necessary for The Company or The Company in its reasonable discretion wishes to make any addition to or omission from or amendment to the [Transmission Connection Asset Works and/or] Transmission Reinforcement Works and/or the One Off Works and/or the Third Party Works The Company shall notify the User in writing of such addition, omission or amendment and Appendices [B1 (One Off Works), [G (Transmission Connection Asset Works)] H (Transmission Reinforcement Works), MM (Attributable Works) and N (Third Party Works)] to this Construction Agreement and consequently Appendices [A (Transmission Connection Assets) and B (Connection Charges and One Off Charges)] to the associated Bilateral Connection Agreement shall be automatically amended to reflect the change. Provided that where a User has elected for the Local Cancellation Amount to be based on the Fixed Local Cancellation Charge Methodology the Attributable Works can only be changed after the Trigger Date as provided for in CUSC Section 15. [If at any time prior to the Completion Date it is necessary for the User or the User in its reasonable discretion wishes to make any addition to or omission from or amendment to the OTSDUW (including any changes to the Offshore Works Assumptions), the User shall propose such revision to The Company and the parties shall (without prejudice to paragraph 6.9.2) agree changes to this Construction Agreement as are necessary to reflect such revision. The parties acknowledge that any dispute regarding such amendments shall be referable to and determined by the Authority under the provisions of condition E13.5 of the ESO Licence, and where such application is made, the parties shall take into account any determination or other direction from the Authority.]
The User shall apply to the Secretary of State for Trade and Industry as part of its application under Section 36 of the Act for its generating station, for deemed planning permission in relation to the substation forming part of the Transmission Connection Asset Works. The User shall use its best endeavours to procure that the said deemed planning permission is so obtained. The Company's obligations under Clause 2.2 of this Construction Agreement shall not require it to obtain planning consent for the said substation unless and until the relevant Secretary of State shall for whatever reason refuse to deem the grant of planning permission in respect of the same. The User shall liaise with The Company as to its construction and operational requirements and shall ensure that the said application meets The Company's requirements. The Company shall provide the User with all information reasonably required by it in relation to the application and the User shall ensure that all requirements of The Company are incorporated in the application for deemed planning consent.
[The Enabling Works are conditional on British Energy Generation Limited and/or Magnox Electric plc (as the case may be)granting approval to the carrying out of the Construction Works in terms of the Nuclear Site Licence Provisions Agreement being an agreement dated 30 March 1990 between The Company and Nuclear Electric plc (now called Magnox Electric plc) and an agreement dated 31 March 1996 between The Company and British Energy Generation Limited (and described as such). In the event of British Energy Generation Limited and/or Magnox Electric plc (as the case may be) not granting approval The Company shall be entitled to change the Construction Works, the Construction Programme and all dates specified in this Construction Agreement.]
[It is hereby agreed and declared for the purposes of the Construction (Design and Management) Regulations 1994 that the User is the only client in respect of the User's Works and The Company is the only client in respect of the Construction Works and each of the User and The Company shall accordingly discharge all the duties of clients under the said Regulations.]
[The Company and the User hereby agree and acknowledge that this Construction Agreement is not to be treated as a construction contract within the meaning of section 104 of the Housing Grants, Construction and Re- generation Act 1996 and sections 104 to 113 of the said Act shall have no application either to the Construction Works or the User's Works and the parties’ rights and obligations with regard to matters of dispute resolution and payment procedures are as expressly set out herein.
Third Party Works
The User shall be responsible for carrying out or procuring that the Third Party Works are carried out and shall carry them out or procure that they are carried out in accordance with the timescales specified in the Construction Programme. The User shall confirm to The Company or, where requested to do so by The Company, provide confirmation from the third party that the Third Party Works have been completed.
Given the nature of these works it may not be possible to fully identify the works required or the third parties they relate to at the date hereof. Where this is the case The Company shall, subject to 2.x.3 below, advise the User as soon as practicable and in any event by [ ] of the Third Party Works and shall be entitled to revise Appendix N and as a consequence the Construction Programme as necessary to reflect this. [2.16.3 Where Third Party Works are likely to be Modifications required to be made by another user(s) (“the “First User(s)”) as a consequence of Modifications to the National Electricity Transmission System to be undertaken by The Company under this Construction Agreement The Company shall as soon as practicable after the date hereof issue the notification to such First User’s in accordance with CUSC Paragraph 6.9.3.1. The User should note its obligations under CUSC Paragraph 6.10.3 in respect of the costs of any Modifications required by the First User(s).]
In the event that the Third Party Works have not been completed by the date specified in the Construction Programme or, in The Company’s reasonable opinion are unlikely to be completed by such date, The Company shall be entitled to revise the Construction Programme as necessary to reflect such delay and also, where The Company considers it necessary to do so, shall be entitled to revise the Construction Works excluding the Wider Transmission Reinforcement Works (and as a consequence Appendices A and B to the Bilateral Connection Agreement). For the avoidance of doubt such revisions shall be at The Company's absolute discretion and the consent of the User is not required. Further, in the event that the Third Party Works have not been completed by [ ] The Company shall have the right to terminate this Construction Agreement upon giving notice in writing to the User and in this event the provisions of Clause 11 of this Construction Agreement shall apply.
Not later than 6 months prior to the Completion Date or such other period as the parties shall agree the User shall enter into the Interface Agreement with the Relevant Transmission Licensee to reflect the Works excluding the Wider Transmission Reinforcement Works14]. [Not later than 6 months prior to the Completion Date or such other period as the parties shall agree the
In the event that there are any [material] changes to the Offshore Works Assumptions] The Company shall be entitled to revise the Construction Works excluding the Wider Transmission Reinforcement Works and Construction Programme and as a consequence Appendices A, B, C and F3 to F5 in the Bilateral Connection Agreement as necessary to reflect such change. The Company shall notify the User as soon as practicable upon it becoming aware that it may need to exercise its rights under this Clause and provide the User with an indication of the nature and scope of the changes required and the reasons for the same.
The Company shall keep the User advised as to progress on the Wider Transmission Reinforcement Works and shall include information on these in the reports produced pursuant to Clause 2.8.
3 Delete where OTSDUW Build
If either party shall have reason to believe that it is being delayed or will be delayed in carrying out that party’s Works excluding the Wider Transmission Reinforcement Works for any reason (whether it is one entitling it to the fixing of a new date under Clause 3.2 of this Construction Agreement or not) it shall forthwith notify the other party in writing of the circumstances giving rise to the delay and of the extent of the actual and/or anticipated delay.
If prior to the Completion Date a party (in this Clause 3.2 “the Affected Party”) shall be delayed in carrying out any of the Affected Party’s Works (including their commissioning) by reason of any act, default or omission on the part of the other Party (in this Clause the “Defaulting Party”) or the Defaulting Party’s employees, agents, contractors or sub-contractors or by reason of an event of Force Majeure, the Affected Party shall be entitled to have such later date or dates fixed as the Commissioning Programme Commencement Date and/or (as the case may be) the Completion Date as may be fair and reasonable in the circumstances provided that it shall have notified the Defaulting Party in writing of such act, default or omission or event of Force Majeure within 28 days of it becoming aware of the occurrence giving rise to the delay together with an estimate of the proposed delay which it will cause the Affected Party. In the event of a dispute between the parties over what is or are any fair and reasonable new date or dates to be fixed in the circumstances this shall be promptly referred to and determined by the Independent Engineer. Once the new date or dates are fixed the Construction Programme and/or Commissioning Programme shall be deemed automatically amended as appropriate.
4 Use where OTSDUW Build purposes by validated actual values and updated estimates for the future and by updated forecasts for forecast data items. “Connection Site Specification” a specification which sets out the following information in relation to the Connection Site:
a description of those OTSUA that are to be classed as Transmission Connection Assets in accordance with the Statement of the Connection Charging Methodology;
a clear identification of the boundary between the OTSUA and the User’s Equipment (ascertained in the absence of agreement to the contrary with the Relevant Transmission Licensee by reference to CUSC Paragraph 2.12.1);
information reasonably requested by The Company in order to complete Appendices F1 to F5 in the Bilateral Connection Agreement; and
a description of the technical design and operating criteria which apply to the User’s Equipment. “Consents” in relation to any Works:-
all such planning and other statutory consents; and
all wayleaves, easements, rights over or interests in land or any other consent; or
permission of any kind as shall be necessary for the construction of the Works and for commencement and carrying on of any activity proposed to be undertaken at or from such Works when completed. “Construction Programme” the agreed programme for the Works (excluding the Wider Transmission Reinforcement Works to be carried out by or on behalf of The Company and the User set out in detail in Appendix [J] to this Construction Agreement or as amended from time to time pursuant to Clauses 2.3 and 3.2 of this Construction Agreement. "Construction Site"5 the site where the Transmission Connection Asset Works are being undertaken by or on behalf of The Company; “Construction Works” the [Offshore Construction Works and6] Onshore Construction Works but excluding for the avoidance of doubt any Third Party Works "Dispute Resolution Procedure” the procedure for referral to arbitration set out in Paragraph 7.4 of the CUSC. “Enabling Works” Those Onshore Transmission Reinforcement Works which are specified in Appendix H1 Part 1 to this Construction Agreement. “Event of Default” any of the events set out in Clause 10 of this Construction Agreement as constituting an event of default. “Gate 2 Date” means [the date on which the last of the conditions at Clause 1.2A of this Construction Agreement are satisfied - include only in Gate 1 Agreements with Reservation] “Independent Engineer” the engineer specified in Appendix L to this Construction Agreement. Provided that:-
where the parties fail to agree on a suitable engineer within 120 days of the date of this Construction Agreement; or
where any Independent Engineer appointed from time to time shall fail, refuse or cease to act in the capacity set out herein and no substitute engineer of suitable standing and qualification can be agreed by the parties within 30 days; then such engineer as the President of the Institution of Electrical Engineers shall, on
Each party shall give written notice to the other declaring its readiness to commence the Commissioning Programme when this is the case.
The Commissioning Programme shall commence forthwith once both parties have given written notice to the other under Clause 4.1.
The Works excluding the Wider Transmission Reinforcement Works shall be deemed to have been Commissioned on the date that the Independent Engineer certifies in writing to that effect.
In the event that the actual date of commencement of the Commissioning Programme is later than the Commissioning Programme Commencement Date The Company (if and to the extent that it is responsible for delayed commissioning beyond the Commissioning Programme Commencement Date, such responsibility and/or its extent to be determined by the Independent Engineer failing agreement between the parties) shall be liable to pay to the User Liquidated Damages for each day that the actual date of commencement of the Commissioning Programme is later than the Commissioning Programme Commencement Date. It is declared and agreed that such Liquidated Damages shall cease to be payable in respect of any period after the date of actual commencement of the Commissioning Programme.
In the event that the actual date on which the Construction Works are Commissioned is later than the Completion Date The Company (if and to the extent that it is responsible for delayed completion beyond the Completion Date, such responsibility and/or its extent to be determined by the Independent Engineer failing agreement between the parties) shall be liable to pay to the User Liquidated Damages for each day that the actual date on which the Construction Works are Commissioned is later than the Completion Date. It is hereby agreed and declared that such Liquidated Damages shall cease to be payable in respect of any period after completion of the Construction Works.
Liquidated Damages payable under Clauses 4.4 and 4.5 of this Construction Agreement shall accumulate on a daily basis but shall be payable calendar monthly. On or before the 15th day of each month the party entitled to receive the payment of Liquidated Damages shall send to the other party a statement of the Liquidated Damages which have accrued due in the previous calendar month. The party receiving such statement shall in the absence of manifest error pay the Liquidated Damages shown on the statement within 28 days of the date upon which the statement is received.
Without prejudice to and in addition to the obligation of the User pursuant to Clause 2.4 of this Construction Agreement, the payment or allowance of Liquidated Damages pursuant to this Clause 4 shall be in full satisfaction of The Company's liability for failure to perform its obligations by the Commissioning Programme Commencement Date and/or the Completion Date as appropriate.
In the event that the User shall have failed, in circumstances not entitling it to the fixing of a new date as the Commissioning Programme Commencement Date pursuant to Clause 3.2, to complete the User's Works by [ ] to a stage where the User is ready to commence the Commissioning Programme, The Company shall have the right to terminate this Construction Agreement upon giving notice in writing to the User and the provisions of Clause 11 shall apply.
5 Delete where OTSDUW Build
Not later than 4 months prior to the expected Commissioning Programme Commencement Date or by such other time as may be agreed between the parties the parties shall prepare and submit the Operation Diagrams required to be prepared and submitted by each of them respectively under CC 7.4.7 and 7.4.10 and likewise the Site Common Drawings required under CC 7.5.2 and 7.5.4 and, if necessary, Gas Zone Diagrams referred to in CC 7.4.9 and 7.4.12.
Not later than 3 months prior to the expected Commissioning Programme Commencement Date or by such other time as may be agreed between the parties the parties shall prepare and submit the Operation Diagrams required to be prepared and submitted by each of them respectively under CC 7.4.8 and 7.4.11 and likewise the Site Common Drawings required under CC 7.5.3 and 7.5.5.
Not later than 3 months prior to the expected Commissioning Programme Commencement Date or by such other time as may be agreed between the parties:- 5.3.1 each party shall submit to the other data within its possession needed to enable the completion of Appendices F3 and F4 to the Bilateral Connection Agreement; and 5.3.2 the User shall submit to The Company evidence satisfactory to The Company that the User's Equipment [and OTSUA] complies or will on completion of the User's Works comply with Clause 8 of this Construction Agreement and Paragraphs 1.3.3(b), 2.9 and 6.7 of the CUSC.
Not later than 8 weeks prior to the expected Commissioning Programme Commencement Date or by such other time as may be agreed between the parties each party shall submit to the other:
for the Connection Site information to enable preparation of Site Responsibility Schedules complying with the provisions of Appendix 1 to the Connection Conditions together with a list of managers who have been duly authorised by the User to sign such Site Responsibility Schedules on the User's behalf;
written confirmation as required under CC.5.2(g) that the list of Safety Co-ordinators are authorised and competent [and a list of persons appointed pursuant to Grid Code CC5.2(m)];
a list of the telephone numbers for the facsimile machines referred to in CC6.5.9.
Confirmation of access to the Electronic Communications Platform referred to in CC6.5.9 upon access being provided by The Company
[For the Transmission Interface Site information to enable preparation of Site Responsibility Schedules between the User and the Onshore Transmission Licensee for the period up to the OTSUA Transfer Time and between the Onshore Transmission Licensee and Relevant Transmission Licensee for the period from the OTSUA Transfer Time complying with the provisions of Appendix 1 to the Connection Conditions16].
Not later than 3 months prior to the expected Commissioning Programme Commencement Date each party shall submit to the other a statement of readiness to complete the Commissioning Programme in respect of the Works excluding the Wider Transmission Reinforcement Works and the statement submitted by the User shall in addition contain relevant Connected Planning Data and a report certifying to The Company that, to the best of the information, knowledge and belief of the User, all relevant Connection Conditions applicable to the User have been considered and complied with. If The Company considers that it is necessary, it will require this latter report to be prepared by the Independent Engineer. The report shall incorporate if requested by The Company type test reports and test certificates produced by the manufacturer showing that the User's Equipment meets the criteria specified in CC6.
6 Delete where OTSDUW Build the application of either party, nominate shall be the Independent Engineer. “Installed Capacity” the installed capacity provided in the Original Red Line Boundary and set out in Appendix [P]. “Interface Agreement” the agreement substantially in the form of CUSC Exhibit O [Part IC or Part IIC] to be entered into pursuant to Clause 2.17. “Key Consents” those Consents required in respect of the [User’s/Developer’s] Power Station which The Company has identified as such and which are
(Confidentiality), 6.18 (Intellectual Property), 6.19 (Force Majeure), 6.24 (Counterparts), 6.20 (Waiver), 6.21 (Notices), 6.22 (Third party Rights), 6.23 (Jurisdiction), 6.25 (Governing Law), 6.26 (Severance of Terms), 6.27 (Language), 6.38 (Directions related to national security),inclusive of the CUSC shall apply mutatis mutandis to this Construction Agreement as if set out in this Construction Agreement.
DISPUTES Except as specifically provided for in this Construction Agreement any dispute arising under the terms of this Construction Agreement shall be referred to arbitration in accordance with the Dispute Resolution Procedure.
7 Delete if OTSDUW Build “Offshore TO Construction the offer to be made to The Company in Offer8” respect of the Offshore Construction Works pursuant to the System Operator – Transmission Owner Code. “Offshore Transmission those works other than the Transmission Reinforcement Works9 Connection Asset Works, Onshore Transmission Reinforcement Works, Network Options Assessment Works and One Off Works, which in the reasonable opinion of The Company are necessary to extend or reinforce the National Electricity Tra
The Company shall connect and Energise the User's Equipment at the Connection Site [and the OTSUA at the Transmission Interface Site ] during the course of and in accordance with the Commissioning Programme and thereafter upon compliance by the User with the provisions of Clause 5 and provided (1) the Construction Works excluding the Wider Transmission Reinforcement Works and Network Options Assessment Works [and the OTSDUW] shall be Commissioned and (2) the Network Options Assessment Works and Third Party Works shall be completed. The Company shall forthwith notify the User in writing that the Connection Site [Transmission Interface Site17] shall become Operational. [7.2 If, on completion of the User's Works in accordance with the terms of this Construction Agreement the Registered Capacity of the User's Equipment is less than [ ]MW, The Company shall automatically have the right to amend Clause 7 and Appendix C to the Bilateral Connection Agreement to reflect the actual Registered Capacity of the User's Equipment. Users in the capacity of a Directly Connected Power Station or Embedded Power Station (other than those who are a BELLA) insert the following.
Transmission Entry Capacity Reduction
If, at any time prior to the Completion Date The Company reasonably believes from data provided by the User to The Company, the reports provided by the User pursuant to Clause 2.8. and Clause 5 of this Construction Agreement, the commissioning process under the Construction Agreement or otherwise that the User’s Equipment will be such that it will not be capable of exporting power onto the National Electricity Transmission System at the level of the Transmission Entry Capacity The Company shall advise the User accordingly in writing setting out its reasons for this belief, the source of the information giving rise to the concern and seeking clarification from the User.
The User shall respond to The Company within 15 Business Days of the date of the Preliminary Request providing such information or data as is necessary to satisfy The Company’s concerns set out in the Preliminary Request and making any amendments necessary to the report provided by the User pursuant to Clause 2.8 and/or data provided by the User to The Company to reflect this.
In the event that The Company is satisfied from the information provided in accordance with 7.3.2 by the User that the User’s Equipment is such that it will be capable of exporting power onto the National Electricity 17 Use OTSDUW Build Transmission System at the level of the Transmission Entry Capacity The Company shall notify the User accordingly.
In the event that the User does not respond to the Preliminary Request or, notwithstanding the User’s response, The Company remains of the view that the User’s Equipment will be such that it will not reasonably be capable of exporting power onto the National Electricity Transmission System at the level of the Transmission Entry Capacity The Company shall inform the User in writing that it intends to amend Clause 7 and Appendix C to the Bilateral Connection Agreement to reflect the Transmission Entry Capacity that it reasonably believes to be the level of power that the User's Equipment will be capable of exporting .
The User shall respond to the Notice of Intent within 15 Business Days of the date of the Notice of Intent explaining why it still reasonably believes that its User's Equipment will be capable of exporting power onto the National Electricity Transmission System at the level of the Transmission Entry Capacity or at more than the MW figure proposed by The Company in the Notice of Intent or providing a reasonable explanation as to why this is not the case.
In the event that The Company is satisfied from the information provided in accordance with 7.3.5 by the User that the User’s Equipment is such that it will be capable of exporting power onto the National Electricity Transmission System up to the level of the Transmission Entry Capacity The Company shall notify the User accordingly.
Where notwithstanding the User’s response to the Notice of Intent The Company remains of the view that the User’s Equipment is such that it will not reasonably be capable of exporting power onto the National Electricity Transmission System at the level of the Transmission Entry Capacity or at more than the MW figure proposed by The Company in the Notice of Intent or the User does not provide a response that is satisfactory to The Company within the timescale specified in 7.3.5 above The Company will issue the Notice of Reduction to the User and will send a copy of the same to the Authority.
Unless during such period the matter has been referred by the User to the Authority for determination by the Authority under the provisions of condition E13.5 of the ESO Licence, the Notice of Reduction shall take effect on the day 15 Business Days after the date of the Notice of Reduction and Appendix C of the Bilateral Connection Agreement shall be amended on that date in the manner set out in the Notice of Reduction. Where the matter has been referred the amendments of the Bilateral Connection Agreement and the date they take effect shall be as set out in the Authority’s determination
After a Notice of Reduction has taken effect The Company shall be entitled to make such amendments to this Construction Agreement as are reasonably necessary as a result of the reduction in Transmission Entry Capacity effected by the Notice of Reduction and as a consequence to the Bilateral Connection Agreement. The Company shall advise the User as soon as practicable and in any event within 3 months of the date of the Notice of Reduction (or if the matter has been referred by the User to the Authority for determination, the date of determination) of such amendments by way of offer of an agreement to vary the Construction Agreement and Bilateral Connection Agreement. This agreement to vary will also provide for payment by the User of the Reduction Fee where applicable. The parties acknowledge that any dispute regarding this variation shall be referable to and determined by the Authority under the provisions of condition E13.5 of the ESO Licence.
Compliance with Original Red Line Boundary -add only where it’s a Gated Agreement If a User is not compliant at a User Progression Milestone with the Original Red Line Boundary (other than as it may be changed under the Queue Management Guidance) for one or more technologies, The Company shall be entitled to amend the Construction Agreement and as a consequence the Bilateral Connection Agreement to:
reduce the Installed Capacity (of each technology that is non- compliant).
remove that technology if the Installed Capacity of a technology is reduced to 0 MW. reduce the [Transmission Entry Capacity] if the sum of the Installed Capacity [of all technologies] is reduced such that it is less than the [Transmission Entry Capacity] and such that the [Transmission Entry Capacity] is no higher than the sum of the Installed Capacity [of all technologies.]
Where there is a reduction in Transmission Entry Capacity under Clause 7.3 or 7.4 prior to the Charging Date, on such reduction in Transmission Entry Capacity taking effect the User the User shall pay to The Company the Cancellation Charge such payment to be made within 14 days of the date of The Company’s invoice in respect thereof.
COMPLIANCE WITH SITE SPECIFIC TECHNICAL CONDITIONS The User shall ensure that on the Completion Date the User's Equipment complies with the site specific technical conditions set out in Appendix F 1-5 to the Bilateral Connection Agreement [and that the OTSUA complies with the site specific technical conditions set out in Appendix OF to this Construction Agreement]. The obligation in respect of OTSUA shall apply up to the OTSUA Transfer Time, whereupon such provisions shall (without prejudice to any prior non-compliance) cease to apply
PROVISION OF SECURITY Where required to do so under the CUSC Section 15, the User shall provide The Company with security arrangements in accordance with CUSC Section 15 Part Three in respect of the User’s obligations to pay the Cancellation Charge to The Company on termination of this Construction Agreement or a reduction in Transmission Entry Capacity prior to the Charging Date.
EVENT OF DEFAULT Once any of the Events of Default in Paragraph 5.3.1 and/or Paragraph 5.4.6.2 and/or Paragraph 5.4.6.3 of the CUSC has occurred and is continuing The Company may give notice of termination to the User whereupon this Construction Agreement shall forthwith terminate and the provisions of Clause 11 shall apply.
8 Delete if OTSDUW Build
9 Delete if OTSDUW Build
10 Delete if OTSDUW Build
11 Use if OTSDUW Build Assessment Works and One Off Works, which in the reasonable opinion of The Company (and in the absence of the Connect and Manage Derogation) are necessary to extend or reinforce the National Electricity Transmission System to ensure that the National Electricity Transmission System complies with the requirements of condition E7 of the ESO Licence and Standard Condition D3 of any Relevant Transmission Licensee’s transmission system and which are specified in Appendix H1 to this Constructi
a description of those OTSUA at the Transmission Interface Site;
a clear identification of the boundary between the OTSUA and the Onshore Transmission System; and
a description of the technical design and operating criteria which apply to the OTSUA (including any reliance on the User’s Equipment in respect the minimum technical, design and operational criteria and performance requirements set out or referred to in CC.6.3)] “Transmission Reinforcement the Offshore Transmission Works” Reinforcement Works and Onshore Transmission Reinforcement Works. “Trigger Date” [date] as identified in accordance with the User Commitment Methodology. “User Data” the data set out in Appendix O.
On termination of this Construction Agreement The Company shall disconnect all the User’s Equipment at the Connection Site and:
where the Relevant Transmission Licensee is the owner of the Offshore Platform the User shall remove any of the User’s Equipment on the Offshore Platform within such period as may be agreed between the Relevant Transmission Licensee and the User; or
where the User is the owner of the Offshore Platform The Company shall procure that the Relevant Transmission Licensee removes, any [Transmission Connection Assets] on the Offshore Platform within such period as may be agreed between the Relevant Transmission Licensee and the User.] OR [(a) The Company shall disconnect the OTSUA at the Transmission Interface Site; and
the User shall remove any of the OTSUA on the Onshore Transmission Licensee’s land at the Transmission Interface Site and The Company shall (as appropriate) remove or procure that the Onshore Transmission Licensee removes its equipment (if any) from the User’s land at the Transmission Interface Site in each case within such period as may be agreed between Onshore Transmission Licensee and the User. ]
The User shall where this Construction Agreement terminates prior to the Charging Date be liable forthwith on the date this Construction Agreement so terminates to pay to The Company the Cancellation Charge such payment to be made within 14 days of the date of The Company’s invoice in respect thereof.
12 Delete if OTSDUW Build “User Progression Milestones” the milestones (applied in accordance with CUSC Section 16) for the User’s project (excluding any OTSDUW) as set out in Appendix Q of this Construction Agreement. “User’s Works” those works necessary for installation of the User’s Equipment which are specified in Appendix I [(Part 1)] to this Construction Agreement [and OTSDUW [subject to Clause [1.4] of this Construction Agreement13]. “Wider Transmission those Onshore Transmission Reinforcement Works” R
Subject to the provisions for earlier termination set out in the CUSC this Construction Agreement shall continue until terminated in accordance with Clause 1, 2.5, 2.6, 4.8, 11 or 18 hereof.
In addition this Construction Agreement shall terminate upon termination of the associated Bilateral Connection Agreement and in the event that this is prior to the Charging Date the provisions of Clause 11 shall apply.
The associated Bilateral Connection Agreements will automatically terminate upon termination of this Construction Agreement prior to the Charging Date.
Any provisions for payment shall survive termination of this Construction Agreement.
CUSC The provisions of Sections 6.6 (Payment), 6.14 (Transfer and Subcontracting),
13 Delete if OTSDUW Build [To include where the Construction Agreement Is A Gate 1 Agreement [with/without Reservation] 1.2A GATED APPLICATION AND OFFER PROCESS – GATE 1 CONDITIONAL CLAUSE [AND RESERVATION] 1.2A.1 The rights and obligations of the User and The Company under this Construction Agreement [and the [Bilateral Connection Agreement] are conditional on: 1.2A.1.1 the User making a Gate 2 Application; 1.2A.1.2 the Gate 2 Application meeting the Gate 2 Criteria; and 1.2A.1.3 the User accepting the terms
The nature, extent of and the timescales associated with the Onshore Construction Works are based on the Offshore Works Assumptions and User Data.
The Offshore Construction Works will need to be identified and where there are changes from the Offshore Works Assumptions and\or User Data the nature, extent of and the timescales associated with the Offshore Construction Works and as a consequence the Onshore Construction Works may need to be amended.
[The Company [shall] as soon as practicable and (save where the Authority consents to a longer period) in any event within 3 months of the receipt of notice from the Authority that the Relevant Transmission Licensee has been appointed propose to the User an agreement to vary this Construction Agreement and the Bilateral Connection Agreement. This agreement to vary will identify the Offshore Construction Works as set out in the Offshore TO Construction Offer and shall make such further amendments to the Construction Agreement and Bilateral Connection Agreement as are necessary as a consequence of this identification and the timing of the Offshore Tender Process on the Offshore Works Assumptions and the Onshore Construction Works and shall include such terms and conditions as The Company in its discretion requires as a consequence of such amendments]. [In the case of OTSDUW The Company may as soon as practicable and (save where the Authority consents to a longer period) in any event within 3 months of the receipt of notice from the Authority that the Relevant Transmission Licensee has been appointed propose to the User an agreement to vary this Construction Agreement and the Bilateral Connection Agreement to amend the Bilateral Connection Agreement and Construction Agreement as necessary to reflect any inconsistencies between the OTSDUW, OTSUA and Offshore Works Assumptions.]
The Offshore Agreement to Vary will be open for acceptance for a period of three months from receipt. If the User does not accept the Offshore Agreement to Vary within three months of receipt [or, where the Offshore Agreement to Vary has been referred to the Authority pursuant to condition E13.5 of the ESO Licence, within 14 days after any determination by the Authority pursuant to such application] then The Company shall be entitled to terminate this Construction Agreement.
[With effect from acceptance by the User of the Offshore Agreement to Vary the provisions of this Construction Agreement as amended by the Offshore Agreement to Vary shall have full force and effect and the provisions of this Sub-Clause 1.2 shall cease to have any further force or effect.]
[The rights and obligations of the User and The Company under this Construction Agreement (with the exception of those rights and obligations under or referred to in this Clause 1.2 and Clause 1.3) are subject to the above provisions of this Clause 1.2 (and neither party shall have any rights or obligations under any other provisions of this Construction Agreement until the provisions of sub-clause 1.2.5 have been fulfilled)] OR [The rights and obligations of the User and The Company under this Construction Agreement (with the exception of those rights and obligations under or referred to in this Clause 1.2 and Clause 1.3) and Clauses 2.2, 2.3 and 2.4, and rights and obligations flowing from those Clauses) are subject to the above provisions of this Clause 1.2.]
The User shall confirm that the User Data remains the same prior to the start of the Offshore Tender Process. [1.4 Where the OTSDUW comprise only the design, planning and/or consenting of (and/or other pre-construction activities relating to) the [Offshore Transmission System], and do not comprise works for construction and installation, direct or indirect references to the User's Works shall be deemed to include the Offshore Construction Works for the purposes only of (and to the extent so provided in the description of OTSDUW) Clauses 2.2, 2.3 and 2.4 of this Construction Agreement.] 2. CARRYING OUT OF THE WORKS
14 Not OTSDUW Build User shall enter into an agreement (in similar form to the Interface Agreement) with the Onshore Transmission Licensee to reflect the Works excluding the Wider Transmission Reinforcement Works at the Transmission Interface Site for the period up to and including the OTSUA Transfer Time.15]
15 Use OTSDUW Build 4 COMMISSIONING PROGRAMME AND LIQUIDATED DAMAGES
Subject to Clause 15.2 and 15.3 below, no variation to this Construction Agreement shall be effective unless made in writing and signed by or on behalf of both The Company and the User.
The Company and the User shall effect any amendment required to be made to this Construction Agreement by the Authority as a result of a change in the CUSC, the ESO Licence or the Transmission Licence, an order or direction made pursuant to the Act or a Licence, or as a result of settling any of the terms hereof. The User hereby authorises and instructs The Company to make any such amendment on its behalf and undertakes not to withdraw, qualify or revoke such authority or instruction at any time.
The Company has the right to vary this Construction Agreement and Appendices in accordance with Clauses 1, 2.3 and 2.11, 2.13, 2.16, 2.18, 7.3, 18 and Paragraph 6.9 of the CUSC.
16 RESTRICTIVE TRADE PRACTICES ACT Any restriction or information provision (as each of those terms are defined or construed in Section 43(1) of the Restrictive Trade Practices Act 1976) contained in this Construction Agreement shall not take effect or shall cease to have effect:-
if a copy of this Construction Agreement is not provided to the Department of Trade and Industry (“DTI”) within 28 days of the date of this Construction Agreement; or
if, within 28 days of the provision of that copy to the DTI, the DTI gives notice of objection to the party providing it. [Clause 17 is to be included where the User is undertaking OTSDUW]
17 Development of Offshore Transmission System Development User Works
To the extent not already provided and, within three months of the date of this Construction Agreement (or such later date as The Company shall agree) the User shall provide The Company with:
confirmation of the OTSDUW to be undertaken by the User;
confirmation of the programme for the OTSDUW to be undertaken by the User; and
information equivalent to that provided under Sections B and D of the Connection Application but by reference to the Transmission Interface Site rather than the Connection Site. Upon any revision to the Offshore Works Assumptions, the User shall provide updated information under paragraphs (a), (b) and (c) to and the parties shall (without prejudice to paragraph 6.9.2) agree such amendments to this Construction Agreement as are necessary to reflect such updated information. The parties acknowledge that any dispute regarding such amendments shall be referable to and determined by the Authority under the provisions of condition E13.5 of the ESO Licence, and where such application is made, the parties shall take into account any determination or other direction from the Authority.
The User and The Company shall within 3 months of the date of this Construction Agreement (or such later date as The Company and User shall agree) agree a timeline (the OTSDUW Development and Data Timeline) detailing the activities to be undertaken by the User in order to develop the scope of the OTSDUW and (provided for under the PC) providing for the exchange of data and information required.
Such data shall take account of The Company’s obligations to the Relevant Transmission Licensees under the STC in providing information and data in respect of additions to and changes on the National Electricity Transmission System and the need to coordinate the OTSDUW with the Onshore Construction Works and other works planned on the National Electricity Transmission System.
Within six months of the date of this Construction Agreement (or such later date as the The Company shall agree) the User shall provide The Company on an initial and indicative basis with:
information that would enable the Relevant Transmission Licensee to complete the Connection Site Specification (advising of any changes from or additions required to the site specific technical conditions set out in Appendices F1 to F5 to the Bilateral Connection Agreement) (to the extent practicable given the information and data available to the User at that time);
information that would enable the Relevant Transmission Licensee to complete the Transmission Interface Site Specification (advising of any changes from or additions required to the site specific technical conditions set out in Appendix OF to this Construction Agreement) (to the extent practicable given the information and data available to the User at that time);
information that would enable the Relevant Transmission Licensee to complete the Services Capability Specification (to the extent practicable given the information and data available to the User at that time).
Information referred to in Clause 17.4 (a), (b) and (c) shall be developed and amended by the User and agreed by The Company as the design and detail of the OTSDUW is finalised and such that the information can be provided by The Company to the extent practicable to the Relevant Transmission Licensee on its appointment and such that the Connection Site Specification and Services Capability Specification and Transmission Interface Site Specification are capable of being finalised on or prior to the OTSUA Transfer Time.
Any dispute between The Company and the User as to the information provided to enable finalisation of the Connection Site Specification, Services Capability Specification or Transmission Interface Site Specification shall be managed in accordance with CUSC Section 7 Paragraph 7.4.1 but the reference to the London Court of International Arbitration shall instead be to the Authority and the Authority’s determination of such dispute shall, without prejudice to apply for judicial review of any determination, be final and binding on The Company and the User.
The User shall provide The Company with such information and assistance as The Company may reasonably require to enable the Onshore Transmission Licensee and the Relevant Transmission Licensee to have in place a Transmission Interface Agreement relating to the Transmission Interface Site and an Interface Agreement relating to the Connection Site in each case from no later than the OTSUA Transfer Time.
Taking into account the expected extent of the OTSUA Commissioning Period prior to the OTSUA Transfer Time, The Company and the User shall establish, as part of the OTSDUW Development and Data Timetable:
a timetable for the provision of the items required from the User pursuant to Clause 5 of this Construction Agreement, the Grid Code and CUSC Paragraphs 2.10 and 2.11 as they relate to the Connection Site; and
where the Transmission Interface Site will be Operational prior to the OTSUA Transfer Time, by when and to what extent the information referred to in Clause 17.4 (a), (b) and (c) should be in final form prior to the OTSUA Transfer Time;
where the Transmission Interface Site will be Operational prior to the OTSUA Transfer Time, to what extent and by when the User has to comply with the requirements in Appendices OF prior to the OTSUA Transfer Time.18
18 QUEUE MANAGEMENT PROCESS
The Queue Management Process shall be incorporated into this Construction Agreement and apply between The Company and the User and Appendix Q to this Construction Agreement has been prepared in accordance with the principles set out in CUSC Section 16.
Where, in accordance with the Queue Management Process,:
in the case of any of the Conditional Progression Milestones, the status of the User’s project at the end of the Project Milestone Remedy Period is categorised as “Termination”, The Company will terminate this Construction Agreement by notice in writing (such notice being not less than 10 Business Days); and 18.2.2 in the case of any of the Construction Progression Milestones, the status of the User’s project at the end of the Project Milestone Remedy Period is categorised as “Termination”, The Company may terminate this Construction Agreement by notice in writing (such notice being not less than 10 Business Days); and 18.2.3 on such termination the provisions of Clause 11 of this Construction Agreement shall apply.
Where in accordance with the Queue Management Process there is a variation to the date by which a User Progression Milestone has to be met The Company shall revise Appendix Q to this Construction Agreement as required to reflect such change.
Use OTSDUW Build
Any dispute or difference between The Company and the User on the Queue Management Process in respect of this Construction Agreement shall be resolved as an Other Dispute under the Dispute Resolution Procedure. IN WITNESS WHEREOF the hands of the duly authorised representatives of the parties hereto at the date first above written
| Milestone | Date due |
|---|---|
| M1 – Initiate Planning Consent | |
| M2 – Secure Consent | |
| M3 – Land Rights | |
| M5 – Contestable Design Works Submission | |
| M6 – Agree Construction Plan | |
| M7 – Project Commitment | |
| M8 – Initiate Construction |
Schedule 2 Exhibit 4
1. The company registered in England with number 11014226 (“The Company”), which expression shall include its successors and/or permitted assigns); and
2. [] a company registered in [] with number [] whose registered office is at [] (“User”, which expression shall include its successors and/or permitted assigns) WHEREAS
Pursuant to the ESO Licence, The Company is required to prepare a Connection and Use of System Code (CUSC) setting out the terms of the arrangements for connection to and use of the National Electricity Transmission System and the provision of certain Balancing Services.
As at the date hereof, The Company and the User are parties to the CUSC Framework Agreement (being an agreement by which the CUSC is made contractually binding between the parties).
This Mandatory Services Agreement is entered into pursuant to the terms of the CUSC and shall be read as being governed by it and, as between The Company and the User, has priority over the terms of the CUSC in accordance with (and subject to) Paragraph 11.2.2 of the CUSC. NOW IT IS HEREBY AGREED as follows:
1. DEFINITIONS, INTERPRETATION AND CONSTRUCTION Unless the subject matter or context otherwise requires or is inconsistent therewith, terms and expressions defined in Section 11 of the CUSC have the same meanings, interpretations or constructions in this Mandatory Services Agreement. Subject thereto, unless the subject matter or context otherwise requires or is inconsistent therewith, in this Mandatory Services Agreement the terms set out in Appendix 3 shall have the meanings set out respectively therein.
2. COMMENCEMENT This Mandatory Services Agreement shall commence on [] (“Commencement Date”).
3. OBLIGATORY REACTIVE POWER SERVICE - DEFAULT UTILISATION
Schedule 3, Part I to the CUSC The provisions of this Clause 3 implement the terms of Paragraph 2 of Schedule 3, Part I to the CUSC (“CUSC Schedule”) with respect to the payments to be made by The Company to the User for the provision by the User from the BM Units of the Obligatory Reactive Power Service, and in accordance with Paragraph 2.1 thereof the Parties hereby agree to make all necessary amendments to this Mandatory Services Agreement so as to give effect to the provisions of the CUSC Schedule as amended or modified from time to time.
Term and Suspension [3.2.1 The provisions of this Clause 3 shall be deemed to have applied in relation to each BM Unit with effect from 00.00 hours on the [date hereof] [Commencement Date] and, subject always to Sub-Clause 3.2.2, shall continue thereafter unless and until the earlier of termination of the CUSC Schedule and termination of this Mandatory Services Agreement. For the avoidance of doubt, in the event this Mandatory Services Agreement is terminated in relation to any individual BM Unit, the provisions of this Clause 3 shall terminate in relation to that BM Unit only.] OR [3.2.1 The provisions of Sub-Clauses 3.3 to 3.6 inclusive shall apply with effect from 00.00 hours on the date on which it is demonstrated (having regard to industry practice) to the reasonable satisfaction of The Company that each of the [CCGT] [BM] [Non-Synchronous Generating] Units complies with the provisions of Grid Code CC 6.3.2 and 6.3.4 as applicable (or the coming into force of a direction issued by the Authority relieving the User of the obligation under its Licence to comply therewith) or (where The Company in its sole discretion requires Reactive Power from the BM Units before then for the purposes of security of the National Electricity Transmission System) such earlier date as The Company may agree with the User and, subject always to Sub-Clause 3.2.3, shall continue thereafter unless and until the earlier of termination of the CUSC Schedule and termination of this Mandatory Services Agreement. For the avoidance of doubt, the issue by The Company in relation to the BM Unit of a Reactive Despatch Instruction to unity power factor or zero Mvar shall not imply demonstration to The Company’s reasonable satisfaction of compliance as referred to above nor imply in relation to the BM Unit agreement by The Company of an earlier date as referred to herein.
No demonstration referred to in Sub-Clause 3.2.1 shall take place until the User shall have demonstrated to The Company’s reasonable satisfaction (having regard to industry practice) that [each [CCGT] [BM] Unit’s Excitation System, and in particular where applicable) the Under-excitation Limiter] [the continuously-acting automatic control system required to provide control of the volatage or zero transfer of Reactive Power with respect to each [Power Park Moule] [DC Converter] has been successfully commissioned and complies with the provisions of Grid Code CC 6.3.8.] 3.2.2/3 In relation to any BM Unit, the provisions of this Clause 3 (except this Sub-Clause 3.2) shall be suspended and have no force and effect upon the coming into effect, and for the duration of, any agreement (referred to in the CUSC Schedule as a "Market Agreement" and being either a new Ancillary Services Agreement or an agreement incorporating provisions into this Mandatory Services Agreement) which may be entered into between the Parties pursuant to Paragraph 3 of the CUSC Schedule for the provision by the User in relation to that BM Unit of:-
the Obligatory Reactive Power Service but with alternative payment arrangements to those provided in this Clause 3; or
an Enhanced Reactive Power Service. For the avoidance of doubt, with effect from the expiry or termination of any Market Agreement such provisions shall in relation to that BM Unit cease to be suspended and shall resume full force and effect. 3.2.3/4 Termination or suspension of this Clause 3 shall not affect the rights and obligations of the Parties accrued as at the date of termination or suspension.
Capability Data
The Parties agree that, for the purposes of the Appendices to the CUSC Schedule:- [(a) the figures set out in Table B of Appendix 1, Section A, Part I represent for each BM Unit the Reactive Power capability at Rated MW which the User is obliged to provide under and in accordance with the Grid Code CC 6.3.2(a), together with Reactive Power capability at other levels of MW Output as specified therein by reference to the Generator Performance Chart submitted in accordance with Grid Code OC 2.4.2 and measured at the generator stator terminals; and
the figures set out in Table A of Appendix 1, Section A, Part I shall constitute for each of the BM Units the value of QC and lead QC referred to in Section 2 of Appendix 3 to the CUSC lag Schedule representing the Reactive Power capability at Rated MW shown at the Commercial Boundary (by application of the formulae set out in Appendix 8, Part 1 to the CUSC Schedule).] OR [(a) the figures set out in Table B of Appendix 1, Section A, Part I represent for each relevant CCGT Unit the Reactive Power capability at Rated MW which the User is obliged to provide under and in accordance with Grid Code CC 6.3.2(a), together with Reactive Power capability at other levels of MW Output as specified therein by reference to the Generator Performance Chart submitted in accordance with Grid Code OC 2.4.2 and measured at the generator stator terminals; and
the figures set out in summary Table C of Appendix 1, Section A, Part I represent for the BM Unit the Reactive Power capability of each relevant CCGT Unit at Rated MW (derived from Table B) but shown at the high voltage side of the Generating Unit step-up transformer by application of the formulae set out in Appendix 8, Part 2 to the CUSC Schedule; and
the figures set out in Table A of Appendix 1, Section A, Part I shall constitute for the BM Unit the value of QC and QC lead lag referred to in Section 2 of Appendix 3 to the CUSC Schedule representing the Reactive Power capability of the BM Unit at Rated MW shown at the Commercial Boundary (derived by the summation of the Reactive Power capability of each relevant CCGT Unit at Rated MW extracted from summary Table C and by application of the formulae set out in Appendix 8 , Part 2 to the CUSC Schedule.] [(a) the figures set out in Table B of Appendix 1, Section A, Part I represent for the BM Unit the Reactive Power capability at Rated MW and at various other Active Power output levels which the User is obliged to provide under and in accordance Grid Code CC 6.3.2(c) or 6.3.2(d)(i) (as the case may be) by reference to the Generator Performance Chart submitted in accordance with Grid Code OC 2.4.2 and measured at either the Grid Entry Point in England and Wales or at the HV side of the 33/132 kV or 33/275 kV or 33/400 kV transformer for Users connected to the National Electricity Transmission System in Scotland or the User System Entry Point if Embedded; and
the figures set out in Table A of Appendix 1, Section A, Part I shall constitute for the BM Unit the value of QC and QC lead lag referred to in Section 2 of Appendix 3 to the CUSC Schedule representing the Reactive Power capability at Rated MW shown at the Commercial Boundary. [(a) the figures set out in Table B of Appendix 1, Section A, Part I represent for each relevant Non-Synchronous Generating Unit the Reactive Power capability at Rated MW which the User is obliged to provide under and in accordance with Grid Code CC 6.3.2(d)(ii), together with Reactive Power capability at other levels of MW Output as specified therein by reference to the Generator Performance Chart submitted in accordance with Grid Code OC 2.4.2 and measured at the generator stator terminals; and
where applicable, the figures set out in summary Table C of Appendix 1, Section A, Part I represent for a Power Park Module the Reactive Power capability of each relevant Power Park Unit at Rated MW (derived from Table B) but shown at the high voltage side of the Generating Unit step-up transformer by application of the formulae set out in Appendix 8, Part 3 to the CUSC Schedule; and
the figures set out in Table A of Appendix 1, Section A, Part I shall constitute for the BM Unit the value of QC and QC lead lag referred to in Section 2 of Appendix 3 to the CUSC Schedule representing the Reactive Power capability of the BM Unit at Rated MW shown at the Commercial Boundary (where applicable, derived by the summation of the Reactive Power capability of each relevant Power Park Unit at Rated MW extracted from summary Table C and by application either of the formulae set out in Appendix 8, Part 3 to the CUSC Schedule or such other methodology as The Company and the User may agree in writing.]
Payments to User
In respect of each BM Unit, and in consideration of the User providing the Obligatory Reactive Power Service from that BM Unit, The Company shall pay to the User in respect of each calendar month in accordance with Paragraph 4.3 of the CUSC the aggregate total payments calculated in accordance with Appendix 1 to the CUSC Schedule and referred to therein as "PT".
For the purposes of Sub-Clause 3.4.1:-
the Relevant Zone in which the BM Units are situated is specified in Appendix 1, Section A, Part I;
without prejudice to Paragraph 4.1.2.2 of the CUSC, The Company shall use the meters and aggregation principles specified and/or referred to in Appendix 1, Section A, Part II to ascertain the amount of Leading and Lagging Mvarh produced in each Settlement Period by the BM Units, and such amount of Leading or Lagging Mvarh shall constitute the respective values of U and U as referred to in paragraph 1 of Appendix lead lag 3 to the CUSC Schedule; and
the Parties acknowledge that all meters and metered data used for the purposes of this Clause 3 shall comply with the provisions of Appendix 4 to the CUSC Schedule.
4. FREQUENCY RESPONSE
Paragraph 4.1.3 of CUSC The provisions of this Clause 4 give effect to the provisions of Paragraph 4.1.3 of the CUSC in respect of the provision by the User from the BM Units of the Mandatory Ancillary Service of Frequency Response and the payments to be made by The Company to the User in respect thereof.
Term
The provisions of this Clause 4 shall be deemed to have applied in relation to each BM Unit with effect from 00.00 hours on the [date hereof] [Commencement Date] and shall continue thereafter unless and until this Mandatory Services Agreement is terminated. For the avoidance of doubt, in the event this Mandatory Services Agreement is terminated in relation to any individual BM Unit, the provisions of this Clause 4 shall terminate in relation to that BM Unit only.
Termination of this Clause 4 shall not affect the rights and obligations of The Company and the User accrued as at the date of termination.
Provision of Frequency Response
The Parties agree that:-
[subject always to Sub-Clause 4.4,] for the purposes of Paragraph 4.1.3.7 of the CUSC, the figures set out in the response tables in Appendix 1, Section B, Part I represent the amount of Primary Response, Secondary Response and High Frequency Response referred to therein;
[subject always to Sub-Clause 4.4] for the purposes of Paragraph 4.1.3.9 of the CUSC, the figures set out in the summary response table in Appendix 1, Section B, Part II represent the capabilities in respect of Primary Response, Secondary Response and High Frequency Response at given levels of De-Load referred to therein;
for the purposes of Paragraph 4.1.3.4 of the CUSC, the table in Appendix 1, Section B, Part III shows the permissible combinations of Primary Response, Secondary Response and High Frequency Response referred to therein;
for the purposes of Paragraph 4.1.3.9 of the CUSC, the figures (if any) set out in the plant configuration table in Appendix 1, Section B, Part II represent the plant configuration adjustment factors referred to therein to be applied where the BM Unit is a CCGT Module;
[subject always to Sub-Clause 4.4,] for the purposes of Paragraph 4.1.3.9A(a) of the CUSC in respect of calculation of the Response Energy Payment, the response values in Appendix 1, Section B, Part IV represent the Frequency Response Power that is deemed to be delivered in respect of Primary Response, Secondary Response and High Frequency Response.
[Commissioning and Provisional Response Levels Without prejudice to Paragraph 4.1.3.14 of the CUSC, the User acknowledges that the levels of Response set out in the response tables in Appendix 1, Section B, Parts I, II and IV are indicative figures only during the period in which the relevant Generating Unit(s) is being commissioned and the User hereby undertakes to use its reasonable endeavours to forward to The Company levels of Response which represent the true operating characteristics of such Generating Unit(s) for inclusion in Appendix 1, Section B, Parts I, II and IV as soon as possible following completion of commissioning.] [Indicative Response Levels Without prejudice to Paragraph 4.1.3.14 of the CUSC, the Parties acknowledge and agree that the levels of Response set out in Appendix 1, Section B, Parts I, II and IV reflect either the absence of or incomplete submissions of data required for the purposes of this Clause 4 to be made by the User for the relevant BM Unit(s) as at the Commencement Date, and furthermore the performance of such BM Units(s) has not been assessed by The Company to establish that such levels of Response represent the true operating characteristics of such BM Unit(s), and accordingly:-
to that extent the figures set out in Appendix 1, Section B, Parts I, II and IV for such BM Unit(s) are provisional pending:-
the submission by the User of such complete data, which the User hereby undertakes to provide to The Company, and
subsequent assessment by The Company of the performance of such BM Unit(s) (based upon demonstration to The Company by the User of operation of such BM Unit(s) and/or the provision by the User to The Company of such information as The Company shall reasonably require) in order to establish to The Company’s reasonable satisfaction that such figures represent the true operating characteristics of such BM Unit(s); and
upon submission by the User of such complete data and following assessment by The Company of performance of such BM Unit(s) as aforesaid, if The Company is of the reasonable opinion that any or all of the levels of Response set out in Appendix 1, Section B, Parts I, II and IV do not represent the true operating characteristics of such BM Unit(s), then The Company shall so notify the User and the Parties shall discuss and agree consequential changes to the relevant part or parts of Appendix 1, Section B, Parts I, II and IV to reflect such true operating characteristics, provided always that such complete data shall be submitted by the User, the assessment by The Company of the performance of such BM Unit(s) shall be completed and (where applicable) any consequential changes to the relevant part or parts of Appendix 1, Section B, Parts I, II and IV shall be agreed by the Parties, in each case as soon as reasonably practicable and in any event no later than 6 months after the Commencement Date (or such later date as the Parties may agree in writing). ]
5. NOT USED
6. GENERAL PROVISIONS Paragraphs 6.12 (limitation of liability), 6.14 (transfer and subcontracting),
(confidentiality), 6.18 (intellectual property), 6.19 (force majeure), 6.20 (waiver), 6.21 (notices), 6.22 (third party rights), 6.23 (jurisdiction), 6.24 (counterparts), 6.25 (governing law), 6.26 (severance of terms) and 6.27 (language), 6.38 (Directions related to National Security), and Section 7 (dispute resolution) of the CUSC are incorporated into this Mandatory Services Agreement mutatis mutandis.
7. VARIATIONS
Subject to Sub-Clause 7.2, no variation to this Mandatory Services Agreement shall be effective unless made in writing and signed by or on behalf of both The Company and the User.
The Company and the User shall effect any amendment required to be made to this Mandatory Services Agreement by the Authority as a result of a change in the CUSC, the ESO Licence or the Transmission Licence, an order or direction made pursuant to the Act or a Licence, or as a result of settling any of the terms hereof. The User hereby authorises and instructs The Company to make any such amendment on its behalf and undertakes not to withdraw, qualify or revoke such authority or instruction at any time.
8. NOTICES For the purposes of this Mandatory Services Agreement, unless and until otherwise notified by the relevant Party to the other in accordance with Paragraph 6.21.1 of the CUSC, any notice or other communication to be given by The Company or the User to the other under, or in connection with matters contemplated by, this Mandatory Services Agreement shall be sent to the following address and/or email address and marked for the attention of the person named below: The Company: Address: Email Address: Fo
9. BANK ACCOUNT DETAILS For the purposes of Paragraph 4.3.2.18 of the CUSC, unless and until otherwise notified by the relevant Party to the other in accordance with that Paragraph, details of each of the Party’s bank accounts to which sums payable in connection with this Mandatory Services Agreement shall be paid are set out below: The Company: Bank: Branch: Account Number: User: Bank: Branch: Account Number: [10. AGREEMENT TO AMEND THIS MANDATORY SERVICES AGREEMENT The Parties hereby acknowledge and agree th
| NATIONAL ENERGY SYSTEM ) |
|---|
| OPERATOR LIMITED ) |
| TABLE A | LEAD (Mvar) | LAG (Mvar) |
|---|---|---|
| AT RATED MW |
| TABLE B | MW | LEAD (Mvar) | LAG (Mvar) |
|---|---|---|---|
| AT RATED MW | |||
| AT FULL OUTPUT (MW) | |||
| AT MINIMUM OUTPUT (MW) |
| TABLE A AT RATED MW | LEAD (Mvar) | LAG (Mvar) |
|---|
| TABLE B | MW | LEAD (Mvar) | LAG (Mvar) |
|---|---|---|---|
| AT RATED MW | |||
| AT FULL OUTPUT (MW) | |||
| AT MINIMUM OUTPUT (MW) |
| TABLE A | LEAD (Mvar) | LAG (Mvar) |
|---|---|---|
| AT RATED MW |
| TABLE B | MW | LEAD (Mvar) | LAG (Mvar) |
|---|---|---|---|
| AT RATED MW | |||
| AT FULL OUTPUT (MW) | |||
| AT MINIMUM OUTPUT (MW) |
| TABLE A AT RATED MW | LEAD (Mvar) | LAG (Mvar) |
|---|
| TABLE B | MW | LEAD (Mvar) | LAG (Mvar) |
|---|---|---|---|
| AT RATED MW | |||
| AT FULL OUTPUT (MW) | |||
| AT MINIMUM OUTPUT (MW) |
| TABLE A | MW | LEAD (Mvar) | LAG (Mvar) |
|---|---|---|---|
| AT RATED MW |
| TABLE B | MW | LEAD (Mvar) | LAG (Mvar) |
|---|---|---|---|
| AT RATED MW | |||
| AT FULL OUTPUT (MW) | |||
| AT MINIMUM OUTPUT (MW) | |||
| AT RATED MW | |||
| AT FULL OUTPUT (MW) | |||
| AT MINIMUM OUTPUT (MW) | |||
| AT RATED MW | |||
| AT FULL OUTPUT (MW) | |||
| AT MINIMUM OUTPUT (MW) |
| SUMMARY TABLE C | RATED MW | LEAD (Mvar) | LAG (Mvar) |
|---|---|---|---|
| CCGT UNIT |
| TABLE A | MW | LEAD (Mvar) | LAG (Mvar) |
|---|---|---|---|
| AT RATED MW |
| TABLE B | MW | LEAD (Mvar) | LAG (Mvar) |
|---|---|---|---|
| AT RATED MW | |||
| AT 50% OF RATED MW | |||
| AT 20% OF RATED MW | |||
| AT BELOW 20% OF RATED MW | |||
| AT 0% OF RATED MW |
| TABLE A | MW | LEAD (Mvar) | LAG (Mvar) |
|---|---|---|---|
| AT RATED MW |
| TABLE B | MW | LEAD (Mvar) | LAG (Mvar) |
|---|---|---|---|
| AT RATED MW | |||
| AT 50% OF RATED MW | |||
| AT 20% OF RATED MW | |||
| AT BELOW 20% OF RATED MW | |||
| AT 0% OF RATED MW |
| SUMMARY TABLE C | RATED MW | LEAD (Mvar) | LAG (Mvar) |
|---|---|---|---|
| POWER PARK UNIT |
| [BM] or [CCGT ] Unit No | Metering Subsystem ID | Outstation ID | Channel Number | Meter Register ID | Measurement Quantity ID (RI or RE) | Loss Adjustment Factor |
|---|
| Reactive Load | |
|---|---|
| BM Unit | Q ts |
| Table 1 | Low Frequency Response – Mode A | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Genset De- Load (MW) | f p (Hz) | Primary Respons e (MW) | Secondary Response (MW) | ||||||||||||
| f= - 0.1Hz s | f= - 0.2Hz s | f= - 0.3Hz s | f= - 0.4Hz s | f= - 0.5Hz s | |||||||||||
| -0.1 | |||||||||||||||
| -0.2 | |||||||||||||||
| -0.3 | |||||||||||||||
| -0.4 | |||||||||||||||
| -0.5 | |||||||||||||||
| -0.6 | |||||||||||||||
| -0.7 | |||||||||||||||
| -0.8 | |||||||||||||||
| -0.1 | |||||||||||||||
| -0.2 | |||||||||||||||
| -0.3 | |||||||||||||||
| -0.4 | |||||||||||||||
| -0.5 | |||||||||||||||
| -0.6 | |||||||||||||||
| -0.7 | |||||||||||||||
| -0.8 | |||||||||||||||
| -0.1 | |||||||||||||||
| -0.2 | |||||||||||||||
| -0.3 | |||||||||||||||
| -0.4 | |||||||||||||||
| -0.5 | |||||||||||||||
| -0.6 | |||||||||||||||
| -0.7 | |||||||||||||||
| -0.8 | |||||||||||||||
| -0.1 | |||||||||||||||
| -0.2 | |||||||||||||||
| -0.3 | |||||||||||||||
| -0.4 | |||||||||||||||
| -0.5 | |||||||||||||||
| -0.6 | |||||||||||||||
| -0.7 | |||||||||||||||
| -0.8 | |||||||||||||||
| -0.1 | |||||||||||||||
| -0.2 | |||||||||||||||
| -0.3 | |||||||||||||||
| -0.4 | |||||||||||||||
| -0.5 | |||||||||||||||
| -0.6 | |||||||||||||||
| -0.7 | |||||||||||||||
| -0.8 | |||||||||||||||
| -0.1 | |||||||||||||||
| -0.2 | |||||||||||||||
| -0.3 | |||||||||||||||
| -0.4 | |||||||||||||||
| -0.5 | |||||||||||||||
| -0.6 | |||||||||||||||
| -0.7 | |||||||||||||||
| -0.8 |
| Table 2 | High Frequency Response (MW) - Mode A | ||||
|---|---|---|---|---|---|
| Genset De- Load (MW) | Frequency Deviation from Target Frequency | ||||
| f = +0.1 Hz h | f = +0.2 Hz h | f = +0.3 Hz h | f = +0.4 Hz h | f = +0.5 Hz h |
| Table 1 | Frequency Response Capability Summary - Mode A | ||
|---|---|---|---|
| Genset De-Load (MW) | Primary Response @-0.5Hz (MW) | Secondary Response @-0.2Hz (MW) | High Frequency Response @+0.5Hz (MW) |
| PMW | SMW | HMW |
| Table 2 | Plant Configuration Adjustment Factor KGRC – Mode A | |
|---|---|---|
| 1 Gas Turbine and 1 Steam Turbine | ||
| 1 Gas Turbine |
| Table 1 | Mode A Response | |
|---|---|---|
| Primary Response | ✓ | ✓ |
| y Secondary Response | ✓ | |
| High Frequency Response | ✓ | ✓ |
| Primary Response Power Delivery – Mode A | ||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Frequency | Genset De-load (MW) | |||||||||||||||||||
| Deviation (Hz) | ||||||||||||||||||||
| -0.1 | ||||||||||||||||||||
| -0.2 | ||||||||||||||||||||
| -0.3 | ||||||||||||||||||||
| -0.4 | ||||||||||||||||||||
| -0.5 | ||||||||||||||||||||
| Primary & Secondary Response Power Delivery – Mode A | ||||||||||||||||||||
| Frequency | Genset De-load (MW) | |||||||||||||||||||
| Deviation (Hz) | ||||||||||||||||||||
| -0.1 | ||||||||||||||||||||
| -0.2 | ||||||||||||||||||||
| -0.3 | ||||||||||||||||||||
| -0.4 | ||||||||||||||||||||
| -0.5 | ||||||||||||||||||||
| High Frequency Response Power Delivery – Mode A | ||||||||||||||||||||
| Frequency | Genset De-load (MW) | |||||||||||||||||||
| Deviation (Hz) | ||||||||||||||||||||
| +0.1 | ||||||||||||||||||||
| +0.2 | ||||||||||||||||||||
| +0.3 | ||||||||||||||||||||
| +0.4 | ||||||||||||||||||||
| +0.5 |
Schedule 2 Exhibit 5
1. The company registered in England with number 11014226 (“The Company”, which expression shall include its successors and/or permitted assigns); and
2. [] a company registered in [] with number [] whose registered office is at [] (“User”, which expression shall include its successors and/or permitted assigns). WHEREAS
Pursuant to the ESO Licence, The Company is required to prepare a Connection and Use of System Code (CUSC).
The User has applied in the capacity of an EELPS whose Boundary Point Metering System is [to be] registered in SMRS or in CMRS by a User who is responsible for the Use of System Charges associated with the BM Unit [to be] registered in CMRS.
The User has made a BELLA Application and The Company is required to make a BELLA Offer in accordance with Paragraph 1.5.2 of the CUSC.
This Offer has been made on the basis of the Connect and Manage Arrangements.
This BELLA is a [Gate 1 Agreement][Gate 2 Agreement]. NOW IT IS HEREBY AGREED as follows:
1. DEFINITIONS, INTERPRETATION AND CONSTRUCTION Unless the subject matter or context otherwise requires or is inconsistent therewith, terms and expressions defined in Section 11 of the CUSC have the same meanings, interpretations or constructions in this BELLA and the following term(s) shall have the meaning(s) set out below: S2E5-3
| DNO | name address and registered number of owner\operator of the distribution network to which user is to connect. |
|---|---|
| DNO Construction Agreement | the agreement between The Company and the DNO for Transmission Reinforcement Works as a consequence of the User’s connection to the Distribution System. |
| Enabling Works | those elements of the Transmission Reinforcement Works which are required to be completed prior to the User’s Equipment being Energised and specified in Appendix H Part 1. |
| [Gate 2 Agreements | the acceptance of the Gate 2 Offers and entering into the Gate 2 Agreements by both (a) the User and (b) the DNO in each case accepting the Gate 2 Offer to amend the Gate 1 Agreements between the User and The Company and the DNO and The Company respectively such that the Gate 1 Agreements become Gate 2 Agreements – Gate 1 Agreement only.] |
| Notice of Reduction | the notice of that name given by The Company to the DNO and the User pursuant to Clause 7 of the DNO Construction Agreement. |
| Notice of Reduction Effective Date | the date the amendments proposed by the Notice of Reduction take effect. |
| Transmission Reinforcement Works | those works which in the reasonable opinion of The Company are necessary to extend or reinforce the National Electricity Transmission System as a consequence of the User’s Equipment being Energised specified in Appendix H. |
| User’s Capacity | the MW [export] figure specified in the User’s Data. |
| User’s Data | the data submitted by the User and set out in Appendix A to the BELLA against which the effect on the National Electricity Transmission System of the User’s connection to the Distribution System has been assessed. |
| Wider Transmission Reinforcement Works | those elements of the Transmission Reinforcement Works which are not required to be completed prior to the User’s Equipment being Energised and specified in Appendix H Part 2. |
2. CONDITIONS PRECEDENT AND COMMENCEMENT
The rights and obligations of the User and The Company pursuant to this BELLA are subject to the following conditions precedent having been fulfilled before such rights and obligations arise:
the User having provided (in a form reasonably satisfactory to The Company) proof of having entered into a Distribution Agreement with the owner/operator of the Distribution System; and 2.1.2 of the acceptance by the owner/operator of the Distribution System of any necessary Modification Offer relevant to the Embedded Power Station; and S2E5-4
The Company and / or the Users as appropriate having received the derogations [if any] required in respect of the Grid Code; and [2.1.4 The Gate 2 Agreements having been entered into - Gate 1 Agreements with/without Reservation only].
If the conditions precedent have not been fulfilled, in the case of 2.1.1 and 2.1.3 within 6 months of the date hereof, and in the case of 2.1.2 within 3 months of the date of receipt by the owner/operator of the Distribution System of the Modification Offer, The Company or the User may rescind this BELLA by giving to the other notice to that effect in which event all rights and liabilities of the parties hereunder and under the CUSC in relation to this Embedded Power Station shall cease.
This BELLA shall commence on [ ].
It is a condition of this Agreement that the Embedded Exemptable Large Power Station is SMRS registered (or CMRS registered by a Supplier) in the BSC. If, at any time the Embedded Exemptable Large Power Station ceases to be SMRS registered (or CMRS registered by a Supplier) and becomes CMRS registered other than by a Supplier then the User hereby undertakes to forthwith apply for and enter into a Bilateral Embedded Generation Agreement.
3. THE SITE OF CONNECTION TO THE DISTRIBUTION SYSTEM The site of Connection of the EELPS to the Distribution System to which this BELLA relates is more particularly described in Appendix A.
4. OUTAGES Subject to the provisions of the Grid Code, The Company and the User shall be entitled to plan and execute outages of parts of, in the case of The Company, the National Electricity Transmission System or Transmission Plant or Transmission Apparatus and in the case of the User, its System or Plant or Apparatus, at any time and from time to time.
5. GRID CODE MATTERS
Paragraph 6.3 of the CUSC applies in respect of this Embedded Exemptable Large Power Station as amended in accordance with the following provisions of this Clause 5.
The provisions in BC1 and BC2 of the Grid Code provide that compliance is only required with such provisions in respect of those Generating Units at an Embedded Exemptable Large Power Station where The Company reasonably requires such compliance and has specified such a requirement in respect of such Generating Units in the BELLA. S2E5-5 [5.2 The Company and the User hereby agree that compliance by the User in respect of this Embedded Exemptable Large Power Station with the provisions of BC1 and BC2 of the Grid Code are reasonably required and therefore the provisions of BC1 and BC2 shall apply and be complied with by the User so far as applicable to it. Therefore, the provisions in BC1 and BC2 in respect of Generating Units and Generating Unit Data shall apply to and be complied with by the User. For the purposes of the Grid Code the User shall be treated as a BM Participant. [5.2 The Company does not require compliance by the User in respect of this Embedded Exemptable Large Power Station with the provisions of BC1 and BC2] [Note: which alternative of Clause 5.2 will apply will depend upon whether or not The Company reasonably requires compliance with these Grid Code obligations. Please note that the User has a right to ask the Authority to determine on these matters.]
6. OPERATIONAL NOTIFICATION Subject to the provisions of Clause 2.1 having been fulfilled, and subject, if The Company so requires, to Enabling Works [and/or works for any Modification Offer] being carried out and to notification by the User that the site of connection of the User's Equipment to the Distribution System is operational, The Company shall forthwith notify ("Operational Notification") the User in writing that it may energise its Equipment.
7. COMPLIANCE WITH SITE SPECIFIC TECHNICAL CONDITIONS
The site specific technical conditions applying to the site of Connection are set out in Appendices F1 to F5 to this BELLA as modified from time to time in accordance with Paragraph 6.9 of the CUSC.
The Company and the User shall operate respectively the National Electricity Transmission System and the User System with the special automatic facilities and schemes set out in Appendix F3 to this BELLA.
The User shall ensure that the User's Equipment complies with the site specific technical conditions set out in Appendix F4 to this BELLA.
The User shall use all reasonable endeavours to ensure that the User's Equipment shall continue to comply with the site specific technical conditions set out in Appendix F5 of this BELLA.
If the User or The Company wishes to modify alter or otherwise change the site specific technical conditions or the manner of their operation under Appendix F1, F3, F4 or F5 to this BELLA this shall be deemed to be a Modification for the purposes of the CUSC. S2E5-6
8. TERM
Subject to the provisions for earlier termination set out in CUSC and Clause 8.2 below, this BELLA shall continue until all of the User’s equipment is Disconnected from the relevant Distribution System at the site of Connection as provided in Section 5 of CUSC.
This BELLA shall terminate on the earlier of
the Notice of Reduction Effective Date where as a result of the Notice of Reduction the User is no longer an Embedded Exemptable Large Embedded Power Station.
termination of the DNO Construction Agreement pursuant to Clause 7.4.10.2 of the Construction Agreement and provided that the Bilateral Connection Agreement between the DNO and The Company has, where required by The Company, been amended to reflect the fact that the Developer is no longer party to a BELLA but is a Relevant Embedded Small Power Station S2E5-7
9. VARIATIONS
Subject to 9.2, 9.3 and 9.4, no variation to this BELLA shall be effective unless made in writing and signed by or on behalf of both The Company and the User.
The Company and the User shall effect any amendment required to be made to this BELLA by the Authority as a result of a change in the CUSC, the ESO Licence or the Transmission Licence, an order or direction made pursuant to the Act or a Licence, or as a result of settling any of the terms hereof. The User hereby authorises and instructs The Company to make any such amendment on its behalf and undertakes not to withdraw, qualify or revoke such authority or instruction at any time.
If it is necessary for The Company or The Company in its reasonable discretion wishes to make any addition to or omission from or amendment to the Transmission Reinforcement Works, Appendix H shall be automatically amended to reflect the change.
Appendix A shall be automatically amended to reflect any Notice of Reduction on the Notice of Reduction Effective Date
10. RESTRICTIVE TRADE PRACTICES ACT Any restriction or information provision (as each of those terms are defined or construed in Section 43(1) of the Restrictive Trade Practices Act 1976) contained in this BELLA shall not take effect or shall cease to have effect:
if a copy of this BELLA is not provided to the Department of Trade and Industry (“DTI”) within 28 days of the date of this; or 10.1.2 if, within 28 days of the provision of that copy to the DTI, the DTI gives notice of objection to the party providing it.
11. GENERAL PROVISIONS Paragraph 6.10 and Paragraphs 6.12 to 6.26 of the CUSC are incorporated into this BELLA mutatis mutandis.
12. WIDER TRANSMISSION REINFORCEMENT WORKS The Company shall keep the User informed as to its progress on the Wider Transmission Reinforcement Works. IN WITNESS WHEREOF the hands of the duly authorised representatives of the parties hereto at the date first above written S2E5-8
Schedule 2 Exhibit 6
1. The company registered in England with number 11014226 (“The Company”), which expression shall include its successors and/or permitted assigns); and
2. [] a company registered in [] with number [] whose registered office is at [] ("User", which expression shall include its successors and/or permitted assigns). WHEREAS
The Company and the User are parties to the CUSC Framework Agreement which gives effect to the document designated by the Secretary of State and adopted by The Company as the Connection and Use of System Code pursuant to the ESO Licence, as from time to time modified pursuant to the ESO Licence (the “CUSC”).
The Company and the User are parties to a [Bilateral Connection Agreement] [Bilateral Embedded Generation Agreement] dated [ ] (ref: [ ]) in respect of the connection to and\or use of the National Electricity Transmission System at [ ] (the “Bilateral Agreement”).
Under the terms of the Bilateral Agreement restrictions on availability apply under certain conditions and as a result the User is required to enter into this Transmission Related Agreement on the terms and subject to the conditions set out below. NOW IT IS HEREBY AGREED as follows:
1. DEFINITIONS, INTERPRETATION AND CONSTRUCTION
Unless the subject matter or context otherwise requires or is inconsistent therewith, terms and expressions defined in Section 11 of the CUSC and in the Bilateral Agreement, [the Construction Agreement,] the Balancing and Settlement Code and the Grid Code have the same meanings, interpretations or constructions in this Transmission Related Agreement.
“Base Rate“ shall be defined in respect of any day as the rate per annum which is equal to the base lending rate from time to time of Barclays Bank plc as at the close of business on the immediately preceding week-day other than a Saturday on which banks are open in the City of London (the “Business Day”).
“Enhanced Rate” shall be defined in respect of any day as the rate per annum which is 4 % per annum above the base lending rate from time to time of Barclays Bank plc at the close of business immediately preceding the Business Day.
“Party” shall be defined as each party to this Transmission Related Agreement and any successor(s) in title to, or permitted assign(s) of such person.
References in this Transmission Related Agreement to “this Transmission Related Agreement” include references to the Schedule hereto.
On the fifth Business Day of each calendar month The Company shall where applicable send to the User a statement (“the Provisional Monthly Statement”) consisting of:-
a statement (the “Provisional Statement”) containing details of the payment calculation(s) made pursuant to Clause 3.2 of this Transmission Related Agreement in respect of the previous month; and,
if relevant, a statement showing adjustments to be made (net of interest) in relation to any dispute regarding the payment calculation(s) in respect of any month prior to the previous month (“the Provisional Adjustments Statement”), in each case showing the payments due to or from the User as a result thereof and the net amount due to or from the User.
If the User disagrees with any of the dates, times, facts or calculations as set out in the Provisional Statement and/or the Provisional Adjustments Statement, it shall produce to The Company the evidence which it relies upon in support of such disagreement. The Parties shall discuss and endeavour to resolve the matter but if it cannot be resolved the Parties may have recourse to an arbitrator appointed pursuant to Paragraph 7.4 of the CUSC. Where a dispute is resolved, The Company shall adjust the account between itself and the User accordingly in the Final Statement where practicable or otherwise in the next Provisional Adjustments Statement which it issues.
Thirteen Business Days after the date specified in paragraph 1.1 The Company shall send to the User a statement (“the Final Monthly Statement”) consisting of:-
a statement (“the Final Statement”) incorporating:-
in the case of an undisputed Provisional Statement (or where any dispute has been resolved and no changes have been effected to the calculations contained in the Provisional Statement) the calculation made under paragraph 1.1.(a) together with an invoice for the amount shown as being due to or from the User (as the case may be) ; or
In the case of a disputed Provisional Statement where the dispute has been resolved prior to the issue of the Final Statement and changes to the calculations contained in the Provisional Statement have been agreed, a revised calculation made under paragraph 1.1(a) together with an invoice for the amount shown as being due to or from the User (as the case may be) ; and
if a Provisional Adjustments Statement has been issued in accordance with paragraph 1.1(b), a statement (“the Final Adjustments Statement”) showing adjustments to be made in relation to any dispute concerning any month prior to the previous month together with interest thereon up to and including the date of payment referred to in paragraph 1.5 such adjustments will be reflected in the invoice referred to at paragraph 1.3 (a) .
Where either Party discovers that any previous Provisional Monthly Statement or Final Monthly Statement contains an arithmetic error or omission The Company shall adjust the account between itself and the User accordingly in the next Provisional Adjustments Statement which it issues, setting out the reason why the adjustment has been made and the provisions of paragraph 1.2 shall apply mutatis mutandis to such adjustments.
The due date of payment in respect of any disputed amount subsequently determined or agreed to be payable shall be the date for payment of the relevant Provisional Statement from which the dispute arises. The successful Party to the dispute shall be entitled to interest at the Base Rate on any disputed amount until the date of payment.
Each Party shall pay to the other the net amount shown as due from that Party in the Final Monthly Statement within three Business Days of the date on which such statement is issued.
If either Party (“the Defaulting Party”), in good faith fails to pay under paragraph 1.6 any amount properly due under this Transmission Related Agreement, then such Defaulting Party shall pay to the other Party interest on such overdue amount from and including the due date of such payment to (but excluding) the date of actual payment at the Base Rate. Provided that should the Defaulting Party otherwise fail to pay any amount properly due under this Transmission Related Agreement on the due date then the Defaulting Party shall pay to the other Party interest on such overdue amount at the Enhanced Rate from the due date on which such payment was properly due to (but excluding) the date of actual payment. Any interest shall accrue from day to day.
If following a dispute or by virtue of paragraphs 1.2 or 1.4 it is determined or agreed that a Party was entitled to a further payment from the other Party, that Party shall be entitled to interest at the Base Rate on the amount of such further payment from the due date calculated in accordance with paragraph 1.5 until the date of payment.
If following a dispute or by virtue of the provisions of paragraphs 1.2 or 1.4 it is determined or agreed that a Party was not entitled to any payment it has received, the other Party shall be entitled to interest at the Base Rate on the amount so paid from the date of payment until the date of repayment or the date when the first Party makes a payment to the other Party which takes such payment into account.
Notwithstanding the terms thereof, The Company shall be entitled to set off against any amount falling due and payable by The Company to the User under any Balancing Services Agreement from time to time in force, all or a part of any payment or payments falling due and payable by the User to The Company under this Transmission Related Agreement.
All amounts specified hereunder shall be exclusive of any Value Added Tax or other similar tax and The Company or the User as the case may be shall pay the Value Added Tax at the rate for the time being and from time to time properly chargeable in respect of all payments made under this Transmission Related Agreement.
Save where otherwise stated, references in this Schedule to paragraphs are references to paragraphs of this Schedule.
2. COMMENCEMENT AND TERM
This Transmission Related Agreement shall come into effect on the date hereof and shall continue in force and effect until the Bilateral Agreement is terminated in accordance with the CUSC.
Any provisions for payment shall survive termination of this Transmission Related Agreement.
3. PAYMENTS BY THE USER
Where in accordance with Clause [9] of the Bilateral Agreement the provisions of this Transmission Related Agreement are expressed to apply then the User shall make a payment to The Company determined in accordance with Clause 3.2 hereof.
The payment by the User referred to in Clause 3.1 above shall be an amount calculated on a Settlement Period basis and for each relevant BM Unit and shall be determined in accordance with the provisions set out below:- Where in respect of all or part of an Outage Period:-
in respect of a BM Unit, either the prevailing Maximum Export Limit or the prevailing Maximum Import Limit is other than that permitted under Clause [10/9] of the Bilateral Agreement; and
The Company issues in accordance with the Grid Code a Bid-Offer Acceptance requiring the BM Unit to reduce the absolute value of Output or Demand to the figure as required under Clause [9] of the Bilateral Agreement, then the following formula shall apply:- ( ( ) ( ) ) = n min 0, PBn QABn + max 0, PO n QAO n PNGC i ij ij ij ij J j Where:- PNGC represents the payment from the User to The Company in respect of BM Unit i i n represents the sum over all Bid-Offer Pair Numbers for the BM Unit J j represents the summation over all Settlement Periods j in the set of Settlement Periods J being those Settlement Periods in respect of which both the events specified in (a) and (b) above occurred And: PBn = Bid Price n for BM Unit i in Settlement Period j ij QABn = Period BM Unit Total Accepted Bid Volume ij PO n = Offer Price n for BM Unit i in Settlement Period j ij QAO n = Period BM Unit Total Accepted Offer Volume ij n = Bid–Offer Pair Number i = BM Unit j = Settlement Period
The payment by the User referred to in Clause 3.1 above shall be made in accordance with the Schedule to this Transmission Related Agreement.
4. VARIATIONS
Subject to Clause 4.2, no variation to this Transmission Related Agreement shall be effective unless made in writing and signed by or on behalf of both The Company and the User.
The Company and the User shall effect any amendment required to be made to this Transmission Related Agreement by the Authority as a result of a change in the CUSC, the ESO Licence or the Transmission Licence, an order or direction made pursuant to the Act or a Licence, or as a result of settling any of the terms hereof. The User hereby authorises and instructs The Company to make any such amendment on its behalf and undertakes not to withdraw, qualify or revoke such authority or instruction at any time.
5. GENERAL PROVISIONS The following provisions of the CUSC shall apply to this Transmission Related Agreement mutatis mutandis as if set out in full herein:- Paragraphs 6.12 (Liability), 6.14 (Transfer and Sub-contracting), 6.15 (Confidentiality), 6.16 (Data), 6.18 (Intellectual Property), 6.19 (Force Majeure), 6.20 (Waiver), 6.21 (Notices), 6.22 (Third Party Rights), 6.23 (Jurisdiction), 6.25 (Governing Law), 6.26 (Severance of Terms),
(Language), 6.38 (Directions Relating to national security), 7.4 (Disputes) and 7.5 (Third Party Claims).
COUNTERPARTS This Transmission Related Agreement may be entered into in any number of counterparts and by different parties in separate counterparts, each of which when signed shall constitute an original but all the counterparts shall together constitute but one and the same agreement. IN WITNESS WHEREOF the hands of the duly authorised representatives of the parties hereto at the date first above written
Schedule 2 Exhibit 7
1. DEFINITIONS, INTERPRETATION AND CONSTRUCTION
2. CONDITION PRECEDENTS AND COMMENCEMENT
This VLPA shall commence on the date hereof.
It is a condition of this VLPA that the VLP Assets operated by the User are associated to a SMRS registered Boundary Point Metering System as per the Balancing and Settlements Code.
OUTAGES & NETWORK MANAGEMENT
3. OUTAGES & NETWORK MANAGEMENT
Subject to the provisions of the Grid Code, The Company and the User shall be entitled to plan and execute outages on parts of, in the case of The Company, the National Electricity Transmission System or Transmission Plant or Transmission Apparatus and in the case of the User, its VLP Assets, at any time and from time to time.
GRID CODE MATTERS
4. GRID CODE MATTERS
The User is required (as per paragraph 6.3.1 of the CUSC) to comply with the relevant parts of the Grid Code which apply in respect of the relevant Boundary Point Metering Systems associated with the VLP Assets, as amended in accordance with the following provisions of this Clause 4.
The provisions in BC1 and BC2 of the Grid Code provide that compliance is required with such provisions in respect of those VLP Assets in this VLPA.
COMPLIANCE WITH TECHNICAL CONDITIONS
5. COMPLIANCE WITH TECHNICAL CONDITIONS
The Company and the User shall operate respectively the National Electricity Transmission System and the User System with the special automatic facilities and schemes set out in Appendix F5 to this VLPA.
The User shall ensure that the VLP Assets which it operates for the purposes of this VLPA complies with the technical conditions set out in Appendix F5 to this VLPA.
The User shall use all reasonable endeavours to ensure that the VLP Assets shall continue to comply with the technical conditions set out in Appendix F5 of this VLPA.
TERM [Company Name] [Reference] [Month Year]
6. TERM
Subject to the provisions for earlier termination set out in the CUSC, this VLPA shall continue until; i) the User notifies The Company in writing, providing no less than 28 days notice, of its wish to terminate this VLPA, or; ii) the User has no VLP Assets registered to a Secondary BMU and so The Company may give notice of termination in writing to the User whereupon this VLPA shall terminate 28 days from such notice.
Once an Event of Default has occurred and is continuing The Company may give notice of termination to the User whereupon this VLPA shall forthwith terminate.
VARIATIONS
7. VARIATIONS
Subject to 7.2 no variation to this VLPA shall be effective unless made in writing and signed by or on behalf of both The Company and the User.
The Company and the User shall effect any amendment required to be made to this VLPA by the Authority as a result of a change in the CUSC, Grid Code, the ESO Licence or the Transmission Licence, an order or direction made pursuant to the Act or a Licence, or as a result of settling any of the terms hereof. The User hereby authorises and instructs The Company to make any such amendment on its behalf and undertakes not to withdraw, qualify or revoke such authority or instruction at any time.
GENERAL PROVISIONS Paragraph 6.10, Paragraphs 6.12 to 6.26 and Paragraph 6.38 of the CUSC are incorporated into this VLPA mutatis mutandis. IN WITNESS WHEREOF the hands of the duly authorised representatives of the parties hereto at the date first above written [Company Name] [Reference] [Month Year]
8. GENERAL PROVISIONS [Company Name] [Reference] [Month Year] THIS VIRTUIAL LEAD PARTY AGREEMENT is made on the [] day of [] 20[XX] BETWEEN
1. The company registered in England with number 11014226 (“The Company”, which expression shall include its successors and/or permitted assigns); and
2. [] a company registered in [] with number [] whose registered office is at [] (the “User”, which expression shall include its successors and/or permitted assigns). WHEREAS
Pursuant to the ESO Licence, The Company is required to prepare a Connection and Use of System Code (“CUSC”) setting out the terms of the arrangements for connection to and use of the National Electricity Transmission System.
The User has applied to The Company in the capacity of a Virtual Lead Party who intends to operate one or more Secondary BMU Units.
As at the date hereof, The Company and the User are parties to the CUSC Framework Agreement (being an agreement by which the CUSC is made contractually binding between the parties).
This Virtual Lead Party Agreement (“VLPA”) is entered into pursuant to the CUSC and shall be read as being governed by it. NOW IT IS HEREBY AGREED as follows: [Company Name] [Reference] [Month Year]
DEFINITIONS, INTERPRETATION AND CONSTRUCTION Unless the subject matter or context otherwise requires or is inconsistent therewith, terms and expressions defined in Section 11 of the CUSC have the same meanings, interpretations or constructions in this VLPA.
CONDITION PRECEDENTS AND COMMENCEMENT
Schedule 3
1. Definitions and Interpretations
For the purpose of this Part I and the Appendices, “Obligatory Reactive Power Service” means the Mandatory Ancillary Service referred to in Grid Code CC 8.1 which the relevant User is obliged to provide (for the avoidance of doubt, as determined by any direction in force from time to time and issued by the Authority relieving a relevant User from the obligation under its Licence to comply with such part or parts of the Grid Code or any Distribution Code or, in the case of The Company, the ESO Licence as may be specified in such direction) in respect of the supply of Reactive Power (otherwise than by means of synchronous or static compensation except in the case of a Power Park Module where synchronous or static compensation within the Power Park Module may be used to provide Reactive Power) and in respect of the required Reactive Power capability referred to in Grid Code CC 6.3.2. This Mandatory Ancillary Service shall comprise, in relation to a Generating Unit, DC Converter or Power Park Module compliance by the relevant User in all respects with all provisions of the Grid Code applicable to it relating to that supply of Reactive Power and required Reactive Power capability, together with the provision of such despatch facilities (including the submission to The Company of all relevant technical, planning and other data in connection therewith) and metering facilities (meeting the requirements of Appendix 4), and upon such terms, as shall be set out in a Mandatory Services Agreement entered into between The Company and the relevant User. For the avoidance of doubt, “Obligatory Reactive Power Service” when used in this Part I and the Appendices excludes provision of Reactive Power capability from Synchronous Compensation and from static compensation equipment ( except in the case of a Power Park Module where synchronous or static compensation SC3-1 within the Power Park Module may be used to provide Reactive Power, and the production of Reactive Power pursuant thereto.
For the purpose of this Part I and the Appendices, “Enhanced Reactive Power Service” means the Commercial Ancillary Service of:-
the provision of Reactive Power capability of a Generating Unit, DC Converter or Power Park Module in excess of that which a User is obliged to provide from that Generating Unit, DC Converter or Power Park Module, under and in accordance with the Connection Conditions of the Grid Code and the production of Reactive Power pursuant thereto, which a User may agree to provide and which is capable of being made available to, and utilised by, The Company in accordance with the Balancing Codes of the Grid Code (or as may otherwise be agreed in writing between The Company and a User) for the purposes of voltage support on the GB Transmission System, upon and subject to such terms as may be agreed in writing between The Company and such User; or
the provision of Reactive Power capability from Synchronous Compensation or from static compensation equipment (except in the case of a Power Park Module where Grid Code CC8,1 specifies that such Reactive Power capability is a Mandatory Ancillary Service) and the production of Reactive Power pursuant thereto, which a User or any other person may agree to provide and which is capable of being made available to, and utilised by, The Company for the purposes of voltage support on the GB Transmission System, upon and subject to such terms as may be agreed in writing between The Company and such User or other person; or
such other provision or enhancement of capability of Plant and/or Apparatus or other equipment to generate or absorb Reactive Power, and the production of Reactive Power pursuant thereto, which a User or any other person may agree to provide and which is capable of being made available to, and utilised by, The Company for the purposes of voltage support on the GB Transmission System, upon and subject to such terms as may be agreed in writing between The Company and such User or other person. SC3-2
Unless otherwise defined in the CUSC, terms and expressions found in the Grid Code have the same meanings, interpretations and constructions in this Part I and the Appendices.
In this Part I and the Appendices, except where the context otherwise requires, references to a particular Appendix, Part, Section, sub-section, Paragraph or sub-Paragraph shall be a reference to a particular Appendix to or part of this Part I or, as the case may be, that Section, sub-section, Paragraph or sub- Paragraph in this Part I.
In respect of each BM Unit, a Tenderer must nominate a Registered Capacity which it anticipates will be the actual Registered Capacity on the Contract Start Day for that BM Unit (in this Appendix 5 referred to as “Nominated Registered Capacity”) to be used for the duration of the Market Agreement. All capability data used for the purpose of a Tender must be expressed as the capability of a BM Unit at the Commercial Boundary and must represent the value of Reactive Power output which can be supplied continuously at the Commercial Boundary when the BM Unit is operating at the Nominated Registered Capacity.
In respect of each BM Unit, all capability data relating to the provision of the Enhanced Reactive Power Service specified in sub-Paragraph 1.2(a) of this Part I must be expressed as the capability of that BM Unit at the Commercial Boundary across a system voltage range to be specified by the Tenderer in its Tender (or otherwise in accordance with directions given by The Company).
All Reactive Power capability data in respect of a BM Unit must be expressed as positive, whole numbers in Mvar, with leading and lagging capability data distinguished by the subscripts and . lead lag
In respect of each BM Unit, and subject to any directions issued from time to time by The Company with regard to such values, the User must submit at least one Reactive Power capability value and may in addition submit up to a further two Reactive Power capability values (all three being “Tendered Capability Breakpoints”), for both leading and lagging Mvar. One of these Tendered Capability Breakpoints, in respect of both leading and lagging Mvar, must be equivalent to the minimum Reactive Power capability of a BM Unit which a User is obliged to provide under SC3-36 and in accordance with the Connection Conditions of the Grid Code (to the nearest whole Mvar) after application of the principles set out in sub- paragraphs 1.2 and 1.3 above and as further described in the package of information referred to in sub-Paragraph 3.3(b)(i) of this Part I.
The Tendered Capability Breakpoints shall be defined for the purposes of this Appendix as TQ1, TQ2, TQ3, for leading and lagging Mvar as the case may be, where:- TQ3 > TQ2 > TQ1 > 0 lead lead lead and TQ3 > TQ2 > TQ1 > 0 lag lag lag
Where only two Tendered Capability Breakpoints are tendered, for leading or lagging Mvar as the case may be, then the value of TQ3 shall be deemed to be null for the purposes of calculating payments for capability and utilisation and no additional payments for capability will fall due and payable in respect of a BM Unit for the provision of Reactive Power capability above Tendered Capability Breakpoint TQ2.
Where only one Tendered Capability Breakpoint is tendered, for leading or lagging Mvar as the case may be, then the values of TQ2 and TQ3 shall be deemed to be null for the purposes of calculating payments for capability and utilisation and no additional payments for capability will fall due and payable in respect of a BM Unit for the provision of Reactive Power capability above Tendered Capability Breakpoint TQ1.
The Reactive Power capability value at zero Mvar (referred to in paragraph 2 below as Q0) shall be treated as a Tendered Capability Breakpoint for the purposes of tendering capability and utilisation prices and calculating capability and utilisation payments.
Prices In respect of each Tendered Capability Breakpoint, prices submitted by Users must be zero or positive, quoted in pounds sterling to the nearest tenth of a penny and shall otherwise be tendered as described in sub- paragraphs 2.1, 2.2 and 2.3 below. The prices shall be described using the following notation:- C1 is the price applicable between Tendered Capability Breakpoints lag Q0 and TQ1 including TQ1 lag lag C2 is the price applicable between Tendered Capability Breakpoints lag TQ1 and TQ2 including TQ2 lag lag lag SC3-37 C3 is the price applicable between Tendered Capability Breakpoints lag TQ2 and TQ3 including TQ3 lag lag lag C1 is the price applicable between Tendered Capability Breakpoints lead Q0 and TQ1 including TQ1 lead lead C2 is the price applicable between Tendered Capability Breakpoints lead TQ1 lead and TQ2 including TQ2 lead lead C3 is the price applicable between Tendered Capability Breakpoints lead TQ2 lead and TQ3 including TQ3 lead lead where C shall represent CU, CA or CS as the case may be.
2. Obligatory Reactive Power Service – Default Payment Arrangements
Notwithstanding any other provision of the CUSC, the provisions of this Part I and the Appendices, together with the Mandatory Services Agreements referred to in sub-Paragraph 2.6, shall govern the rights and obligations of The Company and relevant Users with respect to payments to be made by The Company to such Users for the provision of the Obligatory Reactive Power Service.
Subject always to Paragraph 3, and notwithstanding the provisions of any Ancillary Services Agreement now or hereafter in effect (but subject always to sub-Paragraph 4.2), the payments to be made by The Company to Users for the provision of the Obligatory Reactive Power Service in all Mandatory Services Agreements under which Users are or will be paid for the Obligatory Reactive Power Service shall, subject always to sub- Paragraph 2.7, comprise solely payments for utilisation determined in respect of each Settlement Period in accordance with sub- Paragraph 2.3.
Save to the extent and for the duration of any Market Agreement (as defined in sub-Paragraph 3.1) which may be entered into between The Company and a User as referred to in Paragraph 3 the utilisation payment for provision of the Obligatory Reactive Power Service shall be determined in accordance with the provisions of Appendix 1.
The Parties acknowledge and agree that, as at 1st October 1997:-
the totality of payments for the provision of the Obligatory Reactive Power Service, determined in accordance with the provisions of this Paragraph 2, reflect so far as SC3-3 reasonably practicable the overall variable costs (on the basis of the charging principles set out in Appendix 7) incurred across all relevant Generating Units of the provision of the Obligatory Reactive Power Service (whether or not payments are made in respect of those Generating Units pursuant to this Paragraph 2 or pursuant to Market Agreements entered into in accordance with Paragraph 3); and
such totality of payments will continue to reflect those overall variable costs notwithstanding all and any variations thereto reasonably anticipated at such date.
It is hereby agreed and acknowledged that nothing in this Part I and the Appendices shall affect in any way the obligation on each User to comply with the provisions of the Grid Code insofar as they relate to Reactive Power. For the avoidance of doubt, and without limiting the foregoing, it is hereby agreed and acknowledged that, notwithstanding that the payments for the Obligatory Reactive Power Service shall comprise solely payments for utilisation, nothing in this Part I and the Appendices shall relieve Users from the obligations to comply with the provisions of the Grid Code in relation to Reactive Power by virtue of Paragraph 6.3.3 of the CUSC or otherwise howsoever.
Mandatory Services Agreements have been and will continue to be entered into bilaterally between The Company and Users but it is intended that, subject as provided below, Mandatory Services Agreements between The Company and Users providing the Obligatory Reactive Power Service will be amended or (if not in existence when this Part I takes effect) concluded so as to give effect to the provisions of sub-Paragraphs 2.2 and 2.3. Subject always to sub-Paragraphs 2.8 and 4.2, The Company and each relevant User therefore agree, as soon as reasonably practicable, to amend the existing Mandatory Services Agreement or conclude a new Mandatory Services Agreement in respect of each relevant Generating Unit, DC Converter or Power Park Module in order to give effect to the provisions of sub-Paragraphs 2.2 and 2.3.
For the avoidance of doubt, no payments referred to in this Paragraph 2 shall be payable by The Company to a User in relation to any Generating Unit, DC Converter or Power park Module unless and until the relevant Mandatory Services Agreement is so amended or concluded as provided in sub- Paragraph 2.6. SC3-4
Notwithstanding the foregoing provisions of this Paragraph 2, and without prejudice to Paragraph 5, The Company shall only be obliged to amend or conclude any Mandatory Services Agreement with regard to any Generating Unit, DC Converter or Power Park Module if:-
either:-
the leading or lagging Reactive Power capability required of that Generating Unit, DC Converter or Power Park Module in accordance with Grid Code CC 6.3.2 (or, where the Generating Unit, DC Converter or Power Park Module is Derogated Plant of an Embedded Exemptable Large Power Station the level to which, it has been Derogated) is 15Mvar or more (measured at the Commercial Boundary); or
that Generating Unit, DC Converter or Power Park Module is at or comprises a Large Power Station where such required capability is less than 15Mvar (measured at the Commercial Boundary) and the User requests The Company in writing to so amend or conclude a Mandatory Services Agreement with respect thereto; and
there exists in relation to that Generating Unit, DC Converter or Power Park Module metering facilities meeting the requirements of Appendix 4.
For the purposes of this Part I and the Appendices, subject always to sub-paragraph 2.2, the quantities of Mvarh imported and exported by a BM Unit shall be derived from the relevant Metering System for that BM Unit registered pursuant to Section K of the Balancing and Settlement Code.
Where the existing Metering System for the BM Unit registered pursuant to Section K of the Balancing and Settlement Code does not incorporate Metering Equipment capable of measuring and recording Mvarh imports and exports for that BM Unit for each Settlement Period, then the relevant User shall register or procure that there is registered pursuant to Section K of the Balancing and Settlement Code a Metering System which does incorporate such Metering Equipment.
All relevant Metering Equipment identification and location codes shall be set out in the relevant Mandatory Services Agreement, and the User hereby agrees to facilitate agreement between The Company and that User with respect thereto by providing The Company as soon as reasonably practicable following request with all necessary supporting diagrams and other written documentation.
Where the configuration of the Metering System is such that:-
Mvarh import and export values for the BM Unit are not measured at the Commercial Boundary; and/or 2.4.2 Mvarh import and export values for the BM Unit are measured by more than one Meter; and/or SC3-33 2.4.3 the Mvarh import and export values for the BM Unit are measured by a Meter which also measures the Mvarh import and export values of one or more other Generating Units, DC Converters, Power Park Modules Plant and Apparatus or other equipment, then appropriate loss adjustment factors and aggregation methodologies (as the case may be) shall be used to determine on a Settlement Period basis the Mvarh import value and Mvarh export value for the relevant BM Unit at the Commercial Boundary to be used for the purposes of this Part I. The appropriate factors and methodologies for each relevant BM Unit shall be agreed by The Company and each relevant User (both acting reasonably) in the relevant Mandatory Services Agreement by adoption of one or more of the factors or methodologies set out in the document entitled “Methodology Document for the Aggregation of Reactive Power Metering” (as amended from time to time) published by The Company for this purpose. This document shall specify the respective factors and methodologies to be applied for particular Metering System configurations in order to determine so far as reasonably practicable the Mvarh import value and Mvarh export value for the relevant BM Unit at the Commercial Boundary as required by this sub-paragraph 2.4
Other Plant and/or Apparatus (or other equipment) In all other cases not covered by paragraph 2, unless otherwise agreed in writing by The Company, the following provisions shall apply:-
Utilisation Prices (CU)
Utilisation prices submitted by Users must be:-
quoted in units of £/Mvarh; and
no greater than £999.999/Mvarh.
Utilisation prices must increase across the Reactive Power capability range, for leading or lagging Mvar as the case may be, such that:- CU3 CU2 CU1 0 lead lead lead CU3 CU2 CU1 0 lag lag lag
Utilisation payments shall be made for metered Reactive Power output and shall be calculated in accordance with Appendix 2.
Available Capability Prices (CA)
Available capability prices submitted by Users must be:-
quoted in units of £/Mvar/h; and
no greater than £999.999/Mvar/h.
Available capability prices must increase across the Reactive Power capability range, for leading or lagging Mvar as the case may be, such that:- SC3-38 CA3 CA2 CA1 0 lead lead lead CA3 CA2 CA1 0 lag lag lag
Available capability payments shall be calculated in accordance with Appendix 2
Synchronised Capability Prices (CS)
Synchronised capability prices submitted by Users must be:-
quoted in units of £/Mvar/h; and
no greater than £999.999/Mvar/h.
Synchronised capability prices must increase across the Reactive Power capability range, for leading or lagging Mvar as the case may be, such that:- CS3 CS2 CS1 0 lead lead lead CS3 CS2 CS1 0 lag lag lag
Synchronised capability payments shall be calculated in accordance with Appendix 2.
Indexation Where a Tender is submitted in respect of a period which exceeds the minimum twelve month period required by sub-Paragraph 3.3(d)(v) of this Part I, then the User shall submit one mechanism for calculating indexation on an annual basis which shall apply to all prices submitted in the Tender for all subsequent periods of twelve months following the minimum twelve month period to which the Tender applies. Such mechanism shall be based on either the Retail Prices Index (as referred to in paragraph 3 of Appendix 1), a fixed percentage (which may be positive, zero or negative) or a summation of such Retail Prices Index and such fixed percentage.
Other Technical Information A User shall submit with a Tender such other technical information as reasonably directed by The Company in accordance with sub-Paragraph 3.3 (b)(i) of this Part I. Such information may include (without limitation):- SC3-39 4.1 in relation to a Tender for the Enhanced Reactive Power Service specified in sub-Paragraph 1.2 (a) of this Part I, details of the capability of the Generating Unit, DC Converter or Power Park Module (as the case may be) to provide Reactive Power either:-
in the case of Generating Unit, at the generator stator terminals: or
in the case of a Non-Synchronous Generating Unit, DC Converter or Power Park Module, either at the Grid Entry Point in England and Wales or at the HV side of the 33/132 kV or 33/275 kV or 33/400 kV transformer for Users connected to the National Electricity Transmission System in Scotland or the User System Entry Point if Embedded, In each case by reference to the Generator Performance Chart submitted in accordance with Operating Condition 2.4.2 of the Grid Code, which capability must represent the true operating characteristics of that Generating Unit, DC Converter or Power Park Module; and 4.2 details of the system voltage range over which the User proposes to make available from the Generating Unit, DC Converter or Power park Module such Enhanced Reactive Power Service (and in each case any restrictions thereto); and 4.3 in relation to a Tender for the Enhanced Reactive Power Service specified in sub-Paragraph 1.2 (a) of this Part I, the ambient air temperature at which such Enhanced Reactive Power Service is specified, and variations to such Enhanced Reactive Power Service in accordance with any air temperature range specified by The Company; and 4.4 details, including prices, of any additional services offered as part of any Enhanced Reactive Power Service (not being the Enhanced Reactive Power Service specified in sub-Paragraph 1.2 (a) of this Part I); and 4.5 any restrictions on The Company selecting part of an Enhanced Reactive Power Service. SC3-40 Appendix 6 Qualification and Evaluation Criteria Section A – Qualification Criteria
Without prejudice to the requirements of sub-Paragraph 3.3 of this Part I, all Tenders must satisfy the following mandatory qualification criteria:- 1.1 in relation to a Tender for provision of the Enhanced Reactive Power Service specified in sub-Paragraph 1.2 (a) of this Part I, the leading and/or lagging capability (as the case may be) comprised therein, being the capability in excess of that required under and in accordance with the Connection Conditions of the Grid Code, must be at least 15 Mvar leading and/or 15 Mvar lagging (as the case may be) or (if lower) such amount of Mvar representing an additional 10% of that required under and in accordance with the Connection Conditions of the Grid Code (in each case as measured at the Commercial Boundary); and 1.2 in relation to a Tender for provision of any other Enhanced Reactive Power Service, the leading and/or lagging capability (as the case may be) comprised therein meet the requirements of sub- Paragraph 2.8(a) of this Part I; and 1.3 the tendered capability must be subject to Mvar metering meeting the requirements of Appendix 4; and 1.4 the tendered capability must be subject to Mvar despatch facilities reasonably acceptable to The Company, incorporating the ability for The Company to receive from the Tenderer relevant technical, planning and other data in The Company’s reasonable opinion necessary in connection therewith; and 1.5 the site in question must be the subject of an agreement for connection to, and/or use of, the GB Transmission System or (as the case may be) a Distribution System. Section B – Evaluation Criteria
The overall economic value of a Tender (and where appropriate any part thereof) will be assessed by reference to the following criteria (which are not listed in any order of importance or priority):- SC3-41 2.1 in relation to a Generating Unit, DC Converter or Power park Module providing the Obligatory Reactive Power Service, a comparison with the default payment arrangements for that Generating Unit, DC Converter or Power Park Module including the effect (if any) of the balance of tendered capability and utilisation prices as a hedge against forecast costs of that Generating Unit, DC Converter or Power Park Module pursuant to the default payment arrangements;
the location of the tendered capability and its effectiveness in providing voltage support for the GB Transmission System;
its interaction with other Tenders, in terms (inter alia) of relatives prices and capability tendered and relative effectiveness in providing voltage support as referred to in sub-paragraph 2.2 above;
forecast savings (if any) in constraint costs resulting from the consequential effect on power flows; and 2.5 any forecast benefit or detriment attributable to it in the context of the investment planning process referred to at paragraph 4 below.
Particular factors affecting the value of a Tender (and where appropriate any part thereof) may include (without limitation) the following evaluation criteria (which are not listed in any order of importance or priority):- 3.1 the amount of leading and lagging Mvar tendered and the impact (if any) of any changes in the technical data, the Registered Capacity and other information submitted to The Company pursuant to the Data Registration Codes of the Grid Code since the date of submission of the Tender;
Subject always to sub-paragraph 2.5, the appropriate factors and methodologies for each relevant BM Unit shall be agreed by The Company and each relevant User (both acting reasonably) in the relevant Mandatory Services Agreement by adoption of one or more of the factors or methodologies set out in the document entitled “Methodology Document for the Aggregation of Reactive Power Metering” (as amended from time to time) published by The Company for this purpose. This document shall specify the respective factors and methodologies to be applied for particular Metering System configurations in order to determine so far as reasonably practicable the Mvarh import value and Mvarh export value for the relevant BM Unit at the Commercial Boundary as required by this sub-paragraph 2.4.
Loss adjustment factors and aggregation methodologies need not be agreed between The Company and the relevant User in connection with any configuration described in sub-paragraph 2.4.3 in respect of periods prior to (1st April 1998).
Matters for Review - Appendix 7 of MCUSA, Schedule 5 Matter Date of review
The values of X and Y referred to 1st October 1998 in Appendix 1 in respect of Settlement Periods from (and including) 1st April 1999. Applicable principle: The degree and extent to which a competitive market has been established in accordance with the SC3-65 provisions of this Schedule (taking into account, inter alia, the amount of Mvar capability the subject of Market Agreements and the utilisation thereof).
Any payment arrangements 1st October 1999 formulated by The Company in conjunction with any unlicensed providers . Applicable principle: The extent to which it is reasonably practicable to achieve consistency with the provisions of Appendix 1 or Appendices 2 and 5 (as the case may be). 1st October 1999
The treatment of Trading Units for the purposes of metering and calculation of Mvar capability in connection with this Schedule. Applicable principle: None
The indexation factor referred to in 1st October 2000 Appendix 1 to apply in respect of all periods from (and including) 1st April 2001. Applicable principles: Those charging principles set out in Appendix 8.
(a) The extent of any change in Not applicable the nature of, or extent of recovery under the Balancing and Settlement Code of, variable costs incurred or to be incurred by Generating Units providing the Obligatory Reactive Power Service; SC3-66 and
the extent to which such changes should lead to a change in the specific costs identified in paragraph 1 of Appendix 8 upon which the totality of payments referred to therein is based and founded. Applicable principle: That, to the extent innovation in the development of the default payment arrangements or the giving of appropriate economic signals is not thereby stifled, the specific costs from time to time identified in paragraph 1 of Appendix 8 (and upon which the totality of payments referred to therein is based and founded) should continue to comprise the totality of variable costs (actual or estimated) incurred or to be incurred in respect of, and aggregated across, all Generating Units providing the Obligatory Reactive Power Service, provided always that each of those specific costs from time to time identified shall only be a variable cost not recovered under the Balancing and Settlement Code which:-
is not being incurred at the date this Schedule comes into effect; or
is being incurred at the date SC3-67 this Schedule comes into effect and as at that date is either identified as a specific cost in paragraph 1 of Appendix 8 or is being recovered under the Balancing and Settlement Code.
Charging Principles - Appendix 8 of MCUSA Schedule 5 In accordance with the relevant provisions of this Part I, the following principles are intended to form the basis of the default payment arrangements for the provision of the Obligatory Reactive Power Service set out in this Schedule I and are intended to be taken into account in any review of the indexation factor referred to in Appendix 1. However, they are not intended to stifle innovation in the development of the default payment arrangements or the giving of appropriate economic signals. It is therefore the Parties’ intention that, upon any change in the nature of, or extent of recovery under the Balancing and Settlement Code of, variable costs (actual or estimated) incurred or to be incurred by Generating Units providing the Obligatory Reactive Power Service, the specific costs identified in paragraph 1 below shall be a matter for review by the Transmission Users Group as more particularly referred to as item 5 of Appendix 7. SC3-68 Part II Not Used SC3-69
3. Obligatory Reactive Power Service and Enhanced Reactive Power Service – Market Payment Mechanism
Nothing in this Part I and the Appendices, and nothing in any Mandatory Services Agreement entered into or amended in accordance with sub-Paragraph 2.6, shall prevent or restrict:-
the entering into of an Ancillary Services Agreement or the amendment of any Mandatory Services Agreement between The Company and any User to provide for the making of payments by The Company to that User for the provision of the Obligatory Reactive Power Service on an alternative basis to that set out or referred to in Paragraph 2; or SC3-5
the entering of an Ancillary Services Agreement between The Company and any User (or other person) for the provision of an Enhanced Reactive Power Service, and any such agreement so entered into in accordance with the principles contained in sub-Paragraph 3.3 is referred to in this Part I and the Appendices as a “Market Agreement”.
The coming into effect of a Market Agreement in relation to any Generating Unit , DC Converter or Power Park Module shall, in respect of that Generating Unit, DC Converter or Power Park Module, suspend and replace for the duration thereof the provisions for payment for the Obligatory Reactive Power Service (if applicable) set out or referred to in Paragraph 2. In such a case, and for the avoidance of doubt, with effect from the expiry or termination of the Market Agreement, the provisions for payment for the Obligatory Reactive Power Service set out or referred to in Paragraph 2 shall in relation to that Generating Unit, DC Converter or Power Park Module cease to be suspended and shall resume full force and effect.
The following principles shall govern the entering into of Market Agreements:-
Relevant Dates
Each Market Agreement will commence on either 1st April or 1st October, whichever next follows the submission by The Company of the package of information as more particularly described in sub- Paragraph 3.3(b)(i) (“Contract Start Days”).
For the purposes of this sub-Paragraph 3.3:-
a “Market Day“ shall be a date not earlier than twelve weeks and not later than eight weeks prior to a Contract Start Day; and
a “Tender Period“ shall be a period of at least four consecutive weeks commencing on a date nominated by The Company and ending on a Market Day.
Submission of Tender information by The Company SC3-6
The Company shall, acting reasonably and having regard to the principles contained in this sub- Paragraph 3.3, compile a package of information for the use of interested parties comprising technical, procedural and contractual requirements, directions and specifications to govern Market Agreements to take effect from the following Contract Start Day. The Company shall ensure that such requirements, directions and specifications do not conflict with any of the principles contained in this sub-Paragraph 3.3 and so far as reasonably practicable do not discriminate between Tenderers.
Prior to the commencement of each Tender Period, The Company shall provide to all persons who shall by then have requested the same the package of information as more particularly described in sub- Paragraph 3.3(b)(i).
Submission of Tenders During the Tender Period, but for the avoidance of doubt not later than the Market Day, an interested party may submit to The Company:-
in relation to any Generating Unit, DC Converter or Power Park Module providing the Obligatory Reactive Power Service, prices for and Tendered Capability Breakpoints relating to the provision thereof; or
in relation to that Generating Unit, DC Converter or Power Park Module a tender for provision of the Enhanced Reactive Power Service specified in sub- Paragraph 1.2(a) and/or (b) and/or (c); and/or
in relation to any other Generating Unit, DC Converter or Power Park Module or other Plant and Apparatus (or other equipment), a tender for provision of the Enhanced Reactive Power Service specified in sub-Paragraph 1.2(b) and/or (c), in each case in accordance with sub-Paragraph 3.3(d). All such submissions are referred to in this Part I and the Appendices as “Tenders”, and “Tenderers” shall be construed accordingly. SC3-7
Form of Tenders
All Tenders submitted by Users which comprise:-
prices for and Tendered Capability Breakpoints relating to the provision of the Obligatory Reactive Power Service; and
terms for the provision of the Enhanced Reactive Power Service specified in sub- Paragraph 1.2(a), shall be completed on the basis that payment will be determined in respect of each Settlement Period in accordance with the formulae and other provisions set out in Appendix 2 and in the manner set out in Appendix 5.
All other Tenders (including without limitation those comprising terms for the provision of the Enhanced Reactive Power Service specified in sub-Paragraphs 1.2(b) and (c)) shall be submitted in accordance with and on the basis of such (if any) reasonable directions given by The Company in the package of information referred to in sub-Paragraph 3.3(b)(i) or otherwise in such manner as may be reasonably specified by The Company from time to time, which directions shall in either case be, so far as reasonably practicable, consistent with the provisions of Appendices 2 and 5.
Each Tender comprising prices for and Tendered Capability Breakpoints relating to the provision of the Obligatory Reactive Power Service shall be submitted on the basis that The Company may only select all (and not some) of the prices and Tendered Capability Breakpoints comprised therein.
Save where expressly provided otherwise in a Tender, each Tender comprising terms for the provision of an Enhanced Reactive Power Service shall be treated as having been submitted on the basis that The Company may select all or part only of the Reactive Power capability comprised therein (which, in the case of the Enhanced Reactive Power Service specified in sub-Paragraph 1.2(a), shall SC3-8 mean all or part only of the excess capability comprised therein).
All Tenders shall be submitted in respect of periods of whole and consecutive calendar months, to be not less than twelve months and in multiples of six months, to commence on the next following Contract Start Day. Save where expressly provided otherwise in a Tender, a Tender (whether in relation to the Obligatory Reactive Power Service or an Enhanced Reactive Power Service) shall be treated as having been submitted on the basis that The Company may select all or part only of any period so tendered (in multiples of six months), subject to a minimum period of twelve consecutive months, commencing on the next following Contract Start Day.
Qualification and Evaluation of Tenders
Each Tender must satisfy the mandatory qualification criteria set out in Section A of Appendix 6.
The Company shall evaluate and (without prejudice to sub-Paragraphs 3.3(d)(iii), (iv) and (v)) select Tenders (or part(s) thereof) on a basis consistent with its obligations under the Act the ESO Licence and the CUSC and, subject thereto, in accordance with the evaluation criteria set out in Section B of Appendix 6. Without limitation, The Company reserves the right to require tests of a Generating Unit, DC Converter or Power Park Module or other Plant and Apparatus (or other equipment), on a basis to be agreed with a Tenderer, as part of the evaluation of a Tender.
The Company shall use reasonable endeavours to evaluate Tenders within five weeks from each Market Day.
Entering into Market Agreements
Having selected a Tender (or part(s) thereof) in accordance with sub-Paragraph 3.3(e), The Company shall notify the relevant Tenderer that it wishes to enter into a Market Agreement in respect SC3-9 thereof, and that Tenderer and The Company shall each use reasonable endeavours to agree the terms of, and enter into a Market Agreement in respect thereof as soon as reasonably practicable but in any event not later than two weeks prior to the relevant Contract Start Day. Notwithstanding the foregoing, if a Market Agreement has not been entered into by the date being two weeks prior to the relevant Contract Start Day, then either The Company or the Tenderer shall be entitled, provided that it shall have used all reasonable endeavours to agree the terms of, and enter into, the Market Agreement as aforesaid, to notify the other that it no longer wishes to enter into the Market Agreement, whereupon the Tender in question shall be deemed to be withdrawn.
In the event of a deemed withdrawal of a Tender in the circumstances set out in sub-Paragraph 3.3(f)(i), The Company shall be entitled to re-evaluate and select all or part of any outstanding Tenders in accordance with sub-Paragraphs 3.3(e)(i) and (ii) and to notify one or more Tenderers if, in substitution for the Tender so deemed to be withdrawn, it wishes to enter into a Market Agreement in respect of any other Tender or Tenders (or part(s) thereof). Following such notification, The Company and each Tenderer in question shall use reasonable endeavours to agree the terms of, and enter into, a Market Agreement prior to the relevant Contract Start Day.
If, in respect of any Tender, a Market Agreement is not entered into by the relevant Contract Start Day, that Tender shall be deemed to be withdrawn.
Save where otherwise provided in this Paragraph 3, all Market Agreements must be entered into on the basis of the terms set out in the relevant Tender (or relevant part(s) thereof).
Legal Status of Tenders For the avoidance of doubt, a Tender shall not constitute an offer open for acceptance by The Company, and in respect of any Tender (or part(s) thereof) selected by The Company SC3-10 pursuant to sub-Paragraph 3.3(e) or (f), neither the Tenderer in question nor The Company shall be obliged to provide or pay for the Obligatory Reactive Power Service and/or an Enhanced Reactive Power Service upon the terms of that Tender (or the relevant part(s) thereof) unless and to the extent that those terms are incorporated in a Market Agreement subsequently entered into.
Publication
Within the six weeks following each Contract Start Day, The Company shall provide to all persons requesting the same the following information:-
in respect of all Market Agreements then subsisting, prices and contracted Reactive Power capability on an individual Tender basis relating to the period from the immediately preceding Contract Start Day until the next following Contract Start Day;
in respect of all Mandatory Services Agreements and Market Agreements subsisting in respect of the six month period ending on the immediately preceding Contract Start Day, details of utilisation of Mvarh provided by individual BM Units (or, where relevant, other Plant and/or Apparatus or other equipment) pursuant to the Obligatory Reactive Power Service and Enhanced Reactive Power Service;
details of the circumstances surrounding any failure by The Company during the preceding six month period to perform any of its duties and responsibilities under this Paragraph 3 in the circumstances referred to in Paragraph 5; and
any other information reasonably considered by The Company to be pertinent to the Tender process, and, to this extent, each relevant User consents to the disclosure by The Company of the information referred to in sub-sub-Paragraphs (a) and (b) above in so far as it relates to the provision of the Obligatory SC3-11 Reactive Power Service and (where applicable) an Enhanced Reactive Power Service from its Generating Units, DC Converters or Power Park Modules and/or other Plant and Apparatus (or other equipment).
Without prejudice to the provision of information pursuant to sub-Paragraph 3.3(h)(i), The Company further agrees to use all reasonable endeavours to provide to all persons requesting the same, within the six weeks following each Contract Start Day, estimates of the Mvarh absorption and generation by the GB Transmission System, where used for the purposes of voltage support, during the preceding six month period.
The indexation factor I used in the formulae in paragraph 2 above shall be determined as follows:-
For all periods up to (and including) 31st March, 2004, I shall with effect from 1st April in respect of each subsequent 12 month period ending 31st March be determined as follows:- I = RP1 RP1 SC3-15 where For the period from (and including) 1st October, 1997 to (and including) 31st March, 1998 RPI =155.4, and thereafter RPI is the 2 2 RPI for March of the immediately preceding twelve month period ending 31st March. RPI is the RPI for March, 1994 (142.5).
For all periods from (and including) 1st April, 2004, I shall in respect of each calendar month be determined as follows:- I = I m where I = the indexation factor I for the calendar month in question m I = C*[(0.5*FRPI /RPI )+(0.5*PI )] m m x m where C = RPI /RPI x 1 RPI is the RPI for March, 2003 (179.9) x RPI is as defined in sub-paragraph (a) above FRPI is the Forecast RPI for the calendar month in question m and where PI is a wholesale power price index determined as follows:- m PI = [(p* HPI /HPI ) + (q* PAPI /PAPI ) + (r* PPI /PPI ) m m 1 m 1 m 1 Where HPI is the mean average of the OTC baseload month ahead Heren m power index bid and offer prices for all days on which this index is published in the calendar month immediately preceding the calendar month in question PAPI is the mean average of the OTC baseload month ahead Petroleum m Argus power index bid and offer prices for all days on which this index is published in the calendar month immediately preceding the calendar month in question SC3-16 PPI is the mean average of the OTC baseload month ahead Platts m power index bid and offer prices for all days on which this index is published in the calendar month immediately preceding the calendar month in question and where p = 1/3 (subject always to sub-paragraph 3.2 (c) q = 1/3 (subject always to sub-paragraph 3.2(c) r = 1/3 (subject always to sub-paragraph 3.2(c) and where HPI is the mean average of the OTC baseload month ahead Heren power index bid and offer prices for all days on which this index is published during the period from (and including) 1st October 2002 to (and including) 30th September 2003 PAPI is the mean average of the OTC baseload month ahead Petroleum Argus power index bid and offer prices for all days on which this index is published during the period from (and including) 1st October 2002 to (and including) 30th September 2003 PPI is the mean average of the OTC baseload month ahead Platts power index bid and offer prices for all days on which this index is published during the period from (and including) 1st October 2002 to (and including) 30th September 2003
For the purposes of sub-paragraph 3.1 above:-
the RPI Index used is the Retail Price Index with 1987 = 100 base, and the source of the RPI Index is the monthly Office for National Statistics “Business Monitor MM23”;
Forecast RPI is as provided monthly by Experian Business Strategies Ltd; and
if in respect of any calendar month the mean average of any of the power indices more particularly referred to in sub-paragraph 3.1(b) is incapable of being derived and/or there is a material change in the basis of that power index, then subject as provided below, for the purpose of sub-paragraph 3.1(b) The Company shall determine the wholesale power price index PI for that calendar m SC3-17 month by substituting for the original value of factor p,q, or r as relates to that power index (“the Affected Factor”) the value of zero, and by substituting for the original value of each of the remaining factors p, q, or r a value which is increased from the original value by a pro rata proportion of the original value of the Affected Factor. Provided always that if in respect of any calendar month the mean average of each of such power indices is incapable of being derived and/or there is a material change in the basis of each such power index, then The Company shall determine the wholesale power price index PI for that calendar month by substituting for the m value PI in the determination of I the value FRPI /RPI. m m m x
Information Unavailable Save where otherwise provided in this Part I, where any information or data required by The Company for the calculation of payments to be made pursuant to this Part I is not available to The Company at the relevant time, The Company shall calculate payments using The Company’s best estimate of the unavailable information of data. Once such information or data is available, The Company shall accordingly make all consequential adjustments to the payments from itself to Users as soon as reasonably practicable thereafter to reflect any repayment or additional payment so required to be made by one party to the other in respect of the relevant period (including interest thereon at the Base Rate from the original date of payment or due date (as the case may be) until the date of such repayment or additional payment).
Commissioning
For each Settlement Period, PUM = PUM + PUM [£ per Settlement Period per BM Unit] lead lag where PUM = defined in sub-paragraph 3.2 below; lead PUM = defined in sub-paragraph 3.3 below. lag
Leading Utilisation (PUM ) lead There are four mutually exclusive cases (a), (b), (c) or (d):
If Q2 < (U /SPD) and both Q2 and Q3 are lead lead lead lead not deemed null (i.e. there are three breakpoints) then PUM = SPD * [(CU1 * Q1 ) + (CU2 * lead lead lead lead (Q2 – Q1 )) + (CU3 * ((U /SPD) – Q2 ))] lead lead lead lead lead
If either Q1 < (U /SPD) Q2 and Q2 is not lead lead lead lead deemed null (i.e. there are at least two breakpoints) or Q2 < (U /SPD) and Q2 is not deemed null lead lead lead and Q3 is deemed null (i.e. there are only two breakpoints) then PUM = SPD * [(CU1 * Q1 ) + (CU2 * lead lead lead lead ((U /SPD) – Q1 ))] lead lead SC3-23
If either 0 < (U /SPD) Q1 lead lead (i.e. irrespective of the number of breakpoints) or Q1 < (U /SPD) and Q2 and Q3 are lead lead lead lead deemed null (i.e. there is only one breakpoint) then PUM = CU1 * U lead lead lead
otherwise PUM = 0 [£ per Settlement Period per BM Unit] lead
Lagging Utilisation (PUM ) lag There are four mutually exclusive cases (a), (b), (c) or (d):
If Q2 < (U /SPD) and both Q2 and Q3 are not lag lag lag lag deemed null (i.e. there are three breakpoints) then PUM = SPD * [(CU1 * Q1 ) + (CU2 * (Q2 – lag lag lag lag lag Q1 )) + (CU3 * ((U /SPD) – Q2 ))] lag lag lag lag
If either Q1 < (U /SPD) Q2 and Q2 is not deemed lag lag lag lag null (i.e. there are at least two breakpoints) or Q2 < (U /SPD) and Q2 is not deemed null and lag lag lag Q3 is deemed null (i.e. there are only two breakpoints) then PUM = SPD * [(CU1 * Q1 ) + (CU2 * lag lag lag lag ((U /SPD) – Q1 ))] lag lag
If either 0 < (U /SPD) Q1 lag lag (i.e. irrespective of the number of breakpoints) or Q1 < (U /SPD) and Q2 and Q3 are deemed to lag lag lag lag be null SC3-24 (i.e. there is only one breakpoint) then PUM = CU1 * U lag lag lag
otherwise PUM = 0 [£ per Settlement Period per BM Unit] lag
Available Capability Payment
The quantities of Mvarh imported and exported shall be measured and recorded through Meters complying with all relevant Codes of Practice to the extent applying to Reactive Energy, which shall include without limitation those relating to calibration, testing and commissioning.
Such Meters shall be capable of providing a Mvarh import and export value for each Settlement Period for each item of Plant and/or Apparatus or other equipment.
Such Meters shall be situated as close as reasonably practicable to the Commercial Boundary taking into account relevant financial considerations. SC3-34
The principles set out in paragraph 2.4 in relation to adjustment and aggregation shall apply.
For the purposes of remote interrogation the relevant Mandatory Services Agreement shall include appropriate terms with regard to the provision and maintenance of all communication links. SC3-35 Appendix 5 Submission of Tenders The provisions of this Appendix 5 specify the manner in which Users shall complete Tenders comprising prices and Tendered Capability Breakpoints relating to the Obligatory Reactive Power Service and terms for the provision of the Enhanced Reactive Power Service specified in sub-Paragraph 1.3 (a) of this Part I, in each case in respect of BM Units. A Tender shall include (inter alia) details of the Reactive Power range, the prices tendered for utilisation and capability and an indexation mechanism as set out below. Each Tender must relate to one BM Unit only. Users wishing to tender in relation to more than one BM Unit must therefore submit separate Tenders for each BM Unit.
Reactive Power Capability
prices and other terms offered within the Tender;
the number of months over which capability is tendered;
forecast Mvarh output, including any revised forecast of Mvarh output taking into account tendered utilisation prices (for the avoidance of doubt of the Tender and of all other Tenders pursuant to sub-paragraph 2.3 above);
in relation to a Generating Unit, DC Converter or Power Park Module forecast MW output and MW availability; SC3-42 3.6 the expected availability and quality of capability tendered, in terms of reliability and dependability for despatch purposes, derived from:-
historical performance (where relevant);
expected reliability of capability tendered signalled by tendered prices;
any programme agreed with The Company for the restoration of capability;
the availability of suitable monitoring facilities;
the capability (if any) of a Generating Unit, DC Converter or Power Park Module to provide voltage support services when not providing Active Power (for example pumped storage plant operating in spin-gen mode or when pumping and open cycle gas turbine plant when declutched and operating in Synchronous Compensation mode);
the complexity of the terms offered within the Tender;
the results of any testing carried out pursuant to sub-Paragraph 4.3
(ii) of this Part I and (where applicable) the absence of any such testing; and 3.11 any other factors enhancing or constraining the capability tendered, derived (inter alia) from technical and other information made available to The Company (including without limitation operational and planning data provided to The Company pursuant to the Grid Code).
For the avoidance of doubt, Tenders will be considered in the investment planning process of The Company’s Transmission Business only if, and to the extent, required to enable The Company to comply with its obligations under the Act and the ESO Licence, and in such a case any consequential benefit or detriment attributable to the Tender will be taken into account in the tender evaluation process and Tenders will be evaluated accordingly.
For the avoidance of doubt:-
extant voltage support for the GB Transmission System whether via contracted services from third parties or assets owned and/or operated by The Company’s Transmission Business; and SC3-43
forecast Mvarh Demand on the GB Transmission System and at Grid Supply Points in each case as at the relevant Market Day and as anticipated by The Company at the subsequent Contract Start Day and throughout the term of the Tender, will be taken into account in the tender evaluation process and Tenders will be evaluated accordingly. SC3-44 Appendix 7 Charging Principles In accordance with the relevant provisions of this Part I, the following principles are intended to form the basis of the default payment arrangements for the provision of the Obligatory Reactive Power Service set out in this Part I and are intended to be taken into account in any review of the indexation factor referred to in Appendix 1. However, they are not intended to stifle innovation in the development of the default payment arrangements or the giving of appropriate economic signals.
The totality of payments that would be made pursuant to the default payment arrangements in the absence of Market Agreements shall be based and founded upon the following variable costs (actual or estimated) incurred or to be incurred in respect of, and aggregated across, all Generating Units, DC Converters and Power Park Modules providing the Obligatory Reactive Power Service:- 1.1 the additional heat losses incurred as a consequence of producing Reactive Power, measured at the high voltage side of the generator/transformer terminals, the calculation of such heat losses to take account of the square law relationship between the electric current and the additional heat losses incurred; and 1.2 maintenance costs incurred as a direct result of Reactive Power output (including a sum in respect of any reduction in the working life of Generating Unit, DC Converter or Power Park Module components consequent upon Reactive Power output).
For the avoidance of doubt, and without limitation, the totality of payments referred to in paragraph 1 above shall not take into account in respect of any Generating Unit, DC converter or Power Park Module providing the Obligatory Reactive Power Service the fixed costs incurred in achieving initial compliance with the relevant provisions of the Grid Code.
Further for the avoidance of doubt, the totality of payments referred to in paragraph 1 above shall, to the extent affecting the specific costs therein identified, take due account of any change in or amendments to, or replacement of, the Pooling and Settlement Agreement, the Balancing and Settlement Code, the Grid Code and any other statutory or regulatory obligation, in each case coming into force or effect after 1st October, 1997 and affecting the provision of the Obligatory Reactive Power Service. SC3-45 Appendix 8 Calculation of Reactive Power Capability at the Commercial Boundary Part 1 In accordance with the terms of the Mandatory Services Agreement, where applicable the formulae in this Part 1 will be used to convert Reactive Power capability of a BM Unit at the generator stator terminals to the capability at the Commercial Boundary. [(P − P )2 + (Q + Q )2]*F*X Q = (Q + Q )+ G U Glead U t + Q lead Glead U 100.MVA ts X Where the BM Unit has a Reactive Power capability (leading), this shall be expressed as a positive integer. Where the BM Unit does not have a Reactive Power capability (leading), Q and/or Q shall be the minimum Reactive lead Glead Power capability (lagging) expressed as a negative integer or zero. [(P − P )2 + (Q − Q )2]*F*X G U Glag U t Q = (Q − Q )− − Q lag Glag U 100.MVA ts X Where the BM Unit has a Reactive Power capability (lagging), this shall be expressed as a positive integer. Where the BM Unit does not have a Reactive Power capability (lagging), Q and/or Q shall be the minimum Reactive lag Glag Power capability (leading) expressed as a negative integer or zero. Where: Q = the Reactive Power capability (leading) of the BM Unit at Rated lead MW at the Commercial Boundary in Mvar; Q = the Reactive Power capability (lagging) of the BM Unit at Rated lag MW at the Commercial Boundary in Mvar; P = Rated MW referred to in Schedule 1 of Grid Code DRC; G P = normal auxiliary load (Active Power) supplied by the BM Unit at U Rated MW referred to in Schedule 1 of Grid Code DRC in MW; Q = normal auxiliary lagging load (Reactive Power) supplied by the BM U Unit at Rated MW referred to in Schedule 1 of Grid Code DRC in Mvar; X = positive sequence reactance, nominal tap, of the BM Unit step-up t transformer in percentage of rating as referred to in Schedule 1 of Grid Code DRC; SC3-46 F = the factor (if any) identified as such in the Mandatory Services Agreement representing the number of station transformers, otherwise 1; Q = the Reactive Power capability (lagging) of the BM Unit at Rated Glag MW at the generator stator terminals, where applicable as set out in Table B of Appendix 1, Section A, Part I of the Mandatory Services Agreement or as redeclared by the User pursuant to Grid Code BC; Q = the Reactive Power capability (leading) of the BM Unit at Rated Glead MW at the generator stator terminals, where applicable as set out in Table B of Appendix 1, Section A, Part I of the Mandatory Services Agreement or as redeclared by the User pursuant to Grid Code BC; Q = the relevant reactive load applicable to each of the relevant BM ts Unit shown in the relevant table in the Mandatory Services Agreement, the summation of which represents the lagging reactive load in Mvar taken by a Trading Unit calculated in accordance with the values for Demand (Active Power) and Power Factor referred to in Grid Code PC.A.4.3.1(a) or Grid Code PC.A.5.2.2(a) (as the case may be), or as agreed between The Company and the User from time to time (and where such load is leading, Q will be negative); ts MVA = BM Unit step-up transformer rated MVA referred to in Schedule 1 X of Grid Code DRC. N.B. All of the above factors referred to in Grid Code DRC shall be expressed in such units as are specified in Grid Code DRC and to the same number of significant figures as also specified therein (as varied from time to time). SC3-47 Part 2 In accordance with the terms of the Mandatory Services Agreement, where applicable the formulae in Section 1 of this Part 2 will be used by The Company to convert Reactive Power capability of a CCGT Unit at the generator stator terminals to the capability at the HV side of the Generating Unit step-up transformer, and the formulae in Section 2 of this Part 2 will be used to calculate the Reactive Power capability of the BM Unit at the Commercial Boundary. Section 1 [(P − P )2 + (Q + Q )2]*F*X CQ = (Q + Q )+ G U Glead U t lead Glead u 100.MVA X Where the CCGT Unit has a Reactive Power capability (leading), this shall be expressed as a positive integer. Where the CCGT Unit does not have a Reactive Power capability (leading), Q and/or Q shall be the minimum lead Glead Reactive Power capability (lagging) expressed as a negative integer or zero. [(P − P )2 + (Q − Q )2]*F*X G U Glag U t CQ = (Q − Q )− lag Glag u 100.MVA X Where the CCGT Unit has a Reactive Power capability (lagging), this shall be expressed as a positive integer. Where the CCGT Unit does not have a Reactive Power capability (lagging), Q and/or Q shall be the minimum lag Glag Reactive Power capability (leading) expressed as a negative integer or zero. Where: CQ = the Reactive Power capability (leading) of the CCGT Unit at lead Rated MW at the HV side of the Generating Unit step-up transformer in Mvar; CQ = the Reactive Power capability (lagging) of the CCGT Unit at lag Rated MW at the HV side of the Generating Unit step-up transformer in Mvar; P = Rated MW of a CCGT Unit referred to in Schedule 1 of Grid G Code DRC; P = normal auxiliary load (Active Power) supplied by the CCGT U Unit at Rated MW referred to in Schedule 1 of Grid CodeDRC in MW; Q = normal auxiliary lagging load (Reactive Power) supplied by U the CCGT Unit at Rated MW referred to in Schedule 1 of Grid Code DRC in Mvar; SC3-48 F = the factor (if any) identified as such in the Mandatory Services Agreement representing the number of station transformers, otherwise 1; X = positive sequence reactance, nominal tap, of the CCGT Unit t step-up transformer in percentage of rating as referred to in Schedule 1 of Grid Code DRC; Q = the Reactive Power capability (lagging) of the CCGT Unit at Glag Rated MW at the User stator terminals as set out in Table B of Appendix 1, Part I of the Mandatory Services Agreement or as redeclared by the User pursuant to Grid Code BC; Q = the Reactive Power capability (leading) of the CCGT Unit at Glead Rated MW at the User stator terminals as set out in Table B of Appendix 1, Part I of the Mandatory Services Agreement or as redeclared by the User pursuant to Grid Code BC; MVA = Generating Unit step-up transformer rated MVA referred to X in Schedule 1 of Grid Code DRC. Section 2 CCGTunits Q lead = CQlead + Qts n CCGTunits Q lag = CQlag − Qts n Where Q = the Reactive Power capability (leading) of the BM Unit at lead the Commercial Boundary in Mvar; CCGTUnits = the summation over each relevant CCGT Unit; n Q = the Reactive Power capability (lagging) of the BM Unit at lag the Commercial Boundary in Mvar; Q = the relevant reactive load applicable to each of the BM Units ts shown in the relevant table in the Mandatory Services Agreement, the summation of which represents the lagging SC3-49 reactive load in Mvar taken by a Trading Unit calculated in accordance with the values for Demand (Active Power) and Power Factor referred to in Grid Code PC.A.4.3.1(a) or Grid Code PC.A.5.2.2(a) (as the case may be), or as agreed between The Company and the User from time to time (and where such load is leading, Q will be negative). ts N.B. All of the above factors referred to in Grid Code DRC shall be expressed in such units as are specified in Grid Code DRC and to the same number of significant figures as also specified therein (as varied from time to time). SC3-50 Part 3 In accordance with the terms of the Mandatory Services Agreement, where applicable the formulae in Section 1 of this Part 3 will be used by The Company to convert Reactive Power capability of a Power Park Unit at the generator stator terminals to the capability at the HV side of the Generating Unit step-up transformer, and the formulae in Section 2 of this Part 3 will be used to calculate the Reactive Power capability of the Power Park Module at the Commercial Boundary. Section 1 [(P − P )2 + (Q + Q )2]*F*X CQ = (Q + Q )+ G U Glead U t lead Glead u 100.MVA X Where the Power Park Unit has a Reactive Power capability (leading), this shall be expressed as a positive integer. Where the Power Park Unit does not have a Reactive Power capability (leading), Q and/or Q shall be the lead Glead minimum Reactive Power capability (lagging) expressed as a negative integer or zero. [(P − P )2 + (Q − Q )2]*F*X CQ = (Q − Q )− G U Glag U t lag Glag u 100.MVA X Where the Power Park Unit has a Reactive Power capability (lagging), this shall be expressed as a positive integer. Where the Power Park Unit does not have a Reactive Power capability (lagging), Q and/or Q shall be the lag Glag minimum Reactive Power capability (leading) expressed as a negative integer or zero. Where: CQ = the Reactive Power capability (leading) of the Power Park lead Unit at Rated MW at the HV side of the Generating Unit step-up transformer in Mvar; CQ = the Reactive Power capability (lagging) of the Power Park lag Unit at Rated MW at the HV side of the Generating Unit step-up transformer in Mvar; P = Rated MW of a Power Park Unit referred to in Schedule 1 G of Grid Code DRC; SC3-51 P = normal auxiliary load (Active Power) supplied by the Power U Park Unit at Rated MW referred to in Schedule 1 of Grid Code DRC in MW; Q = normal auxiliary lagging load (Reactive Power) supplied by U the Power Park Unit at Rated MW referred to in Schedule 1 of Grid Code DRC in Mvar; F = the factor (if any) identified as such in the Mandatory Services Agreement representing the number of Power Park Units transformers, otherwise 1; X = positive sequence reactance, nominal tap, of the Power t Park Unit step-up transformer in percentage of rating as referred to in Schedule 1 of Grid Code DRC; Q = the Reactive Power capability (lagging) of the Power Park Glag Unit at Rated MW at the User stator terminals as set out in Table B of Appendix 1, Part I of the Mandatory Services Agreement or as redeclared by the User pursuant to Grid Code BC; Q = the Reactive Power capability (leading) of the Power Park Glead Unit at Rated MW at the User stator terminals as set out in Table B of Appendix 1, Part I of the Mandatory Services Agreement or as redeclared by the User pursuant to Grid Code BC; MVA = Generating Unit step-up transformer rated MVA referred to X in Schedule 1 of Grid Code DRC. Section 2 PPUnits (P1 −P1 )2 +(Q1 +Q1 )2 F1X1 Q = CQ +Q + G U Glead U t lead lead ts 100.MVA1 n x PPUnits (P1 −P1 )2 + ( Q1 −Q1 )2 F1X1 Q = CQ −Q − G U Glag U t lag lag ts 100.MVA1 n x Where Q = the Reactive Power capability (leading) of the Power Park lead Module at the Commercial Boundary in Mvar; PPUnits = the summation over each relevant Power Park Unit; n SC3-52 Q = the Reactive Power capability (lagging) of the BM Unit at lag the Commercial Boundary in Mvar; Q = [the relevant reactive load applicable to the Power Park ts Module shown in the relevant table in the Mandatory Services Agreement, the summation of which represents the lagging reactive load in Mvar taken by a Trading Unit calculated in accordance with the values for Demand (Active Power) and Power Factor referred to in Grid Code PC.A.4.3.1(a) or Grid Code PC.A.5.2.2(a) (as the case may be), or as agreed between The Company and the User from time to time (and where such load is leading, Q will be ts negative).] PPUnits P1 = P G G n PPUnits P1 = P U U n PPUnits Q1 = Q Glag Glag n PPUnits Q1 = Q Glead Glead n F1 = the factor (if any) identified as such in the Mandatory Services Agreement representing the number of station transformers, otherwise 1; X1 = positive sequence reactance, nominal tap, of the Power t Park Module step up transformer in percentage of rating as referred to in Schedule 1 of Grid Code DRC MVA1 = Power Park Module step-up transformer rated MVA x referred to in Schedule 1 of Grid Code DRC SC3-53 N.B. All of the above factors referred to in Grid Code DRC shall be expressed in such units as are specified in Grid Code DRC and to the same number of significant figures as also specified therein (as varied from time to time). SC3-54 Appendix 9 Redundant Provisions
Introduction This Appendix 9 is included in this Part I for information purposes only as more particularly described in Paragraph 6 of this Part I.
Definitions - Paragraph 1.1 of MCUSA, Schedule 5. In this Appendix 9, except where the context otherwise requires, the following expressions shall have the following meanings:- “Reactive Power Zone” means those separate areas of England and Wales identified as zones in the Seven Year Statement for 1997 for the purpose of specifying local Reactive Power capability and need; “Relevant Zone” means in relations to any Despatch Unit, the Reactive Power Zone to which the Despatch Unit is allocated as specified in an Ancillary Services Agreement. “Transmission Users Group” means the group established pursuant to paragraph 4 of Schedule 4 to this Agreement.
Variations and Review – Paragraph 2.5 of MCUSA Schedule 5 The Parties acknowledge and agree that the Transmission Users Group shall be requested to review each of the matters described in Appendix 7 by the respective date (if any) shown opposite each therein. In carrying out such review, the Transmission Users Group shall be requested to take into account the respective applicable principles (if any) set out therein and to give due and proper consideration to any matter referred to it by the Director. For the avoidance of doubt, following each such review The Company or any User may raise a Proposed Variation with respect thereto in accordance with sub- paragraph 2.2(a). It is further agreed that:-
The Company shall consider and no later than 31st December 1999, report to the Transmission Users Group on the practicalities of establishing a unified mechanism for the provision of voltage support for The Company Transmission System; and SC3-55
the Transmission Users Group shall be requested, no later than 31st March 2000 to invite the Grid Code Review Panel to review the provisions of the Grid Code with respect to Reactive Power in light of this Schedule.
Obligatory Reactive Power Service – Default Payment Arrangements – Paragraph 4 of MCUSA, Schedule 5
4. Amendment and Conclusion of Mandatory Services Agreements
The Company and each relevant User shall promptly do all such acts and execute and deliver such agreements and other documentation as may be necessary to amend or conclude the relevant Mandatory Services Agreements so as to give effect to the provisions of this Part I and the Appendices as amended from time to time.
Sub-Paragraphs 2.6 and 4.1 shall not require The Company or any User to amend or conclude a Mandatory Services Agreement so as to give effect to this Part I and the Appendices if and to the extent that, in respect of any Generating Unit, DC Converter or Power Park Module. The Company and such User shall have expressly agreed in writing that no payments shall be made by The Company to such User under an Ancillary Services Agreement for the provision of the Obligatory Reactive Power Service from that Generating Unit, DC Converter or Power Park Module (as the case may be).
For each Settlement Period, where at any time MEL(t)> 10MW i then PCA = K* ((V * PCA ) + (V * PCA )) lead lead lag lag otherwise PCA = 0 [£ per Settlement Period per BM Unit] where PCA = defined in sub-paragraph 4.2 below; lead PCA = defined in sub-paragraph 4.3 below. lag
Available Leading Capability (PCA ) lead There are four mutually exclusive cases (a), (b), (c) or (d):
If Q2 < Q Q3 and both Q2 and Q3 are lead lead lead lead lead not deemed null (i.e. there are three breakpoints) then PCA = SPD * [(CA1 * Q1 ) + (CA2 * lead lead lead lead (Q2 – lead Q1 )) + (CA3 * (Q – Q2 ))] lead lead lead lead
If Q1 < Q Q2 and Q2 is not deemed null lead lead lead lead (i.e. there are at least two breakpoints) then PCA = SPD * [(CA1 * Q1 ) + (CA2 * (Q lead lead lead lead lead – Q1 ))] lead
If 0 < Q Q1 lead lead SC3-25 (i.e. irrespective of the number of breakpoints) then PCA = SPD * CA1 * Q lead lead lead
otherwise PCA = 0 [£ per Settlement Period per BM Unit] lead
Available Lagging Capability (PCA ) lag There are four mutually exclusive cases (a), (b), (c) or (d):
If Q2 < Q Q3 and Q2 and Q3 are not lag lag lag lag lag deemed null (i.e. there are three breakpoints) then PCA = SPD * [(CA1 * Q1 ) + (CA2 * (Q2 – lag lag lag lag lag Q1 )) + (CA3 * (Q – Q2 ))] lag lag lag lag
If Q1 < Q Q2 and Q2 is not deemed null lag lag lag lag (i.e. there are at least two breakpoints) then PCA = SPD * [(CA1 * Q1 ) + (CA2 * (Q – lag lag lag lag lag Q1 ))] lag
If 0 < Q Q1 lag lag (i.e. irrespective of the number of breakpoints) then PCA = SPD * CA1 * Q lag lag lag
otherwise PCA = 0 [£ per Settlement Period per BM Unit] lag
Synchronised Capability Payment
---
Subject always to Paragraph 5, and notwithstanding:-
the provisions of the Works Programme for reactive power ancillary services agreed by Pool Members on 1st March 1994, as adopted from 1st August 1994; and
the provisions of any Ancillary Services Agreement now or hereafter in effect (but subject always to sub-Paragraph 6.2), the payments to be made by The Company to Users for the provision of the Obligatory Reactive Power Service in all Mandatory Services Agreements under which Users are or will be paid for the Obligatory Reactive Power Service shall, subject always to sub-Paragraph 4.5 and 4.7, comprise solely payments for utilisation determined in respect of each Settlement Period in accordance with sub-Paragraph 4.3.
---
The Parties acknowledge and agree that, as at the date this Schedule comes into effect:-
the totality of payments for the provision of the Obligatory Reactive Power Service, determined in accordance with the provisions of this Paragraph 4, reflect so far as reasonably practicable the overall variable costs (on the basis of the charging principles set out in Appendix 8) incurred across the relevant Generating Units of the provision of the Obligatory Reactive Power Service (whether or not payments are made in respect of those Generating Units pursuant to this Paragraph 4 or pursuant to Market Agreements entered into in accordance with Paragraph 5); and SC3-56
without prejudice to the review of the indexation factor specified as item 4 in Appendix 7, such totality of payments will continue to reflect those overall variable costs notwithstanding all and any variations thereto reasonably anticipated at such date.
It is hereby agreed and acknowledged that nothing in this Schedule and the Appendices shall affect in any way the obligation on each User to comply with the provisions of the Grid Code insofar as they relate to Reactive Power. For the avoidance of doubt, and without limiting the foregoing, it is hereby agreed and acknowledged that, notwithstanding that the payments for the Obligatory Reactive Power Service with affect from 1st April 2000, subject always to sub-paragraph 2.5 shall comprise solely payments for utilisation, nothing in this Schedule and the Appendices shall relieve Users from the obligations to comply with the provisions of the Grid Code in relation to Reactive Power by virtue of Sub-Clause 9.3 of this Agreement or otherwise howsoever.
---
---
---
Obligatory Reactive Power Service (Default Payment Arrangements) – Appendix 1 of MCUSA, Schedule 5 The provisions of this Appendix 1, as referred to in sub-paragraph 4.2 of this Schedule shall apply to the calculation of default payments for provision of the Obligatory Reactive Power Service from BM Units. All payments shall be expressed in pounds sterling.
Total Payment Total Payment (PT) = PU+PC Where, subject always to Paragraph 7 and 8 below: PU = the utilisation payment in respect of a BM Unit for a Settlement Period determined in accordance with Paragraph 2 below. PC = the capability payment in respect of BM Unit for a Settlement Period determined in accordance with paragraph 3 below. SC3-57
Utilisation Payment PU = BP *U [£ per Settlement Period per BM Unit] U Where 46,270,000*1*X BP = [£/Mvarh] U 42,054,694 Where I = defined in Paragraph 5 below; X = a factor which should be:-
in respect of any Settlement Period from (and including) 1st October, 1997 to (and including) 31st March 1998, 0.2; and
in respect of any Settlement Period from (and including) 1st April 1998 to (and including 31st March 1999, 0.5 (subject as provided below); and
subject always to sub-paragraph 2.5 of this Schedule, in respect of any Settlement Period from (and including) 1st April 1999 to (and including) 31st March 2000, 0.75 (subject as provided below); and
subject always to sub-paragraph 2.5 of this Schedule, in respect of all Settlement Periods thereafter, 1.00 (subject as provided below); Provided always that with effect from 1st April 1998, X shall be 0.2 in all Settlement Periods from (and including) that in which:-
the relevant BM Unit (or, in relation to a CCGT Module, any relevant CCGT Unit) fails a Reactive Test until (and including) the Settlement Period in which a subsequent Reactive Test is passed in relation to that BM Unit (or CCGT Unit (as the case may be)); or
the User fails (other than pursuant to an instruction given by The Company or as permitted by the Grid Code) to set the Automatic Voltage Regulator of the BM Unit (or, in relation to a CCGT Module, any relevant CCGT Unit) to a voltage following mode until SC3-58 (and including) the Settlement Period in which the User notifies The Company that the Automatic Voltage Regulator is so set; or
the BM Unit fails to comply with a Reactive Despatch Instruction due to the fact that the BM Unit (or, in relation to a CCGT Module, any relevant CCGT Unit) is unable to increase and/or decrease its Mvar output (other than as a direct result of variations in System voltage) until (and including) the Settlement Period in which the User notifies The Company that the BM Unit is so able to comply; or
the BM Unit fails to have a Mvar range which includes the ability to provide zero Mvar at the Commercial Boundary until (and including) the Settlement Period in which the User notifies The Company that the BM Unit has or once more has such rang; and U = defined in Section 1 of Appendix 3
Capability Payment PC = [[BPc*ZWFlead*QClead*QSFlead)+(BPc*ZWFlag*QClag*QSFlag)]*J] [£ per Settlement Period per Despatch Unit] Provided always that PC shall be 0 in all Settlement Periods from (and including) that in which:-
the User fails (other than pursuant to an instruction given by The Company or as permitted by the Grid Code) to set the Automatic Voltage Regulator of the Despatch Unit (or, in relation to a Centrally Despatched CCGT Module, any relevant CCGT Unit) to a voltage following mode until (and including) the Settlement Period in which the User notifies The Company that the Automatic Voltage Regulator is so set; or
the Despatch Unit fails to comply with a Reactive Despatch Instruction due to the fact that the Despatch Unit (or in relation to a Centrally Despatched CCGT Module, any relevant CCGT Unit) is unable to increase and/or decrease its Mvar output (other than as a direct result of variations in System voltage) until (and including) the Settlement Period in which the User notifies The Company that the Despatch Unit is so able to comply; or
the Despatch Unit fails to have a Mvar range which includes the ability to provide zero Mvar at the Commercial Boundary until (and including) the Settlement Period in which the User notifies The SC3-59 Company that the Despatch Unit has or once more has such range; or
a continuous period of unavailability of a Despatch Unit to be Despatched by The Company in accordance with Grid Code SDC extends beyond 75 consecutive days until (and including) the Settlement Period in which the Despatch Unit is subsequently declared available in accordance with Grid Code SDC. where 46,270,000*1*Y BP = [£/Mvar per Settlement Period] c 0.868178624*16,112*8,760*2 Where I = defined in paragraph 5 below; Y = a factor which shall be:-
in respect of any Settlement Period from (and including) 1st October, 1997 to (and including ) 31st March 1998, 0.8; and
in respect of any Settlement period from (and including) 1st April, 1998 to (and including) 31st March, 1999, 0.5; and
subject always to sub-paragraph 2.5 of this Schedule, in respect of any Settlement Period from (and including) 1st April, 1999 to (and including) 31st March, 2000, 0.25; and
subject always to sub-paragraph 2.5 of this Schedule, in respect of all Settlement Periods thereafter, 0; ZWF = the provisional Zonal Weighting Factor defined in paragraph 4 below (expressed to apply to both leading and lagging Mvar) subject to reconciliation in accordance with that paragraph: QC = defined in Section 2 of Appendix 3 (expressed to apply to both leading and lagging Mvar); QSF = the shortfall factor relating to the capability payment (expressed as either QSF or QSF to apply respectively lead lag to capability leading and capability lagging as applicable), being:- SC3-60 min QR )2 1,( QC where QR = defined in Section 2 of Appendix 3 (expressed to apply to both leading and lagging Mvar); and J = 1 in each Settlement Period in which, in relation to the Despatch Unit in question, Genset Registered Capacity is greater than 2MW, otherwise 0.
Zonal Weighting Factors ZWF = the Provisional Zonal Weighting Factor (expressed as either ZWF or ZWF to apply respectively to the zonal lead lag weighting factor leading and the zonal weighting factor lagging) for the Despatch Unit, calculated as follows:-
In respect of the period from (and including) 1st October, 1997 to (and including) 31st March, 1998 and in respect of each subsequent twelve month period ending 31st March, provisional zonal weighting factors (“the Provisional Zonal Weighting Factors”) shall be calculated by The Company in respect of both leading and lagging Reactive Power by reference to:-
the leading or lagging (as the case may be) Mvar “need” for leading or lagging (as the case may be) Reactive Power for that period in each Relevant Zone, divided by
the total leading or lagging (as the case may be) Mvar capability for that period in each Relevant Zone as forecast by The Company (“the Total Forecast Capability”), with the result of that division in each case being multiplied by an adjustment factor being:- 16112 TAN Where SC3-61 TAN = a figure being, for the period from (and including) 1st October, 1997 to (and including) 31st March 1998, 14,775, and for each subsequent twelve month period ending 31st March, a figure being the sum total of the leading Mvar “need” for leading Reactive Power plus the sum total of the lagging Mvar “need” for lagging Reactive Power in all Reactive Power Zones for the twelve month period in question, as given each year in the Seven Year Statement, provided that each Provisional Zonal Weighting Factor (both leading and lagging) shall not in any event be greater than 3.000 and provided further that (for the avoidance of doubt) no determination of ZWF ZWF and TAN shall be lead, lag made in respect of any such twelve month period when Y = 0.
The Provisional Zone Weighting Factors, together with the Total Forecast Capability, will be notified by The Company as soon as reasonably practicable by publication in the first practicable Seven Year Statement (or any update thereof). Reconciliation As soon as reasonably practicable following the expiry of each twelve month period ending 31st March, The Company shall recalculate ZWF lead and ZWF for that twelve month period in accordance with the above lag provision for calculation of the Provisional Zonal Weighting Factors but substituting for the Total Forecast Capability the actual total leading or lagging (as the case may be) Mvar capability for that twelve month period in each Relevant Zone as determined by The Company (“the Total Actual Capability”). Such recalculation of ZWF and ZWF shall be lead lag undertaken by The Company in a manner consistent with the principles and methodologies set out in the document entitled “Methodology Document for the Recalculation of Zonal Weighting Factors” published by The Company for this purpose. Such recalculated figures for ZWF and lead ZWF (“the Final Zonal Weighting Factors”), together with the Total lag Actual Capability, shall be published by The Company in the Seven Year Statement. Each Final Zonal Weighting Factor (both leading and lagging) shall not in any event be greater than 3.000 and (for the avoidance of doubt) no determination of ZWF ZWF and TAN shall be made in lead lag respect of any such twelve month period when Y=0. SC3-62 The Company shall derive the Total Actual Capability from the Mvar capability (required under and in accordance with the Connection Conditions of the Grid Code) of Generating Units in respect of which Ancillary Services Agreements have been or will be amended or concluded to give effect to the provisions of sub-paragraphs 4.2 and 4.3 of this Schedule. In respect of any twelve month period ending 31st March, such Mvar capability shall be reduced pro rata for all Settlement Periods in such twelve month period in respect of which no capability payments referred to in this Appendix 1 shall fall due:-
by virtue of paragraph 7 below (with effect from the commencement of the twelve month period in question ); and
by virtue of paragraph 8 below (until the end of the twelve month period in question); and
by virtue of factor J referred to in paragraph 3 above being set to zero (at any time during the twelve month period in question). As soon as reasonably practicable following publication of the relevant Seven Year Statement, The Company shall pay to each relevant User or be paid by each relevant User such sum as will reconcile:-
capability payments made to that User and calculated in accordance with paragraph 3 above by reference to the Provisional Zonal Weighting Factors, with
capability payments due to or from that User and calculated in accordance with paragraph 3 above by reference to the Final Zonal Weighting Factors. For the avoidance of doubt, such reconciliation will include the payment of interest at the Base Rate from the date of payment by The Company to that User of the capability payments referred to at (i) above. For clarification purposes, each reference in this paragraph 4 to “need” does not imply actual Reactive Power need but is used merely to refer to the figure identified as “need” in the Seven Year Statement. Such figure shall be determined each year using the same principles and methodologies as used to determine the zonal weighting factors for the twelve month periods ended on 31st March 1996 and 31st March 1997.
Indexation SC3-63 The indexation factor I used in the formulae in Paragraph 2 above shall 1[, with effect form 1st October 1997 in respect of the period from (and including) that date to (and including) 31st March 1998,] with effect from 1st April in respect of each subsequent twelve month period ending 31st March, be determined as follows:- I = RP1 RP1 where For the period from (and including) 1st October, 1997 to (and including) 31st March, 1998 RPI =155.4, and thereafter RPI is the RPI for March of 2 2 the immediately preceding twelve month period ending 31st March. RPI is the RPI for March, 1994 (142.5). The index used is the Retail Price Index (RPI) with 1987 = 100 base. The source of the RPI index is the monthly Department of Employment “Employment Gazette”. Subject always to sub-paragraph 2.5 of this Schedule, In respect of all periods from (and including) 1st April, 2001 the indexation factor I applicable for the period from (and including) 1st April, 2000 to (and including) 31st March 2001 shall apply.
---
---
---
5. Statutory and Regulatory Obligations
Neither The Company nor any User shall be bound to perform any of its duties or responsibilities under this Part I and the Appendices (including without limitation with regard to the amending or concluding of Mandatory Services Agreements in accordance with sub-Paragraph 2.6 and the entering into of Market Agreements in accordance with Paragraph 3) if and to the extent that to do so would be likely to involve that party in breach of its SC3-12 duties and obligations (if any) under the Act of or any condition of a Licence. Accordingly, nothing in this Part I and the Appendices shall preclude The Company from procuring the provision of any Enhanced Reactive Power Service in a manner otherwise than in accordance with Paragraph 3 in order to comply with its duties and obligations under the Act and/or any condition of the ESO Licence to the extent such compliance cannot reasonably be assured by the performance of its duties and responsibilities under Paragraph 3.
Without prejudice to sub-Paragraph 5.1, The Company shall not be bound to comply with the provisions of sub-Paragraph 3.3(h) with regard to the disclosure of information to the extent that to do so would be likely to restrict, distort or prevent competition in the provision of the Obligatory Reactive Power Service and/or Enhanced Reactive Power Service.
Save in relation to BM Units operational prior to 1st April, 1997 no utilisation payments referred to in this Appendix 1 shall fall due and payable to any User in respect of any BM Unit until the Settlement Period in which it is demonstrated to the reasonable satisfaction of The Company, having regard to industry practice, that the BM Unit (or, in the case of a CCGT Module, but subject always to sub-paragraph 5.4 below, each relevant CCGT Unit) complies with the provisions of Grid Code CC 6.3.2 and CC 6.3.4 or (where The Company in its sole discretion requires Reactive Power from a BM Unit before then for the purposes of security of the GB Transmission System) such earlier date as The Company may agree with a User in respect of that BM Unit.
Before any demonstration of compliance referred to in sub-paragraph 5.1 above, it shall be necessary for the User to demonstrate to The Company’s reasonable satisfaction, having regard to industry practice, that the BM Unit’s (or, in the case of a CCGT Module, each relevant CCGT Unit’s) Excitation System, and in particular the under–excitation SC3-18 limiter, has been successfully commissioned and complies with the provisions of Grid Code CC 6.3.8.
For the avoidance of doubt the issue by The Company in relation to a BM Unit of a Reactive Despatch Instruction to unity power factor or zero Mvar shall neither imply by itself that The Company is reasonably satisfied with compliance as referred to in sub-paragraph 5.1 above nor imply in relation to the BM Unit agreement by The Company of an earlier date as also referred to therein.
Until such time as it shall be demonstrated to the reasonable satisfaction of The Company that, in relation to a CCGT Module, all relevant CCGT Units comply with the provisions of Grid Code CC 6.3.2 and CC 6.3.4 as referred to in sub-paragraph 5.1 above, it is the intention that utilisation payments shall fall due to a User in respect of that CCGT Module notwithstanding the provisions of sub-paragraph 5.1 above. For such period, and in relation to that CCGT Module, only, this Appendix 1 and the definitions of QC and QR set out in Appendix 3 shall be read and construed accordingly.
De-energisation and Disconnection Subject to all rights and obligations of The Company and the User accrued at such date, utilisation payments referred to in this Appendix 1 shall cease to fall due and payable to any User in respect of any BM Unit with effect from the date of expiry or termination for whatever reason of the relevant Mandatory Services Agreement in accordance with its terms or (if earlier) with effect from the date of De-energisation or Disconnection of that BM Unit for any reason pursuant to the relevant Bilateral Agreement or the CUSC. SC3-19 Appendix 2 Obligatory Reactive Power Service and Enhanced Reactive Power Services – Market Payment Mechanism The provisions of this Appendix 2, as referred to in sub-Paragraph 3.3(d)(i) of this Part I, shall apply to the calculation of payments in respect of Tenders comprising prices for and Tendered Capability Breakpoints relating to the Obligatory Reactive Power Service and in respect of Tenders comprising terms for the provision of the Enhanced Reactive Power Services specified in sub-Paragraph 1.2(a) of this Part I, in each case in respect of BM Units. All payments shall be expressed in pounds sterling. All algebraic terms contained in this Appendix 2 shall bear the meanings set out in paragraph 1 below unless the context otherwise requires.
Definitions For the purposes of this Appendix 2, unless the context otherwise requires, the following terms shall have the following meanings:- CA1,CA2 and CA3 = the available capability prices (expressed to apply to both leading and lagging) (£/Mvar/h) (as more particularly described in paragraph 2 of Appendix 5) as specified in the relevant Market Agreement; CS1,CS2 and CS3 = the synchronised capability prices (expressed to apply to both leading and lagging) (£/Mvar/h) (as more particularly described in paragraph 2 of Appendix 5) as specified in the relevant Market Agreement; CU1,CU2 and CU3 = the utilisation prices (expressed to apply to both leading and lagging) (£/Mvarh) (as more particularly described in paragraph 2 of Appendix 5) as specified in the relevant Market Agreement; K = in respect of CCGT Modules and Power Park Modules the relevant configuration factor as specified in the relevant Market Agreement, otherwise 1; Q = defined in Section 2 of Appendix 3; lead Q = defined in Section 2 of Appendix 3; lag SC3-20 QM = BM Unit Metered Volume (as defined in the ij Balancing and Settlement Code); Q1, Q2 and Q3 = the contracted capability breakpoints (expressed to apply to both leading and lagging) in whole Mvar as may be specified in the relevant Market Agreement, where:
Q1 = TQ1, Q2 = TQ2 and Q3 = QC where TQ2< QCTQ3
Q1 = TQ1, Q2 = QC Q3 = null where TQ1 < QCTQ2
Q1 = QC, Q2 = null Q3 = null where 0 QCTQ1 SPD = the duration of a Settlement Period, being 0.5; TQ1, TQ2 and TQ3 = defined in Appendix 5; U = defined in Section 1 of Appendix 3; lead U = defined in Section 1 of Appendix 3; lag V = the system voltage range performance factor (expressed to apply to both leading and lagging) as calculated in accordance with the formulae set out in the relevant Market Agreement, otherwise 1; MEL(t) = Maximum Export Limit (as defined in the i Balancing and Settlement Code). SC3-21
Total Payment Total Payment (PTM) = PUM + PCA + PCS [£ per Settlement Period per BM Unit] where, subject always to paragraphs 6, 7 and 8 below: PUM = the utilisation payment in respect of a BM Unit for a Settlement Period determined in accordance with paragraph 3 below; PCA = the available capability payment in respect of a BM Unit for a Settlement Period determined in accordance with paragraph 4 below; and PCS = the synchronised capability payment in respect of a BM Unit for a Settlement Period determined in accordance with paragraph 5 below. Provided always that PTM shall be 0 in all Settlement Periods from and including that in which:-
the relevant BM Unit (or, in relation to a CCGT Module, any relevant CCGT Unit) fails a Reactive Test or a Contract Test until (and including) the Settlement Period in which a subsequent Reactive Test or Contract Test (as the case may be) is passed in relation to that BM Unit (or CCGT Unit (as the case may be)); or
the User fails (other than pursuant to an instruction given by The Company or as permitted by the Grid Code) to set the automatic voltage regulator of the BM Unit (or, in relation to a CCGT Module, any relevant CCGT Unit) to a voltage following mode until (and including) the Settlement Period in which the User notifies The Company that the automatic voltage regulator is so set; or
the BM Unit fails to comply with a Reactive Despatch Instruction due to the fact that the BM Unit (or, in relation to a CCGT Module, any relevant CCGT Unit) is unable to increase and/or decrease its Mvar Output (other than as a direct result of variations in System voltage) until (and including) the Settlement Period in which the User notifies The Company that the BM Unit is so able to comply; or
the BM Unit fails to have a Mvar range which includes the ability to provide zero Mvar at the Commercial Boundary until (and SC3-22 including) the Settlement Period in which the User notifies The Company that the BM Unit has or once more has such range; or
the BM Unit is affected by a Reactive Despatch to Zero Mvar Network Restriction until (and including) the Settlement Period in which notification is given to The Company pursuant to the Grid Code that such Reactive Despatch to Zero Mvar Network Restriction is no longer affecting that BM Unit
Utilisation Payment
For each Settlement Period, where QM > 5MWh ij PCS = K* ((V * PCS ) + (V * PCS )) lead lead lag lag Otherwise SC3-26 PCS = 0 [£ per Settlement Period per BM Unit] where PCS = defined in sub-paragraph 5.2 below; lead PCS = defined in sub-paragraph 5.3 below. lag
Synchronised Leading Capability (PCS ) lead There are four mutually exclusive cases (a), (b), (c) and (d):
If Q2 < Q Q3 and Q2 and Q3 are not lead lead lead lead lead deemed null (i.e. there are three breakpoints) then PCS = SPD * [(CS1 * Q1 ) + (CS2 * (Q2 lead lead lead lead lead – Q1 )) + (CS3 * (Q – Q2 ))] lead lead lead lead
If Q1 < Q Q2 and Q2 is not deemed null lead lead lead lead (i.e. there are at least two breakpoints) then PCS = SPD * [(CS1 * Q1 ) + (CS2 * (Q lead lead lead lead lead – Q1 ))] lead
If 0 < Q Q1 lead lead (i.e. irrespective of the number of breakpoints) then PCS = SPD * CS1 * Q lead lead lead
otherwise PCS = 0 [£ per Settlement Period per BM Unit] lead
Synchronised Lagging Capability (PCS ) lag There are four mutually exclusive cases (a), (b), (c) or (d):
If Q2 < Q Q3 and Q2 and Q3 are not lag lag lag lag lag deemed null (i.e. there are three breakpoints) then PCS = SPD * [(CS1 * Q1 ) + (CS2 * (Q2 – lag lag lag lag lag Q1 )) + (CS3 * (Q – Q2 ))] lag lag lag lag SC3-27
If Q1 < Q Q2 and Q2 is not deemed null lag lag lag lag (i.e. there are at least two breakpoints) then PCS = SPD * [(CS1 * Q1 ) + (CS2 * (Q – lag lag lag lag lag Q1 ))] lag
If 0 < Q Q1 lag lag (i.e. irrespective of the number of breakpoints) then PCS = SPD * CS1 * Q lag lag lag
otherwise PCS = 0 [(£ per Settlement Period per BM Unit] lag
Testing The Company reserves the right to require to be included in any Market Agreement, on a basis to be agreed with a Tenderer, terms with regard to the carrying out of a Contract Test. The provisions of Grid Code OC 5.5.1 relating to the carrying out of a Reactive Test (including re-tests) shall apply to the carrying out of Contract Tests.
6. Redundant Provisions Certain redundant provisions of Schedule 5 to the MCUSA with respect to capability payments comprised within the default payment arrangements and matters for review which were applicable on and from 1 October 1997 but are of no continuing effect by effluxion of time or otherwise, together with other provisions contained elsewhere in this Part I and the Appendices which, prior to the CUSC Implementation Date, included reference to such provisions, are set out (or, as the case may be, rep
Total Payment Total Payment (PT) = PU [£ per Settlement Period per BM Unit] where, subject always to paragraphs 5 and 6 below: PU = the utilisation payment in respect of a BM Unit for a Settlement Period determined in accordance with paragraph 2 below.
Utilisation Payment PU = BP * U [£ per Settlement Period U per BM Unit] Where BP = 46,270,000*I*X*Y U 42,054,693 [£/Mvarh] Where I = defined in paragraph 3 below; X = 1 (unless the circumstances in sub-paragraphs (a) through to (d) apply) And where X shall be 0.2 in all Settlement Periods from (and including) that in which:-
the relevant BM Unit (or, in relation to a CCGT Module, any relevant CCGT Unit) fails a Reactive Test until (and including) the SC3-14 Settlement Period in which a subsequent Reactive Test is passed in relation to that BM Unit (or CCGT Unit (as the case may be)); or
the User fails (other than pursuant to an instruction given by The Company or as permitted by the Grid Code) to set the automatic voltage regulator of the BM Unit (or, in relation to a CCGT Module, any relevant CCGT Unit) to a voltage following mode until (and including) the Settlement Period in which the User notifies The Company that the automatic voltage regulator is so set; or
the BM Unit fails to comply with a Reactive Despatch Instruction due to the fact that the BM Unit (or, in relation to a CCGT Module, any relevant CCGT Unit) is unable to increase and/or decrease its Mvar output (other than as a direct result of variations in System voltage) until (and including) the Settlement Period in which the User notifies The Company that the BM Unit is so able to comply; or
the BM Unit fails to have a Mvar range which includes the ability to provide zero Mvar at the Commercial Boundary until (and including) the Settlement Period in which the User notifies The Company that the BM Unit has or once more has such range; and Y = 1, except that Y shall be 0 in all Settlement Periods from and including that in which the BM Unit is affected by a Reactive Despatch to Zero Mvar Network Restriction until (and including) the Settlement Period in which notification is given to The Company pursuant to the Grid Code that such Reactive Despatch to Zero Mvar Network Restriction is no longer affecting that BM Unit U = defined in Section 1 of Appendix 3
Indexation
7. Termination Save where expressly provided otherwise in a Tender, each Market Agreement shall contain terms entitling The Company to terminate that Market Agreement in the event that the User fails to provide a satisfactory level of service and entitling the User to terminate the Market Agreement in the event that The Company fails (without reasonable cause) to make due payment to the User, in each case as more particularly defined therein.
8. De-energisation and Disconnection Subject to all rights and obligations of The Company and the User accrued at such date, utilisation, available capability and synchronised capability payments referred to in this Appendix 2 shall cease to fall due and payable to any User in respect of any BM Unit with effect from the date of expiry or termination for whatever reason of the relevant Market Agreement in accordance with its terms or (if earlier) with effect from the date of De-energisation or Disconnection of
For the purposes thereof, the following terms shall have the following meanings:- Q = min (QR QC ) [Mvar] lead lead, lead Q = min (QR QC ) [Mvar] lag lag, lag where QC = as specified in the relevant Mandatory Services Agreement and/or Market Agreement, being either (1) the high voltage value (specified in whole Mvar) equivalent at the Commercial Boundary to the low voltage Mvar capability (leading or lagging) of the relevant BM Unit as described in paragraph 2 below, or (2) where applicable, the high voltage Mvar capability (leading or lagging) of the relevant BM Unit as described in paragrpagh 2 below, in each case representing the capability to supply continuously leading or lagging Mvar (as the case may be); QR = as determined in accordance with the relevant Mandatory Services Agreement and/or Market Agreement, being, in relation to a Settlement Period, either (1) the high voltage value (specified in whole Mvar) equivalent to the redeclared low voltage Mvar capability (leading or lagging) or (2) the redeclared high voltage Mvar capability (leading or lagging), in each case of the relevant BM Unit (or, in the absence of such redeclaration, such high voltage value reasonably determined by The Company as a result of monitoring and/or testing as provided in the relevant Mandatory Services Agreement and/or Market Agreement), and QR and QR shall be construed accordingly. lead lag
(a) In respect of capability payments made in accordance with Appendix 1:-
QC shall be the low voltage (or high voltage, as the case may be) capability required to be provided under and in accordance with the Connection Conditions of the Grid Code (where applicable, as determined by any direction in SC3-31 force from time to time and issued by the Authority relieving the relevant User from the obligation under its Licence to comply with such part or parts of the Grid Code as may be specified therein); and
QC and QR shall represent the high voltage (or high voltage value equivalent capability (or redeclared capability) at Rated MW at the Commercial Boundary.
In respect of capability payments made pursuant to a Market Agreement in accordance with Appendix 2:-
QC shall be the capability required to be provided under and in accordance with the Connection Conditions of the Grid Code or, where the Market Agreement is in respect of a Tender for terms for the provision of the Enhanced Reactive Power Service specified in sub-Paragraph 1.3(a) of this Part I, a capability agreed to be provided in excess of that required under and in accordance with the Connection Conditions of the Grid Code but so that in such a case QC cannot exceed TQ3 (defined in Appendix 5);
QC shall represent the high voltage value equivalent at a nominated Registered Capacity specified by a Tenderer in the Tender at the Commercial Boundary within the system voltage range specified in the relevant Market Agreement; and
QR shall represent the high voltage value equivalent at the then current Registered Capacity at the Commercial Boundary within the system voltage range specified in the relevant Market Agreement.
For the purposes of this Section 2, the figures for QC and QR shall be determined in a manner consistent with the principles and methodologies set out in a document published or to be published from time to time by The Company for this purpose. For the avoidance of doubt, leading capability shall mean the ability to import Reactive Power at the Commercial Boundary irrespective of the direction of Active Power flow, and lagging capability shall mean the ability to export Reactive Power at the Commercial Boundary irrespective of the direction of Active Power flow. SC3-32 Appendix 4 Metering
Balancing and Settlement Code For the avoidance of doubt, nothing in this Appendix shall affect the rights and obligations of The Company and those Users also bound by the Balancing and Settlement Code by virtue of being a party to the BSC Framework Agreement with regard to Metering Equipment and Metering Systems insofar as such provisions relate to Reactive Energy.
BM Units
9. Reconciliation As soon as practicable after this Schedule has taken effect and Ancillary Services Agreements have been amended so as to give effect thereto, The Company will pay to each relevant user or be paid by each relevant User such sum as will reconcile:-
payments (if any) made to such User for the provision of the Obligatory Reactive Power Service from BM Units in respect of the period from 1st October, 1997 to (and including) the date of such reconciliation by The Company with SC3-64
payments due to or from such User pursuant to any Ancillary Services Agreement giving effect to this Schedule in respect of the period from 1st October, 1997 to the date of such reconciliation (both dates inclusive) as if such Ancillary Services Agreements had then been effective. For the avoidance of doubt, such reconciliation will include the payment of interest at Base Rate from the date of the relevant payment by The Company referred to at sub- paragraph 9(a) above.
Metering – Appendix 4 of MCUSA Schedule 5
Exhibit A
1. National Energy System Operator Limited a company registered in England with number 11014226 whose registered office is St Catherines Lodge, Bearwood Road, Sindlesham, Berkshire RG41 5BN (“The Company”, which expression shall include its successors and/or permitted assigns); on its own behalf and on behalf of all the other parties to the CUSC Framework Agreement; and
2. [Insert name of person wishing to be admitted to the CUSC] (the "Party Applicant") whose principal office is at []. WHEREAS:
By the CUSC Framework Agreement dated 18 September 2001 made between the Original Parties named therein and as now in force between CUSC Parties and by virtue of any CUSC Accession Agreement entered into by any New Party before the date of this CUSC Accession Agreement, the CUSC Parties agreed to give effect to and be bound by the CUSC.
The Party Applicant has complied with the requirements of the CUSC (if any) as to accession and wishes to be admitted as a CUSC Party.
By the CUSC Framework Agreement and the provisions of the CUSC all CUSC Parties authorise The Company to sign this CUSC Accession Agreement on their behalf. Exhibit A Exhibit A IT IS HEREBY AGREED as follows:
1. In this CUSC Accession Agreement, words and expression defined in or for the purposes of the CUSC Framework Agreement and not otherwise defined herein shall have the meanings ascribed thereto under the CUSC Framework Agreement.
2. The Company (acting on its own behalf and on behalf of each of the other CUSC Parties) hereby admits the Party Applicant as an additional CUSC Party under the CUSC Framework Agreement with effect from the date of this CUSC Accession Agreement on the terms and conditions hereof.
3. The Party Applicant hereby accepts its admission as a CUSC Party and undertakes with The Company acting on its own behalf and on behalf of each of the other CUSC Parties) to perform and to be bound by the CUSC Framework Agreement as a CUSC Party as from the date hereof.
4. For all purposes in connection with the CUSC Framework Agreement the Party Applicant shall as from the date hereof be treated as if it has been a signatory of the CUSC Framework Agreement from the date hereof, and as if this CUSC Accession Agreement were part of the CUSC Framework Agreement from the date hereof, and the rights and obligations of the CUSC Parties shall be construed accordingly.
5. This CUSC Accession Agreement and the CUSC Framework Agreement shall be read and construed as one document and Exhibit A Exhibit A references (in or pursuant to the CUSC Framework Agreement) to the CUSC Framework Agreement (howsoever expressed) should be read and construed as reference to the CUSC Framework Agreement and this CUSC Accession Agreement.
6. If any provision of this CUSC Accession Agreement is or becomes invalid, unenforceable or illegal or is declared to be invalid, unenforceable or illegal by any court of competent jurisdiction or by any other Competent Authority (as defined in the CUSC), such invalidity, unenforceability or illegality shall not prejudice or affect the remaining provisions of this CUSC Accession Agreement, which shall continue in full force and effect notwithstanding the same. The Party Applicant and The Company (acting on it
7. This CUSC Accession Agreement may be executed in counterparts.
8. This CUSC Accession Agreement shall be governed by and construed in accordance with the laws of England and Wales and the parties hereby submit to the jurisdiction of the courts of England and Wales and the courts of Scotland only. Exhibit A Exhibit A
9. If the Party Applicant is not a company incorporated under the Companies Act 1985, as amended, it shall provide to The Company an address in Great Britain for service of process on its behalf in any proceedings. AS WITNESS the hands of the duly authorised representatives of the parties hereto the day and year first above written. Exhibit A
Exhibit B
1. The Company requires the information requested in this application form for the purpose of preparing an Offer (the “Offer”) to enter into an agreement for connection to and in the case of a directly connected power station, use of the National Electricity Transmission System. It is essential that the Applicant supplies all information requested in the application form and that every effort should be made to ensure that such information is accurate. Please note that in the case of a Gated Application you can
2. Where The Company considers that any information provided by the Applicant is incomplete or unclear, or further information is required, the Applicant will be requested to provide further information or clarification. The provision/clarification of this information may impact on The Company’s ability to commence preparation of an Offer.
3. Should there be any change in the information provided by the Applicant then the Applicant should immediately inform The Company of such a change. Where this is a change in the information provided for Sections B to D then the Applicant should contact The Company to see if such a change can be accommodated as it is unlikely that material changes could be accommodated. If The Company cannot accommodate such a change bearing in mind the timescales within which the Offer must be made then the application will
4. The Company shall charge the Applicant, and the Applicant shall pay to The Company, The Company’s Engineering Charges in relation to the application. A fee will be charged by The Company in accordance with the Charging Statements. No application will be considered until such payment has been received.
5. The effective date upon which the application is made shall be the later of the date when The Company has received the application fee pursuant to paragraph 4 above or the date when The Company is reasonably satisfied that the Applicant has completed Sections A-D. The Company shall notify the Applicant of such date. Please note the additional requirements for a Letter of Authority and Letter of Acknowledgement in the case of a Gate 1 Application and the additional requirements under the Gated Application an
6. The Company will make the Offer in accordance with the terms of Paragraphs 2.13, 6.9 (Modifications) and Paragraph 6.10 (New Connection Sites) of the CUSC and the ESO Licence.
7. The Company will make the Offer (a) if it is not a Gated Offer under the Gated Application and Offer Process, as soon as is reasonably practicable and, in any event, within three (3) months of the effective date of the application or such later period as the Authority may agree and (b) if it is a Gated Offer under the Gated Application and Offer Process, in accordance with the Gated Application and Offer Process. The Offer may, where it is necessary to carry out additional extensive system studies to evalua
8. In the course of processing the application it may be necessary:
for The Company to consult the appropriate Public Distribution System Operator(s) on matters of technical compatibility of the National Electricity Transmission System with their Distribution System(s) or to consult the Relevant Transmission Licensees to establish the works required on the National Electricity Transmission System or to release information to The Authority in accordance with the Transmission Licence and the ESO Licence. On grounds of commercial confidentiality The Company shall need authorisation for the release to the Public Distribution System Operator(s) or Relevant Transmission Licensees or The Authority of certain information contained in the application. Any costs incurred by The Company in consulting the Public Distribution System Operator(s) or Relevant Transmission Licensees would be included in The Company Charges for the application. If it is found by the Public Distribution System Operator(s) that any work is required on their Distribution System(s) (except in the case of an Application for a New Connection Site located in Offshore Waters), then it will be for the Public Distribution System Operator(s) and the Applicant to reach agreement in accordance with Paragraph 6.10.3 of the CUSC; or
for The Company to share with the Competent Authority information from the application relevant in the consideration of control of qualifying assets under (and as defined in) the National Security and Investment Act 2021.
9. In accordance with Paragraph 6.30.3 of CUSC The Company will need to disclose details of Bilateral Agreements entered into and shall need authorisation from the Applicant in respect of this.
10. If the Applicant is not already a CUSC Party the Applicant will be required as part of this application form to undertake that they will comply with the provisions of the Grid Code for the time being in force. Copies of the Grid Code and the CUSC are available on The Company’s Website1 and the Applicant is advised to study them carefully. Data submitted pursuant to this application shall be deemed submitted pursuant to the Grid Code.
11. The Company’s Offer will be based upon its standard form terms of Connection Offer and the Charging Statements issued by The Company under conditions E10 and E11 of the ESO Licence. The Applicant should bear in mind The Company’s standard form terms of Offer when making this application. In the case of The Company’s Offer for a New Connection Site located in Offshore Waters, the Offer will identify the Onshore Construction Works based on specified assumptions about the Offshore Construction Works and these
12. In particular, and subject to paragraphs 24 – 27 below The Company prepares Offers upon the basis that each party will design, construct, install, control, operate and maintain, in the case of the User, the Plant and Apparatus which they will own and, in the case of The Company, Transmission Plant and Transmission Apparatus usually but not necessarily applying the ownership rules set out in Paragraph 2.12 of the CUSC (Principles of Ownership). If the Applicant wishes The Company to carry out any of these ma
13. Applicants of a type set out in Grid Code CC 8.1, Generators and DC Converter Station Owners, should appreciate that they will be required to perform Mandatory Ancillary Services to ensure that System Operational Standards can be achieved. This requirement may have implications towards Plant specification. You should be satisfied that before an application is made that your intended Plant design can meet the requirements.
14. Applicants have the option to request a Connection Offer on the basis of a Design Variation. In requesting such an Offer, the Applicant acknowledges that the connection design (which provides for connection to the National Electricity Transmission System) will fail to satisfy the deterministic criteria detailed in paragraphs 2.5 to 2.13 or 7.7 to 7.19, as appropriate, of the NETS SQSS. In making such an Offer, in accordance with its obligations under Paragraphs 2.13.3 and 2.13.8 or 2.13.12 of CUSC, The Comp
15. The Company will include Offshore Restrictions on Availability in any Offer made for New Connection Sites located in Offshore Waters which meet the Offshore Standard Design and Design Variation but not where the design is of a standard equivalent to or higher than the deterministic criteria detailed in paragraphs 2.5 to 2.13 of the NETS SQSS.
16. In the case of New Connection Sites located in Offshore Waters the Offer will be based on an assumption of connection to an Offshore Transmission System rather than an ET Offshore Transmission System. Consideration may be given as to whether the connection should be to an ET Offshore Transmission System and as a result it may be necessary for The Company to consult the appropriate Public Distribution System Operator(s). Where the New Connection Site is to be connected to an ET Offshore Transmission System t
17. The Applicant has the ability to pay a fixed price application fee in respect of their application or pay the actual costs incurred (variable price application fee). The fixed price application fee is derived from analysis of historical costs of similar applications. The variable price application fee is based on an advance of the Transmission Licensee’s Engineering and out of pocket expenses and will vary according to the size of the scheme and the amount of work involved. The Applicant is requested to ind
18. The Company will provide an Offer based upon the National Electricity Transmission System Security and Quality of Supply Standards (NETS SQSS). The criteria presented in the NETS SQSS represent the minimum requirements for the planning and operation of the National Electricity Transmission System. The NETS SQSS allows for a generation or demand Applicant to request a variation to the connection design. For example, such a connection design variation may be used to take account of the particular characterist
19. Any variation to connection design must not reduce the security of the MITS (Main Interconnected Transmission System) to below the minimum planning standard, result in any additional costs to any particular customer and compromise a transmission licensee’s ability to meet other statutory obligations or licence obligations. Further details of these conditions and standards can be found on The Company’s Website.
20. Applicants in respect of New Connection Sites located in Offshore Waters should be aware that their Connection will be dependent on the appointment of an Offshore Transmission Owner in respect of such Connection Site by the Authority. Applicants should indicate their earliest date for entry into the Offshore Tender Process as part of their Connection Application.
21. Entry into the Offshore Tender Process is conditional on the Applicant having procured the appropriate lease(s) from the Crown Estate or Crown Estate Scotland or having secured an appropriate option on such lease or leases. Applicants should provide evidence of such leases or options as part of this Application or evidence reasonably satisfactory to The Company that such leases or options will be obtained prior to the Applicant’s desired entry date into the Offshore Tender Process.
22. Applicants in respect of New Connection Sites located in Offshore Waters should also be aware that except where the Offshore Construction Works are being progressed as Offshore Transmission System Development User Works the Onshore Construction Works will not generally be progressed in advance of the outcome of the Offshore Tender Process and acceptance of the variations envisaged in CUSC Paragraph 2.13.10. There may be some occasions however where The Company considers it better for specific elements of t
23. Applicants in respect of New Connection Sites located in Offshore Waters should indicate at Section A if they are not interested in undertaking Offshore Transmission System Development User Works. In such case the Onshore Construction Works will be based on assumptions about the Offshore Construction Works and these assumptions will be set out in the Construction Agreement. The Offshore Construction Works will not themselves be identified at that time.
24. The OTSDUW Arrangements allow the Applicant to undertake Offshore Transmission System Development User Works that is: activities and works in respect of the Offshore Construction Works which would otherwise be undertaken by an Offshore Transmission Licensee.
25. Whilst not compulsory, and recognising that until the Applicant receives the Offer it will not have received the assumptions referred to in paragraph 11, the Applicant may wish to indicate the scope of the Offshore Transmission Development User Works that it is interested in undertaking.
26. Any Offer made to the Applicant in respect of New Connection Sites located in Offshore Waters (other than an Applicant who has indicated at Section A that they are not interested in undertaking Offshore Transmission System Development User Works) will be made on the basis of the OTSDUW Arrangements and, unless the Applicant has requested otherwise, the Construction Agreement will be framed on the basis of OTSDUW Build although this can be reviewed prior to acceptance. The scope and extent of the Offshore Tr
27. Applicant’s should note that any assets resulting from the OTSDUW Build will not be available for use for the purposes of transmission (except during the OTSUA Commissioning Period) until they have been transferred to an Offshore Transmission Licensee.
28. Please complete this application form in black print and return it together with the appropriate application fee to The Company. In addition to returning the application form to the Customer Services Manager an electronic copy of the application form may be e-mailed to The Company.
29. For the most up to date contact details applicants are advised to visit The Company’s Website.
Registered Company Name:…………………………………………………………………………... Address (of Registered Office in the case of a Company) ................................................................................................................. ................................................................................................................. ................................................................................................................. Company Number:................................................................................... Parent Company Name (if applicable):…..………………………………….
Company Secretary or person to receive CUSC notices Name:…………………………………………………………………………... Email:…………………………………………………………………………… Telephone:……………………………………………………………………...
Commercial Contact/Agent (person to receive Offer if different from Company Secretary or person to receive CUSC notices identified in 2 above) Name:…………………………………………………………………………...
Please confirm whether you agree to us sending the Offer in electronic form instead of hard copy and, if so, confirm the address for this as follows. Yes [ ] No [ ] Email address …………………………………………………..
Please identify which application fee basis you wish to use for this application. Fixed price application fee [ ]
If this is an application for connection to the National Electricity Transmission System Onshore in England and Wales please complete 6a. If this is an application for connection to the National Electricity Transmission System Onshore in Scotland please complete 6b. 6a. Have you made any applications for connection to the National Electricity Transmission System Onshore in Scotland which are being processed prior to Offer by The Company or where an Offer has been made that Offer has not yet been accepted by you but remains open for acceptance? If so, are such applications intended as alternatives to this one i.e. you intend to choose which of this or those other applications to proceed with on the basis of the offer made. Yes – please list the applications. ………………………………………………………………………………… ………………………………………………………………………………… No [ ] Not sure [ ] (The Company will contact you to clarify) 6b. Have you made any applications for connection to the National Electricity Transmission System Onshore in England and Wales which are being processed prior to Offer by The Company or where an Offer has been made that Offer has not yet been accepted by you but remains open for acceptance? If so, are such applications intended as alternatives to this one i.e. you intend to choose which of this or those other applications to proceed with on the basis of the offer made.
Where the New Connection Site is located in Offshore Waters please complete the confirmation below if you are not interested in undertaking Offshore Transmission Development User Works. Confirm [ ]
Please identify (preferably by reference to an extract from an Ordnance Survey Map for Onshore locations, or with the latitude and longitude or some other corresponding equivalent for Offshore locations) the intended location (the “Connection Site”) of the Plant and Apparatus (the “User Development”) which it is desired should be connected to the National Electricity Transmission System and where the application is in respect of a proposed New Connection Site other than at an existing sub-station. Please specify the proposed location and name of the New Connection Site (which name should not be the same as or confusingly similar to the name of any other Connection Site) together with details of access to the Connection Site including from the nearest main road. ................................................................................................................. ................................................................................................................. .................................................................................................................
Please provide a plan or plans of the proposed Connection Site indicating (so far as you are now able) the position of all buildings, structures, Plant and Apparatus and of all services located on the Connection Site. ................................................................................................................. ................................................................................................................. ................................................................................................................. .................................................................................................................
Give details of the intended legal estate in the Connection Site (to include leasehold and freehold interests and in the case of Connection Sites in Scotland legal interests and heritable or leasehold interests
Who occupies the Connection Site in so far as you are aware? ................................................................................................................. .................................................................................................................
If you believe that a new sub-station will be needed, please indicate by reference to the plan referred to in Section B question 2 above the Applicant’s suggested location for it - giving dimensions of the area. ................................................................................................................. .................................................................................................................
If you are prepared to make the land necessary for the said sub-station available the Relevant Transmission Licensee for New Connection Sites Onshore or Offshore, make the land or Offshore, make the land or Offshore Platform available to the Relevant Transmission Licensee ` please set out brief proposals for their interest in it including (if relevant) such interest and the consideration to be paid for it. .................................................................................................................
Is space available on the New Connection Site for working storage and accommodation areas for the contractors of the Relevant Transmission Licensee? If so, please indicate by reference to the plan referred to in Section B question 2 above the location of such areas, giving the approximate dimensions of the same. ................................................................................................................. ................................................................................................................. .................................................................................................................
For Connection Sites located Onshore, please provide details (including copies of any surveys or reports) of the physical nature of land in which you have a legal estate or legal interest at the proposed Connection Site including the nature of the ground and the sub-soil. ................................................................................................................. .................................................................................................................
Please give details and provide copies of all existing relevant planning and other consents (statutory or otherwise) relating to the Connection Site and the User Development and/or details of any pending applications for the same. ................................................................................................................. ................................................................................................................
Is access to or use of the Connection Site for the purposes of installing, maintaining and operating Plant and Apparatus subject to any existing restrictions? If so, please give details.
If you are aware of them, identify by reference to a plan (if possible) the owners and (if different) occupiers of the land adjoining the Connection Site. To the extent that you have information, give brief details of the owner's and occupier's estates and/or interests in such land. ................................................................................................................. ................................................................................................................. .................................................................................................................
If the New Connection Site is located in Offshore Waters, please indicate of the earliest date for entry of this project into the Offshore Tender Process. If no date is provided it will be assumed to be for entry into the first Offshore Tender Process following acceptance of the Offer. .................................................................................................................
Summary of Application (brief description of plant to be connected): ....…………………………………………………………………………………... ……………………………………………………………………………………… ………………………………………………………………………………………
Please provide full details of the proposed application together with the relevant Standard Planning Data as listed in Part 1 of the appendix to the Planning Code which are applicable to you. Note: the data concerned forms part of the Planning Code and Data Registration Code. Applicants should refer to these sections of the Grid Code for an explanation.
Please provide a copy of your Safety Rules if not already provided to The Company. Included [ ] Already provided [ ] Will be provided later [ ]
Please indicate if your plant may be able to provide (or you could consider providing) the following technical capability):- a. Generation from Auxiliary Units (Reserve Services) [ ] b. Spinning Generation [ ] c. Fast Start capability [ ]
Please confirm your intended Connection Entry Capacity (MW) Connection Site [ ] Generating Unit(s) (if applicable) Generating Unit 1 [ ] Generating Unit 2 [ ] Generating Unit 3 [ ] Generating Unit 4 [ ]
Please state the required Transmission Entry Capacity………….....MW
Please confirm if: a. You would like an offer that is compliant with the deterministic criteria detailed, in the case of Onshore Connection Sites, in paragraphs 2.5 to 2.13 and, in the case of Offshore Connection Sites, in paragraphs 7.7 to 7.19 of the NETS SQSS YES/NO and/or b You would like an offer on the basis of a Design Variation. YES/NO If yes, please provide any information relevant to such an offer below: ……………………………………………………………………………………. …………….................................................................................................. ……………………………………………………………………………………. If yes, please confirm if you require information from The Company in relation to the probability of Notification of Restrictions on Availability being issued. YES/NO
Do you wish to suggest an ownership boundary different from that set out in CUSC Paragraph 2.12? Yes [ ] No [ ] If yes please give details:……………………………………………..………… ……………………………………………………………………………………… ……………………………………………………………………………………… ………………………………………………………………………………………
Please confirm which ownership boundary at CUSC Paragraph 2.12.1 (f) you would want in the event that the Transmission substation at which the Applicant is to be connected is to be of a Gas Insulated Switchgear design:
CUSC Paragraph 2.12.1 (f) (i) [ ]
CUSC Paragraph 2.12.1 (f) (ii) [ ] Please note that in the case where the ownership boundary is in accordance with CUSC Paragraph 2.12.1 (f) (i) restrictions on availability as described within CUSC Schedule 2 Exhibit 1 will apply in the event of a GIS Asset Outage.
Are you considering building any assets that would be identified as Transmission Connection Assets? If you indicate yes The Company will contact you to discuss further details.
For New Connection Sites located in Offshore Waters please indicate whether you are including any of the following items of additional information alongside your application. Applicants should note that though these items are not compulsory The Company will supply such information into the Offshore Tender Process in order that it may be expedited and may use the information in developing assumptions prior to the identification of Construction Works required Offshore. Feasibility Studies [ ] Crown Estate Lease [ ] Identified sub-sea cable routes [ ] Identified cable landing points [ ] Other (please specify) [ ]
Applicants should note that for Generating Units proposed to be connected to an Offshore Transmission System certain requirements in respect of Reactive Power capability (contained within the STC, Section K and in the case of Offshore Transmission System Development User Works, the Grid Code) are placed upon the owner of the Offshore Transmission System. However the Grid Code also permits part or all of this requirement to be met by the Generating Units connected to the Offshore Transmission System should it be more efficient to do so. In order that an assessment of the most efficient method of providing Reactive Power capability may be made by an owner of an Offshore Transmission System an Applicant for a New Connection Site located Offshore is required to indicate (where known) the expected Reactive Power capability of the Generating Units expected to be connected at the New Connection Site. Where applicable please also reference in Section C, part 4f above. ………………………………………………………………………………. ………………………………………………………………………………. ………………………………………………………………………………. ………………………………………………………………………………. ……………………………………………………………………………….
We confirm we do not/do want the Enabling Works to be greater in scope than the MITS Connection Works.
If you want the Enabling Works to be greater in scope than the MITS Connection Works specify the concerns, reasons or technical requirements that you are seeking to address by this.
We hereby apply to connect our Plant and Apparatus to the National Electricity Transmission System at a New Connection Site. We agree to pay The Company’s Engineering Charges on the terms specified in the Notes to the Connection Application.
We will promptly inform The Company of any change in the information given in this application as quickly as practicable after becoming aware of any such change.
If we are not already a CUSC Party we undertake for the purposes of this application to be bound by the terms of the Grid Code from time to time in force and to sign a CUSC Accession Agreement.
We authorise the release of certain information, on the grounds of commercial confidentiality, to the appropriate Public Distribution System Operator(s) or to the Relevant Transmission Licensee, or to the Authority in order to comply with The Company’s obligations with respect to the Offshore Tender Process, should it be considered necessary.
We confirm that we: meet The Company Credit Rating [ ] do not meet The Company Credit Rating. [ ]
We confirm our agreement to the disclosure in the manner set out in Paragraph 6.30.3 of CUSC of the information specified in such Paragraph.
We confirm that we are applying in the category of: Directly Connected Power Station [ ] Non-Embedded Customer [ ] Distribution System Directly Connected to the National Electricity Transmission System [ ] [Please tick correct option].
We confirm that this is an application for a: Gate 1 Offer [ ] Gate 2 Offer [ ] Please tick correct option
If this was to be considered by The Company, we would/would not be interested in Reservation. [delete as appropriate]
Exhibit C
1. The Company offers to enter into a Bilateral Connection Agreement and Construction Agreement covering the Connection Site, reference number []. If you are not already a CUSC Party you are required to enter into the enclosed CUSC Accession Agreement.
2. It is a condition of this Offer that (i) you also enter into an Interface Agreement covering the Connection Site in a form to be agreed between the parties but substantially in the form of Exhibit O of the complete CUSC [and (ii) where required by The Company you enter into a Transmission Related Agreement (power station with Design Variation and/or Offshore Standard Design and/or a connection via an ET Offshore Transmission System and/or Non Standard Boundary only)].
3. It is a condition of this Offer that the Connection Site is not a nominated site under the “NAECI” (the National Agreement for the Engineering Construction Industry) conditions and will not become one and any agreement for this site will be conditional upon this. In the event that this condition should not be met, The Company will be entitled to revise all the dates and charges contained in the Bilateral Connection Agreement and Construction Agreement.
4. The technical conditions with which you must comply as a term of this Offer are set out in the Grid Code. Additional technical conditions are set out in the Appendices to the Bilateral Connection Agreement. It is your responsibility to ensure that your equipment complies with the requirements of the relevant conditions.
5. This Offer is open for acceptance according to the terms of Paragraph 2.13 of the CUSC and the ESO Licence. Please note your right to make an application to the Authority to settle the terms of the offer pursuant to condition E13 of the ESO Licence.
6. [Please note the provisions of Paragraph 6.10.4 of the CUSC in respect of interactive offers which, inter alia, allows The Company to vary the * Delete if connection only. terms of this Offer if a Connection or Modification Offer, which interacts with this Offer, is accepted first. In terms of Paragraph 6.10.4 of the CUSC, The Company will advise you of another offer being made by The Company, which may interact with your Offer. Delete if Offer is a Gated Offer]
7. Please note that in accordance with the obligation in Paragraph 1.3.3 of the CUSC a Mandatory Services Agreement must be entered into not later than 6 months (or such lesser time as may be agreed) prior to the expected Commissioning Programme Commencement Date.
8. In the case of New Connection Sites located in Offshore Waters this Connection Offer identifies the Onshore Construction Works. These are based on assumptions about the Offshore Construction Works. The assumptions are set out in the Construction Agreement but the Offshore Construction Works are not themselves be identified at this time. Please note that the Construction Programme assumes a date by which the Offshore Transmission Owner will be appointed and will be amended should this date not be met.
9. This Offer in respect of New Connection Sites located in Offshore Waters has been prepared on the basis that you wish to undertake OTSDUW Build). The Offer assumes (unless you have advised us of the extent of the Offshore Transmission System Development User Works that you wish to undertake) that these are the works (and the activities associated with them) required to deliver a connection from the Offshore Grid Entry Point to the Onshore Transmission System at the Transmission Interface Point based on the
10. Should you wish to revise the nature or extent of the Offshore Transmission System Development User Works that you wish to undertake prior to acceptance of the Offer please advise us as soon as practicable as to your intentions.] [clause 9 and 10 will be included in your connection offer unless you have have indicated in your connection application that you are not interested in undertaking OTSDUW.]
11. To accept this Offer, please sign (and where issued by email, having printed off 2 copies of each) and return the originals of the [CUSC Accession Agreement and] Bilateral Connection Agreement [Construction Agreement] attached to this Offer as Sections A. The Company will then itself countersign these agreements and one original of each will be returned to you for your retention. The agreements are only effective in accordance with their terms once they have been countersigned by The Company.
12. All communications in relation to this Offer must, in the first instance, be directed to [description]. [13 This Offer is made on the basis of the Connect and Manage Arrangements [except that as requested the Enabling Works are greater in scope than the MITS Connection Works] [Directly Connected Power Station or Distribution System where associated with Distributed Generation only]] 14. This is a [[Gate 1 Offer] [with] [without] Reservation]] [Gate 2 Offer] for the purposes of the Gated Application and Offe
Exhibit D
1. The Company requires the information requested in this application form for the purposes of preparing an Offer (the “Offer") to enter into an agreement for use of the National Electricity Transmission System. It is essential that the Applicant should supply all information requested in this application form and that every effort should be made to ensure that such information should be accurate. Please note that in the case of a Gated Application under the Gated Application and Offer Process you can apply fo
2. Where The Company considers that any information provided by the Applicant is incomplete or unclear, or further information is required, the Applicant will be requested to provide further information or clarification. The provision/clarification of this information may impact on The Company’s ability to commence preparation of an Offer.
3. Should there be any change in the information provided by the Applicant immediately inform The Company of such a change. Where this is a change in the information provided for Sections B to D then the Applicant should inform The Company to see if such a change can be accommodated as it is unlikely that material changes could be accommodated. If The Company cannot accommodate such a change bearing in mind the timescales within which the Offer must be made then the application will be processed on the origina
4. The Company shall charge the Applicant, and the Applicant shall pay to The Company, The Company’s Engineering Charges in relation to the application. A fee will be charged by The Company in accordance with the Charging Statements. No application will be considered until such payment has been received.
5. The effective date upon which the application is made shall be the later of the date when The Company has received the application fee pursuant to Paragraph 4 above or the date when The Company is reasonably satisfied that the Applicant has completed Sections A-D. The Company shall notify the Applicant of such date. Please note the additional requirements for a Gate 2 Application under the Gated Application and Offer Process at CUSC Section 17. Also note that whilst a Distribution EG Related Application is
6. The Company will make the Offer in accordance with the terms of Paragraph 3.7 (Use of System Application) and Paragraph 6.10 (Modifications and New Connection Sites) of the CUSC and the ESO Licence.
7. The Company will make the Offer (a) if it is not a Gated Offer under the Gated Application and Offer Process, as soon as is reasonably practicable and, in any event, within 28 days of the effective date of the application or such later period as the Authority agrees to and (b) if it is a Gated Offer, in accordance with the Gated Application and Offer Process or such later period as the Authority agrees to. The Offer may, where it is necessary to carry out additional extensive system studies to evaluate more
8. In the course of processing your application, it may be necessary:
for The Company to consult the appropriate Public Distribution System Operator(s) on matters of technical compatibility of the National Electricity Transmission System with their Distribution System(s) or to consult the Relevant Transmission Licensees to establish the works required on the National Electricity Transmission System. On grounds of commercial confidentiality The Company shall need your authorisation to the release to the Public Distribution System Operator(s) or the Relevant Transmission Licensees of certain information contained in your application. Any costs incurred by The Company in consulting the Public Distribution System Operator(s) or Relevant Transmission Licensees would be included in The Company Charges for the application. If it is found by the Public Distribution System Operator(s) that any work is required on their Distribution System(s), then it will be for the Public Distribution System Operator(s) and the Applicant to reach agreement in accordance with Paragraph 6.10.3 of the CUSC; or
for The Company to share with the Competent Authority information from the application relevant in the consideration of control of qualifying assets under (and as defined in) the National Security and Investment Act 2021.
9. In accordance with 6.30.3 of CUSC The Company will need to disclose details of the Bilateral Embedded Generation Agreement entered into and shall need authorisation from the Applicant in respect of this.
10. If the Applicant is not already a CUSC Party the Applicant will be required as part of this application form to undertake that he will comply with the provisions of the Grid Code for the time being in force. Copies of the Grid Code and the CUSC are available on The Company’s Website and the Applicant is advised to study them carefully. Data submitted pursuant to this application shall be deemed submitted pursuant to the Grid Code.
11. The Company's Offer will be based to the extent appropriate upon its standard form terms for Use of System Offer and the Charging Statements issued by The Company under conditions E10 and E11 of the ESO Licence. The Applicant should bear in mind The Company 's standard form terms of Offer when making this application.
12. In particular please note that The Company may require as a condition of the Offer, that the Applicant's Plant or Apparatus should meet or provide some or all of the technical requirements set out in the Appendices of the draft Bilateral Embedded Generation Agreement attached to The Company's standard form terms of Offer and may propose that the Applicant's Plant or Apparatus should have the capability to provide Mandatory Ancillary Services.
13. As provided for in Grid Code CC8.1 Generators and DC Converter station owner should appreciate that they will be required to perform Mandatory Ancillary Services to ensure that System Operational Standards can be achieved. This requirement may have implications towards plant specification. You should be satisfied before an application is made that your intended plant design can meet the requirements.
14. The Applicant has the ability to pay a fixed price application fee in respect of their application or pay the actual costs incurred (variable price application fee). The fixed price application fee is derived from analysis of historical costs of similar applications. The variable price application fee is based on an advance of the Transmission Licensee’s Engineering and out of pocket expenses and will vary according to the size of the scheme and the amount of work involved. The Applicant is requested to ind
15. Applicants have the option to request a Connection Offer on the basis of a Design Variation. In requesting such an Offer, the Applicant acknowledges that the connection design (which provides for connection to the National Electricity Transmission System) will fail to satisfy the deterministic criteria detailed in paragraphs 2.5 to 2.13 of the NETSSQSS. In making such an Offer, in accordance with its obligations under Paragraphs 2.13.2 and 2.13.7 of CUSC. The Company may include Restrictions on Availability
16. Please complete this application form in black print and return it together with the appropriate application fee to The Company. In addition to returning the application to the Customer Services Manager an electronic form may be e-mailed to The Company.
17. For the most up to date contact details applicants are advised to contact The Company Website.
Registered Company Name: Address (of Registered Office in the case of a Company): Company Number: Parent Company Name (if applicable):
Company Secretary or person to receive CUSC notices Name: Email: Telephone: F a x :
Commercial Contact/Agent (person to receive Offer if different from Company Secretary or person to receive CUSC notices identified in 2 above) Name: Title: Address: Email: Telephone: F a x :
Please identify which application fee basis you wish to use for this application. Fixed application fee [ ] Variable application fee [ ]
If this is an application for connection to the National Electricity Transmission System in England and Wales please complete 5a. If this is an application for connection to the National Electricity Transmission System in Scotland please complete 5b. 5a Have you made any applications for connection to the National Electricity Transmission System in Scotland which are being processed prior to Offer by The Company or where an Offer has been made that Offer has not yet been accepted by you but remains open for acceptance? If so, are such applications intended as alternatives to this one i.e. you intend to choose which of this or those other applications to proceed with on the basis of the offer made. Yes – please list the applications. No [ ] Not sure [ ] (The Company will contact you to clarify) 5b Have you made any applications for connection to the National Electricity Transmission System in England and Wales which are being processed prior to Offer by The Company or where an Offer has been made that Offer has not yet been accepted by you but remains open for acceptance? If so, are such applications intended as alternatives to this one i.e. you intend to choose which of this or those other applications to proceed with on the basis of the offer made. Yes – please list the applications.
Please identify (preferably by reference to an extract from Ordnance Survey Map) the intended location of the Plant and Apparatus (the "User Development") which it is desired should be connected to the Distribution System.
If you believe that a new sub-station will be needed, please indicate by reference to a plan your suggested location for it.
Summary of Application (brief description of plant to be connected):
Please provide the data listed in Part 1 of the Appendix to the Planning Code which are applicable to you. Note: the data concerned forms part of the Planning Code and Data Registration Code. Applicants should refer to these sections of the Grid Code for an explanation. Further guidance is available from The Company on request.
Please provide a copy of your Safety Rules if not already provided to The Company. Included [ ] Already provided [ ] Will be provided later [ ]
Please indicate if your plant may be able to provide (or you could consider providing) the following technical capability:- a. Generation from Auxiliary Units (Reserve Services) [ ] b. Spinning Generation [ ] c. Fast Start capability [ ] d. Frequency Response above Mandatory requirements [ ] e. Demand Reduction / Management [ ] f. Reactive capability above Mandatory requirements [ ] g. Synchronous Compensation [ ] h. Black Start Capability [ ] i. Emergency Maximum Generation [ ] j. Intertrip [ ] k. Other (please detail below) [ ]
Please state the required Transmission Entry Capacity .................. MW 5. Please confirm if: a. You would like an offer that is compliant with the deterministic criteria detailed in paragraphs 2.5 to 2.13 of the National Electricity Transmission System SQSS YES/NO and\or b. You would like an offer on the basis of a Design Variation YES/NO If yes, please provide any information relevant to such an offer below. If yes, please confirm if you require information from The Company in relation to the probability of Notification of Restrictions on
We confirm we do not/do want the Enabling Works to be greater in scope than the MITS Connection Works.
If you want the Enabling Works to be greater in scope than the MITS Connection Works specify the concerns, reasons or technical requirements that you are seeking to address by this.
We hereby apply to use the National Electricity Transmission System from our connection to [ ] Distribution System.
We will promptly inform The Company of any change in the information given in this application as quickly as practicable after becoming aware of any such change.
If we are not already a CUSC Party we undertake for the purposes of this application to be bound by the terms of the Grid Code from time to time in force and to sign a CUSC Accession Agreement.
We authorise the release of certain information, on the grounds of commercial confidentiality, (a) to the appropriate Public Distribution System Operator(s) or Relevant Transmission Licensees should it be considered necessary and (b) to the Competent Authority relevant in the consideration of control of qualifying assets under (and as defined in) the National Security and Investment Act 2021.
We confirm that we do/do not meet the Approved Credit Rating [and The Company Credit Rating].
We confirm our agreement to the disclosure in the manner set out in Paragraph 6.30.3 of CUSC of the information specified in such Paragraph.
We confirm that we are applying in the category of : Embedded Generator [ ] Distribution Interconnector Owner [ ] Small Power Station Trading Party [ ] [Please tick correct option].
We confirm that this is an application for a: Gate 1 Offer [ ] Gate 2 Offer [ ] Please tick correct option
Where the Application is in respect of a Large Embedded Generator, if this was to be considered by The Company, we would/would not be interested in Reservation. [delete as appropriate]. SIGNED BY: For and on behalf of the Applicant Date:
Exhibit E
1. The Company offers to enter into a Bilateral Embedded Generation Agreement [and Construction Agreement] reference number [] in the form and terms attached as Section A.
2. It is a condition of this offer that:
if not already a CUSC Party you enter into a CUSC Accession Agreement;
you satisfy The Company that you have entered into a Distribution Agreement with the owner/operator of the Distribution System for the connection of the User’s Plant to and the use of such Distribution System; [(iii) where required by The Company that you enter into a Transmission Related Agreement (power station with Design Variation only)]
3. The technical conditions with which you must comply as a term of this offer are set out in the Grid Code. Additional or different technical conditions are set out in the Appendices to the Bilateral Embedded Generation Agreement. It is your responsibility to ensure that your equipment complies with the requirements of the relevant conditions.
4. This offer is open for acceptance according to the terms of Paragraph 3.7.4 of the CUSC and the ESO Licence. Please note your right to make an application to the Authority to settle the terms of the offer pursuant to condition E13 of the ESO Licence. [5 Please note the provisions of Paragraph 6.10.4 of the CUSC in respect of interactive offers which, inter alia, allows The Company to vary the terms of this Offer if a Connection or Modification Offer, which interacts with this Offer, is
All communications in relation to this Offer should, in the first instance, be directed to [Description].
[This Offer is made on the basis of the Connect and Manage Arrangements [except that as requested the Enabling Works are greater in scope than the MITS Connection Works] [except Distribution Interconnector Owner]” ].
Include where a Gated Offer -This is a [Gate 1 Offer] [Gate 2 Offer] for the purposes of the Gated Application and Offer Process. Yours faithfully for and on behalf of
Exhibit F
1. The Company requires the information requested in this application form for the purposes of preparing an Offer (the “Offer") to allow the Applicant to use the National Electricity Transmission System. It is essential that the Applicant supplies all information requested in this application form and that every effort should be made to ensure that such information is accurate.
2. Where The Company considers that any information provided by the Applicant is incomplete or unclear or further information is required, the Applicant will be requested to provide further information or clarification. The provision/clarification of this information may impact on The Company’s ability to commence preparation of an Offer.
3. Should there be any change in any information provided by the Applicant after it has been submitted to The Company, the Applicant must immediately inform The Company of such a change.
4. The effective date upon which the application is deemed to have been received by The Company shall be the date when The Company is reasonably satisfied that the Applicant has completed Section A and paid The Company the application fee set out in the Statement of Use of System Charges2. The Company shall notify the Applicant of such date.
5. The Company will make the Offer in accordance with the terms of Paragraph 3.7 or 9.21 (Use of System Application) of the CUSC and the ESO Licence.
6. The Company will make the Offer as soon as is reasonably practicable and in any event within 28 days of the effective date of the application or such longer period as the Authority agrees to.
7. If the Applicant is not already a CUSC Party the Applicant will be required as part of this application form to undertake that they will comply with the provisions of the Grid Code for the time being in force. Copies of the Grid Code and the CUSC are available on The Company’s
Electricity Connections, National Grid Electricity System Operator, Faraday House, Warwick Technology Park, Gallows Hill, Warwick, CV34 6DA 2 https://www.nationalgrideso.com/node/120336 Website3 and the Applicant is advised to study them carefully. Data submitted pursuant to this application shall be deemed submitted pursuant to the Grid Code.
8. The Company's Offer will be based to the extent appropriate upon its standard form terms for Use of System Offer and the Charging Statements issued by The Company under conditions E10 and E11 of the ESO Licence. The Applicant should bear in mind The Company's standard form terms of offer when making this application.
9. Please complete this application form in black print and return it duly signed to Electricity Connections, National Energy System Operator, Faraday House, Warwick Technology Park, Gallows Hill, Warwick, CV34 6DA. In addition to returning the application to the Customer Services Manager an electronic form may be e-mailed to The Company.
10. For the most up to date contact details applicants are advised to visit The Company Website4.
https://www.nationalgrideso.com/codes 4 https://www.nationalgrideso.com/connections
Registered Company Name:…………………………………………………………………………... Address (of Registered Office in the case of a Company): .................................................................................................................... .................................................................................................................... .................................................................................................................... Company Number:...................................................................................... VAT Number (if applicable):…………………………………………………… Parent Company Name (if applicable):………………………..……………..
UK Address if company is registered outside the UK Name:………………………………………………………………………….... Address:…………………………………………………………………………. Email:……………………………………………………………………........... Telephone:………………………………………………………………………
Company Secretary or person to receive CUSC notices Name:………………………………………………………………………….... Email:……………………………………………………………………………. Telephone:……………………………………………………………………....
Commercial Contact/Agent (person to receive application fee invoice and Offer if different from Company Secretary or person to receive CUSC notices identified in 2 above) Name:…………………………………………………………………………..... Title:……………………………………………………………………………… Address:………………………………………………………………………..... ……………………………………………………………………………………. ……………………………………………………………………………………. Email:…………………………………………………………………………….. Telephone:…………………………………………………………………….....
Please confirm whether you agree to us sending the Offer in electronic form instead of hard copy and, if so, confirm the address for this as follows. Yes [ ] No [ ] Email address …………………………………………………..
We hereby apply to use the National Electricity Transmission System.
We will promptly inform The Company of any change in the information given in this Application as quickly as practicable after becoming aware of any such change.
If we are not already a CUSC Party we undertake for the purposes of this Application to be bound by the terms of the Grid Code from time to time in force and to sign a CUSC Accession Agreement.
We confirm that we are applying in the category of: Supplier [ ] Interconnector User [ ] Interconnector Error Administrator [ ] Virtual Lead Party [ ]
Where applying in the category of a Supplier, we confirm that we: meet the Approved Credit Rating [ ] do not meet the Approved Credit Rating [ ]
Where applying in the category of a Supplier, without prejudice to our right to provide security by other means, we can confirm that we intend to provide security via: Qualifying Guarantee [ ] Letter of Credit [ ] Cash in Escrow Account [ ] Bilateral Insurance Policy [ ] Insurance Performance Bond [ ] Independent Security Arrangement [ ] SIGNED BY: ............................................................................... For and on behalf of the Applicant Date:......................................................................
Exhibit G
01 October he Company Secretary Date: [] Dear XXXXXX, We refer to your application dated [] for use of the National Electricity Transmission System and to [here list other documents submitted by applicant in support of their application together with any relevant The Company communications relating to the application] and now set out below our offer for the use of the National Electricity Transmission System. Please note that certain expressions which are used in this Offer are defined in the Inte
The Company offers to provide use of the National Electricity Transmission System on the terms of the CUSC and as set out in the attached combined Use of System Supply Offer and Confirmation Notice. [As you are not already a CUSC Party you are also required to enter into the enclosed CUSC Accession Agreement].
2 If at the date you sign and return the acknowledgement and acceptance of the Use of System Supply Offer Notice you hold an Approved Credit Rating, you should delete Option B in the acknowledgement.
3 If at the date that you sign and return the acknowledgement and acceptance of the Use of System Supply Offer Notice you do not have an Approved Credit Rating, then you should delete Option A in the acknowledgement and then in accordance with Paragraph 3.21 of the CUSC you must put in place Security Cover to take effect from the date set out in the Use of System Supply Confirmation Notice.
4 The technical conditions with which you must comply as a term of this Offer are set out in the Grid Code.
5 This Offer is open for acceptance according to the terms of Paragraph 3.7 of the CUSC and the ESO Licence. Please note your right to make an application to the Authority to settle the terms of the Offer pursuant to condition E13 of the ESO Licence.
6 To accept this Offer, please sign (and where issued by email, having printed off 2 copies of each) and return the acknowledgement and acceptance on the duplicate copy of the Use of System Supply Offer and Confirmation Notice [and execute and return the CUSC Accession Agreement]. Subject to providing Security Cover in accordance with the provisions referred to in paragraph 3 above The Company will then itself [execute the CUSC Accession Agreement and] return a copy of the Use of System Offer and Confirmation
7 The CUSC Accession Agreement and use of the National Electricity Transmission System pursuant to the CUSC as indicated in the Confirmation Notice are only effective in accordance with their terms once they have been executed (or signed in the case of the Confirmation Notice) and dated by The Company.
8 All communications in relation to this Offer must, in the first instance, be directed to [description]. Yours faithfully for and on behalf of National Energy System Operator Limited
DEFINITIONS, INTERPRETATIONS AND CONSTRUCTION Unless the subject matter or context otherwise requires or is inconsistent therewith, terms and expressions defined in Section 11 of the CUSC have the same meanings, interpretations or constructions in this Use of System Supply Offer and Confirmation Notice (the “Notice”). Part I - Use of System Supply Offer Notice
COMMENCEMENT Subject to the other terms of this Notice, use of the National Electricity Transmission System and the requirement to pay Use of System Charges shall commence on the date The Company signs and dates Part II of this Notice,
CREDIT REQUIREMENTS The amount to be secured by the User if Option A in the acknowledgement is deleted is set out in the Appendix to this Notice.
TERM Subject to the provisions for earlier termination set out in the CUSC, the User’s right to use the National Electricity Transmission System pursuant to this Notice shall continue until the User gives The Company a Use of System Termination Notice pursuant to Paragraph 3.8 of the CUSC or use ceases under the provisions of the CUSC. We acknowledge and agree to the terms set out above. [ ] [Name of User] Date: Option A: We meet the Approved Credit Rating Option B: We do not meet the Approved Credit Rating Part II - Use of System Supply Confirmation Notice CONFIRMATION We hereby confirm that with effect from the date set out below you can use the National Electricity Transmission System as a Supplier in accordance with the terms of the CUSC and this Notice and are required to pay Use of System Charges. [ ] National Energy System Operator Limited Date: Appendix Amount of Security Cover required if Option A deleted: £[ ]
Exhibit H
1. The Company offers to provide use of the National Electricity Transmission System to you as an [Interconnector User / Interconnector Error Administrator] on the terms of the CUSC and as set out in the attached combined Use of System Interconnector Offer Notice and Confirmation Notice. [As you are not already a CUSC Party you are also required to enter into the enclosed CUSC Accession Agreement.]
2. The technical conditions with which you must comply as a term of this Offer are set out in the Grid Code.
3. This Offer is open for acceptance according to the terms of Paragraph 9.21.4 of the CUSC and the ESO Licence. Please note your right to make an application to the Authority to settle the terms of the Offer pursuant to condition E13 of the ESO Licence.
4. To accept this Offer, please sign (and where issued by email, having printed off 2 copies of each) and return the acknowledgement and acceptance on the duplicate copy of the Use of System Interconnector Offer and Confirmation Notice [and execute and return the CUSC Accession Agreement]. Subject to providing Security Cover in accordance with paragraph 3 above The Company will then itself [execute the CUSC Accession Agreement and] return a copy of the Use of System Interconnector Offer and Confirmation Notice
5. The [CUSC Accession Agreement and] use of the National Electricity Transmission System pursuant to the CUSC as indicated in the Confirmation Notice are only effective in accordance with their terms once they have been signed [(or executed in the case of the CUSC Accession Agreement)] and dated by The Company. v18 – 01 October
6. All communications in relation to this Offer must, in the first instance, be directed to [description]. Yours faithfully for and on behalf of National Energy System Operator Limited
DEFINITIONS, INTERPRETATIONS AND CONSTRUCTION Unless the subject matter or context otherwise requires or is inconsistent therewith, terms and expressions defined in Section 11 of the CUSC have the same meanings, interpretations or constructions in this Use of System Interconnector Offer and Confirmation Notice ("Notice"). Part I - Use of System Interconnector Offer Notice
COMMENCEMENT Subject to the other terms of this Notice, use of the National Electricity Transmission System as an [Interconnector User/Interconnector Error Administrator] shall commence on the date The Company signs and dates Part II of this Notice. v1.8 – 01 October
TERM Subject to the provisions for earlier termination set out in the CUSC, the User’s right to use the National Electricity Transmission System pursuant to this Notice shall continue until the User gives The Company a Use of System [Interconnector] Termination Notice pursuant to Paragraph [9.23.1] of the CUSC or use ceases under the provisions of the CUSC. We acknowledge and agree to the terms set out above. [ ] [Name of User] Date: Part II - Use of System Interconnector Confirmation Notice CONFIRMATION We hereby confirm that with effect from the date set out below you can use the National Electricity Transmission System as an [Interconnector User / Interconnector Error Administrator] in accordance with the terms of the CUSC and this Notice. [ ] National Energy System Operator Limited Date:
Exhibit I
1. The Company requires the information requested in this application form for the purposes of preparing an offer (the “Offer”) of a Construction Agreement for the construction of a proposed Modification and for the variation of the existing [Bilateral Connection Agreement or Bilateral Embedded Generation Agreement or Construction Agreement] affected by the Modification. It is essential that the Applicant should supply all information requested in this application form and that every effort should be made to e
2. Where The Company considers that any information provided by the Applicant is incomplete or unclear, or further information is required, the Applicant will be requested to provide further information or clarification. The provision/clarification of this information may impact on The Company’s ability to commence preparation of an Offer.
3. Should there be any change in the information provided by the Applicant then the Applicant should immediately inform The Company of such a change. Where this is a change in the information provided for Sections B to D then the Applicant should contact The Company to see if such a change can be accommodated as it is unlikely that material changes could be accommodated. If The Company cannot accommodate such a change bearing in mind the timescales within which the Offer must be made then the application will
4. The Company shall charge the Applicant, and the Applicant shall pay to The Company, The Company’s engineering charges in relation to the application. A fee will be charged by The Company in accordance with the Charging Statements. No application will be considered until such payment has been received.
5. The effective date upon which the application is made shall be the later of the date when The Company has received the application fee pursuant to paragraph 4 above or the date when The Company is reasonably satisfied that the Applicant has completed Sections A-D. The Company shall notify the Applicant of such date.
6. The Company will make the Offer in accordance with the terms of Paragraphs 6.9 (Modification) and 6.10 (Modifications and New Connection Sites) of the CUSC and the ESO Licence.
7. The Company will make an Offer (a) if it is not a Gated Modification Offer, as soon as is reasonably practicable and, in any event, within three
3 months of the effective date of the application or such later period as the Authority may agree and (b) if it is a Gated Modification Offer, in accordance with the Gated Application and Offer Process or such later period as the Authority may agree. The Offer may, where it is necessary to carry out additional extensive system studies to evaluate more fully the impact of the proposed development, indicate the areas that require more detailed analysis. Before such additional studies are required, the Applicant
8. In the course of processing the application, it may be necessary:
for The Company to consult the appropriate Public Distribution System Operator(s) on matters of technical compatibility of the National Electricity Transmission System with their Distribution System(s) or to consult the Relevant Transmission Licensees to establish the works required on the National Electricity Transmission System. On grounds of commercial confidentiality, The Company shall need authorisation for the release to the Public Distribution System Operator(s) or Relevant Transmission Licensees of certain information contained in your application. Any costs incurred by The Company in consulting the Public Distribution System Operator(s) or Relevant Transmission Licensees would be included in The Company charges for the application. If it is found by the Public Distribution System Operator(s) that any work is required on their Distribution System(s), then it will be for the Public Distribution System Operator(s) and the Applicant to reach agreement in accordance with Paragraph 6.10.3 of the CUSC.
for The Company to share with the Competent Authority information from the application relevant in the consideration of control of qualifying assets under (as defined in) the National Security and Investment Act 2021.
9. In accordance with Paragraph 6.30.3 of CUSC, The Company will need to disclose details of any agreement to vary Bilateral Agreements and shall need authorisation from the Applicant in respect of this.
10. Data submitted pursuant to this application shall be deemed submitted pursuant to the Grid Code.
11. The Company’s Offer will, to the extent appropriate, be based upon its standard form terms of Modification Offer and the statement of charges issued by The Company under conditions E10 and E11 of the ESO Licence. The Applicant should bear in mind The Company’s standard form terms of Offer when making this application.
12. As provided for in Grid Code CC 8.1, Generators and Dc Converter Station owners should appreciate that they will be required to perform Mandatory Ancillary Services to ensure that System Operational Standards can be achieved. This requirement may have implications towards Plant specification. You should be satisfied that before an application is made that your intended Plant design can meet the requirements. Applicants are recommended to contact The Company1 where our staff will be pleased to help.
13. The Applicant has the ability to pay a fixed price application fee in respect of their application or pay the actual costs incurred (variable price application fee). The fixed price application fee is derived from analysis of historical costs of similar applications. The variable price application fee is based on an advance of the Transmission Licensee’s Engineering and out of pocket expenses and will vary according to the size of the scheme and the amount of work involved. The Applicant is requested to ind
14. Please complete this application form in black print and return it duly signed to The Company. In addition to returning the application to the Customer Services Manager an electronic form may be e-mailed to The Company.
15. For the most up to date contact details applicants are advised to visit The Company’s Website. SECTION A. DETAILS OF APPLICANT (in respect of this application)
Registered Company Name:……………………………………………………………………………. Address (of Registered Office in the case of a Company): .................................................................................................................... .................................................................................................................... .................................................................................................................... Company Number:...................................................................................... Parent Company Name (if applicable):……………………………………….
Company Secretary or person to receive CUSC notices Name:…………………………………………………………………………..... Email:…………………………………………………………………………….. Telephone:…………………………………………………………………….....
Commercial Contact/Agent (person to receive Offer if different from Company Secretary or person to receive CUSC notices as identified in 2 above) Name:…………………………………………………………………………..... Title:……………………………………………………………………………… Address:………………………………………………………………………..... ……………………………………………………………………………………. ……………………………………………………………………………………. Email:…………………………………………………………………………….. Telephone:…………………………………………………………………….....
Please identify which application fee basis you wish to use for this application. Fixed price application fee [ ] Variable price application fee [ ]
Please confirm whether you agree to us sending the Offer in electronic form instead of hard copy and, if so, confirm the address for this as follows. Yes [ ] No [ ] Email address ………………………………………………….. SECTION B THE CONNECTION SITE [AND, IN THE CASE OF A USER UNDERTAKING OTSDUW, THE TRANSMISSION INTERFACE SITE]
Please provide agreement reference number. ...............................................................................................................................
Please identify by name the Connection Site [and, in the case of a User undertaking OTSDUW, the Transmission Interface Site] at which the Modification is to be undertaken. ...............................................................................................................................
Give details of the rights in any additional land which you are proposing to acquire at the Connection Site [or, in the case of a User undertaking OTSDUW, the Transmission Interface Site] (to include leasehold and freehold interests and in the case of Connection Sites [or, in the case of a User undertaking OTSDUW, the Transmission Interface Site] in Scotland legal interests and heritable or leasehold interests including servitudes or other real rights) so as to undertake the Modification). ............................................................................................................................... ............................................................................................................................... ...............................................................................................................................
Is space available on the Connection Site [or, in the case of a User undertaking OTSDUW, the Transmission Interface Site] for working storage and accommodation areas for the contractors of the Relevant Transmission Licensees? If so, please indicate by reference to a plan the location of such areas, giving the approximate dimensions of the same. .............................................................................................................................. ............................................................................................................................... ...............................................................................................................................
Please provide details (including copies of any surveys or reports) of the physical nature of any additional land the subject to your answer to Question 2 above including the nature of the ground and the sub-soil. ...............................................................................................................................
Please give details and provide copies of all existing relevant planning and other consents (statutory or otherwise) held by you relating to the Connection Site [and/or, in the case of a User undertaking OTSDUW, the Transmission Interface Site] or the Modification and/or details of any pending applications for the same. ................................................................................................................... ...................................................................................................................
Please indicate what, if any, of the necessary construction works necessary for the Modification you would like The Company to conduct upon your behalf. ................................................................................................................... ...................................................................................................................
Summary of Application (brief description of plant to be connected): …………………………………………………….......................................... …............................................................................................................... ................................................................................................................
Please provide full details of the proposed Modification together with the relevant Standard Planning Data as listed in Part 1 of the Appendix to the Planning Code to the extent that the data will change from previously submitted Committed Project Planning Data or Connected Planning Data as a result of the proposed Modification. Note: the data concerned form part of the Planning Code and Data Registration Code. Applicants should refer to these sections of the Grid Code for an explanation. Further guidance is available from The Company on request.
Please notify The Company as to whether the Modification is associated with a BELLA/BEGA Application and if so details of the relevant BELLA/BEGA Application. BELLA/BEGA Agreement Ref: ……………………………………………… Site of Connection……………………………………………………………..
Please notify The Company as to whether the Modification is in respect of a request for a connection to and / or for the use of the User’s Distribution System from a Relevant Embedded Power Station Yes / No……………………………………………
We confirm we do not/do want the Enabling Works to be greater in scope than the MITS Connection Works.
If you want the Enabling Works to be greater in scope than the MITS Connection Works specify the concerns, reasons or technical requirements that you are seeking to address by this.
We hereby apply to modify our connection to the National Electricity Transmission System at [ ] Connection Site [and/or in the case of a User undertaking OTSDUW [ ] Transmission Interface Site].
We agree to pay The Company’s Engineering Charges on the terms specified in the Notes to the Connection Application.
We will promptly inform The Company of any change in the information given in this Application as quickly as practicable after becoming aware of any such change.
We authorise the release of certain information, on the grounds of commercial confidentiality, (a) to the appropriate Public Distribution System Operator(s) or Relevant Transmission Licensees should it be considered necessary and (b) to the Competent Authority relevant in the consideration of control of qualifying assets under (and as defined in) the National Security and Investment Act 2021.
We confirm that we do/do not meet The Company’s Credit Rating/Approved Credit Rating.
We confirm our agreement to the disclosure in the manner set out in Paragraph 6.30.3 of CUSC of the information specified in such Paragraph.
We confirm that this Modification is associated with a: BELLA Application [ ] BEGA Application [ ] [small or medium] Embedded Power Station [ ] None of the above [ ]
We confirm that this Modification is associated with: Gate 1 Agreements with/without Reservation [ ] Gate 1 Agreements which are to remain as Gate 1 Agreements [ ] Gate 1 Agreements which the Applicant wishes to modify into Gate 2 Agreements [ ]
We confirm this Modification is/is not a Modification of a type which is a Gated Modification in accordance with the Gated Modification Guidance. SIGNED BY: …………………………………………. For and on behalf of the Applicant Date..................................
Exhibit J
1. The Company offers to enter into an agreement to vary the [Bilateral Connection Agreement] or [Bilateral Embedded Generation Agreement] [Construction Agreement] in the form and terms attached (Reference No. []).
2. This offer has been prepared upon the basis that each party will construct, install, control, operate and maintain, in the case of the User, the Plant and Apparatus which it will own, and in the case of The Company, the Transmission Plant and Transmission Apparatus [including any OTSUA] applying the ownership rules set out in Paragraph 2.12 of the CUSC.
3. [It is a condition of this offer that prior to the relevant date for charging set out in the relevant Bilateral Agreement you also [enter into an Interface Agreement] or [agreement to vary the existing Interface Agreement] covering the Connection Site in a form to be agreed between the parties.]
4. [It is a condition of this offer that the Connection Site [or, in the case of a User undertaking OTSDUW, the Transmission Interface Site] is not a nominated site under the “NAECI” (the National Agreement for the Engineering Construction Industry) conditions and will not become one and any agreement for this site will be conditional upon this. In the event that the condition should not be met, The Company will be entitled to revise all the dates and charges contained in the Bilateral Connection Agreement [an
5. The technical conditions with which you must comply as a term of this offer are set out in the Grid Code. Additional or different technical conditions are set out in the Appendices to the [Bilateral Connection Agreement] or [Bilateral Embedded Generation Agreement] or, in the case of a User undertaking OTSDUW, the Construction Agreement]. It is your responsibility to ensure that your equipment complies with the requirements of the relevant conditions.
6. This offer is open for acceptance according to the terms of Paragraph 6.9 (Modifications) of the CUSC and the ESO Licence. Please note your right to make an application to the Authority to settle the terms of the Offer pursuant to condition E13 of the ESO Licence.
7. [Please note the provisions of Paragraph 6.10.4 of the CUSC in respect of interactive offers which, inter alia, allows The Company to vary the terms of this offer if a Connection or Modification Offer which interacts with this offer is accepted first. In terms of Paragraph 6.10.4 of the CUSC The Company will advise you of another offer being made by The Company which may interact with your offer. – delete if this is a Gated Modification Offer]
8. To accept this offer, please sign (and where issued by email, having printed off 2 copies of each) and return the [Construction Agreement] [Bilateral Construction Agreement] and [Bilateral Embedded Generation Agreement] attached to this offer as Section A and Section B. The Company will then itself countersign these agreements and one original of each will be returned to you for your retention. The agreements are only effective in accordance with their terms once they have been executed by The Company.
9. [This Offer is made on the basis of the Connect and Manage Arrangements [except that as requested the Enabling Works are greater in scope than the MITS Connection Works] [and on the basis of the OTSDUW Arrangements [Connect and Manage Power Station only].]
10. [Include where a Gated Modification Offer – This Offer is a Gated Modification Offer.] Yours faithfully for and on behalf of National Energy System Operator Limited SECTION A
Exhibit K
1. This Modification Notification is issued by The Company pursuant to Paragraph 6.9 of the CUSC. The User has certain rights under Paragraph 6.9 of the CUSC and is advised to consider whether it wishes to avail itself to such rights upon receipt of this Modification Notification.
2. The Company proposes to make the Modification to the National Electricity Transmission System (or in the case of Offshore Transmission System Development User Works those works) set out below:-
3. The Company reasonably believes that you may have to carry out the following works as a result of the proposed Modification:-
4. The latest date upon which you may apply to the Authority under condition E13 of the ESO Licence is [date: to be supplied by The Company, subject to Paragraph 6.9 of the CUSC.] Dated: Signed for and on behalf of National Energy System Operator Limited
Exhibit L
1. The Company Engineering Charges and expenses for obtaining Consents pursuant to Clause 2.4;
2. Termination Amounts.
Exhibit M
Exhibit MM1
Exhibit MM2
January 2026 EXH MM2 v4
Exhibit MM3
| Pre Trigger Amount | Cancellation Charge Profile | TEC/DC | £/MW | |
|---|---|---|---|---|
| Financial Year [1] | ||||
| Financial Year [ 2] | ||||
| Financial Year [3] | ||||
| Attributable Works Cancellation Amount | Cancellation Charge Profile | £/MW | ||
| Financial Year [1] | £ | % | ||
| Financial Year [2] | £ | % | ||
| Financial Year [3] | £ | % | ||
| Charging Date/Financial Year [0] | £ | % |
Exhibit N
Exhibit O - Part 1B
1. [] a company registered in [] (with number []) whose registered office is at [] (“User”, which expression shall include its successors and/or permitted assigns); and
2. [Insert name of Relevant Transmission Licensee] a company registered in [] with number [] whose registered office is at [] (“RTL”, which expression shall include its successors and/or permitted assigns)] WHEREAS Certain assets and facilities of the RTL are to be installed on property title to which is vested in User and this Agreement is entered into by the Parties to give effect to appropriate arrangements in respect of such assets and the use of such assets and facilities. NOW IT IS HEREBY AGREED as fo
1. DEFINITIONS AND INTERPRETATION In this Agreement, the following words and expressions shall, unless the subject-matter or context otherwise requires or is inconsistent therewith, bear the following meanings:- “Act” the Electricity Act 1989 as amended by Utilities Act 2000; “Affiliate” in relation to User means any holding company or subsidiary of that Party or any subsidiary of a holding company of User, in each case within the meaning of Sections 736, 736A and 736B of the Companies Act 1985 as substituted
unless the context otherwise requires all references to a particular clause, sub-clause, paragraph or Schedule shall be a reference to that clause, sub-clause, paragraph or Schedule in or to this Agreement;
the table of contents and headings are inserted for convenience only and shall be ignored in construing this Agreement;
references to the words “include” or “including” are to be construed without limitation to the generality of the preceding words;
unless there is something in the subject matter or the context which is inconsistent therewith, any reference to an Act of Parliament or any Section thereof or Schedule thereto, or other provision thereof or any instrument, order or regulation made thereunder shall be construed at the particular time as including a reference to any modification, extension, replacement or re-enactment thereof then in force and to all instruments, orders or regulations then in force and made under or deriving validity from the relevant Act of Parliament; and
references to the masculine shall include the feminine and references in the singular shall include the plural and vice versa and words denoting natural persons shall include companies, corporations and any other legal entity and vice versa.
unless otherwise provided to the contrary herein, defined terms used in this Agreement and not defined herein shall have the meaning set forth in the Connection and Use of System Code or the Bilteral Connection Agreement.
2. Right to Install and Retain Asset 8
Subject to sub-clause 5.1, User hereby grants to the RTL the right to install and thereafter retain and replace as provided in this Agreement RTL Assets on User’s Land in such places as are currently proposed (subject to such variations between the date hereof and the actual date of installation as may be agreed to by User) and such right shall extend to any Modified RTL Assets. User shall maintain any shelter and/or support enjoyed by any RTL Assets at the date of this Agreement or, if later, when relocated on User’s Land in accordance with clause 5 and grants to the RTL a Right of Access for the purpose of the maintenance, inspection, testing, removal, operation, Modification or repair of any RTL Assets.
3. Modifications, Replacements and Alterations 8
The RTL may at its own expense replace or alter any RTL Assets provided that:- 3.1.1 the replacement RTL Assets or the RTL Assets as so altered:-
are placed in the same or approximately the same position;
fulfil the same or a similar purpose;
can, where relevant, be accommodated in and on existing buildings or structures;
do not require additional or improved facilities or services from User;
do not restrict the actual and intended use of User’s Land and any equipment thereon or therein to any materially greater extent than the RTL Assets so replaced or altered; and
are either of the same or a similar or smaller size or the alteration is effected substantially within the space occupied by such RTL Assets to enable the RTL Assets to be used up to their full capability; and 3.1.2 prior written notification has been given to User.
If any replacement or alteration permitted by clause 3.1 shall require minor alterations or work to the existing buildings or structures housing or supporting the RTL Assets in question, such alterations or works may be carried out (with the prior written approval of User (such approval not to be unreasonably withheld or delayed)) but at the cost of the RTL.
To the extent that any of the conditions of clause 3.1 are not in User’s reasonable opinion met in relation to any replacement or alteration, User may by notice in writing require the RTL promptly to remove such replacement or alteration and, if the RTL fails to do so, may remove the same itself at the cost and expense of the RTL. On such removal, the RTL may reinstate the RTL Assets so replaced or altered.
The RTL shall, if considering moving, replacing, or altering any of the RTL Assets, give due consideration as to whether it shall be operationally practicable, desirable and reasonably economic to move such RTL Assets to (or place the replacement or altered RTL Assets on) its own property.
For the avoidance of doubt it is hereby agreed that any dispute between the Parties regarding this clause shall be determined in accordance with the provisions of Clause 10 of this Agreement.
4. SECURITY AND COMPLIANCE WITH STATUTES etc
User undertakes to maintain and provide security in relation to the RTL Assets in accordance with the arrangements set out in Part I of Schedule 3.
Each Party shall procure that, as between the Parties, all reasonable and necessary steps are taken, as and when necessary or desirable, in co-operation with the other (and, so far as applicable, with any third party), to ensure compliance with the provisions (each such provision or part thereof being in this clause 4 an “Obligation”) of:-
all statutes and Directives applicable to any RTL Assets and/or any part (including the whole) of User’s Land;
any statute or Directive which may affect any other property (of whatever nature) of either Party as a result of the existence, nature, location, or manner of operation of any RTL Assets; and
any statute or Directive requiring the reporting of any occurrence relating to or affecting any RTL Assets and/or User’s Land (including the Reporting of Injuries Diseases and Dangerous Occurrence Regulations 1985 and the Regulations).
Each Party shall, so far as it is aware of the same, unless it has reasonable grounds for believing that the other Party possesses the information, keep the other Party informed of all matters relating to any Obligation or potential Obligation and/or the extent to which such Obligation may be applicable.
In the event of any dispute as to responsibility, as between the Parties, pursuant to clause 4.2, for compliance with an Obligation, that responsibility shall be allocated, so far as practicable, on the basis that:-
each Party shall refrain from taking or permitting any act or omission which would prevent compliance with an Obligation; and
positive action required in relation to a Party’s property as a consequence of the existence, nature, location or manner of operation of that property or any other property of that Party shall be the responsibility of that Party, and, to the extent that such action is required in respect of or affecting any property of the other Party (or property of a third party located in or on that other Party’s land), such action may be taken with the prior approval of that other Party (such approval, subject to (i) above, not to be unreasonably withheld or delayed).
The provisions for safety co-ordination between the Parties contained in Part II of Schedule 3 shall apply.
5. Relocations 11
At any time and from time to time during the term of this Agreement, User may with the prior written consent of the RTL (such consent not to be unreasonably withheld or delayed) require the RTL to relocate any RTL Assets either to a different location on the User Land or to the RTL’s or a third party’s land, such consent to be sought and given or refused in accordance with the following procedure:-
User shall serve a written notice on the RTL, which notice shall specify:-
the RTL Assets which User wishes to be relocated;
the reasons for such wish;
the proposed new location for such RTL Assets; and
the timing of the carrying out of such relocation.
The RTL shall within one month of receipt of any such notice (or such longer period as shall be reasonably necessary) serve a counter notice stating:-
whether or not in its reasonable opinion such Relocation Proposal is acceptable to it;
if the Relocation Proposal is not acceptable to the RTL, the grounds for such opinion and the terms of any alternative proposal (the “Alternative Relocation Proposal”) covering so far as relevant the matters referred to in items (a) - (d) of clause 5.1.1 which would be acceptable to the RTL; and
in respect of the Relocation Proposal (if accepted) or of any Alternative Relocation Proposal, the costs likely to be incurred in connection with considering the Relocation Proposal or the Alternative Relocation Proposal and effecting the said relocation of the RTL Assets and the proper and reasonable costs of relocating any other equipment that may be necessary as a result of the relocation of those RTL Assets and any consequential losses including payments to third parties incurred as a result of the relocation of those RTL Assets and the proposed manner and timing of payment of the same by User.
If within one month of the date of such counter notice (or such longer period as shall be reasonably necessary) User has not withdrawn the Relocation Proposal and the Parties have not agreed upon it or the Alternative Relocation Proposal (if any) or a variation of either of them (such agreement to include agreement on the costs referred to in item (c) of clause 5.1.2) the matter shall be dealt with in accordance with Clause 10.
Upon approval or settlement of any Relocation Proposal, Alternative Relocation Proposal or variation thereof pursuant to clause 5.1, the RTL shall (conditionally upon it being able to obtain all necessary licences and consents which it will use reasonable endeavours to do) relocate or procure the relocation of the relevant RTL Assets as quickly as reasonably practicable (having regard to, amongst other things, technical and operational requirements and to the availability of all necessary licences and consents).
User shall render all reasonable assistance to the RTL in connection with such relocation licences and consents and pay to the RTL all costs referred to in item (c) of clause 5.1.2 as agreed or settled pursuant to clause 5.1 provided that all reasonable endeavours are used to minimise such costs and in the event that a Relocation Proposal is withdrawn or consent thereto is reasonably withheld pursuant to clause 5.1, User shall pay to the RTL all costs reasonably incurred by the RTL in connection with considering the Relocation Proposal and any counter notice.
Such of the provisions of this Agreement as are appropriate and relevant (including the provisions of this clause 5), shall continue to apply to any relocated RTL Assets.
6. Removals 13
In the event that there shall cease to be a Bilateral Connection Agreement relating to any RTL Assets on User’s Land the RTL shall remove all RTL Assets from User’s Land in accordance with the provisions relating thereto contained in the Connection Agreement and the Bilateral Connection Agreement.
Where the RTL is obliged to remove any of the RTL Assets from User’s Land, whether under this Clause 6, and fails to do so in accordance with the relevant provisions, (whether they be contained in this Clause 6, Clause 3 or Clause 5) User shall be entitled to remove those RTL Assets to land belonging to the RTL and the RTL shall provide all reasonable assistance to enable User safely so to do and shall pay and reimburse to User all costs and expenses reasonably incurred by User in so doing.
7. Rights of Access 13
A Right of Access includes the right to bring on to User’s Land such vehicles, plant, machinery and maintenance or construction materials as shall be reasonably necessary for the Permitted Purpose.
A Right of Access given to the RTL may be exercised by any person, including third party contractors, reasonably nominated from time to time by the RTL. To the extent (if any) that any particular authorisation or clearances may be required to be given by User and the procedures for giving and obtaining the same are not for the time being stipulated in arrangements made pursuant to clause 7.3, the same shall be given within a reasonable time from the date of the request therefor, save in the case of emergency in which case it shall be given without delay.
The RTL shall procure that all reasonable arrangements and provisions are made and/or revised from time to time, as and when necessary or desirable, to facilitate the safe exercise by it of any Right of Access with the minimum of disruption, disturbance or inconvenience to User. Such arrangements and provisions shall provide for User to have the right to make directions or regulations from time to time in relation to a specified matter. Matters to be covered by such arrangements and/or provision shall include:-
the identification of any relevant RTL Assets;
the particular access routes applicable to the land in question having particular regard for the weight and size limits on those routes;
any limitations on times of exercise of a Right of Access;
any requirements as to prior notification and as to authorisation or security clearance of individuals exercising such Rights of Access, and procedures for obtaining the same;
the means of communication between the Parties and all employees and/or contractors who may be authorised from time to time by the RTL to exercise a Right of Access of any relevant directions or regulations made by the RTL;
the identification of and arrangements applicable to Emergency Personnel.
any limitation or restriction on the exercise of such Right of Access to the extent that in the circumstances is reasonable.
The RTL shall procure that any such arrangements and/or provisions (or directions or regulations issued by User pursuant thereto) made from time to time between the Parties shall be observed and performed by it and all persons authorised by it to exercise any Right of Access.
The RTL shall procure that all reasonable steps are taken in the exercise of any Right of Access to:
avoid or minimise damage to User’s Land, or any other property thereon or therein;
cause as little disturbance and inconvenience as possible to User or other occupier of User’s Land; and shall promptly make good any damage caused to User’s Land and/or such other property in the course of the exercise of such rights and shall indemnify User against all actions, claims, proceedings, losses, costs and demands arising out of such exercise.
Subject to clause 7.4.1, all such rights shall be exercisable free of any charge or payment of any kind.
Subject to any contrary arrangements for the time being made under clause 7.3, 7.5.1 a Right of Access for operation or inspection shall be available without prior notice;
a Right of Access for the purpose of maintenance, testing or repair of HV Apparatus granted shall only be exercisable on the giving of at least seven days prior written notice to User except in the case of loss of generation or demand or other emergency (in which event User shall render all possible assistance in procuring that the Right of Access shall be exercisable as soon as possible); and 7.5.3 a Right of Access for the purpose of Modifying any RTL Asset shall be exercisable only after two weeks prior written notice to User.
8. Services and Use of Assets 15
Subject as hereinafter provided, in relation to each Facility Asset, User shall, if required by the RTL, make the Facility Asset in question available for use by the RTL to such extent as is necessary for the purposes of the RTL’s undertaking but not so as to prejudice the use now or hereafter of such Facility Asset by User for its undertaking.
Subject as hereinafter provided, in relation to each of the Services, User shall, if required by the RTL, provide the same to the RTL. Such provision shall be of such a quality and quantity and shall be provided at such times as the RTL shall reasonably request. User shall not be required to exceed the level of quality or quantity of the Services as is anticipated by the Parties at the date of this Agreement, unless specifically agreed otherwise between the Parties.
Where the use of any Facility Asset is made available or such Services are supplied as aforesaid, the Parties shall procure that all reasonable arrangements and provisions are made and/or revised from time to time, as and when necessary or desirable between the local personnel employed by each of them in that regard, such arrangements to include:- 8.3.1 the identification of the Facility Asset and/or Services in question including (where relevant) the extent of their availability;
the hours during which such use or provision shall be allowed or made;
any requirements as to notification of use or call for supply or temporary suspension thereof;
any requirements as to authorisation or security clearance of individuals and the procedures for obtaining the same; and 8.3.5 any safety requirements;
The provision of use of the Facility Asset listed in Schedule 4, Part One and the supply of the Services listed in Schedule 5, Part One shall not be terminated unless User ceases to require the Facility Asset or Services for its own use in which case the supply of the Services or use of the Facility Asset may be terminated by not less than one year’s notice in writing;
The provision of use of the Facility Asset listed in Schedule 4, Part Two and the supply of the Services listed in Schedule 5, Part Two shall continue until terminated by not less than six months notice in writing by either Party. User shall maintain the Facility Asset in accordance with Good Industry Practice.
9. Non-Interference 16
User agrees that neither it nor its agents, employees and invitees will interfere in any way with any of the RTL Assets without the consent of the RTL. For the purposes of this clause “interfere” shall include:
disconnecting or altering the connection of any RTL Assets to any system of cables, foundations, pipes, drains or other media to which it may be connected from time to time or to prevent supply of any substance or thing through such connected system;
affixing or removing any item or substance of any nature whatsoever to or from any RTL Assets;
damaging any RTL Assets;
allowing any other person to interfere with any RTL Assets;
altering any meters or settings on any RTL Assets.
the obstruction of access to any RTL Assets.
The obligations contained in this clause 9 shall be suspended to the extent that emergency action is taken by Emergency Personnel in good faith to protect the health and safety of persons or to prevent damage to property. All reasonable care shall be taken in the course of such emergency action. When the emergency has ended, any damaged property will be reinstated by the RTL, save for damage occurring by reason of lack of reasonable care in the course of the emergency action taken by User which shall be the responsibility of User.
10. Dispute Resolution 17
Any dispute arising under this Agreement between Location Managers of the Parties shall, if not resolved within 14 days of first arising, be referred at the instance of either party to the respective line managers, or those fulfilling a similar function whether or not so called, of User and the RTL who shall use all reasonable endeavours to resolve the matter in dispute within one month.
Save where expressly stated in this Agreement to the contrary (including the procedure for initial dispute resolution contained in Clause 10.1) and subject to any contrary provision of the Act, any Licence, or the Regulations, or the rights, powers, duties and obligations of the Authority or the Secretary of State under the Act, any Licence or otherwise howsoever, any dispute or difference of whatever nature howsoever arising under out of or in connection with this Agreement between the Parties shall (subject to initial dispute resolution procedures referred to in Clause 1 having been exhausted) be and is hereby referred to arbitration pursuant to the rules of the London Court of International Arbitration in force from time to time.
Whatever the nationality residence or domicile of any Party and wherever the dispute or difference or any part thereof arose the law of England and Wales shall be the proper law of any reference to arbitration hereunder and in particular (but not so as to derogate from the generality of the foregoing) the provisions of the Arbitration Act 1996 (including any modification, extension, replacement or re-enactment thereof for the time being in force) shall apply to any such arbitration wherever the same or any part of it shall be conducted.
11. Governing Law and Jurisdiction 19
This Agreement shall be governed by and construed in all respects in accordance with English law.
Subject and without prejudice to clause 10 and to clause 11.4 the Parties irrevocably agree that only the courts of England and Wales and the courts of Scotland are to have jurisdiction to settle any dispute which may arise out of or in connection with this Agreement and that accordingly any suit, action or proceeding (together in this clause 11 referred to as “Proceedings”) arising out of or in connection with this Agreement may be brought in such courts.
Each Party irrevocably waives any objection which it may have now or hereafter to the laying of the venue of any Proceedings in any such court as is referred to in this clause 11 and any claim that any such Proceedings have been brought in an inconvenient forum and further irrevocably agrees that a judgment in any Proceedings brought in the courts of England and Wales or the courts of Scotland shall be conclusive and binding upon such Party and may be enforced in the courts of any other jurisdiction.
For the avoidance of doubt nothing contained in the foregoing provisions of this clause 11 shall be taken as permitting a Party to commence Proceedings in the courts where this Agreement otherwise provides for proceedings to be referred to arbitration.
12. Confidentiality 20
For the purposes of this Clause 12 except where the context otherwise requires:
“Authorised Recipient”, in relation to any Protected Information, means any Business Person who, before the Protected Information had been divulged to them by the RTL or any subsidiary of the RTL, had been informed of the nature and effect of this clause 12 and who requires access to such Protected Information for the proper performance of their duties as a Business Person in the course of Permitted Activities;
“Business Person” means any person who is a Licensed Business Person, or a Corporate Functions Person and “Business Personnel” shall be construed accordingly.
“Confidential Information” means all data and other information
To consider simplifying? supplied to User under the provisions of this Agreement.
“Corporate Functions Person” means any person who:-
is a director of the RTL; or
is an employee of the RTL or any of its subsidiaries carrying out any administrative, finance or other corporate services of any kind which in part relate to the Licensed Business; or
is engaged as an agent of or adviser to or performs work in relation to or services for the Licensed Business.
“Licensed Business” means any business or activity of the RTL or any of its associates authorised by its RTL Licence;
“Licensed Business Person” means any employee of the RTL or any director or employee of its subsidiaries who is engaged solely in its Licensed Business and “Licensed Business Personnel” shall be construed accordingly;
“Permitted Activities” means activities carried on for the purposes of the Licensed Business;
“Protected Information” means any information relating to the affairs of a Party which is furnished to Business Personnel pursuant to this Agreement unless, prior to such information being furnished, such Party has informed the recipient thereof by notice in writing or by endorsement on such information, that the said information is not to be regarded as Protected Information.
Confidentiality for the RTL and its Subsidiaries The RTL and its subsidiaries in each of their capacities in this Agreement shall secure that Protected Information is not:- 12.2.1 divulged by Business Personnel to any person unless that person is an Authorised Recipient;
used by Business Personnel for the purposes of obtaining for the RTL or any of its subsidiaries or for any other person:-
any Licence; or
any right to purchase or otherwise acquire, or to distribute, electricity including by means of an electricity purchase contract (as defined in the Transmission Licence); or
any contract or arrangement for the supply of electricity to customers or suppliers; or
any contract for the use of any electrical lines or electrical plant belonging to or under the control of a supplier.
used by Business Personnel for the purpose of carrying on any activities other than Permitted Activities except with the consent in writing of the Party to whose affairs such Protected Information relates.
Nothing in this Clause 12 shall apply:
to any Protected Information which, before it is furnished to Business Personnel is in the public domain;
to any Protected Information which, after it is furnished to Business Personnel:
is acquired by the RTL or any subsidiary of the RTL in circumstances in which this Clause 12 does not apply; or
is acquired by the RTL or any subsidiary of the RTL in circumstances in which this Clause 12 does apply and thereafter ceases to be subject to the restrictions imposed by this Clause 12; or
enters the public domain otherwise than as a result of a breach by the RTL or any subsidiary of the RTL of its obligations in this Clause 12.
to the disclosure of any Protected Information to any person if the RTL or any subsidiary is required or permitted to make such disclosure to such person:
in compliance with the duties of the RTL or any associate under the Act or any other requirement of a Competent Authority; or
in compliance with the conditions of its RTL Licence or any document referred to in its RTL Licence with which the RTL is required to comply; or
in compliance with any other requirement of law; or
in response to a requirement of any recognised stock exchange or regulatory authority or the Panel on Take- overs and Mergers; or
pursuant to the rules for the London Court of International Arbitration or pursuant to any judicial or other arbitral process or tribunal.
to any Protected Information to the extent that the RTL or any of its subsidiaries is expressly permitted or required to disclose that information under the terms of any agreement or arrangement (including the Fuel Security Code) with the Party to whose affairs such Protected Information relates.
The RTL and its subsidiaries may use all and any information or data supplied to or acquired by it, from or in relation to the other Party to this Agreement in performing its Permitted Activities and may pass the same to subsidiaries of the RTL which carry out such activities and the User hereto agrees to provide all information to the RTL and its subsidiaries for such purpose.
The Company and its subsidiaries may use all and any information or data supplied to or acquired by it from the RTL pursuant to Clause 12.3.3 in relation to this Agreement in performing its activities under the ESO Licence including for the following purposes:
the operation and planning of the National Electricity Transmission System;
the calculation of charges and preparation of offers of terms for connection to or use of the National Electricity Transmission System; and the User agrees to provide all information to the RTL and its subsidiaries for such purposes.
The RTL undertakes that, having regard to the activities in which any Business Person is engaged and the nature and effective life of the Protected Information divulged to them by virtue of such activities, neither the RTL nor any of its subsidiaries shall unreasonably continue (taking into account any industrial relations concerns reasonably held by it) to divulge Protected Information or permit Protected Information to be divulged to any Business Person:
who has notified the RTL or the relevant subsidiary of their intention to become engaged as an employee or agent of any other person (other than of the RTL or any subsidiary thereof); or
who is authorised by licence or exemption to generate or supply electricity.
Without prejudice to other provisions of this clause 12 the RTL shall procure that any additional copies of the Protected Information, whether in hard copy or computerised form, will clearly identify the Protected Information as protected.
The RTL undertakes to use all reasonable endeavours to procure that no employee is a Corporate Functions Person unless the same is necessary for the proper performance of their duties.
Confidentiality for User
User hereby undertakes with the RTL and its subsidiaries that it shall preserve the confidentiality and secrecy of, and not directly or indirectly reveal, report, publish, disclose or transfer or use for its own purposes Confidential Information except:
in the circumstances set out in Clause 12.9.2;
to the extent expressly permitted by this Agreement; or
with the consent in writing of the RTL.
Exceptions: the circumstances referred to in Clause 12.9.1(a) are:
where the Confidential Information, before it is furnished to User, is in the public domain; or
where the Confidential Information, after it is furnished to User:
is acquired by User in circumstances in which this Clause 12 does not apply; or
is acquired by User in circumstances in which this Clause 12 does apply and thereafter ceases to be subject to the restrictions imposed by this Clause 12; or
enters the public domain otherwise than as a result of a breach by User of its obligations in this Clause 12; or
if User is required or permitted to make disclosure of the Confidential Information to any person:
in compliance with the duties of User under the Act or any other requirement of a Competent Authority;
in compliance with the conditions of any Licence or any document referred to in any Licence with which User is required to comply;
in compliance with any other requirement of law;
in response to a requirement of any stock exchange or regulatory authority or the Panel on Takeovers and Mergers; or
pursuant to the rules for the London Court of International Arbitration or pursuant to any judicial or other arbitral process or tribunal; or
where Confidential Information is furnished by User to the employees, directors, agents, lenders, consultants and professional advisers of User in each case on the basis set out in Sub-Clause 12.10.
With effect from the date of this Agreement User shall adopt procedures within its organisation for ensuring the confidentiality of all Confidential Information which it is obliged to preserve as confidential under this Clause 12. These procedures will include:
the Confidential Information will be disseminated within User only on a “need to know” basis;
employees, directors, agents, lenders, consultants and professional advisers of User in receipt of Confidential Information will be made fully aware of User’s obligations of confidence in relation thereto.
13. Title to Assets 26
The RTL acknowledges that it does not have and will not acquire any title, right or interest in User’s Land save for such rights as are expressly granted herein or otherwise provided nevertheless that, if according to any rule of law, the RTL could acquire any such title, right or interest in any of User’s Land, then:
in the case of land in England & Wales, such title right or interest shall be held upon trust, insofar as it relates to the User’s land for such User absolutely; or 13.1.2 in the case of land in Scotland, the RTL undertakes to do all that is required to transfer such right or interest to User to ensure that User shall not, by reason of such right or interest arising, have its full rights in such land diminished (and in the interim to hold such rights in trust for User) and shall if requested by User, be obliged forthwith to establish trust arrangements valid under Scottish law so as to ensure that any such right or interest shall be held on behalf of User.
User agrees that it shall not by any act or default render the RTL Assets liable to any distress execution or other legal process, and in the event that the RTL Assets shall become so liable, shall forthwith give notice of any such proceedings to the RTL and shall forthwith notify any third party instituting any such process of the ownership of such RTL Assets.
If User desires to mortgage or charge User’s Land or its interest therein on which any RTL Assets are located or to enter into any arrangement which, if made, might affect the rights of the RTL expressly granted herein, then User shall ensure that the RTL Assets are not and will not be subject to the rights granted therein and are not and will not be affected by the mortgage, legal charge or other agreement or arrangement, and shall give prior written notification thereof to the RTL.
In the event that User shall wish to grant rights over or dispose of any interest in or change the use of User’s Land User shall notify the RTL of such wish and fully consult the RTL in respect thereof and shall not grant such rights or make such disposal or change of use save on terms securing to the reasonable satisfaction of that other the Rights of Access granted in respect of User’s Land.
14. Limitation of Liability 27
Subject to sub-clauses 5.3, 6.2, 9.2 and 14.5 and save as provided in this sub-clause 14.1 and sub-clause 14.2 neither Party (“the Party Liable”) nor any of its officers, employees or agents shall be liable to the other Party for loss arising from any breach of this Agreement other than for loss directly resulting from such breach and which at the date hereof was reasonably foreseeable as not unlikely to occur in the ordinary course of events from such breach and which resulted from:
physical damage to the property of the other Party, its officers, employees or agents; and/or 14.1.2 the liability of the other Party to any other person for loss arising from physical damage to the property of any person.
Nothing in this Agreement shall exclude or limit the liability of the Party Liable for death or personal injury resulting from the negligence of the Party Liable or any of its officers, employees or agents and the Party Liable shall indemnify and keep indemnified the other Party, its officers, employees or agents, from and against all such and any loss or liability which the other Party may suffer or incur by reason of any claim on account of death or personal injury resulting from the negligence of the Party Liable or any of its officers, employees or agents.
Subject to sub-clauses 5.3, 6.2, 9.2 and 14.5 neither Party, nor any of its officers, employees or agents shall in any circumstances whatsoever be liable to the other Party for:- 14.3.1 any loss of profit, loss of revenue, loss of use, loss of contract or loss of goodwill; or 14.3.2 any indirect or consequential loss; or 14.3.3 loss resulting from the liability of the other Party to any other person howsoever and whensoever arising save as provided in sub-clauses 14.1.2 and 14.2.
The rights and remedies provided by this Agreement to the Parties are exclusive and not cumulative and exclude and are in place of all substantive (but not procedural) rights or remedies express or implied and provided by common law or statute in respect of the subject matter of this Agreement, including any rights either Party may possess in tort which shall include actions brought in negligence and/or nuisance. Accordingly, each of the Parties hereby waives in the fullest extent possible all such rights and remedies provided by common law or statute, and releases the Party Liable, its officers, employees and agents to the same extent from all duties, liabilities, responsibilities or obligations provided by common law or statute in respect of the matters dealt with in this Agreement and undertakes not to enforce any of the same except as expressly provided herein.
Save as otherwise expressly provided in this Agreement, this clause 14 insofar as it excludes or limits liability shall override any other provision in this Agreement provided that nothing in this clause 14 shall exclude or restrict or otherwise prejudice or affect any of:
the rights, powers, duties and obligations of either Party which are conferred or created by the Act, the User’s Licence, RTL’s Licence or the Regulations or any amendment or re-enactment thereof; or 14.5.2 the rights, powers, duties and obligations of the Authority or the Secretary of State under the Act, any such licence as aforesaid or otherwise howsoever.
Each of the sub-clauses of this clause 14 shall:
be construed as a separate and severable contract term, and if one or more of such sub-clauses is held to be invalid, unlawful or otherwise unenforceable the other or others of such sub-clauses shall remain in full force and effect and shall continue to bind the Parties; and 14.6.2 survive termination of this Agreement.
Each Party agrees that the other Party holds the benefit of sub clauses 14.1, 14.2 and 14.3 above for itself and as trustee and agent for its officers, employees and agents
Each Party hereby acknowledges and agrees that the provisions of this clause 14 have been the subject of discussion and negotiation and are fair and reasonable having regard to the circumstances as at the date hereof.
15. INTELLECTUAL PROPERTY All Intellectual Property relating to the subject matter of this Agreement conceived, originated, devised, developed or created by a Party, its officers, employees, agents or consultants during the currency of this Agreement shall vest in such Party as the sole beneficial owner thereof save where the Parties agree in writing otherwise.
16. FORCE MAJEURE If either Party (the “Non-Performing Party”) shall be unable to carry out any of its obligations under this Agreement due to a circumstance of Force Majeure this Agreement shall remain in effect but save as otherwise provided herein the Non-Performing Party’s obligations hereunder shall be suspended without liability for a period equal to the circumstance of Force Majeure provided that:
the Non-Performing Party gives the other Party prompt notice describing the circumstance of Force Majeure, including the nature of the occurrence, its expected duration and the particular obligations affected by it, and continues to furnish regular reports with respect thereto during the period of Force Majeure;
the suspension of performance is of no greater scope and of no longer duration than is required by the Force Majeure;
no liabilities of either Party that arose before the Force Majeure causing the suspension of performance are excused as a result of the Force Majeure;
the non-performing Party uses all reasonable efforts to remedy its inability to perform; and
as soon as practicable after the event which constitutes Force Majeure the Parties shall discuss how best to continue their operations so far as possible in accordance with this Agreement.
17. WAIVER No delay by or omission of a Party in exercising any right, power, privilege or remedy under this Agreement shall operate to impair such right, power, privilege or remedy or be construed as a waiver thereof. Any single or partial exercise of any such right, power, privilege or remedy shall not preclude any other or future exercise thereof or the exercise of any other right, power, privilege or remedy.
18. Notices 30
Any notice or other communication to be given by one Party to the other under, or in connection with the matters contemplated by, this Agreement shall be addressed to the recipient and sent to the address, or email address of such other Party given in Schedule 6 and marked for the attention of the person so given or to such other address, and/or email address and/or marked for such other attention as such other Party may from time to time specify by notice given in accordance with this clause 18 to the Party giving the relevant notice or other communication to it.
Any notice or other communication to be given by one Party to the other Party under, or in connection with the matters contemplated by, this Agreement shall be in writing and shall be given by letter delivered by hand or sent by first class prepaid post (airmail if overseas) or email, and shall be deemed to have been received:
in the case of delivery by hand, when delivered; or 18.2.2 in the case of first class prepaid post, on the second day following the day of posting or (if sent airmail from overseas) on the fifth day following the day of posting; or 18.2.3 in the case of telex, on the transmission of the automatic answerback of the addressee (where such transmission occurs before 1700 hours on the day of transmission) and in any other case on the day following the day of transmission; or 18.2.4 in the case of email, when delivered to the email address (where such delivery occurs before 1700 hours on the day of delivery) and in any other case on the day following the day of delivery.
19. VARIATIONS The provisions of Schedules 1, 3, 4, 5 and 6 may be varied from time to time by written memorandum signed by an authorised officer of each of the Parties. Subject thereto no variations to this Agreement shall be effective unless made by way of supplemental deed.
20. Overriding Provisions & Good Industry Practice 31
In the event of any conflict between RTL’s or User’s obligations hereunder and their obligations under the User’s Licence and RTL’s Licence, the Act, any direction of the Secretary of State, the Authority or ruling of the Competition Commission, the Grid Code, Connection Agreement or the Bilateral Connection Agreement, the provisions of the User’s Licence and RTL’s Licence, the Act, the Grid Code, the Connection Agreement or Bilateral Agreement the direction of the Secretary of State, the Authority, or ruling of the Competition Commission shall prevail and accordingly the RTL and User respectively shall not be responsible for any failure to perform their respective obligations hereunder to the extent that any such failure is directly attributable to proper compliance with such provisions, rulings or directions.
Both parties shall observe their respective obligations hereunder in accordance with Good Industry Practice.
21. Assignment and Sub-Contracting 32
The rights and obligations of a Party may not be assigned (otherwise than to an Affiliate or by way of a charge or an assignment by way of security) without the consent of the other Party, such consent not to be unreasonably withheld.
Each Party shall have the right to sub-contract or delegate the performance of any of its obligations or duties arising under this Agreement without the consent of the other. The sub-contracting by either Party of the performance of any obligations or duties under this Agreement shall not relieve such Party from the liability for performance of such obligation or duty.
22. Illegality and Partial Invalidity 32
If at any time any provision of this Agreement should become or be declared unlawful, invalid, illegal or unenforceable in any respect under the law of any jurisdiction, neither the validity, legality or enforceability of the remaining provisions nor the validity, legality or enforceability of such provision under the law of any other jurisdiction shall be affected.
If any part of a provision of this Agreement is or becomes or is declared invalid, unlawful, illegal or unenforceable but the rest of such provision would remain valid, lawful or enforceable if part of the wording were deleted the provision shall apply with such modifications as may be necessary to make it valid, lawful, enforceable and effective but without affecting the meaning of legality, validity or enforceability of any other provision of this Agreement.
23. TERM AND TERMINATION This Agreement shall continue until no RTL Assets are on User’s land and no Facility Assets or Services are shared or provided.
24. Registration and Memorandum 33
Where any or all of User’s Land is registered or the RTL’s interest therein is subject to compulsory registration at H.M Land Registry or the Land Register of Scotland (as relevant), the parties hereto agree to apply to the Chief Land Registrar or the Keeper (as relevant]) for the registration as appropriate of the rights and obligations granted by or contained in this Agreement and User agrees to place on deposit at H.M Land Registry or the Land Register of Scotland (as relevant) all relevant Land or Charge Certificates to enable such registration to be effected.
Where any of User’s Land is not so registered or subject to compulsory registration, User shall procure within six months of the date hereof that certified copies of any such agreement are attached to the most recent conveyance (in the case of a heritable interest) or the lease under or pursuant to which they hold such land.
25. Entire Agreement 33
This Agreement contains the entire agreement between the Parties with respect to the subject-matter hereof, and expressly excludes any warranty, condition or other undertaking implied at law or by custom, and supersedes all previous agreements and understandings between the Parties with respect thereto and:
each of the Parties acknowledges and confirms that it does not enter into this Agreement in reliance on any representation, warranty or other undertaking not fully reflected in the terms of this Agreement; but
the RTL acknowledges that User may have entered or may enter into agreements with other parties who hold a Licence containing similar rights and/or liabilities to those contained in this Agreement affecting User’s Land and any assets thereon. User shall, when entering into such agreement with any such party use reasonable endeavours to avoid conflicts between the provisions thereof and the provisions of this Agreement but in the event of any conflict User shall use all reasonable endeavours to procure that appropriate arrangements are made to settle the same to give full effect (so far as practicable) to the rights and liabilities under this Agreement and under such other agreements as aforesaid. In the event of any dispute as to such conflict and/or arrangements the dispute shall be dealt with in accordance with Clause 10. IN WITNESS whereof this Agreement has been entered into as a deed the day and year first above written. SCHEDULE 1
1. The Parties will comply with the Site Specific Safety Rules and any agreed modifications thereto.
2. The Parties will arrange for the Site Specific Safety Rules to be written down and to be implemented by the person or persons responsible on behalf of the relevant Parties for the co-ordination of safety. SCHEDULE 4
Exhibit O - Part 1C
1. [] a company registered in [] (with number []) whose registered office is at [] (“User”, which expression shall include its successors and/or permitted assigns); and
2. [Insert name of Relevant Transmission Licensee] a company registered in [] with number [] whose registered office is at [] (“RTL”, which expression shall include its successors and/or permitted assigns)] WHEREAS Certain assets of the RTL are to be installed on the Offshore Platform title to which is vested in User and this Agreement is entered into by the Parties to give effect to appropriate arrangements in respect of such assets and also the use of certain facilities provided by the User. NOW IT IS HER
1. DEFINITIONS AND INTERPRETATION In this Agreement, the following words and expressions shall, unless the subject-matter or context otherwise requires or is inconsistent therewith, bear the following meanings:- “Act” the Electricity Act 1989 as amended by Utilities Act 2000; “Affiliate” in relation to User means any holding company or subsidiary of that Party or any subsidiary of a holding company of User, in each case within the meaning of Sections 736, 736A and 736B of the Companies Act 1985 as substituted
unless the context otherwise requires all references to a particular clause, sub-clause, paragraph or Schedule shall be a reference to that clause, sub-clause, paragraph or Schedule in or to this Agreement;
the table of contents and headings are inserted for convenience only and shall be ignored in construing this Agreement;
references to the words “include” or “including” are to be construed without limitation to the generality of the preceding words;
unless there is something in the subject matter or the context which is inconsistent therewith, any reference to an Act of Parliament or any Section thereof or Schedule thereto, or other provision thereof or any instrument, order or regulation made thereunder shall be construed at the particular time as including a reference to any modification, extension, replacement or re-enactment thereof then in force and to all instruments, orders or regulations then in force and made under or deriving validity from the relevant Act of Parliament; and
references to the masculine shall include the feminine and references in the singular shall include the plural and vice versa and words denoting natural persons shall include companies, corporations and any other legal entity and vice versa.
unless otherwise provided to the contrary herein, defined terms used in this Agreement and not defined herein shall have the meaning set forth in the Connection and Use of System Code or the Bilteral Connection Agreement.
2. Right to Install and Retain Asset 8
Subject to sub-clause 5.1, User hereby grants to the RTL the right to install and thereafter retain and replace as provided in this Agreement RTL Assets on User’s Offshore Platform in such places as are currently proposed (subject to such variations between the date hereof and the actual date of installation as may be agreed to by User) and such right shall extend to any Modified RTL Assets. User shall maintain any shelter and/or support enjoyed by any RTL Assets at the date of this Agreement or, if later, when relocated on User’s Offshore Platform in accordance with clause 5 and grants to the RTL a Right of Access for the purpose of the maintenance, inspection, testing, removal, operation, Modification or repair of any RTL Assets.
3. Modifications, Replacements and Alterations 8
The RTL may at its own expense replace or alter any RTL Assets provided that:- 3.1.1 the replacement RTL Assets or the RTL Assets as so altered:-
are placed in the same or approximately the same position;
fulfil the same or a similar purpose;
can, where relevant, be accommodated in and on existing buildings or structures;
do not require additional or improved facilities or services from User;
do not restrict the actual and intended use of User’s Offshore Platform and any equipment thereon or therein to any materially greater extent than the RTL Assets so replaced or altered; and
are either of the same or a similar or smaller size or the alteration is effected substantially within the space occupied by such RTL Assets to enable the RTL Assets to be used up to their full capability; and 3.1.2 prior written notification has been given to User.
If any replacement or alteration permitted by clause 3.1 shall require minor alterations or work to the existing buildings or structures housing or supporting the RTL Assets in question, such alterations or works may be carried out (with the prior written approval of User (such approval not to be unreasonably withheld or delayed)) but at the cost of the RTL.
To the extent that any of the conditions of clause 3.1 are not in User’s reasonable opinion met in relation to any replacement or alteration, User may by notice in writing require the RTL promptly to remove such replacement or alteration and, if the RTL fails to do so, may remove the same itself at the cost and expense of the RTL. On such removal, the RTL may reinstate the RTL Assets so replaced or altered.
For the avoidance of doubt it is hereby agreed that any dispute between the Parties regarding this clause shall be determined in accordance with the provisions of Clause 10 of this Agreement.
4. SECURITY AND COMPLIANCE WITH STATUTES etc
User undertakes to maintain and provide security in relation to the RTL Assets in accordance with the arrangements set out in Part I of Schedule 3.
Each Party shall procure that, as between the Parties, all reasonable and necessary steps are taken, as and when necessary or desirable, in co-operation with the other (and, so far as applicable, with any third party), to ensure compliance with the provisions (each such provision or part thereof being in this clause 4 an “Obligation”) of:-
all statutes and Directives applicable to any RTL Assets and/or any part (including the whole) of User’s Offshore Platform;
any statute or Directive which may affect any other property (of whatever nature) of either Party as a result of the existence, nature, location, or manner of operation of any RTL Assets; and
any statute or Directive requiring the reporting of any occurrence relating to or affecting any RTL Assets and/or User’s Offshore Platform (including the Reporting of Injuries Diseases and Dangerous Occurrence Regulations 1985 and the Regulations).
Each Party shall, so far as it is aware of the same, unless it has reasonable grounds for believing that the other Party possesses the information, keep the other Party informed of all matters relating to any Obligation or potential Obligation and/or the extent to which such Obligation may be applicable.
In the event of any dispute as to responsibility, as between the Parties, pursuant to clause 4.2, for compliance with an Obligation, that responsibility shall be allocated, so far as practicable, on the basis that:-
each Party shall refrain from taking or permitting any act or omission which would prevent compliance with an Obligation; and
positive action required in relation to a Party’s property as a consequence of the existence, nature, location or manner of operation of that property or any other property of that Party shall be the responsibility of that Party, and, to the extent that such action is required in respect of or affecting any property of the other Party (or property of a third party located in or on that other Party’s Offshore Platform), such action may be taken with the prior approval of that other Party (such approval, subject to (i) above, not to be unreasonably withheld or delayed).
The provisions for safety co-ordination between the Parties contained in Part II of Schedule 3 shall apply.
5. Relocations 11
At any time and from time to time during the term of this Agreement, User may with the prior written consent of the RTL (such consent not to be unreasonably withheld or delayed) require the RTL to relocate any RTL Assets to a different location on the User Offshore Platform, such consent to be sought and given or refused in accordance with the following procedure:-
User shall serve a written notice on the RTL, which notice shall specify:-
the RTL Assets which User wishes to be relocated;
the reasons for such wish;
the proposed new location for such RTL Assets; and the timing of the carrying out of such relocation.
The RTL shall within one month of receipt of any such notice (or such longer period as shall be reasonably necessary) serve a counter notice stating:-
whether or not in its reasonable opinion such Relocation Proposal is acceptable to it;
if the Relocation Proposal is not acceptable to the RTL, the grounds for such opinion and the terms of any alternative proposal (the “Alternative Relocation Proposal”) covering so far as relevant the matters referred to in items (a) - (d) of clause 5.1.1 which would be acceptable to the RTL; and
in respect of the Relocation Proposal (if accepted) or of any Alternative Relocation Proposal, the costs likely to be incurred in connection with considering the Relocation Proposal or the Alternative Relocation Proposal and effecting the said relocation of the RTL Assets and the proper and reasonable costs of relocating any other equipment that may be necessary as a result of the relocation of those RTL Assets and any consequential losses including payments to third parties incurred as a result of the relocation of those RTL Assets and the proposed manner and timing of payment of the same by User.
If within one month of the date of such counter notice (or such longer period as shall be reasonably necessary) User has not withdrawn the Relocation Proposal and the Parties have not agreed upon it or the Alternative Relocation Proposal (if any) or a variation of either of them (such agreement to include agreement on the costs referred to in item (c) of clause 5.1.2) the matter shall be dealt with in accordance with Clause 10.
Upon approval or settlement of any Relocation Proposal, Alternative Relocation Proposal or variation thereof pursuant to clause 5.1, the RTL shall [(conditionally upon it being able to obtain all necessary licences and consents which it will use reasonable endeavours to do)] relocate or procure the relocation of the relevant RTL Assets as quickly as reasonably practicable (having regard to, amongst other things, technical and operational requirements [and to the availability of all necessary licences and consents]).
User shall render all reasonable assistance to the RTL in connection with such relocation [licences and consents] and pay to the RTL all costs referred to in item (c) of clause 5.1.2 as agreed or settled pursuant to clause 5.1 provided that all reasonable endeavours are used to minimise such costs and in the event that a Relocation Proposal is withdrawn or consent thereto is reasonably withheld pursuant to clause 5.1, User shall pay to the RTL all costs reasonably incurred by the RTL in connection with considering the Relocation Proposal and any counter notice.
Such of the provisions of this Agreement as are appropriate and relevant (including the provisions of this clause 5), shall continue to apply to any relocated RTL Assets.
6. Removals 13
In the event that there shall cease to be a Bilateral Connection Agreement relating to any RTL Assets on User’s Offshore Platform the RTL shall remove all RTL Assets from User’s Offshore Platform within [ ] or such longer period as shall be agreed between the User and the RTL and in accordance with the provisions relating thereto contained in the Connection Agreement and the Bilateral Connection Agreement.
Where the RTL is obliged to remove any of the RTL Assets from User’s Offshore Platform, under this Clause 6, and fails to do so in accordance with the relevant provisions, (whether they be contained in this Clause 6, Clause 3 or Clause 5) User shall be entitled to remove those RTL Assets to land belonging to the RTL and the RTL shall provide all reasonable assistance to enable User safely so to do and shall pay and reimburse to User all costs and expenses reasonably incurred by User in so doing.
7. Rights of Access 13
A Right of Access includes the right to bring on to User’s Offshore Platform such vehicles, plant, machinery and maintenance or construction materials as shall be reasonably necessary for the Permitted Purpose.
A Right of Access given to the RTL may be exercised by any person, including third party contractors, reasonably nominated from time to time by the RTL. To the extent (if any) that any particular authorisation or clearances may be required to be given by User and the procedures for giving and obtaining the same are not for the time being stipulated in arrangements made pursuant to clause 7.3, the same shall be given within a reasonable time from the date of the request therefor, save in the case of emergency in which case it shall be given without delay.
The RTL shall procure that all reasonable arrangements and provisions are made and/or revised from time to time, as and when necessary or desirable, to facilitate the safe exercise by it of any Right of Access with the minimum of disruption, disturbance or inconvenience to User. Such arrangements and provisions shall provide for User to have the right to make directions or regulations from time to time in relation to a specified matter. Matters to be covered by such arrangements and/or provision shall include:-
the identification of any relevant RTL Assets;
the particular access routes applicable to the Offshore Platform in question having particular regard for the weight and size limits on those routes;
any limitations on times of exercise of a Right of Access;
any requirements as to prior notification and as to authorisation or security clearance of individuals exercising such Rights of Access, and procedures for obtaining the same;
the means of communication between the Parties and all employees and/or contractors who may be authorised from time to time by the RTL to exercise a Right of Access of any relevant directions or regulations made by the RTL;
the identification of and arrangements applicable to Emergency Personnel.
any limitation or restriction on the exercise of such Right of Access to the extent that in the circumstances is reasonable.
The RTL shall procure that any such arrangements and/or provisions (or directions or regulations issued by User pursuant thereto) made from time to time between the Parties shall be observed and performed by it and all persons authorised by it to exercise any Right of Access.
The RTL shall procure that all reasonable steps are taken in the exercise of any Right of Access to:
avoid or minimise damage to User’s Offshore Platform, or any other property thereon or therein;
cause as little disturbance and inconvenience as possible to User or other occupier of User’s Offshore Platform; and shall promptly make good any damage caused to User’s Offshore Platform and/or such other property in the course of the exercise of such rights and shall indemnify User against all actions, claims, proceedings, losses, costs and demands arising out of such exercise.
Subject to clause 7.4.1, all such rights shall be exercisable free of any charge or payment of any kind.
Subject to any contrary arrangements for the time being made under clause 7.3, 7.5.1 a Right of Access for operation or inspection shall be available without prior notice;
a Right of Access for the purpose of maintenance, testing or repair of HV Apparatus shall only be exercisable on the giving of at least [seven days] prior written notice to User except in the case of loss of generation or demand or other emergency (in which event User shall render all possible assistance in procuring that the Right of Access shall be exercisable as soon as possible); and 7.5.3 a Right of Access for the purpose of Modifying any RTL Asset shall be exercisable only after [two weeks] prior written notice to User.
8. Services and Use of Assets 15
Subject as hereinafter provided, in relation to the Facilities, User shall, if required by the RTL, make the Facilities in question available for use by the RTL to such extent as is necessary for the purposes of the RTL’s undertaking but not so as to prejudice the use now or hereafter of such Facilities by User for its undertaking.
Subject as hereinafter provided, in relation to each of the Services, User shall, if required by the RTL, provide the same to the RTL. Such provision shall be of such a quality and quantity and shall be provided at such times as the RTL shall reasonably request. User shall not be required to exceed the level of quality or quantity of the Services as is anticipated by the Parties at the date of this Agreement, unless specifically agreed otherwise between the Parties.
Where the use of any Facilities made available or such Services are supplied as aforesaid, the Parties shall procure that all reasonable arrangements and provisions are made and/or revised from time to time, as and when necessary or desirable between the local personnel employed by each of them in that regard, such arrangements to include:- 8.3.1 the identification of the Facilities and/or Services in question including (where relevant) the extent of their availability;
the hours during which such use or provision shall be allowed or made;
any requirements as to notification of use or call for supply or temporary suspension thereof;
any requirements as to authorisation or security clearance of individuals and the procedures for obtaining the same; and 8.3.5 any safety requirements;
The provision of use of the Facilities listed in Schedule 4, Part One and the supply of the Services listed in Schedule 5, Part One shall not be terminated unless User ceases to require the Facilities or Services for its own use in which case the supply of the Services or use of the Facilities may be terminated by not less than one year’s notice in writing;
The provision of use of the Facilities listed in Schedule 4, Part Two and the supply of the Services listed in Schedule 5, Part Two shall continue until terminated by not less than six months notice in writing by either Party. User shall maintain the Facilities in accordance with Good Industry Practice.
9. Non-Interference 16
User agrees that neither it nor its agents, employees and invitees will interfere in any way with any of the RTL Assets without the consent of the RTL. For the purposes of this clause “interfere” shall include:
disconnecting or altering the connection of any RTL Assets to any system of cables, foundations, pipes, drains or other media to which it may be connected from time to time or to prevent supply of any substance or thing through such connected system;
affixing or removing any item or substance of any nature whatsoever to or from any RTL Assets;
damaging any RTL Assets;
allowing any other person to interfere with any RTL Assets;
altering any meters or settings on any RTL Assets.
the obstruction of access to any RTL Assets.
The obligations contained in this clause 9 shall be suspended to the extent that emergency action is taken by Emergency Personnel in good faith to protect the health and safety of persons or to prevent damage to property. All reasonable care shall be taken in the course of such emergency action. When the emergency has ended, any damaged property will be reinstated by the RTL, save for damage occurring by reason of lack of reasonable care in the course of the emergency action taken by User which shall be the responsibility of User.
10. Dispute Resolution 17
Any dispute arising under this Agreement between Location Managers of the Parties shall, if not resolved within 14 days of first arising, be referred at the instance of either party to the respective line managers, or those fulfilling a similar function whether or not so called, of User and the RTL who shall use all reasonable endeavours to resolve the matter in dispute within one month.
Save where expressly stated in this Agreement to the contrary (including the procedure for initial dispute resolution contained in Clause 10.1) and subject to any contrary provision of the Act, any Licence, or the Regulations, or the rights, powers, duties and obligations of the Authority or the Secretary of State under the Act, any Licence or otherwise howsoever, any dispute or difference of whatever nature howsoever arising under out of or in connection with this Agreement between the Parties shall (subject to any relevant initial dispute resolution procedures referred to in Clause 10.1 having been exhausted) be and is hereby referred to arbitration pursuant to the rules of the London Court of International Arbitration in force from time to time.
Whatever the nationality residence or domicile of any Party and wherever the dispute or difference or any part thereof arose the law of England and Wales shall be the proper law of any reference to arbitration hereunder and in particular (but not so as to derogate from the generality of the foregoing) the provisions of the Arbitration Act 1996 (including any modification, extension, replacement or re-enactment thereof for the time being in force) shall apply to any such arbitration wherever the same or any part of it shall be conducted.
11. Governing Law and Jurisdiction 19
This Agreement shall be governed by and construed in all respects in accordance with English law.
Subject and without prejudice to clause 10 and to clause 11.4 the Parties irrevocably agree that only the courts of England and Wales and the courts of Scotland are to have jurisdiction to settle any dispute which may arise out of or in connection with this Agreement and that accordingly any suit, action or proceeding (together in this clause 11 referred to as “Proceedings”) arising out of or in connection with this Agreement may be brought in such courts.
Each Party irrevocably waives any objection which it may have now or hereafter to the laying of the venue of any Proceedings in any such court as is referred to in this clause 11 and any claim that any such Proceedings have been brought in an inconvenient forum and further irrevocably agrees that a judgment in any Proceedings brought in the courts of England and Wales or the courts of Scotland shall be conclusive and binding upon such Party and may be enforced in the courts of any other jurisdiction.
For the avoidance of doubt nothing contained in the foregoing provisions of this clause 11 shall be taken as permitting a Party to commence Proceedings in the courts where this Agreement otherwise provides for proceedings to be referred to arbitration.
12. Confidentiality 20
For the purposes of this Clause 12 except where the context otherwise requires:
“Authorised Recipient”, in relation to any Protected Information, means any Business Person who, before the Protected Information had been divulged to them by the RTL or any subsidiary of the RTL, had been informed of the nature and effect of this clause 12 and who requires access to such Protected Information for the proper performance of their duties as a Business Person in the course of Permitted Activities;
“Business Person” means any person who is a Licensed Business Person, or a Corporate Functions Person and “Business Personnel” shall be construed accordingly.
“Confidential Information” means all data and other information supplied to User under the provisions of this Agreement.
“Corporate Functions Person” means any person who:-
is a director of the RTL; or
is an employee of the RTL or any of its subsidiaries carrying out any administrative, finance or other corporate services of any kind which in part relate to the Licensed Business; or
is engaged as an agent of or adviser to or performs work in relation to or services for the Licensed Business.
“Licensed Business” means any business or activity of the RTL or any of its associates authorised by its RTL Licence;
“Licensed Business Person” means any employee of the RTL or any director or employee of its subsidiaries who is engaged solely in its Licensed Business and “Licensed Business Personnel” shall be construed accordingly;
“Permitted Activities” means activities carried on for the purposes of the Licensed Business;
“Protected Information” means any information relating to the affairs of a Party which is furnished to Business Personnel pursuant to this Agreement unless, prior to such information being furnished, such Party has informed the recipient thereof by notice in writing or by endorsement on such information, that the said information is not to be regarded as Protected Information.
Confidentiality for the RTL and its Subsidiaries The RTL and its subsidiaries in each of their capacities in this Agreement shall secure that Protected Information is not:- 12.2.1 divulged by Business Personnel to any person unless that person is an Authorised Recipient;
used by Business Personnel for the purposes of obtaining for the RTL or any of its subsidiaries or for any other person:-
any Licence; or
any right to purchase or otherwise acquire, or to distribute, electricity including by means of an electricity purchase contract (as defined in the Transmission Licence); or
any contract or arrangement for the supply of electricity to customers or suppliers; or
any contract for the use of any electrical lines or electrical plant belonging to or under the control of a supplier.
used by Business Personnel for the purpose of carrying on any activities other than Permitted Activities except with the consent in writing of the Party to whose affairs such Protected Information relates.
Nothing in this Clause 12 shall apply:
to any Protected Information which, before it is furnished to Business Personnel is in the public domain;
to any Protected Information which, after it is furnished to Business Personnel:
is acquired by the RTL or any subsidiary of the RTL in circumstances in which this Clause 12 does not apply; or
is acquired by the RTL or any subsidiary of the RTL in circumstances in which this Clause 12 does apply and thereafter ceases to be subject to the restrictions imposed by this Clause 12; or
enters the public domain otherwise than as a result of a breach by the RTL or any subsidiary of the RTL of its obligations in this Clause 12.
to the disclosure of any Protected Information to any person if the RTL or any subsidiary is required or permitted to make such disclosure to such person:
in compliance with the duties of the RTL or any associate under the Act or any other requirement of a Competent Authority; or
in compliance with the conditions of its RTL Licence or any document referred to in its RTL Licence with which the RTL is required to comply; or
in compliance with any other requirement of law; or
in response to a requirement of any recognised stock exchange or regulatory authority or the Panel on Take- overs and Mergers; or
pursuant to the rules for the London Court of International Arbitration or pursuant to any judicial or other arbitral process or tribunal.
to any Protected Information to the extent that the RTL or any of its subsidiaries is expressly permitted or required to disclose that information under the terms of any agreement or arrangement (including the Fuel Security Code) with the Party to whose affairs such Protected Information relates.
The RTL and its subsidiaries may use all and any information or data supplied to or acquired by it, from or in relation to the other Party to this Agreement in performing its Permitted Activities and may pass the same to subsidiaries of the RTL which carry out such activities and the User hereto agrees to provide all information to the RTL and its subsidiaries for such purpose.
The Company and its subsidiaries may use all and any information or data supplied to or acquired by it from the RTL pursuant to Clause 12.3.3 in relation to this Agreement in performing its activities under the ESO Licence including for the following purposes:
the operation and planning of the National Electricity Transmission System;
the calculation of charges and preparation of offers of terms for connection to or use of the National Electricity Transmission System; and the User agrees to provide all information to the RTL and its subsidiaries for such purposes.
The RTL undertakes that, having regard to the activities in which any Business Person is engaged and the nature and effective life of the Protected Information divulged to them by virtue of such activities, neither the RTL nor any of its subsidiaries shall unreasonably continue (taking into account any industrial relations concerns reasonably held by it) to divulge Protected Information or permit Protected Information to be divulged to any Business Person:
who has notified the RTL or the relevant subsidiary of their intention to become engaged as an employee or agent of any other person (other than of the RTL or any subsidiary thereof); or
who is authorised by licence or exemption to generate or supply electricity.
Without prejudice to other provisions of this clause 12 the RTL shall procure that any additional copies of the Protected Information, whether in hard copy or computerised form, will clearly identify the Protected Information as protected.
The RTL undertakes to use all reasonable endeavours to procure that no employee is a Corporate Functions Person unless the same is necessary for the proper performance of their duties.
Confidentiality for User
User hereby undertakes with the RTL and its subsidiaries that it shall preserve the confidentiality and secrecy of, and not directly or indirectly reveal, report, publish, disclose or transfer or use for its own purposes Confidential Information except:
in the circumstances set out in Clause 12.9.2;
to the extent expressly permitted by this Agreement; or
with the consent in writing of the RTL.
Exceptions: the circumstances referred to in Clause 12.9.1(a) are:
where the Confidential Information, before it is furnished to User, is in the public domain; or
where the Confidential Information, after it is furnished to User:
is acquired by User in circumstances in which this Clause 12 does not apply; or
is acquired by User in circumstances in which this Clause 12 does apply and thereafter ceases to be subject to the restrictions imposed by this Clause 12; or
enters the public domain otherwise than as a result of a breach by User of its obligations in this Clause 12; or
if User is required or permitted to make disclosure of the Confidential Information to any person:
in compliance with the duties of User under the Act or any other requirement of a Competent Authority;
in compliance with the conditions of any Licence or any document referred to in any Licence with which User is required to comply;
in compliance with any other requirement of law;
in response to a requirement of any stock exchange or regulatory authority or the Panel on Takeovers and Mergers; or
pursuant to the rules for the London Court of International Arbitration or pursuant to any judicial or other arbitral process or tribunal; or
where Confidential Information is furnished by User to the employees, directors, agents, lenders, consultants and professional advisers of User in each case on the basis set out in Sub-Clause 12.10.
With effect from the date of this Agreement User shall adopt procedures within its organisation for ensuring the confidentiality of all Confidential Information which it is obliged to preserve as confidential under this Clause 12. These procedures will include:
the Confidential Information will be disseminated within User only on a “need to know” basis;
employees, directors, agents, lenders, consultants and professional advisers of User in receipt of Confidential Information will be made fully aware of User’s obligations of confidence in relation thereto.
13. Title to Assets 26
The RTL acknowledges that it does not have and will not acquire any title, right or interest in User’s Offshore Platform save for such rights as are expressly granted herein or otherwise provided nevertheless that, if according to any rule of law, the RTL could acquire any such title, right or interest in any of User’s Offshore Platform, the RTL undertakes to do all that is required to transfer such right or interest to User to ensure that User shall not, by reason of such right or interest arising, have its full rights in such Offshore Platform diminished (and in the interim to hold such rights in trust for User) and shall if requested by User, be obliged forthwith to establish trust arrangements valid under Scottish law so as to ensure that any such right or interest shall be held on behalf of User.
User agrees that it shall not by any act or default render the RTL Assets liable to any distress execution or other legal process, and in the event that the RTL Assets shall become so liable, shall forthwith give notice of any such proceedings to the RTL and shall forthwith notify any third party instituting any such process of the ownership of such RTL Assets.
If User desires to mortgage or charge User’s Offshore Platform or its interest therein on which any RTL Assets are located or to enter into any arrangement which, if made, might affect the rights of the RTL expressly granted herein, then User shall ensure that the RTL Assets are not and will not be subject to the rights granted therein and are not and will not be affected by the mortgage, legal charge or other agreement or arrangement, and shall give prior written notification thereof to the RTL.
In the event that User shall wish to grant rights over or dispose of any interest in [or change the use of User’s Offshore Platform] User shall notify the RTL of such wish and fully consult the RTL in respect thereof and shall not grant such rights or make such disposal or change of use save on terms securing to the reasonable satisfaction of that other the Rights of Access granted in respect of User’s Land Offshore Platform.
14. Limitation of Liability 27
Subject to sub-clauses 5.3, 6.2, 9.2 and 14.5 and save as provided in this sub-clause 14.1 and sub-clause 14.2 neither Party (“the Party Liable”) nor any of its officers, employees or agents shall be liable to the other Party for loss arising from any breach of this Agreement other than for loss directly resulting from such breach and which at the date hereof was reasonably foreseeable as not unlikely to occur in the ordinary course of events from such breach and which resulted from:
physical damage to the property of the other Party, its officers, employees or agents; and/or 14.1.2 the liability of the other Party to any other person for loss arising from physical damage to the property of any person.
Nothing in this Agreement shall exclude or limit the liability of the Party Liable for death or personal injury resulting from the negligence of the Party Liable or any of its officers, employees or agents and the Party Liable shall indemnify and keep indemnified the other Party, its officers, employees or agents, from and against all such and any loss or liability which the other Party may suffer or incur by reason of any claim on account of death or personal injury resulting from the negligence of the Party Liable or any of its officers, employees or agents.
Subject to sub-clauses 5.3, 6.2, 9.2 and 14.5 neither Party, nor any of its officers, employees or agents shall in any circumstances whatsoever be liable to the other Party for:- 14.3.1 any loss of profit, loss of revenue, loss of use, loss of contract or loss of goodwill; or 14.3.2 any indirect or consequential loss; or 14.3.3 loss resulting from the liability of the other Party to any other person howsoever and whensoever arising save as provided in sub- clauses 14.1.2 and 14.2.
The rights and remedies provided by this Agreement to the Parties are exclusive and not cumulative and exclude and are in place of all substantive (but not procedural) rights or remedies express or implied and provided by common law or statute in respect of the subject matter of this Agreement, including any rights either Party may possess in tort which shall include actions brought in negligence and/or nuisance. Accordingly, each of the Parties hereby waives in the fullest extent possible all such rights and remedies provided by common law or statute, and releases the Party Liable, its officers, employees and agents to the same extent from all duties, liabilities, responsibilities or obligations provided by common law or statute in respect of the matters dealt with in this Agreement and undertakes not to enforce any of the same except as expressly provided herein.
Save as otherwise expressly provided in this Agreement, this clause 14 insofar as it excludes or limits liability shall override any other provision in this Agreement provided that nothing in this clause 14 shall exclude or restrict or otherwise prejudice or affect any of:
the rights, powers, duties and obligations of either Party which are conferred or created by the Act, the User’s Licence, RTL’s Licence or the Regulations or any amendment or re-enactment thereof; or 14.5.2 the rights, powers, duties and obligations of the Authority or the Secretary of State under the Act, any such licence as aforesaid or otherwise howsoever.
Each of the sub-clauses of this clause 14 shall:
be construed as a separate and severable contract term, and if one or more of such sub-clauses is held to be invalid, unlawful or otherwise unenforceable the other or others of such sub-clauses shall remain in full force and effect and shall continue to bind the Parties; and 14.6.2 survive termination of this Agreement.
Each Party agrees that the other Party holds the benefit of sub clauses 14.1, 14.2 and 14.3 above for itself and as trustee and agent for its officers, employees and agents
Each Party hereby acknowledges and agrees that the provisions of this clause 14 have been the subject of discussion and negotiation and are fair and reasonable having regard to the circumstances as at the date hereof.
15. INTELLECTUAL PROPERTY All Intellectual Property relating to the subject matter of this Agreement conceived, originated, devised, developed or created by a Party, its officers, employees, agents or consultants during the currency of this Agreement shall vest in such Party as the sole beneficial owner thereof save where the Parties agree in writing otherwise.
16. FORCE MAJEURE If either Party (the “Non-Performing Party”) shall be unable to carry out any of its obligations under this Agreement due to a circumstance of Force Majeure this Agreement shall remain in effect but save as otherwise provided herein the Non-Performing Party’s obligations hereunder shall be suspended without liability for a period equal to the circumstance of Force Majeure provided that:
the Non-Performing Party gives the other Party prompt notice describing the circumstance of Force Majeure, including the nature of the occurrence, its expected duration and the particular obligations affected by it, and continues to furnish regular reports with respect thereto during the period of Force Majeure;
the suspension of performance is of no greater scope and of no longer duration than is required by the Force Majeure;
no liabilities of either Party that arose before the Force Majeure causing the suspension of performance are excused as a result of the Force Majeure;
the non-performing Party uses all reasonable efforts to remedy its inability to perform; and
as soon as practicable after the event which constitutes Force Majeure the Parties shall discuss how best to continue their operations so far as possible in accordance with this Agreement.
17. WAIVER No delay by or omission of a Party in exercising any right, power, privilege or remedy under this Agreement shall operate to impair such right, power, privilege or remedy or be construed as a waiver thereof. Any single or partial exercise of any such right, power, privilege or remedy shall not preclude any other or future exercise thereof or the exercise of any other right, power, privilege or remedy.
18. Notices 30
Any notice or other communication to be given by one Party to the other under, or in connection with the matters contemplated by, this Agreement shall be addressed to the recipient and sent to the address, or email address of such other Party given in Schedule 6 and marked for the attention of the person so given or to such other address, and/or email address and/or marked for such other attention as such other Party may from time to time specify by notice given in accordance with this clause 18 to the Party giving the relevant notice or other communication to it.
Any notice or other communication to be given by one Party to the other Party under, or in connection with the matters contemplated by, this Agreement shall be in writing and shall be given by letter delivered by hand or sent by first class prepaid post (airmail if overseas) or email and shall be deemed to have been received:
in the case of delivery by hand, when delivered; or 18.2.2 in the case of first class prepaid post, on the second day following the day of posting or (if sent airmail from overseas) on the fifth day following the day of posting; or 18.2.3 in the case of telex, on the transmission of the automatic answerback of the addressee (where such transmission occurs before 1700 hours on the day of transmission) and in any other case on the day following the day of transmission; or 18.2.4 in the case of email, when delivered to the email address (where such delivery occurs before 1700 hours on the day of delivery) and in any other case on the day following the day of delivery.
19. VARIATIONS The provisions of Schedules 1, 3, 4, 5 and 6 may be varied from time to time by written memorandum signed by an authorised officer of each of the Parties. Subject thereto no variations to this Agreement shall be effective unless made by way of supplemental deed.
20. Overriding Provisions 31
In the event of any conflict between RTL’s or User’s obligations hereunder and their obligations under the User’s Licence and RTL’s Licence, the Act, any direction of the Secretary of State, the Authority or ruling of the Competition Commission, the Grid Code, Connection Agreement or the Bilateral Connection Agreement, the provisions of the User’s Licence and RTL’s Licence, the Act, the Grid Code, the Connection Agreement or Bilateral Connection Agreement the direction of the Secretary of State, the Authority, or ruling of the Competition Commission shall prevail and accordingly the RTL and User respectively shall not be responsible for any failure to perform their respective obligations hereunder to the extent that any such failure is directly attributable to proper compliance with such provisions, rulings or directions.
Both parties shall observe their respective obligations hereunder in accordance with Good Industry Practice.
21. Assignment and Sub-Contracting 32
The rights and obligations of a Party may not be assigned (otherwise than to an Affiliate or by way of a charge or an assignment by way of security) without the consent of the other Party, such consent not to be unreasonably withheld.
Each Party shall have the right to sub-contract or delegate the performance of any of its obligations or duties arising under this Agreement without the consent of the other. The sub-contracting by either Party of the performance of any obligations or duties under this Agreement shall not relieve such Party from the liability for performance of such obligation or duty.
22. Illegality and Partial Invalidity 32
If at any time any provision of this Agreement should become or be declared unlawful, invalid, illegal or unenforceable in any respect under the law of any jurisdiction, neither the validity, legality or enforceability of the remaining provisions nor the validity, legality or enforceability of such provision under the law of any other jurisdiction shall be affected.
If any part of a provision of this Agreement is or becomes or is declared invalid, unlawful, illegal or unenforceable but the rest of such provision would remain valid, lawful or enforceable if part of the wording were deleted the provision shall apply with such modifications as may be necessary to make it valid, lawful, enforceable and effective but without affecting the meaning of legality, validity or enforceability of any other provision of this Agreement.
23. TERM AND TERMINATION This Agreement shall continue until no RTL Assets are on User’s Offshore Platform and no Facilities or Services are shared or provided.
24. Registration and Memorandum 33
This Agreement contains the entire agreement between the Parties with respect to the subject-matter hereof, and expressly excludes any warranty, condition or other undertaking implied at law or by custom, and supersedes all previous agreements and understandings between the Parties with respect thereto and:
each of the Parties acknowledges and confirms that it does not enter into this Agreement in reliance on any representation, warranty or other undertaking not fully reflected in the terms of this Agreement; but
the RTL acknowledges that User may have entered or may enter into agreements with other parties who hold a Licence containing similar rights and/or liabilities to those contained in this Agreement affecting User’s Offshore Platform and any assets thereon. User shall, when entering into such agreement with any such party use reasonable endeavours to avoid conflicts between the provisions thereof and the provisions of this Agreement but in the event of any conflict User shall use all reasonable endeavours to procure that appropriate arrangements are made to settle the same to give full effect (so far as practicable) to the rights and liabilities under this Agreement and under such other agreements as aforesaid. In the event of any dispute as to such conflict and/or arrangements the dispute shall be dealt with in accordance with Clause 10. IN WITNESS whereof this Agreement has been entered into as a deed the day and year first above written. SCHEDULE 1
1. The Parties will comply with the Site Specific Safety Rules and any agreed modifications thereto.
2. The Parties will arrange for the Site Specific Safety Rules to be written down and to be implemented by the person or persons responsible on behalf of the relevant Parties for the co-ordination of safety. SCHEDULE 4
Exhibit O - Part 2B
1. [Insert name of Relevant Transmission Licensee (RTL)] - and -
2. (User)
1. [Insert name of Relevant Transmission Licensee] a company registered in [] with number [] whose registered office is at [(“RTL”, which expression shall include its successors and\or permitted assigns); and
2. [] a company registered in [] with number [] whose registered office is at [] (“User”, which expression shall include its successors and/or permitted assigns) WHEREAS Certain assets and facilities of User are to be installed on property title to which is vested in RTL and this Agreement is entered into by the Parties to give effect to appropriate arrangements in respect of such assets and the use of such assets and facilities. NOW IT IS HEREBY AGREED as follows:-
1. DEFINITIONS AND INTERPRETATION In this Agreement, the following words and expressions shall, unless the subject matter- or context otherwise requires or is inconsistent therewith, bear the following meanings:- EXO(2)-5 “Act” the Electricity Act 1989 as amended by Utilities Act 2000 and the Energy Act 2023; “Affiliate” in relation to User means any holding company or subsidiary of that Party or any subsidiary of a holding company of User, in each case within the meaning of Sections 736, 73
unless the context otherwise requires all references to a particular clause, sub-clause, paragraph or Schedule shall be a reference to that clause, sub-clause, paragraph or Schedule in or to this Agreement;
the table of contents and headings are inserted for convenience only and shall be ignored in construing this Agreement;
references to the words “include” or “including” are to be construed without limitation to the generality of the preceding words;
unless there is something in the subject matter or the context which is inconsistent therewith, any reference to an Act of Parliament or any Section thereof or Schedule thereto, or other provision thereof or any instrument, order or regulation made thereunder shall be construed at the particular time as including a reference to any modification, extension, replacement or re-enactment thereof then in force and to all instruments, orders or regulations then in force and made under or deriving validity from the relevant Act of Parliament; and
references to the masculine shall include the feminine and references in the singular shall include the plural and vice versa and words denoting natural persons shall include companies, corporations and any other legal entity and vice versa.
unless otherwise provided to the contrary herein, defined terms used in this agreement and not defined herein shall have the meaning set forth in the connection and Use of System Code or the Bilateral Connection Agreement.
2. Right to Install and Retain Asset 8
Subject to sub-clause 5.1, the RTL hereby grants to User the right to install and thereafter retain and replace as provided in this Agreement User Assets on the RTL’s Land in such places as are currently proposed (subject to such variations between the date hereof and the actual date of installation as may be agreed to by the RTL) and such right shall extend to any Modified User Assets. The RTL shall maintain any shelter and/or support enjoyed by any User Assets at the date of this Agreement or, if later, when relocated on the RTL’s Land in accordance with clause 5 and grants to User a Right of Access for the purpose of the maintenance, inspection, testing, removal, operation, modification or repair of any of User Assets.
3. Modifications, Replacements and 9 Alterations
User may at its own expense replace or alter any User Assets provided that:- 3.1.1 the replacement User Assets or the User Assets as so altered:-
are placed in the same or approximately the same position;
fulfil the same or a similar purpose;
can, where relevant, be accommodated in and on existing buildings or structures;
do not require additional or improved facilities or services from the RTL;
do not restrict the actual and intended use of the RTL’s Land and any equipment thereon or therein to any materially greater extent than the User Assets so replaced or altered; and
are either of the same or a similar or smaller size or the alteration is effected substantially within the space occupied by such User Assets to enable the User Assets to be used up to their full capability; and 3.1.2 prior written notification has been given to the RTL.
If any replacement or alteration permitted by clause 3.1 shall require minor alterations or works to the existing buildings or structures housing or supporting the User Asset in question, such alterations or works may be carried out (with the prior written approval of the RTL (such approval not to be unreasonably withheld or delayed)) but at the cost of User.
To the extent that any of the conditions of clause 3.1 are not in RTL’s reasonable opinion met in relation to any replacement or alteration, the RTL may by notice in writing require User promptly to remove such replacement or alteration and, if User fails to do so, may remove the same itself at the cost and expense of User. On such removal, User may reinstate the User Assets so replaced or altered.
User shall, if considering moving, replacing, or altering any User Assets, give due consideration as to whether it shall be operationally practicable, desirable and reasonably economic to move such User Assets to (or place the replacement or altered User Assets on) its own property.
For avoidance of doubt it is hereby agreed that any dispute between the Parties regarding this clause shall be determined in accordance with the provisions of Clause 10 of this Agreement.
4. SECURITY AND COMPLIANCE WITH STATUTES etc
The RTL undertakes to maintain and provide security in relation to User Assets in accordance with the arrangements set out in Part I of Schedule 3.
Each Party shall procure that, as between the Parties, all reasonable and necessary steps are taken, as and when necessary or desirable, in co-operation with the other Party (and, so far as applicable, with any third party), to ensure compliance with the provisions (each such provision or part thereof being in this clause 4 an “Obligation”) of:-
all statutes and Directives applicable to any User Assets and/or any part (including the whole) of the RTL’s Land;
any statute or Directive which may affect any other property (of whatever nature) of either Party as a result of the existence, nature, location, or manner of operation of any User Assets; and
any statute or Directive requiring the reporting of any occurrence relating to or affecting any User Assets and/or the RTL’s Land (including the Reporting of Injuries Diseases and Dangerous Occurrence Regulations 1985 and the Regulations).
Each Party shall, so far as it is aware of the same, unless it has reasonable grounds for believing that the other Party possesses the information, keep the other Party informed of all matters relating to any Obligation or potential Obligation and/or the extent to which such Obligation may be applicable.
In the event of any dispute as to responsibility, as between the Parties, pursuant to clause 4.2, for compliance with an Obligation, that responsibility shall be allocated, so far as practicable, on the basis that:-
each Party shall refrain from taking or permitting any act or omission which would prevent compliance with an Obligation; and
positive action required in relation to a Party’s property as a consequence of the existence, nature, location or manner of operation of that property or any other property of that Party shall be the responsibility of that Party, and, to the extent that such action is required in respect of or affecting any property of the other Party (or property of a third party located in or on that other Party’s Land), such action may be taken with the prior approval of that other Party (such approval, subject to (i) above, not to be unreasonably withheld or delayed).
The provisions for safety co-ordination between the Parties contained in Part II of Schedule 3 shall apply.
5. Relocations 11
At any time and from time to time during the term of this Agreement, the RTL may with the prior written consent of User (such consent not to be unreasonably withheld or delayed) require User to relocate any User Assets either to a different location on the RTL Land or to User’s or a third party’s land, such consent to be sought and given or refused in accordance with the following procedure:-
The RTL shall serve a written notice on User, which notice shall specify:-
the User Assets which the RTL wishes to be relocated;
the reasons for such wish;
the proposed new location for such User Assets; and
the timing of the carrying out of such relocation.
User shall within one month of receipt of any such notice (or such longer period as shall be reasonably necessary) serve a counter notice stating:-
whether or not in its reasonable opinion such Relocation Proposal is acceptable to it;
if the Relocation Proposal is not acceptable to User, the grounds for such opinion and the terms of any alternative proposal (the “Alternative Relocation Proposal”) covering so far as relevant the matters referred to in items (a) - (d) of clause 5.1.1 which would be acceptable to User; and
in respect of the Relocation Proposal (if accepted) or of any Alternative Relocation Proposal, the costs likely to be incurred in connection with considering the Relocation Proposal or the Alternative Relocation Proposal and effecting the said relocation of the User Assets and the proper and reasonable costs of relocating any other equipment that may be necessary as a result of the relocation of those User Assets and any consequential losses including payments to third parties incurred as a result of the relocation of those User Assets and the proposed manner and timing of payment of the same by the RTL.
If within one month of the date of such counter notice (or such longer period as shall be reasonably necessary) the RTL has not withdrawn the Relocation Proposal and the Parties have not agreed upon it or the Alternative Relocation Proposal (if any) or a variation of either of them (such agreement to include agreement on the costs referred to in item (c) of clause 5.1.2) the matter shall be dealt with in accordance with Clause 10.
Upon approval or settlement of any Relocation Proposal, Alternative Relocation Proposal or variation thereof pursuant to clause 5.1, User shall (conditionally upon it being able to obtain all necessary licences and consents which it will use reasonable endeavours to do) relocate or procure the relocation of the relevant User Assets as quickly as reasonably practicable (having regard to, amongst other things, technical and operational requirements and to the availability of all necessary licences and consents).
The RTL shall render all reasonable assistance to User in connection with such relocation licences and consents and pay to User all costs referred to in item (c) of clause 5.1.2 as agreed or settled pursuant to clause 5.1 provided that all reasonable endeavours are used to minimise such costs and in the event that a Relocation Proposal is withdrawn or consent thereto is reasonably withheld pursuant to clause 5.1, the RTL shall pay to User all costs reasonably incurred by User in connection with considering the Relocation Proposal and any counter notice.
Such of the provisions of this Agreement as are appropriate and relevant (including the provisions of this clause 5), shall continue to apply to any relocated User Assets.
6. Removals 13
In the event that there shall cease to be a Bilateral Connection Agreement relating to any User Assets on the RTL’s Land User shall remove all User Assets from the RTL’s Land in accordance with the provisions relating thereto contained in the Connection Agreement and the Bilateral Connection Agreement.
Where User is obliged to remove any User Assets from the RTL’s Land, under this Clause 6, and fails to do so in accordance with the relevant provisions, (whether they be contained in this clause 6, clause 3 or clause 5) the RTL shall be entitled to remove those User Assets to land belonging to User and User shall provide all reasonable assistance to enable the RTL safely so to do and shall pay and reimburse to the RTL all costs and expenses reasonably incurred by the RTL in so doing.
7. Rights of Access 14
A Right of Access includes the right to bring on to the RTL’s Land such vehicles, plant, machinery and maintenance or construction materials as shall be reasonably necessary for the Permitted Purpose.
A Right of Access given to User may be exercised by any person, including third party contractors, reasonably nominated from time to time by User. To the extent (if any) that any particular authorisation or clearances may be required to be given by the RTL and the procedures for giving and obtaining the same are not for the time being stipulated in arrangements made pursuant to clause 7.3, the same shall be given within a reasonable time from the date of the request therefor, save in the case of emergency in which case it shall be given without delay.
User shall procure that all reasonable arrangements and provisions are made and/or revised from time to time, as and when necessary or desirable, to facilitate the safe exercise by it of any Right of Access with the minimum of disruption, disturbance or inconvenience to the RTL. Such arrangements and provisions shall provide for the RTL to have the right to make directions or regulations from time to time in relation to a specified matter. Matters to be covered by such arrangements and/or provision shall include:-
the identification of any relevant User Assets;
the particular access routes applicable to the land in question having particular regard for the weight and size limits on those routes;
any limitations on times of exercise of a Right of Access;
any requirements as to prior notification and as to authorisation or security clearance of individuals exercising such Rights of Access, and procedures for obtaining the same;
the means of communication between the Parties and all employees and/or contractors who may be authorised from time to time by User to exercise a Right of Access of any relevant directions or regulations made by the RTL;
the identification of and arrangements applicable to Emergency Personnel.
Any limitation or restriction on the exercise of such Right of Access to the extent that in the circumstances is reasonable
User shall procure that any such arrangements and/or provisions (or directions or regulations issued by the RTL pursuant thereto) made from time to time between the Parties shall be observed and performed by it and all persons authorised by it to exercise any Right of Access.
User shall procure that all reasonable steps are taken in the exercise of any Right of Access to:-
avoid or minimise damage to the RTL’s Land, or any other property thereon or therein;
cause as little disturbance and inconvenience as possible to the RTL or other occupier of the RTL’s Land; and shall promptly make good any damage caused to the RTL’s Land and/or such other property in the course of the exercise of such rights and shall indemnify the RTL against all actions, claims, proceedings, losses, costs and demands arising out of such exercise.
Subject to clause 7.4.1, all such rights shall be exercisable free of any charge or payment of any kind.
Subject to any contrary arrangements for the time being made under clause 7.3, 7.5.1 a Right of Access for operation or inspection shall be available without prior notice;
a Right of Access for the purpose of maintenance, testing or repair of HV Apparatus shall only be exercisable on the giving of at least seven days prior written notice to the RTL except in the case of loss of generation or demand or other emergency (in which event the RTL shall render all possible assistance in procuring that the Right of Access shall be exercisable as soon as possible); and 7.5.3 a Right of Access for the purpose of Modifying any User Assets shall be exercisable only after two weeks prior written notice to the RTL.
8. Services and Use of Assets 16
Subject as hereinafter provided, in relation to each Facility Asset, RTL shall, if required by User, make the Facility Asset in question available for use by User to such extent as is necessary for the purposes of User’s undertaking but not so as to prejudice the use now or hereafter of such Facility Asset by the RTL for its undertaking.
Subject as hereinafter provided, in relation to each Services, the RTL shall, if required by User, provide the same to User. Such provision shall be of such a quality and quantity and shall be provided at such times as User shall reasonably request. The RTL shall not be required to exceed the level of quality or quantity of the Services as are anticipated by the Parties at the date of this Agreement, unless specifically agreed otherwise between the Parties.
Where the use of any Facility Asset is made available or such Services are supplied as aforesaid, the Parties shall procure that all reasonable arrangements and provisions are made and/or revised from time to time, as and when necessary or desirable between the local personnel employed by each of them in that regard, such arrangements to include:- 8.3.1 the identification of the Facility Asset and/or Services in question including (where relevant) the extent of their availability;
the hours during which such use or provision shall be allowed or made;
any requirements as to notification of use or call for supply or temporary suspension thereof;
any requirements as to authorisation or security clearance of individuals and the procedures for obtaining the same; and 8.3.5 any safety requirements.
The provision of use of the Facility Asset listed in Schedule 4, Part One and the supply of the Services listed in Schedule 5, Part One shall not be terminated unless the RTL ceases to require the Facility Asset or Services for its own use in which case the supply of the Services or use of the Facility Asset may be terminated by not less than one year’s notice in writing;
The provision of use of the Facility Assets listed in Schedule 4, Part Two and the supply of the Services listed in Schedule 5, Part Two shall continue until terminated by not less than six months notice in writing by either Party. The RTL shall maintain the Facility Asset in accordance with Good Industry Practice.
9. Non-Interference 18
The RTL agrees that neither it nor its agents, employees and invitees will interfere in any way with any of User Assets without the consent of User. For the purposes of this clause “interfere” shall include:- 9.1.1 disconnecting or altering the connection of any User Assets to any system of cables, foundations, pipes, drains or other media to which it may be connected from time to time or to prevent supply of any substance or thing through such connected system;
affixing or removing any item or substance of any nature whatsoever to or from any User Assets;
damaging any User Assets;
allowing any other person to interfere with any User Assets;
alter any meters or settings on any User Assets;
the obstruction of access to any User Assets.
The obligations contained in this clause 9 shall be suspended to the extent that emergency action is taken by Emergency Personnel in good faith to protect the health and safety of persons or to prevent damage to property. All reasonable care shall be taken in the course of such emergency action. When the emergency has ended, any damaged property will be reinstated by User, save for damage occurring by reason of lack of reasonable care in the course of the emergency action taken by the RTL which shall be the responsibility of the RTL.
10. Dispute Resolution 19
Any dispute arising under this Agreement between Location Managers of the Parties shall, if not resolved within 14 days of first arising, be referred at the instance of either party to the respective line managers, or those fulfilling a similar function whether or not so called, of the RTL and User who shall use all reasonable endeavours to resolve the matter in dispute within one month.
Save where expressly stated in this Agreement to the contrary (including the procedure for initial dispute resolution contained in clause 10.1) and subject to any contrary provision of the Act, any Licence, or the Regulations, or the rights, powers, duties and obligations of the Authority or the Secretary of State under the Act, any Licence or otherwise howsoever, any dispute or difference of whatever nature howsoever arising under out of or in connection with this Agreement between the Parties shall (subject to any relevant initial dispute resolution procedures referred to in Clause 10.1 having been exhausted) be and is hereby referred to arbitration pursuant to the rules of the London Court of International Arbitration in force from time to time.
Whatever the nationality residence or domicile of any Party and wherever the dispute or difference or any part thereof arose the law of England and Wales shall be the proper law of any reference to arbitration hereunder and in particular (but not so as to derogate from the generality of the foregoing) the provisions of the Arbitration Act 1996 (including any modification, extension, replacement or re-enactment thereof for the time being in force) shall apply to any such arbitration wherever the same or any part of it shall be conducted.
11. Governing Law and Jurisdiction 21
This Agreement shall be governed by and construed in all respects in accordance with English law.
Subject and without prejudice to clause 10 and to clause 11.4 the Parties irrevocably agree that only the courts of England and Wales and the courts of Scotland are to have jurisdiction to settle any dispute which may arise out of or in connection with this Agreement and that accordingly any suit, action or proceeding (together in this clause 11 referred to as “Proceedings”) arising out of or in connection with this Agreement may be brought in such courts.
Each Party irrevocably waives any objection which it may have now or hereafter to the laying of the venue of any Proceedings in any such court as is referred to in this clause 11 and any claim that any such Proceedings have been brought in an inconvenient forum and further irrevocably agrees that a judgment in any Proceedings brought in the courts of England and Wales or the courts of Scotland shall be conclusive and binding upon such Party and may be enforced in the courts of any other jurisdiction.
For the avoidance of doubt nothing contained in the foregoing provisions of this clause 11 shall be taken as permitting a Party to commence Proceedings in the courts where this Agreement otherwise provides for proceedings to be referred to arbitration.
12. Confidentiality 22
For the purposes of this Clause 12 except where the context otherwise requires:-
“Authorised Recipient”, in relation to any Protected Information, means any Business Person who, before the Protected Information had been divulged to them by the RTL or any 2subsidiary of the RTL, had been informed of the nature and effect of this clause 12 and who requires access to such Protected Information for the proper performance of their duties as a Business Person in the course of Permitted Activities;
To consider simplifying?
“Business Person” means any person who is a Licensed Business Person, or a Corporate Functions Person and “Business Personnel” shall be construed accordingly.
“Confidential Information” means all data and other information supplied to User under the provisions of this Agreement.
“Corporate Functions Person” means any person who:-
is a director of the RTL; or
is an employee of the RTL or any of its subsidiaries carrying out any administrative, finance or other corporate services of any kind which in part relate to the Licensed Business; or
is engaged as an agent of or adviser to or performs work in relation to or services for the Licensed Business.
“Licensed Business” means any business of RTL or any of its associates authorised by its RTL Licence;
“Licensed Business Person” means any employee of the RTL or any Authority or employee of its subsidiaries who is engaged solely in its Licensed Business and “Licensed Business Personnel” shall be construed accordingly;
“Permitted Activities” means activities carried on for the purposes of the Licensed Business;
“Protected Information” means any information relating to the affairs of a Party which is furnished to Business Personnel pursuant to this Agreement unless, prior to such information being furnished, such Party has informed the recipient thereof by notice in writing or by endorsement on such information, that the said information is not to be regarded as Protected Information;
Confidentiality for the RTL and its Subsidiaries The RTL and its subsidiaries in each of their capacities in this Agreement shall secure that Protected Information is not:- 12.2.1 divulged by Business Personnel to any person unless that person is an Authorised Recipient;
used by Business Personnel for the purposes of obtaining for the RTL or any of its subsidiaries or for any other person:-
any Licence; or
any right to purchase or otherwise acquire, or to distribute, electricity including by means of an electricity purchase contract (as defined in the Transmission Licence); or
any contract or arrangement for the supply of electricity to customers or suppliers; or
any contract for the use of any electrical lines or electrical plant belonging to or under the control of a supplier.
used by Business Personnel for the purpose of carrying on any activities other than Permitted Activities except with the consent in writing of the Party to whose affairs such Protected Information relates.
Nothing in this Clause 12 shall apply:- 12.3.1 to any Protected Information which, before it is furnished to Business Personnel is in the public domain;
to any Protected Information which, after it is furnished to Business Personnel:-
is acquired by the RTL or any subsidiary of the RTL in circumstances in which this Clause 12 does not apply; or
is acquired by the RTL or any subsidiary of the RTL in circumstances in which this Clause 12 does apply and thereafter ceases to be subject to the restrictions imposed by this Clause 12; or
enters the public domain otherwise than as a result of a breach by the RTL or any subsidiary of the RTL of its obligations in this Clause 12.
to the disclosure of any Protected Information to any person if the RTL or any subsidiary is required or permitted to make such disclosure to such person:-
in compliance with the duties of the RTL or any associate under the Act or any other requirement of a Competent Authority; or
in compliance with the conditions of its RTL Licence or any document referred to in its RTL Licence with which the RTL is required to comply; or
in compliance with any other requirement of law; or
in response to a requirement of any recognised stock exchange or regulatory authority or the Panel on Take-overs and Mergers; or
pursuant to the rules for the London Court of International Arbitration or pursuant to any judicial or other arbitral process or tribunal.
to any Protected Information to the extent that the RTL or any of its subsidiaries is expressly permitted or required to disclose that information under the terms of any agreement or arrangement (including the Grid Code and the Fuel Security Code) with the Party to whose affairs such Protected Information relates.
The RTL and its subsidiaries may use all and any information or data supplied to or acquired by it, from or in relation to the other Party to this Agreement in performing its Permitted Activities and may pass the same to subsidiaries of the RTL which carry out such activities and the User hereto agrees to provide all information to the RTL and its subsidiaries for such purposes.
The Company and its subsidiaries may use all and any information or data supplied to or acquired by it from the RTL pursuant to Clause 12.3.3 in relation to this Agreement in performing its activities under the ESO Licence including for the following purposes:
the operation and planning of the GB Transmission System;
the calculation of charges and preparation of offers of terms for connection to or use of the GB Transmission System; and the User agrees to provide all information to the RTL and it’s subsidiaries for such purposes.
The RTL undertakes that, having regard to the activities in which any Business Person is engaged and the nature and effective life of the Protected Information divulged to them by virtue of such activities, neither the RTL nor any of its subsidiaries shall unreasonably continue (taking into account any industrial relations concerns reasonably held by it) to divulge Protected Information or permit Protected Information to be divulged to any Business Person:
who has notified the RTL or the relevant subsidiary of their intention to become engaged as an employee or agent of any other person (other than of the RTL or any subsidiary thereof);
who is authorised by licence or exemption to generate or supply electricity.
Without prejudice to other provisions of this clause 12 the RTL shall procure that any additional copies of the Protected Information, whether in hard copy or computerised form, will clearly identify the Protected Information as protected.
The RTL undertakes to use all reasonable endeavours to procure that no employee is a Corporate Functions Person unless the same is necessary for the proper performance of their duties.
Confidentiality for User
User hereby undertakes with the RTL and its subsidiaries that it shall preserve the confidentiality and secrecy of, and not directly or indirectly reveal, report, publish, disclose or transfer or use for its own purposes Confidential Information except:-
in the circumstances set out in Clause 12.9.2;
to the extent expressly permitted by this Agreement; or
with the consent in writing of the RTL.
Exceptions: the circumstances referred to in Clause 12.9.1(a) are:-
where the Confidential Information, before it is furnished to User, is in the public domain; or
where the Confidential Information, after it is furnished to User:-
is acquired by User in circumstances in which this Clause 12 does not apply; or
is acquired by User in circumstances in which this Clause 12 does apply and thereafter ceases to be subject to the restrictions imposed by this Clause 12; or
enters the public domain otherwise than as a result of a breach by User of its obligations in this Clause 12; or
if User is required or permitted to make disclosure of the Confidential Information to any person:-
in compliance with the duties of User under the Act or any other requirement of a Competent Authority;
in compliance with the conditions of any Licence or any document referred to in any Licence with which User is required to comply;
in compliance with any other requirement of law;
in response to a requirement of any stock exchange or regulatory authority or the Panel on Takeovers and Mergers; or
pursuant to the rules for the London Court of International Arbitration or pursuant to any judicial or other arbitral process or tribunal; or
where Confidential Information is furnished by User to the employees, directors, agents, lenders, consultants and professional advisers of User in each case on the basis set out in Sub-Clause 12.10.
With effect from the date of this Agreement User shall adopt procedures within its organisation for ensuring the confidentiality of all Confidential Information which it is obliged to preserve as confidential under this Clause 12. These procedures will include:
the Confidential Information will be disseminated within User only on a “need to know” basis;
employees, Authorities, agents, lenders, consultants and professional advisers of User in receipt of Confidential Information will be made fully aware of User’s obligations of confidence in relation thereto.
13. Title to Assets 28
User acknowledges that it does not have and will not acquire any title, right or interest in the RTL’s Land save for such rights as are expressly granted herein or otherwise provided nevertheless that, if according to any rule of law, User could acquire any such title, right or interest in any of the RTL’s Land, then:
in the case of land in England & Wales, such title right or interest shall be held upon trust, insofar as it relates to the RTL’s land for such RTL absolutely; or 13.1.2 in the case of Land in Scotland, the User undertakes to do all that is required to transfer such right or interest to the RTL to ensure that the RTL shall not, by reason of such right or interest arising, have its full rights in such land diminished (and in the interim to hold such rights in trust for the RTL) and shall if requested by the RTL, be obliged forthwith to establish trust arrangements valid under Scottish law so as to ensure that any such right or interest shall be held on behalf of RTL .
The RTL agrees that it shall not by any act or default render User Assets liable to any distress execution or other legal process, and in the event that User Assets shall become so liable, shall forthwith give notice of any such proceedings to User and shall forthwith notify any third party instituting any such process of the ownership of such User Assets.
If the RTL desires to mortgage or charge RTL’s Land or its interest therein on which any User Assets are located or to enter into any arrangement which, if made, might affect the rights of User expressly granted herein, then the RTL shall ensure that User Assets are not and will not be subject to the rights granted therein and are not and will not be affected by the mortgage, legal charge or other agreement or arrangement, and shall give prior written notification thereof to User.
In the event that the RTL shall wish to grant rights over or dispose of any interest in or change the use of the RTL’s Land the RTL shall notify User of such wish and fully consult User in respect thereof and shall not grant such rights or make such disposal or change of use save on terms securing to the reasonable satisfaction of that other the Rights of Access granted in respect of the RTL’s Land.
14. Limitation of Liability 29
Subject to sub-clauses 5.3, 6.2, 9.2, and 14.5 and save as provided in this sub-clause 14.1 and sub-clause 14.2 neither Party (“the Party Liable”) nor any of its officers, employees or agents shall be liable to the other Party for loss arising from any breach of this Agreement other than for loss directly resulting from such breach and which at the date hereof was reasonably foreseeable as not unlikely to occur in the ordinary course of events from such breach and which resulted from:- 14.1.1 physical damage to the property of the other Party, its officers, employees or agents; and/or 14.1.2 the liability of the other Party to any other person for loss arising from physical damage to the property of any person.
Nothing in this Agreement shall exclude or limit the liability of the Party Liable for death or personal injury resulting from the negligence of the Party Liable or any of its officers, employees or agents and the Party Liable shall indemnify and keep indemnified the other Party, its officers, employees or agents, from and against all such and any loss or liability which the other Party may suffer or incur by reason of any claim on account of death or personal injury resulting from the negligence of the Party Liable or any of its officers, employees or agents.
Subject to sub-clauses 5.3, 6.2, 9.2, and 14.5 neither Party, nor any of its officers, employees or agents shall in any circumstances whatsoever be liable to the other Party for:- 14.3.1 any loss of profit, loss of revenue, loss of use, loss of contract or loss of goodwill; or 14.3.2 any indirect or consequential loss; or 14.3.3 loss resulting from the liability of the other Party to any other person howsoever and whensoever arising save as provided in sub-clauses 14.1.2 and 14.2.
The rights and remedies provided by this Agreement to the Parties are exclusive and not cumulative and exclude and are in place of all substantive (but not procedural) rights or remedies express or implied and provided by common law or statute in respect of the subject matter of this Agreement, including any rights either Party may possess in tort which shall include actions brought in negligence and/or nuisance. Accordingly, each of the Parties hereby waives in the fullest extent possible all such rights and remedies provided by common law or statute, and releases the Party Liable, its officers, employees and agents to the same extent from all duties, liabilities, responsibilities or obligations provided by common law or statute in respect of the matters dealt with in this Agreement and undertakes not to enforce any of the same except as expressly provided herein.
Save as otherwise expressly provided in this Agreement, this clause 14 insofar as it excludes or limits liability shall override any other provision in this Agreement provided that nothing in this clause 14 shall exclude or restrict or otherwise prejudice or affect any of:- 14.5.1 the rights, powers, duties and obligations of either Party which are conferred or created by the Act, the User’s Licence, the RTL’s Licence or the Regulations or any amendment or re-enactment thereof; or 14.5.2 the rights, powers, duties and obligations of the Authority or the Secretary of State under the Act, any such licence as aforesaid or otherwise howsoever.
Each of the sub-clauses of this clause 14 shall:- 14.6.1 be construed as a separate and severable contract term, and if one or more of such sub-clauses is held to be invalid, unlawful or otherwise unenforceable the other or others of such sub-clauses shall remain in full force and effect and shall continue to bind the Parties; and 14.6.2 survive termination of this Agreement.
Each Party agrees that the Other Party holds the benefit of sub clauses 14.1, 14.2 and 14.3 above for itself and as trustee and agent for its officers, employees and agents
Each Party hereby acknowledges and agrees that the provisions of this clause 14 have been the subject of discussion and negotiation and are fair and reasonable having regard to the circumstances as at the date hereof.
15. INTELLECTUAL PROPERTY All Intellectual Property relating to the subject matter of this Agreement conceived, originated, devised, developed or created by a Party, its officers, employees, agents or consultants during the currency of this Agreement shall vest in such Party as the sole beneficial owner thereof save where the Parties agree in writing otherwise.
16. FORCE MAJEURE If either Party (the “Non-Performing Party”) shall be unable to carry out any of its obligations under this Agreement due to a circumstance of Force Majeure this Agreement shall remain in effect but save as otherwise provided herein the Non-Performing Party’s obligations hereunder shall be suspended without liability for a period equal to the circumstance of Force Majeure provided that:-
the Non-Performing Party gives the other Party prompt notice describing the circumstance of Force Majeure, including the nature of the occurrence, its expected duration and the particular obligations affected by it, and continues to furnish regular reports with respect thereto during the period of Force Majeure;
the suspension of performance is of no greater scope and of no longer duration than is required by the Force Majeure;
no liabilities of either Party that arose before the Force Majeure causing the suspension of performance are excused as a result of the Force Majeure;
the non-performing Party uses all reasonable efforts to remedy its inability to perform; and
as soon as practicable after the event which constitutes Force Majeure the Parties shall discuss how best to continue their operations so far as possible in accordance with this Agreement.
17. WAIVER No delay by or omission of a Party in exercising any right, power, privilege or remedy under this Agreement shall operate to impair such right, power, privilege or remedy or be construed as a waiver thereof. Any single or partial exercise of any such right, power, privilege or remedy shall not preclude any other or future exercise thereof or the exercise of any other right, power, privilege or remedy.
18. Notices 33
Any notice or other communication to be given by one Party to the other under, or in connection with the matters contemplated by, this Agreement shall be addressed to the recipient and sent to the address, or email address of such other Party given in Schedule 6 and marked for the attention of the person so given or to such other address, and/or email address and/or marked for such other attention as such other Party may from time to time specify by notice given in accordance with this clause 18 to the Party giving the relevant notice or other communication to it.
Any notice or other communication to be given by one Party to the other Party under, or in connection with the matters contemplated by, this Agreement shall be in writing and shall be given by letter delivered by hand or sent by first class prepaid post (airmail if overseas) or email, and shall be deemed to have been received:- 18.2.1 in the case of delivery by hand, when delivered; or 18.2.2 in the case of first class prepaid post, on the second day following the day of posting or (if sent airmail from overseas) on the fifth day following the day of posting; or 18.2.3 in the case of telex, on the transmission of the automatic answerback of the addressee (where such transmission occurs before 1700 hours on the day of transmission) and in any other case on the day following the day of transmission; or 18.2.4 in the case of email, when delivered to the email address (where such delivery occurs before 1700 hours on the day of delivery) and in any other case on the day following the day of delivery.
19. VARIATIONS The provisions of Schedules 1, 3, 4, 5 and 6 may be varied from time to time by written memorandum signed by an authorised officer of each of the Parties. Subject thereto no variations to this Agreement shall be effective unless made by way of supplemental deed.
20. Overriding Provisions 34
In the event of any conflict between the RTL’s or User’s obligations hereunder and their obligations under the User’s Licence and RTL’s Licence, the Act, any direction of the Secretary of State, the Authority or ruling of the Competition Commission, the Grid Code, Connection Agreement or the Bilateral Connection Agreement, the provisions of the User’s Licence and RTL’s Licence, the Act, the Grid Code, Connection Agreement or Bilateral Connection Agreement, the direction of the Secretary of State, the Authority, or ruling of the Competition Commission shall prevail and accordingly the RTL and User respectively shall not be responsible for any failure to perform their respective obligations hereunder to the extent that any such failure is directly attributable to proper compliance with such provisions, rulings or directions.
Both parties shall observe their respective obligations hereunder in accordance with Good Industry Practice
21. Assignment and Sub-contracting 35
The rights and obligations of a Party may not be assigned (otherwise than to an Affiliate or by way of a charge or an assignment by way of security) without the consent of the other Party, such consent not to be unreasonably withheld.
Each Party shall have the right to sub-contract or delegate the performance of any of its obligations or duties arising under this Agreement without the consent of the other. The sub-contracting by either Party of the performance of any obligations or duties under this Agreement shall not relieve such Party from the liability for performance of such obligation or duty.
22. Illegality and Partial Invalidity 35
If at any time any provision of this Agreement should become or be declared unlawful, invalid, illegal or unenforceable in any respect under the law of any jurisdiction, neither the validity, legality or enforceability of the remaining provisions nor the validity, legality or enforceability of such provision under the law of any other jurisdiction shall be affected.
If any part of a provision of this Agreement is or becomes or is declared invalid, unlawful, illegal or unenforceable but the rest of such provision would remain valid, lawful or enforceable if part of the wording were deleted the provision shall apply with such modifications as may be necessary to make it valid, lawful, enforceable and effective but without affecting the meaning of legality, validity or enforceability of any other provision of this Agreement.
23. TERM AND TERMINATION This Agreement shall continue until no User Assets are on the RTL’s land and no Facility Assets or Services are shared or provided.
24. Registration and Memorandum 36
Where any or all of the RTL’s Land is registered or User’s interest therein is subject to compulsory registration at H.M Land Registry or the land register of Scotland (as relevant), the parties hereto agree to apply to the Chief Land Registrar or the Keeper (as relevant) for the registration as appropriate of the rights and obligations granted by or contained in this Agreement and the RTL agrees to place on deposit at H.M. Land Registry or the Land Registry Scotland (as relevant) all relevant Land or Charge Certificates to enable such registration to be effected.
Where any of the RTL’s Land is not so registered or subject to compulsory registration, the RTL shall procure within six months of the date hereof that memoranda of this Agreement are endorsed on or otherwise securely attached to the most recent conveyance (in the case of a heritable interest) or the lease under or pursuant to which they hold such land.
25. ENTIRE AGREEMENT
This Agreement contains the entire agreement between the Parties with respect to the subject-matter hereof, and expressly excludes any warranty, condition or other undertaking implied at law or by custom, and supersedes all previous agreements and understandings between the Parties with respect thereto and:-
each of the Parties acknowledges and confirms that it does not enter into this Agreement in reliance on any representation, warranty or other undertaking not fully reflected in the terms of this Agreement; but
User acknowledges that the RTL may have entered or may enter into agreements with other parties who hold a licence containing similar rights and/or liabilities to those contained in this Agreement affecting the RTL’s Land and any assets thereon. The RTL shall, when entering into such agreement with any such party, use reasonable endeavours to avoid conflicts between the provisions thereof and the provisions of this Agreement but in the event of any conflict the RTL shall use all reasonable endeavours to procure that appropriate arrangements are made to settle the same to give full effect (so far as practicable) to the rights and liabilities under this Agreement and under such other agreements as aforesaid. In the event of any dispute as to such conflict and/or arrangements the dispute shall be dealt with in accordance with Clause 10. IN WITNESS whereof this Agreement has been entered into as a Deed the day and year first above written. SCHEDULE 1 User’s Assets on RTL Land SCHEDULE 2 RTL’s Land SCHEDULE 3 Part I Security Details (Clause 4.1) Part II Plant MV LV Apparatus Safety Co-Ordination Procedures (Cl.4.5)
1. The Parties will comply with the Site Specific Safety Rules and any agreed modifications thereto.
2. The Parties will arrange for the Site Specific Safety Rules to be written down and to be implemented by the person or persons responsible on behalf of the relevant Parties for the co-ordination of safety. SCHEDULE 4
Exhibit O - Part 2C
1. [Insert name of Relevant Transmission Licensee (RTL)] - and -
2. (User)
1. [Insert name of Relevant Transmission Licensee] a company registered in [] with number [] whose registered office is at [(“RTL”, which expression shall include its successors and\or permitted assigns); and
2. [] a company registered in [] with number [] whose registered office is at [] (“User”, which expression shall include its successors and/or permitted assigns) WHEREAS Certain assets of the User are to be installed on the Offshore Platform title to which is vested in RTL and this Agreement is entered into by the Parties to give effect to appropriate arrangements in respect of such assets and also the use of certain facilities provided by RTL. NOW IT IS HEREBY AGREED as follows:-
1. DEFINITIONS AND INTERPRETATION In this Agreement, the following words and expressions shall, unless the subject-matter or context otherwise requires or is inconsistent therewith, bear the following meanings:- EXO(2)-5 “Act” the Electricity Act 1989 as amended by Utilities Act 2000 and the Energy Act 2023; “Affiliate” in relation to User means any holding company or subsidiary of that Party or any subsidiary of a holding company of User, in each case within the meaning of Sections 736, 736
unless the context otherwise requires all references to a particular clause, sub-clause, paragraph or Schedule shall be a reference to that clause, sub-clause, paragraph or Schedule in or to this Agreement;
the table of contents and headings are inserted for convenience only and shall be ignored in construing this Agreement;
references to the words “include” or “including” are to be construed without limitation to the generality of the preceding words;
unless there is something in the subject matter or the context which is inconsistent therewith, any reference to an Act of Parliament or any Section thereof or Schedule thereto, or other provision thereof or any instrument, order or regulation made thereunder shall be construed at the particular time as including a reference to any modification, extension, replacement or re-enactment thereof then in force and to all instruments, orders or regulations then in force and made under or deriving validity from the relevant Act of Parliament; and
references to the masculine shall include the feminine and references in the singular shall include the plural and vice versa and words denoting natural persons shall include companies, corporations and any other legal entity and vice versa.
unless otherwise provided to the contrary herein, defined terms used in this Agreement and not defined herein shall have the meaning set forth in the Connection and Use of System Code or the Bilateral Connection Agreement.
2. Right to Install and Retain Asset 8
Subject to sub-clause 5.1, the RTL hereby grants to User the right to install and thereafter retain and replace as provided in this Agreement User Assets on the RTL’s Offshore Platform in such places as are currently proposed (subject to such variations between the date hereof and the actual date of installation as may be agreed to by the RTL) and such right shall extend to any Modified User Assets. The RTL shall maintain any shelter and/or support enjoyed by any User Assets at the date of this Agreement [or, if later, when relocated on the RTL’s Offshore Platform in accordance with clause 5 and grants to User a Right of Access for the purpose of the maintenance, inspection, testing, removal, operation, modification or repair of any of User Assets.
3. Modifications, Replacements and 9 Alterations
User may at its own expense replace or alter any User Assets provided that:- 3.1.1 the replacement User Assets or the User Assets as so altered:-
are placed in the same or approximately the same position;
fulfil the same or a similar purpose;
can, where relevant, be accommodated in and on existing buildings or structures;
do not require additional or improved facilities or services from the RTL;
do not restrict the actual and intended use of the RTL’s Offshore Platform and any equipment thereon or therein to any materially greater extent than the User Assets so replaced or altered; and
are either of the same or a similar or smaller size or the alteration is effected substantially within the space occupied by such User Assets to enable the User Assets to be used up to their full capability; and 3.1.2 prior written notification has been given to the RTL.
If any replacement or alteration permitted by clause 3.1 shall require minor alterations or works to the existing buildings or structures housing or supporting the User Asset in question, such alterations or works may be carried out (with the prior written approval of the RTL (such approval not to be unreasonably withheld or delayed)) but at the cost of User.
To the extent that any of the conditions of clause 3.1 are not in RTL’s reasonable opinion met in relation to any replacement or alteration, the RTL may by notice in writing require User promptly to remove such replacement or alteration and, if User fails to do so, may remove the same itself at the cost and expense of User. On such removal, User may reinstate the User Assets so replaced or altered.
For avoidance of doubt it is hereby agreed that any dispute between the Parties regarding this clause shall be determined in accordance with the provisions of Clause 10 of this Agreement.
4. SECURITY AND COMPLIANCE WITH STATUTES etc
The RTL undertakes to maintain and provide security in relation to User Assets in accordance with the arrangements set out in Part I of Schedule 3.
Each Party shall procure that, as between the Parties, all reasonable and necessary steps are taken, as and when necessary or desirable, in co-operation with the other Party (and, so far as applicable, with any third party), to ensure compliance with the provisions (each such provision or part thereof being in this clause 4 an “Obligation”) of:-
all statutes and Directives applicable to any User Assets and/or any part (including the whole) of the RTL’s Offshore Platform;
any statute or Directive which may affect any other property (of whatever nature) of either Party as a result of the existence, nature, location, or manner of operation of any User Assets; and
any statute or Directive requiring the reporting of any occurrence relating to or affecting any User Assets and/or the RTL’s Offshore Platform (including the Reporting of Injuries Diseases and Dangerous Occurrence Regulations 1985 and the Regulations).
Each Party shall, so far as it is aware of the same, unless it has reasonable grounds for believing that the other Party possesses the information, keep the other Party informed of all matters relating to any Obligation or potential Obligation and/or the extent to which such Obligation may be applicable.
In the event of any dispute as to responsibility, as between the Parties, pursuant to clause 4.2, for compliance with an Obligation, that responsibility shall be allocated, so far as practicable, on the basis that:-
each Party shall refrain from taking or permitting any act or omission which would prevent compliance with an Obligation; and
positive action required in relation to a Party’s property as a consequence of the existence, nature, location or manner of operation of that property or any other property of that Party shall be the responsibility of that Party, and, to the extent that such action is required in respect of or affecting any property of the other Party (or property of a third party located in or on that other Party’s Offshore Platform), such action may be taken with the prior approval of that other Party (such approval, subject to (i) above, not to be unreasonably withheld or delayed).
The provisions for safety co-ordination between the Parties contained in Part II of Schedule 3 shall apply.
5. Relocations 11
At any time and from time to time during the term of this Agreement, the RTL may with the prior written consent of User (such consent not to be unreasonably withheld or delayed) require User to relocate any User Assets to a different location on the RTL Offshore Platform, such consent to be sought and given or refused in accordance with the following procedure:-
The RTL shall serve a written notice on User, which notice shall specify:-
the User Assets which the RTL wishes to be relocated;
the reasons for such wish;
the proposed new location for such User Assets; and
the timing of the carrying out of such relocation.
User shall within one month of receipt of any such notice (or such longer period as shall be reasonably necessary) serve a counter notice stating:-
whether or not in its reasonable opinion such Relocation Proposal is acceptable to it;
if the Relocation Proposal is not acceptable to User, the grounds for such opinion and the terms of any alternative proposal (the “Alternative Relocation Proposal”) covering so far as relevant the matters referred to in items (a) - (d) of clause 5.1.1 which would be acceptable to User; and
in respect of the Relocation Proposal (if accepted) or of any Alternative Relocation Proposal, the costs likely to be incurred in connection with considering the Relocation Proposal or the Alternative Relocation Proposal and effecting the said relocation of the User Assets and the proper and reasonable costs of relocating any other equipment that may be necessary as a result of the relocation of those User Assets and any consequential losses including payments to third parties incurred as a result of the relocation of those User Assets and the proposed manner and timing of payment of the same by the RTL.
If within one month of the date of such counter notice (or such longer period as shall be reasonably necessary) the RTL has not withdrawn the Relocation Proposal and the Parties have not agreed upon it or the Alternative Relocation Proposal (if any) or a variation of either of them (such agreement to include agreement on the costs referred to in item (c) of clause 5.1.2) the matter shall be dealt with in accordance with Clause 10.
Upon approval or settlement of any Relocation Proposal, Alternative Relocation Proposal or variation thereof pursuant to clause 5.1, User shall [(conditionally upon it being able to obtain all necessary licences and consents which it will use reasonable endeavours to do)] relocate or procure the relocation of the relevant User Assets as quickly as reasonably practicable (having regard to, amongst other things, technical and operational requirements [and to the availability of all necessary licences and consents]).
The RTL shall render all reasonable assistance to User in connection with such relocation [licences and consents] and pay to User all costs referred to in item (c) of clause 5.1.2 as agreed or settled pursuant to clause 5.1 provided that all reasonable endeavours are used to minimise such costs and in the event that a Relocation Proposal is withdrawn or consent thereto is reasonably withheld pursuant to clause 5.1, the RTL shall pay to User all costs reasonably incurred by User in connection with considering the Relocation Proposal and any counter notice.
Such of the provisions of this Agreement as are appropriate and relevant (including the provisions of this clause 5), shall continue to apply to any relocated User Assets.
6. Removals 13
In the event that there shall cease to be a Bilateral Connection Agreement relating to any User Assets on the RTL’s Offshore Platform User shall remove all User Assets from the RTL’s Offshore Platform within [ ] or such longer period as shall be agreed between the RTL and the User and in accordance with the provisions relating thereto contained in the Connection Agreement and the Bilateral Connection Agreement.
Where User is obliged to remove any User Assets from the RTL’s Offshore Platform, under this Clause 6, and fails to do so in accordance with the relevant provisions, (whether they be contained in this clause 6, clause 3 or clause 5) the RTL shall be entitled to remove those User Assets to land belonging to User and User shall provide all reasonable assistance to enable the RTL safely so to do and shall pay and reimburse to the RTL all costs and expenses reasonably incurred by the RTL in so doing.
7. Rights of Access 14
A Right of Access includes the right to bring on to the RTL’s Offshore Platform such vehicles, plant, machinery and maintenance or construction materials as shall be reasonably necessary for the Permitted Purpose.
A Right of Access given to User may be exercised by any person, including third party contractors, reasonably nominated from time to time by User. To the extent (if any) that any particular authorisation or clearances may be required to be given by the RTL and the procedures for giving and obtaining the same are not for the time being stipulated in arrangements made pursuant to clause 7.3, the same shall be given within a reasonable time from the date of the request therefor, save in the case of emergency in which case it shall be given without delay.
User shall procure that all reasonable arrangements and provisions are made and/or revised from time to time, as and when necessary or desirable, to facilitate the safe exercise by it of any Right of Access with the minimum of disruption, disturbance or inconvenience to the RTL. Such arrangements and provisions shall provide for the RTL to have the right to make directions or regulations from time to time in relation to a specified matter. Matters to be covered by such arrangements and/or provision shall include:-
the identification of any relevant User Assets;
the particular access routes applicable to the Offshore Platform in question having particular regard for the weight and size limits on those routes;
any limitations on times of exercise of a Right of Access;
any requirements as to prior notification and as to authorisation or security clearance of individuals exercising such Rights of Access, and procedures for obtaining the same;
the means of communication between the Parties and all employees and/or contractors who may be authorised from time to time by User to exercise a Right of Access of any relevant directions or regulations made by the RTL;
the identification of and arrangements applicable to Emergency Personnel.
Any limitation or restriction on the exercise of such Right of Access to the extent that in the circumstances is reasonable
User shall procure that any such arrangements and/or provisions (or directions or regulations issued by the RTL pursuant thereto) made from time to time between the Parties shall be observed and performed by it and all persons authorised by it to exercise any Right of Access.
User shall procure that all reasonable steps are taken in the exercise of any Right of Access to:-
avoid or minimise damage to the RTL’s Offshore Platform, or any other property thereon or therein;
cause as little disturbance and inconvenience as possible to the RTL or other occupier of the RTL’s Offshore Platform; and shall promptly make good any damage caused to the RTL’s Offshore Platform and/or such other property in the course of the exercise of such rights and shall indemnify the RTL against all actions, claims, proceedings, losses, costs and demands arising out of such exercise.
Subject to clause 7.4.1, all such rights shall be exercisable free of any charge or payment of any kind.
Subject to any contrary arrangements for the time being made under clause 7.3, 7.5.1 a Right of Access for operation or inspection shall be available without prior notice;
a Right of Access for the purpose of maintenance, testing or repair of HV Apparatus shall only be exercisable on the giving of at least [seven days] prior written notice to the RTL except in the case of loss of generation or demand or other emergency (in which event the RTL shall render all possible assistance in procuring that the Right of Access shall be exercisable as soon as possible); and 7.5.3 a Right of Access for the purpose of Modifying any User Assets shall be exercisable only after [two weeks] prior written notice to the RTL.
8. Services and Use of Assets 16
Subject as hereinafter provided, in relation to the Facilities, RTL shall, if required by User, make the Facilities in question available for use by User to such extent as is necessary for the purposes of User’s undertaking but not so as to prejudice the use now or hereafter of such Facilities by the RTL for its undertaking.
Subject as hereinafter provided, in relation to each of the Services, the RTL shall, if required by User, provide the same to User. Such provision shall be of such a quality and quantity and shall be provided at such times as User shall reasonably request. The RTL shall not be required to exceed the level of quality or quantity of the Services as are anticipated by the Parties at the date of this Agreement, unless specifically agreed otherwise between the Parties.
Where the use of any Facilities is made available or such Services are supplied as aforesaid, the Parties shall procure that all reasonable arrangements and provisions are made and/or revised from time to time, as and when necessary or desirable between the local personnel employed by each of them in that regard, such arrangements to include:- 8.3.1 the identification of the Facilities and/or Services in question including (where relevant) the extent of their availability;
the hours during which such use or provision shall be allowed or made;
any requirements as to notification of use or call for supply or temporary suspension thereof;
any requirements as to authorisation or security clearance of individuals and the procedures for obtaining the same; and 8.3.5 any safety requirements.
The provision of use of the Facilities listed in Schedule 4, Part One and the supply of the Services listed in Schedule 5, Part One shall not be terminated unless the RTL ceases to require the Facilities or Services for its own use in which case the supply of the Services or use of the Facilities may be terminated by not less than one year’s notice in writing;
The provision of use of the Facilities listed in Schedule 4, Part Two and the supply of the Services listed in Schedule 5, Part Two shall continue until terminated by not less than six months notice in writing by either Party. The RTL shall maintain the Facilities in accordance with Good Industry Practice.
9. Non-Interference 18
The RTL agrees that neither it nor its agents, employees and invitees will interfere in any way with any of User Assets without the consent of User. For the purposes of this clause “interfere” shall include:- 9.1.1 disconnecting or altering the connection of any User Assets to any system of cables, foundations, pipes, drains or other media to which it may be connected from time to time or to prevent supply of any substance or thing through such connected system;
affixing or removing any item or substance of any nature whatsoever to or from any User Assets;
damaging any User Assets;
allowing any other person to interfere with any User Assets;
alter any meters or settings on any User Assets;
the obstruction of access to any User Assets.
The obligations contained in this clause 9 shall be suspended to the extent that emergency action is taken by Emergency Personnel in good faith to protect the health and safety of persons or to prevent damage to property. All reasonable care shall be taken in the course of such emergency action. When the emergency has ended, any damaged property will be reinstated by User, save for damage occurring by reason of lack of reasonable care in the course of the emergency action taken by the RTL which shall be the responsibility of the RTL.
10. Dispute Resolution 19
Any dispute arising under this Agreement between Location Managers of the Parties shall, if not resolved within 14 days of first arising, be referred at the instance of either party to the respective line managers, or those fulfilling a similar function whether or not so called, of the RTL and User who shall use all reasonable endeavours to resolve the matter in dispute within one month.
Save where expressly stated in this Agreement to the contrary (including the procedure for initial dispute resolution contained in clause 10.1) and subject to any contrary provision of the Act, any Licence, or the Regulations, or the rights, powers, duties and obligations of the Authority or the Secretary of State under the Act, any Licence or otherwise howsoever, any dispute or difference of whatever nature howsoever arising under out of or in connection with this Agreement between the Parties shall (subject to any relevant initial dispute resolution procedures referred to in Clause 10.1 having been exhausted) be and is hereby referred to arbitration pursuant to the rules of the London Court of International Arbitration in force from time to time.
Whatever the nationality residence or domicile of any Party and wherever the dispute or difference or any part thereof arose the law of England and Wales shall be the proper law of any reference to arbitration hereunder and in particular (but not so as to derogate from the generality of the foregoing) the provisions of the Arbitration Act 1996 (including any modification, extension, replacement or re-enactment thereof for the time being in force) shall apply to any such arbitration wherever the same or any part of it shall be conducted.
11. Governing Law and Jurisdiction 21
This Agreement shall be governed by and construed in all respects in accordance with English law.
Subject and without prejudice to clause 10 and to clause 11.4 the Parties irrevocably agree that only the courts of England and Wales and the courts of Scotland are to have jurisdiction to settle any dispute which may arise out of or in connection with this Agreement and that accordingly any suit, action or proceeding (together in this clause 11 referred to as “Proceedings”) arising out of or in connection with this Agreement may be brought in such courts.
Each Party irrevocably waives any objection which it may have now or hereafter to the laying of the venue of any Proceedings in any such court as is referred to in this clause 11 and any claim that any such Proceedings have been brought in an inconvenient forum and further irrevocably agrees that a judgment in any Proceedings brought in the courts of England and Wales or the courts of Scotland shall be conclusive and binding upon such Party and may be enforced in the courts of any other jurisdiction.
For the avoidance of doubt nothing contained in the foregoing provisions of this clause 11 shall be taken as permitting a Party to commence Proceedings in the courts where this Agreement otherwise provides for proceedings to be referred to arbitration.
12. Confidentiality 22
For the purposes of this Clause 12 except where the context otherwise requires:-
“Authorised Recipient”, in relation to any Protected Information, means any Business Person who, before the Protected Information had been divulged to them by the RTL or any subsidiary of the RTL, had been informed of the nature and effect of this clause 12 and who requires access to such Protected Information for the proper performance of their duties as a Business Person in the course of Permitted Activities;
“Business Person” means any person who is a Licensed Business Person, or a Corporate Functions Person and “Business Personnel” shall be construed accordingly.
“Confidential Information” means all data and other information supplied to User under the provisions of this Agreement.
“Corporate Functions Person” means any person who:-
is a director of the RTL; or 1 To consider simplifying?
is an employee of the RTL or any of its subsidiaries carrying out any administrative, finance or other corporate services of any kind which in part relate to the Licensed Business; or
is engaged as an agent of or adviser to or performs work in relation to or services for the Licensed Business.
“Licensed Business” means any business of RTL or any of its associates authorised by its RTL Licence;
“Licensed Business Person” means any employee of the RTL or any Authority or employee of its subsidiaries who is engaged solely in its Licensed Business and “Licensed Business Personnel” shall be construed accordingly;
“Permitted Activities” means activities carried on for the purposes of the Licensed Business;
“Protected Information” means any information relating to the affairs of a Party which is furnished to Business Personnel pursuant to this Agreement unless, prior to such information being furnished, such Party has informed the recipient thereof by notice in writing or by endorsement on such information, that the said information is not to be regarded as Protected Information;
Confidentiality for the RTL and its Subsidiaries The RTL and its subsidiaries in each of their capacities in this Agreement shall secure that Protected Information is not:- 12.2.1 divulged by Business Personnel to any person unless that person is an Authorised Recipient;
used by Business Personnel for the purposes of obtaining for the RTL or any of its subsidiaries or for any other person:-
any Licence; or
any right to purchase or otherwise acquire, or to distribute, electricity including by means of an electricity purchase contract (as defined in the Transmission Licence); or
any contract or arrangement for the supply of electricity to customers or suppliers; or
any contract for the use of any electrical lines or electrical plant belonging to or under the control of a supplier.
used by Business Personnel for the purpose of carrying on any activities other than Permitted Activities except with the consent in writing of the Party to whose affairs such Protected Information relates.
Nothing in this Clause 12 shall apply:- 12.3.1 to any Protected Information which, before it is furnished to Business Personnel is in the public domain;
to any Protected Information which, after it is furnished to Business Personnel:-
is acquired by the RTL or any subsidiary of the RTL in circumstances in which this Clause 12 does not apply; or
is acquired by the RTL or any subsidiary of the RTL in circumstances in which this Clause 12 does apply and thereafter ceases to be subject to the restrictions imposed by this Clause 12; or
enters the public domain otherwise than as a result of a breach by the RTL or any subsidiary of the RTL of its obligations in this Clause 12.
to the disclosure of any Protected Information to any person if the RTL or any subsidiary is required or permitted to make such disclosure to such person:-
in compliance with the duties of the RTL or any associate under the Act or any other requirement of a Competent Authority; or
in compliance with the conditions of its RTL Licence or any document referred to in its RTL Licence with which the RTL is required to comply; or
in compliance with any other requirement of law; or
in response to a requirement of any recognised stock exchange or regulatory authority or the Panel on Take-overs and Mergers; or
pursuant to the rules for the London Court of International Arbitration or pursuant to any judicial or other arbitral process or tribunal.
to any Protected Information to the extent that the RTL or any of its subsidiaries is expressly permitted or required to disclose that information under the terms of any agreement or arrangement (including the Grid Code and the Fuel Security Code) with the Party to whose affairs such Protected Information relates.
The RTL and its subsidiaries may use all and any information or data supplied to or acquired by it, from or in relation to the other Party to this Agreement in performing its Permitted Activities and may pass the same to subsidiaries of the RTL which carry out such activities and the User hereto agrees to provide all information to the RTL and its subsidiaries for such purposes.
The Company and its subsidiaries may use all and any information or data supplied to or acquired by it from the RTL pursuant to Clause 12.3.3 in relation to this Agreement in performing its activities under the ESO Licence including for the following purposes:
the operation and planning of the National Electricity Transmission System;
the calculation of charges and preparation of offers of terms for connection to or use of the National Electricity Transmission System; and the User agrees to provide all information to the RTL and it’s subsidiaries for such purposes.
The RTL undertakes that, having regard to the activities in which any Business Person is engaged and the nature and effective life of the Protected Information divulged to them by virtue of such activities, neither the RTL nor any of its subsidiaries shall unreasonably continue (taking into account any industrial relations concerns reasonably held by it) to divulge Protected Information or permit Protected Information to be divulged to any Business Person:
who has notified the RTL or the relevant subsidiary of their intention to become engaged as an employee or agent of any other person (other than of the RTL or any subsidiary thereof);
who is authorised by licence or exemption to generate or supply electricity.
Without prejudice to other provisions of this clause 12 the RTL shall procure that any additional copies of the Protected Information, whether in hard copy or computerised form, will clearly identify the Protected Information as protected.
The RTL undertakes to use all reasonable endeavours to procure that no employee is a Corporate Functions Person unless the same is necessary for the proper performance of their duties.
Confidentiality for User
User hereby undertakes with the RTL and its subsidiaries that it shall preserve the confidentiality and secrecy of, and not directly or indirectly reveal, report, publish, disclose or transfer or use for its own purposes Confidential Information except:-
in the circumstances set out in Clause 12.9.2;
to the extent expressly permitted by this Agreement; or
with the consent in writing of the RTL.
Exceptions: the circumstances referred to in Clause 12.9.1(a) are:-
where the Confidential Information, before it is furnished to User, is in the public domain; or
where the Confidential Information, after it is furnished to User:-
is acquired by User in circumstances in which this Clause 12 does not apply; or
is acquired by User in circumstances in which this Clause 12 does apply and thereafter ceases to be subject to the restrictions imposed by this Clause 12; or
enters the public domain otherwise than as a result of a breach by User of its obligations in this Clause 12; or
if User is required or permitted to make disclosure of the Confidential Information to any person:-
in compliance with the duties of User under the Act or any other requirement of a Competent Authority;
in compliance with the conditions of any Licence or any document referred to in any Licence with which User is required to comply;
in compliance with any other requirement of law;
in response to a requirement of any stock exchange or regulatory authority or the Panel on Takeovers and Mergers; or
pursuant to the rules for the London Court of International Arbitration or pursuant to any judicial or other arbitral process or tribunal; or
where Confidential Information is furnished by User to the employees, directors, agents, lenders, consultants and professional advisers of User in each case on the basis set out in Sub-Clause 12.10.
With effect from the date of this Agreement User shall adopt procedures within its organisation for ensuring the confidentiality of all Confidential Information which it is obliged to preserve as confidential under this Clause 12. These procedures will include:
the Confidential Information will be disseminated within User only on a “need to know” basis;
employees, directors, agents, lenders, consultants and professional advisers of User in receipt of Confidential Information will be made fully aware of User’s obligations of confidence in relation thereto.
13. Title to Assets 28
User acknowledges that it does not have and will not acquire any title, right or interest in the RTL’s Offshore Platform save for such rights as are expressly granted herein or otherwise provided nevertheless that, if according to any rule of law, User could acquire any such title, right or interest in any of the RTL’s Offshore Platform, then the User undertakes to do all that is required to transfer such right or interest to the RTL to ensure that the RTL shall not, by reason of such right or interest arising, have its full rights in such Offshore Platform diminished (and in the interim to hold such rights in trust for the RTL) and shall if requested by the RTL, be obliged forthwith to establish trust arrangements valid under Scottish law so as to ensure that any such right or interest shall be held on behalf of RTL .
The RTL agrees that it shall not by any act or default render User Assets liable to any distress execution or other legal process, and in the event that User Assets shall become so liable, shall forthwith give notice of any such proceedings to User and shall forthwith notify any third party instituting any such process of the ownership of such User Assets.
If the RTL desires to mortgage or charge RTL’s Offshore Platform or its interest therein on which any User Assets are located or to enter into any arrangement which, if made, might affect the rights of User expressly granted herein, then the RTL shall ensure that User Assets are not and will not be subject to the rights granted therein and are not and will not be affected by the mortgage, legal charge or other agreement or arrangement, and shall give prior written notification thereof to User.
In the event that the RTL shall wish to grant rights over or dispose of any interest in [or change the use of] the RTL’s Offshore Platform the RTL shall notify User of such wish and fully consult User in respect thereof and shall not grant such rights or make such disposal or change of use save on terms securing to the reasonable satisfaction of that other the Rights of Access granted in respect of the RTL’s Offshore Platform.
14. Limitation of Liability 29
Subject to sub-clauses 5.3, 6.2, 9.2, and 14.5 and save as provided in this sub-clause 14.1 and sub-clause 14.2 neither Party (“the Party Liable”) nor any of its officers, employees or agents shall be liable to the other Party for loss arising from any breach of this Agreement other than for loss directly resulting from such breach and which at the date hereof was reasonably foreseeable as not unlikely to occur in the ordinary course of events from such breach and which resulted from:- 14.1.1 physical damage to the property of the other Party, its officers, employees or agents; and/or 14.1.2 the liability of the other Party to any other person for loss arising from physical damage to the property of any person.
Nothing in this Agreement shall exclude or limit the liability of the Party Liable for death or personal injury resulting from the negligence of the Party Liable or any of its officers, employees or agents and the Party Liable shall indemnify and keep indemnified the other Party, its officers, employees or agents, from and against all such and any loss or liability which the other Party may suffer or incur by reason of any claim on account of death or personal injury resulting from the negligence of the Party Liable or any of its officers, employees or agents.
Subject to sub-clauses 5.3, 6.2, 9.2, and 14.5 neither Party, nor any of its officers, employees or agents shall in any circumstances whatsoever be liable to the other Party for:- 14.3.1 any loss of profit, loss of revenue, loss of use, loss of contract or loss of goodwill; or 14.3.2 any indirect or consequential loss; or 14.3.3 loss resulting from the liability of the other Party to any other person howsoever and whensoever arising save as provided in sub-clauses 14.1.2 and 14.2.
The rights and remedies provided by this Agreement to the Parties are exclusive and not cumulative and exclude and are in place of all substantive (but not procedural) rights or remedies express or implied and provided by common law or statute in respect of the subject matter of this Agreement, including any rights either Party may possess in tort which shall include actions brought in negligence and/or nuisance. Accordingly, each of the Parties hereby waives in the fullest extent possible all such rights and remedies provided by common law or statute, and releases the Party Liable, its officers, employees and agents to the same extent from all duties, liabilities, responsibilities or obligations provided by common law or statute in respect of the matters dealt with in this Agreement and undertakes not to enforce any of the same except as expressly provided herein.
Save as otherwise expressly provided in this Agreement, this clause 14 insofar as it excludes or limits liability shall override any other provision in this Agreement provided that nothing in this clause 14 shall exclude or restrict or otherwise prejudice or affect any of:- 14.5.1 the rights, powers, duties and obligations of either Party which are conferred or created by the Act, the User’s Licence, the RTL’s Licence or the Regulations or any amendment or re-enactment thereof; or 14.5.2 the rights, powers, duties and obligations of the Authority or the Secretary of State under the Act, any such licence as aforesaid or otherwise howsoever.
Each of the sub-clauses of this clause 14 shall:- 14.6.1 be construed as a separate and severable contract term, and if one or more of such sub-clauses is held to be invalid, unlawful or otherwise unenforceable the other or others of such sub-clauses shall remain in full force and effect and shall continue to bind the Parties; and 14.6.2 survive termination of this Agreement.
Each Party agrees that the Other Party holds the benefit of sub clauses 14.1, 14.2 and 14.3 above for itself and as trustee and agent for its officers, employees and agents
Each Party hereby acknowledges and agrees that the provisions of this clause 14 have been the subject of discussion and negotiation and are fair and reasonable having regard to the circumstances as at the date hereof.
15. INTELLECTUAL PROPERTY All Intellectual Property relating to the subject matter of this Agreement conceived, originated, devised, developed or created by a Party, its officers, employees, agents or consultants during the currency of this Agreement shall vest in such Party as the sole beneficial owner thereof save where the Parties agree in writing otherwise.
16. FORCE MAJEURE If either Party (the “Non-Performing Party”) shall be unable to carry out any of its obligations under this Agreement due to a circumstance of Force Majeure this Agreement shall remain in effect but save as otherwise provided herein the Non-Performing Party’s obligations hereunder shall be suspended without liability for a period equal to the circumstance of Force Majeure provided that:-
the Non-Performing Party gives the other Party prompt notice describing the circumstance of Force Majeure, including the nature of the occurrence, its expected duration and the particular obligations affected by it, and continues to furnish regular reports with respect thereto during the period of Force Majeure;
the suspension of performance is of no greater scope and of no longer duration than is required by the Force Majeure;
no liabilities of either Party that arose before the Force Majeure causing the suspension of performance are excused as a result of the Force Majeure;
the non-performing Party uses all reasonable efforts to remedy its inability to perform; and
as soon as practicable after the event which constitutes Force Majeure the Parties shall discuss how best to continue their operations so far as possible in accordance with this Agreement.
17. WAIVER No delay by or omission of a Party in exercising any right, power, privilege or remedy under this Agreement shall operate to impair such right, power, privilege or remedy or be construed as a waiver thereof. Any single or partial exercise of any such right, power, privilege or remedy shall not preclude any other or future exercise thereof or the exercise of any other right, power, privilege or remedy.
18. Notices 33
Any notice or other communication to be given by one Party to the other under, or in connection with the matters contemplated by, this Agreement shall be addressed to the recipient and sent to the address, or email addressof such other Party given in Schedule 6 and marked for the attention of the person so given or to such other address, and/or email address and/or marked for such other attention as such other Party may from time to time specify by notice given in accordance with this clause 18 to the Party giving the relevant notice or other communication to it.
Any notice or other communication to be given by one Party to the other Party under, or in connection with the matters contemplated by, this Agreement shall be in writing and shall be given by letter delivered by hand or sent by first class prepaid post (airmail if overseas) or email, and shall be deemed to have been received:- 18.2.1 in the case of delivery by hand, when delivered; or 18.2.2 in the case of first class prepaid post, on the second day following the day of posting or (if sent airmail from overseas) on the fifth day following the day of posting; or 18.2.3 in the case of telex, on the transmission of the automatic answerback of the addressee (where such transmission occurs before 1700 hours on the day of transmission) and in any other case on the day following the day of transmission; or 18.2.4 in the case of email, when delivered to the email address (where such delivery occurs before 1700 hours on the day of delivery) and in any other case on the day following the day of delivery.
19. VARIATIONS The provisions of Schedules 1, 3, 4, 5 and 6 may be varied from time to time by written memorandum signed by an authorised officer of each of the Parties. Subject thereto no variations to this Agreement shall be effective unless made by way of supplemental deed.
20. Overriding Provisions 34
In the event of any conflict between the RTL’s or User’s obligations hereunder and their obligations under the User’s Licence and RTL’s Licence, the Act, any direction of the Secretary of State, the Authority or ruling of the Competition Commission, the Grid Code, Connection Agreement or the Bilateral Connection Agreement, the provisions of the User’s Licence and RTL’s Licence, the Act, the Grid Code, Connection Agreement or Bilateral Connection Agreement, the direction of the Secretary of State, the Authority, or ruling of the Competition Commission shall prevail and accordingly the RTL and User respectively shall not be responsible for any failure to perform their respective obligations hereunder to the extent that any such failure is directly attributable to proper compliance with such provisions, rulings or directions.
Both parties shall observe their respective obligations hereunder in accordance with Good Industry Practice
21. Assignment and Sub-contracting 35
The rights and obligations of a Party may not be assigned (otherwise than to an Affiliate or by way of a charge or an assignment by way of security) without the consent of the other Party, such consent not to be unreasonably withheld.
Each Party shall have the right to sub-contract or delegate the performance of any of its obligations or duties arising under this Agreement without the consent of the other. The sub-contracting by either Party of the performance of any obligations or duties under this Agreement shall not relieve such Party from the liability for performance of such obligation or duty.
22. Illegality and Partial Invalidity 35
If at any time any provision of this Agreement should become or be declared unlawful, invalid, illegal or unenforceable in any respect under the law of any jurisdiction, neither the validity, legality or enforceability of the remaining provisions nor the validity, legality or enforceability of such provision under the law of any other jurisdiction shall be affected.
If any part of a provision of this Agreement is or becomes or is declared invalid, unlawful, illegal or unenforceable but the rest of such provision would remain valid, lawful or enforceable if part of the wording were deleted the provision shall apply with such modifications as may be necessary to make it valid, lawful, enforceable and effective but without affecting the meaning of legality, validity or enforceability of any other provision of this Agreement.
23. TERM AND TERMINATION This Agreement shall continue until no User Assets are on the RTL’s Offshore Platformand no Facilities or Services are shared or provided.
24. Registration and Memorandum 36
This Agreement contains the entire agreement between the Parties with respect to the subject-matter hereof, and expressly excludes any warranty, condition or other undertaking implied at law or by custom, and supersedes all previous agreements and understandings between the Parties with respect thereto and:-
each of the Parties acknowledges and confirms that it does not enter into this Agreement in reliance on any representation, warranty or other undertaking not fully reflected in the terms of this Agreement; but
User acknowledges that the RTL may have entered or may enter into agreements with other parties who hold a licence containing similar rights and/or liabilities to those contained in this Agreement affecting the RTL’s Offshore Platform and any assets thereon. The RTL shall, when entering into such agreement with any such party, use reasonable endeavours to avoid conflicts between the provisions thereof and the provisions of this Agreement but in the event of any conflict the RTL shall use all reasonable endeavours to procure that appropriate arrangements are made to settle the same to give full effect (so far as practicable) to the rights and liabilities under this Agreement and under such other agreements as aforesaid. In the event of any dispute as to such conflict and/or arrangements the dispute shall be dealt with in accordance with Clause 10. IN WITNESS whereof this Agreement has been entered into as a Deed the day and year first above written. SCHEDULE 1 User’s Assets on RTL Offshore Platform SCHEDULE 2 RTL’s Offshore Platform SCHEDULE 3 Part I Security Details (Clause 4.1) Part II Plant MV LV Apparatus Safety Co-Ordination Procedures (Cl.4.5)
1. The Parties will comply with the Site Specific Safety Rules and any agreed modifications thereto.
2. The Parties will arrange for the Site Specific Safety Rules to be written down and to be implemented by the person or persons responsible on behalf of the relevant Parties for the co-ordination of safety. SCHEDULE 4
Exhibit P
1. The Company requires the information requested in this form for the purposes of considering and assessing whether or not to grant your STTEC Request. It is essential that the User supplies all information requested and provides all the confirmations required and that every effort should be made to ensure that such informations and confirmations are accurate. Please note the same terms used in this form are defined in the Interpretation in Definitions (contained in Section 11 to the CUSC) and when this occur
2. Where The Company considers that any information provided by the User is incomplete or unclear then The Company will reject the STTEC Request.
3. The User may not make any change to the information provided.
4. The Company shall charge the User, and the User shall pay to The Company the non-refundable STTEC Request Fee. The fee will be charged by The Company in accordance with the Charging Statements. No STTEC Request will be considered until such payment has been received.
5. The Company will consider the STTEC Request in accordance with the terms of Paragraph 6.31 of the CUSC.
6. The Company may publish certain information in relation to STTEC Requests as specified in Paragraph 6.31.6 of CUSC.
7. Please complete this form and email it to [] an]. The Company – REQUEST FOR SHORT TERM CAPACITY Please ensure that you have studied the notes before completing and signing this form. A. Details of User Name: Address: Email Address: Registered Number: Name Title and Contact Details (including email address) for the person authorised to deal with this STTEC Request for and on behalf of the User. ………………………………………………………………………………… …… B. Bilateral Agreement details Please detail the Bilateral Agreement reference
We agree to pay the STTEC Request Fee on the terms specified in the Notes to this Request Form.
We confirm that the data submissions in respect of the Connection Site or site of Connection under the Grid Code are complete, accurate and up to date.
We confirm that our STTEC Request for the maximum level of STTEC requested plus Transmission Entry Capacity (plus any STTEC previously granted for any part of the STTEC Period) shall not exceed the total station Connection Entry Capacity. Signed for and on behalf of the User
Exhibit Q
1. The Company requires the information requested in this application form for the purposes of preparing a BELLA Offer the "Offer". It is essential that the Applicant should supply all information requested in this application form and that every effort should be made to ensure that such information should be accurate. Please note that you can apply for a Gate 1 Offer or Gate 2 Offer and confirmation of which type of Offer you are applying for is required.
2. Please note that certain expressions which are used in this application form are defined in the Interpretations in Definitions (contained in Section 11 of the CUSC) and when this occurs the expressions have capital letters at the beginning of each word and are in bold.
3. Should The Company consider that any information provided is incomplete or unclear or The Company require further information in order that it may prepare the Offer, the Applicant will be requested to provide further information or clarification.
4. Should there be any change in any information provided by the Applicant after it has been submitted to The Company, the Applicant must immediately inform The Company of such a change.
5. The Company shall charge the Applicant, and the Applicant shall pay to The Company, The Company’s Engineering Charges in relation to the application. An advance will be charged by The Company in accordance with the Charging Statements. No application will be considered until such advance has been paid. The balance of The Company Engineering Charges shall be notified and invoiced by The Company to the Applicant together with a breakdown of such charges and the Applicant shall pay the same within 28 days of t
6. The effective date upon which the application is made shall be the later of the date when The Company has received the application fee under Paragraph 5 above, the date when The Company is reasonably satisfied that the Applicant has completed Sections A-C, and in the case of a Gate 2 Application, the date when the owner/operator of the Distribution System to whom the Applicant is connecting makes an effective Modification Application to The Company. The Company shall notify the Applicant of such date. Pleas
7. The Company will make the Offer, in accordance with the terms of Paragraph 1.5 of the CUSC
8. The Company will make the Offer in accordance with the Gated Application and Offer Process or such longer period as the Authority agrees to. The Offer may, where it is necessary to carry out additional extensive system studies to evaluate more fully the impact the impact of the proposed development, indicate the areas that require more detailed analysis. Before such additional studies are required, the Applicant shall indicate whether it wishes The Company to undertake the work necessary to make a revised O
9. In the course of processing your application, it may be necessary for The Company to consult the appropriate Public Distribution System Operator(s) on matters of technical compatibility of the National Electricity Transmission System with their Distribution Systems or to consult the Relevant Transmission Licensees to establish the works required on the National Electricity Transmission System. The Company shall need your authorisation to the release to the Public Distribution System Operator(s) or the Relev
10. The Company 's offer will be based to the extent appropriate upon its standard form terms for a BELLA. The Applicant should bear in mind The Company standard form terms when making this application.
11. In particular please note that The Company will require as a condition of Offer that the Applicant's Plant or Apparatus should meet or provide the relevant technical requirements set out in the appendices of the BELLA to the Offer.
12. Applicants should appreciate that they will be required to perform Mandatory Ancillary Services to ensure that system operational standards can be achieved. This requirement may have implications towards plant specification. You should be satisfied before an application is made that your intended plant design can meet the requirements. The Applicants are therefore recommended to contact The Company 's headquarters for further information where our staff will be pleased to help.
13. Please complete this application form in black print and return it duly signed to Customer Agreements Manager, National Energy System Operator Limited, Warwick Technology Park, Gallows Hill, Warwick CV34 6DA (Tel No. 01926 653000).
14. For most up to date contact details Applicants are advised to contact The Company Website at www.nationalgrid.com/uk.
15. Applicants have the ability to choose whether they wish to apply on a fixed or variable application fee basis. Fixed application fee is derived from analysis of historical costs of similar applications. Variable application fee is based on an advance of the Transmission Licensee’s Engineering and out of pocket expenses and will vary according to the size of the scheme and the amount of work involved. Applicants are requested to indicate their preferred application fee in question 6. Applicants are advised t
Name: ………………………………………………………………………………………… ……..
Address: ………………………………………………………………………………………… …..
Registered Office/Address [including email address for CUSC notices]: ………………………………………………………………………………………… ………………..
Name, Title and Address of Contacts for the purposes of this application given description of the field of the responsibility of each person: ………………………………………………………………………………………… …………………
If the Applicant is an agent please give name(s) and addresses of person(s) for whom the Applicant is acting: ………………………………………………………………………………………… …………………
Please confirm whether you agree to us sending the Offer in electronic form instead of hard copy and, if so, confirm the address for this as follows. Yes [ ] No [ ] Email address …………………………………………………..
Please identify which application fee basis you wish to use for this application. [ ] Fixed application fee [ ] Variable application fee B. The Proposed Point of Connection to a Distribution System
Please identify [preferably by reference to an extract from ordinance survey map] the intended point of connection to the Distribution System. ………………………………………………………………………………………… ……………… C. Technical Information
Please provide the Data listed in Part 1 of the Appendix to the Planning Code. Note: the Data concerned forms part of the Planning Code and Data Registration Code. Applicants should refer to these sections of the Grid Code for an explanation.
Please indicate any terms which you are prepared to offer for: A. Black Start Capability B. Gas Turbine Fast Unit Fast Start C. Synchronous Compensation D. Pump Storage Units Spinning-in-Air E. Pump Storage F. Pump Storage Plant Fast Start from Standstill G. Demand Reduction H. Adjustment to Pumped Storage Unit Pumping Programme I. Hot Standby D. Enabling Works
We confirm we do not/do want the Enabling Works to be greater in scope than the MITS Connection Works.
If you want the Enabling Works to be greater in scope than the MITS Connection Works specify the concerns, reasons or technical requirements that you are seeking to address by this.
We hereby apply for a BELLA.
We will promptly inform The Company of any change in the information given in this application as quickly as practicable after becoming aware of any such change.
We authorise the release of certain information to the appropriate Public Distribution System Operators or the Relevant Transmission Licensees should it be considered necessary.
We confirm that we are applying in the category of an Embedded Exemptable Large Power Station whose Boundary Point Metering System is [to be] registered in SMRS or in CMRS by a User who is responsible for the Use of System Charges associated with the BM Unit [to be] registered in CMRS.
We confirm that this is an application for a: Gate 1 Offer [ ] Gate 2 Offer [ ] Please tick correct option
If Reservation was to be considered by The Company, we would/would not be interested in Reservation. [delete as appropriate] Signed: ………………………………………. for and on behalf of the Applicant Date: …………………………………………..
Exhibit R
1. The Company offers to enter into a BELLA reference no. [] in the form and terms attached at Section A.
2. It is a condition of this offer that:
if not already a CUSC Party you enter into a CUSC Accession Agreement;
you satisfy The Company that you have entered into a Distribution Agreement with the owner/operator of the Distribution System for the connection of the User's Plant to and the use of such Distribution System.
3. The technical conditions with which you must comply as a term of this offer are set out in the Grid Code. Additional or different technical conditions are set out in the appendices to the BELLA. It is your responsibility to ensure that your equipment complies with the requirements of the relevant conditions.
4. This offer is open for acceptance according to the terms of Paragraph 1.5 of the CUSC. Please note your right to make an application to the Authority to settle the terms of the Offer pursuant to Paragraph 1.6 of the CUSC.
5. To accept this offer, please sign (and where issued by email, having printed off 2 copies of each) and return the originals of the BELLA [and CUSC Accession Agreement] attached to this offer as Section A. The Company will then itself execute the Agreements and one original of each will be returned to you for your retention. The Agreements are only affective in accordance with their terms once they have been countersigned by The Company.
6. This Offer is made on the basis of the Connect and Manage Arrangements [except that as requested the Enabling Works are greater in scope than the MITS Connection Works].
7. All communications in relation to this offer should, in the first instance, be directed to [].
8. This is a [Gate 1 Offer][Gate 2 Offer] Yours faithfully ……………………………………………………… for and on behalf of National Energy System Operator Limited v1.7 – 10 June2025 SECTION A
Exhibit S
1. The Company requires the information requested in this form for the purposes of considering and assessing whether or not to grant your LDTEC Request. It is essential that the User supplies all information requested and provides all the confirmations required and that every effort should be made to ensure that such information and confirmations are accurate. Please note the same terms used in this form are defined in the Interpretation in Definitions (contained in Section 11 to the CUSC) and when this occurs
2. Where The Company considers that any information provided by the User is incomplete or unclear then The Company will reject the LDTEC Request.
3. The User may not make any change to the information provided.
4. The Company shall charge the User, and the User shall pay to The Company the non-refundable LDTEC Request Fee. The fee will be charged by The Company in accordance with the Charging Statements. No LDTEC Request will be considered until such payment has been received.
5. The Company will consider the LDTEC Request in accordance with the terms of Paragraph 6.31 of the CUSC.
6. The Company may publish certain information in relation to LDTEC Requests as specified in Paragraph 6.32.7 of CUSC.
7. Please complete this form and email it to [] EXHIBIT S The Company – REQUEST FOR SHORT TERM CAPACITY Please ensure that you have studied the notes before completing and signing this form. A. Details of User Name: Address: Email Address: Registered Number: Name Title and Contact Details (including email address) for the person authorised to deal with this LDTEC Request for and on behalf of the User. ………………………………………………………………………………… B. Bilateral Agreement details Please detail the Bilateral
We agree to pay the LDTEC Request Fee on the terms specified in the Notes to this Request Form.
We confirm that the data submissions in respect of the Connection Site or site of Connection under the Grid Code are complete, accurate and up to date.
We confirm that our LDTEC Request for the maximum level of LDTEC requested plus Transmission Entry Capacity (plus any STTEC or LDTEC previously granted for any part of the LDTEC Period) shall not exceed the total station Connection Entry Capacity. We consent to the disclosure of information by The Company in accordance with CUSC Paragraph 6.32.7. Signed for and on behalf of the User EXHIBIT S
Exhibit T
Exhibit U
1. The Company requires the information requested in this application form for the purposes of assessing the impact of a Relevant Embedded Medium Power Station or a Relevant Embedded Small Power Station (or where the User chooses, a number of Relevant Embedded Medium Power Stations or a Relevant Embedded Small Power Stations in which case this application form shall be completed and construed accordingly) upon the National Electricity Trans mission System. It is essential that the User submitting this Transmis
2. Please note that certain expressions which are used in this application form are defined in the Interpretation and Definitions (contained in Section 11 of the CUSC) and when this occurs the expressions have capital letters at the beginning of each word and are in bold.
3. Should The Company consider that any information provided is incomplete or unclear or should The Company require further information in order that it may assess the impact of a Relevant Embedded Medium Power Station or a Relevant Embedded Small Power Station upon the National Electricity Transmission System, the User submitting this Transmission Evaluation Application will be requested to provide further information or clarification.
4. Should there be any change in any information provided by the User submitting this Transmission Evaluation Application after it has been submitted to The Company, the User requesting this must immediately inform The Company of such a change.
5. The Company shall charge and the User submitting this Transmission Evaluation Application shall pay to The Company, The Company’s Engineering Charges in relation to the assessment. An advance will be charged by The Company in accordance with the Charging Statements. No Transmission Evaluation Application will be considered until such advance has been paid. The balance of The Company Engineering Charges shall be notified and invoiced by The Company to the User submitting this Transmission Evaluation Applicat
6. The effective date upon which the application is made shall be the later of the date when The Company has received the advance application fee pursuant to Paragraph 5 above or the date when The Company is reasonably satisfied that the User submitting this Transmission Evaluation Application has completed Sections AD. The Company shall notify the User submitting this Transmission Evaluation Application of such date.
7. The Company will assess the Transmission Evaluation Application in accordance with the terms of Paragraph 6.5.5 (Transmission Evaluation Application) and (where applicable) Paragraph 6.9 (Modifications) and Paragraph 6.10 (Modifications and New Connection Sites) of the CUSC and the ESO Licence.
8. The Company will assess the Transmission Evaluation Application as soon as is reasonably practicable and, in any event, (unless there are no works required on the National Electricity Transmission System) will respond to the User with a Gated Modification Offer or Connection Offer in accordance with the Gated Application and Offer Process or such later period as the Authority agrees to.
9. In the course of processing your Transmission Evaluation Application, it may be necessary for The Company to consult the appropriate Distribution System Operator(s) on matters of technical compatibility of the National Electricity Transmission System with their Distribution System(s) or to consult the Relevant Transmission Licensees to establish the works required on the National Electricity Transmission System. On grounds of commercial confidentiality The Company shall need your authorisation to the releas
10. If the User submitting this Transmission Evaluation Application is not already a CUSC Party the User submitting this Transmission Evaluation Application will be required as part of this application form to undertake that they will comply with the provisions of the Grid Code for the time being in force. Copies of the Grid Code and the CUSC are available on the The Company website and the User submitting this Transmission Evaluation Application is advised to study them carefully. Further
11. Any Gated Modification Offer or Connection Offer made following this Transmission Evaluation Application will be based to the extent appropriate upon its standard form terms for a Gated Modification Offer or Connection Offer and the Charging Statements.
12. The Applicant has the ability to choose whether they wish to apply for a Transmission Evaluation Application on a fixed price or variable price application fee basis. Fixed price application fee is derived from analysis of historical costs of similar applications. Variable price application fee is based on an advance of the Transmission Licensee’s Engineering and out of pocket expenses and will vary according to the size of the scheme and the amount of work involved. Applicants are requested to indicate the
13. Please complete this application form in black print and return it duly signed to The Company, contact details on the Website. For the most up to date contact details Users submitting this Transmission Evaluation Application are advised to review the The Company website.
Name: …................................................................................. ….................................................................................
Address: …................................................................................. …................................................................................. …................................................................................. ….................................................................................
Registered …................................................................................. Office/Address (including …................................................................................. e-mail address for CUSC notices and Registration …................................................................................. Number): …................................................................................. …................................................................................. …................................................................................. …................................................................................. ….................................................................................
Name, title and address of contacts for the purposes of this application, giving description of the field of responsibility of each person: …............................................................................................................................... …............................................................................................................................... …...............................................................................................................................
If User submitting this Transmission Evaluation Application is an agent, please give name(s) and address(es) of person(s) for whom the User submitting this Transmission Evaluation Application is acting: …............................................................................................................................... …............................................................................................................................... …...............................................................................................................................
Please identify (preferably by reference to an extract from Ordnance Survey Map) the intended location of the Plant and Apparatus (the "User Development") which it is desired should be connected to the Distribution System. .................................................................................................................................. .................................................................................................................................. ..................................................................................................................................
Please identify the intended Grid Supply Point through which that part of the User’s Distribution System to which the Relevant Embedded Medium Power Station or Relevant Embedded Small Power Station is connected, connects to the National Electricity Transmission System. .................................................................................................................................. .................................................................................................................................. ..................................................................................................................................
We hereby submit this Transmission Evaluation Application in respect of [……….] Embedded Power Station that is connecting to and/or using [……..]Distribution System.
We will promptly inform The Company of any change in the information given in this Transmission Evaluation Application as quickly as practicable after becoming aware of any such change.
If we are not already a CUSC Party we undertake for the purposes of this application to be bound by the terms of the Grid Code from time to time in force and to sign a CUSC Accession Agreement.
We authorise the release of certain information, on the grounds of commercial confidentiality, to the appropriate operators of Distribution System’s or Relevant Transmission Licensees should it be considered necessary.
We confirm that we do/do not meet the Approved Credit Rating and The Company Credit Rating.
We confirm that we are applying in the category of Distribution System directly connected to the National Electricity Transmission System.
We confirm that as part of this application we want to introduce the Transmission Impact Assessment process into the Bilateral Connection Agreement. Signed: ......................................................................... For and on behalf of the Applicant Date:.......................................................................
Exhibit V
Exhibit W
1. The Company requires the information requested in this form for the purposes of considering and assessing whether or not to grant your Temporary TEC Exchange Rate Request. It is essential that both Joint TEC Exchange Users supply all information requested and provides all the confirmations required and that every effort should be made to ensure that such information and confirmations are accurate. Please note the same terms used in this form are defined in the Interpretation in Definitions (contained in Sec
2. Where The Company considers that any information provided by the Joint TEC Exchange Users is incomplete or unclear then The Company will reject the Temporary TEC Exchange Rate Request.
3. Neither Joint TEC Exchange Users may make any change to the information provided.
4. The Company shall charge the Joint TEC Exchange Users, and the Joint TEC Exchange Users shall pay to The Company the Temporary TEC Exchange Rate Request Fee. The fee will be charged by The Company in accordance with the Charging Statements. No Temporary TEC Exchange Rate Request will be considered until such payment has been received.
5. The Company will consider the Temporary TEC Exchange Rate Request in accordance with the terms of Paragraph 6.34 of the CUSC.
6. The Company may publish certain information in relation to Temporary TEC Exchange Rate Requests as specified in Paragraph 6.34.7 of CUSC.
7. Please complete this form and email it to [].
We agree to pay the Temporary TEC Exchange Rate Request Fee.
As Temporary TEC Exchange Donor User we confirm that the data submissions in respect of our Connection Site or site of Connection under the Grid Code are complete, accurate and up to date.
As Temporary TEC Exchange Recipient User we confirm that the data submissions in respect of our Connection Site or site of Connection under the Grid Code are complete, accurate and up to date
We consent to the disclosure of information by The Company in accordance with CUSC Paragraph 6.34.7 Signed for and on behalf of the: Temporary TEC Exchange Donor User ……………………………………………… Temporary TEC Exchange Recipient User ……………………………………………….
Exhibit X
Exhibit Y
| Article | Text | Code | Section |
|---|---|---|---|
| 18.4 | The terms and conditions for balancing service providers shall: | ||
| 18.4.a | define reasonable and justified requirements for the provisions of balancing services; | CUSC | Section 4.1.3 |
| 18.5 | The terms and conditions for balancing service providers shall contain: | - | - |
| 18.5.a | the rules for the qualification process to become a balancing service provider pursuant to Article 16; | CUSC | Section 4.1 |
| 18.5.d | the requirements on data and information to be delivered to the connecting TSO and, where relevant, to the reserve connecting DSO during the prequalification process and operation of the balancing market; | CUSC | Section 4.1.3.14 and 4.1.3.19 |
| 18.5. f | the requirements on data and information to be delivered to the connecting TSO and, where relevant, to the reserve connecting DSO to evaluate the provisions of Balancing Services pursuant to Article 154(1), Article 154(8), Article 158(1)(e), Article 158(4)(b), Article 161(1)(f) and Article 161(4)(b) of the Electricity Transmission System Operation Regulation; | CUSC | Section 4.1.3.19 |
| 18.5. i | the rules for the settlement of balancing service providers defined pursuant to Chapters 2 and 5 of Title V; | CUSC | Section 4.1.3.9 and 4.1.3.9A |
| 18.5. j | a maximum period for the finalisation of the settlement of balancing energy with a balancing service provider in accordance with Article 45, for any given imbalance settlement period; | CUSC | Section 4.3.2.6 |
| 18.5. k | the consequences in case of non- compliance with the terms and conditions applicable to balancing service providers. | CUSC | Sections 4.1.3.9, 4.1.3.9A and 4.1.3.14 |
Please wait while we prepare the DCUSA Digital Document...